Agenda pack

North Lanarkshire Council · 13 October 2022
Back to Planning Committee — 13 October 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Our Ref:
Your Ref:
Contact:
Tel:
Fax:
E-Mail:
Date:     
Mark Hamill
07811294702 
hamillm@northlan.gov.uk 
4 Oct 2022 
Members of the
Planning Committee     
Chief Executive’s Office
Archie Aitken
Head of Legal & Democratic
Solutions
Civic Centre, Windmillhill Street
Motherwell ML1 1AB
DX 571701, Motherwell 2
www.northlanarkshire.gov.uk      
Notice is given that a hybrid Meeting of the PLANNING COMMITTEE is to be held within the Council
Chamber, Civic Centre, Motherwell on Thursday, 13 October 2022 at 10:00 am which you are
requested to attend. 
The agenda of business is attached.    
Head of Legal and Democratic Solutions 
Members :     Councillors: B Baudo, A Beveridge, G Brennan, B Burgess, A Campbell, M Coyle,
S Coyle, G Currie, A Duffy-Lawson, T Fisher, T Johnston, G Lennon, J Logue,
H Loughran, F MacGregor, P McDade, C McManus, F McNally, M McPake, D Robb,
N Shevlin, A Smith, A Stubbs, L Stubbs and G Woods. 
Page 1 of 113

Page 2

Page 2 of 113

Page 3

AGENDA
(1) Declarations of Interest in terms of the Ethical Standards in Public Life Etc. (Scotland) Act
2000
(2) Planning Applications Index (page 5 - 86)
Submit Planning Applications Index (copy herewith)
(3) Notice of Planning and Enforcement Appeal Lodged (page 87 - 88)
Submit report by the Head of Planning and Regeneration advising of one planning and
enforcement appeal lodged (copy herewith)
(4) Planning and Enforcement Appeals Decision (page 89 - 90)
Submit report by the Head of Planning and Regeneration advising of one planning and
enforcement appeals decision (copy herewith)
(5) The Town and Country Planning (Fees for Applications) (Scotland) Regulations 2022
(page 91 - 104)
Head report by the Head of Planning and Regeneration setting out recommendations in
relation to additional fees the Council may wish to consider charging which could deliver
additional resources to enhance the service provided and ensure a well-resourced and
efficient planning service is maintained (copy herewith)
(6) Contract Award - Idox Hosted and Managed Service (page 105 - 113)
Submit report by the Head of Planning and Regeneration seeking approval to award of  Call-
Off Contract for a Hosted and Managed service to Idox Software Ltd. (copy herewith)
Page 3 of 113

Page 4

Page 4 of 113

Page 5

North
Lanarkshire
Council               
Planning Applications for consideration 
of Planning Committee 
Committee Date: 13-10-2022                      
Ordnance Survey maps reproduced from Ordnance Survey 
with permission of HMSO Crown Copyright reserved 
AGENDA ITEM 2
Page 5 of 113

Page 6

APPLICATIONS FOR PLANNING COMMITTEE 
13th October 2022 
Page
No
Application No  Applicant Development/Site Recommendation 
8-18 19/01460/FUL  Mrs J Fionda Four detached dwellinghouses (including
demolition of existing house) (revised layout)
110 Glen Road
Wishawhill
Wishaw
ML2 7NP
Refuse 
19-27 21/01580/FUL  North
Lanarkshire
Council
Residential development (25 flats) with
associated roads and drainage infrastructure
Site At Gibb Street
Chapelhall 
Grant 
28-61 
62-67 
68-78 
79-86
22/00770/S42 
22/00780/FUL 
22/00836/FUL 
22/00868/FUL 
Greengairs
East Wind
Farm Limited 
ASE 7 LLP 
Guala
Closures UK 
Wireless
Infrastructure
Group
Construction of Wind Farm including
Permanent Meteorological Mast, Site
Entrance, Access Tracks, Crane
Hardstandings, Control Building,
Underground Cables and Temporary
Construction Compound (Section 42
Application to Vary Condition 1 and Delete
Condition 38 of Planning Permission
19/01292/S42 to extend the operational life to
40 years and allow 3 years for restoration)
Site To North Of Easterton
Airdrie Road
Caldercruix 
Change of Use from Class 6 (Storage and
Distribution) to Fitness Studio Class 11
(Assembly and Leisure)
10 Badenheath Place Westfield
Cumbernauld
G68 9HX 
Manufacturing Facility and Offices with
associated Parking, Landscaping and
Infrastructure
Land North Of Craignethan Drive
Gartcosh 
Installation of a new 40m high lattice
telecoms tower with 12 x antennas and
ancillary equipment and the relocation of 4 x
300mm diameter dishes, all contained within
a new compound enclosed by way of a 2.5m
high palisade fence
Grant 
Grant 
Grant 
Grant 
Page 6 of 113

Page 7

Fir Park Stadium
Motherwell
ML1 2PR 
Page 7 of 113

Page 8

Application No:  
19/01460/FUL
Proposed Development: 
Four detached dwellinghouses (including demolition of existing
house) 
Site Address: 
110 Glen Road
Wishawhill
Wishaw
ML2 7NP 
Date Registered:
7th January 2021 
Applicant:
Mrs J Fionda
110 Glen Road
Wishaw
ML2 7NP 
Agent:
Graham  Mckay
GMDL Architecture
11 Orchard Street
Carluke
ML8 5AJ 
Application Level:
Local Application  
Contrary to Development Plan:
Yes
Ward:   
19 Motherwell South East And Ravenscraig: 
Kenneth Duffy, Agnes Magowan, Nathan Wilson,
David Robb
Representations:
9 letter(s) of representation received.   
Recommendation: Refuse 
Reasoned Justification: 
The application is contrary to policy EDQ 3 of the adopted North Lanarkshire Local Development
Plan, because the proposed layout does not demonstrate a high standard of design and would
not result in a high quality development.  The layout of the houses in the rear part of the site
would detract from the amenity of neighbouring houses and would fail to provide a satisfactory
level of amenity for the future residents due to overlooking and overshadowing.  In addition, the
design of the new access as currently proposed would not be acceptable in terms of maintaining
the safety and convenience of road users. 
Page 8 of 113

Page 9

Reproduced by
permission of the
Ordnance Survey on
behalf of HMSO. ©
Crown Copyright and
database right 2009.  All
rights reserved.
Ordnance Survey
Licence number
100023396.
Planning Application: 19/01460/FUL 
Name (of applicant): Mrs J Fionda
Site Address: 110 Glen Road
Wishawhill, Wishaw, ML2 7NP
Development: Four detached
dwellinghouses (including demolition of
existing house)   
Page 9 of 113

Page 10

Recommendation: Refuse for the Following Reasons:- 
1. The proposed development would be contrary to policy EDQ 3 of the adopted North Lanarkshire
Local Development Plan because the proposed layout does not demonstrate a high standard
of design, and would not result in a high quality development.  The proposal would detract from
the amenity of neighbouring houses and would fail to provide a satisfactory level of amenity for
the future residents due to overlooking and overshadowing.  In addition, the design of the new
access would detract from the safety and convenience of road users. 
Background Papers: 
Consultation Responses: 
The Coal Authority    response dated 30 April 2021
Scottish Water    response dated 8 January 2021
Arboriculture    response dated 2 March 2022
Greenspace    response dated 19 March 2021
Protective Services (Environmental Health)  response dated 26 January 2021
Traffic & Transportation    response dated 19 January 2021 
Contact Information: 
Any person wishing to inspect these documents should contact Keith Bathgate at
planningenquiry@northlan.gov.uk 
Report Date: 
27th September 2022
Page 10 of 113

Page 11

APPLICATION NO. 19/01460/FUL 
REPORT 
1. Site Description 
1.1 The application site is a substantial garden of approximately 0.4ha, which currently contains a
large 1960s bungalow and detached garage.  The surrounding area is residential, and the site
is surrounded by a mixture of one- and two-storey houses of varying ages and styles to the
north, west and south, and by a public park (Belhaven Park) to the east.  Although most of the
surrounding houses are themselves detached properties, the application site has a much larger
plot than any of them as it is a remnant of an earlier development pattern in the street (in which
several old houses with large plots have been redeveloped and subdivided over the years). 
The garden contains a number of mature trees, notably two large sequoias in the centre of the
site (a Giant Redwood and a California Redwood), and it is subject to a tree preservation order. 
The site is relatively flat but the prevailing landform falls to the west, meaning that the two
bungalows to the west are at a lower level than the site.  Existing access is by way of two
relatively narrow gates (one currently disused) in the high stone wall which fronts Glen Road. 
The existing bungalow is positioned towards the rear of the site, and due to its distance from
the road and the intervening trees, the building is not prominent when viewed from the street. 
2. Proposed Development 
2.1 The application seeks permission to demolish the existing bungalow and to build four detached
houses on the site.  One house (“Plot 4”) would be located in the southernmost corner of the
site, using the existing main gates for access.  The other three plots would be positioned in the
northern (rear) half of the site, and would share a new driveway and parking / turning areas
accessed from the western end of the site frontage (replacing the existing unused secondary
access gate).  The new houses would all be large two-storey detached houses with five
bedrooms, and would be finished in render with split stone detailing and grey concrete rooftiles.  
Most of the existing trees on the site would be retained, including the two large sequoias,
although some lime trees on the site frontage would be removed to create the new access, and
a small hawthorn would be removed to allow the house on Plot 4. 
3. Applicant’s Supporting Information 
3.1 In addition to the application form and plans, the application includes a SUDS drainage report,
a tree survey report, and a coal risk report. 
4. Site History 
4.1 The present bungalow dates from the 1960s, when it replaced a Victorian villa on the plot.  An
application to redevelop the site as 22 flats in 1998 was withdrawn after it became clear that it
was likely to be refused (application 98/00744/FUL).  Other recent applications on the site have
related to householder development and tree works within the garden of the existing bungalow. 
5. Development Plan 
5.1 The proposed development does not raise any strategic issues, and therefore does not require
to be assessed against the Clydeplan Strategic Development Plan. 
5.2 Under the North Lanarkshire Local Development Plan 2022 the site lies within the General
Urban Area, where policies PP3 and AD3 seek to maintain and improve the level of amenity by
encouraging development that is in keeping with the character of existing residential areas. 
New housing is acceptable in principle within the General Urban Area, subject to site-specific
and design considerations.
Page 11 of 113

Page 12

5.3 The site is subject to a Tree Preservation Order (TPO), and the corresponding policy PROT A
seeks to protect natural and sustainable places by safeguarding natural heritage assets. 
Planning permission will only be granted for proposals affecting locally-designated sites (such
as TPOs) where it can be demonstrated that there will be no adverse impact or that any impacts
can be adequately mitigated against.  Further guidance on trees is contained in supplementary
planning guidance note SPG02 (Trees and Development). 
5.4 Policy CI indicates that the Council will seek developer contributions to address any
infrastructure or service improvements which become necessary as a result of the proposed
development.  Policy EDQ 1 requires that any proposed development be subject to a suitable
site appraisal to ensure that it will integrate successfully into the local area and avoid harming
neighbouring amenity.  Policy EDQ 2 requires that planning applications be accompanied by
suitable supporting information in respect of any specific constraints affecting the site, including
ground instability arising from historic coal mining.  Policy EDQ3 indicates that applications will
only be approved where high standards of site planning and sustainable design are achieved. 
6. Consultations 
6.1 The Coal Authority has no objection to the proposal subject to conditions requiring an invasive
site investigation and approval of any resultant mitigation works prior to commencement of
development. 
6.2 Protective Services (Environmental Health) have no objection subject to a condition requiring
the reporting of any unanticipated contamination found during development work. 
6.3 Transportation Services (Roads) were consulted on an earlier layout and noted concerns about
junction spacing and visibility splays.  The amended layout does not address these concerns,
however the matter is discussed further below. 
6.4 The Greenspace Service has no objection to the proposal but notes the apparent difficulty in
carrying out this level of development without either affecting the existing trees or having major
root protection zone constraints.  Updated ecological surveys would be needed prior to
commencement because of the time which has passed since the previous surveys were
undertaken. 
6.5 Scottish Water has no objection, and have confirmed that at the time of consultation there was
sufficient spare capacity in the local water and sewerage networks. 
7. Representations 
7.1 Nine representations have been received from nearby residents, who object to the application
for the reasons summarised below.  Some of the representations do not object to the principle
of redeveloping the site, but they object to the detail of the proposal.  Some of the specific
comments related to previous layout proposals for the proposed development. 
 Out of character with the surrounding area as it fails to reflect the generosity of space
between existing houses;
 The existing house and most neighbouring houses are bungalows, and any new
development should also be single storey;
 Proposed large 2-storey houses close to edges of site would be out of scale;
 Four large 5-bed houses is overdevelopment – site is only large enough for three plots;
 Overlooking and loss of privacy due to large two-storey houses close to site boundaries;
 Position of first floor windows overlooking neighbouring properties;
 Overbearing effect of large buildings positioned close to neighbours’ gardens/windows;
 Overshadowing of neighbouring properties;
 Neighbouring houses are at lower ground levels which exacerbates overlooking /
overshadowing problems;
Page 12 of 113

Page 13

 Layout is overly concerned with protecting trees and results in houses being positioned in
locations which adversely affect neighbours; 
 Adverse impact on trees on the site and on wildlife in nearby woodland;
 Proposal is contrary to Council’s policies on site appraisal and quality of development;
 Poor quality of drawings, with numerous inaccuracies and omissions;
 Question whether trees are shown in correct positions on plans;
 Alterations to the distinctive/characterful stone garden wall to form access will adversely
affect character of area;
 Alterations to the front garden wall should be in natural stone matching existing material;
 Road safety concerns due to increased traffic on a narrow section of Glen Road with
substandard pavements;
 Inadequate sight lines at junction onto Glen Road;
 Insufficient parking on site and no opportunity for on-street parking;
 Increased traffic noise;
 Noise and damage from construction traffic;
 Need to avoid damage to common walls during demolition;
 Unstable ground in area due to old mineworkings;
 Insufficient details of drainage; and
 Increased demand on utilities, including existing drainage which is said to be poor 
8. Planning Assessment 
Development Plan Policies
8.1 Section 25 of the Town and Country Planning (Scotland) Act 1997 requires that applications for
planning permission be determined in accordance with the policies of the statutory development
plan unless material considerations indicate otherwise.  In this case the proposal raises no
strategic issues and does not conflict with any Clydeplan SDP policies, so the relevant policies
are those of the North Lanarkshire Local Development Plan 2022 (“the LDP”). 
8.2 The site is within the General Urban Area where policies PP 3 and AD 3 seek to maintain and
approve amenity, including encouraging development which is in keeping with the character of
residential areas.  Policy PP 3 indicates that new housing within such areas is deemed to
support the purpose of the plan, subject to the provisions of the EDQ policies.  Policy AD 3
indicates that there is no requirement to justify new housing within the General Urban Area in
terms of need.  The application site is an existing house plot within a residential part of the
town, it is much larger than any of the surrounding house plots, and the existing bungalow is
neither a listed building nor within a conservation area.  The demolition and the subdivision of
the site into smaller house plots would therefore be consistent in principle with the General
Urban Area policies, albeit that the detail of the proposal raises issues in terms of the EDQ
policies (discussed below).  The proposal is also consistent with policy CI as the small scale of
development (i.e. a net increase of only 3 dwellings) does not give rise to a requirement for a
developer contribution towards education, transport infrastructure or green infrastructure. 
8.3 Policy PROT A (Category A3) applies to locally designated natural heritage assets, including
trees which are subject to tree preservation orders.  The policy indicates that permission will
not be granted unless it is demonstrated that the development will not adversely affect the
protected trees or unless adequate mitigation will be undertaken.  In this case the proposal
would retain the two most important trees on the site (the two large sequoias) and many of the
other trees, and whilst some trees would be lost it is considered that these are less significant
specimens and that their loss could be mitigated by suitable new landscaping.  For example,
the group of lime trees on the site frontage which would be removed to form the new access
have been very heavily pollarded and therefore have a quite unnatural form.  There would be
a need for tree root protection to avoid damage to the retained trees during construction work,
and it would also be necessary to update the ecological surveys due to their age, but subject
to these requirements it is considered that the proposal would be consistent with policy PROT
A. 
Page 13 of 113

Page 14

8.4 Policy EDQ 1 covers site appraisal, and in broad terms requires that planning applications be
accompanied by sufficient supporting information to demonstrate that the applicant has
adequately appraised the site and its surroundings and taken relevant matters into account in
the design of the development.  Matters to be taken into account include: 
 Massing and height of buildings on the site and surrounding area;
 Orientation and topography of the site and surrounding area;
 Building lines, plot ratios, groupings of buildings and types of enclosure in the area;
 The nature and types of features to be safeguarded or enhanced on the site 
In this case, despite a very protracted application process, it is considered that these matters
have not been adequately addressed by the proposed layout, a situation which stems in part
from an inadequate site appraisal at the outset of the application.  If the application had been
determined when it was first submitted it would have been contrary to policy EDQ 1 due to lack
of supporting information.  However, these issues were explored during the course of the
application, and whilst the various amendments to the layout have not been able to fully
overcome the problems, this is no longer due to a lack of awareness of the issues, so it is not
considered that there is a conflict with EDQ 1. 
8.5 Policy EDQ 2 requires that specific constraints be addressed, including contaminated land and
coal mining legacy risks.  The supporting information provided is adequate, and subject to
suitable conditions there would be no conflict with this policy. 
8.6 Policy EDQ 3 requires a high standard of site planning and sustainable design, in order to
achieve a high quality development in terms of various assessment criteria including: 
 Establishing a clear vision for the site with design principles which lead to a distinct,
successful place addressing siting, overall layout, density, form, scale, height, massing,
proportion, detailing, colour and materials;
 Providing a safe, pleasant, inclusive, convenient and welcoming development addressing
(amongst other things) safe and convenient access;
 Existing features of green network or historical environmental interest (e.g. traditional
stone walls) protected under policy PROT A or identified under policy EDQ 1 will be
safeguarded or enhanced. 
In this case it is not considered that a high standard of site planning and design has been
demonstrated or that the resultant development would be of a high quality, and the
shortcomings of the design are explained in detail below.  It is therefore considered that the
proposal is contrary to policy EDQ 3. 
Design and Amenity
8.7 On paper, the site is large enough to be divided into four plots of similar size to those of the
neighbouring houses. In practice, however, this is constrained by the need to take account of
existing features of natural and built heritage value, and by the relationship to neighbouring
houses.  In particular, the site has a number of mature trees which contribute significantly to
the appearance and character of this part of Wishawhill, the most significant of which are the
two large and healthy sequoias.  The roots of these trees will extend across much of the centre
of the site, which severely limits the amount of the site which is capable of being developed
without causing damage to these trees.  As it is considered that retention of these two trees is
of particular importance, options for siting of the proposed houses are limited, and the obvious
approach is to locate one house in the southern corner of the site utilising the existing main
access gate, with other new houses positioned towards the north of the plot (behind the sequoia
trees).  The southernmost house (“Plot 4”) is relatively straightforward as it would utilise the
existing access gates, would have a similar relationship to the street to the existing houses on
the north-east side of Glen Road, and would be well enough separated from the sole
neighbouring house (108 Glen Road) to avoid causing any significant overlooking or
overshadowing.  In itself, the proposed house on Plot 4 is therefore considered to be
acceptable. 
Page 14 of 113

Page 15

8.8 The existing driveway leading to the back of the site passes between the two sequoia trees,
but it would be difficult to use this driveway as the access to the new houses because the
necessary widening and additional traffic use would be likely to damage the tree roots, and
retention of this route would also make it difficult to fit a house onto Plot 4.  Consequently, it is
proposed to take the access to Plots 1-3 along the western edge of the site, widening the
existing disused section of driveway at this location and avoiding the root protection areas for
the large trees.  This is also a logical design approach, although it would necessitate alterations
to the original stone wall fronting Glen Road and removal of a group of mature but heavily
pollarded lime trees on this part of the frontage, and as discussed below the geometry of the
access as currently proposed is unsatisfactory. 
8.9 Whilst the aforementioned parts of the development are considered to be either acceptable or
capable of being made acceptable with further amendments, the proposals for the rear of the
site are considered to be unacceptable.  Various amendments to the layout during the course
have explored different ways of fitting three large detached houses and their associated
gardens, parking and turning area into the rear half of the site, but none of these layouts has
been considered satisfactory due to impacts upon neighbouring houses.  Even with two of the
houses (Plots 2 and 3) pushed towards the rear corners of the site (and thus relatively close to
the boundary with neighbouring houses), there is little room for the fourth house (Plot 1) which
can only be accommodated by squeezing it in between the access and either the side boundary
(as previously proposed) or the trees (as currently proposed).  The result is a cramped layout
in which it is considered that the relationship of the three rear houses to each other and to
neighbouring properties is unacceptable. 
8.10 Specific problems with the current layout include: 
 The Plot 1 house is positioned directly north of the two sequoia trees and only 14-18m
from their trunks (i.e. just outwith the root protection area of the nearest tree).  These trees
are 23-28m high and would seriously overshadow the proposed house, making it very
likely that future residents would seek to cut the trees down.  Whilst the height of these
trees would inevitably affect any new houses in the northern part of the site, the proximity
of the proposed Plot 1 house would result in a particularly overbearing relationship;
 Window to window distances between Plots 1 and 2 are around 10m, whereas the
Council’s normal minimum is 18m;
 The Plot 2 house is positioned approximately 6.1m from the rear boundary adjoining 122
Glen Road (whereas normal minimum rear garden depth is 10m) and just over 3m from
the side boundary with 120 Glen Road (which itself is positioned very close to the
boundary).  Although the house type that has been chosen has only bathroom windows
facing these boundaries at first floor level and there is no window to window conflict, the
need to restrict window positions to two adjoining elevations to prevent overlooking when
the front elevation itself fails to provide suitable window to window separation emphasises
the cramped nature of the layout;
 The Plot 3 house is positioned 7.6m from the rear boundary bordering 122 Glen Road, and
whilst previous layouts avoided having first floor habitable-room windows facing towards
this boundary, the present layout has two bedroom windows facing the neighbouring house
creating an overlooking conflict;
 The design of the access onto Glen Road is substandard in width and geometry. 
Whilst some of these are issues which might be addressed by further amendments, the
fundamental difficulty of accommodating four houses on the site would remain.  This
application was first submitted almost three years ago and although officers have worked with
the applicant in an effort to reach an acceptable design, the numerous amendments to the
layout which have already been made have still not resulted in a satisfactory layout.  Under
the circumstances it is considered that seeking further amendments is unlikely to be
productive, as more significant changes to reduce the number or size of houses would be
needed and that would be better addressed as a fresh application. 
Technical Consultations
8.11 Matters raised by the Coal Authority can be addressed by conditions requiring a site
investigation for historic coal mining features, whilst Protective Services also has no objection
Page 15 of 113

Page 16

subject to a standard condition covering any contamination discovered during construction
work.  Greenspace and Arboricultural Services have provided comments on ecology and trees,
and it is considered that although some of the protected trees would need to be removed and
an updated ecological survey would be needed, the proposal is acceptable in these respects
and the issues could all be addressed by conditions. 
8.12 The Transportation Service commented on earlier layouts but not on the most recent
amendment.  Transportation’s preference would be for an adopted road to serve the houses at
the rear of the site, however in practice that could not be achieved on the site without loss of all
of the significant trees and the stone wall, and it is therefore considered that in principle a
shared private driveway would be a reasonable means of access to Plots 1-3, provided that
such driveway was constructed to an appropriate standard. Plot 4 would use the existing
access, which does not comply with current standards but is nevertheless an existing
arrangement which would not be made any worse by the proposal. 
8.13 Whilst in principle a shared driveway along the western boundary of the site is acceptable, it is
clear that the geometry of the access currently proposed is not satisfactory.  In response to
concerns about vehicles egressing at an oblique angle and with apparently limited westwards
visibility due to an adjacent boundary wall, the applicant has amended the plans by simply
narrowing the access in order to force vehicles to egress at a less oblique angle but even closer
to the wall, and has not complied with requests to show the visibility splays.  The resultant
access is therefore now unduly narrow and awkwardly aligned in addition to the visibility
concerns not having been resolved.  Again, this is potentially something which would be
capable of being resolved by amendment, but it is indicative of the lack of attention to detail
which has been a problem with this application from the outset, and it reinforces the concerns
that the design is not of an appropriate quality. 
Matters Raised in Representations
8.14 The issues raised by objectors are considered as follows: 
 Out of character with the surrounding area as it fails to reflect the generosity of space
between existing houses; The existing house and most neighbouring houses are
bungalows, and any new development should also be single storey; Proposed large 2-
storey houses close to edges of site would be out of scale; Four large 5-bed houses is
overdevelopment – site is only large enough for three plots 
Response: The area contains a mix of different house types and plot sizes, and it is
considered that two-storey houses would be acceptable in principle if the layout was
satisfactory.  As discussed above, whilst Plot 4 is considered to be acceptable, Plots 1-3
are squeezed into the back half of the site resulting in an unsatisfactory layout with houses
positioned relatively close to boundaries and with various window to window conflicts.  It
is considered that four houses of the size proposed is likely to be an overdevelopment of
the site given then constraints imposed by the trees. 
 Overlooking and loss of privacy due to large two-storey houses close to site boundaries;
Position of first floor windows overlooking neighbouring properties; 
Response:  The applicant has sought to address overlooking by selecting house types with
limited windows on rear and side elevations and orientating them accordingly.  The
handing of the house on Plot 3 has changed with the most recent amendment, and this
has introduced some overlooking of 122 Glen Road.  Other than that issue (which could
be addressed by handing the house or repositioning windows) the only first floor windows
facing neighbouring properties are bathrooms, and boundary screening should prevent
overlooking from ground floor windows.  However, as noted above, there would be a direct
window to window conflict between Plots 1 and 2 within the development. 
 Overbearing effect of large buildings positioned close to neighbours’ gardens / windows;
Overshadowing of neighbouring properties; Neighbouring houses are at lower ground
levels which exacerbates overlooking / overshadowing problems; 
Page 16 of 113

