North Lanarkshire Council
Report
Planning Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref  Date 30/06/22 
North Lanarkshire Local Development Plan Update and
Development Plan Scheme 2022 
From  Pamela Humphries, Head of Planning and Regeneration  
E-mail laingg@northlan.gov.uk Telephone 07970018874 
1. Background 
1.1 Members will be aware that the Development Plan for North Lanarkshire is at Adoption
stage and that the Planning (Scotland) Act 2019 introduced a new system of
Development planning for Scotland. Consultations were carried out in relation to
National planning Framework 4 (NPF4) and Local Development Plan (LDP)
Regulations and Guidance in late 2021 into spring 2022. These contained significantly
more detailed requirements than in the Act and to date and the Government is currently
considering responses to the consultation with a view to publishing modified proposals
later this year. 
1.2 The Council published a Development Plan Scheme in April 2021 which took account
of the available information on the implementation of the Act and laid out an indicative
timeline accordingly. In accordance with current legislative requirements and
considering the current position with each of these factors a revised Development Plan
Scheme has now been prepared for publication. 
Executive Summary 
The purpose of this report is to update members on the preparation of the North
Lanarkshire Local Development Plan and agree the Development Plan Scheme 2022,
which details the revised timetable for the Plan. 
Recommendations
It is recommended that Committee note the contents of the report and agrees the North
Lanarkshire Local Development Plan Development Plan Scheme 2022. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (5) Grow and improve the sustainability and diversity of North
Lanarkshire's economy

Page 2

2. Report 
Modified Proposed Plan 
2.1 Following publication of the Report of Examination of the Modified Proposed North
Lanarkshire Local Development Plan and in accordance with decisions of the Planning
Committee in November 2021 the Plan Intended for Adoption was submitted to the
Scottish Government on 31st March 2022. The Government has formally extended the
period for consideration twice, to 22nd June 2022. 
North Lanarkshire Local Development Plan Development Plan Scheme 2022 
2.2 The North Lanarkshire Local Development Plan Development Plan Scheme is attached
at Appendix 1 and sets out annually the stages and timetable being followed to deliver
the Local Development Plan. The 2022 Scheme has been updated to reflect the time
taken to complete previous stages and the expected timescales for the remaining
stages in the plan process, with Adoption of the Local Development Plan expected in
summer 2022. The Scheme also incorporates the North Lanarkshire Council Local
Development Plan Stakeholder Engagement Strategy which will form the basis of a
new Participation Statement and Engagement Strategy for LDP2. 
2.3 There remain significant material uncertainties around crucial legislative, regulatory
and strategic obligations and considerations. Although these impact directly on the
Council’s ability to prepare a detailed Scheme for the preparation and delivery of the
next LDP the section relating to LDP2 has been updated to reflect information
contained in Government consultations on NPF4 and the LDP Regulations and
Guidance. Based on our understanding of the changes outlined above, delays in
Adopting NPF4 and LDP Regulations and an assessment of the likely timescales to
carry out this work undertaken by Heads of Planning Scotland this includes information
on
• Status of existing Plans, Policies, Strategies and legislation that affect the LDP
process
• North Lanarkshire LDP2 Process
• North Lanarkshire LDP2 Indicative Timetable to adoption potentially in 2027   
3. Measures of success 
3.1  The long-term aim of the Plan is to increase sustainable growth and regeneration, and
to improve places in support of our Corporate Vision. The Plan looks to achieve this
through policies used to determine applications for planning permission 5.2 
3.2 In particular the Plan will support delivery against the Improving economic opportunities
and outcomes priority and provides the policy framework through which the Economic
Regeneration Delivery Plan can deliver against the land use aspects of the Council’s
Ambition, including 
• Housing regeneration/ re−provisioning 
• Town Centre Regeneration 
• Business and Industry 
• Infrastructure development   
4. Supporting documentation 
North Lanarkshire Council Development Plan Scheme 2022

Page 3

Pamela Humphries
Head of Planning and Regeneration

Page 4

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☐ No ☒
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact?

Page 5

Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☐ No ☒
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed?

Page 6

1 
Appendix 1 
NORTH LANARKSHIRE COUNCIL
LOCAL DEVELOPMENT PLAN 
DEVELOPMENT PLAN SCHEME 
June 2022 
North Lanarkshire Council
Planning and Regeneration

Page 7

2 
CONTENTS        Page 
1 Introduction         2 
2 The Statutory Development Plan      2
For North Lanarkshire 
3 Local Development Plan        4             
4 Local Development Plan Timescales     5 
5 North Lanarkshire Local Development Plan    7   
6 North Lanarkshire Local Development Plan 2    8 
7 Participation Statement & Engagement Strategy    13         
8 Contacting the Development Plan Team    13         
North Lanarkshire Council Local Development Plan
Stakeholder Engagement Strategy     14

