Democracy Spraffa

Agenda Document Pack - Planning Committee - 14/08/2025

North Lanarkshire Council · 14 August 2025
Back to Planning Committee — 14 August 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Clerk Name: Clare Louise McDonald
Clerk Telephone: 07350 435308
Clerk Email: committee@northlan.gov.uk
5 August 2025
Members of the
Planning Committee
Chief Executive’s Office
Rachel Blair
Chief Officer (Legal & Democratic)
Civic Centre, Windmillhill Street,
Motherwell ML1 1AB
www.northlanarkshire.gov.uk
Notice is given that a Meeting of the Planning Committee is to be held in the Council
Chamber, Civic Centre, Windmillhill Street, Motherwell, ML1 1AB on Thursday, 14 August
2025 at 10:00 AM which you are requested to attend.
The agenda of business is attached.
Rachel Blair
Chief Officer (Legal & Democratic)
Members :
N Shevlin, G Currie, G Brennan, B Burgess, A Bustard, J Cairns, T Carragher, M Coyle, S
Coyle, K Docherty, T Fisher, M Hughes, L Jarvie, T Johnston, J Logue, H Loughran, J
McLaren, C McManus, M McPake, A McVey, L Mitchell, J Reddin, D Robb, A Smith, G
Woods.
Page 1 of 88

Page 2

Page 2 of 88

Page 3

Agenda
1 Declarations of Interest In Terms of the Ethical
Standards In Public Life Etc. (Scotland) Act 2000
Operational
2 Planning Applications Index
Submit Planning Applications Index.
5 - 84
3 Notice of Planning and Enforcement Appeals
Decisions
Submit report by the Chief Officer (Place) advising of
recent decisions in respect of Planning Appeals lodged
with the Scottish Ministers
85 - 88
Page 3 of 88

Page 4

Page 4 of 88

Page 5

North 
Lanarkshire 
Council 
Planning Applications for consideration 
of Planning Committee 
Committee Date: 14th August 2025                    
Ordnance Survey maps reproduced from Ordnance Survey 
with permission of HMSO Crown Copyright reserved 
Item 2
Page 5 of 88

Page 6

APPLICATIONS FOR PLANNING COMMITTEE
14th August 2025
Page No Application No Applicant Development/Site Recommendation
8-30 24/00230/PPP North Lanarkshire
Council
Residential Led Mixed Use
Development with
Associated Access, Open
Space, Landscaping,
Drainage Features and
Associated Infrastructure
(in Principle)
Land At
Palacerigg Road
Cumbernauld
Grant
31-37 24/00965/FUL Mr Scott Forrest Erection of a Dwelling
Land At
Baxter Brae
Cleland
Grant
39-52 24/01039/FUL Prime Acres Ltd Part Change of Use of
Former Peat Works
Minerals Operation (Sui
Generis) to form Class 6
Use (Open Storage Yard
for Inert Material) with
Ancillary Class 4 Use of
Replacement Shed (in
Retrospect) for
Administration of Storage
Operation
Land at
Peat Works
Cumbernauld Road
Moodiesburn
Grant
53-59 25/00085/FUL Diack & Macaulay
Ltd
Change of Use from Bus
Depot to Traffic 
Management Depot with
Ancillary Administration 
Building
560 Stirling Road
Airdrie
ML6 7SS
Grant
Page 6 of 88

Page 7

60-76 25/00219/S42 EG on the move Section 42 Application to
Vary Condition 11 (Timing
of Submission of
Landscaping Scheme) of
Planning Permission
21/01275/FUL for Roadside
Services Area Comprising
Petrol Filling Station,
Ancillary Retail Unit, Drive-
Thru (Class 3) Units, HGV
and Car Parking Areas,
Associated Facilities,
Landscaping, Infrastructure
Works and New Junction
Access
2 Hornshill Court
Stepps
G33 6QU
Grant
77-83 25/00444/FUL Mr Richard
Hamilton
Change of Use from Office
to Class 1A (Shops,
Financial, Professional and
other Services) and
Training Academy 
(In Retrospect)
Unit 13
3 Wardpark Road
Wardpark
Cumbernauld
G67 3JZ
Grant
Page 7 of 88

Page 8

Application No:
24/00230/PPP
Proposed Development:
Residential led mixed use development with associated access,
open space, landscaping, drainage features and associated
infrastructure (in principle)
Site Address:
Land At
Palacerigg Road
Cumbernauld
Date Registered:
8th March 2024
Applicant:
North Lanarkshire Council
Assets & Procurement (Estates)
Civic Centre
Motherwell
ML1 1AB
Agent:
Stantec
9 George Square
5th Floor
Glasgow
G21DY
Application Level:
Major Application
Contrary to Development Plan:
No
Ward:   
04 Cumbernauld East
Claire Barclay, Tom Johnston, Barry McCulloch,
Adam Smith.
Representations:
72 letters of representation received.
Recommendation: Approve Subject to Conditions
Reasoned Justification:
The development is considered to accord with the relevant policies of NPF4 and the North
Lanarkshire Local Development Plan.  The development would support the aims of developing
the wider South Cumbernauld Community Growth Area and in principle it would integrate
satisfactorily with the surrounding area and not result in a significant adverse impact on
established residential amenity or environmental designations.
Notes to Committee:
1. It is considered necessary to extend the implementation period for this permission from 5
years to 10 years due to the complexities of the site.
Page 8 of 88

Page 9

Reproduced by
permission of the
Ordnance Survey on
behalf of HMSO. ©
Crown Copyright and
database right 2009.  All
rights reserved.
Ordnance Survey
Licence number
100023396.
Planning Application: 24/00230/PPP 
Name (of applicant): North Lanarkshire
Council
Site Address: Land At
Palacerigg Road
Cumbernauld 
Development: Residential led mixed use
development with associated access,
open space, landscaping, drainage
features and associated infrastructure (in
principle)   
Page 9 of 88

