Agenda Document Pack - Planning Committee - 15/08/2024

North Lanarkshire Council · 15 August 2024
Back to Planning Committee — 15 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

6 August 2024 
Members of the 
Planning Committee
Chief Executive’s Office
Archie Aitken
Chief Officer (Legal & Democratic)
Civic Centre, Windmillhill Street,
Motherwell ML1 1AB
www.northlanarkshire.gov.uk 
Notice is given that a Meeting of the Planning Committee is to be held in the Council
Chamber, Civic Centre, Windmillhill Street, Motherwell, ML1 1AB on Thursday, 15 August
2024 at 10:00 AM which you are requested to attend. 
The agenda of business is attached. 
Archie Aitken
Chief Officer (Legal & Democratic) 
Members : 
Clerk Name: Mark Hamill
Clerk Telephone: 07811294702
Clerk Email: hamillm@northlan.gov.uk 
N Shevlin, G Currie, B Baudo, G Brennan, B Burgess, A Bustard, J Cairns, T Carragher, M
Coyle, S Coyle, K Docherty, T Fisher, M Hughes, L Jarvie, T Johnston, J Logue, H
Loughran, C McManus, M McPake, A McVey, L Mitchell, J Reddin, D Robb, A Smith, G
Woods.  
Page 1 of 74

Page 2

Page 2 of 74

Page 3

Agenda 
1 Declarations of Interest In Terms of the Ethical
Standards In Public Life Etc. (Scotland) Act 2000   
2 Planning Applications Index
Submit Planning Applications Index 
5 - 74 
Page 3 of 74

Page 4

Page 4 of 74

Page 5

North
Lanarkshire
Council 
Planning Applications for consideration     
of Planning Committee 
Committee Date: 15th August 2024 
Ordnance Survey maps reproduced from Ordnance Survey
with permission of HMSO Crown Copyright reserved 
Item 2
Page 5 of 74

Page 6

APPLICATIONS FOR PLANNING COMMITTEE 
15th August 2024 
Page No Application No  Applicant Development/Site Recommendation    
8-17 23/00651/FUL  Mr Barry
Robertson 
Construction of 1.5 Storey
Building Consisting of
Commercial Tattoo Studio &
Two Bedroom Flat
Land At, 6 Moorpark Avenue,
Muirhead 
G69 9DZ 
Grant
18-39 23/00992/FUL  RAW Plant
Recycling Ltd
Extraction of Colliery Shale from
Disused Coal Mine and Rock
from Disused Quarry Face
together with Agricultural
Improvement Works and
Restoration of Colliery Site
Dewshill Farm
Forrest Road
Salsburgh
ML7 4NY
Grant    
40-48 24/00043/FUL Renewable
Connections
Developments
Ltd
Proposed Battery Energy
Storage System (BESS) and
Associated Access
Land At Burnbank Street
Greenhill
Coatbridge 
Grant    
49-61 24/00182/FUL North
Lanarkshire
Council
Construction of Community Hub
Comprising a Replacement St
Stephen's Primary School, the
Language and Communication
Support Centre (LCSC) and
associated LCSC Provision, a
Nursery Class, Community
Facilities and Corresponding
Sports Amenities, together with
a Fully Landscaped Site for the
School and Associated Car
Parking and Drop Off
St Stephen's Primary School
Sikeside Street
Sikeside
Coatbridge
ML5 4QH
Grant    
Page 6 of 74

Page 7

62-74 24/00268/FUL  North
Lanarkshire
Council
Extension to School Teaching
Facilities, New Sports Facilities
and a New Early Years Facility
Chryston High School
Lindsaybeg Road
Chryston
G69 9DL
Grant     
Page 7 of 74

Page 8

Application No:  
23/00651/FUL
Proposed Development:  
Construction of 1.5 Storey Building Consisting of
Commercial Tattoo Studio & Two Bedroom Flat    
Site Address:  
Land At
6 Moorpark Avenue
Muirhead
G69 9DZ      
Date Registered:  
17th July 2023      
Applicant:
Mr Barry Robertson
Sacramental Tattoos
18 Drumsack Avenue
Chryston
Glasgow
G69 9AR  
Agent:
Luke McLeish
McLeish Architectural Design Ltd
22 Eriskay Avenue
Hamilton
South Lanarkshire
ML3 8QB  
Application Level:
Local Application      
Contrary to Development Plan:
No
Ward:   
05 Stepps, Chryston and Muirhead 
John McLaren, Josh Cairns, Claire Louise
Williams
Representations:
12 letter(s) of representation received.        
Recommendation: Approve Subject to Conditions  
Reasoned Justification:  
The proposal is considered acceptable in terms of the criteria set out in the relevant
policies contained within the North Lanarkshire Local Development Plan (2022). The
proposed development is unlikely to have an adverse impact on the surrounding mixed-
use area.   
Page 8 of 74

Page 9

Reproduced by
permission of
the Ordnance
Survey on behalf
of HMSO. ©
Crown Copyright
and database
right 2009.  All
rights reserved.
Ordnance
Survey Licence
number
100023396.
Planning
Application:
23/00651/FUL 
Name (of
applicant): Mr
Barry Robertson
Site Address:
Land At
6 Moorpark
Avenue
Muirhead
G69 9DZ
Development:
Construction of
1.5 Storey
Building
Consisting of
Commercial
Tattoo Studio &
Two Bedroom Flat    Page 9 of 74

Page 10

Proposed Conditions:-  
1. That, except as may otherwise be agreed in writing by the Planning Authority, the
development shall be implemented in accordance with drawing numbers:- 0009 - ELEV –
01A, 0009 - Exist.SP – 01A, 0009 - FF - PLAN – 01A, 0009 - GB - PLAN – 01A, 0009 -
GF - PLAN – 01A, 0009-Prop.SP-01 G and 0009 - Loc.P1-01 D.  
Reason: To clarify the drawings on which the approval of permission is founded.  
2. That BEFORE any works start on site, the applicant must confirm in writing to the Planning
Authority that the foul drainage can be connected to the public sewer in accordance with
the requirements of Scottish Water.  The surface water must be treated in accordance with
the principles of the Sustainable Urban Drainage Systems Design Manual for Scotland
and Northern Ireland published by CIRIA in March 2000.  
Reason: To prevent groundwater or surface water contamination in the interests of
environmental and amenity protection.  
3. That PRIOR to commencement of the development, a site-specific ground gas risk
assessment requires to be carried out to determine the precise level of gas protection
required, which should be submitted to and approved in writing by the planning authority.
Gas protection measures, equivalent to at least Characteristic Situation 2, are highly likely
to be required to be incorporated into the development in line with ‘Ciria 665: Assessing
Risks Posed by Hazardous Ground Gases to Buildings”.  
Reason: To enable the Planning Authority to consider these aspects in detail.  
4. That PRIOR to commencement of the development, a gas verification plan should be
submitted to and approved in writing by the planning authority. Gas protection measures
should be validated in terms of the requirements of “Ciria C735: Good Practice on the
Testing and Verification of Protection Systems for Buildings and Against Hazardous
Ground Gases”.  
Reason: To enable the Planning Authority to consider these aspects in detail.  
5. That the development hereby permitted shall be carried out in accordance with the
approved Noise Impact Assessment submitted as part of the application, and that any
road noise assessment of the residential flat is on a windows-closed basis. Following the
implementation of all of the noise mitigation measures and before the flat is brought into
use a validation report (signed by an Acoustic Consultant) shall be submitted to the
planning authority for written approval.  
Reason: To ensure that the development site will not be subject to unacceptable noise
levels in the interests of amenity.  
6. That the permission hereby granted to use the ground floor of the property as a tattoo
studio is personal to the applicant (Mr Barry Robertson) and is for that use only and unless
separate permission is obtained the ground floor will not be used for any other
commercial/business use.  A maximum of 4 tattoo artists will be permitted to operate within
the property and any time.    
Reason: to control the use of the ground floor of the property and to prevent inappropriate
changes if use that may generate significantly more vehicular traffic. 
7. That before the development starts, the days and hours of operation for the tattoo studio
will be approved in writing by the planning authority and once approved (unless
subsequently varied in writing) the studio will operate in accordance with the details
approved.  Page 10 of 74

Page 11

Reason:  in the interest of residential amenity    
Background Papers:  
Consultation Responses:  
Traffic & Transportation received 9th January 2024 
Scottish Water received 25th July 2023 
from Food Safety / Business Regulations received 24th July 2023
Environmental Health (including Pollution Control) received 9th August 2023 
Contact Information: Mr Joe Gannon at planningenquiry@northlan.gov.uk or 01236 632487  
Report Date:  18th July 2024 
Page 11 of 74

Page 12

REPORT  
1. Site Description  
1.1 The application site comprises of vacant land (approximately 280m2) and a private
garage, which forms part of the established local centre of Muirhead. To all sides of the
land are a mixture of commercial properties including the Co-operative store for Muirhead,
residential properties which range in style, design, and age (1.5 storey terraced dwellings
which face the proposal), the A80 dual carriageway, and mature trees and hedging.  
2. Proposed Development  
2.1 The application seeks full planning permission for the construction of a 1.5 storey property,
for a mixed-use property consisting of a commercial tattoo studio (ground floor) and two-
bedroom flatted dwelling (first floor). The proposed building will measure 12.3m at its
longest point, and is approximately 11.8m in width, giving the property a footprint of
approximately 118m2. The eaves height of the property is 2.65m, with a total height of
approximately 7m. Internally, there are several rooms across the two floors and different
uses:  
• Ground (tattoo studio): main studio, reception area, staff room, office, private room,
and WC.
• First (flat): living room, kitchen, two bedrooms, bathroom, and WC.  
2.2 The proposed materials of the development consist of buff facing brick basecourse,
external rendering, uPVC glazing, and concrete roof tiling, which is considered acceptable
with the neighbouring properties.  
2.3 There are 9 off-street parking spaces proposed as part of the development, with a mixture
of staff and visitor parking, as well as private parking for the flatted dwelling. There is
amenity space and a bin collection point to the east of the property proposed as part of
the development.  
3. Applicant’s Supporting Information  
3.1 Supporting information has been provided during the assessment process of the
application, which includes a Noise Impact Assessment, discussed further in 6.3. The
agent has confirmed the following:  
• Parking for the owner will comprise of two spaces, one for the dwelling and one for
the business
• At any given time, there will be 5 members of staff working at the tattoo parlour (4
artists and 1 receptionist)
• The flatted property will be let out to a family member and not sold or rented to
members of the public
• The tattoo parlour will primarily be appointment-based, with artists booked out a
month in advance, where walk-ins will be available in the event of a cancellation
• At peak, it is estimated that a maximum of 9-10 people will be in the studio at one
given time
• Artists will not share beds and equipment  
At our request calendars of the applicant and two other tattoo artists were also provided,
which indicates each artist will have on average 1-2 clients per day (5-6 in total) across
the entire week. The applicant has advised that the tattoo artists dairies are usually booked
out well in advance limiting the opportunity for ‘walk in’ custom. (The applicant currently
has premises within the Town Centre at Cumbernauld which is now owned by the Council
and will need to be vacated when the centre is demolished)    
Page 12 of 74

Page 13

Furthermore, the agent has provided a written response (dated 28th of March 2024) in
light of an objection from Roads. The agent has stated that sufficient visibility can be
achieved on Cumbernauld Road, exiting Muirhead Road, as well as providing clarification
regarding parking arrangements and the allocation of spaces. 
4. Site History  
4.1 There are no previous applications with pertinence to this site.  
5. Development Plan  
5.1 The application site is covered by Placemaking Policy 1C (Local Centre) within the
adopted North Lanarkshire Local Development Plan (2022).  
5.2 For proposals with housing development and business use in Local Centres, the proposal
must comply with policies set out in PP 1C (Purpose of Place) and AD 1C (Amount of
Development). Policies EDQ 1 (Site Appraisal) and EDQ 3 (Quality of Development) are
also relevant as these policies consider issues such as size, materials, existence and
quality of connections and road safety and which states that proposals must integrate
successfully with the surrounding area by avoiding harm to neighbouring amenity,
supported by high standards of site planning and sustainable design.  
5.3 NPF4 forms part of the development plan; given the nature and scale of this development,
the most relevant considerations are already enshrined in the North Lanarkshire Local
Development Plan policies. The policies within NPF4 that are relevant to the application
include Policy 14 (Design, Quality and Place), Policy 15 (Local Living and 20-minute
neighbourhoods), and Policy 27 (City, town, local and commercial centres).  
5.4 The application can therefore be assessed against the policy provisions of the North
Lanarkshire Local Development Plan and the relevant policies within NPF4.  
6. Consultations  
6.1 NLC Food Safety & Business Regulations – have responded by stating several
requirements should the proposal be developed, relating to the provision of hand wash
basins in each room to be used for skin piercing or tattooing, acceptable ventilation and
illumination within the general premise, and that business activities are undertaken in
conditions of appropriate privacy (can be covered by informative note)  
6.2 Scottish Water – state that a formal connection application will be required should
planning permission be granted, as well as a Pre-Development Enquiry (PDE) Form to
allow the proposal to be fully appraised. This is detailed within Condition 2 of the
permission hereby granted.  
6.3 NLC Pollution Control – raise no objections to the application, provided that appropriate
conditions  were attached to any approval in relation to a Site Investigation and Noise
Impact Assessment, due to site lying on an area of naturally occurring methane gas and
the location being adjacent to the A80 dual carriageway road, the Co-operative store and
the noise which may affect the proposed development. 
6.4 NLC Traffic & Transportation – recommended refusal for the application, based on
substandard visibility to the left along Cumbernauld Road exiting from Moorpark Avenue.  
7. Representations  
7.1  Following standard neighbour notification procedures, 12 letters of representation were
received, 2 of which were received following expiration of the notification period, and 1
asking for an update. Councillor Claire Louise Williams objected but this was received out
of time. The objections can be summarised as follows: Page 13 of 74

Page 14

a. Traffic and road safety issues: visibility, access, limited space for HGVs and
emergency vehicles, parking, turning manoeuvres, condition of existing road, and
increase in residential and commercial traffic
b. Adverse impact on pedestrian safety and wellbeing
c. Increased refuse and bin collection
d. Inadequate drainage infrastructure to support development
e. Limited and inaccurate detail within plans
f. Legal ownership and encroachment of land
g. Loss of privacy to neighbouring properties
h. Current purpose of on-site garage
i. Incongruous with residential area
j. Impact on streetlight, mature trees, hedging, and appearance of area
k. No planning statement provided which provides information on business  
8. Planning Assessment 
8.1 Under Section 25 of the Town and Country Planning (Scotland) Act 1997, planning
decisions must be made in accordance with the development plan unless material
considerations indicate otherwise.  
8.2 Local Development Plan: Policies EDQ 1 (Site Appraisal) and EDQ 3 (Quality of
Development) are relevant as these policies consider issues such as size, materials,
existence, quality of connections and road safety, which states that proposals must
integrate successfully with the surrounding area by avoiding harm to neighbouring
amenity, supported by high standards of site planning and sustainable design.  
8.3 PP 1C (Purpose of Place): North Lanarkshire Council seeks to encourage a range of
uses and a level of development in these Centres to meet the needs of their localities,
whilst directing significant footfall generating uses in line with the Town Centres First
Principle. The aim of the Plan is to maintain and improve the level of amenity appropriate
for the local context. Development in Classes 1 (Shops including Sui Generis) and 9 (Flats)
of the Town and Country Planning (Use Classes) (Scotland) Order 1997 is deemed to be
support the purposes of those places and offer the best opportunity to meet the aims of
those places. The application is, therefore, considered to comply with the objectives of PP
1C (Purpose of Place). 
Meeting those aims will be primarily achieved through the provisions of the Environmental
and Design Qualities policies of the Plan.  
8.4 EDQ 1 (Site Appraisal) – Any proposed development will require to be appraised in terms
of the site and its surroundings to ensure it will integrate successfully into the local area
and avoid harm to neighbouring amenity. The matters to be addressed in the appraisal
include, but are not limited to, criteria set out in the Local Development Plan under EDQ
1. 
As a proposed mixed-use development, it is reasonable to state the residential flat and
tattoo parlour would generally be in keeping with the character of the surrounding area.
Therefore, the site with considered design qualities set out in policy EDQ 3 (Quality of
Development) can accommodate such a mixed-use development without significantly
affecting the amenity of adjacent dwellings.  
8.5 EDQ 3 (Quality of Development) – This policy considers siting, overall layout, density,
form, scale, height, massing, proportion, detailing, colour, materials considering
successful integration into the local area and avoiding harm to neighbouring amenity. This
is discussed below.    
The applicant proposes a mixed-use building (flat and tattoo studio) which is considered
acceptable in design and detail. The proposal is adaptable in its form, with the ground floor Page 14 of 74

Page 15

accommodating potential for residential/future businesses and commercial usage, should
its proposed use cease (future changes have been restricted by planning condition such
that a further application would be required before any change). There are good quality
green networks within a 20-minute walking radius of the proposed development (e.g.,
Seven Lochs Wetland Park). The site is accessible by and integrates well with a range of
sustainable transport modes (e.g., walking/wheeling, bus). Furthermore, there would be
environmental and visual benefits for developing on a long-standing, vacant site.  
The size, orientation, and distance from neighbouring properties ensures that, whilst there
is an impact, there is no detrimental loss of residential amenity in terms of privacy or
sunlight/daylight within the site. It is acknowledged that the proposed flat does not meet
the Council’s Open Space Standards in terms of garden depth, however, the proposal is
considered acceptable given the nature of the site and surrounding properties.  
8.6 In considering National Planning Framework 4 (NPF4) there are a number of policies that
affect the proposal, with the most notable ones being Policy 9 (Brownfield, vacant and
derelict land and empty buildings), Policy 14 (Design, quality and place), Policy 15 (Local
living and 20-minute neighbourhoods), and Policy 27 (City, town, local and commercial
centres). These policies are embedded and reflected within the Local Development Plan
policies listed above.  
8.7 Policy 9 states that development proposals that will result in the sustainable reuse of
brownfield land including vacant and derelict land and buildings, whether permanent or
temporary, will be supported. It is considered that the proposal complies with Policy 9
given the use of vacant and derelict land within the local centre of Muirhead.  
8.8 Policy 14 states that development proposals should be designed to improve the quality
of an area whether in urban or rural locations and regardless of scale. Proposals will be
also supported where they are consistent with the six qualities of successful places NPF4
namely: healthy; pleasant; connected; distinctive; sustainable; and adaptable. It is
considered that the proposal is consistent with these qualities, is of good design and does
not detrimentally impact the surrounding area, therefore, complying with this policy.  
8.9 Policy 15 states that development proposals will contribute to local living including, where
relevant, 20-minute neighbourhoods. To establish this, consideration will be given to
existing settlement pattern, and the level and quality of interconnectivity of the proposed
development with the surrounding area. The proposed development contributes to local
living by bringing employment to the area of Muirhead, and there is local access to
shopping, health facilities, schools, and informal play opportunities within a 20-minute
walking/wheeling distance of the site. As such, the proposal complies with the local living
element of Policy 15.  
8.10 Policy 27 states that development proposals that enhance and improve the vitality and
viability of local centres, including proposals that increase the mix of uses, will be
supported. Furthermore, proposals for uses that generate significant footfall (e.g.,
commercial) will be supported in existing local centres, which can be illustrated by the
existing success of Sacramental Tattoos in Cumbernauld town centre. By introducing a
mixed-use development into the local centre of Muirhead the proposal, therefore, complies
with Policy 27.  
8.11 Representations: In response to the grounds of representation above in 7.1, these are
commented on in the same order as they appear above:  
8.12 Comment: Traffic and road safety issues  
Response: During the planning application process, we consulted with our Roads
Service, to receive their comments on this proposal. 
Page 15 of 74