Page 17

Response: It is acknowledged that neighbours who have been used to a bungalow on this
site would find two-storey houses much more noticeable, especially when some of them
are close to the boundary and the ground level is higher than that of the neighbouring
houses to the west.  However, it is not considered that the relationship would actually be
overbearing, or that any significant overshadowing would arise, especially in view of the
shadow which is already cast by the very tall trees. 
 Layout is overly concerned with protecting trees and results in houses being positioned in
locations which adversely affect neighbours; Adverse impact on trees on the site and on
wildlife in nearby woodland; 
Response: The trees on the site (in particular the two large sequoia) are of significant
benefit to the appearance and character of the area, so it is appropriate that they be
retained and the development designed around them.  Limited felling of poorer quality
trees is considered to be acceptable in order to facilitate development, subject to
appropriate replacement planting, and it is not considered likely that the proposal would
aversely affect ecology provided tree felling did not take place within bird nesting season
and an updated ecological survey was carried out before work started.   The need to retain
the trees does not justify poor design or adverse impacts on neighbours, and it is
recommended that the application be refused. 
 Proposal is contrary to Council’s policies on site appraisal and quality of development;
Poor quality of drawings, with numerous inaccuracies and omissions; Question whether
trees are shown in correct positions on plans; 
Response: As discussed above there have been difficulties with the quality of some of the
plans and documents during the course of the application.  However, the current plans and
information are sufficient to allow the application to be properly assessed. 
 Alterations to the distinctive/characterful stone garden wall to form access will adversely
affect character of area;  Alterations to the front garden wall should be in natural stone
matching existing material; 
Response: The wall contributes to the character of the area and should be retained to the
extent practical, but there are a variety of boundary treatments in the vicinity and it is
considered reasonable to form a wider access at the west end of the frontage and to
provide appropriate visibility splays, which would necessitate changes to the position and
height of the wall.  It would be expected that recovered stone from the existing wall would
be used in any rebuilt sections. 
 Road safety concerns due to increased traffic on a narrow section of Glen Road with
substandard pavements;  Inadequate sight lines at junction onto Glen Road;  Insufficient
parking on site and no opportunity for on-street parking; 
Response: This is a lightly trafficked section of Glen Road which serves only eight houses
beyond the application site, and the application would add only three additional houses. 
The increase in traffic is therefore not likely to be significant.  It is agreed that the new
junction should have suitable sight lines and the shortcomings of the current access
proposal are discussed above.  Each of the houses would have at least three parking
spaces, with three dedicated visitor spaces, and this level of provision is considered to be
adequate.  Whilst the section of Glen Road in front of the site is narrow, other parts of the
street are wide with ample space for on-street parking. 
 Increased traffic noise;  Noise and damage from construction traffic; Need to avoid damage
to common walls during demolition; 
Response:  The additional traffic generated by 3 additional houses would be relatively
minor, and although the proposed new driveway passes close to the western boundary of
the site it is not likely that the limited domestic traffic would give rise to significant
disturbance.  Some disturbance is inevitable during any construction project, but this is not
Page 17 of 113

Page 18

grounds for preventing development.  Damage to third party property would be a civil
matter between the landowners concerned. 
 Unstable ground in area due to old mineworkings;  Insufficient details of drainage; 
Increased demand on utilities, including existing drainage which is said to be poor; 
Response: The application has been supported by a coal mining risk assessment and the
Coal Authority has no objection subject to conditions.  Scottish Water has no objection to
the proposal and have confirmed the availability of spare foul sewage capacity.  Surface
drainage would be by way of SUDS which could be addressed by a condition, and given
the size of the site this should not present any undue difficulty. 
9. Conclusions 
9.1 Whilst the principle of demolishing the existing bungalow and replacing it with several new
houses is consistent with General Urban Area policies AD 3 and PP 3, the detailed proposals
are contrary to policy EDQ 3 because they do not demonstrate a high standard of design and
would not result in a high quality development.  The proposed layout of the houses in the rear
part of the site would detract from the amenity of neighbouring houses and would fail to provide
a satisfactory level of amenity for the future residents due to overlooking and overshadowing. 
In addition, the design of the new access as currently proposed would not be acceptable in
terms of maintaining the safety and convenience of road users. 
Page 18 of 113

Page 19

Application No:  
21/01580/FUL
Proposed Development: 
Residential development (25 flats) with associated roads and
drainage infrastructure (amended layout)  
Site Address: 
Site At Gibb Street
Chapelhall 
Date Registered:
21st June 2022 
Applicant:
North Lanarkshire Council
Fleming House
1 Tryst Road
Cumbernauld
G67 1JW 
Agent:
Coltart Earley Architecture
559 Sauchiehall Street
Glasgow
G3 7PQ 
Application Level:
Local Application  
Contrary to Development Plan:
Yes
Ward:   
12 Airdrie South 
Michael Joseph Coyle, Paul Di Mascio, Sandy
Watson, Michael McBride,
Representations:
7 letter(s) of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
Whilst the proposal is contrary to local development plan policy PROT A, material
considerations justify a departure from that policy in this instance.  The proposal is consistent
with all other relevant LDP policies and would provide high quality social housing without
detracting from the amenity of the surrounding area. 
Page 19 of 113

Page 20

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 21/01580/FUL 
Name (of applicant): North Lanarkshire
Council
Site Address: Site At Gibb Street
Chapelhall 
Development: Residential development
(25 flats) with associated roads and
drainage infrastructure (amended layout)   
Page 20 of 113

Page 21

Proposed Conditions:- 
1. That, except as may otherwise be agreed in writing by the Planning Authority, the development
shall be implemented in accordance with drawing numbers:- 
L(20)015; L(20)016; L(90)001B; L(90)100E; L(91)003; 11043-AT03A, AT04A, AT07A, AT08A
and AT09; 21/11043/114C, 116B and 121B 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. Unless otherwise approved by the Planning Authority, all of the recommendations contained in
Section 9 of the WSP Phase 2 Contaminated Land and Geotechnical Assessment (August 2021)
shall be fully implemented as part of the development of the site.  In particular: 
a) The additional testing for lead in the vicinity of trial pits TP07 and TP11 shall be
undertaken and a report detailing the findings and any changes to the mitigation
proposals arising therefrom shall be submitted to and approved in writing by the
Planning Authority prior to the commencement of development; 
b) In the event of asbestos in soil being identified on the site, a detailed quantitative risk
assessment and any mitigation proposals arising therefrom shall be submitted to and
approved in writing by the Planning Authority as soon as possible following discovery
of the material; and
c) Any imported soils shall be subject to chemical testing to confirm suitability for use on
the site, in terms of human health, water and built environment criteria. 
Reason: In order to ensure that the condition of the ground on the site is suitable for residential
development, in the interests of public health. 
3. No dwelling shall be occupied until such time as a verification report (prepared by a suitably
qualified independent specialist) confirming that all of the remediation measures detailed in
condition 2 above have been fully implemented to the appropriate standard has been submitted
to the Planning Authority. 
Reason: In order to ensure that the condition of the ground on the site is suitable for residential
development, in the interests of public health. 
4. No development shall commence until such time as a detailed Green Network Mitigation Strategy
has been submitted to and approved in writing by the Planning Authority.  Such strategy shall
include: 
a)  landscaping proposals for the whole site including tree/shrub planting in line with the
details shown on the approved layout plan;
b)  ecological/landscaping enhancements to the remaining areas of open space to
increase their biodiversity value; and
c)  details of the timescale for implementation of these works and the arrangements for
future maintenance thereof 
The approved Green Network Mitigation Strategy shall thereafter be implemented and
maintained in accordance with the approved details. 
Reason: In order to secure improvements to the Green Network to mitigate the loss of part of the
open space, and to ensure that the development is appropriately landscaped so as to be of
suitable appearance. 
5. No dwelling shall be occupied until such time as the junction onto Gibb Street has been
completed to its finished standard as detailed on the approved plans, including visibility splays
measuring 4.5m by 60m in both directions along Gibb Street which shall be free of obstructions
greater than 1.05m in height. 
Reason: In the interests of road safety.
Page 21 of 113

Page 22

Background Papers: 
Consultation Responses: 
NLC Traffic & Transportation  responses dated 8 July 2022 and 6 September 2022
NLC Environmental Health   responses dated 16 December 2021 and 3 February 2022
NLC Greenspace  response dated 8 February 2022
Archaeology Service  response dated 29 June 2022
The Coal Authority  response dated 17 December 2021 
Contact Information: 
Any person wishing to inspect these documents should contact Keith Bathgate at
planningenquiry@northlan.gov.uk 
Report Date: 
21st September 2022
Page 22 of 113

Page 23

APPLICATION NO. 21/01580/FUL 
REPORT 
1. Site Description 
1.1 The application site comprises an area of grass open space in the northern part of Chapelhall. 
It  extends to approximately 1.54ha and is surrounded on three sides by the back gardens of
two-storey houses and cottage flats, and by a play area to the north-west.  A small local shop
also backs onto the site close to the play area.  A footpath runs through the middle of the side,
connecting Aitkenhead Road with the play area and Queen’s Crescent, and there is a residents’
car park and a lane accessing back gardens along the western boundary.  The site was once
a railway cutting and despite some infilling this history is still reflected in its levels, with the path
through the middle of the site being slightly lower than the land and houses to either side. 
2. Proposed Development 
2.1 The application seeks full planning permission for 25 flats, comprising 11 one-bedroom and 14
two-bed properties all of which would be social housing units for rent.  Three of the ground floor
flats would be designed specifically to accommodate wheelchair users.  Vehicular access would
be from Gibb Street at the northern of the site (between the play area and the local shop).  The
development would be laid out as a private parking court resembling a cul-de-sac, with the road
and parking running down the middle of the site and the flats arranged as 4 two-storey four-in-
a-block buildings down the west side of the parking court and a three-storey block across the
southern end of the site.  The flats, gardens and parking would occupy around half of the
footprint of the site, and the eastern part of the site would remain as open space, containing a
realigned footpath and new landscaping.  The existing parking and domestic access track on
the western edge of the site would be retained, and a strip of landscaping would separate this
area from the new flats.  Parking would be provided for 45 cars (including 3 disabled spaces),
whilst surface water drainage would be by way of SUDS. 
3. Applicant’s Supporting Information 
3.1 In addition to the application form and plans, the application documents include a drainage
assessment, an ecological survey, a site investigation report and a planning statement. 
4. Site History 
4.1 The site has no recent planning history.  It is assumed to have been landscaped as an open
space area following closure of the railway in the 1960s. 
5. Development Plan 
5.1 The site is within the urban area, and its development for housing would not raise any strategic
issues or conflict with any of the policies of the Clydeplan Strategic Development Plan 2017. 
5.2 The North Lanarkshire Local Development Plan (adopted 2022) designates the site as a Green
Network Site within the General Urban Area.  The corresponding policies are policies PROT A
(Natural Environment and Green Network Assets), PP3 (General Urban Area - Purpose of
Place) and AD3 (General Urban Area - Amount of Development).  In addition, policies CI
(Contributions to Infrastructure), EDQ1 (Site Appraisal), EDQ2 (Specific Features for
Consideration) and EDQ3 (Quality of Development) are relevant to applications of this nature. 
Page 23 of 113

Page 24

6. Consultations 
6.1 The Transportation Service has no objection to the proposal subject to the provision of the
junction visibility splays, parking and turning areas, and the provision of a vehicle barrier
adjacent to the play area. 
6.2 Protective Services (Environmental Health) has no objection subject to conditions relating to
further site investigation and verification of the mitigation works. 
6.3 The Greenspace Service recommends that biodiversity enhancements be incorporated into the
development and its landscaping. 
6.4 The Coal Authority confirms that the site where the physical works would take place is within
the Development Low Risk Area, and they therefore have no comment on the proposal. 
6.5 The Archaeology Service indicates that the development of the site should not impact on nearby
archaeological assets, and no conditions are necessary. 
7. Representations 
Seven representations have been received from people who object to the proposal for reasons
which can be summarised as follows: 
 Support provision of social housing, but not at the expense of existing community open
space;
 Loss of an open space which is well used by local residents for recreation, including
children’s games, football, golf practice, sledging and dog walking;
 This is the only significant area of parkland/open space in the vicinity;
 Contrary to Green Network policy in the adopted LDP, the wording of which was
strengthened by the Scottish Government following the LDP examination in recognition of
the contribution such spaces make to community wellbeing;
 If the council wanted to develop this as a housing site it should have been put forward as
part of the LDP process rather than being included in the Green Network;
 Allowing development of a Green Network site for housing would set an undesirable
precedent and may enable other housebuilders to do likewise;
 Alleyway at back of existing houses may be lonely and dangerous;
 Site has previously been infilled and is subject to flooding in places so may not be suitable
for housing;
 Will this result in the loss of the new play area?
 Complaints about housing allocation system which seems to prioritise people with anti-
social behaviour issues instead of locals 
8. Planning Assessment 
Development Plan Policy
8.1 The proposed development is not of a strategic scale and does not conflict with Clydeplan
housing or green network policies.  The proposal is therefore not a strategic matter and does
not require further assessment against the Clydeplan Strategic Development Plan. 
8.2 In terms of the North Lanarkshire Local Development Plan, the application site is within the
General Urban Area.  Policy PP3 seeks to maintain and improve amenity within urban areas
by encouraging development which is in keeping with their residential character whilst also
encouraging diversity in more mixed-use locations. The development of housing on a
brownfield site within the urban area is in principle consistent with this policy, subject to its
impact on amenity being considered acceptable, which is discussed below.  Policy AD3
confirms that there are no quantity limits and no requirement for any assessment of housing
land supply for sites within the General Urban Area.  The principle of housing within the General
Urban Area is therefore consistent with these policies.
Page 24 of 113

Page 25

8.3 However, the site is also designated as a Green Network Site, where policy PROT A (A4 Urban
Green Network) is applicable.  This policy seeks to protect natural areas, outdoor sports
facilities and other green open spaces which contribute to quality of life in local communities. 
Planning permission will only be granted for proposals affecting such sites if it can be
demonstrated that there will be no adverse impact or that any environmental impacts can be
mitigated against.  In this case, the proposal involves the partial development of an area of
existing open space, and although some environmental enhancements are intended as
mitigation the proposal is contrary to policy PROT A. 
8.4 Policy CI requires that new development proposals should provide or contribute towards any
enhanced infrastructure or services which will be necessary as a result of the development,
including education, transport, green infrastructure and play facilities.  In this case, the
application is by the Council itself so there is no requirement for a developer contribution
towards education, and the proposal is not of a scale which would necessitate any off-site
transport works.  The site is also immediately adjacent to an existing play area and multi-use
games pitch, so there is no requirement for further play facilities.  However, green network
enhancements would be needed to offset the loss of part of the existing open space, and this
could be addressed by a condition.  Subject to such a condition, the proposal is in accordance
with this policy. 
8.5 Policy EDQ1 indicates that all development is required to integrate successfully into the local
area and avoid harm to neighbouring amenity, whilst policy EDQ3 indicates that development
proposals will only be permitted where high standards of site planning and design are achieved. 
Applications are expected to demonstrate that the proposal takes account of an appropriate
site appraisal and that the design would result in a high quality of development.  The proposal
if for housing of a scale and character comparable with the surrounding residential area, and
whilst it would impact upon the Green Network it is not considered that the impact thereon
would be unacceptable.  The design and layout are considered to be appropriate, and overall,
the proposal is considered to be consistent with policies EDQ1 and EDQ3. 
8.6 In terms of policy EDQ2, the only specific feature for consideration in this instance is the
potential for contaminated land, due to the site having historically been part of a railway line
and subject to infilling of ground.  The site has been subject to a detailed site investigation and
Protective Services are content with the proposed remediation scheme, so the proposal is
consistent with this policy. 
Principle of Development
8.7 The main issue for consideration in this application is the principle of developing the site for
housing, given that the site is an existing area of amenity open space which is designated as
part of the Green Network. 
8.8 The applicant’s supporting statement explains that although the site has been used as open
space for many years it was always owned by the Housing Service as opposed to being a
formal public park.  Following a consultation process with ward councillors and the Tenant
Federation during 2019 the site was identified as suitable for housing development as part of
the Council’s housing programme.  In May 2020 the Council’s Housing and Regeneration
Committee approved the inclusion of this site within the new-build programme, which seeks to
provide 5,000 new social rented homes by 2035 to meet identified needs.  In September 2021,
prior to submitting the planning application, the Council’s New Supply team undertook a public
consultation exercise with the local community during September 2021.  The outcome of that
exercise was that 11 responses were received, of which 2 supported the development (due to
provision of new houses and existing fly-tipping problems at the location, whilst 9 did not
support it (because of loss of open space and privacy concerns).  Nevertheless, the project was
pursued because it was considered that adequate open space would remain in the vicinity and
because of the importance of providing new social housing.  The proposed new properties
would include three specially designed accessible flats for disabled people, and all properties
would be designed to modern energy-efficient specifications to minimise carbon emissions and
heating costs.  During the application process, the development was amended and scaled back
from the original plan so that only around half of the site would now be developed and the
Page 25 of 113

Page 26

remainder of the site would stay as open space, the quality of which would be enhanced by
landscape / ecology improvements as mitigation against the reduction in the amount of open
space. 
8.9 The proposal is contrary to LDP policy PROT A because it will result in the reduction in size of
an area of Urban Green Network.  The policy does not prohibit development of such sites, but
it does specify that permission for development adversely affecting the Urban Green Network
will only be granted where the impacts can be adequately mitigated in environmental terms.  In
this case, the application site has very limited ecological / environmental value as it is primarily
an area of maintained amenity grassland, with only small areas of semi-improved neutral
grassland along its boundaries.  The ecological study found no evidence of protected flora or
fauna on the site.  The site is close to the edge of the settlement, but it is separated from the
woodland which borders the town by the play area, and it is unlikely that the site functions as a
wildlife corridor as it is effectively a ‘green cul-de-sac’ which is largely surrounded by houses. 
It is therefore considered that the partial development of the site would have no significant
impact upon the natural environment or upon the integrity of the wider Green Network. 
Conversely, the provision of Green Network enhancements within the undeveloped portion of
the site would have potential to increase its potential as a wildlife habitat, resulting in a net
increase in the ecological value of the site. 
8.10 The other purpose of the Green Network policy is to protect open spaces within urban areas
where these have amenity or recreational value for local residents.  The site evidently has some
value as such a space, and the main focus of the objections to the application is that it would
result in the loss of this area.  Most of the objections were received in response to the original
proposal which would have involved development of the whole site, whereas the amended
proposal would now retain the eastern half of the site as open space.  Nevertheless, it is
acknowledged that the proposal would result in a reduction in the amount of open space at this
location, and would reduce its potential for some recreational uses such as use as a kickabout
area.  There are however several nearby areas of open space in the northern part of Chapelhall,
including the play area and multi-use games area immediately to the north west of the site,
other (smaller) amenity grass areas at George Street and Melrose Avenue, and extensive
publicly-owned woodland walking routes to the north of the town.  On balance, given the
availability of other open space areas in the vicinity, the loss of part of the existing open space
is considered to be acceptable in view of the benefits of providing new social housing and the
ecological mitigation measures. 
Design and Amenity
8.11 The proposed development would comprise primarily two-storey four-in-a-block flats which
would be in keeping with the predominantly two-storey housing of the surrounding area.  There
would also be one three-storey block of nine flats, which would be higher than any building in
the immediate vicinity but this height is not considered to be excessive in the context of the site. 
The layout would take the form of a cul-de-sac, with the new properties running down wester
side and across its southern end only, facing towards the retained area of open space on the
eastern half of the site.  Footpath access through the site would be retained, with the path being
realigned to run through the retained open space area.  The new properties along the western
side of the site would be well off the boundary, at a lower level than the existing houses on Gibb
Street, and separated from these by the existing access lane and by new planting on the
embankment side.  At the southern end of the site the sole three-storey block would back onto
houses at Aitkenhead Road which are at a lower level, but it would be well separated from
these, with flat window to rear garden boundary distances of at least 28m and window to window
distances exceeding 38m.  It is considered that the proposed design and layout would provide
an attractive residential environment in keeping with the character of the area, and that there
would be no significant detriment to the amenity of neighbouring properties. 
Technical Considerations
8.12 The application has been accompanied by a site investigation report which concluded that there
is a low risk of contamination issues affecting human health, and Protective Services agree with
these findings and have no objection to the application.  There are no known coal mining legacy
risks or archaeological features on the site.  The road layout involves a private parking court
rather than an adopted road, but it would provide adequate junction visibility splays, car parking
Page 26 of 113

Page 27

and turning facilities which would be sufficient to allow turning of a bin lorry.  There are therefore
no objections to the application from any technical consultees, subject to various conditions
being applied. 
Representations
8.13 The majority of the representations object to the loss of part of the existing community open
space / Green Network site, which has been addressed in paragraphs 8.7 - 8.10 above. 
However, as explained above it is acknowledged that a loss of open space will occur and that
the proposal is contrary to LDP policy PROT A, but it is considered that there is sufficient
alternative open space in the vicinity and that the benefits of additional social housing combined
with green network enhancements on the balance of the site are sufficient to justify a departure
from policy PROT A. 
8.14 Other matters raised by objectors and the responses to these are as follows: 
 Alleyway at back of existing houses may be lonely and dangerous;
Response:  This is an existing alleyway which needs to be retained to allow access to
existing back gardens, albeit that not all existing householders use it.  The alleyway is
currently open to the grass open space, but would become more enclosed due to the new
flats and planting.  However, the new flats would also increase overlooking of the alleyway,
and it is not considered likely to attract anti-social behaviour. 
 Site has previously been infilled and is subject to flooding in places so may not be suitable
for housing;
Response: As a former railway cutting which had been infilled as a landscaped area the
site undulates and may have been subject to localised flooding, but this would be addressed
by the recontouring of the site and the installation of new surface drainage infrastructure as
part of the development. 
 Will this result in the loss of the new play area?
Response:  The play area is outwith the application site and will not be affected by it. 
 Complaints about housing allocation system which seems to prioritise people with anti-
social behaviour issues instead of locals
Response: The housing allocation system is not a material planning consideration. 
9. Conclusions 
9.1 Whilst the proposal is contrary to local development plan policy PROT A due to the loss of an
area of Urban Green Network, it is considered that in this particular case the availability of other
open space in the vicinity, the benefits of providing new social housing and the potential
ecological benefits arising from the mitigation works are sufficient to justify a departure from
that policy.  The proposal is consistent with all other local development plan policies and there
are no objections from technical consultees, and it is therefore recommended that the
application be approved subject to conditions. 
Page 27 of 113

Page 28

Application No:  
22/00770/S42
Proposed Development: 
Construction of Wind Farm including Permanent Meteorological
Mast, Site Entrance, Access Tracks, Crane Hardstandings,
Control Building, Underground Cables and Temporary
Construction Compound (Section 42 Application to Vary
Condition 1 and Delete Condition 38 of Planning Permission
19/01292/S42 to extend the operational life to 40 years and allow
3 years for restoration) 
Site Address: 
Site To North Of Easterton
Airdrie Road
Caldercruix 
Date Registered: 
6th July 2022 
Applicant:
Greengairs East Wind Farm Limited
Muirhall Farm
Auchengray
Carnwath
ML11 8LL 
Agent:
Andrew Marshall
Muirhall Energy Ltd
Muirhall Farm
Auchengray
Carnwath
ML11 8LL 
Application Level:
Major Application 
Contrary to Development Plan:
No
Ward:   
08 Airdrie North 
Alan Beveridge,Sophia Coyle,Henry Emerson
Dunbar,Richard Alan Sullivan,
Representations:
1 letter(s) of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The proposed variation of Condition 1 and deletion of Condition 38 of planning permission
19/01292/S42 to allow for the extension to the operational life of the wind farm to 40 years and to allow
up to 3 years for restoration of the site is considered to accord with the terms of the development plan. 
Referral to Scottish Government:
If the Council is minded to grant approval against the advice of Glasgow Airport, it must notify Glasgow
Airport, the Civil Aviation Authority and the Scottish Ministers as per Circular 2/2003: Town and Country
Planning (Safeguarded Aerodromes, Technical Sites and Military Explosives Storage Areas) (Scotland)
Direction 2003.  
Page 28 of 113