Page 10

Length of permission 
Direction: 
North Lanarkshire Council directs that subsection (2A)(b) of section 59 of the Town and Country
Planning (Scotland) Act 1997 applies as respects planning application reference 24/00230/PPP with
the substitution for the period of 5 years referred to in (2A) (b) of section 59 by the period of 10 years. 
The following applies: 
The length of the permission: That the development to which this permission in principle relates
must be begun not later than the expiration of 10 years beginning with the date on which the
permission is granted. If development has not begun at the expiration of this period, the planning
permission in principle lapses.  
Submission of matters specified by conditions applications (MSC) and implementation of
development  
To be clear, to enable the full implementation of the development herby permitted before the 10 year
period above has expired, application(s) for approval of all the matters specified above must be
submitted covering the whole development area; all prior to commencement conditions imposed on
said MSC permission(s) must be discharged and a site start made to the satisfaction of the Council as
planning authority.   
Proposed Conditions:- 
1.  That before development of each phase of works starts, a further planning application for
Approval of Matters Specified in Conditions (MSC) shall be submitted to the Planning
Authority in respect of the following matters:- 
(a)  the siting, design and external appearance of all buildings and other structures;
(b)  the means of access and any servicing to the site;
(c)  the layout of the site, including all roads, footways, and parking areas;
(d)  the provision of equipped play areas in accordance with the terms of condition 2(c) below
and shall include;
(i)  details of the type and location of play equipment, seating and litter bins to be
situated within the equipped play areas;
(ii)  details of the surface treatment of play areas, including the location and type of
safety surface to be installed;
(iii)  details of any fences to be erected around play areas,
(iv)  details of a DDA compliant access; 
(v)  a timetable for the implementation of the play area(s) across the site.
(e)  the provision of public open space;
(f)   the details of, and timetable for, the hard and soft landscaping of the site;
(g)  details for management and maintenance of the areas identified in (d), (e) and (f) above
as well as for any active travel infrastructure to be provided as part of delivery of the
phase along with proposed connection points to the wider area and or next adjoining
phase of development; 
(h)   the design and location of all boundary walls and fences;
(i)    the phasing of the development;
(j)    the provision of drainage works;
(k)  the disposal of sewage;
(l)    details of existing trees, shrubs and hedgerows to be retained;
(m)  details of existing and proposed site levels; 
(n)   noise attenuation measures for any parts of the site where there is potential for noise
nuisance;
(o)   details of connectivity through the site and to the wider area;
(p)  details of digital infrastructure with open access to providers;
(q)  biodiversity enhancement plan;
Page 10 of 88

Page 11

(r)  construction environmental management plan. 
Reason: To accord with the provisions of the Town and Country Planning (Scotland) Act
1997 as amended by the Planning etc (Scotland) Act 2006. 
2. That notwithstanding the generalities of Condition 1 above, the first Approval of Matters
Specified by Condition application shall include the following:- 
(a) A detailed phasing plan for the area showing the order of development, including how the
road layout and active travel links will be progressed across the site. For the avoidance of
doubt the location of the Mixed Use Community Hub and central Multi Use Games/play
area shall be clearly defined on the phasing plan and unless otherwise agreed in writing,
the first phase of the development shall be taken from the approved new northern access
from Lenziemill Road; 
(b) An Active Travel and Connectivity Strategy for the area approved under the terms of this
permission. Shared use paths in accordance with the Council’s new Active Travel
Strategy should be provided. For the avoidance of doubt details will be provided to
demonstrate which phase will deliver what part of the strategy; 
(c) A Public Transport Strategy for the area approved under the terms of this permission.
Consideration should be given to improved connectivity to existing bus and rail
infrastructure in the local area and include the diversion and extension of existing bus
services into the site, new or upgraded bus stops and shelters within 400m of all
dwellings and real-time passenger information and accessibility improvements.  Bus stop
provision should be considered throughout the site (along spine road). Relocated and any
new bus stops, infrastructure or services shall be agreed with North Lanarkshire Council
and Strathclyde Partnership for Transport and the costs of works met by the Developer.
Routes to and from new bus stops should be considered in relation to pedestrian
connections within the site and to neighbouring communities. All proposed bus
infrastructure within the site should be designed to current standards, fully accessible with
high access kerbs and shelter provision; 
(d) A Play Strategy for the area approved under the terms of this permission. For the
avoidance of doubt this shall be provided at a proportionate level directly relating to each
development phase as submitted and shall include a central Multi Use Games/play area
and play route located in the heart of the site (This can be a combination of Multi Use
Games Area (MUGA), Local Equipped Play Area (LEAP) and Neighbourhood Equipped
Play Area (NEAP), to be bounded by existing woodland.  Details shall be provided to
demonstrate which phase will deliver what part of the strategy. For the avoidance of doubt
the first phase of the development shall deliver a MUGA. That unless otherwise agreed in
writing the total play provision within the application site shall include the following :- 
• 3 MUGAS (2,400 square metres)
• 6 LEAPS (2,400 square metres)
• 9 NEAPS (9000 square metres) 
These areas shall total 13,800 square metres across the site and shall be delivered
contemporaneously with each phase of housing in accordance with the phasing plan
agreed under the terms of condition 2 (a) above.  Consideration should also be given to
natural or wild play options. The play areas shall be implemented in accordance with the
timescales and phasing plan approved under the terms of this condition; 
(e) A Drainage Strategy for the area approved under the terms of this permission. For the
avoidance of doubt details will be provided to demonstrate which phase will deliver what
part of the strategy; 
(f) A Recreational Management Plan adhering to the design solutions referred to in the
Recreational Management Plan (Stantec Rev D dated February 2025) including the
measures shown in drawing B2-Acad 05 (Rev A) and described in section 5 of the plan.
Page 11 of 88