Page 16

Whilst there may be an increase in both commercial and residential traffic, it is considered
that the scale of this traffic would not be so significant to cause detriment within the area
or justify a refusal of planning permission. Due to Moorpark Avenue being unadopted, the
maintenance of such road’s falls upon the owners of any properties fronting the road.
Furthermore, given the historical make of up of many of the minor roads along
Cumbernauld Road and properties which front it, it can suggest that none/very few would
meet the required visibility splays (2.5 x 60m for 30mph roads), this is an established
access and crucially the visibility to the right is unhindered and the property can also be
accessed/exited via the Co-operative store car park.  It is considered that the fact that it is
visibility to the left that is compromised is not so significant as to justify a refusal of
permission. 
Therefore, the current condition and poor maintenance of the road does not fall under the
remit of the planning authority, and it is our assessment that  the proposed development
would not lead to such a significant intensification on the use of the access road to justify
a refusal of planning permission.  
8.13 Comment: Adverse impact on pedestrian safety and wellbeing  
Response: Following consultation with Roads, they have confirmed that despite there not
being an existing footway on Moorpark Avenue, they do not object to the proposal on the
grounds of the proposal having a detrimental impact on pedestrian safety and wellbeing.  
8.14 Comment: Increased refuse and bin collection  
Response: The location of refuse areas is accepted in the design of the development.
The planning system does not seek to control the increase in refuse and improper disposal
of resident’s waste, as this is considered under environmental legislation. Therefore, the
increase in refuse does not warrant refusal of planning permission.  
8.15 Comment: Inadequate drainage infrastructure to support development  
Response: The standard conditions attached to this permission associated with increased
impact on drainage facilities as a result of the development will ensure that Scottish Water
are satisfied with the proposal.  
8.16 Comment: Limited and inaccurate detail within plans  
Response: Following discussion with the agent, the inaccuracies regarding scale within
a number of plans have been rectified through amendment. 
8.17 Comment: Legal ownership and encroachment of land  
Response: It is not for the Council to undertake detailed legal searches in terms of
ownership or encroachment of land, and it is for the applicant to certify the land ownership
position. As such, these are legal matters and not a material planning consideration.  
8.18 Comment: Loss of privacy to neighbouring properties  
Response: It is considered that the development can be accommodated without having
an adverse impact on neighbouring properties in terms of privacy, due to the windows
having obscured glazing where window-to-window issues are less than 18m in distance
between the proposed development and existing dwellings.  
8.19 Comment: Purpose of on-site garage  
Response: The current purpose of the existing, private garage, which would remain as
part of the development, is not applicable to the consideration of the application.   Page 16 of 74

Page 17

8.20 Comment: Incongruous with residential area  
Response: The proposal has been assessed against the relevant policies within the Local
Development Plan. It is considered that the proposed development is compatible for the
land use (Local Centre) within the surrounding area due to its mixed-use purpose. In terms
of EDQ 3 (Quality of Development), the proposal is acceptable in terms of massing, layout
and materials used, and is considered not to have a detrimental impact on the surrounding
area. Furthermore, it is not considered that the development would have an adverse
impact on the general appearance of the area and the surrounding dwellings to warrant
refusal. 
8.21 Comment: Impact on streetlight, landscaping, and appearance of area  
Response: It is considered that the proposed trees to be removed as part of the
development are not of such significance to the wider streetscape, therefore, their removal
does not warrant refusal of planning permission. Furthermore, the proposal utilises
existing vacant and derelict land, and therefore can be deemed to have an improvement
on the appearance of the area. Subject to approval at committee, the applicant will need
to contact the council’s roads department to relocate the existing streetlight that sits within
one of the proposed parking spaces.  
8.22 Comment: No planning statement regarding business use  
Response: The provision of a planning statement to support the application is not required
for a development of such a scale, and the application has been assessed on its merits,
as well as supplementary information concerning the level of business proposed (e.g.,
client numbers).  
9. Conclusions 
9.1 To conclude, following assessment of the application and notwithstanding the objections
received, it is considered that the proposed mixed-use development satisfactorily
complies with the relevant policies of the North Lanarkshire Local Development Plan and
with the general principles of NPF4. It is, therefore, recommend that planning permission
is granted subject to conditions. 
Page 17 of 74

Page 18

Application No: 
23/00992/FUL 
Proposed Development: 
Extraction of colliery shale from
disused coal mine and rock from
disused quarry face together with
agricultural improvement works and
restoration of colliery site. 
Site Address: 
Dewshill Farm
Forrest Road
Salsburgh
ML7 4NY 
Date Registered: 
22 September 2023 
Applicant: 
RAW Plant & Recycling Ltd
191 Station Road
Shotts
ML7 4BA 
Agent: 
AMS Associates Limited
The Lodge
Philiphaugh Mill
Ettrickhaugh Road
Selkirk
TD7 5AX
Application Level: 
Major Application 
Contrary to Development Plan: 
No
Ward:   
13 – Fortissat 
Cllrs John Leckie, Martin McCulloch, 
Kenneth Stevenson and Margaret Hughes   
Representations: 
5 letters of objection   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The application is supported by sufficient information to demonstrate that the extraction of
colliery shale and rock from the disused coal mine and quarry face together with the
proposed agricultural improvement works and biodiversity enhancement can be
implemented without unacceptable levels of traffic, noise, vibration, dust or visual intrusion.
Adequate mitigation is proposed to minimise any impacts associated with the proposed
development and mitigation would be subject to continual monitoring to ensure compliance
with the conditions attached to the permission. The proposed development raises no Page 18 of 74

Page 19

conflict with Policies PROT C Mineral Resources, PROT A Natural Environment and Green
Network Assets, PP 5 Purpose of Place, AD 5 Amount of Development, EDQ 1 Site
Appraisal, EDQ 2 Specific Features for Consideration and EDQ 3 Quality of Development
of the North Lanarkshire Council Local Development Plan (adopted July 2022) or Policies
3 Biodiversity, 4 Natural Places, 5 Soils, 9 Brownfield, Vacant and Derelict Land and Empty
Buildings, 12 Zero Waste, 14 Design, Quality and Place, 29 Rural Development and 33
Minerals of National Planning Framework 4.   
Planning permission should not be issued until the developer has entered into a Section
75 Agreement with the Planning Authority to secure funds for the restoration of the site. 
Page 19 of 74

Page 20

Page 20 of 74

Page 21

Proposed Conditions:- 
1.  The development hereby approved shall subsist for a period of 15 years from the date of
implementation to be confirmed in writing to the Planning Authority before the development
commences. At the end of the period of 15 years, unless a further planning application is
submitted and approved by the Planning Authority, the development shall cease to operate
and the land will be restored in accordance with the approved Land Management Plan &
Restoration Statement dated March 2023 and Restoration Plan entitled ‘Figure 1.3.1’ dated
April 2023. For the avoidance of doubt, the development shall commence within 3 years of
the date of this permission. 
Reason: To accord with Section 27A of the Town and Country Planning (Scotland) Act 1997
as amended and to protect the visual amenity of the area, beyond the lifetime of the
permission. 
2.  Prior to the commencement of the development, full details of an independent party to act
as a Compliance Officer, shall be submitted to and approved in writing by the Planning
Authority. The Compliance Officer shall undertake monitoring of the development and
operations including archaeology, dust and air quality, hydrology, hydrogeology, flood risk,
noise, transportation, ecology, soils, waste management and biodiversity until full
completion of the restoration phase, in accordance with the submitted Phasing Plan and
Phasing timetable, for the duration of the development hereby approved. The costs
associated with the appointment of the Compliance Officer shall be met by the developer. 
Reason: To monitor and evaluate compliance with this permission 
3.  The Compliance Officer, as required by Condition 2 above, shall annually submit to the
Planning Authority an audit of the conditions attached to this permission. This audit shall
specify the degree of compliance with the conditions and in the event of a failure to comply
with any conditions, provide details of any remedial measures required to safeguard the
environment at the site and the surrounding area. Where it becomes evident to the Planning
Authority that the site is operating outside of the permission granted, a revised audit of
conditions shall be submitted in writing to the Planning Authority for approval within 1 month
of the suspected breach detailing the steps to be taken and timescales involved to regularise
the permission.   
Reason: To monitor and evaluate compliance with this permission 
4.  Prior to the commencement of the development, the developer shall nominate a party to act
as Community Liaison Officer and shall establish a Community Liaison Group, the details
and members of which shall be submitted to and approved in writing by the Planning
Authority. The Community Liaison Officer shall hold regular meetings with members of the
Community Liaison Group to manage community concerns where these relate to the
development the minutes of which shall be submitted to the Planning Authority. For the
avoidance of doubt these meetings shall be held quarterly or as required by the Liaison
Group and agreed by the Planning Authority. 
Reason: In the interests of residential amenity 
5.  Prior to the commencement of the development and notwithstanding the requirements of
Condition 4 above, details of the developer’s procedures for responding to complaints
received by the Planning Authority alleging disturbance to any property as a consequence
of the development, shall be submitted in writing to the Planning Authority for approval. For
the avoidance of doubt, ‘disturbance to any property’ relates to adverse effects on the
amenity of any property affected by the development caused by noise, dust, vehicles and/or
spillages from vehicles onto the public highway. 
Reason: In the interests of residential amenity  Page 21 of 74

Page 22

6.  Prior to the commencement of the development, the developer shall secure the
implementation of a programme of archaeological work in accordance with a Written
Scheme of Investigation which has been submitted in writing and approved by the Planning
Authority. For the guidance of the applicant, the programme of archaeological work shall
include the following: 
a. 5% groundbreaking evaluation of that portion of the development area not previously
impacted.
b. If this exercise identifies sites or objects of merit there should be proposals for further
works potentially including excavation, post-excavation, publication and archiving. 
Reason: To allow the archaeological interest of the site to be preserved by record and to
mitigate the loss of significance and harm to heritage assets. 
7.  Prior to the commencement of the development, a formal Dust Management Plan shall be
submitted in writing to the Planning Authority for approval.  The Dust Management Plan
shall detail the measures to be employed within the site and for vehicles accessing and
leaving the site for the control of dust generated from the works. The Dust Management
Plan shall also detail the procedures the site operator will follow with respect to periodic
routine monitoring of dust emissions from the works, and with respect to the control and
monitoring of dust emissions following any complaints received. 
Reason: To protect local residents from air pollution 
8.  Prior to the commencement of the development, a Construction Environmental
Management Plan (CEMP) shall be submitted to and approved in writing by the Planning
Authority. The CEMP shall set out, as a minimum, site specific measures to control and
monitor impacts arising in relation to hours of operation, lighting, construction traffic, noise,
vibration, dust, and air pollutants.  The CEMP shall also set out arrangements by which the
developer shall maintain communication with residents and businesses in the vicinity of the
site, and by which the developer shall monitor and document compliance with the measures
set out in the CEMP. The development shall be carried out in full accordance with the
approved CEMP. 
Reason: To safeguard the amenities of the neighbouring premises and the area generally. 
9.  If the development has not commenced on site within one year of previous protected
species surveys, further bat, badger and breeding bird surveys shall be undertaken and
submitted to the Planning Authority for approval in writing.  For the avoidance of doubt bat
surveys shall include the quarry and any buildings within the site prior to their demolition.
The badger survey shall include a protection plan for any badger setts that are identified.   
For the avoidance of doubt, a modified common bird census methodology, breeding bird
surveys shall consist of: 
• Three visits with each visit lasting between 3-4 hours;
• Territories to be mapped and transect routes shown (this is to show that the observer is
able to get within 50 metres of every part of the site);
• Proposed mitigation, including a timetable for those works. 
Thereafter, once agreed, any required mitigation shall be implemented to the written
satisfaction of the Planning Authority. 
Reason: To safeguard and protect nature conservation interests. 
10.  Prior to the commencement of the development, details of tree planting, including the
location, species of trees and timescales for planting. This is to compensate for the loss of Page 22 of 74

Page 23

trees associated with the proposed road realignment works at the site entrance, as shown
on 
Drawing DE RP 04 dated July 2024, shall be submitted in writing to the Planning Authority
for approval. 
Reason: In the interests of natural conservation and visual amenity 
11.  Prior to the commencement of the development, a comprehensive site investigation report
shall be submitted in writing to the Planning Authority for approval. The investigation(s) must
be carried out in accordance with current best practice advice such as BS10175: 'The
Investigation of Potentially Contaminated Sites' or CLR 11. The report must include a site-
specific risk assessment of all relevant pollutant linkages and a conceptual site model.
Depending on the results of the investigation, a Detailed Remediation Strategy may be
required. 
Reason: To establish whether site decontamination is required in the interests of public
health. 
12.  Any remediation works identified by the site investigation report(s) as required by Condition
11 above, shall be carried out in accordance with the Detailed Remediation Strategy and a
certificate signed by a suitably qualified specialist /competent person in such matters shall
be submitted to the Planning Authority confirming that remediation works where required
have been carried out in accordance with the agreed Remediation Strategy. 
Reason: To ensure that any remediation identified has been implemented in the interests
of public health. 
13.  Notwithstanding the terms of Condition 12 above a final validation report signed by a
suitably qualified specialist /competent person in such matters shall be submitted to the
Planning Authority to confirm that all remediation works submitted and approved under the
terms of Condition 12 of this permission have been completed. 
Reason: To ensure that the site is free of contamination in the interests of public health. 
14.  Within 6 months of cessation of the shale extraction works (proposed for Phase 5 Year 10
of the approved Phasing Plan and Phasing Timetable), the developer shall submit an
updated Biodiversity, Management and Monitoring Plan in writing for the approval of the
Planning Authority.  The updated Plan shall include details of implementation and
monitoring of the proposals outlined in the approved Biodiversity Net Gain Assessment by
Gavia Environmental dated 22/04/2024 and accompanying Figure 2 Post Enhancement
Plan. 
Reason: In the interests of natural conservation 
15.  No later than 6 months prior to the expiration of this consent, an updated detailed restoration
and after-care strategy, based upon the approved Land Management Plan & Restoration
Statement, Alistair Smith Associates, dated March 2023 and the approved Landscape
Restoration Plan (Figure 1.3.1) shall be submitted to the Planning Authority for approval in
writing. The strategy shall include proposals for the management and the timing of the
restoration and after-care of the site and thereafter, the works shall be undertaken in
accordance with the updated strategy unless otherwise agreed in writing with the Planning
Authority. 
Reason: To ensure restoration of the development and after-care of the site is carried out
in an appropriate manner in the interests of safety, amenity and environmental protection. 
16.  The ecological mitigation shall be carried out in accordance with the recommendations
contained in Section 8 of The Preliminary Ecological Appraisal Update by Baker Ecology Page 23 of 74

Page 24

dated May 2024. 
Reason: In the interests of nature conservation 
17.  Biodiversity enhancement shall be carried out strictly in accordance with the approved
Phasing Plan and Phasing Timetable and recommendations contained in the approved
Biodiversity Net Gain Assessment, Gavia Environmental Ltd, dated April 2024 and
Biodiversity Plans (Figures 1 and 2), 
Reason: In the interests of nature conservation 
18.  All loaded haulage vehicles leaving the site shall be adequately sheeted and loads shall be
trimmed prior to leaving and all other vehicles leaving the site shall be in such a condition
as not to emit dust or deposit mud, slurry or other deleterious material on the public road
network.  
Reason: To prevent fugitive dust affecting sensitive properties 
19.  The approved access road shown on the Site Entrance Plan (Drawing SE RP 01) dated
May 2024, shall be surfaced in concrete and a wheel-wash and mechanical sweeper shall
be installed, maintained and employed for the cleaning of wheels and chassis of all vehicles
leaving the site prior to the commencement of works on site. Thereafter, the condition of the
access road and equipment shall be periodically monitored and maintained for the duration
of the works permitted. 
Reason: In the interests of traffic safety and prevention of damage to the public road network
20.  The site access gates shall be set back from the junction with Forrest Road by a minimum
of 15m to permit waiting off road for HGVs and maintained as such for the duration of the
works hereby approved. 
Reason: In the interests of traffic safety and prevention of damage to the public road
network.
21.  Prior to the commencement of the development, trees within the visibility splays as shown
on Drawing DE RP 04 shall be removed and the visibility splay shall be maintained for the
duration of all operations on site as approved by this permission. 
Reason: To provide unobstructed sight lines within the visibility splays. 
22.  All large and/or heavy good vehicles accessing and exiting the site shall utilise the approved
LGV/HGV route as shown on the submitted Traffic Route Plan (Drawing 9715) and no
vehicles shall travel through the village of Salsburgh.
Reason: To protect the amenities of sensitive properties. 
23.  The proposed operations shall be carried out strictly in accordance with the approved
Phasing Plan (Drawing 9706-B) and corresponding Phasing Timetable (Document PI
submitted 15 May 2024) unless otherwise agreed in writing by the Planning Authority. 
Reason:  To ensure operational activities are carried out in accordance with the approved
phasing plan and timetable. 
24.  The construction of acoustic earth bunds including bunds located to the east and west of
the proposed site compound and to the south of the colliery site as shown on the Approved
Phasing Plan (Drawing Number 9706-B dated 15.05.24), shall be completed within the first
two months of commencing the development and/or ahead of any other significant noise
producing works.  Page 24 of 74

Page 25

Reason: To protect the residential amenity of Dewshill Cottage to the south of the
development site. 
25. The development shall be implemented strictly in accordance with the approved Noise
Monitoring Scheme by Vibrock referenced R24.1055/NMS/1/RK and dated 28 February
2024 with respect to periodic routine monitoring of noise emissions from the works and the
control and monitoring of noise emissions following any complaints received by the Planning
Authority. 
Reason: In the interests of residential amenity. 
26.  That, at all times during the carrying out of operations authorised or required by this
permission, a water bowser and towing vehicle, both in kept in working order, shall be
retained on site for use in the event of dust emission nuisance problems within the site to
the satisfaction of the Planning Authority.
Reason: To prevent fugitive dust affecting sensitive properties
27.  The proposed development shall be carried out strictly in accordance with the
recommendations contained in Section 6 Surface Water Management of the submitted
Flood Risk Assessment by Hafren Water dated April 2023. 
28.  That operations on the site, for which planning permission is hereby granted, shall take
place between the following hours only: 
08:00 hours to 19:00 hours - Monday – Friday
08:00 hours to 13:00 hours - Saturdays
with no noise producing works undertaken on Sundays and Public Holidays 
Reason: In the interests of residential amenity. 
COAL AUTHORITY INFORMATIVE 
The proposed development lies within an area that has been defined by the Coal Authority as
containing coal mining features at surface or shallow depth.  These features may include: mine
entries (shafts and adits); shallow coal workings; geological features (fissures and break lines);
mine gas and former surface mining sites.  Although such features are seldom readily visible,
they can often be present and problems can occur, particularly as a result of new development
taking place. 
Any form of development over or within the influencing distance of a mine entry can be dangerous
and raises significant land stability and public safety risks.  As a general precautionary principle,
the Coal Authority considers that the building over or within the influencing distance of a mine
entry should be avoided. 
In exceptional circumstance where this is unavoidable, expert advice must be sought to ensure
that a suitable engineering design which takes into account all the relevant safety and
environmental risk factors, including mine gas and mine-water.  Your attention is drawn to the
Coal Authority Policy in relation to new development and mine entries available at: 
www.gov.uk/government/publications/building-on-or-within-the-influencing-distance-of-mine-
entries 
Any intrusive activities which disturb or enter any coal seams, coal mine workings or coal mine
entries (shafts and adits) requires a Coal Authority Permit.  Such activities could include site Page 25 of 74

Page 26

investigation boreholes, excavations for foundations, piling activities, other ground works and any
subsequent treatment of coal mine workings and coal mine entries for ground stability purposes.
Failure to obtain permission to enter or disturb our property will result in the potential for court
action. 
If any coal mining features are unexpectedly encountered during development, this should be 
reported immediately to the Coal Authority on 0345 762 6848.  Further information is available on
the Coal Authority website at: 
www.gov.uk/government/organisations/the-coal-authority 
Background Papers: 
Consultation Responses: 
NLC Greenspace - received 13 May 2024
NLC Archaeology Service - received 19th October 2023
NLC Protective Services – received 13 November 2023, 5 March 2024, 5 August 2024
NLC Traffic & Transportation – received 21 May 2024 and 2nd July 2024.
The Coal Authority - received 27 October 2023
Scottish Water - received 25 October 2023
HSE - received 25 October 2023
Scottish Gas Network - received 7 May 2024
SEPA – received 29 May 2024
Transport Scotland – no response received.
Nature Scotland – no response received. 
Contact Information: 
Any person wishing to inspect these documents should contact Ann McGregor at 01236 632500 
Report Date: 
2 August 2024 
Page 26 of 74