Page 29

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 22/00770/S42 
Name (of applicant): Greengairs East
Wind Farm Limited
Site Address: Site To North Of Easterton
Airdrie Road
Caldercruix
North Lanarkshire 
Development: Construction of Wind Farm
including Permanent Meteorological
Mast, Site Entrance, Access Tracks,
Crane Hardstandings, Control Building,
Underground Cables and Temporary
Construction Compound (Section 42
Application to Vary Condition 1 and
Delete Condition 38 of Planning
Permission 19/01292/S42 to extend the
operational life to 40 years and allow 3
years for restoration)   
Page 29 of 113

Page 30

Proposed Conditions:- 
1. That the development hereby shall subsist for a period of 40 years from the date of final
commissioning of the wind farm.  Written confirmation of the final commissioning date shall be
provided to the Planning Authority within 7 days of the final commissioning date.  Within three
years of the date of expiry of the planning permission, unless a further planning application is
submitted and approved, the wind turbines, ancillary equipment, access tracks and buildings
shall be dismantled and removed from the site and the land restored in accordance with a
detailed restoration and after-care scheme to be submitted for the approval of the Planning
Authority no later than 2 years prior to the expiry of the 40-year period. 
Reason: To accord with the provisions of the Town and Country Planning (Scotland) Act 1997
as amended and to allow the Planning Authority to review the circumstances of the temporary
permission, in the interests of the amenity of the area in the longer term, beyond the 40-year
period covered by the permission. 
2. That the operators shall at all times accord with the areas forming the subject of this consent in
accordance with the approved plans and other supporting information, including the
Environmental Impact Assessment and Supplementary Environmental Information submitted
with application 12/00602/FUL and amended by the Supplementary Environmental Information
submitted with application 19/01292/S42 and updated by the Supporting Statement submitted
with application 22/00770/S42, except as amended by the terms of the approval hereby given
and shall omit no part of the approved operations and shall not amend the development
(including changes to the make, model or colour) without the prior written consent of the
Planning Authority. 
Reason: To clarify the drawings and information on which this approval of planning permission
is founded in order that the Planning Authority can retain effective control. 
3. That PRIOR to the erection of any wind turbines, details of the precise positioning of each wind
turbine shall be submitted to and approved in writing by the Planning Authority. The wind
turbines shall be positioned, unless otherwise agreed in writing, no more than 50 metres in any
direction from the location of each wind turbine as shown on the approved plans. 
Reason: To allow flexibility in positioning turbines and to ensure that amenity and
environmental assets are protected. 
4. That the number of wind turbines approved shall not exceed 8, the blade tip shall not exceed
149.9m and the power output of the wind farm shall not exceed 38.4 MW. 
Reason: To define the permission.
Page 30 of 113

Page 31

5. That no symbols, signs or logos or other lettering, other than those required for health and
safety, shall be displayed on any part of the turbines nor any other building or structures without
the written consent of the Planning Authority. 
Reason: In the interests of the amenity of the area. 
6. That all turbine blades shall rotate in the same direction. 
Reason: In the interests of the visual amenity. 
7. That, prior to the erection or installation of any ancillary equipment or buildings on site, the
design, colour and finish of the equipment and buildings shall be submitted to and approved in
writing by the Planning Authority and the development shall be completed in accordance with
these details. 
Reason: To allow the Planning Authority to consider these matters in detail. 
8. The rating level of noise emissions from the combined effects of the wind turbines (including
the application of any tonal penalty) when determined in context with the Guidance Notes
(attached to this condition), shall not exceed the values for the relevant integer wind speed set
out in, or derived from, the tables attached to these conditions at any dwelling which is lawfully
existing or has planning permission at the date of this permission and: 
a) The wind farm operator shall continuously log power production, wind speed and wind
direction, all in accordance with Guidance Note 1(d). These data shall be retained for a period
of not less than 24 months. The wind farm operator shall provide this information in the format
set out in Guidance Note 1(e) to the Planning Authority on its request, within 14 days of receipt
in writing of such a request. 
b) No electricity shall be exported until the wind farm operator has submitted to the Planning
Authority for written approval a list of proposed independent consultants who may undertake
compliance measurements in accordance with this condition. Amendments to the list of
approved consultants shall be made only with the prior written approval of the Planning
Authority. 
c) Within 21 days from receipt of a written request from the Planning Authority following a
complaint to it from an occupant of a dwelling alleging noise disturbance at that dwelling, the
wind farm operator shall, at its expense, employ a consultant approved by the Planning
Authority to assess the level of noise emissions from the wind farm at the complainant’s
property in accordance with the procedures described in the attached Guidance Notes. The
Page 31 of 113

Page 32

written request from the Planning Authority shall set out at least the date, time and location that
the complaint relates to and any identified atmospheric conditions, including wind direction, and
include a statement as to whether, in the opinion of the  Planning Authority, the noise giving rise
to the complaint contains or is likely to contain a tonal component. 
d) The assessment of the rating level of noise emissions shall be undertaken in accordance
with an assessment protocol that shall, prior to the commencement of any measurements, have
been previously submitted to and approved in writing by the Planning Authority.  The protocol
shall include the proposed measurement location identified in accordance with the Guidance
Notes where measurements for compliance checking purposes shall be undertaken, whether
noise giving rise to the complaint contains or is likely to contain a tonal component, and also
the range of  meteorological and operational conditions (which shall include the range of
wind speeds, wind directions, power generation and times of day) to determine the assessment
of rating level of noise emissions. The proposed range of conditions shall be those which
prevailed during times when the complainant alleges there was disturbance due to noise,
having regard to the written request of the Planning Authority under paragraph (c), and such
others as the independent consultant considers likely to result in a breach of the noise limits. 
e) Where a dwelling to which a complaint is related is not listed in the tables (9.2 to 9.6) listed
in Section 9 of the Environmental Statement AES Wind Generation May 2012 (of planning
consent 12/00602/FUL), the wind farm operator shall submit to the Planning Authority for written
approval proposed noise limits selected from those listed in the tables to be adopted at the
complainant’s dwelling for compliance checking purposes. The proposed noise limits shall be
those limits selected from the Tables specified for a listed dwelling which the independent
consultant considers as being likely to experience the most similar background noise
environment to that experienced at the complainant’s dwelling. The rating level of noise
emissions resulting from the combined effects of the wind turbines when determined in
accordance with the attached Guidance Notes shall not exceed the noise limits approved in
writing by the Planning Authority for the complainant’s dwelling. 
f) The wind farm operator shall provide to the Planning Authority the independent consultant’s
assessment of the rating level of noise emissions undertaken in accordance with the Guidance
Notes within 2 months of the date of the written request of the Local Planning Authority for
compliance measurements to be made under paragraph (c), unless the time limit is extended
in writing by the Planning Authority. The measurements shall include all data collected for the
purposes of undertaking the compliance measurements, such data to be provided in the format
set out in Guidance Note 1(e). The instrumentation used to undertake the measurements shall
be calibrated in accordance with Guidance Note 1(a) and certificates of calibration shall be
submitted to the Planning Authority with the independent consultant’s assessment of the rating
level of noise emissions. 
Page 32 of 113

Page 33

g) Where a further assessment of the rating level of noise emissions from the wind farm is
required pursuant to Guidance Note 4(c), the wind farm operator shall submit a copy of the
further assessment within 21 days of submission of the independent consultant’s assessment
pursuant to paragraph (d) above unless the time limit has been extended in writing by the
Planning Authority. 
Location
Standardised wind speed at 10m height (ms-1) within the site averaged over 10-
minute periods  
4 5 6 7 8 9 10 11 12
Greendykeside 33 33 35 35 35 35 35 37 37
Avalon 35 35 37 37 37 37 38 38 38
Meadowfield 30 30 32 33 33 33 33 33 33
Longriggend 34 34 36 37 37 37 37 37 37
Avonhead cottage 38 38 40 40 40 41 42 42 42
Annandale 30 30 32 33 33 33 33 33 33
Meikledrumgray 29 29 31 32 32 32 32 32 32
West arbuckle 36 36 38 38 38 38 38 38 38
Midtown Farm 38 38 39 39 39 40 40 40 40
Easterton Farm 40 40 41 41 41 42 42 42 42
Caldercruix 34 34 36 37 37 37 37 37 37
Mosside cottage 30 30 32 33 33 33 33 33 33 
Table 1 – Between 07:00 and 23:00 – Noise limits expressed in dB LA90, 10-minute as a function of the
standardised wind speed (ms-1) at 10 metre height as determined within the site averaged over 10 minute
periods. 
Location
Standardised wind speed at 10m height (ms-1) within the site averaged over 10-minute
periods
4 5 6 7 8 9 10 11 12
Page 33 of 113

Page 34

Reason: In order to protect residential amenity. 
9. No development shall take place until an acoustic report has been submitted to, and approved
in writing by, the Planning Authority. The acoustic report shall: 
i) Include final details of the wind turbines to be installed along with manufacturer
warranties to show maximum sound power levels from the turbines across
operational wind speeds up to 12m/s and confirm that the noise from the installed
turbines shall be free from tonal characteristics or where tonal noise is present,
the noise limits are met inclusive of any tonal penalty when assessed within
Guidance Note 3;
ii) Be conducted by a suitably competent and indep.endent consultant as approved
in writing by the Planning Authority prior to the report being undertaken;
iii) Comply with the provisions of ETSU-R-97: The Assessment and Rating of Noise
from Wind Farms;
Greendykeside 33 33 35 35 35 35 35 37 37
Avalon 33 33 35 36 37 38 38 38 38
Meadowfield 30 30 32 32 33 33 33 33 33
Longriggend 34 34 36 36 36 36 37 37 37
Avonhead cottage 37 37 39 40 40 42 42 42 42
Annandale 30 30 32 33 33 33 33 33 33
Meikledrumgray 29 29 31 32 32 32 32 32 32
West arbuckle 36 36 38 38 38 38 38 38 38
Midtown Farm 37 37 38 40 40 40 40 40 40
Easterton Farm 40 40 42 42 42 42 42 42 42
Caldercruix 34 34 36 37 37 37 37 37 37
Mosside cottage 30 30 32 33 33 33 33 33 33 
Table 2 – Between 23:00 and 07:00 – Noise limits expressed in dB LA90, 10-minute as a function of the
standardised wind speed (ms-1) at 10 metre height as determined within the site averaged over 10-minute
periods 
Page 34 of 113

Page 35

iv) Include an assessment of the turbine noise emissions at the locations as identified
in Condition 8 above, and at any other location requested in writing by the Planning
Authority; and 
v) Indicate how far below the limits in Condition 8, the noise emissions from the
turbines will be, at each location, at each wind speed. 
Reason: To consider this aspect in detail in order to protect residential amenity. 
10. Amplitude modulation is the variation of aerodynamic noise at the rate at which the blades pass
a given fixed point of their rotation. the operator shall submit a scheme, to be approved by the
Planning Authority prior to the commencement of operation of the wind farm, for the
assessment and regulation of amplitude modulation effects.  The approved scheme shall apply
the methodology published by Renewable UK on 16th December 2013, including any revisions
applied following review by the Institute of Acoustics, or other suitable methodology endorsed
as good practice by the Institute of Acoustics. This scheme shall be used by the developer to
assess any complaint received by the Planning Authority which relates to Amplitude Modulation
and shall be used to regulate any identified effects. 
Reason: In order to protect residential amenity. 
Guidance Notes for Noise Conditions 
These notes are to be read with and form part of the noise condition. They further explain the 
condition and specify the methods to be employed in the assessment of complaints about noise 
emissions from the wind turbine. The rating level at each integer wind speed is the arithmetic 
sum of  the wind turbine noise level as determined from the best-fit curve described in 
Guidance Note 2 of these Guidance Notes and any tonal penalty applied in accordance  with 
Guidance Note 3. Reference to ETSU-R-97 refers to the publication entitled “The Assessment 
and Rating of Noise from Wind Farms” (1997) published by the Energy Technology Support 
Unit (ETSU) for the Department of Trade and Industry (DTI). 
Guidance Note 1 
(a)  Values of the LA90,10 minute noise statistic should be measured at the complainant’s property,
using a sound level meter of EN 60651/BS EN 60804 Type 1, or BS EN 61672 Class 1
quality (or the equivalent UK adopted standard in force at the time of the measurements)
set to measure using the fast time weighted response as specified in BS EN 60651/BS EN
60804 or BS EN 61672-1 (or the equivalent UK adopted standard in force at the time of
the measurements). This should be calibrated in accordance with the procedure specified
in  BS 4142: 2014 (or the equivalent UK adopted standard in force at the time of the
Page 35 of 113

Page 36

measurements).  Measurements shall be undertaken in such a manner to enable a tonal
penalty to be applied in accordance with Guidance Note 3. 
(b)  The microphone should be mounted at 1.2 - 1.5 metres above ground level, fitted with a
two-layer windshield or suitable equivalent approved in writing by the Planning Authority,
and placed outside the complainant’s dwelling.  Measurements should be made in “free
field” conditions.  To achieve this, the microphone should be placed at least 3.5 metres
away from the building facade or any sound reflecting surface except the ground at the
approved measurement location.  In the event that the consent of the complainant for
access to his or her property to undertake compliance measurements is withheld, the wind
turbine operator shall submit for the written approval of the Planning Authority details of
the proposed alternative representative measurement location prior to the commencement
of measurements, and the measurements shall be undertaken at the approved alternative
representative measurement location. 
(c)  The LA90,10 minute measurements should be synchronised with measurements of the 10-
minute arithmetic mean wind and operational data logged in accordance with Guidance
Note 1(d), including the power generation data from the wind turbine control systems. 
(d)  To enable compliance with the conditions to be evaluated, the wind turbine operator shall
continuously log arithmetic mean wind speed in metres per second and wind direction in
degrees from north at hub height for each turbine and arithmetic mean power generated
by the turbine and any noise curtailment mode in use, all in successive 10-minute periods.
All 10-minute arithmetic average mean wind speed data measured at hub height shall be
‘standardised’ to a reference height of 10 metres as described in ETSU-R-97 at page 120
using a reference roughness length of 0.05 metres.  It is this standardised 10 metre height
wind speed data, which is correlated with the noise measurements determined as valid in
accordance with Guidance Note 2, such correlation to be undertaken in the manner
described in Guidance Note 2.  All 10-minute periods shall commence on the hour and in
10- minute increments thereafter.  
(e)  Data provided to the Planning Authority in accordance with the noise condition shall be
provided in comma separated values in electronic format. 
(f)  A data logging rain gauge shall be installed in the course of the assessment of the levels
of noise emissions. The gauge shall record over successive 10-minute periods
synchronised with the periods of data recorded in accordance with Note 1(d). 
Page 36 of 113

Page 37

Guidance Note 2 
(a)  The noise measurements shall be made so as to provide not less than 20 valid data points
as defined in Guidance Note 2(b) 
(b)  Valid data points are those measured in the conditions specified in the agreed written
protocol under paragraph (d) of the noise condition but excluding any periods of rainfall
measured in the vicinity of the sound level meter.  Rainfall shall be assessed by use of a
rain gauge that shall log the occurrence of rainfall in each 10-minute period concurrent
with the measurement periods set out in Guidance Note 1. 
(c)   For those data points considered valid in accordance with Guidance Note 2(b), values of
the LA90,10 minute noise measurements and corresponding values of the 10- minute
standardised ten metre height wind speed, as derived from site measured wind speed
source agreed in writing with the Planning Authority in accordance with Guidance Note
1(d), shall be plotted on an XY chart with noise level on the Y-axis and the standardised
mean wind speed on the X-axis.  Least squares, “best fit” curve of an order deemed
appropriate by the independent consultant (but which may not be higher than a fourth
order) should be fitted to the data points and define the wind farm noise level at each
integer speed. 
Guidance Note 3 
(a)  Where, in accordance with the approved assessment protocol under paragraph (d) of the
noise condition, noise emissions at the location or locations where compliance
measurements are being undertaken contain or are likely to contain a tonal component, a
tonal penalty is to be calculated and applied using the following rating procedure. 
(b)  For each 10 minute interval for which LA90, 10 minute data have been determined as valid
in accordance with Guidance Note 2 a tonal assessment shall be performed on noise
emissions during 2 minutes of each 10 minute period. The 2 minute periods should be
spaced at 10 minute intervals provided that uninterrupted uncorrupted data are available
(“the standard procedure”).  Where uncorrupted data are not available, the first available
uninterrupted clean 2 minute period out of the affected overall 10 minute period shall be
selected. Any such deviations from the standard procedure, as described in  Section 2.1
on pages 104-109 of ETSU-R-97, shall be reported. 
(c)  For each of the 2 minute samples the tone level above or below audibility shall be
calculated by comparison with the audibility criterion given in Section 2.1 on pages 104 -
109 of ETSU-R-97.
Page 37 of 113

Page 38

(d)  The average tone level above audibility shall be calculated for each wind speed bin, each
bin being  1 metre per second wide and centred on integer wind speeds.  Samples for
which the tones were below the audibility criterion or no tone was identified, a value of zero
audibility shall be substituted. 
(e) The tonal penalty is derived from the margin above audibility of the tone according to the
figure below: 
Guidance Note 4 
(a)  If a tonal penalty is to be applied in accordance with Guidance Note 3 the rating level of
the turbine  noise at each wind speed is the arithmetic sum of the measured noise level as
determined from the best fit curve described in Guidance Note 2 and the penalty for tonal
noise as derived in accordance with Guidance Note 3 at each integer wind speed within
the range specified by the Planning Authority in its written protocol under paragraph (d) of
the noise condition. 
(b) If no tonal penalty is to be applied then the rating level of the turbine noise at each wind
speed is equal to the measured noise level as determined from the best fit curve described
in Guidance Note 2. 
(c)  In the event that the rating level is above the limit(s) set out in the Tables attached to the
noise condition, or the noise limits for a complainant’s dwelling approved in accordance
with paragraph (e)  of the noise condition, the independent consultant shall undertake a
further assessment of the rating level to correct for background noise so that the rating
level relates to wind turbine noise emission  only. 
Page 38 of 113

Page 39

(d)  The wind turbine operator shall ensure that all the wind turbines in the development are
turned off for such period as the independent consultant or Planning Authority requires in
order to undertake the further assessment. The further assessment shall be undertaken in
accordance with the following steps: 
(e)  Repeat the steps in Guidance Note 2, with the wind turbine switched off, in order to
determine the background noise (L3) at each integer wind speed within the range
requested by the Planning  Authority in its written request under paragraph (c) and the
approved protocol under paragraph (d) of the noise condition. 
(f)  The wind turbine noise (L1) at this speed shall then be calculated as follows where L2 is
the measured level with the turbine operating but without the addition of any tonal penalty: 
(g)  The rating level shall be re-calculated by adding arithmetically the tonal penalty (if any is
applied in  accordance with Note 3) to the derived wind farm noise L1 at that integer wind
speed. 
(h)  If the rating level after adjustment for background noise contribution and adjustment for
tonal penalty (if required in accordance with Guidance Note 3 above) at any integer wind
speed lies at or below the values set out in the Tables attached to the conditions or at or
below the noise limits approved by the Planning Authority for a complainant’s dwelling in
accordance with paragraph (e) of  the noise condition then no further action is
necessary. If the rating level at any integer wind speed exceeds the values set out in the
Tables attached to the conditions or the noise limits approved by the Planning Authority
for a complainant’s dwelling then the development fails to comply with the conditions. 
11. That prior to the commencement of development a Primary Radar Mitigation Scheme setting
out measures to be taken to prevent the impairment of the performance of the aerodrome
navigation aids and the efficiency of air traffic control services at Glasgow Airport must be
submitted to, and approved by, the Planning Authority, in consultation with Glasgow Airport
Limited. 
Reason: In the interest of aviation safety
12. No wind turbine forming part of the development shall be erected other than in accordance with
the approved Primary Radar Mitigation Scheme. 
Reason: In the interest of aviation safety.
Page 39 of 113

Page 40

13. The development must be constructed, commissioned and operated at all times fully in
accordance with the approved Primary Radar Mitigation Scheme 
Reason: In the interest of aviation safety.
14. No part of any turbine shall be erected until a Primary Radar Mitigation Scheme agreed with
the Operator has been submitted to and approved in writing by the Planning Authority in order
to avoid the impact of the development on the Primary Radars of the Operator located at
Lowther Hill, Cumbernauld, Glasgow and Kincardine and associated air traffic management
operations. 
Reason:  In the interests of aviation safety and in order to ensure suitable mitigation relating to
the impact of the development on the performance of aerodrome navigation aids and/or the
efficiency of air traffic control at Glasgow Airport and associated air traffic management
operations of the NATS Prestwick Centre. 
15. No part of any turbine shall be erected above ground until the approved Primary Radar
Mitigation Scheme has been implemented and the development shall thereafter be operated
fully in accordance with such approved Scheme. 
Reason: In the interests of aviation safety and in order to ensure suitable mitigation relating to
the impact of the development on the performance of aerodrome navigation aids and/or the
efficiency of air traffic control at Glasgow Airport and associated air traffic management
operations of the NATS Prestwick Centre. 
16. That the turbines shall not be brought into operation until the applicant has demonstrated that
they have agreed with the Ministry of Defence, NATS and CAA the following information: 
฀ Construction start and end dates of the turbines;
฀ The position of the turbine towers in latitude and longitude;
฀ The height of the turbines in metres above ordnance datum and above ground
level; and
฀ The proposed methodology for lighting the turbines 
Reason: In the interests of aviation safety.     
17. That turbines 1, 4, 6 and 8 shall be fitted with 25 candela omni-directional red lighting or infrared
lighting with an optimised flash pattern of 60 flashes per minute of 200ms to 500ms duration at
the highest practicable point unless otherwise agreed in writing with the Planning Authority in
consultation with the MOD. Written confirmation that the lighting has been installed to the
satisfaction of the MOD shall be submitted within 2 months of the turbines being operational.
Page 40 of 113

Page 41

Reason: In the interests of aviation safety. 
18. That prior to the commencement of any works, a full site specific Waste Management Plan
shall be submitted to and approved in writing by the Planning Authority (in consultation with
SEPA) and thereafter all work shall be carried out in accordance with the approved plan. For
the avoidance of doubt this shall consider details on position of water quality monitoring points
(prior to construction taking place) following the establishment of a baseline on water quality.
For the avoidance of doubt the program of hydrological monitoring shall be undertaken as set
out in the letter from AES to SNH dated April 2015. 
Reason: To avoid any significant harm to the environment. 
19. The approved Habitat Management Plan shall be implemented in full for the duration of the
operational life of the wind farm, unless otherwise agreed by the Planning Authority. For the
avoidance of doubt, the approved Habitat Management Plan shall incorporate the habitat
enhancement measures referred to in paragraph 12.1.4 and outlined in appendix 12.C of the
Environmental Statement (AMEC May 2012). 
Reason: To ensure that the measures outlined in the approved Habitat Management Plan are
carried out in accordance with the agreed scheme. 
20.  Notwithstanding the terms of condition 19 above the approved Habitat Management Plan shall
make provision for the formation of a Habitat Management Group (HMG) to monitor
implementation of the plan. Should the Habitat Management Group amend the plan approved
in terms of condition 19 above, the agreed plan as amended shall thereafter be implemented
in full. 
Reason: In the interests of ensuring that the approved Habitat Management Plan is carried out
in accordance with the agreed scheme. 
21. Notwithstanding the terms of conditions 19 and 20 above the approved Habitat Management
Plan as may be amended by the Habitat Management Group shall be submitted to the Planning
Authority for review every 12 months from initial approval until decommissioning and restoration
of the site unless otherwise agreed in writing by the Planning Authority. 
Reason: To allow the Planning Authority to consider these aspects in detailed 
22. The Habitat Management Plan approved under the terms of conditions 18 and 19 above or as
amended shall operate until the decommissioning and restoration of the site.
Page 41 of 113

Page 42

Reason: In the interests of ensuring that the approved Habitat Management Plan is carried out
in accordance with the agreed scheme 
23. That the developer shall appoint an independent Ecological Clerk of Works (ECoW) to monitor
the agreed Habitat Management Plan Area (HMPA) for the duration of the operational life of
the wind farm. 
Reason: To ensure that the required ecological mitigation works included in the Habitat
Management Plan are implemented. 
24. That the access junction upgrading works shall be implemented in full, and to the written
satisfaction of the Planning Authority, prior to any construction works starting on site. 
Reason: In the interest of Road Safety. 
25. That BEFORE the development hereby permitted starts, details of mitigation for potential ice
throw shall be submitted to and approved in writing by the Planning Authority. 
Reason: In the interests of public safety 
26. Should shadow flicker problems be identified within three years of the date of final
commissioning of the wind farm, details of measures to overcome shadow flicker problems at
any affected receptor shall be submitted to, and approved in writing, by the Planning Authority
within two months of the first report of problems; thereafter the approved measures shall be
brought into operation and shall continue throughout the operation of the wind turbine except
as may be agreed in writing by the Planning Authority.   
Reason: In order overcome potential nuisance to receptors through shadow flicker and to clarify
the    start and end date of the three-year limitation period during which any potential effects are
to be identified. 
27. That before any turbine is erected on site, a survey of television signal reception (the scope of
which to be agreed in advance with the Planning Authority) shall be submitted to the Planning
Authority. 
Reason: To establish a baseline against which to assess the impact of the wind turbine on
television reception. 
Page 42 of 113