Page 12

For the avoidance of doubt the Recreational Management Plan shall include; 
- full details of the path network to be provided throughout the site, together with controlled
‘gateways’ and entrance features through to the woodland areas surrounding the site and
shall connect to the core path network; 
- provision within the Site of 44.6ha (approx.) of high-quality greenspace, including over
5.6km of signed and waymarked walking routes and the upgrading of 1.49km of core
paths; 
- Gateway features and signage at the entrance points into Palacerigg Country Park which
promote the use of established paths, and discourage use of Slamannan Plateau and
West Fannyside Moss beyond. 
- Use of planting to direct movement and discourage informal access. 
The Recreational Management Plan shall be implemented in accordance with the timescale
approved under the terms of this condition and will align with the programme of phasing
approved under the terms of Condition 2 (a) above.   
(g) A Strategic Biodiversity and Landscaping Strategy, that aligns with the terms of condition
2(f) above and reflects the phasing plan agreed under Condition 2 (a) above.   
For the avoidance of doubt these details require to be submitted and approved in writing by
the Planning Authority prior to the construction of the first dwellinghouse. 
Reason: To ensure that these details are considered at the earliest opportunity and facilitated
at the appropriate time in order to ensure the effective and appropriate delivery of the
development within appropriate timescales, as well as in terms of 2 (f) above to offer
controlled access outwith the site to minimise any disturbance on the Slamannan Plateau
Special Protection Area (SPA), protected for its population of wintering Taiga Bean Geese,
West Fannyside Moss Special Area of Conservation (SAC) and the North Bellstane Plantation 
Site of Special Scientific Interest (SSSI). 
3.  That notwithstanding the requirements of conditions 1 and 2 above, any future applications at
the site shall ensure the following roads and transportation requirements: 
a) No road shall be the sole means of access to more than 300 units:
b) Unless otherwise agreed in writing with the Planning and Roads Authority any roads
serving more than 200 dwellings should be consistent with a ‘connector road’ standard.
Design criteria as follows:
• Design Speed 30kph; Limited frontage access; Carriageway Width 6.5metres;
Gradient 1% to 5% (Up to 8% may be permitted in difficult sites); 25metre minimum
horizontal curve radius, 3.5m shared use path provision on one side of carriageway
with 2m verge or footway on other side (depending on pedestrian demand)
c) Unless otherwise agreed in writing with the Planning and Roads Authority the developer
shall ensure that the length of Palacerigg Road between Lenziemill Road and the junction
with the internal ‘connector road’, meets the geometry requirements in condition 3 b)
above.  Note this does not include a requirement to provide for improved active travel
provision on one side of the road if alternative connections are provided. Active travel
provision will require to align with the strategy approved under the terms of condition 2 (b)
above.
d) Before the first unit is occupied within the site, unless otherwise agreed in writing, a new
traffic signal junction incorporating pedestrian phases shall be formed from Lenziemill
Road, with continuous active travel links to that phase of development. Details of the
improvements to be agreed with the Council’s Transportation Team to ensure school
children have an appropriate walking route to school. Active travel provision will require to
align with the strategy approved under the terms of condition 2 (b) above.
e) The implementation of the second signalised junction from Lenziemill Road shall be
determined by pedestrian and vehicular travel demands. This would be subject to further
Page 12 of 88

Page 13

discussions and agreement with the Council’s Transportation team and shall require to
align with the phasing plan approved under the terms of condition 2 (a) above;
f) Any internal road layout should be designed in accordance with the principles of
'Designing Streets' as published by the Scottish Government;
g) The minimum junction spacing for connector roads is 25 metres. 
Reason: To ensure appropriate roads and transportation arrangements are designed to
accommodate the overall development.   
4. That unless otherwise agreed in writing with the Planning Authority, and subject to the
conditions of this permission, the development shall be designed to accord with the following: 
(a)  the maximum number of residential units to be 1400;
(b)  No trees within the application site shall be lopped, topped or felled and no hedges
shall be removed from the application site, without the prior approval in writing of the
Planning Authority;
(c)  Land for a centrally located Mixed Use Community Hub site shall be safeguarded and
this shall be located adjacent to the centrally located Multi Use Games/play area;
(d) That unless otherwise agreed in writing the build platforms and boundary landscape
buffers shall be as illustrated on the Masterplan Drawing Ind04B;
(e)  Each phase of the development shall include provision for 20% Affordable Homes
and have good connections to the Town Centre and Railway Station. 
Reason:  To define and ensure delivery of all key aspects of the permission. 
5. That with each forthcoming MSC application for each phase of development and BEFORE
any works of any description start on that phase of development , unless otherwise agreed in
writing with the Planning Authority, a comprehensive site investigation report shall be
submitted to and for the approval of the said Authority. The investigation must be carried out
in accordance with current best practice advice, such as BS 10175: 'The Investigation of
Potentially Contaminated Sites' or CLR 11. The report must include a site specific risk
assessment of all relevant pollution linkages and a conceptual site model. Depending on the
results of the investigation, a detailed Remediation Strategy may be required. 
Reason: To establish whether or not site decontamination is required in the interests of the
amenity and wellbeing of future residents. 
6.  That any remediation works identified by the site investigation required in terms of Condition 5
above; shall be carried out to the satisfaction of the Planning Authority.  A certificate (signed
by a chartered Environmental Engineer) shall be submitted to the Planning Authority
confirming that any remediation works have been carried out in accordance with the terms of
the Remediation Strategy.   
Reason: To ensure that the site is free of contamination in the interests of the amenity and
wellbeing of future residents. 
7. That with each forthcoming MSC application for each phase of development, a Ground Gas
Risk Assessment in full accordance with CL:AIRE 2021 guidance shall be submitted for the
written approval of the Planning Authority. 
Reason: To ensure that any potential aspects of ground gas are adequately dealt with in the
interests of public safety and general amenity. 
8. That if remediation works have been identified as being required in terms of Condition 7;
above then a remediation strategy shall be submitted for the written approval of the Planning
Authority and thereafter carried out to the satisfaction of the Planning Authority as part of the
build process.  A certificate (signed by a chartered Environmental Engineer) shall be
submitted to the Planning Authority confirming that any remediation works have been carried
out in accordance with the terms of the Remediation Strategy. 
Page 13 of 88