Page 8

3 
1 Introduction
North Lanarkshire Council is required to publish a Development Plan Scheme that sets out the programme for
preparing and reviewing Development Plans, and what is likely to be involved at each stage. 
It must be updated annually and include: 
- A programme for preparing and reviewing the Local Development Plan;
- Set out what is likely to be involved at each stage;
- A Participation Statement setting out when, how and with whom consultation on the plan will take
place;
- The authority’s proposals for public involvement in the plan preparation process. 
The Development Plan Scheme for North Lanarkshire was first published in April 2011. 
The Council was unable to prepare a 2020 Development Plan Scheme, owing to adjustments introduced in
response to Covid-19, not least the move to remote working and initial suspension of Committee consideration
of non-application matters, along with the need to concentrate resources on preparations for the Modified
Proposed Plan Examination. In addition, Covid-19 led to the Scottish Government pushing back implementation
of key elements of the Planning (Scotland) Act 2019, resulting in continuing material uncertainty and delay. 
2 The Statutory Development Plan for North Lanarkshire 
Development Plans set out policies and proposals for the future development and use of land in our towns and
countryside; where development should, or should not, happen and how development affects its surroundings.
They are the basis for decision making on planning applications. 
They consider a wide range of land use matters including economic development and infrastructure, retail and
town centres, housing and community facilities and the natural and built environment with a view to creating
high quality, sustainable places. 
The current Development Plan for North Lanarkshire consists of the Clydeplan Strategic Development Plan,
the North Lanarkshire Local Plan and a suite of Supplementary Planning Guidance notes. These are
informed by the National Planning Framework for Scotland. 
Supplementary Planning Guidance (SPGs)
North Lanarkshire Local Plan (NLLP) 
Clydeplan Strategic Development Plan (CSDP) 
National Planning Framework for Scotland (NPF)

Page 9

4 
The National Planning Framework for Scotland is produced by the Scottish Government and sets out, in
broad terms, the Scottish Ministers’ strategy and priorities for Scotland’s spatial development. National
Planning Framework 3, came into effect in June 2014. NPF 4 is expected to be Adopted in late 2022. 
The Clydeplan Strategic Development Plan is prepared by the 8 constituent councils that make up the
Glasgow and the Clyde Valley Strategic Development Planning Authority and sets out a long-term Spatial Vision
and Spatial Development Strategy for the wider Glasgow city-region until 2036. It was Approved by Scottish
Ministers on 24 July 2017 
The North Lanarkshire Local Plan was prepared by North Lanarkshire Council and sets out more detailed
policies and proposals to guide development in North Lanarkshire over the next 5 – 10 years. It was Adopted
on 28 September 2012. 
Supplementary Planning Guidance notes prepared by North Lanarkshire Council provide more detailed
guidance on specific issues. There are currently 30 adopted Supplementary Planning Guidance Notes for North
Lanarkshire. 
3 Local Development Plan 
The North Lanarkshire Local Development Plan will replace the North Lanarkshire Local Plan. It will contain a
spatial strategy, proposals map, action programme for identified developments and schedule of the local
authority’s land interests affected by Plan policies or proposals. It will focus on specific proposals for the period
up to Year 10 from Adoption. 
The Local Development Plan will be integrated with Council and Partner statutory plans and strategies affecting
the development of land. It will take account of the National Planning Framework and be consistent with its
relevant Strategic Development Plan and other plans, including The Community Plan and Local Housing
Strategy. 
Statutory and other Assessments of The North Lanarkshire Local Development Plan 
The Local Development Plan is required to include the following: 
- A Strategic Environmental Assessment (SEA) – a process of scoping potential  environmental
impacts resulting from future Local Development Plan development strategy, policy or proposals.  This
will be carried out in conjunction with Scottish Environmental Protection Agency, Scottish Natural
Heritage and Historic Scotland. 
- Equality Impact Assessment (EqIA) (North Lanarkshire Local Development Plan’s incorporates a
Human Rights Impact Assessment and the Health Impact Assessment (HIA)  – a process for ensuring
that Local Development Plan strategy, policy or proposal address potential impacts on disadvantaged
individuals or groups and assessing them against broader impacts on health and wellbeing. 
- Habitats Regulations Appraisal Record  – a process for assessing Local Development Plan strategy,
policies and proposals against potential impacts on Natura 2000 sites and set out potential mitigation.

Page 10

5 
4 Local Development Plan Timescales 
The intended timescales for preparing the Local Development Plan, together with accompanying Strategic
Environmental Assessment are laid out below 
Local Development Plan Process Strategic Environmental
Assessment (SEA) Process 
Timeline 
Development Plan Scheme
Participation Statement 
Updated Annually   
Call for Sites (CfS)
Parameters Engagement 
Call – 10 weeks 
July-Sept 2013   
Main Issues Report  (MIR)
Pre-MIR Analysis & Engagement
Monitoring Statement &
Main Issues Report 
SEA Scoping  2014
Jan-May 2015
Main Issues Report
Report on Responses and  
Site Options Consultation 
Draft Environmental Report
April 2016 
Consultation on MIR Outcomes - 8 weeks Apr 2016 
Proposed Plan 
Proposed Plan Document & Maps
Additional Consultation
Key Agencies/Partners/
Infrastructure Providers
Jan 2017
Environmental Report to SEA
Gateway 
Proposed Plan Consultation – 7 weeks Mar 2017   
Modified Proposed Plan Modified
Plan Document & Maps
Planning Sub Committee 
Approval 
Sep 2018 
Additional Consultation
Key Agencies/Partners/
Infrastructure Providers
Jan 2019
Environmental Report to SEA
Gateway 
Feb-April 2019   
Modified Plan Consultation – 8 weeks          Feb-April 2019   
Examination Preparation
Submit Plan (Schedule 4s)
Proposed Plan Document & Maps
Action Programme 
July 2020