Page 43

28. That except as may otherwise be agreed in writing by the Planning Authority, within one month
of the approved wind turbines coming into operation a report covering the effect of the wind
turbines on local television signal reception shall be submitted to the Planning Authority;
thereafter any approved measures for overcoming television reception interference shall be
brought into operation within two months of the reports submission to the Planning Authority
unless otherwise agreed in writing with the Planning Authority. For the avoidance of doubt the
report shall include measures to ensure public engagement. 
Reason: In order to overcome any television reception interference caused by the wind turbine. 
29. Restoration shall be implemented in accordance with the approved Detailed Restoration
Scheme and Condition 37 of planning permission 19/01292/S42. 
Reason: To ensure that comprehensive and appropriate restoration of the site is secured. 
30. That before development begins, a scheme of protection measures for the protection of the
Avonhead Colliery during construction works shall be submitted to and approved in writing by
the Planning Authority. The scheme as approved shall thereafter be implemented in
accordance with the approved details.
Reason: To ensure the protection of the scheduled monument. 
31. The aftercare of the site shall be implemented in accordance with the approved Detailed
Aftercare Scheme and Condition 40 of 19/0129/S42. 
Reason: To ensure that comprehensive and appropriate restoration of the site is secured.
32. All work shall be carried out in accordance with the approved Peat Management Plan. For the
avoidance of doubt this shall involve the following:
 Working practises for the removal and storage of peat on site. 
 Reuse of peat on site.
 Removal of peat from the site.
 Quality of peat on site.
 Interaction of the Peat Management Plan and Habitat Management Plan.
 The timetables schedule of the management of the Peat Management Plan.
 An updated Peat Slide Hazard Risk Assessment (PSHRA) which must include
full details of all mitigation necessary to avoid, or reduce to acceptable levels,
the risk of peat slide.
Page 43 of 113

Page 44

 Confirmation that the appointed ECoW will ensure that the peat storage, reuse
and restoration proposals are adhered to and will oversee the works and
practices as outlined in the revised PMP (May 2020 Doc Number 1221808). 
Reason: To ensure that the peat habitat is not significantly affected by this development. 
33. The development shall be implemented in accordance with the approved Construction Method
Statement and Environmental Management Plan. 
Reason: In the interests of the amenity of the area, to ensure that necessary contingencies are
in place, to minimise pollution risks arising from construction activities, and to ensure the site is
satisfactorily restored. 
34. At least one month before development begins, a revised bond or other form of financial
guarantee to secure the cost of performance of site restoration and aftercare obligations shall
be submitted for the written approval of the Planning Authority. No development may
commence until the bond or other form of financial guarantee is approved by the Planning
Authority and is in place to the satisfaction of the Planning Authority. The bond or other form of
financial guarantee shall be maintained until the date of completion of all restoration and
aftercare obligations. The value of the financial guarantee shall be determined by a suitably
qualified independent professional valuer as being sufficient to meet the costs of all outstanding
restoration and aftercare obligations. The value of the financial guarantee shall be reviewed by
a suitably qualified independent professional valuer at least once every five years and adjusted
to take account of any variation in the cost of compliance with the then outstanding restoration
and aftercare obligations. Before each determination or periodic review of the value of the
financial guarantee, the independent professional valuer shall be required to submit a written
valuation report to the Planning Authority and the operator and invite submissions 
from the Planning Authority and the operator on the proposed value of the financial guarantee.
The cost of engaging the independent professional valuer shall be borne by the operator. 
Reason: To ensure that there are sufficient funds to secure performance of restoration and
aftercare obligations.  
Page 44 of 113

Page 45

Background Papers: 
Consultation Responses: 
(1) NLC Protective Services received 11th July 2022 (no objection)
(2) NLC Traffic & Transportation 20th July 2022 (no objection)
(3) Scottish Environment Protection Agency received 20th September 2022 (no objection)
(4) Cumbernauld Airport Ltd received 7th July 2022? 20th September 2022 (objection)
(5) Edinburgh Airport received 12th July 2022 (no objection)
(6) Glasgow Airport received 22nd July 2022 (objection)
(7) National Air Traffic Services (Safeguarding) received 11th July 2022 (no objection) 
(8) Ministry of Defence Estates received 22nd July 2022 (no objection) 
(9) Atkins Global received 7th July 2022 (no objection) 
(10) SP Energy Networks received 16th September 2022 (no objection) 
(11) Nature Scotland received 5th September 2022 (no objection) 
(12) Historic Environment Scotland received 19th July 2022 (no objection) 
(13) The Coal Authority received 29th July 2022 (no objection) 
(14) Royal Soc. for the Protection of Birds – no response 
(15) Scottish Gas Network – no response 
(16) Falkirk Council – no response       
Contact Information: 
Any person wishing to inspect these documents should contact Ann McGregor at 01236 632500 
Report Date: 
03 October 2022
Page 45 of 113

Page 46

APPLICATION NO. 22/00770/S42 
REPORT 
1. Site Description 
1.1  The application site extends to 200 hectares and is located on land north of Easterton, Airdrie
Road and east of Greengairs Landfill site.  The site benefits from planning permission for a
wind farm consisting of 8 turbines each with a height of 149.9m (to blade tip) and with total
maximum capacity of 36MW (Planning Reference 19/0129/S42 granted on the 24th September
2020). The consented wind farm is expected to provide sufficient electricity to power 32,835
homes per year and offset 55,099 tonnes of CO2 emissions per year.  Construction works (as
per planning permission 19/0129/S42) has already commenced.   
1.2  The site is characterised by worked bog peatland with evidence of coal mining legacy and peat
cutting. There are intermittent patches of small trees and lower lying scrub mainly following the
remains of a railway solum along the dismantled rail track to the southwest of the site. The site
is crossed by numerous linear drainage channels dissecting the area of peat working. The site
contains a Site of Importance for Nature Conservation (peatland habitat) which is contained in
the northern part of the site covering only a small part of the designation. A Site of Special
Scientific Interest (Longriggend Moss) is located to the east of the SINC. Historic remains of
Avonhead colliery (scheduled monument) lie within the northern edge of the site. The site
boundary is located to the south and west of Longriggend (west of Telegraph Road) and
equidistant from Caldercruix, Plains and Greengairs. Land to the south is characterised by open
agricultural fields and forest plantation with the settlement of Caldercruix lying beyond. The site
is bounded to the north and west by open fields. It is irregular in shape and extends to
approximately 200 hectares.  Access to the site is from Telegraph Road, Longriggend which
forms the eastern boundary of the site. The site is relatively flat or gently sloping in areas. 
2. Proposed Development 
2.1 The planning application is submitted under Section 42 of the Town and Country Planning
(Scotland) Act 1997 and seeks only to vary condition 1 (operational life of the wind farm) and
to remove condition 38 (restoration of wind farm) of planning permission 19/01292/S42.
Condition 1 of the current consent provides that the wind farm shall subsist for a period of 25
years from the first date of generation of electricity and that within six months of the expiry of
the consent, the wind farm infrastructure shall be removed and the land restored in accordance
with a detailed restoration scheme to be submitted to the Planning Authority for approval within
two years of the expiry of the 25 year period.   
2.2  The current application proposes amendments to the wording of Condition 1 to allow for an
extension of the operational life of the proposed wind farm from 25 years (as detailed and
Page 46 of 113

Page 47

approved in 19/01292/S42) to 40 years and to amend the period within which the ancillary
equipment, access tracks and buildings shall be dismantled and removed from the site and
land restored from six months from the expiry date of the permission (as detailed and approved
in 19/01292/S42) to three years from the day of expiry of the permission.  The current
application also proposes that Condition 38 of planning permission 19/01292/S42, which
provides that the site is restored within one year of the date of cessation of the site operation,
is deleted. The Applicants believe that this matter can be regulated by detailed restoration and
after-care scheme provisions in the proposed reworded Condition 1. 
2.3 Conditions 1 and 38 of the existing consent (19/01292/S42) are set out below. 
Condition 1: 
That the development hereby shall subsist for a period of 25 years from the first date of 
generation of electricity from the development to the grid.  Written confirmation of the first date 
of electricity generation shall be provided to the Planning Authority within 7 days of the 
electricity first being generated. Within six months of the end of the planning permission, unless 
a further planning application is submitted and approved, the wind turbines, ancillary 
equipment, access tracks and buildings shall be dismantled and removed from the site and the 
land restored in accordance with a detailed restoration and after-care scheme to be submitted
for the approval of the Planning Authority no later than 2 years prior to the expiry of the 25 year 
period. 
Reason: To accord with the provisions of the Town and Country Planning (Scotland) Act 1997 
as amended by the Planning etc. (Scotland) Act 2006 and to allow the Planning Authority to 
review the circumstances of the temporary permission, in the interests of the amenity of  the 
area in the longer term, beyond the 25 year period covered by the permission. 
Condition 38: 
Unless otherwise agreed in writing with the Planning Authority and notwithstanding the terms of 
condition 37, the site shall be fully restored within one year from the date of cessation of the site 
operation. 
Reason: To ensure the timeous restoration of the site. 
3. Applicant’s Supporting Information 
3.1 A Supporting Statement has been submitted with the application to supplement both the original
Environmental Impact Assessment (approved under planning permission 12/00602/FUL) and
the most recent Environmental Impact Assessment Report and Technical Appendices dated
Page 47 of 113

Page 48

October 2019 and approved under planning permission 19/01292/S42. 
3.2 The Supporting Statement sets out a justification for the proposed variation of Condition 1 and
deletion of Condition 38 of the existing planning permission and cites specific examples of
current practice across Scotland where planning conditions have allowed for operational
periods of up to 50 years and restoration periods of up to 3 years following decommissioning.
The Supporting Statement also addresses matters concerning the potential likelihood of
additional or new significant environmental effects resulting from the proposed extension to the
operation of the wind farm, including effects on landscape, ecology, ornithology, traffic and
transport, noise, geology, hydrology and hydrogeology, historic environment, shadow flicker,
aviation and decommissioning.  The Statement concludes that the proposal will not result in
any change to the existing situation and that no significant effects will arise as a result of the
proposed increase to the operational life of the consented wind farm. 
4. Site History 
4.1 Planning permission was originally approved for a wind farm consisting of eight turbines each
with a height of 125m to blade tip and a capacity of 24MW (Planning Reference: 12/00606/FUL)
in January 2019.  In September 2020, the Applicant submitted an application under Section 42
of the Act to revise the turbine layout and to increase the turbine height to149.9m to blade tip
with a resultant increase in capacity to 36MW (Planning Reference: 19/01292/S42). 
Suspensive Conditions 7, 8, 9, 10, 15, 24, 30, and 32 of the existing consent (19/01292/S42)
have been fully discharged and do not require to be duplicated should planning permission be
granted. Those parts of Conditions 25, 37 and 40 that require to be satisfied before the
development could commence have also been discharged. However, in each case, the
conditions require to be reworded and to remain in force until the end of the compliance period
and/or operational life of the wind farm to ensure ongoing regulation and/or mitigation.  A Notice
of Initiation of Development providing an anticipated date of 10 January 2021 for
commencement of the works was submitted in January 2021. As noted above, the wind farm
is currently in the initial phase of construction. 
4.2 Also relevant to the site history are proposed and proximal wind farm developments. They
include 2 existing turbines at Greendykeside wind farm (approved under Planning Reference
04/01624/FUL) each with a height of 99 metres to blade tip. The turbines are located
approximately 850 metres north of the current application site.  Planning permission was also
approved for nine turbines each with a height of 125 metres to blade tip at Greengairs Landfill
Site Meikle Drumgray Road Greengairs (approved under Planning Reference 19/00707/S42);
a related application to extend the operational life of the consented wind farm from 25 to 30
years (Planning Reference: 22/00817/S42) is now under consideration. 
Page 48 of 113

Page 49

5. Development Plan 
5.1 Schedule 14 of the Strategic Development Plan-Clydeplan (SDP) 2017 determines thresholds
where development may reasonably be considered strategic. In this case the proposal being
greater than 20 MW is considered of strategic significance. The schedule is intended to clarify
the scale of development that is likely to have an impact on the SDP Vision and Spatial
Development Strategy. However, strategic development proposals also require to be assessed
against Diagram 10: Assessment of Development Proposals of the SDP. 
5.2 The site is designated as Countryside in the North Lanarkshire Local (Adopted 6th July 2022)
where Policy PP5 Purpose of Place applies. Policies PROM ID2 Utilities Improvements
(Renewable Energy) and EDQ 3 Quality of Development are also relevant. 
5.3 The provisions in Section 42 of The Town and Country Planning (Scotland) Act 1997 as
amended by the Planning (Scotland) Act 2019 and procedures in Circular 3/2013 Development
Management Procedures are vital to the consideration of the application.   
5.4 The following policy statements and non-statutory guidance are also material to the
determination of the current application: 
(1) National Planning Framework 3 (NPF3). 
(2) Draft National Planning Framework 4 (NPF4). 
(3) Scottish Planning Policy (SPP) 2014. 
(4) The Climate Change (Emissions Reductions Targets) (Scotland) Act 2019. 
(5) SG Onshore Wind Policy Statement 2017
(6) North Lanarkshire Council’s Landscape Capacity Study for Wind Turbine Development
(7) Supplementary Planning Guidance 12 ‘Assessing planning applications for wind turbine
developments’ is also relevant.
(8) CAA Policy and Guidelines on Wind Turbines CAP 764 
6. Consultations 
6.1 A summary of responses from consultees is set out below: 
(1) NLC Protective Services has raised no objection to the proposed development provided 
that the noise conditions previously applied to planning permission19/01292/S42 continue
to be applied to the current proposals if approved. 
(2) NLC Transportation has raised no objection to the proposed development provided that 
the transportation conditions previously applied to planning permission 19/01292/S42 
continue to be applied to the current proposals if approved. 
Page 49 of 113

Page 50

(3) Scottish Environment Protection Agency has no objection to the proposed development 
subject to the continuation and application of conditions relative to the approved Habitat 
Management Plan and Peat Plan. 
(4) Cumbernauld Airport Ltd has objected to the proposed development on the basis that light
aircraft may experience control difficulties as a result of the cumulative effect of turbines in
the vicinity of the airport. It is recognised that aircraft wake vortices can be hazardous to
other aircraft, and that wind turbines produce wakes of similar, but not identical,
characteristics to aircraft. Currently, there is no known method of linking the two. Published
research shows measurements at 16 rotor diameters downstream of the wind turbine
indicating that turbulence effects are still noticeable. In respect of the current application
16 rotor diameters (or 16 X 118m) is equivalent to 1,888 metres and therefore less than
2KM.  Cumbernauld Airport is approximately 8KM from the consented wind farm.  There
are currently no Mandatory Occurrence Reports (MOR)18 or aircraft accident reports
related to wind turbines in the UK.  Furthermore, the CAA is not aware of any formal flight
trials to investigate wake effects behind operating wind turbines and with regard to wind
turbines of larger RD than 30m, the CAA advice is that they are subject to further
investigations and until the results of the investigations are available, discussions between
aerodrome managers and wind farm developers are encouraged, taking note of existing
CAA safeguarding guidance.
(5) Edinburgh Airport has raised no objection to the proposed development.
(6) Glasgow Airport has objected to the proposed development pending an updated mitigation
agreement with the developer to ensure that mitigation is provided for the extended
duration of the wind farm. During the consultation of the consented wind farm
(19/01292/S42), Glasgow Airport withdrew its objection on the basis that a number of
conditions would be attached to mitigate any effects on the performance of aerodrome
navigation aids and the efficiency of air traffic control. It is anticipated that Glasgow Airport
will withdraw its objection on the completion of the agreement between the parties,
However, if the Council is minded to grant approval, against the advice of Glasgow Airport,
it must notify Glasgow Airport, the Civil Aviation Authority and the Scottish Ministers as per
Circular 2/2003: Town and Country Planning (Safeguarded Aerodromes, Technical Sites
and Military Explosives Storage Areas) (Scotland) Direction 2003. It is also recommended
that Conditions 16-21 of the 19/01292/S42 consent are continued (reproduced as
Conditions 11-15 above). 
(7) NATS Safeguarding Services has raised no objection to the proposed development. 
(8) Ministry of Defence Estates has no objection to the proposed development subject to the
conditional requirements for installing MOD accredited lighting onto the turbines (Condition
17 as recommended above) and providing MOD with information to ensure that the
development is appropriately charted (Condition 16 as recommended above) are carried
forward on to any new planning permission that may be issued.
(9) Atkins Global has no objection to the proposed development. 
Page 50 of 113

Page 51

(10) SP Energy Networks has no objection to the proposed development.
(11) Nature Scotland has no objection to the proposed development noting that whilst the
development could affect natural heritage interests of national importance, effects can be
mitigated through a Construction Environmental Management Plan CEMP, Habitat
Management Plan and Peat Slide Hazard Risk Assessment. Nature Scotland has advised
that an appropriate assessment is required to assess the impact of the proposed
development on various sensitive locations and that the previous Appropriate Assessment
remains valid.  
(12) Historic Environment Scotland has no objection to the proposed development subject to
the continuation of a condition to that ensure protection of the scheduled monument
Avonhead Colliery (SM9675) through temporary fencing throughout the duration of the
construction works. (Condition 30 as recommended above)
(13) Scottish Environment Protection Agency has no objection to the proposal. 
(14) The Coal Authority has no objection to the proposed development noting that Conditions
9 and 10 of 19/01292/S42 need not be duplicated on any reissued consent 
7. Representations 
1 letter of representation has been received from Bidwells on behalf of Albert Bartlett.  The
primary concerns raised relate to the potential cumulative impacts from shadow flicker and
noise. The Applicant has requested that up-to-date shadow flicker assessments as well as
updated cumulative noise impact assessments are submitted to the Planning Authority for
approval to ensure that any adverse effects on land within Albert Bartlett’s ownership can be
mitigated and measures enforced to protect the amenities of prospective occupiers of any
proposed development on this land. An additional visual assessment from the west and from
the location of the path to the Stanrigg Memorial as it adjoins the public highway, should be
undertaken to ensure that any future development on Albert Bartlett’s land is not significantly
impacted.   
Response: 
It is noted that the representation does not object or support the Application. The current Section
42 application seeks only to extend the period in which the wind farm is permitted to operate
(from 25 to 40 years) and to allow a three year period for decommissioning. There are no
proposed changes to the physical layout or specification of the wind farm which would alter
shadow flicker, noise or visual impacts previously assessed under planning permission
19/01292/S42.  
It is noted that concerns raised relate to the age of existing environmental assessments. The
original Environmental Impact Assessment submitted in 2012 and the updated supplemental
EIA Report submitted in 2019 in support of the consented wind farm includes a detailed
Page 51 of 113

Page 52

assessment of the environmental matters raised and remains valid.  The wind farm is now in
the early phase of construction and in view of the nature of the current proposal and with no
evidence of significant changes that would warrant updated assessments, the Council has no
basis to request updated assessments under the current S42 Application.  Condition 2 of
19/01292/S42 (reproduced in Condition 2 above) will remain in force should permission be
granted to ensure that the wind farm is constructed and operated in accordance with the existing
EIA Report and associated mitigation measures.  
In relation to concerns regarding noise, it is recommended that if planning permission is
approved, Conditions 12, 13 and 14 and guidance notes 1- 4 of Planning Permission
19/01292/S42 which seek to regulate noise levels and specify methods to be employed in the
assessment of complaints about noise, remain in force.  The conditions are reproduced in
Conditions 8, 9 and 10 above.  
In relation to matters concerning shadow flicker, it is recommended that if planning permission
is approved Condition 34 of planning permission 19/01292/S42 which seeks to overcome
potential nuisance to receptors through mitigation of shadow flicker, remains in force.  This
condition is reproduced in Condition 26 above. The above matters are summarised in more
detail in Section 3.4 of the Supporting Statement submitted alongside the current application.  
Whilst the current Section 42 Application would grant a new planning permission, the existing
planning permission (19/01292/S42) has been initiated and construction of the wind farm has
already commenced. If planning permission for the extension to the operational and restoration
periods is not granted, the consented wind farm would still be constructed under the existing
planning permission. 
8. Planning Assessment 
8.1 Section 25 of the Town and Country Planning (Scotland) Act 1997 (‘the Act’) requires that the
application is determined in accordance with the development plan unless material
considerations indicate otherwise. Section 42 (2) of the Act requires that in determining an
application under this section, the Planning Authority must consider only the question of the
conditions subject to which planning permission should be granted. Where it is decided that
permission should be granted subject to conditions differing from those to which the previous
permission was granted, the Planning Authority may amend any of the original conditions
attached previously which it considers necessary to regulate the development. 
8.2 The existing consent is subject to a condition which imposes an operational period of twenty-
five years commencing from the first date of generation of electricity from the development to
the grid and an obligation on the part of the developer to confirm to the Planning Authority the
date of electricity generation within 7 days of the electricity first being generated in order that
Page 52 of 113

Page 53

the operational period is clearly defined. The condition also requires that turbines, ancillary
equipment, access tracks and buildings are to be dismantled within 6 months of the expiry of
the planning permission. Thereafter, the site is to be restored in accordance with a detailed
restoration and after-care scheme to be approved by the Planning Authority no later than 2
years prior to the expiry of the 25-year period. These requirements are regulated by Condition
1 of the consent.  A further condition (Condition 38) of the consent requires that the site is to
be fully restored within one year from the date of cessation of the site operation. 
8.3 The current application seeks only to modify Condition 1 (Operational Period of the Wind Farm)
of the existing consent to allow for: a) an increase in the operational period of the wind farm
from 25 years as approved to 40 years and; b) an extended period of restoration from 6 months
as approved to three years from the date of expiry of the planning permission. Further variation
to the wording of Condition 1 is proposed to allow for the operational period to subsist from the
date of ‘final commissioning of the development’ rather than from ‘the first date of generation of
electricity from the development to the grid’ as approved. The application also proposes deletion
of Condition 38 (Period of Restoration) from the existing consent since restoration would be
addressed in the proposed variation of Condition 1, if approved. 
8.4 The existing consent (19/0129/S42) which was approved on the 24th September 2020 remains
valid. The current application, submitted under Section 42 does not alter the validity of the
existing consent nor does it alter the status of the development, which is now in the early phase
of implementation.  The principle of siting, layout, number and height of turbines and access to
the wind farm has already been established through the existing consent. Whilst it was
considered in the previous scheme that environmental impacts could be minimised through
mitigation, the Committee must have regard to the possibility or likelihood of new or additional
environmental effects as a consequence of allowing an extension to the operational life of the
wind farm.  Regard must also be had to the operational efficiency of the turbines for the duration
of the extended permission to ensure that any turbines which become redundant during the
extended operational period, if approved, will be decommissioned and removed from the site. 
8.5 The key issues for consideration therefore relate to the following matters only: 
(1) Whether the proposal gives rise to any additional environmental effects. 
(2) The extent to which the proposal continues to comply with relevant development plan  
policy.
(3) Material considerations.
(4) Justification for the proposed extension to the operational and restoration periods 
Page 53 of 113

Page 54

Environmental Considerations 
8.6 An Environmental Statement was submitted in support of the original approved application 
(12/00602/FUL). This was followed by an updated supplemental Environmental Impact 
Assessment Report submitted in support of the approved application (19/01292/S42), where it
was determined that sufficient evidence existed to demonstrate that, subject to conditions and 
mitigation, the wind farm could be accommodated on the site without causing significant 
environmental effects. 
8.7 In determining the current application for an extension to the operational life of the wind farm, 
the  Committee must have regard to the any environmental effects that could result as a 
consequence of allowing the extension. 
8.8 A Supporting Statement has been submitted with the application which provides an updated 
assessment of the key environmental considerations: 
(1)  Landscape and Visual Impact:- The magnitude of change relative to landscape and visual
effects is unaffected by the proposal. It is acknowledged however, that visual impacts
experienced by receptors in the nearby communities of Longriggend and Caldercruix will endure
for a further period of 15 years, although equally it is anticipated that the affected receptors will
be accustomed to experiencing the wind farm within the landscape during its operational life. 
(2) Ecology:- The proposed extension to the operational period will not result in any additional
or  significant adverse impacts on habitat. Effects will continue to be mitigated through the
Construction Environmental Management Plan (CEMP) as imposed by Condition 33 above;
through annual reviews of the Habitat Management Plan in accordance with Condition 21 above
and; through the approved Peat Slide Hazards Risk Assessment in accordance with Condition
32 above. Nature Scotland has raised no objection to the proposal subject to the continuation
of the above conditions. 
(3) Ornithology:- As required under Council Directive 79/409/EEC on the conservation of wild
birds (“Birds Directive”) and Council Directive 92/432/EEC on the conservation of natural
habitats and of wild fauna and flora (“Habitats Directive”), the Council has undertaken an
Appropriate Assessment (AA) and appraisal of impacts on the Forth Islands SPA and separately,
an AA and appraisal of the impacts on the Outer Firth of Forth and St Andrews Bay Complex
SPA.  Both assessments concluded that all conservation objectives will be met and that there
will be no adverse effects on the integrity of either SPA.  Nature Scotland has raised no objection
to the proposal. 
Page 54 of 113