Page 14

Reason: To ensure that any potential aspects of ground gas are adequately dealt with in the
interests of public safety and general amenity. 
9. That with each forthcoming MSC application for each phase of development and BEFORE
any works of any description being commenced on that phase of development , unless
otherwise agreed in writing with the Planning Authority, full details of the proposed surface
water drainage scheme shall be submitted to the said Authority. This scheme will align with
the drainage strategy approved under the terms of Condition 2 (e) above.  For the avoidance
of doubt the drainage scheme must comply with the principles of Sustainable Urban Drainage
Systems (SUDS) in terms of the relevant CIRIA Manual and other advice published by the
Scottish Environment Protection Agency (SEPA). 
Reason:  To ensure that the drainage scheme complies with best SUDS practice to protect
adjacent watercourses and groundwater, and in the interests of the amenity and wellbeing of
existing and future users adjacent to and within the development site respectively. 
10. That with each forthcoming MSC application for each phase of development and before any
works of any description being commenced on that phase of development, the SUDS
compliant surface water drainage scheme approved in terms of Condition 9 above shall be
implemented contemporaneously with the development in so far as is reasonably practical. 
Following the construction of the SUDS, a certificate (signed by a Chartered Civil Engineer)
shall be submitted to the Planning Authority confirming that the SUDS have been constructed
in accordance with the requirements of condition 9 above. 
Reason: To safeguard any adjacent watercourses and groundwater from pollution and in the
interests of the amenity and wellbeing of existing and future users. 
11. That with each forthcoming MSC application for each phase of development and before any
works start on that phase of development, the applicant must confirm in writing to the
Planning Authority that the foul drainage can be connected to the public sewer in accordance
with the requirements of Scottish Water. For the avoidance of doubt the surface water must
be treated by the SUDS compliant drainage scheme approved in terms of Condition 10
above. 
Reason: To prevent groundwater or surface water contamination in the interests of
environmental and amenity protection. 
12. Notwithstanding the requirements of condition 1 above, an updated protected species survey
shall be carried out for each phase of development and the details of the findings of the
surveys submitted, including any mitigation measures required and timescales for their
implementation shall be submitted for the written approval of the Planning Authority.  For the
avoidance of doubt, any mitigation measures required shall be implemented in accordance
with the approved timescale to the satisfaction of the Council as Planning Authority. 
Reason: In the interests of the protection of natural habitats and protected species. 
13. That unless otherwise agreed in writing, and before the occupation of the 370th
dwellinghouse within the development hereby permitted, all works required for the provision of
the central Multi Use Games/play area approved under the terms of Condition 2 (d) above
shall be completed to the satisfaction of the Planning Authority. 
Reason: To ensure the provision of strategic well designed play facilities within the site. 
14.  That notwithstanding the terms of condition 1 above each application for Approval of Matters
Specified by Condition for housing development shall require to make a financial contribution
towards education provision.  The final figure of the financial contribution shall be agreed with
North Lanarkshire Council Education Services during the assessment of the planning
application. 
Reason:  In order to secure a financial contribution towards addressing the capacity issues in
Page 14 of 88

Page 15

education provision as a result of the proposed development. 
15. That unless otherwise agreed in writing no development shall take place within the
development area until the applicant has secured the implementation of a staged programme
of archaeological work in accordance with a Written Scheme of Investigation which has been
submitted by the applicant, agreed by the Local Archaeology Service and approved by the
Planning Authority.  For guidance, the response should be characterised by the following:- 
1. 5% ground breaking evaluation of that portion of the development area.
2. If this exercise identifies sites or objects of merit there should be proposals for further
works potentially including excavation, post-excavation, publication and archiving. 
Reason: To enable the Planning Authority to consider these aspects in detail. 
Background Papers: 
Consultation Responses: 
NatureScot received 03.06.2024, 17.05.2024, 03.06.2024, 19.12.2024, 03.02.2025, 28.04.2025,
06.05.2025,
Royal Society for the Protection of Birds (RSPB) received 28.06.2024 and 06.05.2025.
Scottish Environment Protection Agency received 11.03.2024, 04.06.2024, 05.07.2024, 09.07.2024,
24.07.2024 and 18.09.2024
Scottish Water received 21.03.2024  
SportScotland received 02.04.2024
Scottish Gas Network received 08.03.2024
Network Rail received 25.03.2024 
Coal Mining Remediation Authority received 10.06.2024 
Strathclyde Partnership for Transport received 25.07.2025
NLC Infrastructure & Transportation received 06.05.2024 and 29.07.2025 
NLC Protective Services received 06.06.2024 
NLC Education received 26.03.2025.
NLC Play Services received 05.06.2025
NLC Housing received 02.09.2024
NLC Archaeology Service received 13.03.2024 
Contact Information: 
Any person wishing to inspect these documents should contact Paul Williams at 01236 632500 
Report Date: 
29th July 2025
Page 15 of 88

