AUDIT  AND  SCRUTINY  PANEL  -  24 NOVEMBER 2022 
1
24 November 2022 at 2 pm. 
A Meeting of the AUDIT  AND  SCRUTINY  PANEL 
PRESENT 
Councillor Watson, Convener; Councillor Dunbar, Vice-Convener; Councillors Fisher, Hume, T. Johnston,
Loughran, McNally, Robinson and Stevenson. 
CHAIR 
Councillor Watson (Convener) presided. 
IN  ATTENDANCE 
Head of Audit and Risk; Business Strategy Manager; Strategy and Performance Manager; Corporate Risk
Manager; Principal Auditor, and Democratic Services Manager. 
ALSO IN ATTENDANCE 
P. Murray (Senior Audit Manager), Audit Scotland. 
APOLOGIES 
Councillors D. Johnston and Sullivan. 
DECLARATIONS  OF  INTEREST  IN  TERMS  OF  THE  ETHICAL  STANDARDS  IN  PUBLIC  LIFE  ETC. 
(SCOTLAND)  ACT  2000 
1. There were none. 
STRATEGIC  FRAMEWORKS  ANNUAL  POSITION  STATEMENT 
2. There was submitted a report by the Head of Business and Digital (1) referring to the inter-related
Strategic Frameworks which are key to addressing the success of the Plan for North Lanarkshire,
whilst ensuring each stage of delivery towards achieving the overall vision is appropriately planned,
guided, implemented and governed; (2) explaining that the six frameworks focus on ensuring a
corporate one Council approach in respect of Policy, Governance, Performance, Self-Evaluation,
Project Management and Demonstrating Improved Outcomes for Communities and, to ensure that
each framework remains aligned to the Plan for North Lanarkshire, they are on a programme to
undergo a regular review and refresh; (3) reminding the Panel that it has previously considered a
number of reports in relation to these frameworks in line with its responsibility to provide an
independent review of the Council’s Governance, Risk Management, Performance and Control
Frameworks, and (4) setting out the corresponding Annual Position Statement for each framework for
the information of the Panel in line with its remit.   
Decided: 
(1) that the Annual Position Statement for each framework, and the next steps to ensure each
remains aligned to the Plan for North Lanarkshire, monitor delivery towards achieving the
overall vision and ensuring delivery is appropriately planned, guided, implemented and
governed, be acknowledged, and

Page 2

AUDIT  AND  SCRUTINY  PANEL  -  24 NOVEMBER 2022 
2
(2) that it be noted that a Corresponding Review Programme supports each framework which in
turn ensures that all relevant matters are kept under review, updated as required and reported
to the relevant Committee. 
ANNUAL  REVIEW  AND  REFRESH  OF  THE  STRATEGIC  SELF -EVALUATION  FRAMEWORK 
3. There was submitted a report by the Head of Business and Digital (1) recalling that, in order to meet
the Best Value Duty, the Council must ensure arrangements are in place to secure continuous
improvement in performance for all functions and activities undertaken to deliver services and
improved outcomes; (2) explaining that a single strategy for improvement is in place through the
Strategic Self-Evaluation Framework and the rolling review programme, which had been reported to
the Panel in September 2021, and that this framework is specifically designed to be strategic but light
touch and consistent but flexible enough to ensure that self-evaluation exercises are tailored to the
service, function, project or group being evaluated and designed within the context of that operating
environment; (3) reminding the Panel that the Strategic Self-Evaluation Framework is one of six inter-
related corporate frameworks and that, to ensure these frameworks remain aligned to the Plan for
North Lanarkshire, each is on a programme for regular review and refresh; (4) providing an update to
the Panel from the Strategic Self-Evaluation Framework Rolling Review Programme for 2021 to 2022
and presenting a refreshed framework; (5) advising that, as a mechanism that also helps the Council
to provide assurances that the services provided represent value for money and are efficient and
effective, and able to demonstrate best value, a corporate approach to options appraisal had also
been formalised and was included in the Framework and attached as an Appendix to the report, and
(6) setting out, as an Appendix to the report, the Rolling Review Programme for 2022 to 2023. 
Decided: 
(1) that the refreshed Strategic Self-Evaluation Framework and Rolling Review Programme, and
the purpose therein in terms of ensuring that self-evaluation identifies areas for improvement
that contribute to achievement of the vision set out in the Plan for North Lanarkshire, be
acknowledged, and 
(2) that the challenge and scrutiny role of the Panel, in line with its responsibility to provide an
independent review of the Council’s Governance, Risk Management, Performance and
Control Frameworks, be acknowledged. 
AUDIT  AND  RISK -RELATED  ITEMS:  ACTION  LOG 
4. There was submitted a report by the Head of Audit and Risk enabling the Panel to track implementation
of requests and recommendations made by it in respect of Audit and Risk related items in the previous
18 months, with the Action Log, attached as an Appendix to the report, recording those requests and
recommendations made by the Panel and detailing when these had been addressed and/or were
expected to be addressed. 
Decided: that the contents of the report be noted. 
INTERNAL  AUDIT  PROGRESS  REPORT 
5. There was submitted a report by the Audit and Risk Manager (1) providing an overview of Internal
Audit activity; (2) reporting the results of Internal Audit outputs finalised since the last update to the
Panel in September 2022; (3) highlighting the most significant issues arising from the completed audit
work; (4) updating the Panel on other aspects of the work of Internal Audit, and (5) attaching, as an
Appendix to the report, a brief summary of the scope and key findings of each substantive planned
audit, together with a supplementary pack containing copies of those reports.