Page 55

(4)  Traffic and Transport:-  NLC Roads has not objected to the proposal subject to conditions
relating  to upgrading works to the access junction.  The proposal will have no new or additional
effects on traffic or transport during the construction and operational phases. 
(5) Noise:-  The original approved Environmental Statement and supplemental Environmental
Impact  Assessment Report submitted in support of the 2019 application, predicted operational
noise levels at  the residential receptors would be within recommended noise limits. NLC
Protective Services has  raised no objection to the proposed development provided that the
noise conditions previously applied  to planning permission19/01292/S42 will continue to
be applied to the current proposals if approved.  It is  recommended that the relevant
conditions remain in place to ensure that noise levels remain within recommended noise limits
for the duration of the operational period. 
(6) Geology, Hydrology and Hydrogeology:- Condition 2, above, will continue to ensure that the 
proposed mitigation measures are undertaken in accordance with the approved original
Environmental Statement and supplemental Environmental Impact, including, inter alia,
excavation works are completed during periods of dry weather to restrict pooling / surface run-
off and to limit potential infiltration of dirty or contaminated surface water to the water table. NLC
Protective Services has raised no objection to the proposal. Similarly, SEPA has raised no
objection subject to the continuation of conditions relating to the approved Habitat Management
Plan and Peat Plan.   
(7) Historic Environment:- The proposal does not give rise to additional impacts on the historic 
environment beyond those identified in the original Environmental Statement.  Historic 
Environment Scotland has raised no objection to the proposed development subject to the 
continuation of a condition to that ensure protection of the scheduled monument Avonhead 
Colliery (SM9675), through temporary fencing throughout the duration of the construction 
works. Condition 30 is recommended accordingly. 
(8) The Scottish Government Onshore Wind Farms factsheet indicates that shadow flicker
should not be an issue where a separation distance of 10 rotor diameters is retained between
the turbine and the nearest dwelling. In this instance 10 rotor diameters equates to 1380 metres.
The nearest property that may be affected by shadow flicker is Avonhead Cottage to the north
which is approximately 745 metres from the turbines. The original Environmental Statement
concluded that Avonhead Cottage may experience shadow flicker as a result of the proximity of
the turbines to this receptor and a condition was attached accordingly to monitor the impacts of
shadow flicker on the occupiers of Avonhead Cottage and to ensure that the developers of the
wind farm would address any adverse effects on this property through mitigation should any
complaints arise.  If planning permission is granted for the extension to the operation and
restoration periods, this condition would remain enforce for three years after the date of the
Page 55 of 113

Page 56

erection of the turbines.  Minor rewording of the condition is recommended to provide clarity in
respect to the start date of the three-year limitation period in which the occupiers may make a
claim if necessary. 
(9)  Aviation:- In the interests of aviation safety and suitable mitigation relating to the impact of
the development on the performance of aerodrome navigation aids and/or the efficiency of air
traffic control, conditions are attached to ensure that amongst other matters, a Primary Radar
Mitigation Scheme is submitted to the Planning Authority and approved in consultation with
NATS and relevant operators.  Any Primary Radar Scheme will set out measures to be taken
to prevent the impairment of the performance of the aerodrome navigation aids and/or efficiency
of air traffic control services at Glasgow Airport, Cumbernauld Airport and the operations at
Lowther Hill and Kincardine.  Whilst Cumbernauld Airport has objected to the proposal, the
objection relates to the potential cumulative effects on light aircraft from turbulence. This is a
new matter which was not raised by Cumbernauld Airport during the previous consultation of
the now consented wind farm.  The proposed extended period of operation is unlikely to
significantly change any potential effects that the airport operator has now identified.  Glasgow
Airport has also raised a holding objection until such time as the existing mitigation agreement
in place with the airport and the developer has been amended to take account of the extended
period.   It is also noted that, whilst Glasgow Airport initially objected to the previous application
(19/01292/S43), it subsequently withdrew its objection on the condition that a Primary Radar
Mitigation Scheme was submitted to the Planning Authority and was approved in consultation
with the Airport.  If the Council is minded to grant approval against the advice of Glasgow Airport,
it must notify Glasgow Airport, the Civil Aviation Authority and the Scottish Ministers as per
Circular 2/2003: Town and Country Planning (Safeguarded Aerodromes, Technical Sites and
Military Explosives Storage Areas) (Scotland) Direction 2003. 
8.9   The environmental effects of the consented wind farm already identified in the original 
Environmental  Statement (2012) and supplemental Environmental Impact Assessment 
Report (2019) are not expected to change significantly either as a result of the time which has 
passed since planning permission was approved on 24th September 2020 and/or as a 
consequence of the current proposal to extend the operational and restoration periods. The 
effects identified in the approved reports remain relevant to the determination of this application. 
The Strategic Development Plan; Clydeplan 2017 (SDP) 
8.10 The SDP provides a high-level spatial framework for on-shore wind across the City Region,
highlighting in Diagram 6 of the SDP potential locations for wind farm development. The SDP
however pre-dates the Climate Change (Emissions Reduction Targets) (Scotland) Act 2019
which increased Scotland’s emissions reduction targets from 80% by 2050 to 100% by 2045;
for this reason Diagram 6 may therefore be regarded as being out-of date.  Whilst, the
Page 56 of 113

Page 57

consented wind farm site represents a departure from the SDP since it does not fall squarely
within the areas highlighted in Diagram 6 for potential wind farm development, the previous
consent confirmed that the approved wind farm was able to meet the broad objectives in
Diagram 10: Box 2 of the SDP, and was therefore considered to be an acceptable departure
from the SDP.  This in part, was due to the significant contribution it makes towards sustainable
development and carbon reduction. The degree to which the consented wind farm is now
compliant with the relevant SDP criteria is even greater due to legislative changes imposed by
the Climate Change (Emissions Reduction Targets) (Scotland) Act 2019 and the requirement
to meet net zero carbon reduction emission targets by 2045. 
The North Lanarkshire Council Local Development Plan (Adopted 6th July 2022)  
8.11 Development Plan policy has changed since the consented wind farm was approved on 24th 
September 2020 and The North Lanarkshire Local Plan 2012 under which the current consent 
was approved is no longer in force. The Development Plan now consists of The North 
Lanarkshire Local Development Plan (LDP) Adopted 6th July 2022, which is supported by other 
statutory and non-statutory guidance, listed in the appendix of the Plan at pages 122 and 123. 
8.12 The site is designated Countryside (formerly The Rural Investment Area) in the North
Lanarkshire Local Development Plan where Policies PP5 Purpose of Place and AD 5 Amount
of Development, apply.  PP5 is concerned with an assessment of appropriateness of new
development in the Countryside and requires that proposals are supported by evidence of
locational need amongst other matters. Policy AD5 is concerned with implications relating to
the amount of development proposed. An assessment of locational need and amount of
development was considered and justified in the previous approved application. The principle
of siting the turbines, including the number and height of turbines and associated equipment,
on the site has already been established and the wind farm is now in the early stage of
construction.  The current proposal raises no new matters that would change this position
and/or conflict with the current Local Development Plan.  The proposal can therefore be said to
accord with Policies PP5 and AD5 of the Local Development Plan. 
8.13 Onshore wind is addressed in Policy PROM ID2 Utilities Improvements of the LDP and is
generally supported subject to assessment criteria set out in Scottish Planning Policy Spatial
Framework requirements and associated constraints, including potential impacts on features
listed in the Protecting Assets Policies (PROT A and PROT B and Categories A1, A2, A3, B1
and B2), including, World Heritage Sites, European sites, Historic Battlefield and peatlands. 
The consented wind farm is not located on, nor will it have any significant adverse effects on,
land within Categories A1 to B2; those matters having been assessed and determined
previously in 19/01292/S42. 
Page 57 of 113

Page 58

8.14 The site is, however, located within 2km of the urban area where visual impacts on communities
is subject to special consideration in accordance with Policy PROM ID2.  Whilst SPP
recommends that Local Plans should consider a setback distance of 2km from the urban area
when considering areas suitable for wind farm developments, there is no requirement to apply
the 2km distance when determining individual applications. Accordingly, they should be
assessed on their own merits.  It is acknowledged that the proposed wind farm, which is within
2km of the nearby settlements of Longriggend and Caldercruix, may have a visual impact on
those settlements. However, this matter has previously been considered in detail under
approved application 19/01292/S42 and it was concluded that on balance, visual impacts on
sensitive receptors in the nearby settlements would not be so significant and/or demonstrably
adverse as to outweigh the substantial benefits of the wind farm, when assessed against the
Local Development Plan and other material considerations as a whole or to warrant refusal of
the application.  The proposal does not therefore raise any conflict with Policy PROM ID2 of
the Plan. 
8.15 Policy EDQ 3 Quality of Development requires high standards of site planning and sustainable
design in all new development.  The current proposal does not involve any new matters that
will impact the approved site layout or design.  In response to criterion C of EDQ3, it is noted
that by extending the operational life of the wind farm, the current proposal goes further to
addressing issues of resource efficiency and to mitigating and adapting to the effects of climate
change. The proposal does not raise any conflict with Policy EDQ3. 
8.16 The physical layout of the wind farm, including access, turbine positions and turbine heights
remain unaltered since the time of the last report to Members in 2020 (19/01292/S42). Whilst
the previous Local Plan, against which the consented wind farm was considered, is no longer
in force, there has been no major shift in onshore wind policy that would lead to a different
recommendation if the principle of siting and design was to be considered under the adopted
Local Development Plan or the SDP. Similarly, the application raises no significant adverse
environmental impacts or new material considerations that conflict with the adopted Local
Development Plan. 
Material Considerations 
8.17 Material to the current proposal is the fact that the application site has a valid consent (approved
on 24th September 2020) for the development of a 36MW wind farm consisting of 8 turbines,
each with a height of 149.9m to blade tip. The consented wind farm is in the early stages of
construction and can lawfully operate for a period of 25 years. 
8.18 NPF3, SPP, The Scottish Energy Strategy (2017) and the Scottish Government’s Onshore Wind
Policy Statement (2017) support onshore wind and recognise the contribution it can make to
Page 58 of 113

Page 59

renewable energy targets and to achieving a ‘low carbon place’. Draft NPF4 goes further in its
support for onshore wind in its aim to achieve a ‘net zero nature positive Scotland’; when
published it will replace NPF3 and SPP.  The clear shift from a low carbon place to a net zero
Scotland is further evidenced in changes to the Climate Change (Scotland) Act 2009 that were
introduced by the Climate Change (Emissions Reduction Targets) (Scotland) Act 2019.  The
2019 Act increased Scotland’s emissions reduction targets from 80% by 2050 (Section 1 of the
2009 Act) to 100% by 2045 (Section A1 of the 2009 Act as amended by the 2019 Act). The
contribution of renewable energy generation towards achieving the net zero target by 2045 is
therefore a material consideration. 
8.19     Whilst the Local Development Plan does not reference operational periods of wind farms, Policy
19 of Draft NPF4 recognises that extensions to the life of existing wind farms should be
supported and both Policy 19 of draft NPF4 and paragraph 170 of SPP recognise the need for
areas to be identified for wind farms to exist in perpetuity.  Equally, the Scottish Government’s
Onshore Wind Statement (2017) directly references the common practice of limiting the
duration of consent for a wind farm to 25 years and argues that there is no statutory basis for
doing so.  It advocates a more flexible approach whereby the use of land identified as being
suitable for wind farm development should not be time limited and instead should be suitable
for such use in perpetuity. 
Justification for the Proposal 
8.20 The Applicant has provided a justification for the proposed extension to the operational and 
restoration periods of the wind farm.  This is summarised: 
(1) Advancements in wind turbine technology will ensure that turbines will be able to operate  
for longer periods than first envisaged.  It is also expected that components may be  
replaced or upgraded without changing the scale or appearance of turbines to prolong  
their operational life.
(2) The proposal will as a result have a significantly lesser impact than wholescale
replacement of turbines as wholescale redesign may also include amendments to layout,
associated infrastructure and with this, intrusive works.
(3) The additional 15-year period sought under the proposal would generate up to an
additional 1.8 million MWh of generation (122,400 MWh per annum) which would power
the equivalent of up to 32,835 homes per annum over the extended period.
(4) The additional 15-year period sought under the proposal would also result in additional
CO2 savings of up to 826,485 tonnes (55,099 tonnes per year).
(5) Whilst not material, the existing commitment of community benefit payments of £5,000
per installed MW would continue for the operational life of the development and over the
extended 15-year period would equate to an additional £2.8million in community benefits
Page 59 of 113

Page 60

(£192,000 per annum). 
9. Matters to be Secured by a Legal Agreement  
9.1 The existing consent is subject to an agreement under Section 69 of the Local Government
(Scotland) Act 1973 (As Amended). This requires a financial bond to be lodged with the Council
to cover the costs of decommissioning and site restoration. An existing bond has been agreed
for consented wind farm (Planning Reference 12/00606/FUL and 19/01292/S42) is in place.
Should the Committee grant approval for the application, the bond will be updated to reflect the
proposed application and longer period of operation. 
10.        Conclusions 
10.1 A valid consent has been issued under Planning Reference 19/0129/S42 for the development
of a wind farm consisting of 8 turbines (149.9m in height to blade tip) on the site. Many of the
suspensive conditions attached to the consent have been discharged and the wind farm is in
the early phase of construction and can lawfully operate for a period of 25 years with a condition
in place to ensure that the site is restored within 6 months of the expiry of the consent. 
10.2 Temporary planning permission for wind farm developments across Scotland has historically 
been made in line with turbine warranty. However, Scottish Ministers recognise that ‘with 
continual advancement of technology and the production of more efficient wind turbines, it is 
generally expected that turbines will be capable of producing electricity over a long period’ 
(Kilgallioch Wind Farm Extension approved by the Scottish Ministers in December 2021).   
10.3 Extending the operational period of the wind farm for a further 15 years would allow for a 40-
year operation period. This is commensurate with the duration of operational periods for other
wind farms across Scotland and it is now recognised nationally in Draft NPF4 and in SG
Onshore Wind Statement etc that extensions of time to the life of a wind farm should be
supported, alongside opportunities to allocate suitable land for wind farm development in
perpetuity. 
10.4 Whilst the Local Plan under which the existing wind farm was assessed is no longer in force,
there have been no significant shifts in onshore wind policy nor have there been any other
material changes in policy beyond those already assessed, that would place the current
proposal in conflict with the adopted Local Development Plan. 
10.5 Similarly, no significant adverse environmental effects have been identified as a consequence
of the current proposal. The environmental effects of the consented wind farm have already
been identified in the original Environmental Statement (2012) and supplemental
Page 60 of 113

Page 61

Environmental Impact Assessment Report (2019); they are not expected to change significantly
and therefore remain relevant to the determination of this application. 
10.6 The extension of the operational life of the consented wind farm by 15 years would increase 
the wind farm’s contribution to renewable energy targets by up to an additional 1.8 million MWh
of generation (122,400 MWh per annum) which would power the equivalent of up to 32,835 
homes per annum over  the extended period. The wind farm’s contribution to net zero carbon 
reduction targets would  increase over the extended period by up to 826,485 tonnes (55,099 
tonnes per year).   
10.7 There is no reason to assume that turbines could not have a useful extended life after a
manufacturer’s warranty expires. However, if the Committee is minded to grant permission for
variation of Condition 1 and deletion of Condition 38 of the existing permission, it will be
necessary to re-attach the original suspensive conditions that have not yet been discharged
and/or that have in part been discharged but require to remain and be reworded to reflect the
status of the wind farm.  Conditions that are to remain in force for the duration of the consent
will ensure mitigation continues to be secured, that the period of operation of the wind farm is
clear and that decommissioning of the wind farm is secured at the end of the operational life.
The Committee is also advised that any consent approved under Section 42 would effectively
issue a new planning permission, which would benefit from its own 3-year commencement
period from the date on which the new permission was granted. As noted above, the holding
objection from Glasgow Airport means that the Council cannot issue planning permission at this
stage without first of all referring the matter to the CAA, Glasgow Airport and the Scottish
Ministers.  The Scottish Ministers will then have the opportunity (if deemed necessary) to “call
in” the application for their own consideration and decision.  Given the background to this
application (including the fact that works have already started on site as per a previous planning
permission) it is considered highly likely that Glasgow Airport will withdraw their objection soon.  
Page 61 of 113

Page 62

Application No:  
22/00780/FUL
Proposed Development: 
Change of Use from Class 6 (Storage and Distribution) to Fitness
Studio Class 11 (Assembly and Leisure)  
Site Address: 
10 Badenheath Place
Westfield
Cumbernauld
G68 9HX 
Date Registered: 
10th August 2022 
Applicant:
ASE 7 LLP
Sloane Square House
1 Holbein Street
London
SW1W 8NS 
Agent:
Brian O'Hanlon
44 Douglas Street
Motherwell
ML1 3JG 
Application Level:
Local Application 
Contrary to Development Plan:
Yes
Ward:   
02 Cumbernauld North 
Danish Ashraf, Tom Fisher, Alan Masterton,
Gordon Currie
Representations:
No letters of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The proposal is considered acceptable in terms of the criteria set out in the relevant policies
contained within the North Lanarkshire Local Development Plan (2022). The proposed
development is unlikely to significantly adversely affect the surrounding industrial and business
area.   
Page 62 of 113

Page 63

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 22/00780/FUL 
Name (of applicant): ASE 7 LLP
Site Address: 10 Badenheath Place
Westfield
Cumbernauld
G68 9HX
Development: Change of Use from Class
6 (Storage and Distribution) to Fitness
Studio Class 11 (Assembly and Leisure)   
Page 63 of 113

Page 64

Proposed Conditions:- 
1 That this permission will lapse within 3 years of the date of this permission unless the permitted
change of use is implemented 
Reason: To accord with the provisions of the Town and Country Planning (Scotland) Act 1997 
2 That the development hereby permitted shall be carried out strictly in accordance with the
approved details submitted as part of the application and no change to those details shall be
made without prior written approval of the Planning Authority. 
Reason: To clarify the drawings on which this approval of permission is founded. 
3 That, notwithstanding the provisions of the Town and Country Planning (General Permitted
Development) (Scotland) Order 1992, the premises shall be used as a fitness studio and for no
other purposes (including any other Use Classes in the Town and Country Planning (Use
Classes) (Scotland) Order 1997). Should this use cease than the unit shall revert back to use
class 6 (Storage and Distribution). 
Reason: To enable the Planning Authority to retain effective control and to ensure the building
remains an ancillary facility to benefit the operation and viability of the adjacent industrial area. 
Background Papers: 
Consultation Responses: 
None required. 
Contact Information: 
Mr Joe Gannon at esplanning@northlan.gov.uk. 
Report Date: 
13th September 2022
Page 64 of 113

Page 65

APPLICATION NO. 22/00780/FUL 
REPORT 
1. Site Description 
1.1 The application site comprises of a vacant industrial unit located within a group of mixed sized
industrial/leisure units at Badenheath Place, Westfield, Cumbernauld. This forms part of an
established industrial area which in recent times has allowed the introduction of leisure uses
(e.g. arts and crafts centre). The property is a single storey unit with a metal flat roof and
cladding set in a cul-de-sac with buildings of a similar design and finish. The unit, formerly used
for storage and distribution, has been vacant for several years. The application site is bounded
by car parking south and west, industrial units to the east and similar units directly north. 
2. Proposed Development 
2.1 The application seeks full planning permission for the change of use from a Class 6 (Storage
and Distribution) unit to a Class 11 (Assembly and Leisure) Fitness Studio, with no physical
alterations proposed. A planning condition is attached ensuring the upon cessation of the
approved use the unit reverts back to the originally intended industrial use. 
3. Applicant’s Supporting Information 
3.1 Supporting information has been provided by the applicant. The statement confirms that
Revolution Spin, as determined through market research, would be complimentary to the other
leisure services already present in the Westfield estate of Cumbernauld. Revolution Spin
currently operates within both the City Centre and West End of Glasgow, with those running
the business living within North Lanarkshire, providing a knowledge of the locality. Further to
this, many of those who use Revolution Spin within the area of Glasgow, live in
Cumbernauld/North Lanarkshire, meaning closer proximity to a Revolution Spin location will
reduce unnecessary city centre congestion and traffic pollution. As expressed within the
supporting statement, exercise has been shown to contribute towards improved mental and
physical wellbeing, therefore emphasising the importance Revolution Spin would bring towards
improving people’s wellness. The supporting statement further points out that the applicant has
been searching for a suitable unit within the Cumbernauld area for a couple of years and have
been unable to find a suitable location with appropriate floor space and parking. It is pointed
out that the studio would complement the other leisure/non industrial facilities (e.g., soft play
areas, pet daycare) present within the estate and new-build housing, such as providing parents
with a fitness studio/leisure facility who make use of the Children’s Amusement Centre and/or
Nursery, supporting the local economy (as further achieved by the creation of 10-20 jobs
through the business). 
3.2 Furthermore, the unit size and location of the unit is considered to be excellent, as well as the
parking provision within the estate, supported by the surrounding road network being well
planned and accessible (e.g., M73 and M80 motorway). 
4. Site History 
4.1 The site has been the subject of the following planning applications: 
 06/00556/FUL Provision of 13 Additional Parking Spaces (PER – Application Permitted)
 17/00590/FUL Change of Use from Office to Storage/Distribution and Alterations to Building
(PER – Application Permitted)
 18/00210/CLP Use of Unit as a Trade Showroom for Bifold Doors, Windows and Kitchens and
Erection of Signage (PER – Application Permitted) 
Page 65 of 113

Page 66

5. Development Plan 
5.1 The proposal raises no strategic issues and can therefore be assessed in terms of Local
Development Plan (2022) policies. 
5.2 The application site is covered by Placemaking Policy (Business Centre) within the adopted
North Lanarkshire Local Development Plan (2022). 
6. Consultations 
6.1 No consultations were required. 
7. Representations 
7.1 Following the standard neighbour notification process and press advert, no letters of objection
have been received. 
8. Planning Assessment 
8.1 Under Section 25 of the Town and Country Planning (Scotland) Act 1997, planning decisions
must be made in accordance with the development plan unless material considerations indicate
otherwise. 
8.2 Development Plan: North Lanarkshire Local Development Plan: The site falls within an area
covered by Placemaking Policy (Business Centre) which states that North Lanarkshire Council
will encourage small, medium, and large sized enterprises to locate in Local Business Centres,
safeguard their character from dilution by other, inappropriate uses and support upgrading of
premises, amenities, access, parking, and green spaces. The proposal seeks to bring one of
the smaller units in the cul-de-sac back into productive use having been vacant for several
years. In physical terms the unit forms part of a much bigger industrial/business area. In
assessment against the relevant policy, the proposed change of use from a business and
industry unit to an assembly and leisure use, in this instance, is considered to be an appropriate
departure that would not adversely impact on the wider industrial location. It is considered that
the proposal will not detract from the industrial function of the application site or the surrounding
area due to the number of industrial units still available. In this particular industrial estate, there
is a predominance of large industrial units and the loss of one smaller unit to a non-industrial
use is not considered to be a particular concern. The potential physical amenity impact of the
proposal on neighbouring properties is also deemed to be acceptable due to the nature of the
proposed and established uses. In this respect, the application is considered to be an
acceptable departure from policy. 
8.3 The North Lanarkshire Local Development Plan also requires proposed developments to be
assessed against Policies EDQ 1 (Site Appraisal), EDQ 2 (Specific Features for Consideration)
and EDQ 3 (Quality of Development). Due to the scale and nature of the development, the
proposal raises no issues with regards to Policies EDQ1 and EDQ2. Policy EDQ3 (Quality of
Development) only permits development where high standards of site planning, sustainable
design, and development are achieved. When assessed against the terms of policy EDQ3 it is
considered that the re-use of the vacant industrial unit by the proposed business can be
integrated successfully into the surrounding area without detriment to the amenity of the existing
industrial and business area. Furthermore, sufficient infrastructure such as parking, access,
and turning areas are in place to ensure that the proposed use can be carried out and will be
compatible with the wider industrial uses in the area. 
8.4 Other Material Considerations – Supplementary Planning Guidance: A material consideration
is the Supplementary Planning Guidance (SPG) 15 Industrial & Business Development, of
which Section C is relevant. With reference to change of use proposals in Industrial and
Business areas, the SPG states that the Council will not support proposals which would be
Page 66 of 113

