ARGYLL AND BUTE COUNCIL  PPSL COMMITTEE 
Development and Economic Growth  20th December 2023 
Planning Performance Framework 2022/23 
1.0 EXECUTIVE SUMMARY 
1.1 This report contains recent feedback from the Scottish Government in relation to
our Planning Performance Framework (PPF). Appendix A. 
1.2 Our PPF is the principal performance measure for Planning Services
(Development Management and Development Policy – within Planning and
Regulatory Services) and is submitted to the Scottish Government annually for
scrutiny and scoring. The Council’s 2022/23 PPF was submitted in July 2023 and
was independently reviewed by the Scottish Government. A copy of the
submitted document was submitted to the PPSL for noting at their meeting of
23rd August 2023. 
1.3 Overall the feedback report is considered overall to be positive registering ten
‘green’, zero ‘amber’ outcomes, and four ‘red’ outcomes across the fourteen
performance indicators assessed. Whilst it is disappointing to have any ‘red’
markers it is noted that three of these relate to performance measures looking at
timeliness of determining planning applications which have been directly
impacted by the pandemic and its impact upon workflow, and staff availability
(absence and vacancies). 
1.4 Whilst the Scottish Government have not identified any improvement actions for
ABC this year, the service must not be complacent with the focus being year on
year continuous improvement.   
1.5 It is recommended that the Committee consider and note the content of the report
and publicise (press, Twitter, Facebook and website release) the positive
feedback from the Scottish Government.

Page 2

ARGYLL AND BUTE COUNCIL  PPSL COMMITTEE 
Development and Economic Growth  20th December 2023 
Planning Performance Framework 2022/23 
2.0 INTRODUCTION 
2.1 This report contains recent feedback from the Scottish Government in
relation to our Planning Performance Framework (PPF). Appendix A. 
The Executive Summary (above) provides further background
information.     
3.0 RECOMMENDATION 
It is recommended that the Committee consider and note the content of report
and publicise (press, Twitter, Facebook and website release) the positive
feedback from the Scottish Government. 
4.0 DETAIL   
What is the Planning Performance Framework? 
4.1 This was Planning Services 12th Annual Planning Performance
Framework (PPF) and is our ‘balance scorecard’ of performance which all
Local Authorities must submit to the Scottish Government for review and
scrutiny.   
4.2 The PPF aims to be a holistic and easy read document that encapsulates
statistical performance indicators as well as more qualitative information
and case studies of good practice for the previous financial year. The basic
structure of the document is stipulated by the Scottish Government but the
character, tone, style and content is all shaped by the individual Authority.
The Scottish Government has suggested that Authorities use the PPF as
more than a means of simply reporting performance but utilise the
document as an opportunity to promote their service and local area, to
incorporate customer feedback and to provide updated narrative on case
study items from previous years. The PPF seeks to focus on the Council
being ‘open for business’ and the positive economic contribution that
Planning Services have made within Argyll and Bute. The PPF presents
case studies and examples of good practice which demonstrates the ability
of the Service to facilitate the delivery of high quality development on the
ground, to provide certainty to developers and investors, to consult and
engage with customers effectively and to ensure that appropriate
management and service delivery structures are in place to work efficiently. 
Review and Feedback

Page 3

4.3  The review of the PPF was carried out by the Scottish Government and
considered by the Minister for Local Government Empowerment and
Planning. Joe Fitzpatrick MSP. 
4.4 Within our PPF We managed to showcase a variety of good quality
projects and initiatives that demonstrate our ‘open for business’ and
service improvement ethos, and have identified a good range of service
improvement commitments. 
4.5 The covering letter and feedback from Joe Fitzpatrick MSP is contained
in full at Appendix A, however some pertinent points are highlighted
below:- 
• PM 1 Decision Making (Red): This marker was also identified as Red in
2020/21 and 2021/22. Performance in the determination of planning applications
remained significantly affected by the impacts of Coronavirus pandemic during
a reporting period where the effects of service disruption/recovery have
significantly impacted the time taken to determine applications, these include the
longer-term impacts of managing a significant backlog of casework that has
accrued and reduced staffing resource as a result of absence and difficulties in
recruiting to vacancies. During the 2022/23 reporting period the time taken to
determine all categories of application increased from the previous period. This
position was not unexpected and is reflective of a position where Scottish
averages have also increased. It is highlighted that Major applications where
determined 3.6 weeks slower than the national average; and Local (non-
householder) applications were determined 1.9 weeks slower than the Scottish
average. The determination of householder applications remained significantly
slower (+3.8 weeks) than the Scottish average however this is indicative of the
prioritisation of available resources toward determination of applications that
would deliver significant inward investment/employment, or were time critical in
relation to grant funding or public health issues. 
• PM 4 Legal Agreements (Red): This marker was previously identified as Amber
in 2021/22. The performance marker seeks to monitor the efficiency with which
a planning authority concludes legal agreements after resolving to grant planning
permission. During 2022/23 the average time taken to conclude legal
agreements increased from 33.6 weeks to 49.5 weeks; the national average for
this KPI was 41.1 weeks. It is noted that this performance marker relies on a
small body of applications and is readily skewed. It is also recognised however
that continuing pressures upon the DM Management staff resulting from long-
term vacancies in the Service has reduced the scope to provide regular review
and monitoring of outstanding cases awaiting conclusion of legal agreements. 
• PM 5 Enforcement Charter (Green): This marker has been green for the
previous four reporting periods and recognises that the Council’s Planning
Enforcement Charter has been subject to its statutory bi-annual review. It is
noted that the Charter is due to be reviewed again by March 2024. 
• PM 6 Continuous Improvement (Green): This marker was previously identified
as Amber in the previous six reporting periods. The Planning Service received
positive feedback for continuing to progress service improvements during
2022/23, these are detailed in Part 3 of the PPF. 
• PM 7 Local Development Plan (Red): This marker was previously identified as
Red in 2020/21 and 2021/22 as the Argyll and Bute Local Development Plan
2015 has not been replaced within the required 5 year period. Despite the current