Page 16

APPLICATION NO. 24/00230/PPP 
REPORT 
1. Site Description 
1.1 The application site is located on the eastern side of Cumbernauld. It is bound by Lenziemill
Road on its northwestern boundary. The footpath which connects Lenziemill Road (B8054)
and the Luggie Water and the B8039 bounds the site to the west. The eastern boundary of
the site is marked by field boundaries and woodland tree belts up to the northern point of the
site. The Luggie Water and the associated SINC forms the southern boundary of the site
beyond which lies the settlement of Luggiebank. 
1.2 The site is roughly triangular in shape and covers an area of approximately 83 hectares. It
generally slopes upwards from northeast to southwest and also down southwards to the
Luggie Water. The eastern boundary of the site is formed by field boundaries and tree belts
with the northern point of the site converging near the junction of Forest Road and Lenziemill
Road. The site is centrally bisected by Palacerigg Road. 
1.3 The site consists of agricultural fields, some tree belts, smallholdings, an assortment of
dwellings and a golf driving range as well as a ‘foot golf’ course and horse paddocks to the
southeast of the site. Surrounding uses include Cumbernauld model flying club and
Palacerigg Country Park and golf course to the east. Glencryan Forest is to the northeast and
Lenziemill industrial estate to the northwest. There is an existing network of public footpaths
surrounding the site and adjacent to the northeastern flanks of the site. 
2. Proposed Development 
2.1 This application seeks planning permission in principle for the development of 1400 dwellings
and associated access and infrastructure as part of the South Cumbernauld Community
Growth Area (CGA). Its Strategic Development Framework (SDF) was approved by the
Council in June 2016 and the Concept Statement approved in April 2020. The CGA is
identified within the adopted North Lanarkshire Local Development Plan 2022 (LDP). The
CGA also includes the Mid-Forest site to the north of the application site which has Planning
Permission in Principle for approximately 600 dwellings and a detailed Matters Specified in
Conditions (MSC) application for 300 units was approved last year for part of the site
(22/01051/MSC). 
2.2 This application seeks consent for the ‘Proposed residential led mixed use development with
associated access, landscaping, drainage features and all associated infrastructure. The main
element of the proposal is for 1400 residential units of which 20% would be ‘Affordable
Homes’, a new primary access at the northern end of the site onto Lenziemill Road as well as
the retention and enhancement of the existing access onto Lenziemill Road from Palacerigg
Road, the retention and enhancement of the existing footpath network throughout the site and
extending to Glencryan Forest, Palacerigg Country Park and the greater Cumbernauld area in
general. The proposals also include retention and enhancement of existing woodland and a
green buffer zone around the site and proposed development platforms which would take up
approximately half of the overall site. This buffer zone along with internal areas takes up an
area of 44.6 hectares of green infrastructure within the site to accommodate recreation,
informal play and walking routes within the site and a Recreational Management Plan for the
site has been submitted to demonstrate this.  An illustrative masterplan has also been
provided for the residential led development with a Mixed Use Community Hub identified. This
hub would allow for a small parade of shops to come forward to address local needs and align
with placemaking goals for 20 minute neighbourhoods. The illustrative masterplan also
demonstrates enhanced green spaces and children’s play areas as well as Sustainable Urban
Drainage throughout the site. 
2.3 The proposal includes an enhanced footpath network, including Active Travel provision,
upgrading of the existing access from Lenziemill Road onto Palacerigg Road and a new
access to the north of the site onto Lenziemill Road. This new access would facilitate the
Page 16 of 88

Page 17

formation of an internal loop road which would bisect Palacerigg Road at two points and
service identified development platforms which would create smaller residential
neighbourhoods. The centre of the site would include tree retention and enhancement as well
as a central Multi Use Games/play area and Mixed Use Community Hub. An indicative
phasing strategy has been submitted with the north eastern corner of the site being
developed within the first phase, the second phase being the adjoining southern part of the
site adjacent to its eastern boundary, the third phase being the central part of the site fronting
Lenziemill Road, the fourth phase within the south eastern corner of the site and the last
phase within the north western corner of the site bounding Lenziemill Road and the B8039.
Phases 1 to 3 would be north of Palacerigg Road and Phases 4 to 5 south of this road. The
new access onto Lenziemill Road would be formed within Phase 1. 
3. Applicant’s Supporting Information 
3.1 The application submission has provided the following supporting documents: 
Application Forms, Certificates and Notices
Environmental Impact Assessment Report March 2024
Illustrative Masterplan drawing Ind04B
Planning Statement February 2024
Transport Assessment Chapter 9 of the EIA Report
Pre-Application Consultation (PAC) Report
Design and Access Statement March 2024
Tree Report December 2023
Landscape Plan drawing no B2-Acad04
Flood Risk Assessment March 2023
Ecology Survey (Confidential)
Recreational Management Plan 
4. Site History 
4.1 The site forms part of the South Cumbernauld Community Growth Area (CGA) and is
identified within the adopted North Lanarkshire Local Development Plan (LDP) 2022. The
CGA also includes the Mid-Forest site to the north of the application site for approximately
600 dwellings which has Planning Permission in Principle (16/00698/PPP) and an Application
for Approval of Matters Specified in Conditions (MSC) for 300 units was approved in May last
year (22/01051/MSC). Other relevant history is as follows:- 
- 19/00221/EIASCR- EIA Screening Opinion: Residential Development and Associated
Works – EIA required 29.03.19
- 19/01274/PPP Nursery/Garden Centre with Temporary Staff Accommodation –
Withdrawn 9.01.20
- 22/01442/EIASCR Scoping opinion: Proposed residential development with associated
access, open space, landscaping, drainage features and all associated infrastructure –
Issued 11.01.23
- 23/00067/PAN Residential Led, Mixed Use Development with Associated Access, Open
Space, Landscaping, Drainage Features and Associated Infrastructure – Received
18.01.23 
5. Development Plan 
5.1 The Development Plan for the site consists of National Planning Framework 4 (‘NPF4’),
adopted in February 2023; and the North Lanarkshire Local Development Plan (‘LDP’),
adopted in July 2022. 
5.2 The relevant policies in NPF4 are as follows; in summary they advise: 
Policy 1 (Tackling the Climate and Nature Crises) prioritises the climate and nature crises in
all planning decisions and significant weight must be given to this when considering all
proposals.
Page 17 of 88

