North Lanarkshire Council
Report
Policy and Strategy Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  CMcC/JMcK Date 16/03/23 
Abronhill Community Hub 
From  James McKinstry, Chief Officer (Assets & Procurement)  
E-mail mckinstryj@northlan.gov.uk  Telephone 07939281102 
Executive Summary 
At the Policy and Strategy Committee meeting on 1st October 2020, members approved
that feasibility work associated with Abronhill Community Hub could commence, through
the “Town and Community Hub Programme of Work” report approved at that committee.   
The purpose of feasibility work is to establish if a community hub could be delivered on the
land of the former Abronhill High School and surrounding land.  It was recognised, in line
with appropriate governance arrangements, that further approvals would be required
following completion of this feasibility stage, to move the project forward to delivery phase. 
The feasibility work for this project is now complete and it has been determined that it is
feasible for a hub, to house two primary schools on a shared campus, a family learning
centre, a health centre, and community facilities – to be delivered at the proposed site.  As
part of the feasibility exercise, indicative costs were also established. 
Elected members have been updated at various committees over the last year on market
volatility; inflationary pressures; and external factors; all of which are placing significant
pressure on the council’s capital budget.  The Town and Community Hub Programme, like
all other programmes, must manage the projects in line with the budget allocation provided
to the hub programme, within the current five-year capital programme. 
It has been determined that a hub can feasibly be delivered on the preferred site. However,
due to the external pressures and commercial environment linked to this programme, there
is significant pressure on funding allocated to the projects across the Town & Community
Hub Programme.  Due to insufficient availability of funds, at this time, this project cannot
be taken forward. 
As such, members are advised that the Hub Programme Board have reviewed the overall
programme and have recommended that future work on the Abronhill Community Hub
project should be deferred until such time as sufficient funding becomes available. This
project will be evaluated, as a viable project, during the preparation of the next 5-year
capital plan which will be developed during 2023 for commencement on 1 April 2024. If
and when funding is in place, further approval will be sought at a future meeting.

Page 2

1. Background 
1.1 Members may recall the ‘One Place – One Plan’ report and presentation to the Policy
and Strategy Committee in March 2020. At this meeting, members approved the
‘guiding principles’ and ‘prioritisation matrix’ linked to the Town and Community hub
programme. 
1.2 Members may recall a subsequent update report in October 2020 where Policy and
Strategy approved a feasibility study for a proposed new community hub in Abronhill,
Cumbernauld which looked to relocate existing primary provision (Abronhill PS, St
Lucy’s PS) along with other nearby facilities. 
1.3 Members may recall an update report on “The Place, The Vision”, submitted to Policy
and Strategy Committee in September 2021, where, within section 2.23 it was clarified
that “It should be emphasised that these projects would be subject to further approvals
linked to both anticipated project costs and statutory education consultations.
Therefore, these projects are currently only approved to scope the feasibility (and
potential costs)”. 
1.4 Within the same report, in September 2021, the heading attached to Table 2, (which
sits directly above section 2.23 mentioned above), it clearly stated that “Projects will be
brought back to committee for approval once the costs are known and it is assessed
that the projects are deliverable.” 
2. Report 
2.1 The proposal to bring forward a new community hub within Abronhill, Cumbernauld was
outlined in the business case attached to the report, presented to Policy and Strategy
Committee, in October 2020.  Within this report, it was outlined that this project was
being prioritised due to the availability of a site in the heart of the community, which
would regenerate this area, and provide wider benefits to the whole community – and
clearly demonstrated an excellent fit with the guiding principles and vision associated
with the Town and Community Hub programme, as well as The Plan for North
Lanarkshire. 
Recommendations 
It is recommended that the Policy and Strategy Committee: 
(1) Recognise the pressures on the council’s capital programme, the budget associated
with the Town and Community Hub Programme, and acknowledge that the Abronhill
Community Hub project will not be progressed at this time. 
(2) Recognise that this project will be a key consideration as part of the next capital
programme allocations. 
The Plan for North Lanarkshire
Priority  Support all children and young people to realise their full potential
Ambition statement
(2) Refocus our town centres and communities to be multi-
functional connected places which maximise social, economic, and
environmental opportunities

Page 3

2.2 There are two aspects linked to the delivery of any community hub:   
2.2.1 Firstly, can the project be delivered?  The feasibility study carried out has determined
that it is indeed feasibly to deliver the anticipated facilities and zones within this
community hub at the proposed location. 
2.2.2 Secondly, is there adequate funding to take this project forward?  At the time of
requesting the feasibility study, in October 2020, it was projected that there would be
sufficient funding to take this project forward.  This however, was in the middle of the
pandemic; before economic shift across the globe; and before inflationary pressures
and pressure on interest rates etc., currently being experienced - were known. 
2.3 In September 2022, a report on “inflationary pressures” was presented to the Policy
and Strategy Committee.  This report outlined the inflationary pressures placed on both
capital and revenue budgets across this council.  Within section 2.11 of this report, it
was acknowledged that due to the size and scale of ‘hub projects’, issues such as
market volatility, increased material costs, and continued labour scarcity, all have a
negative impact on the costs and budgets associated with the delivery of projects within
the hub programme. 
2.4 At the same committee in September 2022, a report on the procurement strategy for
the hub programme was presented. Within section 2.7 of this report, it was highlighted
to members that “the inflation rate has surged at the fastest rate for 30 years”. 
2.5 The Town and Community Hub programme budget allocation remains as set and
agreed in March 2021 when, through a report submitted to Policy and Strategy in
relation to the strategic capital delivery programme, it was approved that the Town and
Community Hub Programme was allocated £236.8m. Again, this was based, at that
time, on anticipated costs over the five-year programme term, before the economic
landscape and associated increased costs emerged. 
2.6 Due to pressures on the overall capital programme and wider council finances, the hub
programme budget remains static.  Therefore, in order to manage the programme, with
a static budget, and where project costs have increased significantly, the number of
projects which can be delivered (in any given council capital programme) must be
reduced in order to maintain a ‘within budget’ approach to the hub programme delivery. 
Types of hub projects 
2.7 The current Town and Community Hub programme (hereafter referred to as ‘the hub
programme’) has a mix of projects contained within the current five-year capital plan.   
2.7.1 Legacy Projects: These are projects that were already approved for delivery before the
change from Schools and Centres 21 programme, to the hub programme. 
2.7.2 Capacity Projects: These are projects which are required to significantly increase the
capacity of schools, primarily as a result of housing growth within the associated
catchment area. 
2.7.3 Policy Projects: These are projects which are being brought forward in line with the
aspirations of The Plan for North Lanarkshire, and the council ambition to replace all
pre-1996 education establishments.