Page 3

AUDIT  AND  SCRUTINY  PANEL  -  24 NOVEMBER 2022 
3
During consideration of the report the Panel requested that further reports be brought back to a future
meeting on progress made by management implementing agreed actions in relation to audit
recommendations in respect of (1) Debtors and Debt-Management, and (2) Equalities. 
Decided: 
(1) that the findings, conclusions and recommendations of completed Internal Audit Reports,
together with the associated management responses, be noted; 
(2) that reports on progress made by management implementing agreed actions in response to
audit recommendations on (1) Debtors and Debt-Management, and (2) Equalities be
submitted to a future meeting of the Panel; 
(3) that Internal Audit provide a report to future meetings of the Panel on progress made by
management in implementing agreed management actions in relation to all audit
recommendations categorised as “high” or “medium”, and 
(4) that, otherwise, the contents of the report be noted. 
INTERNAL  AUDIT:   FOLLOW  UP  OF  ACTIONS  PREVIOUSLY  AGREED  BY  MANAGEMENT  IN 
RESPONSE  TO  AUDIT  RECOMMENDATIONS 
6. There was submitted a report by the Head of Audit and Risk (1) detailing the extent to which
management had implemented actions previously committed to in response to recommendations
contained in Internal Audit reports, where those actions were due to be completed by the end of
September 2022; (2)  advising that Internal Audit had concluded that 19 of the 24 actions agreed in
response to relevant Internal Audit recommendations during the period had been fully completed and
5 had been assessed as partially implemented; (3) reporting that 9 of the 14 actions agreed in respect
of External Audit outputs had been completed, 1 had been partially implemented and 4 were no longer
considered relevant, and (4) attaching, as an Appendix to the report, commentary from management
together with details of proposed management actions and revised target dates for completion of those
outstanding audit recommendations where Internal Audit had assessed the residual risk as “high” or
“medium”. 
During consideration of the report, the Panel requested that further update reports be provided by
management on a number of matters highlighted by Internal Audit in Appendix 1 of the report namely,
(1) Digital NL (quantifying and reporting on non-financial benefits); (2) Managing Strategic Change
(reporting on key projects), and (3) Governance of Capital Projects (assessing compliance with the
project management framework).  The Panel also requested that, where such reports were submitted
to meetings of the Panel, an appropriate Senior Officer be in attendance. 
Decided: 
(1) that the contents of the report be noted; 
(2) that the recommendations made by Internal Audit in Appendix 1 to the report be noted, and 
(3) that reports be submitted to a future meeting of the Panel in respect of progress on (a) Digital
NL (quantifying and reporting on non-financial benefits; (b) Managing Strategic Change
(reporting on key projects), and (c) Governance of Capital Projects (assessing compliance
with the project management framework, and that each report be accompanied by the
appropriate Senior Officer in attendance at that meeting.