Page 18

Policy 2 (Climate Mitigation and Adaptation) states that proposals are located and designed
to minimise both lifecycle greenhouse gas emissions and vulnerability to current and future
risks from climate change. 
Policy 3 (Biodiversity) aims to protect and enhance biodiversity and strengthen nature
networks by requiring that all proposals will contribute to the enhancement of biodiversity. The
policy highlights that major developments will only be supported where it can be shown that
proposals will protect and enhance biodiversity and provides criteria for this goal. 
Policy 4 (Natural Places) states that development proposals which have an unacceptable
impact on natural assets will only be supported in limited circumstances. It adds that
proposals which are likely to have an adverse effect on species protected by legislation will
only be supported where the proposal meets the relevant statutory tests. 
Policy 6 (Forestry, woodland and trees) states that developments that enhance, expand and
improve woodland and tree cover will be supported. Any woodland removal is required to be
done in accordance with the Scottish Government policy on woodland removal, and
compensatory planting will most likely be expected to be delivered. 
Policy 12 (Zero waste) states that development proposals that are likely to generate waste
when operational, including residential, will set out how much waste the proposal is expected
to generate and how it will be managed. 
Policy 13 (Sustainable Transport) supports developments which prioritise and encourage
active travel and public transport for everyday travel and which reduce the need to travel
unsustainably. Generally, development proposals will be supported where they provide direct,
segregated and safe links to local facilities; will be accessible to public transport; and are
designed to include safe crossings for pedestrians and cyclists in an environment that
reduces the speed of vehicles. 
Policy 14 (Design, Quality and Place) encourages developments which are well designed
and improve the quality of an area and supports developments which are consistent with the
six qualities of successful places. It also states that proposals which are poorly designed;
inconsistent with the six qualities given; or which are detrimental to the amenity of the
surrounding area, will not be supported. The six qualities of successful places are: Healthy; •
Pleasant; • Connected; • Distinctive; • Sustainable; and • Adaptable. 
Policy 15 (Local Living and 20-Minute Neighbourhoods) sets out the requirements relating to
the concepts of Local Living and 20 Minute Neighbourhoods. Broadly, the policy requires
proposed developments to contribute to ‘local living’ by achieving local access to daily needs
within a reasonable distance from homes, ideally via active travel methods or using
sustainable transport. 
Policy 16 (Quality Homes) is a detailed, multi-layered policy which sets out several
considerations on how residential development proposals should be considered through the
planning process. It aims to encourage and promote the delivery of high quality affordable
and sustainable homes. Criterion a) of Policy 16 states that support will be given for the
development of new homes on land allocated for housing in LDPs. Criterion b) of Policy 16
requires a Statement of Community Benefit for development proposals providing more than
50 homes. This statement will require to set out the contribution of the proposed development
to i) meeting local housing requirements including affordable housing; ii) providing or
enhancing local infrastructure facilities and services; and iii) improving the residential amenity
of the surrounding area. Criterion c) of Policy 16 states that support will be given for the
development of “new homes that improve affordability and choice by being adaptable to
changing and diverse needs” and gives examples of housing types which might be included
under this policy, such as accessible, adaptable and wheelchair accessible homes and
homes which provide a range of house sizes. Criterion e) adds that support will be given for
development proposals for housing which include 25% affordable housing provision, unless a
different requirement is set out in the LDP. 
Page 18 of 88

Page 19

Policy 18 (Infrastructure First) supports proposals which address any impact on infrastructure
and offers guidance on the mechanisms for infrastructure provision such as planning
conditions or obligations. The policy notes that support will be given to proposals which
provide (or contribute to) infrastructure in line with that identified as necessary in LDPs and
their delivery programmes. 
Policy 19 (Heating and Cooling) states that development proposals for buildings that will be
occupied by people will be supported where they are designed to promote sustainable
temperature managements, for example by prioritising natural or passive solutions, such as
siting, orientation, and materials. 
Policy 20 (Blue and Green Infrastructure) supports proposals that would not result in, or
exacerbate, a deficit in green infrastructure provision, and the overall integrity of the network
will be maintained. Furthermore, the policy also notes that proposals will be supported for
incorporating new or enhanced blue and/or green infrastructure. 
Policy 21 (Play, Recreation and Sport) supports proposals likely to be occupied or used by
children and young people where they incorporate well designed, good quality provision for
play, recreation, and relaxation that is proportionate to the scale and nature of the
development and existing provision in the area. The policy also states that development
proposals that include new streets and public realm should be inclusive and enable children
and young people to play and move around safely and independently, maximising
opportunities for informal and incidental play in the neighbourhood. 
Policy 22 (Flood Risk and Water Management) aims to strengthen flood resilience by
avoiding development in areas of flood risk where possible and reducing vulnerability of
developments to flooding. It provides criteria which must be met if a proposal in a flood risk
area is to be supported and requires that proposals do not increase the risk of surface water
flooding and manage surface water drainage though SUDS. 
Policy 23 (Health and Safety) supports proposals that will have a positive effect on health
and development proposals that are likely to raise unacceptable adverse effects such as
through noise, air quality or hazards should not be supported. 
Policy 24 (Digital Infrastructure) supports proposals that incorporate appropriate, universal,
and future proofed digital infrastructure connectivity. 
5.3 The site is an identified and allocated housing site within the North Lanarkshire Local
Development Plan (LDP). Relevant policies within the LDP are as follows: 
PROM LOC3 (Housing Development Sites) states that NLC will provide a generous supply of
land to maintain a minimum five-year effective housing supply at all times. Those sites
promoted in the Plan will be brought forward through consideration of applications for
planning permission and/or in accordance with the Action Programme. This has now been
replaced and superseded by NPF4 Policy 16 Quality Homes. 
PROM LOC4 (Special Landscape Areas & Green Network Improvements) states that green
networks are a means of attracting people into their local natural environment by improving
community access, recreation opportunities, and environmental and ecological quality close
to and within communities. 
PROM ID1 (Transport Improvements) states that NLC will support sustainable, multi-modal
transport improvements, identified and delivered through various strategies including the
National Transport Strategy, Cycling Action Plan for Scotland, North Lanarkshire
Transportation Strategy and North Lanarkshire Walking and Cycling Strategy. 
Policy PROT A (Natural Environment and Green Network Assets) is a multi-layered policy
that considers the protection of natural and resilient sustainable places by safeguarding
natural heritage assets, categorising sites into International, National and Local designations.
The Following categories are of relevance to the site:
Page 19 of 88

