North Lanarkshire Council
Report
Policy and Strategy Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref DB/EK/GT Date 11/10/22 
Capital Investment Programme Update 
From  Elaine Kemp, Head of Financial Solutions  
E-mail kempe@northlan.gov.uk Telephone 07939 280601 
1. Background 
1.1 The Council’s updated five-year Strategic Capital Investment Programme from 2021/22
to 2025/26 was approved at Policy and Strategy Committee in March 2022. This
programme totalled £725.354m and was underpinned by significant funding from the
Council’s Community Investment Fund (£261.147m). 
1.2 As the Committee will be aware, the Community Investment Fund is subject to annual
review based on a number of factors including the rate of new house building, Council
Tax rises and the cost of borrowing. The most recent review was presented to Policy
Executive Summary
The Community Investment Fund Annual Update report to Policy and Strategy Committee
in September 2022 highlighted the requirement to reduce the Council’s capital investment
programme by £22.076m to ensure that programme activity matches funding availability. 
This report presents the outcome of the review of the capital programme undertaken by
the Council’s Strategic Capital Delivery Group while ensuring alignment with the Council’s
previously agreed capital prioritisation matrix and, therefore, the Plan for North
Lanarkshire. 
Recommendations
It is recommended that Committee:
(1) Approves the recommended budget reductions outlined in paragraph 2.10 and in
Appendix 1, 
(2) Acknowledges the ongoing capital programme funding risks linked to wider
economic factors, and
(3) Endorses the approach to the development of a future strategic capital programme
as outlined in paragraphs 2.13 to 2.15. 
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

and Strategy Committee on 29 September 2022 and highlighted a projected reduction
of £42.241m over the 10-year planning period. The impact on the current 5-year capital
planning period is a reduction of £22.076m. 
1.3 With the reduction in resources available to support the current capital investment
programmes, the Council’s Strategic Capital Delivery Group (SCDG) was tasked with
reassessing priorities with a view to reducing the programme to match funding
available. 
2. Report 
Review Process
2.1 The Council’s SCDG met on several occasions throughout September and October
2022 to agree the scope and principles of the review and to finalise the
recommendation to Committee. 
2.2 The review process has been guided throughout by the prioritisation matrix agreed for
the development of the initial five-year Strategic Capital Investment Programme as
approved at Policy and Strategy Committee in March 2021. 
2.3 The agreed scoring methodology gave every proposed project for the current capital
programme a weighted score to demonstrate its contribution to the Council’s priority
outcomes and additional criteria linked to contribution to issues such as financial
sustainability, environmental sustainability and asset management planning.   
2.4 The previous scoring process also included an assessment of unavoidable
commitments. Unavoidable commitments were defined as projects that had already
commenced, had been committed as a result of a committee decision or those of
strategic importance. These projects were top sliced from the available resources, with
the remaining bids assessed in accordance with their relative weighted score and
matched with the funding available. Therefore, no project scoring below 50% was
allocated funding unless it was deemed to be unavoidable.   
2.5 Given the Council’s priority outcomes have not changed, and the additional criteria are
still as relevant now as they were when they were established in December 2020,
SCDG agreed that this should be the basis for the review of the capital programme. In
effect, SCDG agreed to focus its attention on the projects with the lowest priority score
to identify budget reductions of £22.076m to match funding availability. 
2.6 In addition, given the scale of the challenge SCDG also agreed to review where there
was potential for reductions in core Council funding where additional grant support had
been received. 
Review Outcome
2.7 Potential budget reductions totalling £31.531m were identified from the review;
£14.520m from a review of prioritisation and £17.010m from potential grant synergies. 
2.8 Removing the Council’s capital contingency of £2.781m reduces the required budget
reduction target from £22.076m to £19.295m. 
2.9 The SCDG met on 6 October 2022 to RAG the options as follows: 
• Green – agreement from the Group on recommending a budget reduction, 
• Amber – sufficient uncertainty or risk associated with the potential budget reduction
so agreement to not to recommend a budget reduction, and

Page 3

• Red – the Group agreed that it could not recommend a budget reduction at this
stage. 
2.10 The outcome is presented on Appendix 1 with explanations and notes on each of the
budget lines. In summary, the SCDG was able to identify £19.295m of recommended
budget reductions (highlighted in Green in the Appendix) with £12.236m not
recommended for reduction at this stage (see those highlighted in Amber and Red).
Note that given the recommendation of removal of the Shared Campus budget
allocation from the current 5-year capital planning cycle there is an allowance made for
essential, unavoidable health and safety and legislative works to be undertaken at the
Civic Centre. 
Risks
2.11 The Community Investment Fund Annual Update report presented to Policy and
Strategy Committee on 29 September 2022 highlights the impact of significant
increases in the Bank of England base interest rate may have on the Council’s cost of
borrowing. It is highlighted that an increase in the average rate of Council borrowing to
4.75% would reduce overall funding available by £64.896m. 
2.12 As part of its proactive Treasury Management Strategy, the Council is continually
reviewing its cash balances and loan debt profile to minimise borrowing costs.
However, Committee should be aware that if interest rates continue to rise, or stay at
higher levels for a sustained period of time, the Council will be required to undertake
further reviews to ensure the capital programme matches funding available.   
Future Capital Programme Development
2.13 The Council is nearing the end of the second year of its five-year capital planning
period. It was always the intention of the SCDG to undertake a review of the 2021/22
to 2025/26 capital programme during the first three years with a view to developing a
new five-year programme, or potentially a plan covering a longer period of time. 
2.14 Therefore, SCDG will seek to work with Services to develop a new, reset capital
programme to commence from 2024/25. It is hoped that there will be more economic
certainty at that stage in relation to issues such as interest rates, house building etc. 
2.15 The new capital programme will also aim to reflect the updated Programme of Work
and will be driven by the recently approved Corporate Asset Management Plan which
creates the potential that funding available for the Council’s ambitions is maximised. 
3. Measures of success 
3.1  Ensuring that capital programme plans are prioritised in line with the Council’s priority
outcomes whilst ensuing that programme activity matches available funding.   
4. Supporting documentation 
Appendix 1 – Capital Programme Review 
Elaine Kemp
Head of Financial Solutions