Page 11

6 
Local Development Plan Process Strategic Environmental
Assessment (SEA) Process 
Timeline 
Examination – Outwith Council Control  
Commenced 20th October 2020       
Further Information Requests  2020/21
Report of Examination May 2021   
Adoption process
Submit Plan for Adoption  Amend Environmental Report  March 2022
Formal Adoption  2022 
Post Adoption Environmental
Report
2022   
5 North Lanarkshire Local Development Plan 
Local Development Plan Process 
The Council undertook a 10-week Call for Sites in 2013, during which some 175 sites were promoted. A Main
Issues Report (MIR) was published in March 2015 outlining key changes affecting North Lanarkshire since
Adoption of North Lanarkshire Local Plan in 2012, covering the Council’s preferred options for development in
North Lanarkshire and alternative development strategies and sites. 45 additional sites were introduced during
the 11-week consultation period, making a total of 220 sites submitted for consideration. In April 2016, the
Council approved a Report on the outcomes of the Main Issues Report and the Urban Boundary Review,
outlining which of the 220 sites were likely to be included wholly or in part in any forthcoming Plan. 
The Proposed Plan was approved in August 2016 and published in January 2017 for a 7-week consultation
period, containing the Council’s final proposals and policies. Engagement stage included the opportunity to
submit formal objections and for those objections to ultimately be determined through an Examination held by
Scottish Government Reporters. 
All development site owners / occupiers / neighbours were notified and a schedule of proposals affecting land
in Council ownership was prepared. The Proposed Plan and associated documents resulted in some 1,594
representations being received. 
Local Development Plan Modified Proposed Plan, Examination & Adoption 
The Development Plan Scheme February 2018 outlined the Council’s intention to prepare a Modified Proposed
Plan, in light of the Scottish Ministers’ decision to Approve the Clydeplan Strategic Development Plan being
subject to Legal Challenge, which concluded in March 2018. The Modified Proposed Plan updated the Plan and
afforded a further opportunity to anyone who wished to make comment/objection through an 8-week period of
consultation that ended in April 2019. 
407 contributions were received during that consultation period and these were validated, acknowledged and
categorised in order to derive the necessary documentation for unresolved issues (objections) to be sent for
Examination by Scottish Government Reporters, along with the Modified Proposed Plan. The Examination
formally began on 20 October 2020 and is expected to take 6-9 months 
The Plan includes all relevant land-use strategies, policies, development proposals and maps. It is available on
the Council website.
Completed Stages

Page 12

7 
It contains: 
A vision statement for North Lanarkshire setting out how development of the area could be undertaken and
what it might look like.   
A spatial strategy incorporating a detailed statement of policies and development proposals for the area to
achieve the vision. 
A long-term sustainable settlement strategy is included that will meet Council needs, priorities and aspirations,
with details of Infrastructure requirements related to planned growth. 
Supplementary Guidance 
The Plan has a focus on vision, spatial strategy, overarching and other key policies and proposals. Detailed
material associated with the development strategy will be contained in supplementary guidance.  Changes
brought in by the Planning (Scotland) Act 2019 will affect the Council’s ability to produce Supplementary
Guidance, as the Section 9 of the 2019 Act, on commencement, removes any provisions for preparing and
adopting statutory Supplementary Guidance. This may have an impact on the contents of future Local
Development Plans. 
Action Programmes 
A Local Development Plan Action Programme has been prepared to assist in delivering the Plan’s objectives. It
includes: 
- list of actions required to deliver each of the Plan’s policies and proposals 
- names of parties responsible for each action 
- timescale for implementation 
The Action Programme accompanied the Modified Proposed Plan to Examination. It will be confirmed within 3
months of Plan Adoption, reviewed and updated every 2 years. 
Examination and Adoption 
As outlined, Examination of the Modified Proposed Plan commenced on 20th October 2020. The Report of
Examination was published in May 2021 
The report deals with 35 unresolved issues identified by the Council and recommends changes in both the
presentation and content of some policies within the North Lanarkshire Local Development Plan Modified
Proposed Plan documents. 
Of particular note in the are:- 
• Merging of all Guidance sections into Policy 
• A replacement PROM LOC3 Policy on Promoting Housing Development Sites 
• Replacement of the Housing Land Requirements Appendix and substitution of the 2019 Housing Land Audit
sites for the 2017 Housing Land Audit Sites 
• A replacement section in Policy PROM ID2 Utilities Improvements on Renewable Energy 
In addition to these Recommended changes the Council received a letter in August 2021 from the DPEA
confirming that any changes required because of the Recommendations made by the Reporters should also be
made. In accordance with the Regulations a number of further changes of a grammatical, typographical or
factual nature have also been made to the text within the Policy Document. 
Following in-depth analysis of the Recommendations, and consequential changes and amendments, there is
only one instance where the Council is seeking to depart from the Recommendations. This is in respect of the
Reporters’ Recommendations at Issues 010 and 012. These Recommendations are contradictory in that they
call for the designation of different numbers of Commercial Centres under a description which does not apply
to them all.

