POLICY  AND  STRATEGY  -  1  DECEMBER  2022 
84
1 December 2022 at 2 pm. 
A Meeting of the POLICY  AND  STRATEGY  COMMITTEE 
PRESENT 
Councillor Logue, Convener; Councillor Kelly, Vice-Convener; Councillor Roarty, Vice-Convener; Councillors
Beveridge, Boyd, Brennan, Campbell, Carragher, Di Mascio, Fotheringham, Hume, Jarvie, Jones, Larson,
Leckie, Loughran, Masterton, McBride, Nolan, Robinson, Stevenson, A. Stubbs, Sullivan and Watson. 
ALSO  PRESENT 
In accordance with Standing Order 64(A) Councillor M. McCulloch attended as a substitute for Councillor
Duffy. 
CHAIR 
Councillor Logue (Convener) presided. 
IN  ATTENDANCE 
The Chief Executive; Deputy Chief Executive; Head of Financial Solutions; Head of Legal and Democratic
Solutions; Head of Business and Digital; Head of Asset and Procurement Solutions; Head of Strategic
Communication; Head of People and Organisation Development; Head of Performance Planning and Quality
Assurance; Head of Audit and Risk; Business Finance Manager (Resource Solutions); Technology Strategy
Manager; Commercial Contracts Manager; Business Strategy Manager, and Democratic Services Manager. 
APOLOGIES 
Councillor Duffy. 
DECLARATIONS  OF  INTEREST  IN  TERMS  OF  THE  ETHICAL  STANDARDS  IN  PUBLIC  LIFE  ETC. 
(SCOTLAND)  ACT  2000 
1. There were no declarations of interest. 
MINUTES  OF  MEETINGS  OF  THE  AUDIT  AND  SCRUTINY  PANEL  HELD  ON  8  SEPTEMBER  AND 
27  OCTOBER  2022 
2. There were submitted the Minutes of the meetings of the Audit and Scrutiny Panel held on
8 September and 27 October 2022 respectively. 
Decided: that the Minutes of the Audit and Scrutiny Panel held on 8 September and 27 October
2022, respectively, be approved. 
CAPITAL  INVESTMENT  PROGRAMME  UPDATE 
3. There was submitted a report by the Head of Financial Solutions (1) reminding the Committee that the
Community Investment Fund Annual Update report considered by it in September 2022 had
highlighted the requirement to reduce the Council's Capital Investment Programme by £22.076m to
ensure that programme activity matched funding availability; (2) presenting the outcome of the review
of the Capital Programme undertaken by the Council's Strategic Capital Delivery Group while ensuring

Page 2

POLICY  AND  STRATEGY  -  1  DECEMBER  2022 
85
alignment with the Council's previously agreed capital prioritisation matrix and, therefore, The Plan for
North Lanarkshire; (3) explaining that the Council was nearing the end of the second year of its five
year capital planning period and that it had always been the intention to undertake a review of the
Programme during its first three years and, accordingly, the Strategic Capital Delivery Group would
work with Services to develop a new, reset, Capital Programme to commence from 2024/25, and
(4) attaching, as an Appendix to the report, the Capital Programme Review. 
Decided: 
(1) that the budget reductions outlined in the report, and in the Appendix to the report, be
approved; 
(2) that the ongoing Capital Programme of Funding Risks linked to wider economic factors be
acknowledged, and 
(3) that the approach to the development of a future Strategic Capital Programme, as outlined in
the report, be endorsed. 
ONE  PLACE  ONE  PLAN  -  GOVERNANCE  UPDATE 
4. There was submitted a report by the Chief Executive (1) indicating that in the four years since the
establishment of a One Place with One Plan approach, with a vision of inclusive growth and prosperity
for all, The Plan for North Lanarkshire and its associated governance arrangements and operating
model have continued to undergo incremental refinements to ensure ongoing alignment which has
enabled an approach to policy setting and strategic and operational decision making that has been
unwavering in its direction; (2) commenting that ensuring ongoing alignment in this way has also been
instrumental in supporting the delivery of a wide range of programmes, projects and activities;
(3) reporting on the pressures – internal and external to the Council – which impact on the local
government landscape and confirming that the Council needs to be prepared if it is to effectively
manage its way through the extent of the business changes to come, and create (and sustain) the
conditions that mean local people will thrive now and in the future and that this will require further
structural refinements to ensure ongoing alignment of vision, plan, governance and operations in order
to maintain the focus and ensure an inclusive growth and prosperity for all, and (4) outlining the first
phase of structural refinements for Committee approval. 
Decided: 
(1) that the deletion of the Head of Environmental Assets post with immediate effect – realising
one-off savings of £54,083 for 2022/23 and recurring savings of £126,992 for 2023/24 onwards
– and the realignment of these functions within existing remits as noted in the report be
approved; 
(2) that the changes to Heads of Service reporting lines and the formalisation of Chief Officer job
titles, with immediate effect, to ensure Council operating structures and governance
arrangements continue to align, as noted in the report and depicted in the Appendix to the
report, be acknowledged, and 
(3) that the intent for a future programme of linked reviews to be undertaken in preparation for the
extent of the business change to come, and the indicative dates for future reports to the
Committee in this respect, as noted in the report, be noted. 
POW:003.2  DIGITALNL  -  NEXT  STEPS 
5. There was submitted a report by the Chief Executive (1) outlining the background to DigitalNL; (2)
highlighting the scope of Digital NL which is much more than just about the Council becoming digitised;