Page 4

2.8 Projects included within the current five-year plan all meet one or more of the three
types of projects outlined above. 
Table 2.8 – Categorisation (types) of projects within current five-year programme: 
Project Legacy Capacity Policy
Newmains/St Brigid’s Community Hub Yes    
Chryston Community Hub Yes Yes  
Riverbank Community Hub Yes    
St Kevin’s Community Hub   Yes  
Orbiston Community Hub Yes    
St Stephen’s Community Hub Yes    
Gartcosh Community Hub Yes Yes  
Chryston High Extension   Yes  
Abronhill Community Hub     Yes
Ravenscraig Community Hub   Yes  
Wishaw Town Hub     Yes 
2.9  The table above clearly shows that only two projects are neither ‘capacity’ nor ‘legacy’
projects.  As outlined to Policy and Strategy Committee in September 2022 within the
‘LEIP Bid’ report, it was established that there is insufficient council funding to progress
with the Wishaw Town Hub build at this time. 
2.10 Whilst Ravenscraig Community Hub is identified as a capacity related project – there
is sufficient capacity within the existing estate to provide places for pupils well beyond
2026.  Furthermore, Ravenscraig Community Hub, in part, should be funded from
developer contributions and these are yet to be received.  Finally, whilst the latest round
of Levelling Up Funding (LUF) has shown Ravenscraig to be unsuccessful, it may be
that this is subject to further bids in future years, similar to the successful second round
allocation for Cumbernauld.   
Given all of the factors above, the Ravenscraig project, along with the Wishaw Town
Hub project, are deferred to be reassessed as part of the next five-year capital plan. 
2.11 Even with the exclusion of both Ravenscraig Community Hub, and Wishaw Town Hub,
from the current cost projections, the overall programme budget is currently projecting
an overspend of over £50m (when including Abronhill Community Hub). 
2.12 It is accepted by the Hub Programme Board that ‘Legacy’ projects are prioritised above
Policy projects as they are long standing/historical commitments made by the council,
are in advanced stages of delivery and have been subject to previous statutory
education consultations.  Furthermore, it is accepted by the Hub Programme Board that

Page 5

‘Capacity’ projects are prioritised as these are required to ensure adequate provision
of spaces for pupils within their catchment areas. 
2.13 Faced with the projected overspend of over £50m within the Town and Community Hub
Programme budget, and the need to deliver both ‘Legacy’ and ‘Capacity’ projects, the
Hub Programme Board made the recommendation to pause the only remaining project
- Abronhill Community Hub, in order to ensure the programme can remain within
budget. 
Abronhill Community Hub – Next Steps 
2.14 It has been determined that a hub can be delivered on the preferred site within
Abronhill. As such, this project is at a further advanced stage than any other project not
currently prioritised within the Town and Community Hub Programme. 
2.15 It is therefore anticipated that, when sufficient funding becomes available, that this
project will score strongly from a ‘deliverability’ perspective. 
2.16 At this time however, it is proposed that the local stakeholders are made aware of the
need to defer this project due to budget pressures and availability of funding. 
3. Measures of success 
3.1  Clear communication of the need to defer this project, due to external factors which
were not present when the project was initially presented.     
4. Supporting documentation 
1. “Presentation: One Place – One Plan” report – Policy and Strategy Committee, March
2020
2. “Town and Community Hub Update” report – Policy and Strategy Committee, October
2020
3. “PO12: Strategic Capital Investment Programme 2021/22 to 2025/26” report – Policy
and Strategy Committee, March 2021
4. “The Place, The Vision – update” report – Policy and Strategy Committee, October
2021
5. “Impact of Inflationary Pressures” report – Policy and Strategy Committee, September
2022
6. “Procurement Strategy – Town & Community Hub Programme” report – Policy and
Strategy Committee, September 2022
7. “Learning Estate Improvement Programme (LEIP) – Phase Three: Project Bid to
Scottish Government” report – Policy and Strategy Committee, September 2022 
All supporting documentation can be accessed via the councils ‘Minute and Reporting System’
(MARS). 
James McKinstry
Chief Officer (Assets & Procurement)

Page 6

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒  
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐  
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐  
If Yes, please provide a brief summary of the impact? 
Finance, as a key stakeholder, are represented on the Hub Programme Board. 
The decision taken, outlined within this report, is to ensure the Hub Programme
remains within budget and does not put further pressure on the wider council
finances at this time. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒  
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐  
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒

Page 7

If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐  
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒  
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐  
If Yes, please provide a brief summary of the impact? 
There may be some negative response to the need to defer this project –
especially within the local community. 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
There may be some negative response to the need to defer this project –
especially within the local community. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒

Page 8

If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.