Page 67

detrimental to the cumulative economic importance of small scale industrial and business sites
or proposals which would have a negative impact on communities and the wider environment.
When the leisure use proposal is assessed against this, it is considered that it will not result in
a detrimental impact on the cumulative economic importance of industrial and business uses
in the Westfield area of Cumbernauld or have a negative impact on the adjacent business uses.
It must also be noted that the surrounding industrial/business area has a number of vacant units
which would indicate that there is a surplus of units to that of demand in the area. It is not
therefore considered that the use of the vacant unit for a fitness studio would be to the detriment
of the existing industrial and business area and would not result in a shortfall of premises for
industrial or business use within this locale. Therefore, the proposal is regarded as being in
accordance with the Supplementary Planning Guidance. 
8.5 Effect on Local Amenity: Due to the nature of the proposal it is not considered to detrimentally
affect the character of this wider industrial area. Whilst the proposed use may well introduce
further non-industrial traffic to the road network the existing range of traffic types is such that
this does not represent a road safety issue. In addition, the proposal has access to a communal
car parking area of approximately 100 spaces. It is also indicated that the unit would in the main
be busiest in the evenings when activity levels in the surrounding industrial estate is generally
quieter. 
8.6 Applicant’s Supporting Information: In planning terms, the potential impact of the proposal on
the industrial area is assessed in detail above and considered, on balance, to be acceptable. It
is noted that in this industrial estate there is no shortage of similar industrial units and if
unavailable in the town or local centres, finding appropriate accommodation can be challenging.
It is considered that this has some weight in the assessment of this application, considering the
special circumstances, and availability of industrial units elsewhere. 
9. Conclusions 
9.1 In conclusion, considering all the circumstances relevant to this application, the proposal is
considered acceptable in this instance and will not result in an unacceptable impact on the
character of the industrial and business area which is considered to be acceptable departure
from Placemaking Policy (Business Areas) of the North Lanarkshire Local Development Plan.
Taking account of the provisions of the development plan and other material considerations it
is recommended that permission be granted. 
Page 67 of 113

Page 68

Application No:  
22/00836/FUL
Proposed Development: 
Manufacturing Facility and Offices with associated Parking,
Landscaping and Infrastructure 
Site Address: 
Land North Of Craignethan Drive
Gartcosh 
Date Registered: 
12th July 2022 
Applicant:
Guala Closures UK
Old Mill Park Estate
Kirkintilloch
G66 1ST 
Agent:
Gordon Gibson
Convery Prenty Shields Architects
231 St Vincent Street
Glasgow
G2 5QY 
Application Level:
Major Application 
Contrary to Development Plan:
No
Ward:   
06 Gartcosh, Glenboig and Moodiesburn 
Greg Lennon, Michael McPake, Joanne Katy
Keltie
Representations:
No representations received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The development meets the criteria set out in the relevant policies contained within the North
Lanarkshire Local Development Plan 2022. The development can be accommodated without
detriment to the Gartcosh Business Interchange and wider surrounding area. 
Page 68 of 113

Page 69

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 22/00836/FUL 
Name (of applicant): Guala Closures UK
Site Address: Land North Of
Craignethan Drive
Gartcosh 
Development: Manufacturing Facility and
Offices with associated Parking,
Landscaping and Infrastructure   
Page 69 of 113

Page 70

Proposed Conditions:- 
1. That the development hereby permitted shall be started within three years of the date of this
permission. 
Reason: To accord with the provisions of the Town and Country Planning (Scotland) Act 1997. 
2. That, except as may otherwise be agreed in writing by the Planning Authority, the development
shall be implemented in accordance with drawing numbers:- 
2107 _P_001, 2107_P_002, 2107_P_003, 2107_P_100, 2107_P_110,
2107_P_200, 2107_P_210, 40167-IFL-XX-DR-10-001-P01,
40167-IFL-XX-DR-20-001-P01, 40167-IFL-XX-DR-50-001-P01, 
Reason: To clarify the drawings on which this approval of permission is founded. 
3. That unless otherwise agreed in writing with the Planning Authority, the facing materials to be
used on all external walls and roofs shall be as outlined on drawing ref 2107_P_200, and the
development shall be implemented in accordance with the details approved under the terms of
this condition. 
Reason: In the interest of the amenity of the site and the general area. 
4. That BEFORE the development hereby permitted starts, unless otherwise agreed in writing with
the Planning Authority, a comprehensive site investigation requires to be submitted to the
satisfaction of the Local Authority. The investigation must be carried out in accordance with the
British Standard Code of Practice BS 10175: 2017 "The Investigation of Potentially Contaminated
Sites". The report must include a site specific risk assessment of all relevant pollution linkages,
be carried out in accordance with the Environment Agency publication, Model Procedures for the
Management of Land Contamination CLR11, and be submitted in electronic format. Depending
on the results of this investigation a detailed remediation strategy may be required. 
Reason: To ensure potential risks arising from previous land uses around the site have been
fully assessed before the development starts. 
5. That for the avoidance of doubt, any remediation works identified by the site investigation
required in terms of Condition 4 above, shall be carried out to the satisfaction of the Planning
Authority.  A certificate (signed by a responsible Environmental Engineer) shall be submitted to
the Planning Authority confirming that any remediation works have been carried out in
accordance with the terms of the Remediation Strategy. 
Reason: To ensure that the site is free of contamination. 
6. That within 3 months of the determination date, unless otherwise agreed in writing with the
Planning Authority, full details of the proposed surface water drainage scheme shall be submitted
to and for the approval of the said Authority.  For the avoidance of doubt the drainage scheme
must comply with the requirements of the publication titled `Drainage Assessment: A Guide for
Scotland' and any other advice subsequently published by the Scottish Environment Protection
Agency (SEPA) or the Sustainable Urban Drainage Scottish Working Party (SUDSWP). 
The post-development surface water discharges shall ensure that the rate and quantity of run-off
to any watercourse are no greater than the pre-development run-off for any storm return period
unless it can be demonstrated that a higher discharge is necessary to protect or improve the
aquatic habitat.  SUDS shall still be provided even where discharges are proposed to public
sewers notwithstanding any conditions imposed by Scottish Water. 
If the area of ground illustrated for the SUDS is inadequate for the purpose, a revised layout
drawing for this part of the proposed development shall be submitted to and for the approval of
the Planning Authority prior to any works of any description being commenced on the application
site, unless otherwise agreed in writing with the said Authority.
Page 70 of 113

Page 71

Reason: To ensure that the drainage scheme complies with best SUDS practice to protect
adjacent watercourses and groundwater. 
7. That the SUDS compliant surface water drainage scheme approved in terms of Condition 7
shall be implemented contemporaneously with the development in so far as is reasonably
practical.  Within three months of the construction of the SUDS, a certificate (signed by a
Chartered Civil Engineer experienced in drainage works) shall be submitted to the Planning
Authority confirming that the SUDS has been constructed in accordance with the relevant
CIRIA Manual and the approved plans. 
Reason: To safeguard adjacent watercourses and groundwater from pollution. 
8. That within 3 months of the determination date, unless otherwise agreed in writing with the
Planning Authority, the applicant must confirm in writing to the Planning Authority that the foul
drainage can be connected to the public sewer in accordance with the requirements of Scottish
Water.  The surface water must be treated in accordance with the principles of the Sustainable
Urban Drainage Systems Design Manual for Scotland and Northern Ireland published by CIRIA
in March 2000. 
Reason: To prevent groundwater or surface water contamination in the interests of
environmental and amenity protection. 
9. That if works have not begun within a year of the approval date, updated protected species
surveys are required to be undertaken and submitted for approval by the Planning Authority, in
consultation with NLC Greenspace Services. 
Reason: To ensure compliance with the Wildlife and Countryside Act (1981) as amended and
the Nature Conservation (Scotland) Act 2004. 
10. That, where possible, the mitigation measures outlined in pages 26 and 27 of the Ecological
Impact Assessment dated 15th July 2022 by ECOS Countryside Services LLP shall be
implemented. For the avoidance of doubt the Great Crested Newt fencing on the site shall be
retained with the exception of at vehicular and pedestrian access points where one-way newt
grids will require to be installed. 
Reason: To ensure compliance with the Wildlife and Countryside Act (1981) as amended and
the Nature Conservation (Scotland) Act 2004. 
11. The noise mitigation measures identified in pages 32 - 34 of the Environmental Noise Impact
Assessment dated 16th August 2022 by Acoustics Energy Vibration shall be implemented within
the development. Upon completion a verification certificate (signed by a suitably qualified
Acoustic Professional) shall be submitted to the Planning Authority confirming the approved
mitigation measures have been provided and correctly installed. For the avoidance of doubt the
mitigation measures are as follows: 
* roof mounted fan cowl and filter box positioning;
* sound emission limits on new plant design;
* louvre positioning;
* A-weighted broadband sound pressure levels at 1m from any plant room louvres or flues should
not exceed Lp 80 dBA. 
Reason: In the interest of the amenity of the nearby residents. 
12. That within 3 months of the determination date an air quality screening technical note, which
includes sufficient justification for not requiring a full Air Quality Impact Assessment, shall be
submitted to, and for the approval of the Planning Authority. In the event mitigation measures are
required they must be agreed with the Planning Authority and undertaken before the development
hereby permitted is brought into use. 
Page 71 of 113

Page 72

Reason: In the interests of air quality. 
13. That BEFORE commencement of the development, unless otherwise agreed, details of the
lighting within the site shall be submitted for the approval of the Planning Authority, after
consultation with Transport Scotland, as the Trunk Roads Authority. 
Reason: To ensure that there will be no distraction or dazzle to drivers on the trunk road and that
the safety of the traffic on the trunk road will not be diminished. 
14. There shall be no drainage connections to the trunk road drainage system. 
Reason: To ensure that the efficiency of the existing trunk road drainage network is not
affected. 
15. That all works included in the scheme of landscaping and planting, approved under the terms of
drawings 0167-IFX-XX-DR-C-60-001-PO1,  40167-IFX-XX-DR-C-60-002-PO1, 40167-IFX-XX-
DR-C-60-003-PO1,  40167-IFX-XX-DR-C-70-001-PO1 sheet 1 of 2,  40167-IFX-XX-DR-C-70-
001-PO1 Sheet 2 of 2,  40167-IFX-XX-DR-C-70-001-PO1, shall be completed, and any trees,
shrubs, or areas of grass which die, are removed, damaged, or become diseased, within two
years of the full occupation of the development hereby permitted, shall be replaced within the
following year with others of a similar size and species. 
Reason: In the interests of the visual amenity of the area. 
16. That BEFORE completion of the development hereby permitted, the management and
maintenance scheme approved under the terms of drawing 40167-IFl-XX-DR-C-60-001-PO1
shall be in operation. 
Reason: In the interests of the visual amenity of the area. 
17. A visibility splay of 4.5m x 60m should be provided and maintained at points 1.05m above the
level of the carriageway from the site access, and service access, to Craignethan Drive in both
directions. 
Reason: In the interests of traffic safety. 
18. A minimum spacing of 25m should be provided between existing accesses on Craignethan Drive
and proposed access points leading into the site. The minimum spacing between the main site
access and the roundabout should be 60m. 
Reason: In the interests of traffic safety. 
19. Existing footways along the frontage of the development should be improved to provide a 3m
wide shared footway/cycleway. The existing footway should therefore be widened where the
existing width is less than this; there may be scope for widening to take place within the existing
verge. 
Reason: In accordance with the Council's Active Travel Strategy. 
20. Disabled Parking spaces require to be provided on the basis of 6% of the total number of spaces
provided, equating to a total requirement of 20 spaces. These spaces should be provided in a
convenient location as close as possible to the building entrance, without the need for pedestrians
to cross parking space aisles. 
Reason: In order to provide adequate disabled parking provision. 
21. Cycle parking should be provided on the basis of 1 space per 8 car parking spaces, equating to
a total of 42 cycle parking spaces. 
Reason: In order to provide adequate cycle parking.
Page 72 of 113

Page 73

22. That within 3 months of the determination date, unless otherwise agreed in writing with the
Planning Authority, full details of the design and location of all fences and walls to be erected on
the site shall be submitted to, and approved in writing by the Planning Authority and the
development shall be implemented in accordance with the details approved under the terms of
this condition. 
Reason: In the interest of the amenity of the site and the general area. 
Background Papers: 
Consultation Responses:  
NLC Greenspace received 12.08.22 &16.09.22 
NLC Environmental Health (including Pollution Control) received 12.08.22
NLC Traffic & Transportation received 07.09.22
Transport Scotland received 02.09.22 
Archaeology Service received 08.08.22   
Contact Information: 
Kirsten Devlin at Planningenquiry@northlan.gov.uk 
Report Date: 28th September 2022
Page 73 of 113

Page 74

APPLICATION NO. 22/00836/FUL 
REPORT 
1. Site Description 
1.1 The application site is an undeveloped area of land approximately 1.60 hectares in area which
is sited within Gartcosh Business Interchange. It is bounded by the M73 embankments on the
north-western boundary, by Auldyards Road and Craignethan Drive on the north and south-
eastern boundaries and undeveloped land, earmarked for future business development, on the
south-western boundary. The Scottish crime campus sits further south and industrial units by
Fusion Assets have been built to the northeast on Bothlin Road. 
1.2 The Business Interchange site previously formed part of Gartcosh steelworks until the late
1980’s when the works were closed and thereafter demolished. The site, which is relatively flat,
was fully remediated and prepared for development a number years ago. 
1.3 Gartcosh Local Nature Reserve (LNR) and Site of Importance for Nature Conservation (SINC)
lies in close proximity to the site on the other side of Craignethan Drive. Gartcosh LNR is known
to have a high population of Great Crested Newts. 
2. Proposed Development 
2.1 Permission is sought for a manufacturing facility and offices with associated parking and
landscaping. The applicant is Guala Closures Group which is a world leading producer of
closures (a wide range of bottle tops) for spirits, wine, water and olive oil. They seek to
consolidate three existing plants in Scotland into one single facility at Gartcosh and intend to
purchase the site from Scottish Enterprise. 
2.2 The footprint of the development is approximately 21,000 square metres with the majority taken
up by the manufacturing facility, which has a simple industrial design with regular window
openings to provide natural light and silver cladding. The offices are situated on the north-
eastern corner of the building and are characterised by large windows, contrasting cladding,
parapet style roof and a protruding feature curtain wall glazed entrance. 
2.3 There will be 2 vehicular access points into the site from Craignethan Drive. The southern
access is exclusively for service vehicles with the northern most access for staff and visitors.
Once within the site the staff access road is flanked either side by car parking areas with a vista
towards the feature office entrance. A total of 332 car parking spaces are proposed with 20
disabled spaces located at both the main office entrance and the manufacturing staff entrance.
42 cycle parking spaces will be provided.  
2.4 There is an area for potential future expansion within the northern portion of the site, which will
be planted with wildflower seeding to assist local biodiversity. A Sustainable Urban Drainage
System (SUDS) basin will be sited at the south of the site adjacent to the service access and
will be planted with a wet meadow wildflower seeding mix. 
3. Applicant’s Supporting Information 
3.1 The applicant has submitted a comprehensive body of information which has allowed detailed
consideration in respect of the following supporting information: 
 Design and Access Statement
 Drainage Assessment
 Ecological Impact Assessment
 EIA Screening Report
 Environmental Noise Impact Assessment
 Pre-application Consultation Report
Page 74 of 113

Page 75

 Site Investigation
 Transport Assessment
 Transport Statement
 Water Vole Status Summary 
3.2 The Pre-Application Consultation report summarised the public consultation event which took
place online between 27th April 2022 and 18th May 2022 providing details of the proposed
development. No public comments were received/lodged as part of the consultation. 
4. Site History 
4.1 The planning history for the application site is as follows: 
 01/00001/OUT Gartcosh Industrial Park (Outline)
 01/00885/FUL Culverting of 40m Length of Bothlin Burn.
 02/00849/REM Landscape Infrastructure Including Earth Modelling, Woodland Planting
and Gateway Feature.
 05/00331/REM Construction of Access Road, Site Preparation Works and General
Engineering Operations
 07/01572/AMD Non-Compliance with Condition No. 16 of Planning Consent
N/01/00001/OUT in Respect of the 27 Ha Single User Site
 22/00421/PAN Proposed Industrial Development for Manufacturing Facility with Associated
Parking, Landscaping and Infrastructure. 
5. Development Plan 
5.1 In terms of strategic planning policy, the application represents a strategic development in terms
of Clydeplan 2017 (see schedule 14 - class 5 over 10 000m2).  With regard to this site the
relevant policy in the Clydeplan 2017 and schedule (Policy 5 & Schedule 3) identifies this site
as being a Strategic Economic Investment Location with a key identified role of Business and
Financial Services although it is recognised that the development sites available at Gartcosh
have the potential to be suitable for a range of business users. Locations such as Gartcosh
Business Interchange are the city region’s strategic response to delivering long-term
sustainable economic growth. This proposal being for a new manufacturing facility supports the
vision and spatial development strategy of the Strategic Development Plan so the proposal can
then be assessed against local plan policy. 
5.2 The Scottish Government confirmed on 5 July 2022 that the Scottish Ministers do not propose
to issue a direction in respect of the adoption the North Lanarkshire Local Development Plan
and that the Council can proceed to Adopt.  Accordingly, the Plan has now been Adopted by
the Council and became operative on 6 July 2022.  Whilst it remains possible that there may
be a legal challenge to adoption from objectors to the Plan, it is unlikely that any such challenge
would relate to matters directly relevant to this application. The North Lanarkshire Local
Development Plan 2022 Identifies the site as being within a Business Centre and is part of a
specifically identified development platform. Placemaking Policy PP2A (Strategic Business
Centres) applies which specifically promotes the development of Class 4 Office, Class 5
General Industrial and Class 6 Storage and Distribution. Policy AD 2A relates to the amount of
such development and in this case no assessment of the amount of development is required
for the above uses. 
5.3 Environmental and Design Policies EDQ 1 (Site Appraisal) and EDQ 3 (Quality of Development)
also apply and require high standards of site planning and sustainable design are achieved and
seek to ensure all developments integrate successfully into the local area and avoid harm to
neighbouring amenity. 
Page 75 of 113

Page 76

6. Consultations 
6.1 The following consultation responses were received in connection with the proposal: 
NLC Pollution Control and Public Health have confirmed the need for an Air Quality Screening
Technical Note as there are more than 300 car parking spaces. They confirm they are satisfied
with the findings of the Noise Impact Assessment and acknowledge receipt of the Site
Investigation which is under review. If the review is not completed before the application is
reported to the Planning Committee standard Site Investigation and remediation conditions will
require to be attached. Standard comments relating to noise, control of dust, health and safety
measures, burning of waste materials and lighting are attached as advisory notes. 
NLC Greenspace Development confirm the newt wall erected around the site perimeter and
translocation of the newts to the Local Nature Reserve (LNR) has kept the site free of Great
Crested Newts. The Ecological Impact Assessment has been accepted and if no work has
begun within a year of the determination date updated surveys are required. The findings of a
requested water vole survey have been accepted and various biodiversity enhancements
recommended by Greenspace have been taken on board by the applicant with the submission
of landscaping plans. 
NLC Roads Operations has no objection to the proposal subject to the imposition of planning
conditions relating to visibility splays, minimum access spacing, swept path drawing, disabled
parking, cycle parking and Electric Vehicle charging provision. 
Transport Scotland have no objection to the proposal subject to the imposition of planning
conditions relating to the approval of the lighting scheme for the development and ensuring that
no drainage is connected to the trunk road network. 
Archaeology Service has no objection to the proposal after receiving information confirming
previous land uses will have destroyed the potential for previously unknown archaeological
remains. 
7. Representations 
7.1 No representations have been received. 
8. Planning Assessment 
8.1 Under Section 25 of the Town and Country Planning (Scotland) Act 1997, planning decisions
must be made in accordance with the development plan unless material considerations indicate
otherwise. 
Strategic Development Plan 
8.2 In terms of strategic planning policy, the application represents a strategic development in terms
of Clydeplan 2017 (see schedule 14 - class 5 over 10 000m2). With regard to this site the
relevant policy in the Clydeplan 2017 and schedule (Policy 5 & Schedule 3) recognises that
Gartcosh has significant development potential with three large scale development areas
offering a range of options for business users. This proposal being for a new manufacturing
facility and offices supports the vision and spatial development strategy of the Strategic
Development Plan so the proposal can then be assessed against Local Development Plan
policy. The proposed development complies wholly with this strategic policy. 
Local Development Plan  
8.3 The North Lanarkshire Local Development Plan 2022 identifies the site as being within a
Business Centre and Placemaking Policy PP2A (Strategic Business Centres) applies. This
specifically promotes the development of Class 4: Business, Class 5: General Industrial and
Page 76 of 113

Page 77

Class 6: Storage and Distribution uses. Policy AD 2A relates to the amount of such
development and in this case no assessment of the amount of development is required for the
above uses. The proposed development complies wholly with this Placemaking policy. 
8.4 Environmental and Design Policy EDQ 1 (Site Appraisal) applies to all development to ensure
it integrates successfully into the local area and avoids harm to neighbouring amenity. It looks
at the detailed environmental and design elements which for this proposal includes massing,
height, finishing materials, accessibility and biodiversity on the site and surrounding area. The
height and massing of the main part of the building is driven by the production process with the
elevations having a simple form. The finishing materials are silver wall panels with dark grey
windows and roof lights. The office building has contrasting cladding and larger windows,
parapet style roof and a protruding feature curtain wall glazed entrance. Both industrial and
office elements are harmonious with the other buildings in the Business Park and are
considered to integrate successfully. Gartcosh Local Nature Reserve (LNR) and Site of
Importance for Nature Conservation (SINC) lies to the north and is known to have a high
population of Great Crested Newts (GCN). The site has been kept GCN free through
translocation of the newts to the LNR and erection of newt wall around the site perimeter. 
Furthermore, consultation with Greenspace has resulted in various biodiversity measures being
introduced. The development is therefore considered to comply with Policy EDQ1.  
8.5 Environmental and Design Policy EDQ 3 (Quality of Development) also applies, and states
development will only be permitted where high standards of site planning are achieved in terms
of design etc. which is discussed in paragraph 8.4 above. It also requires to be attractive to
pedestrians, cyclists, people with disabilities and integrate with public transport networks. The
site is served by a shared footpath that links to Gartcosh and Glenboig. Gartcosh Train Station
is situated at the southern end of the Business Park and the site has direct access to the M73.
There are planning conditions attached to ensure appropriate provision of disabled parking
spaces and cycle racks and the proposal includes electric vehicle charging points. Proposals
must also mitigate any likely pollutants – which in this case is noise from the manufacturing
facility and air quality due to the level of traffic associated with the proposal. An Air Quality
Technical Screening Note is conditioned, and an Environmental Noise Impact Assessment has
established the measures required (which are conditioned) to ensure the proposal has no
detrimental impact on the nearest residents in Gartcosh. Given this the proposal complies with
Policy EDQ3.
Projected Socio-Economic Impact 
8.6 Guala Closures are looking to consolidate their three existing plants into a single facility. The
project will safeguard 425 jobs in the Scottish drinks supply chain as well as resulting in
considerable capital expenditure investment. The current sites are at capacity with a predicated
Gross Value Added (GVA) in 2022 of £30 million. It is calculated that over the period 2023 –
2027 successful delivery of the project could result in £43.6 million of Gross additional GVA in
Scotland. The project with also result in substantial capital investment, not just from Guala
Closures but also some of their key customers, further strengthening the Scottish drinks supply
chain. 
Landscape, Visual Impact and Ecological Impact  
8.7 Due to the location and nature of the scale and massing of the proposed building it is considered
that the proposed development does not raise any landscape and visual impact issues. In
addition to the commentary above on the wider landscape impact of the proposal, it is also
necessary to consider the impact on ecology at and adjacent to the site. In terms of ecology
Policy PROT A indicates that development that significantly affects a species protected by law
will only be permitted where an appraisal has demonstrated that the protected species would
not be compromised. SPG 20 (Biodiversity & Development) requires that applicable
developments demonstrate any risk and means for mitigation of Protected Species. The newt
fencing erected around the site perimeter and translocation of the newts to the LNR has kept
the site free of Great Crested Newts. Ecological appraisals were undertaken to determine the
existence of suitable habitat for, and evidence of bats, otter, water vole, badger, and great
Page 77 of 113

Page 78

crested newts. No protected species were recorded, and Greenspace accepted the findings of
the reports advising that these would require to be updated in the event that development had
not commenced within one year of the survey date.  Biodiversity enhancements recommended
by Greenspace have been incorporated into the approved landscaping plans. Given the policy
(which promotes the development of Class 4 Business, Class 5 General Industrial and Class 6
Storage) and as there are no ecological issues the proposal is considered to be acceptable in
this regard. 
Flooding and Drainage 
8.8 SPG 09 (Flooding & Drainage) requires that applicable developments demonstrate any risk and
means for mitigation of flooding and detail the measures for treatment of surface water through
the use of SUDS principles. A Drainage Assessment was undertaken which concluded that the
proposed development can be operated satisfactorily in terms of surface drainage and is
compliant with the requirements of national policy and guidance. On this basis it is considered
that the development should raise no flooding concerns and conditions are recommended to
confirm the drainage proposals are installed in accordance with the plans and SUDS principles
and that Scottish Water’s requirements for connection are met. The proposals are therefore
considered to comply with the terms of SPG 09 and appropriate planning conditions can be
applied in this respect. 
Building Design, Site Layout, and Boundary Treatment 
8.9 It is considered that the proposed buildings have been sensitively designed in terms of siting,
massing and finishing materials and as such, it is considered that the proposal complies with
policies EDQ 1 and 3. 
Effect on the Road Network 
8.10 In advance of this application, and unrelated to it, NLC Roads Operations had commissioned
Atkins Consultants to undertake a Transport Assessment to consider the cumulative impacts of
the sites to be developed in the business park alongside the ongoing housing developments
within the Community Growth Area (CGA). This report has concluded that no further mitigation
measures are required in addition to that which have already been identified for the CGA. That
said, specific assessments will be required for each development as they materialise and, in
this case, a specific assessment was also made of the Guala development. This concludes the
development can be accommodated on the existing road network. Transport Scotland agreed
with these findings and raised no objections to the proposals in terms of their impact upon the
M73. They requested conditions be attached relating to site lighting and ensuring no drainage
connections to the trunk road drainage system.  NLC Roads Operations have no objection to
the proposal subject to the imposition of planning conditions relating to visibility splays,
minimum access spacing, swept path drawing, disabled parking, cycle parking and Electric
Vehicle charging provision. It is considered that the development can be accommodated without
detriment to the trunk and local road networks. 
9. Conclusions  
9.1 In conclusion, it is considered that the proposal accords with the development plan and
represents a significant investment within North Lanarkshire Council and will activate a large
area of Gartcosh Business Interchange into productive use. In light of the site attributes, it is
considered that the development will be accommodated without detriment to the surrounding
area. Accordingly, it is recommended that planning permission be granted subject to conditions. 
Page 78 of 113