Page 13

8 
The Plan Intended for Adoption was submitted to the Scottish Government in March 2022. Adoption is expected
in summer 2022. 
6 North Lanarkshire Local Development Plan 2 
Implications of the Planning (Scotland) Act 2019 
The Planning (Scotland) Act 2019 introduces significant and far reaching changes to the development planning
system in Scotland. A “Purpose for Planning” which makes provisions for the Development Plan to manage the
development and use of land in the long-term public interest, contributing to sustainable development and
achieving national outcomes. 
The Act changes the current hierarchy of plans by enhancing the status of the National Planning Framework
(NPF) merging it with Scottish Planning Policy (SPP) to produce a high level plan for Scotland which, amongst
other things, sets out how the Scottish Ministers consider development will contribute to achieving the National
Outcomes, sets out targets for housing and identifies national developments. This statutory document is to be
prepared by the Scottish Ministers and reviewed every 10 years, rather than every 5 years which is the current
requirement. 
The requirement for the preparation of strategic development plans (SDPs) is removed and instead introduces
the requirement for planning authorities, working alone, or in partnership with two or more planning authorities
to form strategic partnerships, to prepare and adopt a Regional Spatial Strategy. A planning authority must
adopt a regional spatial strategy as soon as practicable after this part of the Act comes into force and the
Government has the power to direct planning authorities to prepare and adopt such strategies. 
Regional Spatial Strategies will inform the NPF and Local Development Plans (LDPs). The NPF and Local
Development Plans are to be prepared at least every 10 years rather than every 5 years. 
The requirement for the production of a Main Issues Report (MIR) for Local Development Plans is removed and
replaced with an Evidence Report. The Evidence Report will require to be examined by an independent Reporter
at the start of the plan process who will then decide if the information in the report is sufficient for the Planning
Authority to start preparation of the Local Development Plan. 
A further significant change is the introduction of the right for communities to come together and prepare Local
Place Plans (LPPs). Before preparing a Local Development Plan, a Planning Authority must invite local
communities in their district to prepare LPPs, stating the date by which they must be prepared and details of the
assistance available for local communities to prepare LPPs. In preparing its LDP the planning authority must
have regard to LPPs. 
Other changes introduce requirements for Development Plans introduced by the Act include the carrying out of
Play Sufficiency Assessments, preparation of Open Space Strategies to inform the LDP. Additionally, on
commencement of Section 15 of the Act, it will be required to gather evidence and prepare policies and
proposals on subjects new to land use planning, including the provision of water refill locations and public
conveniences, as well as making informed statements on matters relating to health, education and cultural
venues. There remains no guidance, or indication as to how these tasks are to be carried out and how they
relate to the policies and proposals of the authorities responsible, often statutorily, for these matters. The Act
also removes the ability for Planning authorities to prepare and publish Statutory Supplementary Planning
Guidance in support of a LDP. 
The provisions of the Act affecting Development Plans have not been commenced to date and the Government
intends to consult on regulations on these matters throughout 2021 making it difficult to be precise regarding
the timetabling of the preparation of the next Local Development Plan. 
LDP 2 
North Lanarkshire Council is already considering the processes and project planning required to deliver its
second Local Development Plan. However, there remain significant material uncertainties around crucial
legislative, regulatory and strategic obligations and considerations that impact directly on the Council’s ability to
prepare appropriately. These include the

Page 14

9 
• Planning (Scotland) Act 2019 Implementation Timetable
o LDP Implications
o DM Implications to be included in LDPs
• Local Development Planning Regulations
o Timetable
o Contents
• National Planning Framework 4 and Scottish Planning Policy
o Timetable
o Contents
o Applicability to Development Planning
o Delivery strategy
• Regional Spatial Strategy
o Timetable
o Contents
o Status in Development Planning 
Based on our understanding of the changes outlined above and an assessment of the likely timescales to carry
out this work undertaken by Heads of Planning Scotland the following tables have been prepared outlining the
range of Plans, Policies, Strategies and legislation that affect the LDP process, the process of developing and
an indicative timetable for production of LDP2.

Page 15

10 
Local Development Plan and Related Strategies & Polices, Lead Authorities and Current Status 
Plan and related Strategies & Policies Lead Current Status
North Lanarkshire Local Development
Plan (Modified Plan) 
NLC Plan Intended for Adoption submitted to Scottish Government in March 2022. Adoption expected in late
2022.
National Planning Framework 4
(NPF4) incorporating Scottish
Planning policy (SPP)
SG Government laid the draft NPF4 in the Scottish Parliament in December 2021 with public consultation at
that stage. The responses are now being assessed with a revised NPF4 expected
in mid to late 2022 with Adoption thereafter.
Regional Spatial Strategy (non-
statutory)
GCR -
Clydeplan
Revised Indicative RSS submission April 2021. Final RSS 2022 following NPF4 Adoption.
Local Place Plans  Communit
ies
Regulations in force from January 2022. Awaiting LDP Regulations to advertise for expressions of interest
as per legislation.
Open Space Strategy  NLC Consultation on Regulations completed March 2022.
Regulations expected Autumn 2022.
Other Strategies (incl. Local Housing
Strategy, Transportation Strategy,
The Plan for North Lanarkshire, City
Region City Deal, City Region
Economic Strategy)
NLC and
Partners
A range of NLC and Partner Strategies at various stages of development, some of which have statutory
links to the Local Development Plan (e.g. Local Housing Strategy)
North Lanarkshire Local Development
Plan 2:
• Evidence Gathering process
• Gatecheck 
• Call for Ideas
• Draft Plan preparation and
consultation 
• Submission and Examination
• Adoption 2027 at earliest 
NLC Draft Local Development Plan Regulations and Guidance were consulted upon concurrently with NPF4.
Regulations are expected to be commenced following Adoption of NPF4 (likely late 2022). Subject to the
timing and content of the regulations this is a potential timetable
• Evidence Gathering starts in 2022 and continues in 2023 (HoPS estimate this will take a year)
• Gatecheck process 2024 (HoPS estimate this will 44 weeks) 
• Call for Ideas replaces Call for Sites and has moved to the post Gatecheck stage in draft regulations 
• Draft Plan preparation 2025 and consultation early 2026 (HoPS estimate 48-week process)
• Submission 2026 and Examination 2026/27 (HoPS estimate 1-year process)
• Adoption 2027 (HoPS estimate 16-week process) but this process is proposed to change in Draft
LDP Regulations

Page 16

11 
North Lanarkshire LDP2 Process 
Adoption
Recieve Report of Examination Assess RoE and Prepare Adoption Plan
Submission and Examination
Assess Consultation Responses
Agree non-material amendments
and Schedule 4 responses at
Committee
Submit for Examination
Draft Plan preparation and consultation
Prepare Plan based on Gatecheck
Outcome and Call for Ideas Agree Plan at Committee Publish and Consult
Call for Ideas
Set Call for Ideas Parameters Carry out Call for Ideas
Gatecheck
Compile Evidence Submit to Reporters Gatecheck 'Discussion' Gatecheck outcome
Implications of National Planning Framework 4 (NPF4) incorporating Scottish Planning policy (SPP) Regional Spatial Strategy (non-statutory), Local
Place Plans other legistlation and Strategies, Land Supply Requirements, Economic and environmental circumstances
New requirements of Planning Act including
Health and education needs and the effect of development on them and cultural venues planning
Policies and proposals on
public conveniences, water refill locations
Evidence Gathering process