Page 27

APPLICATION NO. 23/00992/FUL 
1. Site Description 
1.1 The application site relates to the former Dewshill Colliery, which ceased operating in the
1950s.  The site lies approximately 3km east of the village of Salsburgh and 5km west of
Harthill on the north side of the M8 motorway and is centred on National Grid Reference
NS 85384 64049, postcode ML7 4PA. Forrest Road defines the site boundary to the east
beyond which lies Forrestburn Reservoir, approximately 550m to the northeast. Duntilland
Quarry lies approximately 500m to the west. 
1.2 The site occupies an area of 21.4 hectares and consists of the colliery site, pastureland to
the north and an existing farm access track west of Forrest Road and north of the colliery
site. Access to the site is off Forrest Road which connects to the B7066 Hirst Road
approximately 1.5 km west of Junction 5 of the M8. 
1.3 The site is characterised by a heavily modified landform to the east and a larger flat-topped
bing to the west. Elevations range from around 270m AOD (above ordnance datum) along
the eastern boundary to 250m AOD in the west.  The site has some limited vegetation,
primarily tall grasses growing around the fringes of the quarry and colliery site and scrub
and young trees which have established around the edges of the site and within voids.   A
further track along the southern edge of the colliery site, north of Dewshill Cottage,
provides access from the western bing to Forrest Road.  The western bing is steep sided
rising to c.283m and is grassed over with a few self-seeded trees. The southwestern area
of the site is more open and contains rough grasses and scrub. Higher undulating land to
the west of Dewshill Farm, which is proposed for reprofiling and agricultural improvement,
consists of poor-quality agricultural land.  This land is currently grazed for the milking
operation carried out at Dewshill Farm.   
1.4 The immediate landscape surrounding the site is characterised by a mix of countryside
with open views to the north and east across Forrestburn Reservoir, by mineral
development at Duntilland Quarry to the west and by lower lying land in the south where
the site is defined by hedges and tree cover that limit views to the M8 motorway.  The M8
motorway separates the site from a row of semi-detached houses approximately 120m to
the southeast.   The wider landscape lies within the Plateau Moorlands Landscape
Character Type (Central Plateau) where the presence of coal reserves and, to a lesser
extent, hard rock deposits, have cumulatively, had a major effect on the landscape in the
form of hard rock quarries, bings and tips, areas of derelict land, operating open-cast
workings and associated infrastructure including disused railway embankments. 
2. Site History 
•  98/00401/FUL - Erection of Agricultural Building 
•  11/00475/FUL- Erection of Two Agricultural Sheds 
•  11/00477/FUL - Erection of 67m Wind Turbine with Ancillary Equipment/Infrastructure. 
•  12/00225/PREAPE - Installation of Wind Turbine 
•  12/01023/PAN - Proposal of Application Notice: Proposed Drilling Operations 
•  14/01379/PREAPE - Proposed Wind Turbine Development (130m High) 
•  15/00016/EIASCO - Erection of 3 Wind Turbines: Requested for EIA Scoping Opinion 
•  18/00357/PRA - Prior Notification for Farm-related Building Works (Non-residential) 
•  21/00076/PPP - Replacement farmhouse and demolition of existing farmhouse (in
principle)
•  21/01632/PPP - New farmhouse (in principle)
•  21/01870/FUL - Two agricultural sheds and two slurry lagoons
•  22/00130/PRN - Agricultural Shed 
•  22/00216/PRN - Agricultural shed 
•  22/00541/MSC - Single dwellinghouse (application covering matters specified by Page 27 of 74

Page 28

conditions of planning permission in principle 21/01632/PPP) and associated
infrastructure 
•  22/01094/EIASCR - EIA Screening Opinion - Reclamation of Former Colliery Site
Together with Agricultural Land Improvement Works on Adjoining Land 
•  22/01440/PAN - Extraction and Processing of Colliery Shale and Reclamation of the
Former Colliery Site and Quarry and Consequential Raising and Profiling of Land at
Dewshill Farm 
•  23/00652/PRN - Site re-levelling and engineering works to create cow ramp 
•  23/00992/FUL - Extraction of colliery shale from disused coal mine and rock from
disused quarry face together with agricultural improvement works and restoration of
colliery site 
•  24/00360/PRN - Prior Notification for Farm-related Building Works (Non-residential). 
3. Proposed Development 
3.1 The application seeks full planning permission for extraction of colliery shale from the
disused colliery and mine, together with rock extraction and profiling of the disused quarry
face, agricultural improvement works and consequential land raising, importation of inert
waste, restoration of the colliery site and off-site biodiversity enhancement. No blasting is
proposed.  The total period of operational development would be in the region of 15 years.   
3.2 The development works would take place within two areas of the application site; the
northern half of the site consisting of 17.8ha of poor-quality agricultural land and the
southern half of the site consisting of approximately 12.9ha of colliery waste tips of which
6.4 ha would form the proposed shale extraction and rock face profiling areas. 
3.3 In the southern half of the site, the proposed operations would involve extraction and
processing of shale from the former colliery site for sale to the construction industry as a
secondary aggregate.  The colliery site would be shielded with the remaining shale being
retained around the perimeter of the site to form a bowl like acoustic bund and imported
soils being spread around the bund to provide a soil planting surface. The bund would be
planted by native species trees including silver birch, hazel, rowan, Scots pine etc.  As
part of the reprofiling works in the northern half of the site, the fines derived from
processing tipped material in the southern half would be deposited on land in the northern
half, together with imported soils.  It is intended that the reprofiling works would improve
the agricultural potential of the land as part of a wider agricultural expansion plan and
would not significantly alter the landform in this area of the site. 
3.4 The volume of shale to be extracted would be in the region of 356,000m3. The volume of
imported clays and soils to improve the agricultural land in the northern half of the site
would be in the region of 297,500m3. The imported soil would be delivered to the site by
HGV road going vehicles.   
3.5 The proposed HGV route from Junction 5 of the M8 would ensure that vehicles did not
pass through the village of Salsburgh. Vehicles would access the site via the B7066 Hirst
Road turning right onto Forrest Road to enter the site and/or left onto B7066 when exiting
the site.   An upgraded internal access road/ site entrance running along the northern edge
of the colliery site (south of the agricultural improvement land site), together with wheel
washing facilities etc is also proposed, together with realignment and resurfacing of the
road past the site entrance to Dewshill Farm.  A section of Forrest Road would be widened
and realigned from the overbridge to the proposed site entrance in order to improve
visibility. Trees within the visibility splay close to the proposed site entrance on the east
side of Forrest Road will also be removed. 
3.6 The proposed development falls within Schedule 2 of the Town and Country Planning
(Environmental Impact Assessment) (Scotland) Regulations 2017 and has been screened
to determine whether it is likely to have significant effects on the environment. It was
determined that the development will not have significant environmental effects and is not Page 28 of 74

Page 29

therefore considered to constitute Environmental Impact Assessment (EIA) development. 
4. Applicant’s Supporting Information 
4.1 The application is accompanied by the following supporting information: 
• PAC Report, AMS Associates Limited, August 2023
• Land Management Plan & Restoration Statement, AMS Associates Ltd, March
2023
• Design and Access Statement, AMS Associates Ltd, October 2023
• Supporting Statement, AMS Associates Ltd, August 2023
• Waste Management Plan, AMS Associates Ltd, January 2024
• Traffic Statement, AMS Associates Ltd, February 2024
• HGV Route Plan, AMS Associates Ltd, February 2024
• Phasing Plan and Phasing Timetable, AMS Associates Ltd, May 2024
• Flood Risk Assessment, Hafren Water, April 2023
• Water Impact Assessment Report, Hafren Water, April 2023
• Landscape and Visual Impact Assessment, Heplan, March 2023
• Ecological Assessment, Nigel Rudd, February 2023
• Phase 1: Ground Condition Assessment (Contamination), Peter Brett, July 2016 
• Biodiversity Net Gain Assessment, Gavia Environmental Ltd, April 2024
• Archaeological Desk Based Assessment, Guard Archaeology, February 2023
• Air Quality Assessment, Vibrock, February 2023
• Noise Impact Assessment, Vibrock, January 2023
• Updated Bat Roost Survey, Baker Ecology, May-June 2024 
5. Development Plan 
5.1 The statutory development plan consists of the National Planning Framework 4 (NPF4)
and the North Lanarkshire Local Development Plan, Adopted 6th July 2022 (LDP). 
5.2 The following LDP and NPF4 policies apply:   
• LDP Policy PROT A Natural Environment and Green Network Assets 
• LDP Policy PROT C Mineral Resources 
• LDP Policy PP 5 Purpose of Place 
• LDP Policy AD 5 Amount of Development
• LDP Policy EDQ 1 Site Appraisal
• LDP Policy EDQ 2 Specific Features for Consideration
• LDP Policy EDQ 3 Quality of Development
• LDP Policy CI Contributions to Infrastructure 
• NPF4 Policy 1 Climate Tackling the climate change and nature crisis
• NPF4 Policy 2 Climate mitigation and adaptation
• NPF4 Policy 3 Biodiversity 
• NPF4 Policy 4 Natural Places
• NPF4 Policy 5 Soils
• NPF4 Policy 9 Brownfield, Vacant and Derelict Land and Empty Buildings
• NPF4 Policy 12 Zero Waste
• NPF4 Policy 13 Sustainable Transport
• NPF4 Policy 14 Design, Quality and Place 
• NPF4 Policy 22 Flood Risk and Water Management
• NPF4 Policy 23 Health and Safety
• NPF4 Policy 29 Rural Development
• NPF4 Policy 33 Minerals 
Page 29 of 74

Page 30

6. Consultations 
6.1 NLC Greenspace – Has no objection to the application and has advised that a condition
be attached to ensure that if the development does not commence within one year of the
date of the Ecological Appraisal, updated protected species surveys should be submitted
to the Planning Authority for approval. 
6.2 NLC Archaeology Service – Has confirmed that the proposed development has the
potential to damage previously unknown archaeological remains. However, as the scope
and scale of such putative remains are unknown, there are insufficient grounds to object
to the development. Therefore, a condition should be attached to ensure that in advance
of any construction works, an experienced and suitably qualified archaeological contractor
undertakes a programme of archaeology in accordance with a Written Scheme of
Investigation (WSI) to mitigate against the potential loss of the site. The WSI should be
submitted to the Planning Authority for approval in consultation with the Council’s
Archaeologist. 
6.3 NLC Protective Services – Has no objection to the application subject to conditions relating
to dust management and monitoring; noise monitoring; phasing of the construction of an
acoustic bund and hours of operation, 
6.4 NLC Traffic & Transportation – Has no objection to the application subject to conditions
relating to HGV routing, road realignment, removal of trees, impermeable surfacing of
internal road and wheel washing facilities. 
6.5 The Coal Authority – Has no objection to the application but has recommended that
informatives are placed on any decision to grant planning permission. 
6.6 Scottish Water – Has no objection to the application. 
6.7 HSE - Does not advise against the granting of planning permission on safety grounds. 
6.8 Scottish Gas Network – Does not have any high-pressure assets within the vicinity of the
application and as such has no objection or comments to make. 
6.9 SEPA – Has no comments to make. 
7. Representations 
7.1 Following the standard neighbour notification process and press advertisement, the
Planning Authority received 5 letters of objection to the proposal. Grounds of objection
include the following matters: 
7.2 Objection: Concern raised regarding road safety due to the number of lorries travelling to
and from the site along Forrest Road and the speed at which they travel. This is a particular
issue for pedestrians, children accessing the nearby play area and for users of mobility
scooters since they cannot be accommodated on the narrow footway. 
Response: The national speed limit on Forrest Road is currently 60mph.  However, in
recognition of concerns raised by members of the community, the grant of planning
permission would be subject to a number of conditions which the developer is in
agreement with.  These include: establishment of a Community Liaison Group and
quarterly meetings with the developer which community members could attend to raise
concerns regarding the development, particularly in relation to matters concerning
residential amenity (speed of vehicles, dust, noise, debris and spillages on the public road
etc); details of the developers complaints handling procedure is to be submitted and
approved by the Planning Authority; requirements to ensure that all loaded haulage
vehicles leaving the site are adequately sheeted to avoid deposit of mud, slurry or other
deleterious material on the public road network and; an approved LGV/HGV route to Page 30 of 74

Page 31

ensure that no vehicles accessing and exiting the site shall travel through the village of
Salsburgh. 
7.3 Objection: Concern raised in respect of lorries travelling through the village of Salsburgh. 
Response: A vehicle route plan has been provided as part of the submitted Traffic
Assessment. Should planning permission be granted, a condition would be attached to
ensure that all heavy goods vehicles travelling to and from the site are not permitted to
travel through the village of Salsburgh. 
7.4 Objection: Concern raised about damage to the road surface caused by HGVs utilising
Forrest Road. 
Response: A procedure is in place to report potholes, uneven surfaces and cracked paving
slabs to North Lanarkshire Council: Roads and pavements: report a problem | North
Lanarkshire Council.  Note that Transport Scotland is responsible for repairing the
following roads: A8 and A725 trunk roads and the M8, M73, M74 and M80.   
7.5 Objection: Concern raised regarding spillages from HGVs onto the public road. 
Response: Should planning permission be granted, a condition would be attached to
ensure that vehicles are appropriately sheeted when accessing/leaving the site and that
wheel washing facilities are provided at the site entrance. 
7.6 Objection: Concern raised relating to contamination of nearby waterbodies. 
Response: Should planning permission be granted, pre-commencement conditions would
be attached requiring an intrusive ground investigation to be submitted to the Planning
Authority for approval in order to assess ground conditions and any risks associated with
contaminated land, together with a Construction Environmental Management Plan to
ensure that all site operations are managed in accordance with relevant guidance,
including drainage and management of the water environment. 
7.7 Objection: Concern raised relating to noise nuisance from ongoing operations and HGVs
traveling along Forrest Road. 
Response: Should planning permission be granted, various noise mitigation measures
would be put in place via condition to protect residential amenity including acoustic bunds
and noise monitoring.  Conditions would also be placed on the grant of planning
permission to ensure establishment of a Community Liaison Group and quarterly meetings
with the developer which community members could attend to raise concerns regarding
the development, particularly in relation to matters concerning residential amenity (speed
of vehicles, dust, noise, debris and spillages on the public road etc).  A further condition
would be attached requiring details of the developers complaints handling procedure to
be submitted and approved by the Planning Authority 
7.8 Objection:  Concern raised about absence of consultation with Harthill Community
Council. 
Response: The site lies within the Salsburgh Community Council.  The Applicant is legally
required to consult only the community council any part of whose area is within or adjoins
the land where the proposed development is situated. The site is not within nor does it
adjoin the Harthill Community Council area. 
7.9 Objection:  Concern raised that no justification of locational need has been provided. 
Response: The application site is a former colliery site and is classed as ‘previously
developed land/brownfield land’. The proposed extraction of shale on a former colliery site Page 31 of 74

Page 32

that is characterised by bings and heavily modified landform, together with proposals for
restoration, aftercare and biodiversity net gain is considered a sustainable use of the site
and overall. The proposal will not result in significant adverse environmental impacts and
will provide an adequate buffer zone between sensitive receptors and settlements in
accordance with Policy 33 d) Minerals of NPF4. The proposal is also in accordance with
Policy PP 5 Purpose of Place of the LDP which requires proposals to demonstrate a specific
locational requirement where agricultural diversification is proposed. 
7.10 Objection: Concern raised regarding hours of operation. 
Response: Should planning permission be granted, the hours of operation would follow
North Lanarkshire Council’s longstanding guidance ‘Noise from Construction
Sites/Operations’ and a condition to this effect is recommended. 
8. Planning Assessment 
The Development Plan
8.1 Section 25 of the Town and Country Planning (Scotland) Act 1997 as amended provides
that where, in making a determination under the Planning Acts, regard is to be had to the
Development Plan unless material considerations indicate otherwise. The Development
Plan consists of The North Lanarkshire Local Development Plan (Adopted 6th July 2022)
and the National Planning Framework 4 (NPF4, Adopted on 13th February 2023). 
Consequently, the determination of the application must be made in accordance with both
and, in the event of any incompatibility between NPF4 and the Local Development Plan,
NPF4 is to prevail.  The application does not raise any issues of regional or national
significance and can therefore be determined in accordance with policies contained in the
Local Development Plan (Adopted 6 July 2022) where these are compatible with NPF4.
Statements in NPF4 are also material to the determination of the application. 
PAC Consultation /PAC Report 
8.2 The application belongs to the category of major development in accordance with
Regulation 2 (1) of the Town and Country Planning (Hierarchy of Development) (Scotland)
Regulations 2009 and was subject to pre-application consultation.  Following receipt of a
Proposal of Application Notice, two public events were held on 16th March 2023 and 20th
April 2023 in Salsburgh Community Centre, in accordance with Regulation 7 of the Town
and Country Planning (Development Management Procedure) (Scotland) Regulations
2013 as amended. The events were attended by 34 people including the chair of
Salsburgh Community Council. The main issues raised during the public events relate to
the following matters: the proposed route of HGVs and request to ensure that they do not
travel through Salsburgh; the proposed restoration programme and request to ensure full
restoration /restoration bond and aftercare and; queries relating to the proposed waste
and imported material.  All of the above matters have been addressed by the developer
and are considered in this report. 
Principle of the Development 
8.3 Policy PP 5 Purpose of Place of the LDP requires proposals to demonstrate a specific
locational requirement, which may include extending existing businesses in the
countryside and/or and agricultural diversification whilst ensuring that development is sited
and designed to minimise lifecycle greenhouse gas emissions and adapt to current and
future risks of climate change in accordance with NPF4 Policy 1 Tackling the climate and
nature crises and NPF4 Policy 2 Climate mitigation and adaption. Similarly, Policy PROT
C Mineral Resources of the LDP directs proposals for extraction to extension areas within or
adjacent to existing operational sites where proposals require to be assessed in relation to
their environmental, social and economic impacts and to restoration.   The former Dewshill
Colliery site has been derelict since the colliery closed in the 1950s, although it is understood Page 32 of 74