Page 4

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Financial impacts are outlined throughout the report. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒

Page 5

If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
Through SCDG the Council will be managing ongoing risk associated with the
strategic capital investment programme, including but not limited to:
• Failure to spend in-year capital grant which may result in any unspent portion
being returned to the Scottish Government. However, given the significant level
of Community Investment Fund activity this risk is deemed to be low at this
stage. 
• Project delays and programme issues that impact on the delivery of the
programme and result in increases costs or reduced outcomes.
• Reductions in funding available through the Community Investment Fund as a
result of external factors facing the Council. This is managed through regular
monitoring of CIF assumptions and sensitivity analysis / scenario planning.

Page 6

Appendix 1 
Capital Programme Review
Total
£m
Reduction to be identified 22.076            
Removal of contingency 2.781              
Balance to be identified 19.295            
Review of Prioritisation (recommended budget reductions):
Demolitions 1.000               G HoS assessment that it is possible to reduce within the current 5 year planning period
but requires consideration for future capital planning rounds
IT 6.01  Minor (application dependancy software) 0.006               G HoS assessment that this would be a low risk reduction
SEPA funding Garrellburn 0.112               G Additional funds from SEPA to contribute towards the project overspend.  Note the
project overspend was absorbed in NLC funds during 21/22 therefore this balance now
available to allocate in 22/23.
Traffic Signals 0.150               G Budget for A73 Corridor Improvements no longer required
Design Fees underspend 22/23 Environmental Assets 0.381               G Based on 22/23 forecast. Sufficient budget remains in future years to support costs
Design Fees underspend 22/23 Asset and Procurement Solutions 0.056               G Based on 22/23 forecast. Sufficient budget remains in future years to support costs
Shared Campus 6.000               G Current economic climate with increased costs of construction and increased
borrowing costs have resulted in an agreement to pause work on the Shared Campus
proposals until external market conditions improve.
A consequence of the reprofiling of work on the Shared Campus proposal would be the
requirement to review essential, unavoidable maintenance on the Civic Centre building
to include issues such as lifts, roof works, limited window works, electrical
improvements etc.
ASC - Aids and adaptations 0.650               G Based on forecast spend levels in 22/23 - thereby reducing future 3 years allocation to
£2.2m per annum
City Deal - Ravenscraig North 4.762               G RIA (North and South) allocated £17.6m in current 5 year programme. Deferral of some
expenditure to beyond the current capital planning period linked to latest information
from transport assessments
IT3.04 Co-ordinated Interactive Panels Installations 0.303               G Schools to contribute more towards the replacement / renewal of current smart board
estate
IT5.04 - Immersive Experience Pods 0.181               G Funding pressures on capital programme necessitates a longer-term deployment of the
additional immersive experience rooms across Council locations. This reduction
enables immersive experience rooms to be deployed to a further two towns, with
locations determined following a rigorous option appraisal and assessment against the
Town and Community Hub design and delivery principle
IT3.05 Co-ordinated Education End User Device Hardware Upgrade 0.920               R HoS recommendation this is reduced as very last resort.  The current budget allocation
supports refresh of hardware across the Council to ensure compatability with the
current network infrastructure
Sub Total 14.520

Page 7

Review of external funding synergies:
Community Board Project Investment Fund - SG Play grant and Shared
Prosperity Fund
4.016               G £7.5m allocation over the 5 year period but significant additional funding received via
NLC investments / Covid recovery, Scottish Government grants to support play area
renewal / upgrades and Shared Properity Fund.
Active travel / Infrastructure & Transportation Improvements 1.116               A Additional funding included in the Shared Prosperity Fund bid and additional funding
from Scottish Government for Cycling, Walking and Safer Routes (CWSR) are in excess
of full 5 year NLC 'priority allocation' for Active Travel. There is the potential to remove
core NLC budget, however, recognition that NLC resource levers additional funding
from Sustrans and SPT
Economic Regeneration - Town Centres - Placed Based Investment
Programme
1.678               G £1.678m represents the 'priority allocation' value. Consideration of known future
Scottish Government capital grant allocations: 22/23 £2.436m, 23/24 £1.698m, 24/25
£1.698m
Traffic Signals 0.500               R HoS recommendation that there is no reduction at this stage
LUF - Cumbernauld Town Centre 9.700               R Currently assumed to be funded from Economic Regeneration (Town Centre) allocation
and Committee approval so a successful LUF bid could 'release' this allocation.
Note: £9.7m represents the purchase of the site(s) only.
17.010            
Total Potential Solutions Identified 31.531            
Balance to be identified / (excess) (12.236)
Summary:
Green 19.295            
Amber 1.116              
Red 11.120