Page 17

12 
NLLDP2 
Indicative Timetable   
2022 2023 2024 2025 2026 2027
Evidence Gathering process 
Gatecheck  1 year   
Call for Ideas  12
wks   
Draft Plan preparation      36 wks   
Draft Plan consultation      12
wks  
Assess Responses and Submission       24 wks  
Examination      36 weeks 
Adoption  16
wks 
SEA  SEA Scoping Consult with Key
Partners and Agencies
Draft Environmental report Consult with Key Partners
and Agencies
Environm
ental
report 
Post
Adopti
on ER

Page 18

13 
7 Participation Statement & Engagement Strategy 
The Participation Statement aligned with the Development Plan Scheme was published as a stand-alone
document along with the Engagement Strategy and is attached below for reference. In light of the expanded
range of previously considered non-planning “responsibilities” and taking account of the new sections 16A and
16B of the Act, the Council will have to review its Participation Statement and Engagement Strategy accordingly
following commencement of those parts of the Act. 
The Participation Statement and Engagement Strategy for the Local Development Plan, along with the most up
to date Scottish Government requirements, guidance and advice will form the basis of a new Participation
Statement and Engagement Strategy which will be incorporated in future Development Plan Schemes. 
Stakeholders, including the wider public, have an important role in shaping their Plan. The Council’s
Engagement Strategy will guide engagement for the North Lanarkshire Local Development Plan 2 and will set
out when, how and with whom consultation on the plan will take place, and the Council’s proposals for public
involvement in the plan preparation process. 
The Strategy will be updated regularly throughout the process and can be accessed through the Council’s
website. 
The Council is committed to engaging with communities in line with the National Standards on Community
Engagement: 
Relevant Parties for Engagement 
These are detailed in the relevant documents but are outlined below. The following stakeholders are Key
Agencies, have geographical or strategic planning association with North Lanarkshire, are community or
residents’ groups, or may be expected to have an interest in the North Lanarkshire Local Development Plan. 
• Key Agencies;
• Public sector organisations
• Partner Organisations
• Special Interest & Representative Organisations
• Community & Representative Organisations
• Members of the Public
• Private Sector Organisations
• Special interest & representative organisations
• Private sector organisations 
8 Planning and Regeneration Service Contact Details 
Online:   www.northlanarkshire.gov.uk 
By Email: ESNLLDP@northlan.gov.uk 
By Mail:  Enterprise & Communities 
Planning and Regeneration  
North Lanarkshire Council
Civic Centre
Motherwell 
By Phone: 01236 632622

Page 19

14 
NORTH LANARKSHIRE COUNCIL
LOCAL DEVELOPMENT PLAN 
STAKEHOLDER ENGAGEMENT STRATEGY 
North Lanarkshire Council
Planning and Regeneration

Page 20

15 
NORTH LANARKSHIRE COUNCIL LOCAL DEVELOPMENT PLAN
STAKEHOLDER ENGAGEMENT STRATEGY
INTRODUCTION
1. The North Lanarkshire Local Development Plan will be the key
document which sets the land use framework for North Lanarkshire. 
2. The North Lanarkshire Local Development Plan is a land use policy
document which has a significant influence on what is built on or
what uses can be undertaken on land in North Lanarkshire. It does
this by allocating sites for specific land uses such as housing,
retailing, business and industry or developments such as schools,
health centres and waste management facilities and by including
policies designed to promote the economic, social, physical and
environmental well being for North Lanarkshire. It therefore affects
everyone who lives in, works in or visits North Lanarkshire. 
3. The North Lanarkshire Local Development Plan will replace the
current adopted North Lanarkshire Local Plan. The first North
Lanarkshire Local Development Plan is planned for adoption in
2017. 
4. We are committed to preparing the Council’s first North Lanarkshire
Local Development Plan on the basis of genuine engagement with
a broad range of stakeholders and this Strategy sets out how we will
achieve this. 
5. The Council is required to publish a Development Plan Scheme that
sets out the programme for preparing and reviewing Development
Plans, and what is likely to be involved at each stage. The
Development Plan Scheme must be updated annually and will be
published alongside the Participation Statement which in turn sets
out when, how and with whom consultation on the plan will take
place and the Council’s proposals for public involvement in the plan
preparation process. 
6. Engagement with a broad range of stakeholders is an important part
of the production of the North Lanarkshire Local Development Plan.
However although important, the outcome of this is only part of the
evidence base upon which decisions are made. 
7. It is intended this Strategy and the Participation Statement will
ensure that the outcome of engagement undertaken throughout the
Local Development Plan process and its role in the decision making
process is clearly understood and any decisions taken are made in
a transparent way. 
HOW DOES THE STAKEHOLDER ENGAGEMENT STRATEGY
WORK?
8. The purpose of the Strategy is to set the background and outlines
the Strategy’s objectives to support and improve the effectiveness
of engagement with stakeholders by providing guidance for Council
staff and a clear explanation for stakeholders who will be engaged,
when and how and also what engagement has happened so far in
the preparation of the North Lanarkshire Local Development Plan. 
9. The Participation Statement will be updated regularly throughout the
preparation of the North Lanarkshire Local Development Plan to
provide an up to date position on the Councils progress and to
respond to issues as they arise. 
10. The use of ‘we’ within this strategy refers to the Development Plan
Team within the Council’s Planning and Regeneration Service. We
are responsible for the preparation of the North Lanarkshire Local
Development Plan on the Council’s behalf, for approval by the
elected members.