Page 79

Application No:  
22/00868/FUL
Proposed Development: 
Installation of a new 40m high lattice telecoms tower with 12 x
antennas and ancillary equipment and the relocation of 4 x
300mm diameter dishes, all contained within a new compound
enclosed by way of a 2.5m high palisade fence 
Site Address: 
Fir Park Stadium
Fir Park Street
Motherwell
ML1 2PR 
Date Registered: 
23rd August 2022 
Applicant:
Wireless Infrastructure Group
Wireless Information Group
Braidhurst House
2 Finch Way
Strathclyde Business Park
Bellshill
ML4 3PE 
Agent:
Harlequin Group
Rutland House
5 Allen Road
Livingston
EH54 6TQ 
Application Level:
Local Application 
Contrary to Development Plan:
No
Ward:   
19 Motherwell South East And Ravenscraig 
Kenneth Duffy, Agnes Magowan, Nathan Wilson,
David Robb,
Representations:
52 letter(s) of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The proposed development would have less impact on the locale than the 45m mast which was
refused planning permission in 2021, and meets the criteria set out in the relevant policies
contained within the North Lanarkshire Local Development Plan 2022. 
Page 79 of 113

Page 80

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 22/00868/FUL 
Name (of applicant): Wireless
Infrastructure Group
Site Address: Fir Park Stadium
Fir Park Street
Motherwell
ML1 2PR
Development: Installation of a new 40m
high lattice telecoms tower with 12 x
antennas and ancillary equipment and
the relocation of 4 x 300mm diameter
dishes, all contained within a new
compound enclosed by way of a 2.5m
high palisade fence   
Page 80 of 113

Page 81

Proposed Conditions:- 
1. That the development hereby permitted shall be carried out strictly in accordance with the
approved details submitted as part of the application and no change to those details shall be
made without prior written approval of the Planning Authority. 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That, in the event that the telecommunications equipment, supporting structure or the apparatus
within the site becomes redundant it must be removed to the satisfaction of the Planning Authority
within one month of becoming redundant. If the site ceases to be used for telecommunications
transmissions, it must be reinstated to the satisfaction of the Planning Authority within six months
of cessation. 
Reason: To minimise the level of visual intrusion and to ensure the reinstatement of the site to a
satisfactory standard. 
Background Papers: 
Consultation Responses: 
Memo from Environmental Health (including Pollution Control) dated 30th August 2022 
Contact Information: 
Stewart MacCallum at Planningenquiry@northlan.gov.uk 
Report Date: 
27th September 2022  
Page 81 of 113

Page 82

APPLICATION NO. 22/00868/FUL 
REPORT 
1. Site Description 
1.1 The site is located within the grounds of Motherwell FC`s Fir Park Stadium in Motherwell. In
particular, the site is immediately to the west of the South stand which is immediately bordered
by residential properties (Fir Park Street) to the west, and to the south by Firpark Secondary
School. 
2. Proposed Development 
2.1 The application seeks permission to erect a 40 metre high lattice telecommunications mast
which would include 12 antenna, 4 dishes and ancillary works including a 2.5 metre high
palisade fence to enclose the compound. The mast would be 5 metres or so from the school
boundary and around 40 metres from the closest part of the school building.  It would also be
around 7 metres from the nearest house boundary and around 36 metres from the nearest
house. 
2.2 The site (Fir Park Stadium) currently has the applicant`s existing telecommunications
equipment on the opposite side of the south stand which is incorporated into the existing free-
standing metal lattice floodlight structure. However due to having insufficient structural capacity
to be suitably redeveloped, it would be the proposal to remove the equipment from this existing
structure and build a new mast which does have that capability and also relocate some of the
existing equipment on to this new mast. It is also noted that there is currently also separate
telecommunications equipment located on some of the other floodlight structures as well. 
2.3 The applicant has identified that there is a requirement to upgrade to 5G coverage to ensure
that this is available for users in the locality. Whilst existing coverage can be maintained for
telephone calls, text messages and internet access, the proposal is to allow the new technology
for enhanced coverage and more efficient internet and streaming services. It should be noted
that included within this proposal is an upgrade of the current 4G Emergency Service Network
(ESN) which is the telecommunications system used by the emergency services, and an
upgrade from the current system to provide improved communications coverage and usage of
such technology. 
3. Applicant’s Supporting Information 
3.1 The applicant submitted supporting information in respect of the following:
 Full suite of drawings
 ICNIRP Certification (International Commission on Non-Ionizing Radiation Protection)
has been submitted with the application which confirms that the mast will operate well
within the required Government levels.
 Planning Statement and various other supporting statement regarding the benefits of
5g   
4. Site History 
4.1 Fir Park Stadium is an established site for telecommunications apparatus which currently
utilises the existing free-standing lattice floodlight structures at the stadium. It has various
previous permissions to install equipment and then subsequent upgrade works to these. 
4.2 It should be noted that there has been a similar application (21/01132/FUL) refused by
Members at October Planning Committee 2021 against officer`s recommendation. The reason
for refusal was:  
Page 82 of 113

Page 83

That the mast would detract from the amenity of the immediate and wider area due to its height,
location and appearance and due to significant local concerns regarding the possibility of health
impacts, all of which mean that the proposal is deemed to be contrary to the adopted 2012
North Lanarkshire Local Plan, in particular: policy HCF 1 B1 (in that it would not maintain
community well-being), policy RTC 3B (in that local amenity would be adversely affected),
policy EDI 3 (in that visual and environmental impacts would not be acceptable) and policy DSP
4 (in that the development would not be successfully integrated into the wider area).   
The decision to refuse permission was not appealed to the Scottish Ministers and any
opportunity to appeal that previous decision is now time lapsed.   This proposal sees a revised
application in which the height of the mast is 40 metres (a reduction of 5 metres from the 45m
mast proposed before).  The site of the proposed mast remains unchanged. 
5. Development Plan 
5.1 In the adopted 2022 North Lanarkshire Local Development Plan 2022, the application site is
designated  under policy PP3 General Urban Policy(Purpose of Place) which states that   “The
Council seeks to maintain and improve the level of amenity in urban areas, by encouraging
development that is in keeping with their residential character and encouraging diversity in more
mixed-use areas”. Policy AD3 General Urban Policy(Amount of Development) links to policy
PP3 and states that applications for new development will be assessed for their implications
related to the amount of development proposed. The need for an assessment depends on the
combination of type (Use Class), scale and location of development.  There is not a limit on
communications, utilities or infrastructure development. 
5.2 Policy PROM 1D2 (Utilities Development) states that the council “will support utilities
developments in principle, subject to the assessment criteria..” 
This comprises of the council seeking evidence as to how the proposed equipment will deliver
new or enhanced connectivity to an area, fits into the wider network and complies with ICNIRP
Radiation Guidelines. This also advises that any assessment should also consider the
cumulative effects of the proposed development in combination with existing equipment in the
area. This states that the council will encourage telecommunications proposals that will share
existing and new facilities, or use existing buildings or structures and are sited and designed to
reduce visual and environmental impact. 
5.3 Policy EDQ3 Development Quality states that development will only be permitted where high
standards of site planning and sustainable design are achieved. Planning applications will need
to demonstrate that the proposed development takes account of the site appraisal carried out
as a requirement of policies EDQ1 and, if appropriate, EDQ2, assets protected under Policy
PROT, any evaluation of design options, and achieved a high quality development.   
6. Consultations 
6.1 NLC Protective Services have no objections to the proposal. 
7. Representations 
7.1 A total of 52 objections were received during the neighbour notification process and
advertisement of this application, however only 41 would be recognised as representations. We
received some anonymous and multiple representations for several individual property
addresses. It would be noted that in regard to counting representations, the North Lanarkshire
Council Scheme of Delegation confirms that  that multiple representations from the same
property would count as a single representation and anonymous representations are not
counted. Objections were received from Councillors Agnes Magowan, Kenneth Duffy and
Nathan Wilson. 
Page 83 of 113

Page 84

7.2 In summary, the objections to this application raised concerns in the following areas: 
 The mast is out of character and context with the residential area causing a significant
impact upon the outlook of residential properties. The mast is of a significant height and
visually prominent being taller than any other nearby structure. 
 The mast is not an essential use and has locational need to be in this location.
 Noise and disruption caused from the mast and equipment
 Potential radiation and health impacts to people
 Location of mast near to sensitive sites such as schools
 Potential impact of mast to low level aircraft
 Loss of privacy/overlooking works on mast. 
7.3  Other issues were raised however they are not material planning considerations. They include
devaluation of property, lease agreements between the applicant and Motherwell FC and
blocking of existing views. 
7.4 Health concerns in relation to people and pets were raised by many as a concern. As part of
any application of this nature the applicant is required to provide an ‘ICNIRP’ Certificate (see
para 3.1 above) and this has been done, This certificate confirms that the level of impact is
within the required levels. As a result of the submission of this information, the health concerns
are in effect not part of  the assessment of the mast under planning legislation. 
8. Planning Assessment 
8.1 Section 25 of the Town and Country Planning (Scotland) Act 1997 requires  that a planning
determination  shall be such as to accord with the  Development plan  unless material
considerations indicate otherwise. In this case, the proposal is not of strategic significance and
as such, should be assessed in terms of the relevant local plan policies. 
8.2 In terms of the primary zoning of the site, the focus of policies PP3 General Urban Policy (and
policy  AD3) is to maintain and improve the level of amenity in urban areas, by encouraging
development that is in keeping with their residential character and encouraging diversity in more
mixed-use areas. The application site is positioned to the side of the South Stand and there is
no impact to the existing main use of the site as a football stadium. The use is ancillary to the
overall use of the facility which experiences high volumes of people attending matches and
requires to maintain mobile coverage for the public and emergency services. As noted above,
the stadium already accommodates telecoms infrastructure.  Although the scale of the
development is not generally in keeping with residential character, it is acknowledged that the
mast would fit in with the actual character and appearance of the application site itself (i.e. a
large football stadium with stands floodlights sanctions and other associated structures). It is
considered therefore that the planning application is in accordance with this policy.   
8.3 Policy PROM 1D2 (Utilities Improvements) states that the council supports utilities development
in principle. The council seek the submission of evidence as to how the proposed equipment
will deliver new or enhanced connectivity to an area, fits into the wider network and complies
with ICNIRP Radiation Guidelines. In terms of sharing facilities, the initial option considered by
the applicant was to utilise the existing floodlight structure and redevelop this to accommodate
the new equipment. However, it was physically not possible to undertake these works on this
structure and the most viable option was to create a new mast structure which would reach the
required height to be able to provide adequate network coverage. Whilst it is a new mast, the
site has been utilised for telecommunications albeit in a different location within the stadium on
a floodlight structure. It is also considered that the new structure would be acceptable in terms
of visual and environmental impact (see assessment of EDQ 3 below).  It is therefore
considered that the development would be in accordance with Policy PROM 1D2. 
8.4 Policy EDQ 3 sets out that development will only be permitted where high standards of site
planning and sustainable design are achieved. This policy sets out criteria and requirements in
this respect which include character and setting, integration into the local area, impact on traffic
and avoiding harm to the neighbouring amenity. When assessed against the terms of policy
EDQ 3 (Quality of Development), it is considered that the proposal can be integrated
Page 84 of 113

Page 85

successfully into the surrounding area without detriment to the amenity of the existing
residential area and other mixed uses. Justification for this assessment is as follows: 
8.5 It would be accepted that the mast is of a considerable height and because of this it will be
visually prominent given its height of 40 metres, However, in this instance, context also has to
be taken into account in regard to where the site is located and the existing structures that it is
adjacent to. The existing South stand is 30 metres in height and is higher than most structures
nearby and there are four existing lattice style free-standing floodlights reaching 35 metres in
height which currently accommodate telecommunications equipment. The mast would see an
increase of 5 metres from the that of the existing floodlights. Nevertheless, the mast is much
narrower and thinner towards the last top 10 metres or so, thus reducing its overall impact. The
position of the mast near to the stand adds a substantial element of screening and backdrop. 
In terms of visual impact, the greatest impact would be the view from those houses on Fir Park
Street which back onto the site.  However, the stands and the floodlights already make up a
view and the introduction of a 40m high structure would be seen in that context. Moreover,
whilst obviously a new structure, it is very similar in appearance to the existing floodlight
structures.  On balance therefore, in visual terms, the new structure is considered to be
acceptable.  
8.6 It is therefore assessed that any determination that approves the proposal would  in accordance
with the development plan.  In accordance with Section 25, the proposal must therefore be
granted planning permission unless material considerations suggest otherwise. Other material
considerations, including those raised within the representations, are set out and assessed as
follows: 
o There is no impact to roads as it is contained within the grounds of Fir Park Stadium
and would not generate any additional traffic other than during the construction works.
There are no discernible noise issues associated with masts and the concerns
regarding health impacts are addressed above. 
o In terms of impact on aviation, contact was made with Glasgow Airport Safeguarding
in the previous application and they confirmed that a 45m high mast and they advised
that they do not require to be consulted on that planning application. It is noted that this
application proposes a smaller mast than before.   
o In relation to overlooking/loss of privacy to nearby residential properties, it would not
be considered to be an issue. There would be initial works to erect the structure, but
thereafter it would only be routine maintenance or upgrading which would not be a
regular occurrence. 
o Planning history is a material consideration. In this case the current proposal is very
similar to the previous planning application (21/01132/FUL) with the main difference
being a lowering in height from 45 metres to 40 metres. All other aspects are the same
as the previous application. Both applications were the basis of significant local concern
albeit the current application has received slightly fewer representations that the initial
application. A mast of such a height is always going to be visually prominent however
the reduction by 5 metres does make a meaningful change as its impact would be
reduced and would bring it down to being  only be 5 metres higher than the existing
floodlights structures. The design of the mast is of a similar type design to the floodlights
and would generally have the backdrop of these to blend into. The noted reasons for
refusal related to the height and location of the mast and subsequent visual impact it
would have upon the appearance of the area. However, it would be considered that
there is a reduction to the impact with the decrease in the height of the structure. The
other point referred to in the initial application refusal was regarding health impacts.
The planning application, as required, has provided the required ICNIRP certificate
and, like the previous proposal, is well within acceptable limits. Health cannot be
considered as a reason to refuse an application provided this documentation has been
provided. It would be noted that the applicant did not progress to take this previous
decision to appeal after refusal. The other main change to occur since the previous
application is the change from the North Lanarkshire  Local Plan 2012 to the North
Page 85 of 113

Page 86

Lanarkshire Local Development Plan 2022. It would be noted that there has been a
change in the relevant policies  used to consider the proposal. Under the plan, the site
specific policy identified the site as a community facility, however in the new Local
Development Plan it is identified under General Urban Policies PP3 and AD3 which
does refer to telecommunications and a more specific assessment under Policy PROM
1D2. Largely most of the considerations of the former Policy ED1 3 (Utilities
Development) of the former local plan are retained within Policy PROM 1D2 (Utilities
Improvements). Overall it would be considered that this proposal has shown a
meaningful reduction in its impact and sufficient justification that it would be appropriate
to be located at this site and there is a locational requirement to be there. 
9. Conclusions 
9.1 This is a large structure which is in close proximity to houses and a school but the amenity
impacts (most notably visual impacts) are mitigated by the fact that there are already large
structures nearby.  It is noted that there are already telecoms infrastructure at the stadium,
albeit as part of the existing floodlight structures.  The facility will bring benefits to the local
community and to the emergency services. Whilst it is noted that the previous application
(21/01132/FUL) had been refused, it is considered that there have been changes to the
proposal which reduce its overall impact 
9.2 Despite the many objections from the local community, a determination by the council to
approve the development would accord with the development plan and, in terms of Section 25
of the Act, there are no material considerations to indicate that the decision should be different.
It is therefore, recommended that planning permission be granted.   
Page 86 of 113

Page 87

North Lanarkshire Council
Report
PLANNING COMMITTEE  
Agenda item _________   approval  noting Ref PH/SW Date 13/10/2022  
PLANNING AND ENFORCEMENT NOTICE APPEALS LODGED 
From HEAD OF PLANNING AND REGENERATION
Email humphriesp@northlan.gov.uk Telephone 01236 632500 
Executive Summary
1. Purpose of Report 
1.1       This report is to advise the Committee of the undernoted planning appeals      
recently lodged with the Scottish Ministers. 
Recommendations
It is recommended that the Committee notes the position. 
Background
Application No.        Applicant          Date of Council   Form of   Note
& Proposal            & Site           Decision      Appeal  
22/00462/AMD
Modification of
existing Section 75
Planning Obligation
relating to
permission
17/01248/PPP
(Reduction of
education
contribution for
residential
development) 
Morgan
Properties
Newmains LLP
Land East Of
Main Street
Newmains 
N/A Written
Submission
Appeal for Non-
Determination 
PAMELA HUMPHRIES
HEAD OF PLANNING AND REGENERATION 
AGENDA ITEM 3
Page 87 of 113

Page 88

Page 88 of 113

Page 89

North Lanarkshire Council
Report
PLANNING COMMITTEE  
Agenda item _    ____   approval x noting Ref LB/ES Date 13/10/2022  
NOTICE OF PLANNING AND ENFORCEMENT APPEALS
DECISIONS 
From HEAD OF PLANNING AND REGENERATION
Email humphriesp@northlan.gov.uk Telephone 01236 632500 
Executive Summary
1. Purpose of Report 
1.1        This report is to advise the Committee of the recent decisions in respect of the 
undernoted planning appeals. 
Recommendations
It is recommended that the Committee note the decision in respect of this appeal. 
Background
Application No. & Proposal  Applicant & Site Appeal Decision
& Date
Note
21/00892/FUL
Siting of Storage
Containers for Self Storage
Facility Along with Admin
Office (Part Retrospective),
Reuse of Existing Class 5
Industrial Unit for Storage
& Distribution Use, New
Access and Landscaping
Chryston Self Storage
194 Cumbernauld Road
Chryston
Glasgow
North Lanarkshire
G69 9NB
Appeal Dismissed
26/09/22 
PAMELA HUMPHRIES 
HEAD OF PLANNING & REGENERATION 
AGENDA ITEM 4
Page 89 of 113

Page 90

Page 90 of 113

Page 91

North Lanarkshire Council
Report
Planning Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref  Date 13/10/22 
The Town and Country Planning (Fees for Applications)
(Scotland) Regulations 2022 
From  Pamela Humphries, Head of Planning and Regeneration  
E-mail BowdenL@northlan.gov.uk Telephone Lorna Bowden, 07939
280460 
Executive Summary
The Town and Country Planning (Fees for Applications) (Scotland) Regulations 2022 (“the
Regulations”) set out the level of fees required as part of the submission of planning
applications and other associated applications.  The Regulations for the first time include
new sections on discretion to charge fees, waiving or reducing of fees and surcharges on
retrospective planning applications.   
The Regulations require us, as planning authority, to set out what we will charge for these
services, when and by how much fees will be reduced, and clarify the level of surcharges
applied. This report sets out recommendations in relation to additional fees the Council
may wish to consider charging which could deliver additional resources to enhance the
service provided and ensure a well-resourced and efficient planning service is maintained. 
Recommendations 
It is recommended that the Planning Committee agree to the following: 
i) the introduction of fees for providing the following: 
• pre-application discussions / written advice as set out in section 2.7
• considering a request to vary a planning permission under section 64 of
the 1997 Act (non-material variations) as set out in section 2.11
• considering a request for written confirmation of compliance with a
condition imposed on the grant of planning permission (Conditions
Discharge) as set out in section 2.12 
ii) the reduction of fees by 50% for the following: 
• where the application relates to development which, in the opinion of the
planning authority, has the primary purpose of contributing to a not-for-
profit enterprise or a social enterprise. 
AGENDA ITEM 5
Page 91 of 113

Page 92

1. Background 
1.1 The Regulations set out the level of fees required as part of the submission of planning
applications and other associated applications. The Regulations replace the Town and
Country Planning (Fees for Applications and Deemed Applications) (Scotland)
Regulations 2004. They also introduce some additional categories of payment and
enabling the planning authority to charge discretionary fees for some services, to
reduce or waive fees in certain cases and to apply a surcharge for retrospective
applications. 
1.2 The Regulations require us, as planning authority, to set out what we will charge for
these services, when and by how much fees will be reduced and clarify the level of
surcharges applied. 
1.3 The increase in planning fees came into effect on 1st April 2022 and included planning
fees for a single house increasing from £401 to £600 and householder application fees
increasing from £202 to £300. The most significant increase relates to the category of
electricity generation where the maximum fee has been increased from £125,000 to
£150,000 albeit some fees for large scale wind turbines up to a maximum of 3 have
also been significantly reduced from that previously applicable. 
1.4 The Regulations for the first time include new sections on discretion to charge fees,
waiving or reducing of fees, and surcharges on retrospective planning applications. The
majority of Local Planning Authorities across Scotland have already been charging for
preliminary enquiries and non-material variations services. North Lanarkshire has thus
iii) the implementation of a surcharge on retrospective applications for the
following: 
• An additional 25% surcharge fee where, on or after 1st November 2022,
an application for planning permission is made after the carrying out of
the development to which it relates. 
iv) the additional or amended charges in relation to the following as set out in
sections 2.29, 2.30 and 2.33: 
• Submitting paper applications
• Refund charges
• Property History Search and Provision of Decision Notice and Plans 
v) note the deferral until publication of NPF4 on a decision on the reduction of fees
for the following: 
• where the application relates to development which, in the opinion of the
planning authority, is likely to contribute to improving the health of
residents of the area to which the application relates. 
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement All ambition statements
Page 92 of 113

Page 93

far not charged for such services as outlined in the new discretionary fees section of
the regulations. 
1.5 This report sets out recommendations in relation to additional fees the Council may
wish to consider charging which could increase income to provide additional support to
applicants, and ensure a well-resourced and efficient planning service is maintained. 
2. Report 
2.1 This report is intended to advise on potential options for additional fees to be charged
by the planning authority in relation to functions we currently carry out but do not
currently charge a fee for in line with both the Regulations and additional fees currently
charged by other Local Authority areas. 
2.2 Having reviewed various Local Authority areas it is noted that some have been charging
additional fees for some services for a considerable period already. Given the current
and future budgetary constraints placed upon all Council areas it is considered prudent
to consider the potential for any additional revenue streams to help ensure a well-
resourced and efficient planning service is maintained going forward. 
2.3 It is estimated that the introduction of charging as set out in the report below has the
potential to generate an annual income of £50,000. 
Pre-application Discussions / Written Advice 
2.4 The provision of pre-application enquiry advice is fundamental to identify the
appropriate supporting information to front load a planning application and assist in
reducing determination timescales. Currently the planning authority offers generic pre-
application advice for local developments (defined as all development other than
national and major developments) and householder developments (works to a
residential dwelling and within its curtilage) via the Council’s website which provides
useful links to information that can help inform if planning permission is required, clarify
the process for applying for a certificate of lawfulness, provide links to the interactive
local development plan and supplementary planning guidance notes. The planning
authority also offers bespoke pre-application advice for major developments but does
not charge for this service. 
2.5 The Regulations state that a planning authority may only charge fees for pre-application
discussions after the publication of information setting out the following: - 
i) which services a fee is to be charged for,
ii) how fees are to be calculated for those services, and
iii) under what circumstances the planning authority may waive or reduce that fee. 
The planning authority is also required to publish the information on the Council’s
website. 
2.6 While the introduction of fees for local and householder pre application advice will
potentially have resource implications in terms of staff time, it is considered that, on
balance, the time invested in providing this pre application advice could be offset
against time saved later in the process if less officer time required to secure a compliant
planning application. 
Page 93 of 113