Page 33

that recovery of anthracite took place within the colliery in the 1980s for a limited period.
Whilst, not an existing operational mineral site, the site is nevertheless characterised by bings
and tips and remnants of past mining legacy and is currently classed as derelict on the
Council’s Vacant and Derelict Land Register (Last Survey 2022). The site is owned by the
operators of the adjacent Dewshill Farm and as part of the current proposal to extract shale,
the owners also seek to reprofile land in northern half of the site consisting of some 17.8ha
of poor-quality agricultural land in order to improve the agricultural potential of land as part
of an agricultural expansion plan.  The proposed development demonstrates locational
requirement in accordance with Policies PP5 and PROT C of the LDP and, subject to
satisfying all other requirements of the Development Plan, is in principle compatible with the
aims and objectives of Policies 1 and 2 of NPF4. 
8.4 Policy 29 a) viii. Rural Development of NPF4 supports development proposals that contribute
to the sustainability and economy of rural communities. Similarly, Policy 33 d) Minerals of
NPF4 supports proposals for the sustainable extraction of minerals, that is where it can be
demonstrated that the proposal will not result in significant adverse environmental impacts,
will provide an adequate buffer zone between sites and settlements, will minimise transport
impacts through the number and length of lorry trips and, will include a high standard of
restoration and aftercare. The application proposes extraction and processing of shale for
onward sale to the construction industry as a secondary aggregate. Given that mineral
products are essential to the development of the built environment (‘the annual turnover
of extraction in the UK was £15bn in 2019’: Minerals: bedrock of the economy share, RICS
14 January 2019), it is anticipated that the development will make a significant contribution
to the sustainability and economy of the rural area in line with the requirements of Policy
29 a) iii of NPF4. Whilst there are a number of residential properties within proximity to the
site, including Dewshill Cottage which lies immediately south of the former colliery site and
Nos 1-18 Dewshill Cottages which lie immediately south of the M8 motorway, residential
amenity will be protected through various mitigation measures addressed elsewhere in
this report. 
8.5 In view of the site’s previous mining use and current derelict land status and subject to
mitigation to protect residential amenity, restoration works and the proposal satisfying all
other requirements of the Development Plan, the proposed development is in accordance
with Policies 1, 2, 29 a) viii and 33d) of NPF4 and Policies PROT C and Policy PP 5 of the
LDP. 
Landscape and Visual Impact 
8.6 Policy EDQ 1 Site Appraisal of the LDP and Policy 14 Design, Quality and Place of NPF4
require proposals to integrate successfully into the local area and to address impacts on
landscape character and reinforce identity.  Policy 33 Minerals of NPF4 supports the
sustainable extraction of minerals where this will not result in significant adverse landscape
and visual impacts and Policy 9 Brownfield, Vacant and Derelict Land and Empty Buildings
of NPF4 will support proposals that will result in the sustainable reuse of brownfield land. In
determining whether the reuse is sustainable, the biodiversity value of brownfield land which
has naturalised should be taken into account. 
8.7 A Landscape and Visual Impact Assessment (LVIA) has been submitted in support of the
application.  The LVIA considers the effects of the development on landscape fabric,
landscape character and on visual amenity. 
8.8 Landscape Fabric – The site is divided into two elements pastureland in the north which has
naturalised in part and an abandoned colliery site to the south which presents as spoil heaps,
small ponds, grassland, scrub, bare ground and a disused unstable quarry face.  The
development will result in incremental large-scale change to the existing landscape fabric in
the southern half of the site following the proposed extraction of shale and creation of a level
area and bowl like acoustic bund around the perimeter of the site.  The deposit of materials
from the southern half of the site, together with the importation and spreading of soils and
consequent reprofiling of land in the northern half of the site would not significantly alter Page 33 of 74

Page 34

the landform in this part of the site.  The direct effects on the landscape fabric during the
construction phase, although large scale, would be moderate and localised with final
restoration of the site resulting in beneficial restructuring of the landscape fabric. Significant
effects on the landscape fabric in the long term are not anticipated. 
8.9 Landscape Character -The site is located in the large-scale landform of the Plateau
Moorlands Landscape Character Type (Central Plateau) where past deep mining and
opencast mining activity have had a major influence on the landscape character. The
sensitivity of the landscape is therefore considered to be low with capacity to
accommodate further change. The magnitude of change as a result of the proposed
development would be moderate within the immediate vicinity of the site, reducing to slight
/negligible with distance particularly from the south since the site is sheltered by a
woodland belt on the north side of the M8 motorway. From the north, west and east, the
oblique nature of views to the site and across the landscape would provide an effective
level of containment to the operations. Consequently, no significant effects on landscape
character are anticipated.   
8.10 Visual Amenity - Views from key locations within a defined study area of a 1km radius circle
centred on the application site were considered in the visual amenity assessment of the LVIA. 
The selected locations include: the Graveyard to the east of the Kirk of Shotts, Shottsburn
Road, House O’ Muir Road, M8 slip road beside Blairmains Guest House, Bentfoot,
Forrestburn Road and Forrestburn Road above Forrestburn Reservoir. Within 500m of the
site, elements of the construction works are likely to be visible. Beyond this distance from
certain viewpoints (some noted above), visibility is less distinct, assimilating with existing
elements in wider views of the landscape.  Visibility from the north would be limited since
the land rises in the north and the site would be contained from view.  From the south, the
existing western colliery bing and quarry are visible. The proposed extraction of shale will
gradually remove the western bing until it is completely removed from visibility and re-
shaped into a lower landform.  The extent of the working face that will be visible in the
short term will be similar in extent to the existing view. Further to the southeast and
southwest, the proposed development will be largely contained by the existing landform
which will limit the majority of direct views to the site.  In the short to medium term as
restoration progresses, views of the site from the south will be softened and contained
and replaced by views of a proposed tree belt around the acoustic bund. Consequently,
no significant effects on visual amenity are anticipated.   
8.11 The landscape and visual effects associated with the proposed development do not raise
any conflicts with Policy EDQ1 of the LDP or Policies 14 and 33 of NPF4 as the effects
would be moderate in the short to medium term and would be viewed in the context of a
heavily modified existing landscape which has been affected by former deep mining and
opencast mining activity. In the longer term, the proposed restoration works, including
planting of native tree and shrub species through traditional forestry planting techniques
using cell grown stock which will establish quickly, will help the site integrate successfully
with the surrounding landscape and help return the site to a condition closer to its former
use prior to Dewshill mining activities in accordance with Policy 9 of NPF4. 
Ecology and Biodiversity 
8.12 Development that significantly affects protected species will only be permitted under Policy
PROT A Natural Environment and Green Network Assets (Category 5) of the LDP and Policy
4 Natural Places of NPF4, where an appraisal has demonstrated that the protected species
would not be compromised or that any significant adverse effects on the protected species
can be mitigated.   
8.13 A Preliminary Ecological Appraisal (PEA) dated February 2023 and an updated PEA dated
May 2024 have been submitted in support of the application. The updated PEA notes that
species diversity within the site is relatively poor and that of the habitats evidenced, they are
secondary colonising habitats.  There is no evidence of otters, badgers, water vole or bat Page 34 of 74

Page 35

roosts within the survey area. However, the site is considered to have locally moderate value
for breeding birds, particularly within the open pastureland in the northern half of the site.
Proposed mitigation includes either: a) the establishment of any immediate exclusion areas
following a pre-start walkover survey where site preparation works in certain parts of the site
would be delayed until the breeding season has finished whilst site preparation works in other
parts of the site could continue without disruption to breeding birds or; b) any site preparation
works such as vegetation removal or soil stripping would be carried out between October
and the end of February to completely avoid the bird breeding season, so as to remove any
possibility of disruption to breeding birds.   Following the identification of crevices in the former
Dewshill Quarry face as potential roost features a bat roost survey was commissioned during
May 2024 to confirm whether any roosting bats were present. The survey consisted of two
dusk emergence surveys (one in May and one in June 2024).  The surveys conclusively
proved that no active bat roost was present in the former Quarry face. Therefore, roosting
bats are not an ecological constraint for the proposed former Quarry face re-profiling works. 
8.14 The proposed mitigation detailed in the updated PEA by Baker Ecology dated May 2024
relative to breeding birds, demonstrates compliance with Policy PROT A Natural
Environment and Green Network Assets (Category 5) of the LDP and Policy 4 Natural Places
of NPF4.  It is recommended that conditions are attached to any grant of planning permission
to ensure that the proposed mitigation is carried out in accordance with the recommendations
contained in the updated PEA. 
8.15 Policy 3 Biodiversity of NPF4 provides that development proposals shall contribute to the
enhancement of biodiversity, including where relevant, restoring degraded habitats and
building and strengthening nature networks. A Biodiversity Net Gain Assessment by Gavia
Environmental, dated April 2024, is submitted in support of the application. Proposals for
biodiversity net gain both on-site and off-site are contained in the Assessment and shown in
the submitted Biodiversity Plans (Figures 1 and 2) and include: creation of new
woodland/planting of trees and hedgerows to increase habitat connectivity, foraging corridors
and nesting opportunity; creation of wildflower meadow on open pasture land; installation of
bat boxes and; off-site pond enhancement to provide diversity, shelter and food for
amphibians and invertebrates.  Whilst ‘net gain’ is not a requirement of NPF4 at the present
time, the Biodiversity Net Gain Assessment advises that the proposed post-development
enhancements will achieve biodiversity net gain of +43.24% from the site baseline. The
proposed biodiversity measures exceed the requirements of Policy 3 of NPF4 and are
therefore considered acceptable. 
Access and Transportation 
8.16 Policies EDQ 1 Site Appraisal and EDQ3 Quality of Development of the LDP requires all
development to achieve safe site access into and through development. The impact of traffic
generated by the development on the road network and highway safety is accounted for in
Policy CI Contributions to Infrastructure of the LDP which provides that all new development
individually or cumulatively that generates a requirement for new or enhanced infrastructure
or services, will be expected to contribute towards the provision of the required infrastructure,
facilities and services. Policy CI is generally compatible with Policy 13 Sustainable
Transport of NPF4 which requires development to incorporate safety measures including
those to adequately mitigate against any impacts on local public access routes through,
for example, reduction in the number and speed of vehicles. 
8.17 The proposed development will generate approximately 60 LGV/HGV trips per day. 
Lorries will be securely sheeted to prevent spillages onto the public road network and will
follow the route of the submitted Traffic Route Plan (Drawing Number 9715), along Forrest
Road and Hirst Road towards junction 5 of the M8, thereby bypassing the village of
Salsburgh.  Forrest Road will be upgraded and realigned from the proposed site entrance
to the overbridge which will ensure adequate visibility splays are provided for. Other
measures will be conditioned to protect residential amenity, including: concrete surfacing
of the internal access road together with wheel wash facilities; controlled hours of
operation; a noise monitoring scheme; a complaints handling procedure and; Page 35 of 74

Page 36

establishment of a community liaison group to allow members of the community to raise
concerns with the developer during site operations.    Subject to conditions to protect
residential amenity, NLC Roads does not object on grounds of access or transportation. 
The proposed development is therefore considered to comply with Policies EDQ and EDQ3
of the LDP and Policy 13 of NPF4. 
Noise Impact  
8.18 Policy PROT C Mineral Resources (Category C1 Construction Minerals) aims to take
account of any changes to national policy relative to noise impacts from mineral extraction
processes.  Both Policies 23 Health and Safety, and 33 (d) Minerals of NPF4 requires that a
development demonstrates acceptable levels (including cumulative impact) of noise.   
8.19 A Noise Impact Assessment (NIA) dated January 2023 and NIA Addendum dated
February 2024 by Vibrock have been submitted in support of the application. A visual
survey of the proposed development area was carried out and noise levels measured at
three noise sensitive locations around the proposed development site.  Properties most
likely to be affected by the development are: Dewshill Farm to the northeast of the former
colliery site, the occupiers of which have a financial interest in the development; Dewshill
Cottage which lies immediately south of the former colliery site and; Nos 1-18 Dewshill
Cottages which lie immediately south of the M8 motorway.   
8.20 A series of noise prediction levels carried out in accordance with BS 5228-1: 2009 + A1:
2014 are included in the submitted NIA and assumptions were based on worst case
scenarios when operations would be undertaken at their closest distances to the three
noise sensitive locations and/or at highest topographic levels.  The results conclude that
the calculated noise levels from soils handling operations, shale extraction operations and
land improvement operations do not exceed the BS 5228-1: 2009 daytime threshold if the
proposed mitigation measures are implemented.  Proposed mitigation measures to reduce
noise emissions include a proposed 4m-5m height acoustic bund/barrier designed to run
continuously along the southern edge of the colliery site, which will be formed during the
initial phase of the works, together with controlled hours of operation and a continual noise
monitoring scheme for the duration of the works, including a procedure to manage noise. 
8.21 NLC Protective Services has indicated that, subject to the above mitigation measures and
conditions attached to any grant of planning permission, it has no objection to the proposed
development.  In view of this, the predicted noise levels and proposed mitigation are
considered to be acceptable and are therefore in accordance with the requirements of Policy
PROT C of the LDP and Policies 23 Health and Safety and 33 (d) Minerals of NPF4. 
Air Quality 
8.22 Policy PROT C Mineral Resources (Category C1 Construction Minerals) of the LDP and
Policy 33 (d) Minerals of NPF4 also aim to ensure that the impacts of development on air
quality, as a consequence of mineral extraction processes, are taken into account and that
all mineral development demonstrates acceptable levels of dust and potential pollution of air. 
8.23 An Air Quality Assessment has been submitted in support of the application and has been
reviewed by NLC Protective Services in respect of the following considerations: adherence
to policy requirements; characterisation of baseline air quality, method of assessment;
evaluation of predictions; and study conclusions. The assessment has followed the Source-
Receptor-Pathway methodology laid out in the IAQM Guidance on the Assessment of
Mineral Dust Impacts for Planning and details each process that will be carried out as part
of the proposed development.  The assessment provides an emission magnitude based on
various onsite processes, including, for example, the amount of material extracted and
moved etc and distance to relevant receptors including those within 400m of the site
(Dewshill Farm and Dewshill Cottages) in line with the IAQM Guidance.   
Page 36 of 74

Page 37

8.24 Protective Services has advised that the emission magnitudes noted in the Assessment are
considered to be appropriate for the proposed onsite processes and that the proposed
mitigation measures will ensure that air quality objectives will not be exceeded and that the
effect of the proposed development on local air quality will not be significant. Protective
Services has raised no objection to the development subject to a condition being attached to
the grant of any planning permission to ensure that the proposed mitigation measures are
included in a formal Dust Management Plan to be submitted to the Planning Authority for
approval prior to the commencement of works on site.  On this basis, the proposed
development does not raise any conflicts with Policy PROT C of the LDP or Policy 33 (d) of
NPF4. 
Coal Mining Legacy 
8.25 Policy EDQ2 Specific Features for Consideration of the LDP requires that where land is
known or suspected to be unstable or contaminated, development proposals will
demonstrate that the land is, or can be made, safe and suitable for the proposed new use.
The site lies within a Coal Authority high risk area, however, given the nature of the
proposal, the Coal Authority has indicated that a Coal Mining Risk Assessment would not
be proportionate in this particular instance and as such does not object to the application
but recommends that should planning permission be granted, an advisory note is attached
to provide guidance to the developer in the event of coal mining features being
unexpectedly encountered during the course of the development.  Relative to the above
matters, the proposed development raises no conflict with Policy EDQ2 of the LDP. 
Archaeology 
8.26 Policy PROT B Historic Environment Assets (Category B3) of the LDP and Policy 7 Historic
Assets and Places of NPF4 provide that for sites of archaeological interest, the aim should
be to preserve in situ wherever feasible. 
8.27 The application is supported by an Archaeological Desk-based Assessment dated
February 2023. The Assessment notes that since the land in the northern half of the site
has not previously been extensively developed, there is some potential for the survival of
hitherto unrecorded sub-surface remains within the site. Whilst the land in the southern
half of the site (the former colliery) has been heavily exploited, there is potential for the
survival of remains relating to the activity of the colliery underneath the spoil heaps. The
Assessment also notes that there are ten known cultural heritage sites within the
application site that could potentially be directly affected by the proposal. These consist of
Dewshill Colliery (CHS 1), Dewshill well (CHS 8), Dewshill quarries (CHS 9, CHS 10 and
CHS 14), two modern structures (CHS 11 and CHS 16) and three drystone field
boundaries (CHS 12, CHS 13 and CHS 15).
8.28 Accordingly, NLC’s Archaeologist has recommended that if planning permission is
granted, a condition is attached to ensure that prior to the commencement of the
development, the developer has secured, and submitted to the Planning Authority for
approval, the implementation of a programme of archaeological mitigation to establish the
presence, or otherwise, of cultural heritage remains within the site. The condition will
ensure that the development meets the requirements of Policy PROT B of the LDP and
Policy 7 of NPF4. 
Waste Management and Soils 
8.29 Policy 5 Soils of NPF4 seeks to ensure development minimises the amount of disturbance
to soils on undeveloped land and Policy 12 Zero Waste of NPF4 supports developments
which use materials with the lowest forms of embodied emissions, such as recycled and
natural construction materials and/or are suitable for reuse with minimal reprocessing. 
8.30 Whilst there will be some disturbance to soil attributed to the proposed extraction and
reprofiling works, the site is currently classed as derelict land associated with past mining
activity.  Accordingly, the development presents no conflict with Policy 5 of NPF4.   Page 37 of 74

Page 38

8.31  Following the proposed extraction process, the shale will be processed by dry screening
and sold on to the construction industry as a secondary aggregate. The unusable material,
together with imported inert waste will be used in the northern half of the site for agricultural
improvement.  As colliery shale falls within the definition of ‘extractive waste’ of Regulation
2 of The Management of Extractive Waste (Scotland) Regulations 2010, applications
involving extractive waste require to be supported by a Waste Management Plan in
accordance with Regulation 11.  This application has been accompanied by a Waste
Management Plan which provides details of the reduction of waste and its harmfulness,
together with details of recovery of the extractive waste by means of recycling, reusing,
reclaiming and/or by short and long-term safe disposal of the waste.  The submitted Waste
Management Plan meets the objectives of Schedule 1 of The Management of Extractive
Waste (Scotland) Regulations 2010 and demonstrates that the development will generate
minimal waste with waste materials either being reused on site as part of the reprofiling
works and/or being removed from site and sold as secondary aggregate to the
construction industry. The proposed extraction of colliery shale and reprofiling works do
not conflict with the b)v. reuse and recycle objectives of Policy 12 of NPF4.   
Flood Risk / Drainage 
8.32 Policy EDQ1 Site Appraisal provides that development shall take account of any impacts
associated with the holistic water environment, flood risk, public utilities and drainage
systems and, as required by Policy 22 Flood risk and Water Management of NPF4, all rain
and surface water will be managed through sustainable urban drainage systems (SUDS). 
8.33 SEPA’s large scale Flood Maps show that small sections of the site corresponding to
minor watercourses and waterbodies surrounding the site are identified at risk of surface
water (pluvial) flooding.  The application is accompanied by a Flood Risk Assessment,
dated April 2023, which demonstrates how surface water run-off will be managed.  The
fines derived from processing tipped material in the southern catchment will be deposited
in the northern catchment to improve the agricultural potential of the land. This will not
significantly alter the landform or the subsequent run-off regime in the northern catchment
and a small pond located in this area will provide attenuation of surface water run-off, prior
to discharging off-site, during both the processing and restoration phases. The pond will
be maintained and improved as part of the proposed works and post-restoration the pond
will be enlarged to enable it to accommodate run-off from the whole site.  A drainage ditch
will be installed in the southern catchment to ensure run-off from this area is directed
towards the pond and the watercourse network. It will also ensure that the pond outside
the site, forming part of the proposal for biodiversity enhancement, does not receive run-
off from the development site. 
8.34 SEPA has raised no objection to the application and/or provided any comments and it is
considered that the submitted FRA provides sufficient mitigation against surface-water
run-off.  In view of the above and subject to mitigation to prevent flood risk and conditions
to this effect, the proposed development does not raise any conflict with Policy EDQ1 of
the LDP or Policy 22 of NPF4. 
Restoration 
8.35 For development involving the sustainable extraction of minerals, Policy PROT C Mineral
Resources of the LDP and Policy 33 Minerals of NPF4 require proposals to be
accompanied by restoration plans that demonstrate high standards of restoration and
aftercare. 
8.36 Details of restoration have been submitted in support of the proposal, although the costs
associated with the restoration are unknown at this time. Progressive reinstatement works
would begin before land profiling is complete in a phased manner with the topsoil from
each forward phase being transposed onto the previous completed phase. Seeding works
would be carried out together with woodland shelter belts planted.  On completion of the Page 38 of 74