Page 4

AUDIT  AND  SCRUTINY  PANEL  -  24 NOVEMBER 2022 
4
RISK  MANAGEMENT  UPDATE 
7. There was submitted a report by the Head of Audit and Risk (1) providing an update to the Panel on
key risk management developments since the most recent report in September 2022; (2) highlighting
a selection of the more significant issues which are of current focus from a risk perspective, and
(3) providing a narrative on the justification for additional risks to be added to the Corporate Risk
Register. 
Decided: 
(1) that the current residual scores for those risks previously agreed for inclusion in the Corporate
Risk Register for 2022-23, as indicated in Appendix 1 to the report, be noted; 
(2) that the addition to the Corporate Risk Register of new risks relating to data migration and
school transport, as detailed in the report, be noted; 
(3) that the references to other topical risk issues, as highlighted in the report, be noted, and 
(4) that the work ongoing to include key service risks, and an overview of how these risks are
being managed, as part of future reporting to the Corporate Management Team and the Panel,
be noted.   
CORPORATE RISK UPDATE – GOVERNANCE, LEADERSHIP AND DECISION MAKING 
8. There was submitted a report by the Head of Audit and Risk (1) reminding the Panel that, to support
the Council in mitigating risks and uncertainty, the Council operates risk management arrangements
which identify, evaluate, manage and control a range of key corporate risks; (2) highlighting that all
risks identified and agreed as meriting inclusion in the Corporate Risk Register are subject to regular
monitoring and review by relevant Senior Management and periodic review and consideration of
individual risks by both the Corporate Management Team and the Panel in line with the Council’s Risk
Management Strategy and their respective governance roles; (3) advising that, in line with the
previously approved timetable for reporting on corporate risks, this report focused on the deep dive of
the ”Governance, Leadership and Decision-Making” corporate risk providing an overview of the current
risk environment together with an overview of existing controls and actions taken to date to mitigate
against this risk, as well as further actions planned to continue to manage and update this risk, and
(4) informing the Panel that, following the most recent review of this risk, the residual risk score had
increased from 12 to 16 largely attributable to the Elections in May 2022 and subsequent political
events which are assessed as having increased uncertainty in a number of areas. 
Decided: 
(1) that it be noted that the updated deep dive, attached as Appendix 1 to the report, highlights
that the residual risk score in relation to the “Governance, Leadership and Decision-Making”
corporate risk had increased; 
(2) that the current and planned controls and actions relating to this corporate risk be noted, and 
(3) that the important role that Elected Members and Chief Officers have in relation to the ongoing
management and mitigation of this risk be recognised. 
CORPORATE  RISK  UPDATES  –  SUPPLY  CHAIN 
9. There was submitted a report by the Head of Audit and Risk (1) reminding the Panel that, to support
the Council in mitigating risks and uncertainty, the Council operates risk management arrangements
which identify, evaluate, manage and control a range of key corporate risks; (2) advising that, in line

Page 5

AUDIT  AND  SCRUTINY  PANEL  -  24 NOVEMBER 2022 
5
with the previously approved timetable for reporting on corporate risks, this report focused on the deep
dive of the ”Supply Chain” corporate risk providing an overview of the current risk environment together
with an overview of existing controls and actions taken to date to mitigate against this risk, as well as
further actions planned to continue to manage and update this risk; (3) indicating that the increased
costs associated with the Supply Chain risk will largely have to be managed within existing budgets
which are not expected to increase in line with inflationary pressures and the Council can increasingly
expect to see impacts on service provision, projects, Programme of Work items and challenges in
delivering the Capital Programme as previously planned, and (4) concluding that there will require to
be decisions made to review and update previously approved plans and projects, assessing what will
progress and what may need to be delayed or ceased. 
Decided: 
(1) that it be noted that the updated deep dive, attached as Appendix 1 to the report, highlights
that the residual risk score in relation to the “supply chain and associated inflationary
pressures” corporate risk is unchanged and remains high; 
(2) that the current and planned controls and management actions relating to this corporate risk
be noted, and 
(3) that the important role that short and medium-term financial planning has in allowing the
Council to respond to pressures arising from this risk, and a need to ensure that future plans
and ambitions are realistic and aligned with available resources, be recognised.