Page 21

16 
LEGAL CONTEXT
11. The Stakeholder Engagement Strategy is about making a complex
statutory process accessible to stakeholders so that they can
influence its policies. It is not about focussing on technical details.
However, every element of the Plan’s preparation is influenced by
legislation and policy guidance. 
12. The preparation and adoption of the North Lanarkshire Local
Development Plan is a legal process and it is important to be aware
that:
• The North Lanarkshire Local Development Plan is a statutory
document the Council is required by law to prepare. The Town
and Country Planning (Scotland) Act 1997, as amended by the
Planning etc (Scotland) Act 2006 requires Council’s to prepare
a development plan for their area. These plans must be updated
every five years. 
• The process of preparing the North Lanarkshire Local
Development Plan is also determined by law. The Town and
Country Planning (Development Planning) (Scotland)
Regulations 2008 provides the detail for the preparation and
publication of local development plans and in particular provides
a minimum set of requirements for consultation and publicity of
local development plans. 
13. In addition to legislation, the Council is also required to observe a
number of policies and advice documents prepared by the Scottish
Government. These take the form of:
• National Planning Framework 3
• Scottish Planning Policy
• Planning Advice Notes, Guides, Letters from the Chief Planner;
and
• Circulars (including the Planning Series Circular 6/2013:
Development Planning) 
14. Planning Advice Note 3/2010 Community Engagement provides
advice to communities on how they can get involved as well as
advising planning authorities and developers on ways of effectively
engaging with communities on planning matters. The Planning
Advice Note 3/2010 also links directly with the National Standards
for Community Engagement. The Standards set out best practice
principles for the way that councils and other public bodies should
engage with communities. 
15. Planning Aid Scotland has produced SP=EED (Scottish Planning
equals Effective Engagement and Delivery) as a practical guide to
effective community engagement in planning.  This Strategy has
been produced to be in line with this guide. 
STAKEHOLDERS AND EFFECTIVE ENGAGEMENT
16. Throughout this Strategy the terms ‘stakeholder’ and ‘communities’
are interchangeable. They refer to any person, group or organisation
that has an interest in, could be affected by or could affect the North
Lanarkshire Local Development Plan. 
17. Stakeholders could be individual residents, neighbourhoods,
community groups, businesses, landowners, developers, parents,
government organisations, and people with disabilities or special
interest groups. 
18. When talking about engagement, we are referring to actions or
processes that enable stakeholders to be aware of, or be involved
in the Local Development Plan process and then use their input to
make more informed decisions. 
19. Substantial changes have been made recently to Scotland’s
planning system. As part of this modernisation, there has been a
wider push for earlier and more effective engagement. 
20. In order for engagement to be effective it needs to be genuinely
open and accessible. This means ensuring that people are aware of
the Local Development Plan as early in the process as possible, that
they have the facts that allow them to make a genuine contribution,
that they have had the opportunity to engage and that, having made

Page 22

17 
their views known, they get a clear explanation of how and why
decisions were made. 
21. Engagement has been designed into the reformed planning system
and it is integral to the process of preparing a Local Development
Plan. 
22. For example, Council’s are required to let communities know at the
beginning of the process when and how engagement will happen
through the Development Plan Scheme. Council’s are required to
identify the main land use issues for their area and consult on the
options for how these can be addressed through a Main Issues
Report prior to drafting a new plan. This means that communities
are involved earlier in the process and have more influence over the
outcomes. 
WHAT IS THE PURPOSE OF ENGAGEMENT 
23. The purpose of engagement refers to the level or role of stakeholder
involvement and the amount of influence they have in the process. 
24. For the purposes of this Strategy, three levels of engagement are
used to describe the nature and purpose of engagement methods.
These are inform, consult and involve. 
25. Some engagement methods seek to simply ‘inform’ stakeholders
and there is no expectation of receiving feedback, consequently
there is a low level of public involvement. However, when the
purpose of engagement is to ‘involve’ stakeholders this implies a
more interactive process with increased expectations by
stakeholders and an increased level of influence. 
26. The nature of these three levels of engagement is described in the
diagram below. 
Table 1
Inform Consult Involve
Purpose: to provide
stakeholders with
balanced and
objective information
Purpose: to seek
stakeholder
views on policy
Purpose:  to seek
stakeholder views
and input to policy
• One way flow of
information
• Purpose is to provide
information/educate
• Factual Information is
needed to describe a
policy, program or process
• Foundation of all
community engagement
processes
• There is no opportunity to
influence the final outcome
• Information is necessary to
abate concerns or prepare
for involvement
• To advise the public needs
on the results of a process
• A decision may have
already been made (no
decision is required), i.e.
informing that the plan is
adopted
• Two-way interactive
process
• There is an
opportunity to
influence the final
outcome.
• Input may shape
policy directions
• To obtain public
feedback on analysis,
alternatives and/or
decisions.
• Two way flow of
information
• A higher level of
participation is
expected from
stakeholders than with
consulting.
• In depth joint working
with key stakeholders
• We wish to encourage
discussion among and
with stakeholders 
Increasing level of stakeholder engagement