Page 20

Category A3 (Local Sites) acknowledges local sites including Sites of Importance for Nature
Conservation, Country Parks, Tree Preservation Orders and Core Paths. 
Category A5 (Protected Species) notes that development that significantly affects a species
protected by law will only be permitted where an appraisal has demonstrated that the
protected species would not be compromised, or any significant adverse effects on the
protected species are mitigated through planning conditions or use of planning agreements
to: facilitate protection of individual species members, reduce disturbance to a minimum and
provide appropriate alternative habitats to sustain at least the current levels of the species
locally. 
Policy CI (Contributions to Infrastructure) requires that the Council will seek to secure
developer contributions for new developments that cumulatively generate a requirement for
new or enhanced infrastructure or services, covering Affordable Housing in Cumbernauld
Housing Sub-Market Area, Education, Transport and Green Network Infrastructure, Amenity
Space and Play across North Lanarkshire.  
Policy PP 3 (Purpose of Place) states that the Council will seek to maintain and improve the
level of amenity in urban areas, by encouraging development that is in keeping with their
residential character and encouraging diversity in more mixed-use areas. 
Policy AD3 (Amount of Development) assesses the implications of the amount of
development proposed. 
Policy EDQ 1 (Site Appraisal) notes that any proposed development will require to be
appraised in terms of the site and its surroundings to ensure it will integrate successfully into
the local area and avoid harm to neighbouring amenity. 
Policy EDQ 2 (Specific Features for Consideration) Category 2C states that development
proposals should detail how any likely air quality, noise, or pollution impacts particularly in or
adjacent to Air Quality or Noise Management Areas will be mitigated. 
Policy EDQ 3 (Quality of Development) states that development will only be permitted where
high standards of site planning and sustainable design are achieved. 
6. Consultations 
6.1  Scottish Environment Protection Agency (SEPA) originally objected to the proposal in
terms of potential flood risk. Amendments were therefore made to the existing Flood Risk
Assessment (FRA) to include bespoke hydrological and hydraulic modelling in order to
evidence that all elements of the proposed residential areas are outwith the flood risk area
(200yr + Climate Change Allowance) from likely fluvial features throughout the site. From the
Technical Note provided by Stantec, SEPA are satisfied that this provides sufficient evidence
that the residential elements are not at flood risk and that modelling is no longer required.
SEPA therefore removed their objection. 
6.2 NatureScot have advised that the proposal could affect internationally important natural
heritage interests but could be progressed with appropriate mitigation. They have therefore
advised that they would not object to the application so long as it is made subject to
conditions so that the development is carried out strictly in accordance with the mitigation
detailed below: 
6.3 That the design solutions presented in the Palacerigg, Cumbernauld Recreational
Management Plan (Stantec, Rev. D, Feb 2025) are implemented in full. This must include the
measures shown on Drawing No. B2-Acad05 (Revision A) and described in Section 5 of the
Plan, which take in the following: 
- provision within the Site of 44.6ha (approx.) of high-quality greenspace, including over
5.6km of signed and waymarked walking routes and the upgrading of 1.49km of core
Page 20 of 88