Page 3

POLICY  AND  STRATEGY  -  1  DECEMBER  2022 
86
(3) explaining that in January 2021 Audit Scotland produced its report "Digital Progress in Local
Authorities" with North Lanarkshire participating as one of six selected field work sites for the national
performance audit on digital progress in local government; (4) reporting that Audit Scotland
acknowledged that the Council had a digital vision that went beyond technology and focussed on
people and outcomes; (5) advising that delivering digital savings during the pandemic has been
extremely challenging with Services unable to resource the service redesign and consequential user
acceptance testing essential for delivering the vision of Digital First due to refocussing their resources
to respond to the pandemic, and (6) reviewing programme deliverables achieved to date against those
outlined within the Full Business Case approved in March 2019. 
Decided: 
(1) that it be recognised that the financial benefits and associated Full Time Equivalent (FTE)
reduction available from this transformation programme are very different post-pandemic to
those identified – based on pre-pandemic historical experience – by the Council's Digital
Business Partner; 
(2) that it be recognised that the Year 4 Roadmap and future digital developments build upon
lessons learnt, and knowledge and experience gained, from progressing the transformation
strands of DigitalNL and SmartNL; 
(3) that the successful delivery of the Digital Workplace and Cloud Migration components of the
DigitalNL Transformation Programme be acknowledged; 
(4) that it be recognised that commitment to the continued development of the Digital Council,
and associated governance alongside enhancements and reuse of the Digital Platform, create
scope to deliver digital processes, automation and financial and non-financial benefits; 
(5) that it be acknowledged that the Connectivity Framework, and the partnership with
Commsworld, provide the underlying infrastructure to transform and innovate Council
services, ultimately placing local people, elected members and communities at the heart of
the Council's revised operating model; 
(6) that it be recognised that the actions outlined within the report enable the Council to drive
forward its ambition to become a leading digital authority, and 
(7) that, otherwise, the contents of the report be noted. 
P077.1  WORKFORCE  FOR  THE  FUTURE  PROGRESS  UPDATE 
6. There was submitted a report by the Deputy Chief Executive (1) reminding the Committee that the
Council has a well established Workforce for the Future Strategy, which takes forward the aspirations
of the Plan for North Lanarkshire to drive inclusive growth; (2) providing an update on how the Council
is partnering with employers as it progresses its rolling out of the Strategy and in response to emerging
challenges; (3) reporting that the Council’s integrated and innovative approach has put it in an
excellent position to capitalise on new opportunities, such as the UK Shared Prosperity Fund, which
will enable the Council to better navigate the challenging economic landscape being faced by both
employers and employees; (4) intimating that the plan is to create jobs and to meet employment
demand by enabling businesses to grow and develop their workforce and to ensure that all
opportunities, including apprenticeships and work placements, demonstrate the principles of fair work
and pay and providing an update on the success of a recently launched scheme to reward businesses
which demonstrate these values in practice; (5) highlighting a number of planned developments in
regards to engagement with key industry sectors, which are anticipated to ensure much more effective
pathways are in place to employment in these areas, and (6) detailing successes, so far, in creating
jobs and pathways to jobs and the potential to add significant ongoing value in the labour market.

Page 4

POLICY  AND  STRATEGY  -  1  DECEMBER  2022 
87
Decided: 
(1) that the increase in workforce demands now being seen within growth sectors, and a
concerning position with overall workforce availability in North Lanarkshire’s labour market, be
noted; 
(2) that the good progress being made with the Workforce for the Future Programme of Work in
the challenging context, including the significant employer engagement and positive feedback
which is now informing the Council’s plans, be endorsed; 
(3) that the further development of the academy model, and the first stage outcome of the
construction skills options appraisal , and the development of a full business case to progress
this work, be noted and endorsed; 
(4) that the increased funding and resources which have now been aligned to support delivery of
the Programme of Work in the next phase be noted, and 
(5) that the intention to bring a further progress update to the Committee in Cycle 2 of 2023 be
endorsed. 
It was agreed in terms of Section 50A(4) of the Local Government (Scotland) Act 1973, that the public
be excluded from the meeting for the following item on the grounds that the business involved the
likely disclosure of exempt information as defined in paragraph 10 of Part 1 of Schedule 7A of the Act. 
P001  THE  ENTERPRISE  STRATEGIC  VEHICLE  –  UPDATE  AND  FUTURE  DEVELOPMENT 
7. There was submitted a report by the Head of Asset and Procurement Solutions (1) providing a further
update on the Enterprise Project highlighting both progress to date and planned future development;
(2) explaining that the project aims to achieve an integrated client function for asset management
across the Council with Phase 1 contract awards expected to be made for the Housing and Corporate
Contract in October 2023 and the Roads Contract in December 2023 and that Phase 2 of the project,
from 2026, will thereafter aim to optimise asset related arrangements that underpin the delivery of the
Plan for North Lanarkshire and allow further integration and development of strategic supply
relationships;  (3) providing details of procurement activity, and decisions made to date, by the Project
Board;  (4) explaining that project resource is necessarily focused on the delivery of the Housing and
Corporate and the Roads Contracts and that suitable short-term arrangements to provide play shaping
advisory services, as and when required, are available, and the longer-term solution will be developed
as soon as project resource capacity allows; (5) outlining the Project Governance arrangements, and
(6) indicating that a further report will be provided to Committee in May 2023 reporting the progress of
the procurement and the outcome of the options revalidation exercise for the Housing and Corporate
Contract and the progress of the Roads Contract. 
Decided: 
(1) that the status of the Housing and Corporate Contract as set out in the report be
acknowledged; 
(2) that the status of the Roads Contract as set out in the report be acknowledged; 
(3) that the status of the play shaping contract as set out in the report be acknowledged; 
(4) that, in relation to the Housing and Corporate Contract, the decisions taken by the Project
Board, as detailed in the report, be acknowledged, and 
(5) that a further report be provided to the Committee in May 2023 reporting on the progress of
the procurement and the outcome of the options revalidation exercise for the Housing and
Corporate Contract and the progress of the Roads Contract.