Page 23

18 
27. Table 1 indicates the purpose of engagement for each stage of the
North Lanarkshire Local Development Plan preparation process and
is summarised in the figure below. 
Both Table 1 and the figure below clearly illustrate that higher levels
of stakeholder involvement will be towards the start of the process,
allowing genuine opportunities to influence the process and that
providing information is important throughout the plan process. 
A LONGER TERM APPROACH 
28. This Strategy is not only about how we engage communities in the
preparation of the Council’s first North Lanarkshire Local
Development Plan, but also subsequent development plans. Some
of our actions will be focussed on raising the profile and awareness
of the North Lanarkshire Local Development Plan and the land use
planning process with a view to increasing the interest in, ease and
desire for stakeholders to be involved. 
29. This will take time and commitment and the benefits are likely to be
more significant to future development plans. We see this as
investing in both the present and future communities’ capacity to be
involved in the land use planning process. 
BENEFITS OF ENGAGEMENT 
30. Both communities and the Council stand to benefit from effective
engagement. 
Benefits to the community Benefits to the Council 
• Allow the various
communities within North
Lanarkshire to influence
the decision-making
process
• Result in decisions being
made that are more likely
to reflect the needs of
communities and be
supported by them.
• Foster a sense of
belonging to the
community and create
stronger communities.
• Empower individuals with
regard to issues that affect
them.
• More transparency and
accountability 
• Allows the Council to make
more informed decisions
based on stronger evidence
and thus prepare better
policies
• People who live, work,
play, use services, do
business and manage
resources within North
Lanarkshire have a range
of local knowledge and
expertise that should be
utilised to inform and
influence Council decisions
that impact upon them.
• If undertaken early in the
process, where there is
more scope to influence
decisions, it can save time
later on. 
THE STRATEGY OBJECTIVES 
31. The objectives of the Stakeholder Engagement Strategy are:
• To make a better plan for North Lanarkshire 
• To meet our statutory engagement requirements. 
• To raise awareness of the North Lanarkshire Local
Development Plan amongst a broad range of stakeholders.
Main Issues
Report 
Proposed
Plan 
Examination 
Justify 
Adoption of
the Plan

Page 24

19 
• To make it easy for stakeholders to contribute to the North
Lanarkshire Local Development Plan. 
• That stakeholder’s can see how their contribution has
been considered and understand the reasoning behind
decisions. 
• To use a range of engagement methods. 
• To undertake engagement in line with the National
Standards of Community Engagement. 
OUR COMMITTMENT 
32. In preparing North Lanarkshire Local Development Plan we want to
take a more pro-active approach to engaging with our communities.
We will do this by having a coordinated approach to how we engage
and promote the plan and by exploring new engagement methods. 
33. We are committed to engaging with communities in line with the 10
National Standards on Community Engagement: 
• The INVOLVEMENT Standard
We will identify and involve the people and organisations who
have an interest in the Local Development Plan. 
• The SUPPORT Standard 
We will identify and overcome any barriers to involvement. 
• The PLANNING Standard
We will gather evidence of the needs and available resources
and use this to agree the purpose, scope and timescale of the
engagement and the actions to be taken. 
• The METHODS Standard
We will agree and use methods of engagement that are fit for
purpose. 
• The WORKING TOGETHER Standard
We will agree and use clear procedures that enable the
participants to work with one another efficiently and effectively. 
• The SHARING INFORMATION Standard
We will ensure that necessary information is communicated
between the participants. 
• The WORKING WITH OTHERS Standard
We will work effectively with others with an interest in
engagement. 
• The IMPROVEMENT Standard
We will develop actively the skills, knowledge and confidence
of all the participants. 
• The FEEDBACK Standard
We will feedback the results of the engagement to the wider
community and agencies affected. 
• The MONITORING and EVALUATION Standard
We will monitor and evaluate whether the engagement
achieves its purposes and meets the National Standards for
Community Engagement. 
WHO WILL WE ENGAGE? 
34. We interact with a broad range of stakeholders with varying interests
in terms of land use. 
35. There are a number of stakeholders that we are required to engage
with because they; are identified by legislation as a Key Agency,

Page 25

20 
because of their geographical or strategic planning association with
North Lanarkshire, are an identified community group, or simply
because they may be expected to have an interest in the North
Lanarkshire Local Development Plan. 
36. These stakeholders include:
• Key Agencies;
• Public sector organisations;
• Partner Organisations;
• Special Interest & Representative Organisations
• Community & Representative Organisations
• Private Sector Organisations 
37. A list of organisations under each of the stakeholder groups
mentioned above is included within the North Lanarkshire Local
Development Plan Stakeholder Database which is within the
Participation Statement. Organisations on the North Lanarkshire
Local Development Plan Consultation Database will be notified and
invited to comment during formal consultation periods for the North
Lanarkshire Local Development Plan. 
38. In addition to the stakeholders identified above, there are a number
of internal stakeholders within the Council who have an interest in or
will be affected by the outcomes of the North Lanarkshire Local
Development Plan. Key internal stakeholders include colleagues
within Chief Executive’s Office, Corporate Services, Regeneration &
Environmental Services, Finance & Customer Services, Housing &
Social Work Services and Learning & Leisure Services. A full list of
internal stakeholders is detailed within North Lanarkshire Local
Development Plan Consultation Database which will be included
within the Participation Statement. 
39. Community Councils and Community Forums have an important
role to play in the Local Development Plan process as statutory
community representatives. We intend to engage with Community
Councils and Community Forums at the early stages of producing
the North Lanarkshire Local Development Plan (prior to the
production of the Main Issues Report). 
40. Gypsy/Travellers have a unique set of land use requirements which
may need to be addressed through the North Lanarkshire Local
Development Plan. In order to engage effectively with
Gypsy/Travellers extra effort will be made to identify suitable
engagement methods to understand the land use requirements of
this group. 
41. Young People require extra effort to be made to achieve effective
engagement with the planning system. Young people will live with
the land use planning decisions made today and developing an
awareness of the planning system and how it impacts on them will
hopefully lead to active citizenship as adults. We intend to engage
with Young People through the use of social media and the Council’s
website as well as engaging directly with Young People groups. 
42. We are also committed to engaging with the broader public and a
number of engagement methods will be targeted to this group. In
particular we will be making extra efforts to involve anyone who
would not normally engage with the planning system. 
HOW AND WHEN WE WILL ENGAGE 
43. The focus for engagement activity will be the lead up to and
consultation on the Main Issues Report which is one of the initial key
stages in the plan process. After this point the purpose of
engagement shifts largely to informing stakeholders and there is
limited scope for stakeholders to influence the final plan. 
44. The extent to which the Council can engage is constrained by limited
resources. Engagement costs money and with shrinking budgets the
Council needs to prioritise how resources are used for engagement. 
45. The internet will be a focus for engagement activity related to the
North Lanarkshire Local Development Plan as it is cost effective and