Page 39

land raising, drainage works and reinstatement works, the land would be managed for
rehabilitation and management over a period of 5 years. This continued involvement
should prove beneficial with respect to the long-term quality of restoration and aftercare
of the land. 
8.37 The costs of restoration will be met by the developer and secured by the developer
entering into a legal agreement with the Council. The Council’s legal costs, including any
peer review costs associated with the restoration works, will be borne by the developer. 
8.38 Subject to the aforementioned legal agreement, the proposed restoration plan is
considered to acceptable and is in accordance with Policy PROT C of the LDP and Policy
33 of NPF4. 
Conclusion 
8.39 The extraction and processing of shale for onward sale to the construction industry as a
secondary aggregate coupled with reprofiling of poor-quality agricultural land to improve
the agricultural potential of the land, would take place over a period of 15 years without
significant effects to landscape, air quality, the water environment, the road network or
communities. 
8.38  The temporary landscape and visual effects associated with the development during the
operational phase would be mitigated through progressive and phased restoration
including woodland planting around the perimeter of the site. At present the site is of low
ecological value due to the type and condition of habitats present. The proposed
biodiversity net gain measures, including native hedgerows and broadleaved woodland,
would promote a variety of habitats and foraging opportunities for mammals, bats and
birds together with improved accessibility and path connections to enhanced and
managed green spaces.  Allowing for habitats retention and biodiversity enhancement
both on and off site, the total post-development score shows a net gain of +43.24% from
the site baseline, confirming that the proposed development offers biodiversity
enhancements to the site and immediate surrounding area. 
8.39 The proposed drainage and flood protection measures would mitigate against the risk of
flood from all sources.   In terms of noise, a proposed 4m-5m height acoustic bund/barrier
designed to run continuously along the southern edge of the colliery site, would be formed
during the initial phase of the works to mitigate against noise. A continual noise monitoring
and complaints scheme would also be in place for the duration of the works. 
8.40 Subject to all other conditions, including those to protect residential amenity, the proposed
development is considered to meet the requirements of Policies PROT A, PROT C, PP 5,
AD 5, EDQ 1, EDQ 2 and EDQ 3 of the LDP and Policies 2, 3, 4, 9, 12, 13, 14, 22, 23 and
33 of NPF4 and is therefore recommended for approval. 
Page 39 of 74

Page 40

Application No:  
24/00043/FUL
Proposed Development:  
Proposed battery energy storage system (BESS) and
associated access    
Site Address:  
Land At
Burnbank Street
Greenhill
Coatbridge        
Date Registered:  
6th February 2024      
Applicant:
Renewable Connections Developments Ltd
Level 4
3 Noble Street
London
EC2V 7EE  
Agent:
Wardell Armstrong LLP
FAO Abigail Brown
Suite 3/1, Great Michael House
14 Links Place
Edinburgh
EH6 7EZ  
Application Level:
Major Application      
Contrary to Development Plan:
No
Ward:   
07 Coatbridge North 
Kirsten Larson, Alexander McVey, Bill Shields,
Allan Stubbs,
Representations:
0 letter(s) of representation received.        
Recommendation: Approve Subject to Conditions  
Reasoned Justification: The proposed Battery Energy Storage System complies with
and gains support from the policies contained in both National Planning Framework 4
and the North Lanarkshire Local Development Plan as it could be accommodated within
the site without adverse impact on the wider surrounding area.          
Page 40 of 74

Page 41

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 24/00043/FUL 
Name (of applicant): Renewable
Connections Developments Ltd
Site Address: Land At
Burnbank Street
Greenhill
Coatbridge
Development: Proposed Battery Energy
Storage System (BESS) and Associated
Access   
Page 41 of 74

Page 42

Proposed Conditions:-    
1. That, except as may otherwise be agreed in writing by the Planning Authority, the
development shall be implemented in accordance with drawing numbers:-           
RCN1015-171 E; ED13500-C-3100B; RCN1015-230; RCN1015-231;          
RCN1015-232;  RCN1015-220; RCN1015-221;           
RCN1015-222; RCN1015-226; RCN1015-250; RCN1015-255           
RCN1015-PLE-01 REVH; ED13500-WAS-XX-XX-D-L-0001   
Reason: To clarify the drawings on which this approval of permission is founded.   
2. That prior to works commencing on site details of the colour and materials to be used on
all structures shall be submitted to and approved in writing by the Planning Authority.   
Reason: In the interests of the visual amenity of the area.   
3. That before works commence on site full details of the biodiversity enhancement
measures (including the species and number of hedging plants) shown on plan ED13500-
WAS-XX-XX-D-L-0001 Landscape Masterplan shall be submitted to and approved in
writing by the Planning Authority.   
Reason: In the interests of biodiversity.   
4. That prior to works starting on site, a detailed route and protocol for abnormal load
movements shall be submitted to the Planning Authority for its written approval in
consultation with NLC Traffic and Transportation.   
Reason: In the interests of traffic safety.    
Background Papers:  
Consultation Responses:  
Environmental Health (including Pollution Control) 27.02.2024,  03.07.2024
The Coal Authority 19.02.2024, 14.06.2024 
Traffic & Transportation 14.02.2024,  03.04.2024
Scottish Fire & Rescue 
Scottish Environment Protection Agency 12.02.2024, 05.03.2024, 07.05.2024 
Scottish Gas Network 12.2.2024 
Contact Information:  
Susan Hunt at planningenquiry@northlan.gov.uk or 01236 632487 
Report Date:  
26th July 2024 
Page 42 of 74

Page 43

REPORT  
1. Site Description  
1.1 The site is located within an existing industrial estate to the North of Coatbridge which
consists of a mixture of operational and vacant sites.  The current site is vacant, consists
of fairly level hardstanding with some self seeded scrub vegetation in the south east of the
site and extends to 1.18 acres. The site takes access from Burnbank Street via an existing
access serving the industrial estate. The site is bound by a stone wall to the east and south
and by open yard space to the north and west.  The nearest residential properties are
located on Burnbank Street to the north of the site (approximately 125m away from the
location of the battery energy storage containers). 
2. Proposed Development  
2.1 The application seeks full planning permission for the installation of a battery energy
storage system and associated infrastructure, including a substation, switch room building,
storage unit, fencing and CCTV cameras.  The proposed batteries store electricity and
would allow the local Grid network to operate more efficiently, taking excess energy,
storing it and releasing it into the network when the grid needs it a times of peak demand. 
The system would have a maximum import capacity of 30MW. 
2.2 The development would comprise:  
• A substation measuring 12m long by 4.5m wide by 3.75m high. 
• A customer Switchgear measuring 12m long by 2.4m wide and 2.6m high. 
• 168 units positioned in 7 groups, each group consisting of 2 rows of battery units, 2
inverters and 1 transformer. Each battery unit is 2.2m long, 1.3m wide and 1.4 high. 
• The site would be bound by security fencing approximately 2m high with CCTV security
cameras mounted along the fence at regular intervals. 
2.3 Construction is expected to take around 20 weeks. 
2.4 Estimated that up to 10 construction workers will be on site at peak times during the
construction period.  A temporary car parking area will be provided on the site within a
contractor’s compound.  On average 6 cars/vans and 2 HGVs are expected to visit the
site every day (total 8 x two way vehicle movements per day). 
2.5 During the operational phase the activities on-site would consist of the maintenance and
servicing of plant and equipment.  No more than one or two vehicles would need to access
the site per month. Most would be undertaken by an operative in a van or 4x4 type vehicle
except where repairs or replacement is required. 
2.6 The proposal comprises the development of an energy storage facility which has a
capacity of 30MWW (which exceeds 20 megawatts but does not exceed the 50MW limit
at which the Scottish Government’s Energy Consents Unit would determine the application
under the Electricity Acts). The Chief Planner’s Letter dated 27th August 2020 advises
that the Scottish Government considers that a battery installation generates electricity and
is therefore to be treated as a generating station. This application is, therefore, classified
as a Major Development under The Town and Country Planning (Hierarchy of
Developments) (Scotland) Regulations 2009. The applicant has carried out the required
pre-application consultation (21/01176/PAN and 23/00229/PAN) and a Pre-Application
Consultation Report outlining comments made by the public has been submitted as part
of this application. The manner of the consultation exercise, including the notification and
press advertisement process, complied with the relevant legislation. 
Page 43 of 74

Page 44

3. Applicant’s Supporting Information  
• Design and Access Statement
• Noise Assessment
• Flood Risk Assessment
• Coal Mining Risk Assessment 
4. Site History  
• 21/01152/EIASCR EIA Screening Opinion Request - 30MW Battery Energy
Storage System (BESS) with Associated Access and Infrastructure 
• 21/01176/PAN Proposed 30MW Battery Energy Storage System (BESS) with
Assoicated Access & Infrastructure 
• 23/00229/PAN Proposed 30MW Battery Energy Storage System (BESS) with
Associated Access & Infrastructure 
• 23/00818/FUL battery energy storage system (20MW) and associated access
(application withdrawn)  
5. Development Plan  
5.1 The development plan comprises National Planning Framework 4 and the North
Lanarkshire Local Development Plan.  
6. Consultations  
6.1  The Coal Authority have reviewed the Coal Mining Risk Assessment submitted with the
application and have no objection to the application nor wish any conditions imposed. 
6.2 SEPA have reviewed the application and supporting Flood Risk Assessment and raise no
objection to the application.   
6.3 NLC Protective Services requested further information in respect of the Noise Impact
Assessment which was provided and found to satisfy the queries raised.  No objection has
been raised and no conditions requested.  Further standard guidance was provided for
the construction phase including noise, working hours, dust emissions and waste (will be
added as informative notes). 
6.4 NLC Roads had no objection subject to further information being provided on the details
of the size of vehicles required during construction (particularly abnormal loads which may
impact access, internal layout and delivery route) together with details showing any traffic
management at the site access and along the delivery route to facilitate large vehicles
during construction.  It is considered that this can adequately be secured via planning
condition. 
6.5 Scottish Gas Network confirmed that they had no high pressure pipelines in the vicinity
and had no objection. 
6.6 Scottish Fire & Rescue raised no objection but provided their guidance on Battery Energy
Storage Systems the content of which had been addressed by the applicant in their
supporting statement. 
7. Representations  
7.1 Following standard neighbour notification and press advert procedures no letters of
representation were received. 
Page 44 of 74

Page 45

8. Planning Assessment 
8.1 Sections 25 and 37(2) of the Town and Country Planning (Scotland) Act 1997 require
that  planning applications be determined in accordance with the development plan
unless material considerations indicate otherwise. 
National Planning Framework 4 (NPF4) 
8.2  National Planning Framework 4 was adopted on 13 February 2023, replacing NPF3 and
Scottish Planning Policy. NPF4 guides spatial development, designates national
developments, highlights regional spatial strategies and sets out national planning
policies until 2045. 
8.3 The development draws support from NPF4 in principle. NPF4 clearly states “As
technologies continue to develop, storage and other forms of generation will grow” and
also outlines general support for storage technology and capacity. The document also
details that the planning system should ‘provide support’ for energy storage. 
8.4 There are six overarching spatial principles contained within NPF4. The most pertinent
to renewable energy is ‘just transition’. This principle is designed to ensure that the move
to net zero is fair and inclusive.  
8.5 NPF 4 Policy 1 Tackling the climate and nature crisis states that when considering all
development proposals significant weight will be given to the global climate and nature
crisis. 
8.6 The proposed development is a battery energy storage facility which assists the
distribution network via grid stabilisation and regulation of peak and surplus demand.  In
terms of the climate crisis, provision of a management resource for renewable energy
will assist by aiding the efficient use of low carbon alternatives to existing traditional
fossil based energy sources that contribute to the climate crisis.  With regard to the
nature crisis, the site is of very limited ecological value as it is primarily hard surfaced. 
Biodiversity enhancements are discussed below.  It is considered that the development
is supported by Policy 1. 
8.7 NPF4 Policy 2 Climate mitigation and adaptation.  The proposed Battery Energy Storage
System is designed to support the efficient management of low carbon energy from
renewable sources and is therefore a facilitating development that aids wider renewable
developments to minimise emissions.  It is considered that the application gains some
support from Policy 2.  
8.8 NPF 4 Policy 3 Biodiversity states:  
Development proposals will contribute to the enhancement of biodiversity, including
where relevant, restoring degraded habitats and building and strengthening nature
networks and the connections between them.  Proposals should also integrate nature-
based solutions where possible. 
Development proposals for national or major development will only be supported where
it can be demonstrated that the proposal will conserve, restore and enhance biodiversity,
including nature networks so they are in a demonstrably better state than without
intervention. 
8.9 The proposed site is considered to be of very low ecological value, given its location,
limited area and with the majority of the site comprised of hardstanding.  It is considered
that the potential negative effects are minimal.  Taking a proportional and pragmatic
approach to biodiversity the applicant was asked to consider what measures could be
utilised within the development to improve biodiversity.  The applicant has agreed to Page 45 of 74

Page 46

include native hedge planting along the western boundary, retain the and enhance the
small pockets of scrub in the south east of the site; and to look to create two small areas
of habitat creation within the site (such as bee bricks, bug hotels or hibernacula).  These
measures are considered to represent an enhancement to biodiversity within the site
and the details of the planting and habitat creation can be secured by condition.  On this
basis, it is considered that the proposal complies with the requirements of NPF4 policy 3.  
8.10 NPF4 Policy 9 Brownfield, vacant and derelict land and empty buildings seeks to
encourage, promote and facilitate the reuse of brownfield, vacant and derelict land and
empty buildings, and to help reduce the need for greenfield development’. One of the
key policy outcomes is to ensure development is directed to the right locations,
maximising the use of existing assets and minimising additional land take. NPF4 defines
brownfield land as being ‘land which has previously been developed. The term may
cover vacant or derelict land, land occupied by redundant or unused buildings and
developed land within the settlement boundary where further intensification of use is
considered acceptable. 
8.11 The proposed development is located on a brownfield, vacant site and is therefore
supported in principle by policy 9 in that it would bring back into use an area of vacant
land utilising an existing asset and avoiding new land take.  The policy also notes that
details of the proposed use must also be assessed in terms of its own acceptability and
impact under separate policies. 
8.12 NPF4 Policy 11 Energy states that project design and mitigation will demonstrate how
visual impacts on communities and individual dwellings are addressed along with any
significant landscape and visual impacts and cumulative impacts, recognising that such
impacts are to be expected for some forms of renewable energy. Where impacts are
localised and/or appropriate design mitigation has been applied, they will generally be
considered to be acceptable. The policy also advises that impacts on the historic
environment should also be addressed through acceptable design and mitigation.  
8.13 In terms of visual impact, it is considered that this element of the policy is primarily
aimed at turbine type developments. The proposed BESS development is functional in
nature and comprises containers within a site compound.  It is considered that the
limited height of the containers will largely prevent any adverse visual impacts and would
not result in far reaching impacts. 
8.14 Policy 11 of NPF4 also states that project design and mitigation will demonstrate how
impacts on communities and individual dwellings, including, residential amenity and
noise are addressed. Policy 23 (Health and Safety) of NPF4 requires that development
proposals that are likely to raise unacceptable noise issues will not be supported, whilst
the agent of change principle applies to noise sensitive development and a noise impact
assessment may be required where the nature of the proposal or its location suggests
that significant effects are likely.  
8.15 A Noise Impact Assessment was submitted in support of the application and
demonstrates that it is unlikely that there will be any detrimental noise impact on the
surrounding area resulting from the proposed development and the findings of the report
have been reviewed, consulted upon and are accepted. 
8.16 Policy 11 of NPF4 also states that development proposals will only be supported where
they maximise net economic impact, including local and community socio-economic
benefits such as employment, associated business and supply chain opportunities.  
8.17 The applicant advises that the development would provide inward investment to the local
community by providing local job opportunities during construction and
decommissioning, either directly or down the supply chain; by enabling local clean
energy production and by increased local economic activity from construction and
maintenance workers. The proposal would contribute towards meeting renewable Page 46 of 74

Page 47

energy targets by providing grid support to facilitate greater deployment of renewable
energy. 
8.18 Taking the above into account it is considered that the application is supported by Policy
11.  
8.19 NPF 4 Policy 22 Flood Risk requires a precautionary approach to flood risk be taken by
avoiding development within areas at risk of flooding.   The site is partly shown to be at
risk of flooding based on the SEPA future flood maps at the east and west boundaries of
the site.  This indicates that there is a risk of flooding from the North Burn situated to the
east of the site.    
8.20 It is considered that the application qualifies under exemption (a) (iii) of Policy 22 where
the site has historically had an industrial use and the proposal is for an equal or less
vulnerable land use. 
8.21 There will be minimal land raising within the site and the proposal is not considered likely
to lead to any material increase in flood risk to either the site itself or to other down
stream receptors.    
8.22 SEPA has reviewed the proposal and Flood Risk Assessment and has offered no
objection to the application.  It is considered that the application is in acceptable in terms
of policy 22. 
8.23 Overall it is considered that policies 1, 2 ,3 11 and 22 of National Planning Framework
are most applicable to this application and, on the basis of discussions above, the
application is in accordance with and gains support from these policies. 
8.24 Turning to the North Lanarkshire Local Development Plan the site lies within an area
characterised as General Urban Area (Purpose of Place Policy 3) and is identified as
NLC00502 with a PROMLOC2 Existing Business Site designation but falling outwith
Strategic Business Centres and Local Centres and identified as other. 
8.25 PP3 Purpose of Place (General Urban Area) seeks to maintain and improve the level of
amenity in urban areas, by encouraging development that is in keeping with their
residential character and encouraging diversity in more mixed-use areas.   The policy
also provides for the maintenance of the existing mix of other urban uses, or introduction
of a limited range of ancillary uses and activities out with Classes 8 and 9 of an
appropriate scale within recognisably mixed use areas can be appropriate to support the
operation of the General Urban Area.  The site falls in an established industrial area and
as such the proposal is considered an acceptable use on that basis. The supporting
statement outlines the specific locational need constraints and site selection process. 
Policy AD3 Amount of Development in General Urban Area points the assessment of
acceptability of the proposal to policies EDQ, PROM and PROT.  
8.26 In terms of Promotion (PROM) policies the site does not fall within a Strategic or Local
Business Centre but is classed as other identified business site and, as such, this
application as a utilities proposal should be assessed against the Environmental and
Design Policies EDQ1-3 rather than justified under the Amount of Development polices.  
There are no Protect (PROT) polices that cover this site. 
8.27 In terms of Environmental Design Qualities Policies EDQ 1 Site Appraisal requires that
any proposed development be appraised in terms of the site and its surroundings to
ensure that it will integrate successfully into the local area and avoid harm to
neighbouring amenity.  The applicant has submitted a Design and Access Statement
with the application and it is considered that this meets the requirements of policy EDQ1. 
8.28 EDQ Policy 2 requires applications to be accompanied by an assessment of how Page 47 of 74

Page 48

constraints affect sites dependant on the characteristics of the site, its surroundings and
the form of development.   In terms of EDQ2A Hazardous Zones the application is
supported by a Flood Risk Assessment and Coal Mining Risk Assessment both of which
have been reviewed, consulted upon and found to be acceptable.  In terms of
contaminated land it is acknowledged that as a site within a historic industrial area there
may be some contamination; however, as there will be limited ground breaking works
and due to the nature of the containers there is not a requirement for a Site Investigation
to be submitted. In terms of EDQ2B Utilities Infrastructure Scottish Gas Networks have
confirmed that there are no high pressure pipelines within the vicinity of the site.  Turning
to EDQ2C Management Areas it is noted that the site does not fall within an Air Quality
Management Area and due to the nature and scale of the development does not require
an Air Quality Assessment and the site does not fall within a Noise Management Area.
On this basis, it is considered that the application meets the requirements to assess the
relevant constraints affecting the site. 
8.29 EDQ Policy 3 Quality of Development states that development will only be permitted
where high standards of site planning and sustainable design are achieved whilst taking
into account policies EDQ1 and 2.  It is considered that the proposal is of utilitarian
design and is designed to wholly support an efficient and effective Battery Energy
Storage System.  The units are of standard commercial design and not dissimilar to
storage containers laid out in a linear fashion.  The site will be fenced and some
additional native hedgerow planting provided along the western boundary.  It is
considered that the Battery Energy Storage System would not be visually intrusive given
its site location amongst an industrial estate and its limited height.  The application is
supported by a Coal Mining Risk Assessment, Flood Risk Assessment and Noise Impact
Assessment which have been reviewed and found acceptable. A Drainage plan has
been submitted and also found acceptable.  As noted above NLC Traffic and
Transportation have no objection to the development but seek the provision of details of
vehicles and routes during the construction period and it is considered that this can be
adequately secured by condition. 
8.30 Taking the above into account it is considered that the application complies with the
relevant policies of the North Lanarkshire Local Development Plan  
9. Conclusions  
9.1  Taking the above discussions into account it is considered that the proposed Battery
Energy Storage System complies with and gains support from the policies contained in
both National Planning Framework 4 and the North Lanarkshire Local Development Plan
as it could be accommodated within the site without adverse impact on the surrounding
area. As such, it is recommended that planning permission be granted subject to
conditions.  
Page 48 of 74