Page 4

adopted LDP being more than 5 years old, this policy framework is still
considered up to date and relevant, and a more than adequate housing land
supply still exists as demonstrated in our annual Housing Land Audit (which has
recently been cited by Scottish Government as an example of good practice). It
is observed that pLDP2 has been on deposit with the Scottish Government for
the duration of the reporting period and as such it has been outwith the control
of the Council to deliver an improvement. It is noted that pLDP2 has
subsequently progressed and is expected to be adopted during 2023/24. 
• PM 8 Development Plan Scheme (Green): This marker was previously
identified as Amber in the previous four reporting periods. Whilst confirmation
that the LDP will not be replaced within the 5 year cycle flags as Red, this is
balanced against the fact that the Council had recognised that the project was
behind time within an updated Development Plan Scheme and amended the
project plan for delivery accordingly. The feedback report notes that PLDP2 had
progressed to Examination stage and was expected to be adopted during
2023/24. 
• PM 14 Stalled Sites / Legacy Cases (Red): This marker was identified as
Amber in the previous reporting period. The feedback commentary identifies that
whilst 18 legacy cases were cleared during the reporting period the number of
remaining legacy cases nearly doubled from 65 in 2021/22 to 125 undetermined
applications as of 31st March 2023. The degradation in this measure is directly
attributable to the matters identified in PM 1 above in relation to determination
timescales, but also a reduction in availability of management resource available
to actively progress determination of legacy cases whilst addressing the other
significant challenges facing the DM Service during this period. The measure
improved from Red to Amber as due to an increase in the volume of legacy cases
that were determined during the reporting period. 
Focus on Performance / Resources 
4.6 The cover letter from the Minister for Local Government Empowerment
and Planning. Joe Fitzpatrick MSP recognises that “resourcing remains a
high priority” and sets out intent to continue to discuss this issue with the
High Level Group on Planning Performance. It is identified that a variety
of measures to improve resources require to be considered including “full
cost recovery, the local setting of fees, charges for additional services,
and approaches which could enable authorities to access the skills and
expertise at the time they require”. 
4.7 The Minister has also highlighted the appointment of the National
Planning Improvement Champion (NPIC), Craig McLaren, who has taken
up post in September 2023. It is identified that this new role will be pivotal
in “supporting improvement and will also be looking at how we can
improve the way we measure and assess the performance of the planning
system in the future”. 
5.0 CONCLUSION   
5.1 Feedback from the Scottish Government is overall considered to be positive
and has confirmed that the Planning Service has an ‘open for business’
approach to delivering sustainable economic growth throughout Argyll and
Bute, and has set out appropriate service improvement measures to

Page 5

address the current challenges impacting on performance. 
6.0 IMPLICATIONS 
6.1 Policy: None 
6.2 Financial: None   
6.3 Legal: None 
6.4 HR : None 
6.5 Fairer Scotland Duty: 
6.5.1 Equalities Protected Characteristics: None 
6.5.2  Socio-Economic Duty: None 
6.5.3 Islands: None 
6.6 Risk: Reputational of being identified as a poor performing authority if next
year’s PPF performance is substandard.   
6.7 Customer Service: The PPF report provides Customers with an overview
of the statistical and qualitative performance of the Council as the planning
authority in a format that can be benchmarked with other authorities.   
6.8 Climate Change: None 
Executive Director with responsibility for Development and Economic Growth:
Kirsty Flanagan
Policy Lead:-  Kieron Green
8th December 2023                                                  
For further information contact: Peter Bain – 01546 604204 
APPENDICES 
Appendix A – Planning Performance Framework 2022/23 Feedback