Page 26

21 
many people have access to and expect information to be available
on the internet. The internet will be the hub for making submissions
and accessing information on the North Lanarkshire Local
Development Plan throughout the process. 
46. However, hard copies will still be available to read at Council offices
and public libraries and submissions can still be made in writing. 
47. In addition to the North Lanarkshire Local Development Plan
Stakeholder Database, North Lanarkshire Council has signed up to
‘Gov Delivery’. This system allows us to reach customers in an as
efficient and customer-friendly a way as possible.  Gov Delivery
enables interested parties who had signed up to the Strategic
Planning Mailing List it replaces to receive emails updates on the
progress of the Local Development Plan, as well as other aspects of
the work of the Council's Planning Service. 
48. The Participation Statement provides a list of all the engagement
methods we intend to use, what stakeholders they are aimed at and
at what stage of the process. These methods are grouped into those
methods that are aimed at raising awareness and skills, and those
methods which are to aid exploring the issues. 
49. The Council will be using a wide range of engagement methods
throughout the preparation of the North Lanarkshire Local
Development Plan. The method used will be tailored according to
the purpose of the consultation (e.g. inform, consult etc) and which
stakeholder it is intended for (target group or general public). 
50. The Participation Statement provides a record of any media activity
related to the North Lanarkshire Local Development Plan. It lists any
public notices, newspaper articles, blogs, newsletters or social
media mention the North Lanarkshire Local Development Plan we’re
aware of in relation to the North Lanarkshire Local Development
Plan. 
51. The Participation Statement will be updated regularly alongside the
Development Plan Scheme and will be published on the Council’s
website. 
FEEDBACK, MONITORING AND EVALUATION 
52. We are committed to providing feedback about the issues that
emerge from engagement, the actions taken as a result of the views
expressed, and how input affected a decision. 
53. We are expecting a lot of people to have their say by making a
submission as part of the planning process. For example, throughout
the process to prepare the North Lanarkshire Local plan we received
nearly 3,000 submissions, some of which raised multiple issues. 
54. With this in mind we will consider and report on each of the issues
raised in every submission it will not be possible to provide an
explanation in writing to each individual on how their comments have
been considered as we simply don’t have the resources to do this. 
55. To address this we will make sure that documents which include
feedback are presented in a clear and accessible way, are easily
available to the public and that, in particular, people who have made
submissions know where and how access these. 
56. Engaging with communities is not new for us; however, this is the
first time we have prepared an engagement strategy which brings all
our engagement activities together in a coordinated approach. 
57. We will be focussing on regular monitoring and we therefore need
to start gathering information to provide a basis for evaluation and
review. 
58. We will monitor and evaluate how we engage throughout the
process, but in particular after the Call for Sites, Main Issues Report,
Proposed Plan and at the adoption stage so that we can build on
strengths and learn from aspects that don’t work so well to

Page 27

22 
continually improve the engagement process throughout the
preparation of the North Lanarkshire Local Development Plan. 
IT’S NOT A POPULARITY CONTEST! 
59. Land use policies are complex. There are many different and
competing interests and it is unlikely that all stakeholders will agree
with each other, or the proposed solutions. 
60. It is also important to note that the findings from consultation with
stakeholders, although important, are only part of the evidence base
upon which decisions are made. 
61. It is therefore important to be clear that the outcome of engagement
is not about preparing a plan that pleases the most people. It’s about
ensuring that planning decisions are made taking an informed
view on all, of the evidence available. 
62. If a policy does not accord with a stakeholder’s view, it does not
mean that his/her view has not been considered. 
63. There will always be cases where differences cannot be resolved.
The challenge lies in ensuring that communities are engaged in
shaping the future of their area; that the basis and justification for
polices, land allocations, infrastructure priorities and decisions are
clear and that the trade-offs between competing and, in some cases,
conflicting interests are explicit and transparent. 
HOW TO CONTACT US 
64. If you have any questions or comments about this document or
about the North Lanarkshire Local Development Plan the
Development Plan Team can be contacted using the following
methods: 
Through our website:
www.northlanarkshire.gov.uk/developmentplan 
By email: ESNLLDP@northlan.gov.uk 
By mail: Development Planning Team  
Regeneration and Environmental Services  
North Lanarkshire Council  
Fleming House  
2 Tryst Road  
Cumbernauld 
G67 1JW 
OTHER SOURCES OF ADVICE OR INFORMATION 
65. For more information on the Scottish Planning System refer to the
Planning page on the Scottish Government’s website:
http://www.scotland.gov.uk/Topics/Built-Environment/planning 
66. For more information on community engagement and the National
Standards on Community Engagement refer to Planning Advice
Note 3/2010: Community Engagement by the Scottish
Government which can be downloaded from the Scottish
Government website:
http://www.scotland.gov.uk/Publications/2010/08/30094454/0 
67. For more information on SP=EED – Successful Planning equals
Effective Engagement and Delivery by Planning Aid Scotland which
can be downloaded from the Planning Aid Scotland’s website:
http://www.planningaidscotland.org.uk/speed