Page 49

Application No:  
24/00182/FUL
Proposed Development:  
Construction of Community Hub comprising a
replacement St Stephen's primary school, the Language
and Communication Support Centre (LCSC) and
associated LCSC provision, a nursery class, community
facilities and corresponding sports amenities, together
with a fully landscaped site for the school and associated
car parking and drop off.    
Site Address:  
St Stephen's Primary School
Sikeside Street
Sikeside
Coatbridge
ML5 4QH      
Date Registered:  
23rd February 2024      
Applicant:
North Lanarkshire Council
Civic Centre
Windmillhill Street
Motherwell 
ML1 1AB  
Agent:
Ryder Architecture
FAO Chris Malcolm
221 West George Street
Glasgow
G2 2ND  
Application Level:
Major Application  
Contrary to Development Plan:
No
Ward:   
11 Coatbridge South 
Tracy Carragher, Geraldine Woods, Fergus
MacGregor, Andrew Bustard,
Representations:
1 letter(s) of representation received.        
Recommendation:  Approve Subject to conditions  
Reasoned Justification:  
The proposed development of a Community Hub comprising a replacement St
Stephen's primary school, the Language and Communication Support Centre (LCSC)
and associated LCSC provision, a nursery class, community facilities and
corresponding sports amenities, together with a fully landscaped site for the school
and associated car parking and drop off, is considered to be acceptable and aligns
with the principles of both National Planning Framework 4 and the North Lanarkshire
Local Plan (2022).        
Page 49 of 74

Page 50

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 24/00182/FUL 
Name (of applicant): North Lanarkshire
Council
Site Address: 
St Stephen's Primary School
Sikeside Street
Sikeside
Coatbridge
ML5 4QH
Development: Construction of
Community Hub Comprising a
Replacement St. Stephen's Primary
School, the Language and
Communication Support Centre (LCSC)
and Associated LCSC Provision, a
Nursery Class, Community Facilities and
Corresponding Sports Amenities,
together with a Fully Landscaped Site for
the School and Associated Car Parking
and Drop Off   
Page 50 of 74

Page 51

Proposed Conditions:- 
1. That, except as may otherwise be agreed in writing by the Planning Authority, the
development shall be implemented in accordance with drawing numbers or such
updated drawings as may be required to reflect the requirements of planning conditions
2-21 that follow:-  :-    
SCH-RYD-ZZ-00-DR-A-1410-S2-P22, SCH-RYD-ZZ-00-DR-A-1411-S2-P22, SCH-RYD-
ZZ-R2-DR-A-1412-S2-P9, SCH-RYD-ZZ-ZZ-DR-A-0100-S2-P2, SCH-RYD-ZZ-ZZ-DR-A-
0102-S2-P1, SCH-RYD-ZZ-ZZ-DR-A-1414_S2-P10, SCH-RYD-ZZ-ZZ-DR-A-1415-S2-
P7, SCH-RYD-ZZ-ZZ-DR-L-2103-S2-P22, SCH-RYD-ZZ-ZZ-DR-L-2141-S2-P4, SCH-
RYD-ZZ-ZZ-DR-L-2142-S2-P5, SCH-RYD-ZZ-ZZ-DR-L-2150-S2-P5, SCH-RYD-ZZ-ZZ-
DR-L-2700-S2-P10, SCH-RYD-ZZ-ZZ-DR-L-7000-S2-P4, SCH-RYD-ZZ-ZZ-DR-A-0110-
S2-P2, SCH-RYD-ZZ-ZZ-DR-L-9005-S2-P10, SCH-SZE-XX-XX-DR-S-9016, SCH-SZE-
XX-XX-DR-S-9017 and SCH-SZE-XX-XX-DR-S-9018.  
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That visibility splays of 4.5m x 60m at a height of 1.05m shall be provided in both
directions along Sikeside Street and shown on a drawing. The visibility splay should be
provided entirely within the public road boundary, or on land within control of the
applicant. Everything above 1.05m shall be removed from the sight lines and thereafter
nothing exceeding 1.05m shall be planted, placed, erected or allowed to grow within the
slight lines area.   
Reason: To ensure adequate sight lines are achieved.  
3. That before development herby permitted is taken into beneficial use, with the exception
of ground enabling works which includes land profiling, and unless otherwise agreed in
writing with the Planning Authority, details shall be submitted and approved in writing by
the planning authority showing the following active travel improvements: 
a) The existing bus-stop on Sikeside Street, which has been relocated, requires
high access kerbs, bus-cage markings a bus shelter and an uninterrupted 4.0m
footway width in order to to accommodate a bus shelter.
b) The footway to the north of the site at Shiel Place shall be widened to a minimum  
width of 3m.
c) The right turn, ‘Ghost Lane’ on Sikeside Street, shall have a minimum width of
2.5m.
d) Within the site, minimum carparking spaces of 2.5m x 5.0m with an isle width of
6.0m shall be provided.
e)  Road Construction Consent shall be required for all safety apparatus and active
travel improvements on the public carriageway/footway.  
Reason:  To ensure that the site is served by appropriate pedestrian access facilities
and in the interest of road safety.  
4. That before the school is brought into use the pedestrian links shall be completed to the
satisfaction of the planning authority.  
Reason: To ensure that the site is served by appropriate pedestrian access facilities and
in the interest of road safety.  
5. That no later than 9 months of the development hereby permitted being brought into use,
all the parking and manoeuvring areas shown on the approved plans, shall be levelled,
properly drained, surfaced in a material which the Planning Authority has approved in
writing before the start of surfacing work and clearly marked out, and shall, thereafter, be
maintained as parking and manoeuvring areas.   Page 51 of 74

Page 52

Reason: To ensure that the parking and manoeuvring areas are suitable surfaced.  
6. That before the development hereby permitted starts, a scheme of landscaping shall be
submitted to, and approved in writing by the Planning Authority, and it shall include:- 
a) Details of any earth moulding and hard landscaping, grass seeding and turfing;
b) A scheme of tree and shrub planting, incorporating details of the location,
number, variety and size of trees and shrubs to be planted; in particular this
should include a detailed scheme of biodiversity enhancement, seasonal shrub
planting and trees within and bordering the edge of the site. 
c) A detailed timetable for all landscaping works within the site and shall set out that
the works be carried out contemporaneously with the development of the site.  
For the avoidance of doubt, the details submitted to discharge this condition shall build
upon the landscaping plans submitted as part of the application.  
Reason: To enable the Planning Authority to consider these aspects.  
7. That all works included in the scheme of landscaping and planting, approved under the
terms of Condition 6 above, shall be completed in accordance with the approved
timetable, and any trees, shrubs, or areas of grass which die, are removed, damaged, or
become diseased, within two years of the full occupation of the development hereby
permitted, shall be replaced within the following year with others of a similar size and
species.  
Reason: To ensure the implementation of the landscaping scheme in the interest of
amenity.  
8. That before any works of any description start on the application site, with the exception
of ground enabling works which includes land profiling and unless otherwise agreed in
writing with the Planning Authority, a comprehensive site investigation report shall be
submitted to and for the approval of the Planning Authority. The investigation must be
carried out in accordance with current best practice advice such as BS10175: ‘The
Investigation of Potentially Contaminated Sites’ or CLR 11. The report must include a
site-specific risk assessment of all relevant pollutant linkages and a conceptual site
model. Depending on the results of the investigation, a Detailed Remediation Strategy
may be required.  
Reason: To establish whether or not site decontamination is required in the interests of
the amenity and wellbeing of future residents of the site.  
9. That any remediation works identified by the report agreed in terms of Condition 8 above
shall be carried out in accordance with an implementation timetable.  This timetable shall
be agreed in writing with the Planning Authority before any works start on site.  The
shared campus shall not be occupied until a certificate (signed by a chartered
Environmental Engineer) has been submitted to the Planning Authority confirming that
any remediation works have been carried out in accordance with the agreed
Remediation Strategy.  
Reason: To ensure that any remediation identified has been implemented in the
interests of the amenity and wellbeing of users.  
10. That before the development hereby permitted starts, with the exception of ground
enabling works which includes land profiling and unless otherwise agreed in writing with
the Planning Authority, full details of the proposed surface water drainage scheme shall
be submitted to the said Authority and shall be certified by a chartered civil engineer as
complying with the most recent SEPA SUDS guidance.  
Reason: To ensure that the drainage scheme complies with best SUDS practice to Page 52 of 74

Page 53

protect adjacent watercourses and groundwater and in the interests of the amenity and
wellbeing of existing and future residents adjacent to and within the development site.   
11. That the SUDS compliant surface water drainage scheme approved in terms of
Condition 10 shall be implemented contemporaneously with the development in so far as
is reasonably practical. Within three months of the construction of the SUDS, a certificate
(signed by a Chartered Civil Engineer experienced in drainage works) shall be submitted
to the Planning Authority confirming that the SUDS has been constructed in accordance
with the relevant CIRIA Manual and the approved plans.  
Reason: To safeguard adjacent watercourses and groundwater from pollution and in the
interests of the amenity and wellbeing of existing and future residents adjacent to and
within the development site.  
12. That prior to the commencement of development, with the exception of ground enabling
works which includes land profiling, the applicant shall provide written confirmation to the
Planning Authority that all the requirements of Scottish Water can be fully met to
demonstrate that the development will not have an impact on their assets, and that
suitable infrastructure can be put in place to support the development.  
Reason: To ensure the provision of satisfactory drainage arrangements.  
13. That prior to any works commencing on site, with the exception of ground enabling
works which includes land profiling a Construction Environmental Method Statement
shall be submitted to and approved by the Planning Authority. The Construction Method
Statement shall cover:  
• Details of how the development will be phased
• Details of the location of site compound and management facilities
• Details of construction access, construction worker parking and storage areas
• Details of all parking areas to be retained and maintained to assist with the operation
of the existing and proposed schools.
• Submission of a Dust Action Plan  
The development shall thereafter be implemented in accordance with the approved
Construction Method Statement.  
Reason: In the interests of the amenity of the area, to ensure adequate parking
provision for the functioning of the school. and to ensure ecological protection measures
are in place.  
14. That should 18 months or more has elapsed between the timing of the initial ecological
survey, dated February 2024 hereby approved, and development commencing, a further
survey shall be undertaken on the site to determine the presence of any statutorily
protected species including Badgers and bats, the said surveys shall thereafter be
submitted to and approved in writing by the Planning Authority before any development
commences on the site. As a result of the study, should any mitigation measures be
required for any protected species, this shall be implemented in accordance with the
species protection plan agreed in writing with the Planning Authority in consultation with
Scottish Natural Heritage before works commence on the site.  
Reason: To ensure compliance with The Conservation (Natural Habitats & c.)
Regulations 1994 (as amended); the Wildlife and Countryside Act (1981) as amended;
the Protection of Badgers Act 1992 (as amended); and the Nature Conservation
(Scotland) Act 2004.'  
15. That before the development hereby permitted starts, with the exception of ground
enabling works which includes land profiling, and unless otherwise agreed in writing with Page 53 of 74

Page 54

the Planning Authority, full details of the facing materials to be used on all external walls
and roofs shall be submitted to and approved in writing by the Planning Authority.    
Reason: In the interests of amenity and design by ensuring that external materials are
appropriate for the site.  
16. That before the development hereby permitted starts, with the exception of ground
enabling works which includes land profiling, and unless otherwise agreed in writing with
the Planning Authority, full details of the design and finish materials to be used in the
construction of the access road, footways, junctions, parking and manoeuvring areas
shall be submitted to and approved in writing by the Planning Authority.  The approved
details shall be implemented contemporaneously with the development in so far as is
reasonably practical.  
Reason: In the interests of amenity and design by ensuring that the materials are
appropriate for the site.  
17. That before the development hereby permitted starts, with the exception of ground
enabling works which includes land profiling, and unless otherwise agreed in writing with
the Planning Authority, full details of the design and location of all fences and walls to be
erected on the site shall be submitted to and approved in writing by the Planning
Authority.  The approved details shall be implemented contemporaneously with the
development in so far as is reasonably practical.   
Reason: To enable the Planning Authority to consider these aspects in detail.  
18. The design, installation and operation of any air conditioning/ventilation or other plant for
the proposed development and any other noise associated with the completed
development shall be such as will not give rise to a noise level, assessed with the
windows open, within any dwelling or noise sensitive buildings in excess of the
equivalent to Noise Rating Curve (N.R.C.) 35 between 07.00 hours and 22.00 hours and
N.R.C. 25 at all other times.  
Reason:  In the interests of surrounding residential amenity.  
19. Unless otherwise agreed in writing with the Planning Service, Prior to commencement,
an Air Quality Impact Assessment shall be submitted to, and agreed in writing by the
Planning Service, in conjunction with the Protective Services Department. All
recommendations of the submitted report shall be implemented in full along with any
further recommendations as identified by the Environmental Health Officer.   
Reason: To enable the Planning Authority to retain effective control, and to protect the
surrounding area from adverse air quality during construction and operation of the site.  
20. No development (other than the demolition of any buildings) shall commence until the
remediation works to address land instability arising from coal mining legacy, as
identified in the Geo-Environmental Report on Site Investigations (January 2024,
prepared by Mason Evans Geo-Environmental Consultants), have been implemented on
site in full. 
The remedial works shall be carried out in accordance with authoritative UK guidance.   
Reason: In order to ensure that the site is made safe and stable for the development
proposed.    
21. Prior to the occupation of the development, or it being taken into beneficial use, a signed
statement or declaration prepared by a suitably competent person confirming that the
site is, or has been made, safe and stable for the approved development shall be
submitted to the Local Planning Authority for approval in writing.  This document shall Page 54 of 74

Page 55

confirm the satisfactory completion of the remedial works to address the risks posed by
past coal mining activity.   
Reason: In order to ensure that the site is made safe and stable for the development
proposed.        
Background Papers:  
Consultation Responses:  
Scottish Gas Network     27th February 2024
Environmental Health (including Pollution Control) 28th March 2024 & 1st August 2024 
The Coal Authority     7th March 2024
Traffic & Transportation    9th April 2024 & 29th July 2024
Scottish Water      11th March 2024
NLC Greenspace     2nd July 2024
Food Safety / Business Regulations   5th March 2024    
Contact Information:  
Colin Bradley at planningenquiry@northlan.gov.uk or 01236 632487    
Report Date:  
1st August 2024  
Page 55 of 74

Page 56

REPORT  
1. Site Description  
1.1 The application site is located to the east of Sikeside Street in Coatbridge. The principal
access point is from Sikeside Street.  The site is further bound by Cumbrae Crescent to
the south and Shiel Place to the north.  
1.2 The overall site has previously been occupied by 2 separate primary schools, Sikeside
Primary and St Stephens Primary School. Sikeside Primary School has been
demolished in order to accommodate the new proposed hub and St Stephens Primary
School remains in-situ and shall be retained until such time as the replacement hub has
been built out. The new proposed building shall be directly to the south of the existing St
Stephens Primary School.  
1.3 The overall site measures some 3.33 hectares and the gross floor space of the building
itself shall measure 5,126m2 over two storeys within this overall space.   
2. Proposed Development  
2.1 It is intended to replace 2 primary schools that previously sat on site with a single,
community hub with capacity for the needs of the local community. Specifically,
permission is sought for the Construction of a Community Hub comprising a replacement
St Stephen's Primary School, the Language and Communication Support Centre (LCSC)
and associated LCSC provision, a nursery class, community facilities and corresponding
sports amenities, together with a fully landscaped site for the school and associated car
parking and drop off. Initially it was intended to accommodate a level of Police
accommodation within the building however during the processing of this application
Police Scotland have withdrawn their interest in utilising accommodation within the
building.  
2.2 The building shall have floorspace of 5,126m2, be two storeys tall and shall be located to
the central/southern aspect of the main site immediately adjoining Sikeside Street. The
principal access point for the school faces north and features a large void area which
could act as a ‘shelter shed’ from inclement weather. On the ground floor there shall be a
double height community hall with ancillary store, kitchen waiting area and facilities
management office to the northwest of the building. The ‘Early Years Centre’ of the
school is located immediately behind the community hall and is accessed from both
internally within the school and has a dedicated access point to the outdoor play, fenced
enclosure immediately adjacent to it. The ground floor also features the assembly / P.E.
Hall, associated changing rooms, the dining area, administration and staff areas,
classrooms and the LCSC area along with plant rooms and storage areas. The upper
floor of the proposed building shall feature two wings of classrooms, to the east and the
west, and both shall have ‘breakout spaces, associated to the respective wings and
bathroom facilities for the children and staff. Alongside this there are two ‘General
Purpose’ rooms and an ‘E-Learning suite. Directly above the principal access area of the
community hub shall be an area of roof-space which shall be utilised to accommodate
plant infrastructure for the overall school / hub.  
2.3 It is intended to supply a single carpark area which shall be accessed from the northern
aspect of the site directly off Sikeside Road and egressed through a point immediately
north of the proposed building itself.  This one-way car park shall have 131 spaces which
are intended to be used for staff and visitor parking and a drop off zone. The parking
spaces shall comprise of 7 disabled bays (2 of which are electric), 12 further electric
charging bays, 93 staff and visitor parking bays and 19 drop off bays. There is also
space within this car park for bus/coach drop off zone. Pedestrian access is accounted
for via one point to the west of the site accessed via the cycle path immediately adjacent
to the site and access points adjacent to the vehicular access points located on Sikeside
Street. Cycle storage has been accommodated close to the principal entrance of the hub Page 56 of 74

Page 57

and it is considered this shall allow for ‘active travel’ to form part of the possible routes to
school.  
2.4 Play provision shall be provided in the form of a landscape/play mounding to the north
and west of the car parking area and a ‘community use’ MUGA, (Multi Use Games
Area), to the west of the car-parking.  To the south and west of the School building itself
there shall be a compound of play space exclusively for the use of the School itself. A
second MUGA is located within this compound to the west of the building, for the
exclusive use of the school and its pupils, south of this a large, ‘soft outdoor PE’ area set
to grass. There shall also be an ‘out-building’ which shall be used as an ‘Outdoor
Classroom’.  Early Years learning have an area to the east of the building which is
fenced off to allow for ‘play learning’ to the younger pupils of the school and to the ‘cut
away area’ to the immediate north of the building is a further fenced in play area
intended to be associated to the LCSC element of the proposed school. There is also
picnic benches located to accommodate al-fresco dining for the pupils. Throughout any
level changes across the site, there shall be play opportunities included to the
embankments. There is a variety of biodiversity enhancements included in the overall
landscaping scheme such as a ‘Natural Area’ to the school compound area and a
‘Nature Garden’ with growing area.  
2.5 The site also has a fenced compound, Scottish Power Energy Network substation to its
eastern flank adjacent to the car parking area and accessed directly off Sikeside Street
and a fenced off compound featuring an Air Source Heat Pump, (ASHP) and sprinkler
tank compound located to the north of the school use MUGA.  
3. Applicant’s Supporting Information  
3.1 Alongside a full suite of drawings, the applicant has supplied the following documents;  
• Noise Impact Assessment (NIA)
• Design and Access Statement,
• Drainage Strategy Report,
• Ecological Assessment,
• Site Investigation Report,
• Transport Statement,
• Transport Statement Travel Plan
• Sustainability Statement,
• Pac Report  
3.2 A condition, (19), has been added requiring the submission of an Air Quality Impact
Assessment to be submitted to, and approved in writing by, the Planning service in
conjunction with our Protective Services Colleagues prior to any development. This
condition has been worded in such a way that any additional requirements of the
Protective Services department may be accommodated prior to the condition being
purified.  
4. Site History  
• 23/00415/PAN Erection of Community Hub Including Primary School, Early Learning
Centre, Community Centre & Police Scotland Partnership Zone with Associated
Parking, Bus Drop Off & External Landscape Spaces – Comments given 20th April
2023. 
5. Development Plan  
5.1 The site sits within a ‘General Urban Area’ and is cover by policies ‘PP 3 – Purpose of
Place’ and ‘AD 3 Amount of Development’ in the North Lanarkshire Local Development
Plan 2022. All development is required to be assessed against the Environmental
Design Qualities policies, EDQ 1-3 also. Page 57 of 74