Page 94

2.7 Notwithstanding the recent changes in legislation it should be noted that a number of
other Local Authorities have been charging for pre-application advice for a considerable
period of time. Having reviewed some of the services and charges that they provide,
and taking into account likely resources involved, the suggested fees for pre-application
advice are set out below: - 
Listed Building Pre-Application Proposals  £65 
Householder Pre-Application Proposals  £65 
Single House Pre-Application Proposals  £200 
Commercial Developments and Change of Use £200 
Pre-Application Proposals 
(Maximum Floor Space 500m²) 
Local Pre-Application Proposals   £500 
(Other than Householder Developments, 
Single Houses and Commercial Developments and 
Changes of Use up to Max 500m²) 
Major Pre-Application Proposals   £1000 
2.8 Should the fees be agreed the Council will need to provide detail on the content and
advice that will be provided by the paid for service for pre application advice. A draft of
the proposed content of the written advice (for consideration) is provided in the attached
Annex - (Draft Pre-Application Service Guidance Document) to this report. 
2.9 It should be noted that any paid pre-application service would not preclude applicants
from utilising the current means for obtaining pre-application advice in terms of:- 
i) The use of the Council’s website which includes useful links to information that
can help inform if planning permission is required, process for applying for a
certificate of lawfulness, links to the interactive local development plan and
supplementary planning guidance notes.
ii) Use of an architect or planning consultant who should be familiar with local
policies and procedures as well as national planning guidance.
iii) Use of the duty officer enquiry system – for general and non-specific advice
only for which there is no charge for the service – enquiries of a specific nature
would be directed to the paid for pre-application advice service. 
Request to Vary a Planning Permission Under Section 64 of the 1997 Act (Non-material
Variations)
2.10 The request to vary a planning permission under section 64 of the 1997 Act (Non-
material Variations) currently attracts no fee. The Regulations set out a flat fee of £200
for each request and it is proposed to charge this fee for all development types in line
with the level set out in the Regulations. 
2.11 It should be noted that if the recommendation for the £200 charge is agreed it would
only apply to applications made on or after 1st April 2022 and non-material variation
requests made after the date of Committee approval of these fee charges. 
Page 94 of 113

Page 95

Request for Written Confirmation of Compliance with a Condition Imposed on the Grant
of Planning Permission (Conditions Discharge)
2.12 The written confirmation of compliance with a condition and discharge of a Planning
condition (Conditions Discharge) currently attracts no fee. The Regulations outline that
”where a request is made to a planning authority for written confirmation of compliance
with a condition imposed on the grant of planning permission the fee payable to that
planning authority is £100 for each request”. It is therefore recommended that this
discretionary fee is applied to each separate request made if approved. It should be
noted that whilst the ability to charge is discretionary the fee level of £100 is set by the
legislation. For clarity the fee charges are in relation to a formal request for discharge
submitted by the applicant/agent and would not be applicable to general enquiries on
the status of compliance/discharge of planning conditions from interested third parties
such as neighbours. 
2.13 The fee would apply to each request made and could cover more than one planning
condition on the same planning consent. Each separate request will attract a new fee.
In terms of applications where the fee is waived under Regulation 7 (means of access,
etc. for disabled persons for example) it is proposed to waive fees relating to discharge
and compliance with condition fees. 
2.14 It should be noted that if the recommendation for the £100 charge is agreed it would
only apply to applications made on or after 1st April 2022 and condition discharge
requests made after the date of Committee approval of these fee charges. 
Waiving or Reduction of Fees 
2.15 Currently there are no fees payable for works or alterations to improve access, safety,
health or comfort for a disabled person in terms of householder developments in
circumstances where a health professional has provided written confirmation that the
works will positively impact the health or comfort of the applicant. 
2.16  The Regulations allow a planning authority to waive or reduce a fee following the
publication of a charter setting out the circumstances in which the planning authority
will consider waiving or reducing a fee payable to them. The charter must include but
is not limited to the circumstances: - 
i) where the application relates to development which, in the opinion of the
planning authority, has the primary purpose of contributing to a not-for-profit
enterprise or a social enterprise, and
ii) where the application relates to development which, in the opinion of the
planning authority, is likely to contribute to improving the health of residents of
the area to which the application relates. 
2.17 Section 252(1F) of the 1997 Town and Country Planning (Scotland) Act 1997 as
amended (“The 1997 Act”) defines “not for profit enterprise” and “social enterprise” as
follows: - 
i) “not for profit enterprise” means an organisation which a person might
reasonably consider to exist wholly or mainly to provide benefits for society,
ii) “social enterprise” means an organisation whose activities are wholly or mainly
activities which a person might reasonably consider to be activities carried on
for the benefit of society (“its social objects”), and which— 
a) generates most of its income through business or trade,
Page 95 of 113

Page 96

b) reinvests most of its profits in its social objects,
c) is independent of any public authority, and
d) is owned, controlled and managed in a way that is consistent with its social
objects 
2.18 In waiving or reducing any fee payable, the planning authority must state the reasons
for doing so on any decision notice and the charter produced by the planning authority
as noted in paragraph 2.16 above must also be published on the Council’s website. 
2.19 On the basis of the revised guidance the Council can waive or reduce planning fees for
applications that are considered to fall within the categories and definitions contained
within paragraphs 2.16 and 2.17 above. 
2.20 At this stage it is recommended that we offer a 50% fee reduction for developments
considered to have the primary purpose of contributing to a not-for-profit enterprise or
a social enterprise as defined by the 1997 Act as outlined in 2.16 above. It should be
noted that it would be for the applicant to show how they fall within the category defined
when seeking the fee reduction and the planning authority would take a view on such
a submission on a case-by-case basis. 
2.21 In terms of development which, in the opinion of the planning authority, is likely to
contribute to improving the health of residents of the area to which the application
relates. Due to the lack of clarity on the implications of this it is not recommended that
a fee reduction is provided at this stage, and this will be reviewed after the publication
of the finalised National Planning Framework (NPF4) later this year or early next year,
at which time the Council can fully consider the implications of introducing such a fee
reduction. 
A Surcharge on Retrospective Applications 
2.22 Currently there are no additional fees payable for an application for planning permission
which is made retrospectively. The Regulations allow a planning authority to impose a
surcharge for such applications and for this to be an amount calculated by the planning
authority but not exceeding one quarter of the level of the fee that would be payable if
the application were for planning permission to carry out that development. 
2.23 A planning authority may only impose a surcharge following the publication of
information on its website which includes: - 
a) how the surcharge is calculated, and
b) under what circumstances the planning authority may impose a surcharge 
2.24 It is recommended therefore that in line with the Regulations a surcharge of 25% of the
application fee is applied to all retrospective applications. It should be noted that many
retrospective applications are made once all the development is complete and others
when the development has been started but not completed. In circumstances where
work has started but not completed and may include a revised design these planning
applications shall also attract a surcharge of 25%. The introduction of a surcharge is
hoped to reduce the number of unauthorised developments that are carried out without
the necessary planning permission in place and is considered commensurate with the
additional officer time and resources that can be expended with such applications given
their sometimes more challenging nature. 
2.25 It is envisaged that the fee will be applied at the time of validation for retrospective
applications or (at the discretion of the planning service) before the application is
Page 96 of 113

Page 97

determined in cases whereby it only becomes clear during the assessment process
that the application is in fact retrospective. 
2.26 It should be noted that if the recommendation for the 25% fee surcharge is agreed this
can only take effect from the 1st of November 2022. 
Additional Options for Charges 
2.27 It is noted that other Local Authorities also charge fees for submitting paper applications
and refunds of planning fees. 
Submitting Paper Applications 
2.28 Currently there are no additional fees payable for the submission of paper applications.
An additional fee for the submission of paper applications would help towards providing
additional revenue to off-set the additional time and resources required when
processing paper applications. Notwithstanding the environmental benefits for further
incentivising the submission of applications electronically it is envisaged that such a
charge is a reasonable cost in relation to the additional time and resource spent
scanning and processing such submissions. 
2.29 It is recommended that the following fees would be commensurate with the time and
resource spent on such submissions: - 
Non-Householder / Local £80 
Major Applications  £180 
Refund Charge 
2.30 Currently we do not charge a fee for processing a refund and it is recommended that a
fee of £10 is deducted to refund requests and the charges will cover the time and costs
associated with such requests. 
Increase in Fees for Property History Search, Decision Notice and Plans 
2.31 Currently the Council charges an initial fee for a history search (first two hours) at
£26.50 and thereafter, each hour £19. A copy of the Decision Notice is charged at
£14.10 in addition to the history search fee. The provision of copies of plans (charge
applies for both paper and electronic copies) is as follows: - 
A4 £0.10 
A3 £0.15 
A2 £0.60 
A1 £0.95 
A0 £1.88 
In addition to £3.20 per 15 minutes of officer time. 
2.32  Should requests be received for a planning history search, a certified copy of the
Decision Notice and/or plans associated with it, then it is recommended that a fee
representing the time and resource spent on providing such a service is reflected in the
overall charge. It is noted that other planning services charge higher fees for such
services already. 
Page 97 of 113

Page 98

2.33 It is recommended that the following fees would be commensurate with the time and
resource spent on such provision: - 
Planning Application History for a Single Property £150 
Certified Copy of Decision Notice   £50 
Certified Copy of Decision Notice including Plans £100 
(Householder, Local and Advert Applications)   
Certified Copy of Decision Notice including Plans £200 
(Major Applications) 
2.34 It should be noted that the decision notice and approved plans for applications received
for at least the last decade are also available to view on the Council’s Planning Portal
for no charge. 
3. Measures of success 
3.1  The proposed additional discretionary planning fees being charged offer additional
resources to give additional financial support to the planning authority and ensure a
well-resourced and efficient planning service is maintained. 
4. Supporting documentation 
4.1 A draft of the likely content of the written advice to be included within the pre-application
response is provided in the attached Annex - (Draft Pre-Application Service
Guidance Document) to this report. 
Pamela Humphries
Head of Planning and Regeneration 
Page 98 of 113

Page 99

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒ 
During the passage of the Planning (Scotland) Bill, draft assessments (EQIA and
CRWIA) were published by the Scottish Government in advance of Stage 3 (June
2019). These assessments did not provide any direct evidence on matters pertaining
to performance or fees 
The consultation undertaken between December 2019 and February 2020 indicated
that the Scottish Government considered that an EQIA, CRWIA, SEA, Fairer
Scotland Duty or an Islands Impact Assessment were not required. 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
The proposed report outlines how the Planning Service can potentially recoup
additional resources by introducing discretionary charges for functions that it currently
carries out for free. The proposed charges represent a reasonable estimation of costs
in relation to officer time and resource in processing these requests. It is anticipated
that the introduction of charging as set out in the report below has the potential to
generate an annual income of £50,000. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact?
Page 99 of 113

Page 100

5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☐ No ☒
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
Page 100 of 113

Page 101

Pre-Application Enquiry Guidance Document
North Lanarkshire Council Planning Service provide a chargeable pre-application advice service. The
benefits of seeking pre-application advice can be summarised as follows: - 
• The advice will identify the relevant local development plan policies and supplementary
planning guidance where relevant and offer the context on how the policies and guidance will
be applied to your proposals. 
• May allow the identification at an early stage of the need for specialist input in terms of
Transportation requirements, Ground Conditions (SI and CMRA), Drainage, Flooding,
Protected Species etc. (we will not be undertaking consultations – see point 3 below) 
• It may flag up unacceptable proposals at an early stage or ones that require significant changes
to be acceptable thus saving the cost of submitting a formal application unlikely to receive a
favourable recommendation. 
• Early pre-application engagement may reduce the timescales for determination of the
application – provided that all matters raised are included within the subsequent planning
application submission. 
• The service is confidential, and no information will appear on the public planning portal. 
Submission Requirements 
SUBMISSION REQUIREMENTS (minimum information required for an assessment to be made)
All dimensions / scales to be shown in metric. 
An ordinance survey-based location plan (scale 1;1250, 1;2500 or suitable scale to outline the 
application site) that outlines the pre-application site in red and any additional land ownership       
outside of the application site in blue.  
Details of the means of access to the site. 
SUBMISSION REQUIREMENTS (additional information to offer the best possible advice)
Site Layout / Block Plan 
Existing / Proposed Elevations 
Existing / Proposed Floor Plans
Site Photographs 
Topographical Plans / Site levels (where site levels are a potential issue)
Design Statement / Design and Access Statement 
It should be noted that the more detailed the information you provide with the pre-application
submission the better and more detailed site-specific pre-application advice it will allow the
Planning Authority to provide. 
Page 101 of 113

Page 102

Cost 
The fee for this service is based on the pre-application type as follows: 
Pre-Application Type Cost
Listed Building Pre-Application Proposals £65
Householder Pre-Application Proposals £65
Single Residential Dwelling Pre-Application Proposal £200
Commercial Developments and Change of Use Pre-Application
Proposals (Maximum Floor Space 500m²
£200
Local Development Pre-Application Proposals (Other than
Householder Developments, Single Houses and Commercial
Developments and Change of Use up to a Max 500m²
£500
Major Development Pre-Application Proposals £1000 
Timescales 
The standard timescale we would expect to deal with your pre-application enquiry would be as follows: 
Pre-Application Type Timescale
Listed Building Pre-Application Proposals 20 Working Days
Householder Pre-Application Proposals 20 Working Days
Single Residential Dwelling Pre-Application Proposal 20 Working Days
Commercial Developments and Change of Use Pre-Application
Proposals (Maximum Floor Space 500m²
20 Working Days
Local Development Pre-Application Proposals (Other than
Householder Developments, Single Houses and Commercial
Developments and Change of Use up to a Max 500m²
30 Working Days
Major Development Pre-Application Proposals 40 Working Days 
It should be noted that some of the more complex cases may take longer to consider and in such
circumstances the case officer will contact you and explain the reasons for delay and try to give an 
indication of the likely timescales for our response. 
Pre-Application Response 
In response to a completed pre-application submission including the required fee the Planning Service 
will provide the following within its response: - 
1. An assessment of the planning merits of the proposals in terms of the development plan and in
particular the relevant North Lanarkshire Local Development Plan Policies and Supplementary
Planning Guidance where relevant. 
2. Detail the submission requirements by identifying where possible the relevant material
considerations to be taken account of in terms of but not limited to: - 
• Roads Infrastructure Requirements, Access and Parking;
• Ground conditions (SI and CMRA); 
• Drainage and Flooding;
Page 102 of 113

Page 103

• Protected Species; 
• Design (Materials, Layout, Landscaping, Topography, Open Space/Play Provision); 
• Impacts on surrounding Residential Amenity in terms of Daylight/Sunlight
(overshadowing), Overlooking (privacy), Scale and Massing (overdevelopment)
• Other such matters that are considered relevant to the determination of the proposals. 
3. Offer general design and layout advice but will not include consultation with internal or external
stakeholders – Advice will be limited to existing Council Design Guidance, Constraints Mapping
and outline requirements such as parking standards, open space and play provision etc. 
4. Highlight any other specific matters of note in relation to the proposals such as EIA
screening/scoping requirements and PAC/PAN requirements if applicable. 
5. The advice will not offer definitive view of the likely outcome as a formal planning application
is still required before a full assessment can be made. Please note that the planning process
includes consulting with internal and external consultees, a site visit, neighbour notification and
advertisement procedures which may result in representations on material planning
considerations not available at the pre-application stage and requires the taking account of any
other material considerations that may arise during the planning assessment process. 
6. The pre-application service does not include provision of a meeting. Meetings may be offered
but only in specific circumstances when the Planning Service considered it necessary to inform
the content of the pre-application response. 
It should be noted while we will make every effort to ensure that any pre-application advice is
as accurate and comprehensive as possible, any advice given by officers in response to a pre-
application advice request does not constitute a formal decision of North Lanarkshire Council
as Planning Authority and is given without prejudice to the determination of a planning
application and any views expressed are not binding and are not intended to prejudice North
Lanarkshire Council’s formal determination of any subsequent planning application. 
Page 103 of 113

Page 104

Page 104 of 113

Page 105

North Lanarkshire Council
Report
Planning Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref DWB/LB Date 13/10/22 
Contract Award – Idox Hosted and Managed Service 
From  Pamela Humphries, Head of Planning and Regeneration  
E-mail bowdenl@northlan.gov.uk Telephone Lorna Bowden
07939280460 
Executive Summary 
Committee is asked to approve the award of a Call-Off Contract for Hosted and Managed
service (the ‘Contract’) to Idox Software Ltd. 
The Call-Off Contract is for an initial period of 60 months anticipated to commence on 1st
November 2022. The Council reserves the right to extend the Contract for additional
periods up to a maximum of a further 24 months. 
The value of the Contract shall not exceed one million two hundred and nine thousand six
hundred and eighty four Pounds Sterling (£1,209,684) exclusive of VAT. 
Recommendations 
It is recommended that Planning Committee approves the award of the Call-Off Contract
to Idox Software Ltd at the maximum value one million two hundred and nine thousand six
hundred and eighty four Pounds Sterling (£1,209,684) exclusive of VAT. 
This recommendation follows the completion of a procurement procedure facilitated via
direct award from Crown Commercial Services Data and Application Solutions framework
– Lot 2b Environmental and Planning. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (18) Ensure our digital transformation is responsive to all people's
needs and enable access to the services they need
AGENDA ITEM 6
Page 105 of 113

Page 106

1. Background
1.1 North Lanarkshire Council have used Idox software since 1996 for the Planning and
Building Standards Services and all other Local Authorities in Scotland now use the
Planning and Building Standards modules that integrate with the national
eDevelopment Portals. The Idox software provides:   
• A case management system, Uniform, including modules for Planning, Building
Standards and Estates and is also used for the Corporate Address Gazetteer (CAG)
in the Gazetteer Management System (GMS) module.  
• An electronic document records management system to support document retention
for Planning, Appeals, Enforcement, and Building Standards.   
• An Estates category is currently in Test and will eventually hold the documents
related to Acquisition/Ownership/Leases and Disposal once they have been
scanned.   
• Uniform is closely tied into our use of the online Scottish Planning Portal which gives
the public 24/7 access to online planning services. 
• A public access portal provides Planning and Building standards registers on the NLC
website, receiving over 61,000 searches per month, and also offers the public a place
to submit comments on planning applications.  
1.2 Some of the requirements within the Call-Off Contract are currently under contract with
Idox Software Ltd. This contract for support and maintenance only is due to expire on
31st March 2023. There is an overlap in the new contract award to allow for the
transition to cloud-based system. 
1.3 The National Framework for the supply of Data and Application Solutions, established
by Crown Commercial Services on behalf of the UK public sector, went live on 22nd
February 2019. The Council is utilising this Framework by conducting a direct award to
deliver a Call-Off contract for our new Social Care Case Management Solution. 
2. Report 
2.1 A user intelligence group (the ‘UIG’) of technical and procurement representatives was
formed to review technical specifications, discuss trading processes, market conditions
and trends, ways to maximise community benefits and sustainability and to agree the
procurement strategy that would deliver maximum benefit for the Council via the Call-
Off Contract. 
2.2 The initial estimated value of the Call-Off Contract dictated that the procurement
procedure be undertaken in accordance with the Public Contracts (Scotland)
Regulations 2015. 
2.3 The procurement procedure was undertaken as a “Direct Award” from the Crown
Commercial Services framework agreement for Data and Application Solutions
RM3821 Lot 2b Environmental & Planning. 
2.4 The Call-Off Contract award recommendation is made on the basis of an intelligent
market search via Crown Commercial Services Digital Marketplace. 
2.5 The tender(s) submitted by Idox Software Ltd has been evaluated as representing best
value by the Council by analysing scope, service delivery, cost analysis, efficiency
savings and available budget. 
Page 106 of 113

Page 107

2.6 Further details of the procurement procedure is provided in Appendix 1 and the SME
status and location of all tenderers is located within Appendix 2. 
2.7 The value of the Contract is one million two hundred and nine thousand six hundred
and eighty four Pounds Sterling (£1,209,684) exclusive of VAT, including any option to
extend. 
2.8 The costs associated with contract delivery will be contained within the Revenue budget
for Enterprise and Communities - Planning and Place, Built Environment, Asset and
Procurement, and NL Properties. The onboarding cost will be contained within the
Capital Budget of Business and Digital 
Price Savings / Increases 
2.9 The Call-Off Contract will result in increased revenue costs for the services. 
The hosting and managed service will result in an increase off £103,359 per annum
above the current £65,403.13 support and maintenance contract. This increase costs
will enable services to: 
• Retain current levels of service; 
• Improve system uptime;    
• Reduce NLC IT and technical resources required to support the applications; 
• Reduce dependence on specialist knowledge and systems including Oracle
and Citrix; and 
• Address issues of connectivity and performance for remote working. 
The costs to each service will be as follows: 
Planning and Place  £64,129.56 
Built Environment  £64,129.56 
Asset and Procurement £20,251.44 
NLProperty   £20,251.44 
Price Stability 
2.10 The Call-Off Contract will establish fixed costs for the term of the contract enabling the
services greater certainty on cost for the provision of the software, future upgrades and
support and maintenance costs 
Community Benefits 
2.11. The procurement did not include a community benefit requirement as the framework
only permitted inclusion of community benefits via mini-competition procurement
procedure. As part of contract supplier management the supplier will be approached to
derive unofficial community benefit.   
Fair Work First  
2.12 Within their framework submission, IDOX advised that they will commit to the following
areas of the Scottish Government’s “Fair Work First” initiative: 
• Appropriate channels for effective voice;
• Investment in workforce development;
Page 107 of 113

Page 108

• No inappropriate use of zero hours contracts;
• Action to tackle the gender pay gap and create a more diverse and inclusive workplace;
• Payment of the real Living Wage;
• Offer flexible and family friendly working practices for all workers from day one of
employment; and
• No use of fire and rehire practice. 
Contract Strategy 
2.13 Officers from Business Development and Support will be responsible for managing the
Contract which will be undertaken in accordance with the Council’s agreed approach
to contract and supplier management. 
3. Measures of success 
3.1  The Call-Off Contract will deliver the following outcomes; 
• A compliant appointment in line with the procurement legislation, Crown Commercial
Services Framework Terms & Conditions and internal procedures.
• Quicker and more stable connection to case and document management systems.
• Improved uptime of case management system.
• Reduction in unplanned outages   
4. Supporting documentation 
Appendix 1 Summary of Procurement Process
Appendix 2 SME Status and Location of All Tenderers 
Pamela Humphries
Head of Planning and Regeneration 
Page 108 of 113

Page 109

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Services will have increased revenue costs in place of the current support and
Maintenance contract. 
Business and Digital will pay the onboarding costs from Capital and there are no
direct savings from revenue.
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☒ No ☐ 
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject? 
Yes ☒ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
Page 109 of 113

Page 110

5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
The Contract will result in migration of software and data to a hosted and managed
service. Access to that service will require installation of a citrix client to service
users devices. The service will also result in removal of on premises server, and a
reduction in the support required from Business and Digital to deliver patching,
upgrades and security testing and support. 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☒ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
Risk Description  Impact
H/M/L 
Mitigation Description 
Service delivery – if support and maintenance
is not renewed then there would be significant
impact on the service delivery should there be
a system or hardware failure 
H  Ensure replacement contract is in place for
31st March 2023 
Improvements in remote access will not be
realised. 
M  Reduce remote working 
Reduction in planned and unplanned
downtime is not realised 
M  Appropriate Contract Supplier Management
and performance appraisals. 
Current support and maintenance is provided
by service team (Alex Hamilton/ David
Baxter), NLC IT (Application Support Team B)
and the IDOX service desk.    
There is a risk that unplanned incidents may
occur if specialist resource detailed above
from the service team or Business and Digital
is unavailable. Unplanned downtime may
result in longer service disruption. 
M  To ensure unplanned incidents are
minimised support calls should always be
evaluated and prioritised using the service
desk grading (P1, P2, P3 etc.) 
Training should be provided as required to
service and service desk staff to ensure
they are fully aware of how this process
works. 
Page 110 of 113

Page 111

Front line staff should also be provided
training in how to log calls and also to
increase the awareness of what’s involved
in completing key activities including user
acceptance testing following any planned
outages. 
By continuing with the current support model
there is a risk of delay in upgrades and issue
resolution as internal resources and expertise
are scheduled or consultancy procured. 
M  All requests for updates/upgrades should
by default follow NLC’s ICT Change
Management processes and timelines to
ensure the required technical and
governance support is available to match
the timeline and expectations of the
service. 
Page 111 of 113

Page 112

Appendix 1 – Summary of Procurement Process 
Response
Procurement Procedure Utilised: Direct Award
Governing Legislation / Regulations: Public Contracts (Scotland) Regulations
2015
Date Call-Off Contract Strategy Approved: 02 September 2022
Number of Companies Invited to Take Part:  1
Tender Return Deadline: 30th September 2022
Number of Tenders Received: 1
Where Only One Tender Is Received, Why?: Direct Award Procurement Procedure 
Tenders Received from SME’s: 0
Tenders Received from NLC Based Tenderers:  0
Number of Recommended Tenderers: 1
Evaluation Team: Members of Business Solutions &
Planning
Anticipated Call-Off Contract Start Date: 01 November 2022
Total Call-Off Contract Period (Months): 60 + 12 + 12
Maximum Total Call-Off Contract Value: £1,209,684 
Page 112 of 113

Page 113

2 – SME Status and location of all Tenderers 
Name of Tenderer
Size of Tendering
Organisation
(Micro, Small,
Medium or Large)
Location
(Local Authority /
Council Area)
IDOX Software Ltd  Large Reading Borough
Council 
Page 113 of 113