Page 58

5.2 The site is also subject to National Planning Framework 4 and of particular relevance are
policies 3 - Biodiversity 9 – Brownfield vacant and derelict land and empty buildings, 14 –
Design quality and place, 15 Local living and 20-minute neighbourhoods, 21 – Play,
recreation and sport and 25 - Community wealth building.  
5.3 The impacts of the policies identified above shall be examined in the planning
assessment stage of the report in section 8.  
6. Consultations  
6.1 Consultations have been requested from a number of both in house and external
consultees. Their responses, shall be discussed in the following paragraphs;  
6.2 NLC Traffic & Transportation have undertaken detailed discussions with the applicant
and upon completion of these discussions identified a number of recommendations with
regards to the internal layout of the proposal and external road safety equipment.  The
salient points of this response have been translated into planning conditions or
informative notes that shall be included in the planning permission. 
6.3 NLC Protective Services have accepted the findings of the Noise Impact Assessment
NIA and were satisfied with the assessment methodology. They have requested that
conditions are applied to the permission ensuring that the defined mitigation measures
identified in the report are applied in order to achieve the relevant indoor criteria at
nearby dwelling houses. A further condition is requested to ensure compliance with the
measures outlined.   
A Site Investigation (S.I.) has been requested by NLC Protective Services and upon
submission of this document further information was requested with regards to a ‘Mine
Gas Risk Assessment’, further commentary on the ground gas risk assessment, human
health risk assessment, post-demolition ground investigation report and radon risks. The
process of the Site Investigation has been initiated and it shall be possible to condition
the completion of this process as part of the determination.   
An Air Quality Impact Assessment, (AQIA), has also been requested from the Protective
Services department. This has been commissioned and it is considered that this element
of the proposal shall be able to be controlled by a Planning Condition. This condition has
been worded in such a way that any additional requirements of the Protective Services
department may be accommodated prior to the condition being purified. 
6.4 NLC Greenspace have stated that all works must be undertaken within 18 months of the
surveys being undertaken or further surveys must be undertaken. Bespoke ecological
enhancement measures will be required for the development, incorporated within the
design, along with long-term management requirements are also required and this shall
be controlled through a Planning Condition.  
6.5 The Coal Authority have requested that two conditions are placed on any planning
permission relating to the findings, and implementation, of the Geo Environmental
Report. The Coal Authority has no objection subject to the imposition of these two
conditions which have been included. A further two informative notes have been
requested to be added to any planning permission.  
6.6 Scottish Water have stated that they have sufficient capacity to accommodate the
proposals requirements for potable water however they are unable to confirm capacity at
the Daldowdie Wastewater Treatment Plant. It is intended to place a planning condition
requiring a letter to be submitted from Scottish Water confirming that there is sufficient
capacity to accommodate the requirements of the proposal.   
Page 58 of 74

Page 59

6.7 Scottish Gas confirmed that they do not have any high-pressure assets in the vicinity of
the application site and, as such, they do not have any comments / objections to the
proposal.  
6.8 NLC Food Safety Business Regulations have requested that two planning conditions
relating to the design, layout and construction comply with Food Hygiene (Scotland)
Regulations 2006 and that full details of the design of the kitchen / food handling areas is
submitted prior to the commencement of work. These requests have been included as
informative note rather than Planning Conditions. 
7. Representations  
7.1 1 letter(s) of representation received objecting to the proposal. The reasons for objection
and our comment on them follows: 
Noise (during construction period)   
Response: Any construction brings with it a level of noise and disturbance; this is an
unfortunate side effect of the construction process however it should be noted that there
is existing legislation to cover the hours of construction which is controlled by the
Protective Services Department of NLC.   
Noise (during school being used)   
Response: The site currently hosts two primary schools, and it is not considered that this
proposal shall result in an intensification of the use of the land nor an increase in the
level of noise coming from the site.   
Air Pollution (Dust and Smells)   
Response: Similarly to construction noise, dust and air pollution is controlled through
legislation controlled by the Protective Services Department of NLC.   
Overshadowing “Would the school tower over my home and block the sunlight?”  
Response: The overall height of the school shall be 10.8m in height and the school is
located some 100m from objectors dwelling houses.  As such it will have no impact on
their property and will have no impact on sunlight daylight for other houses immediately
adjoining the development site.  
Privacy There is concern that classrooms may be level with the objectors windows and
that persons may be able to see into their home.  
Response: The distance of circa 100m means that it is not considered that the proposal
shall not result in any loss of privacy the objectors property and will not impact on privacy
for any other residential properties around the site.  
Wildlife Concern is expressed over animals relocating from the school grounds towards
the residential properties in close proximity of the development site.  
Response: The proposal features a variety of biodiversity enhancements such as the
‘Natural Area’ to the school compound area and a ‘Nature Garden’ with growing area. 
Outwith the confines of the site there is a large open grass area to the northwest and a
large wooded area to the south west.  It is considered likely that any animal relocation
would be towards these two large areas offering better habitat.   
Page 59 of 74

Page 60

8. Planning Assessment 
Development Plan  
8.1 In accordance with Sections 25(1) (a) and 37(2) of the Town and Country Planning
(Scotland) Act 1997, planning decisions must be made in accordance with the
Development Plan unless material considerations indicate otherwise. The development
plan consists of National Planning Framework 4 (NPF4) and the Adopted North
Lanarkshire Local Development Plan 2022 The National Planning Framework was
adopted on the 13th of February 2023. Of particular relevance, is NPF Policies 3 –
Biodiversity, 9 – Brownfield vacant and derelict land and empty buildings, 14 – Design
quality and place, 15 Local living and 20 minute neighbourhoods, 21 – Play, recreation
and sport and 25 - Community wealth building.  
NPF4  
8.2 Policy 3 of NPF 4 -Biodiversity has the stated aim of including appropriate measures to
conserve, restore and enhance biodiversity, in accordance with national and local
guidance. It goes on to state that measures should be proportionate to the scale and
nature of the development. delivering positive effects from the development and
strengthen nature networks. It is considered this proposal is compliant with the principles
of this NPF 4 policy. Some measures have already been identified within the proposals
and a planning condition has been included that requires that biodiversity enhancements
should be included within the landscaping proposals for the site.  
8.3  Policy 9 of NPF 4, Brownfield, vacant and derelict land and buildings seeks to
promote and facilitate the reuse of brownfield land and help reduce the need for
greenfield development. By reusing and redeveloping an existing school site it is
considered this proposal is compliant with the principles of this NPF 4 policy.  
8.4  Policy 14 of NPF 4, Design, quality and place seeks to encourage, promote and
facilitate well designed development that makes successful places by taking a design led
approach. The proposal has been well designed and as such it is considered this
proposal is compliant with the principles of this NPF 4 policy.  
8.5 Policy 15 of NPF 4, Local Living and 20 minute neighbourhoods seeks to create
connected and compact neighbourhoods within a reasonable distance of their home,
preferably by walking, wheeling or cycling or using sustainable transport options. By
redeveloping an existing school site within the school catchment area it is considered
this proposal is compliant with the principles of this NPF 4 policy.  
8.6  Policy 21 of NPF 4, Play, recreation and sport seeks to encourage, promote and
facilitate spaces and opportunities for play, recreation and sport. Again, through the
redevelopment of an existing school site and including new facilities it is considered this
proposal is compliant with the principles of this NPF 4 policy.  
8.7 Policy 25 of NPF 4, Community wealth building seeks to encourage, promote and
facilitate a new strategic approach to economic development.  As this proposal is for an
educational facility, it is considered this proposal is compliant with the principles of this
NPF 4 policy.  
Local Development Plan  
8.8  Purpose of Place Policy PP 3 (General Urban Area) applies seeks to maintain and
improve the level of amenity in urban areas by encouraging development that is in
keeping with their residential character and encouraging diversity in more mixed-use
areas.  As the site is currently host to a primary school, and previously hosted two
primary schools, it is considered that this shall maintain and improve the level of amenity
and is therefore compliant to this policy. Page 60 of 74

Page 61

8.9  Policy AD 3 Amount of Development requires new development to be assessed for their
implications related to the amount of development proposed and depends on a
combination of use class, scale and location. Class 10 non-residential do not require the
amount of development to be assessed and thus the proposal is acceptable.  
8.10  Environmental and Design Qualities Policies EDQ 1 -3 apply to all new development
proposals and are addressed in turn below.   
Policy EDQ 1 (Site Appraisal): This policy requires a high quality of development by
ensuring proposals integrate well into the surrounding area and avoid harm to
neighbouring amenity. It also considers the impact of the proposed development in terms
of its requirements for additional community facilities or infrastructure which is necessary
to meet future demands on existing provisions.  
Policy EDQ2 (Specific Features for Consideration): There are no Hazardous Zones and
as such the policy is not relevant in this case.  
Policy EDQ 3 (Quality of Development): This policy requires high standards of site
planning and sustainable design.  
8.11  The proposed development seeks to replace 2 primary schools, Sikeside Primary School
and St Stephens Primary School, with a single Community Hub / Primary School.  The
hub has been the subject of detailed discussions with the community in advance of the
application having been submitted to ensure it reflects all the needs of the community it
will serve.  This is detailed in the Design and Access Statement submitted by the
applicant. As required it has been designed to provide a safe, inclusive, convenient and
welcoming development. The site has been considered in its entirety with the building
positioned in such a way as to sympathetically relate to surrounding residential
development. The scale and massing of the building, although considerable, is
considered to be acceptable given the large plot within which it shall sit.  The material
palette is reflective of modern building practices. The proposal provides Biodiversity gain
through design elements and the site will be well landscaped. Updated sports facilities
will also be delivered to the area.  The proposal is considered to be compliant with the
requirements of the policies as outlined above and is considered to be acceptable in
planning terms and in keeping with the character the area. 
9. Conclusions  
9.1 It is therefore considered for the above reasons that the proposed development is
acceptable in policy terms and is acceptable in terms of residential amenity. This
application is consequently recommended for approval subject to the imposition of
appropriate planning conditions. Taking the above assessment into account, it is
considered that the detailed design and layout of the proposal represents an acceptable
development in creating a sense of place and identity in complying with the provisions of
the adopted North Lanarkshire Local Development Plan with no other material
considerations to the contrary. It is also considered to align with NPF4 for the reasons
stated above.  There is no objection from consultees, subject to conditions. Whilst the
concerns expressed by a neighbouring resident are noted, it is considered that the
replacement of two primary schools with a primary school and replacement hub will be
built to serve the community and its’ future needs.  There shall be a MUGA pitch which
be available for community use.   It is therefore recommended that planning permission
be granted, subject to conditions. 
Page 61 of 74

Page 62

Application No:  
24/00268/FUL
Proposed Development:  
Extension to school teaching facilities, new sports facilities
and a new early years facility    
Site Address:  
Chryston High School
Lindsaybeg Road
Chryston
G69 9DL      
Date Registered:  
19th March 2024      
Applicant:
North Lanarkshire Council
Civic Centre 
Windmillhill St.
Motherwell 
ML1 1AB    
Agent:
BDP Limited
15 Exchange Place
Glasgow
G1 3AN  
Application Level:
Major Application      
Contrary to Development Plan:
No
Ward:   
05 Stepps, Chryston and Muirhead 
John McLaren, Josh Cairns, Claire Louise
Williams,
Representations:
11 letter(s) of representation received.        
Recommendation: Approve Subject to conditions  
Reasoned Justification:  
The extension to the school teaching facilities, new sports facilities and a new early
years facility, together with a fully landscaped site for the school and associated car
parking and drop off, is considered to be acceptable and aligns with the principles of
both National Planning Framework 4 and the North Lanarkshire Local Plan (2022).     
Page 62 of 74

Page 63

Reproduced by
permission of the
Ordnance Survey on
behalf of HMSO. ©
Crown Copyright and
database right 2009. 
All rights reserved.
Ordnance Survey
Licence number
100023396.
Planning Application: 24/00268/FUL 
Name (of applicant): North
Lanarkshire Council
Site Address: Chryston High School
Lindsaybeg Road
Chryston
G69 9DL
Development: Extension to School
Teaching Facilities, New Sports
Facilities and a New Early Years
Facility   
Page 63 of 74

Page 64

Proposed Conditions:-    
1. That, except as may otherwise be agreed in writing by the Planning Authority, the
development shall be implemented in accordance with drawing numbers or such updated
drawings as may be required to reflect the requirements of planning conditions 2-22 that
follow:-  :-    
CHS-BDP-ZZ-ZZ-PL-L-101008, 23087-SK-03, 23721-SK-01, 23721-SK-02, 46864,
47052, 632001,75981, 900002, 900002, CHS-BDP-ZZ-00-PL-A-PP90004,  CHS-BDP-ZZ-
00-PL-L-A -PP0002,  CHS-BDP-ZZ-RF-PL-A-PP0001,  CHS-BDP-ZZ-SE-A-PP0001,
CHS-BDP-ZZ-ZZ-EL-A-PP90005, CHS-BDP-ZZ-ZZ-PP-L-90001,   CHS-BDP-ZZ-ZZ-PP-
L-90003,  CHS-BDP-ZZ-ZZ-PP-L-90004, DR-C-960003 P03, PL-A-PP0001 P01, PL-A-
PP0003 P01, PP0001, PP0002, PP0003,  PP0004,  Sheet 1 Of 2 (Drainage Construction
Details) , SHEET 2 Of 2 (Drainage Construction Details) Sheet 1 Of 3 (Elevations
Proposed), Sheet 2 Of 3 (Elevations Proposed) and Sheet 3 Of 3 (Elevations Proposed)  
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That visibility splays of 2.0m x 2.0m at a height of 0.60m shall be provided in both directions
along the footway at Pentland Road and shown on a drawing, with the 2m setback
measured from the back of the footway.   
Reason: To ensure adequate sight lines are achieved.  
3. That prior to the development being brought into beneficial use unless otherwise agreed in
writing with the Planning Authority, A ‘School Travel Plan’ shall be produced with the aim of
ensuring that the school commute is via more sustainable means. This School Travel Plan
must align with the principles of the Councils wider travel ambitions.  
Reason:  To ensure that the site is served by appropriate access facilities and in the interest
of road safety.  
4. That prior to any development, unless otherwise agreed in writing with the Planning
Authority, A report detailing measures to mitigate the impact of development traffic shall be
submitted to, and approved in writing by, the Planning Authority in conjunction with the
Traffic & Transportation Officers.  
Reason: To ensure that the site is adequately provisioned without detriment to the local
road network and in the interest of road safety.  
5. That unless otherwise agreed in writing with the Planning Authority before the development
hereby permitted is brought into use, all the parking and manoeuvring areas shown on the
approved plans, shall be levelled, properly drained, surfaced in a material which the
Planning Authority has approved in writing before the start of surfacing work and clearly
marked out, and shall, thereafter, be maintained as parking and manoeuvring areas.  
Reason:  To ensure that the parking and manoeuvring areas are suitable surfaced.  
6. That before the development hereby permitted starts, a scheme of landscaping shall be
submitted to, and approved in writing by the Planning Authority, and it shall include:- 
a) Details of any earth moulding and hard landscaping, grass seeding and turfing;
b) A scheme of tree and shrub planting, incorporating details of the location, number,
variety and size of trees and shrubs to be planted; in particular this should include
a detailed scheme of biodiversity enhancement, seasonal shrub planting and trees
within and bordering the edge of the site. 
c) A detailed timetable for all landscaping works within the site and shall set out that
the works be carried out contemporaneously with the development of the site. Page 64 of 74

Page 65

For the avoidance of doubt, the details submitted to discharge this condition shall build upon
the landscaping plans submitted as part of the application.  
Reason: To enable the Planning Authority to consider these aspects.  
7. That all works included in the scheme of landscaping and planting, approved under the
terms of Condition 6 above, shall be completed in accordance with the approved timetable,
and any trees, shrubs, or areas of grass which die, are removed, damaged, or become
diseased, within two years of the full occupation of the development hereby permitted, shall
be replaced within the following year with others of a similar size and species.  
Reason: To ensure the implementation of the landscaping scheme in the interest of
amenity.  
8. That before any works of any description start on the application site, with the exception of
ground enabling works which includes land profiling and unless otherwise agreed in writing
with the Planning Authority, a comprehensive site investigation report shall be submitted to
and for the approval of the Planning Authority. The investigation must be carried out in
accordance with current best practice advice such as BS10175: ‘The Investigation of
Potentially Contaminated Sites’ or CLR 11. The report must include a site-specific risk
assessment of all relevant pollutant linkages and a conceptual site model. Depending on
the results of the investigation, a Detailed Remediation Strategy may be required.  
Reason: To establish whether or not site decontamination is required in the interests of the
amenity and wellbeing of future residents of the site.  
9. That any remediation works identified by the report agreed in terms of Condition 8 above
shall be carried out in accordance with an implementation timetable.  This timetable shall
be agreed in writing with the Planning Authority before any works start on site.  The shared
campus shall not be occupied until a certificate (signed by a chartered Environmental
Engineer) has been submitted to the Planning Authority confirming that any remediation
works have been carried out in accordance with the agreed Remediation Strategy.  
Reason: To ensure that any remediation identified has been implemented in the interests
of the amenity and wellbeing of users.  
10. That before the development hereby permitted starts, with the exception of ground enabling
works which includes land profiling and unless otherwise agreed in writing with the Planning
Authority, full details of the proposed surface water drainage scheme shall be submitted to
the said Authority and shall be certified by a chartered civil engineer as complying with the
most recent SEPA SUDS guidance.  
Reason: To ensure that the drainage scheme complies with best SUDS practice to protect
adjacent watercourses and groundwater and in the interests of the amenity and wellbeing
of existing and future residents adjacent to and within the development site.  
11. That the SUDS compliant surface water drainage scheme approved in terms of Condition
10 shall be implemented contemporaneously with the development in so far as is
reasonably practical. Within three months of the construction of the SUDS, a certificate
(signed by a Chartered Civil Engineer experienced in drainage works) shall be submitted to
the Planning Authority confirming that the SUDS has been constructed in accordance with
the relevant CIRIA Manual and the approved plans.  
Reason: To safeguard adjacent watercourses and groundwater from pollution and in the
interests of the amenity and wellbeing of existing and future residents adjacent to and within
the development site.  
Page 65 of 74

Page 66

12. That prior to any works commencing on site, with the exception of ground enabling works
which includes land profiling a Construction Environmental Method Statement shall be
submitted to and approved by the Planning Authority. The Construction Method Statement
shall cover:  
• Details of how the development will be phased 
• Details of the location of site compound and management facilities
• Details of construction access, parking and manoeuvring areas
• Submission of a Dust Action Plan  
The development shall thereafter be implemented in accordance with the approved
Construction Method Statement.  
Reason: In the interests of the amenity of the area and to ensure ecological protection
measures are in place.  
13. That should 12 months or more has elapsed between the timing of the initial ecological
survey dated August 2023 hereby approved, and development commencing, a further
survey shall be undertaken on the site to determine the presence of any statutorily protected
species including Badgers and water voles, the said surveys shall thereafter be submitted
to and approved in writing by the Planning Authority before any development commences
on the site. As a result of the study, should any mitigation measures be required for any
protected species, this shall be implemented in accordance with the species protection plan
agreed in writing with the Planning Authority in consultation with Scottish Natural Heritage
before works commence on the site.  
Reason: To ensure compliance with The Conservation (Natural Habitats & c.) Regulations
1994 (as amended); the Wildlife and Countryside Act (1981) as amended; the Protection of
Badgers Act 1992 (as amended); and the Nature Conservation (Scotland) Act 2004.'  
14. That unless otherwise agreed in writing with the Planning Authority and before the
development hereby permitted starts a letter/confirmation is provided from Nature Scot
confirming that the all works in relation to the relocation of the Water Voles has been
undertaken in accordance with the licence issued by Nature Scot.   
Reason: To ensure compliance with The Conservation (Natural Habitats & c.) Regulations
1994 (as amended); the Wildlife and Countryside Act (1981) as amended; the Protection of
Badgers Act 1992 (as amended); and the Nature Conservation (Scotland) Act 2004.  
15. That before the development hereby permitted starts, with the exception of ground enabling
works which includes land profiling, and unless otherwise agreed in writing with the Planning
Authority, full details of the facing materials to be used on all external walls and roofs shall
be submitted to and approved in writing by the Planning Authority.    
Reason: In the interests of amenity and design by ensuring that external materials are
appropriate for the site.  
16. That before the development hereby permitted starts, with the exception of ground enabling
works which includes land profiling, and unless otherwise agreed in writing with the Planning
Authority, full details of the design and finish materials to be used in the construction of the
access road, footways, junctions, parking and manoeuvring areas shall be submitted to and
approved in writing by the Planning Authority.  The approved details shall be implemented
contemporaneously with the development in so far as is reasonably practical.  
Reason: In the interests of amenity and design by ensuring that the materials are
appropriate for the site.  
17. That before the development hereby permitted starts, with the exception of ground enabling
works which includes land profiling, and unless otherwise agreed in writing with the Planning Page 66 of 74

Page 67

Authority, full details of the design and location of all fences and walls to be erected on the
site shall be submitted to and approved in writing by the Planning Authority.  The approved
details shall be implemented contemporaneously with the development in so far as is
reasonably practical.   
Reason: To enable the Planning Authority to consider these aspects in detail.  
18. The design, installation and operation of any air conditioning/ventilation or other plant for
the proposed development and any other noise associated with the completed development
shall be such as will not give rise to a noise level, assessed with the windows open, within
any dwelling or noise sensitive buildings in excess of the equivalent to Noise Rating Curve
(N.R.C.) 35 between 07.00 hours and 22.00 hours and N.R.C. 25 at all other times.  
Reason:  In the interests of surrounding residential amenity.  
19. The New synthetic pitch and netball court as shown on the proposed site plan shall be
designed and constructed by a recognised (e.g. SAPCA* registered) specialist pitch
contractor. Details of the contractor(s) and pitch specifications (including lighting
specification for the synthetic pitch) shall be submitted to, and approved in writing by, the
Planning Authority prior to the commencement of the development. Thereafter the
development shall be completed in accordance with the approved details.  
Reason: To ensure that the replacement pitches are of suitable quality.  
20. That prior to the 9-a-side football pitch being brought into beneficial use, a 4m high acoustic
barrier fence, as detailed in drawing reference CHS-BDP-ZZ-ZZ-PL-L-101008, shall be
constructed.  This fence shall have a minimum mass of 15kg/m2 and shall be maintained
and retained for the duration of the development.  
Reason: In the interest of the amenity of the site and the general area.  
21. The completed 9-a-side football pitch, when brought into beneficial use, shall have restricted
hours of operation limiting the hours from 9am until 9pm, Monday to Friday and 9am until
6pm on Saturday and Sunday.  
Reason: In the interest of the amenity of the site and the general area.  
22  A lighting schedule shall be submitted to and approved in writing by, the Planning Authority
prior to any part of the development being brought into beneficial use. Any floodlighting
associated with the 9-a-side football pitch, when brought into beneficial use, shall have
restricted hours of operation limiting the hours from 9am until 9pm, Monday to Friday and
9am until 6pm on Saturday and Sunday.  
Reason: In the interests of residential amenity.     
Page 67 of 74

Page 68

Background Papers:  
Consultation Responses:  
Traffic & Transportation     29th July 2024
Environmental Health (including Pollution Control)  9th April 2024 & 1st August 2024
Sport Scotland      5th April 2024
Scottish Gas Network      21st March 2024
The Coal Authority      25th March 2024 
Scottish Water      2nd April 2024 
Contact Information:  
Any person wishing to inspect these documents should contact Colin Bradley at 01236 632500    
Report Date:  
2nd August 2024 
Page 68 of 74

Page 69

APPLICATION NO. 24/00268/FUL  
REPORT  
1. Site Description  
1.1  The existing school is centrally located within Chryston. It is intended to site a 500
pupil capacity extension to the south of the existing building running parallel with
Pentland Road.  
1.2 The site is bound by residential properties accessed from Main Street to the North,
Pentland Road to the east, private residential dwellings accessed from Bowling Green
Road and Park Road to the south and Lindsaybeg Road to the west.  
1.3 The overall site measures some 5.83 hectares and the gross floor space of the proposed
school including the extension shall measure 4,653m2 over two storeys within this
overall space.  
2. Proposed Development  
2.1 It is intended to provide a 500 pupil extension, bringing the total roll call to 1,400 pupils,
with an extension footprint of 2,915m2, to the existing Chryston High School alongside
new sports facilities and a new early years facility.  
2.2 The proposed extension, split over two storeys, features a games hall along with
ancillary changing areas, 2 x fitness studios, toilets, a drama studio, dining and
socialising space and 10 classrooms dedicated to the ‘English’ department. There are
further ancillary services and a water storage tank room.  To the 2nd floor there are 4
modern language classrooms, 3 Religious education rooms and 6 social subject
education to the high school extension. Separately, through two internal ‘bulkhead’
doors, there shall be the early years facility element of the design. This facility shall
feature an entrance lobby, circulation space, cloak room, two large ‘playrooms’, toilets
and nappy changing facilities, a kitchen area, parents room, an admin room and a ‘head
of centre’ room. The principal access point for the Early Years facility shall be taken from
Pentland Road, whereas the principal access point is taken from Lindsaybeg Road.    
2.3 It is intended to expand the principal parking provision by 92 spaces to the east of the
existing 11-aside football pitch and to the south of the principal access point to the
building.  This element of parking provision is accessed via Lindsaybeg Road.  Further
parking provision provided is via Pentland Road and the overall development, including
the existing parking provision, provides 200 parking spaces.  NLC Traffic &
Transportation have been consulted and are satisfied that the level of provision and the
levels of electric parking and Disabled bays are satisfactory to accommodate the
proposed development.  
3. Applicant’s Supporting Information  
3.1  The applicant has provided the following documents alongside a full suite of drawings;  
• Construction Method Statement
• Environmental Noise Survey Report
• Transportation Assessment
• Flood Risk Assessment
• Design & Access Statement
• Drainage Strategy Report
• Ground Investigation Report
• Preliminary Ecological Assessment
• Tree Survey Page 69 of 74

Page 70

• Water Vole Species Protection Plan. 
4. Site History  
• 09/00972/PASE Erection of High School – Comments given 11th September 2009
• 09/01051/PAN Construction of a New Secondary School – Comments given 1st
October 2009
• 10/00315/FUL Erection of School Building and Culture Centre, Construction of
Floodlight Synthetic Pitch with Associated Parking and Landscaping – 13th May
2010
• 23/00983/PAN Extension to High School – comments given 27th September 2023  
5. Development Plan  
5.1 The site sits within a ‘General Urban Area’ and is cover by policies ‘PP 3 – Purpose of
Place’ and ‘AD 3 Amount of Development’ in the North Lanarkshire Local Development
Plan 2022. All development is required to be assessed against the Environmental Design
Qualities policies, EDQ 1-3 also.  
5.2 The site is also subject to National Planning Framework 4 and of particular relevance are
policies 3 - Biodiversity 9 – Brownfield vacant and derelict land and empty buildings, 14 –
Design quality and place, 15 Local living and 20-minute neighbourhoods, 21 – Play,
recreation and sport and 25 - Community wealth building.  
5.3 The impacts of the policies identified above shall be examined in the planning assessment
stage of the report in section 8.  
6. Consultations  
6.1 NLC Traffic & Transportation do not object to the proposal subject to two conditions with
regards to a visibility splay for pedestrians where the access crosses a footway and a
report detailing mitigation measures to offset the impact of traffic generated by the
development.  This report shall be required to be signed off on consultation with NLC
Traffic & Transportation.  
6.2 NLC Protective Services initially requested further information with regards to the
proposed 9 a-side pitch which is to be sited to the south of the overall development site
and in close proximity to dwelling houses accessed via Bowling Green Road. Upon receipt
of the further information supplied by the applicant with regards to the 9-a-side football
pitch, NLC Protective Services are happy to condition the siting of a 4m tall acoustic barrier
fence and a restriction in hours of operation for the football pitch (and its floodlights) limiting
its use to 9am till 9 pm 
A site Investigation has also been requested along with a lighting schedule.  
6.3 NLC Greenspace have been consulted with regards to this proposal.  They have been
involved, along with Nature Scot, in providing a licence to move Water-Voles which had
been detected on site.  This work has been undertaken with Gatcosh Nature Reserve
being the preferred relocation area. A planning condition has been added to ensure that
the work has been undertaken in accordance with the relevant licence.  
6.4 Sport Scotland explicitly state that whilst they do not object to the proposal, they would
recommend that further consideration is given to meeting the minimum recommended
levels of sports provision, (specifically 1 SPG and 4 full-size grass pitches). Sport Scotland
recognise however the constrained nature of the site and as such hold no objection,
subject to a condition with regards to the installation of the 9-a-side football pitch which
has been added to the list of conditions.  
Page 70 of 74

Page 71

6.5 Scottish Gas Networks have confirmed that they do not have any high-pressure assets
in the immediate vicinity and as such have no comments on the application nor any
objection to it.  
6.6 The Coal Authority did not seek to hold an objection to the proposal as the site sits within
a ‘Low Risk Area’.  
6.7 Scottish Water have confirmed capacity for both ‘potable’ water from the Balmore Water
Treatment Plant and foul water connection to the Dalmuir PFI Waste Water Treatment
Plant.  
7. Representations  
7.1 11 letter(s) of representation have been received all seeking to object to the proposal. The
reasons for these objection comments are principally based around the proposed 9-a-side
football pitch, the impact of the proposal with regards to traffic and traffic management and
ecological considerations. All of the points raised shall be discussed in the following
paragraphs.  
7.2 Comment: Noise Pollution from 9-a-side football pitch shall have a detrimental impact on
residential amenity. (Including Anti-social language and unsupervised social gathering)   
Response: NLC Protective Services have been consulted with regards to the proposal
and have recommended that 2 conditions are attached ensuring that a 4m high acoustic
barrier fence, as detailed in drawing reference CHS-BDP-ZZ-ZZ-PL-L-101008, is included
in the final construction.  A further condition is requested restricting the hours of the use
of the pitch from 9am until 9pm, Monday to Friday and 9am until 6pm on Saturday and
Sunday. With the implementation of these conditions, it is considered that the impact on
residential amenity of the 9-a-side pitch shall be within acceptable levels.  
7.3 Comment: Light Pollution from 9-a-side football pitch shall have a detrimental impact on
residential amenity and garden ground.   
Response: The flood lighting provision associated to the 9-a-side pitch shall be restricted
to operating to the opening hours of the pitch, 9am until 9pm, Monday to Friday and 9am
until 6pm on Saturday and Sunday. It is considered that the solod acoustic barrier fence
shall also do much to reduce light pollution spilling into the homes and gardens for nearby
residents and as such, it is considered that light pollution shall not have a significant or
detrimental impact on neighbouring residential properties.  
7.4 Comment: The ecological impacts of artificial grass are detrimental to bio-diversity,
(including Fossorial Water Voles):   
Response: Nature Scot and NLC Greenspace have been working with the applicants to
ensure suitable safe-guarding and relocation to a suitable alternative environment have
been identified and a licence has been issued by Nature Scot to relocate the Fossorial
Water Voles.  This action is being undertaken as part of the preparatory works, undertaken
through permitted development legislation. The applicant has identified various bio-
diversity enhancements that may be added to the development site and details of this
require to be finalised in the landscaping scheme to be submitted for the site.  
7.5  Comment: Access may be taken directly to the 9-a-side football pitch from Bowling Green
Road.   
Response: There is no access point proposed to link Bowling Green Road to the school
campus.  
7.6  Comment: Bowling Green Road is privately maintained and additional strain shall be
placed on the road surface to the expense of the local residents. Page 71 of 74

Page 72

Response: There shall be no access to the school campus via Bowling Green Road.
Substantial additional parking has been included within the site and as such, it is not
considered there shall be a significant or detrimental impact to the current quality of the
road surface at Bowling Green Road.  
7.7  Comment: Parking issues are prevalent across the surrounding road network.   
Response: NLC Traffic & Transportation have been consulted with regards to this
application and did not seek to object to the proposal.  As part of their response, NLC
Traffic & Transportation have requested that a report detailing mitigation measures to
offset the impact of traffic generated by the development be submitted to the Planning
Authority and visibility splay requirements for pedestrians.  With regards to parking, the
department noted that “Two new parking areas are proposed with the site, providing a
total of 108no. spaces including 7no. accessible bays to compliment the existing 92no.
spaces.” It is therefore considered that the proposal shall not have a significant or
detrimental impact on the current parking provision in the immediate vicinity.  
7.8  Comment: General disruption due to the construction process, (including parking and
deliveries).   
Response: Within the ‘Construction Methodology Report’ there is a ‘Site Access/Traffic
Management Plan’ which includes details of how the development shall proceed without
hinderance to the road network and there is an area set aside for staff parking within the
development site.  The Planning Service are satisfied that the development can be carried
out without detriment to the local road network.  
7.9    Comment: Alternative sites available locally for sports provision.   
Response: The Planning Service can only determine applications presented to them. In
this instance the application is seeking to extend an existing educational facility (achieved
through the relocation of the primary school) along with the sports provision required to
support the extension.  
7.10 Comment: Over-development of the site.   
Response: The site was previously host to both Chryston High School and Chryston
Primary School, which has been relocated through a previous application. As the
application is to replace the previous educational facility with an extension to an existing
educational facility it is considered that there is no over-development of the site.  
7.11  Comment: Query as to whether enhanced job opportunities for the local community may
come from the development.   
Response: This query, received from the Chryston Community Council, is out with the
remit of the Planning Service.  Therefore, this query cannot be commented on within this
report.  
8. Planning Assessment 
8.1  In accordance with Section 25 of the Town and Country Planning (Scotland) Act 1997,
planning decisions must be made in accordance with the Development Plan unless
material considerations indicate otherwise. The development plan consists of National
Planning Framework 4 (NPF4) and the Adopted North Lanarkshire Local Development
Plan 2022 The National Planning Framework was adopted on the 13th of February 2023.
Of particular relevance, is NPF Policies 9 – Brownfield vacant and derelict land and empty
buildings, 14 – Design quality and place, 15 Local living and 20 minute neighbourhoods,
21 – Play, recreation and sport and 25 - Community wealth building.   Page 72 of 74

Page 73

NPF4  
8.2 Policy 3 of NPF 4 -Biodiversity has the stated aim of including appropriate measures to
conserve, restore and enhance biodiversity, in accordance with national and local
guidance. It goes on to state that measures should be proportionate to the scale and
nature of the development. delivering positive effects from the development and
strengthen nature networks. The applicant has submitted a Biodiversity Enhancement
plan at point 5.1.15 of the Preliminary Ecological Report, (PEA) which features details on
the biodiversity enhancement opportunities including tree & shrub planting, hedgerow
planting, along with bat and bird boxes. It is considered this proposal is compliant with the
principles of this NPF 4 policy.  
8.3  Policy 9 of NPF 4, Brownfield, vacant and derelict land and buildings seeks to promote
and facilitate the reuse of brownfield land and help reduce the need for greenfield
development. It is considered this proposal is compliant with the principles of this NPF 4
policy through the redevelopment of a previous educational facility to extend an existing
educational facility.  
8.4  Policy 14 of NPF 4, Design, quality and place seeks to encourage, promote and facilitate
well designed development that makes successful places by taking a design led approach.
Through the pre application engagements with the community and other relevant
stakeholders along with the benefits the development shall bring to the community, it is
considered this proposal is compliant with the principles of this NPF 4 policy.  
8.5 Policy 15 of NPF 4, Local Living and 20-minute neighbourhoods seeks to create
connected and compact neighbourhoods within a reasonable distance of their home,
preferably by walking, wheeling or cycling or using sustainable transport options. This
proposal includes re-instatement of a path running east to west through site and as such
it is considered this proposal is compliant with the principles of this NPF 4 policy.  
8.6  Policy 21 of NPF 4, Play, recreation and sport seeks to encourage, promote and
facilitate spaces and opportunities for play, recreation and sport. Through the inclusion of
an additional 9-a-side football pitch within the design, it is considered this proposal is
compliant with the principles of this NPF 4 policy.  
8.7 Policy 25 of NPF 4, Community wealth building seeks to encourage, promote and
facilitate a new strategic approach to economic development.  As this proposal is for an
educational facility, it is considered this proposal is compliant with the principles of this
NPF 4 policy.  
Local Development Plan  
8.8  Purpose of Place Policy PP 3 (general Urban Area) applies seeks to maintain and improve
the level of amenity in urban areas by encouraging development that is in keeping with
their residential character and encouraging diversity in more mixed-use areas.  As the site
was previously host to a primary school, and is intended to provide additional educational
facilities to an existing high school, it is considered that this shall maintain and improve
the level of amenity and is therefore compliant to this policy.  
8.9  Policy AD 3 Amount of Development requires new development to be assessed for their
implications related to the amount of development proposed and depends on a
combination of use class, scale and location. Class 10 non-residential do not require the
amount of development to be assessed and thus the proposal is acceptable.  
8.10  Environmental and Design Qualities Policies EDQ 1 -3 apply to all new development
proposals and are addressed in turn below.  
i. Policy EDQ 1 (Site Appraisal): This policy requires a high quality of development by
ensuring proposals integrate well into the surrounding area and avoid harm to Page 73 of 74

Page 74

neighbouring amenity. It also considers the impact of the proposed development in
terms of its requirements for additional community facilities or infrastructure which is
necessary to meet future demands on existing provisions.  
ii. Policy EDQ2 (Specific Features for Consideration): There are no Hazardous Zones and
as such the policy is not relevant in this case.  
iii. Policy EDQ 3 (Quality of Development): This policy requires high standards of site
planning and sustainable design  
8.11  The proposed development seeks to extend the existing high school provision within the
settlement of Chryston, provide further sports facilities to the community and replace an
existing ‘Early Years Facility’.  The high school extension has been the subject of detailed
discussions with the community in advance of the application having been submitted to
ensure it reflects all the needs of the community it will serve. This is detailed in the Design
and Access Statement submitted by the applicant. As required it has been designed to
provide a safe, inclusive, convenient and welcoming development. The site has been
considered in its entirety with the building positioned in such a way as to sympathetically
relate to surrounding residential development. The scale and massing of the building,
although considerable, is considered to be acceptable given the large plot within which it
shall sit. The material palette is reflective of modern building practices. The proposal
provides Biodiversity gain through design elements and the site will be well landscaped.
Updated sports facilities will also be delivered to the area. The proposal is considered to
be compliant with the requirements of the policies as outlined above and is considered to
be acceptable in planning terms and in keeping with the character the area.  
9. Conclusions  
9.1 It is therefore considered for the above reasons that the proposed development is
acceptable in policy terms and is acceptable in terms of residential amenity. This
application is consequently recommended for approval subject to the imposition of
appropriate planning conditions. Taking the above assessment into account, it is
considered that the detailed design and layout of the proposal represents an acceptable
development in creating a sense of place and identity in complying with the provisions of
the adopted North Lanarkshire Local Development Plan with no other material
considerations to the contrary. It is also considered to align with NPF4 for the reasons
stated above.  There is no objection from consultees, subject to conditions. Whilst the
concerns expressed by a neighbouring residents are noted, it is considered that the
extension to school teaching facilities, new sports facilities and a new early years facility
will be built to serve the community and its’ future needs.  There shall be a sports pitch
which be available for community use. It is therefore recommended that planning
permission be granted, subject to conditions.
Page 74 of 74