Page 21

paths; 
- Gateway features and signage at the entrance points into Palacerigg Country Park which
promote the use of established paths, and discourage use of Slamannan Plateau and
West Fannyside Moss beyond. 
- Use of planting to direct movement and discourage informal access. 
6.4 In addition to these comments NatureScot advised that given the environmental status of the
Slamannan Plateau Special Protection Area (SPA), protected for its population of wintering
taiga bean geese and West Fannyside Moss Special Area of Conservation (SAC), protected
for its blanket bog, the requirements of the Conservation (Natural Habitats, &c.) Regulations
1994 as amended (the ‘Habitats Regulations’) apply or, for reserved matters, The
Conservation of Habitats and Species Regulations 2017 and the Council was required to
consider the effect of the proposal on the qualifying interest of the SPA and SAC. 
6.5 The Council as the competent authority, has therefore carried out an appropriate
assessment to assess this effect. This was produced by Applied Ecology dated March 2025.
Under the terms of the regulations. A shadow Habitats Regulations Appraisal (HRA) was
produced first drawing on the information available regarding the SPA and SAC, knowledge of
the usage of the area, the relevant ecological features and the potential impacts of the
proposed development on these features. A final HRA was then adopted by the Council.
NatureScot has confirmed that they concur with the findings of the HRA which advises that
subject to the proposed mitigation measures detailed above it is considered that the proposal
would have no adverse effects on the integrity of the Slamannan Plateau SPA or West
Fannyside Moss SAC. Appropriate conditions have therefore been attached to meet these
requirements. 
6.6     Royal Society for the Protection of Birds (RSPB) originally objected to the proposal due to     
the lack of assessment of the impact of increased recreational disturbance on the Taiga Bean
Geese and supporting habitats of the Slamannan Plateau SPA/SSSI and West Fannyside
SAC/SSSI given there was no Recreational Management Plan to show how the potential
increased recreational disturbance will be mitigated to avoid disturbance of the wintering
Taiga Bean Geese, or negative impacts on the integrity of the supporting habitats of the
Slamannan Plateau SPA/SSSI and West Fannyside SAC/SSSI. The RSPB stated that they
would reconsider their position following the provision of the required assessment and
mitigations. Following the provision of the updated Recreational Management Plan (RMP) the
RSPB confirmed the withdrawal of their objection subject to conditions that the Council carry
out a Habitats Regulations Appraisal. This has been done and an appropriate assessment
has been carried out. This has found that impacts on these conservation assets can be
satisfactorily managed by the proposed mitigation measures detailed in the RMP. NatureScot
has confirmed agreement with the findings of the appropriate assessment and the RSPB
confirmed removal of their objection subject to condition that the design solutions presented in
the Palacerigg, Cumbernauld Recreational Management Plan (Stantec, Rev. D, Feb 2025)
are implemented in full and that this include the measures shown on Drawing No B2-Acad05
(Revision A) and in Section 5 of the plan. Appropriate conditions have therefore been
attached to meet these requirements. 
6.7    Scottish Water has confirmed that there is currently sufficient capacity in the Balmore Water 
Treatment Works to service the development. Scottish Water cannot confirm that the 
Dunnswood Waste Water Treatment works has current capacity but suggests that the 
applicant completes a  Pre-Development Enquiry (PDE) form and submits it directly to 
Scottish Water via their customer Portal or contact Development Operations. They also 
advise that they will not accept any surface water connections into the combined sewer 
system. 
6.8    Sportscotland originally made comments regarding the proposed development and the 
inherent loss of the existing Foot Golf Course on the site and how this should be assessed 
against Policy 21 of NPF4 in terms of demonstrating adequate sports facility provision in the 
local area and that this should be informed by the Council’s Open Space Strategy.
Page 21 of 88

Page 22

Sportscotland consulted Golf Scotland and a further response was received from 
Sportscotland withdrawing their objection on the basis that Golf Scotland had provided no 
objection to the proposal in terms of capacity elsewhere in the area.  Palacerigg Golf Course 
is nearby and could be utilised and given the nature of the current use of the site and nearby 
golf course it is considered that the demand for golf in the area could be met. Therefore, the 
proposal would satisfy criterion 4 of NPF4 Policy 21 and Sportscotland confirmed no objection
to the proposal. 
6.9    Scottish Gas Networks has confirmed that the development will not affect the High Pressure 
Pipeline near the planned area of works. 
6.10 Network Rail has confirmed that they consider that the proposal will have no impact on 
railway infrastructure and therefore tthey have no objections to the proposal. 
6.11 Coal Mining Remediation Authority has confirmed that as the site falls within a low risk 
area that they have no specific comments to make. 
6.12 Scottish Wildlife Trust were consulted on two separate occasions with no response 
forthcoming. 
6.13 NLC Infrastructure and Transportation have provided detailed feedback in terms of the 
requirements for junction improvements, visibility splays, traffic control, road/street hierarchy, 
traffic signals, active travel provision, footpath design, parking provision and advised that the 
development be designed in accordance with principles of ‘Designing Streets. Appropriate 
conditions have been attached to meet their requirements. 
6.14 NLC Greenspace– no comments made. 
6.15 NLC Protective Services have provided comment on the Preliminary Risk Assessment of 
ground conditions (Contamination and Stability), Stantec, October 2023 and the Preliminary 
Mining Hazard Assessment, Stantec, December 2023. Other additional information has been 
requested in terms a mine gas risk assessment in full accordance with CL:AIRE 2021 
guidance. This can be conditioned along with other standard site investigation and 
remediation conditions. 
6.16 NLC Education advised that the proposed development lies within the catchment areas of 
Woodlands Primary school and St Margaret of Scotland Primary school in Cumbernauld. 
Pupils from these developments ordinarily transfer to Greenfaulds High and Our Lady’s High 
school for secondary provision. A development of this scale cannot be accommodated within 
the school estate without the requirement for additional capacity in the local educational 
establishments. 
6.17 The Service therefore requests a Developer Contribution of £5,631,949.25. This contribution 
is towards additional provision in the early years, primary and secondary sectors. The 
calculation is based on the development comprising 1500 units and is proportionate to the 
impact of the development on the school estate. If the number of units within this 
development were to increase or the development is not completed within a five-year period, 
the Service reserves the right to revisit the issue of developer contributions at that time. 
6.18 This contribution can be achieved through conditions and related legal agreements in each 
MSC phase and determined by the number of residential units in each phase. The 
contributions for phases that relate to council owned land can be achieved as part of the 
capital receipt for the sale of the land where funds are deducted from the Capital receipt and 
internally transferred to NLC Education. It should be noted that through the course of the 
assessment of the application the maximum number of units considered acceptable for the 
development of the site is 1400. Therefore, the developer contribution required would be 
reduced accordingly. 
6.19 NLC Community Partnership Team (Play Services) has offered detailed advice in terms of 
what is required for a proposed development of this scale. Within the various phases of the
Page 22 of 88

Page 23

development multiple play areas should be included throughout the development. They 
advise this could be made up from 6 X LEAP’s (Local Equipped Area of Play), 9 x NEAP’s 
(Neighbourhood Equipped Play Area) and 3 x MUGA’s (Multi Use Games Area) and that the 
proposed centrally located play area identified within the masterplan could form part of this 
provision. The provision of play can be controlled by planning condition. 
6.20 NLC New Supply has advised that 20% affordable housing provision should be provided 
across the site. As this application seeks planning permission in principle this matter can be 
controlled by planning condition at this time. 
6.21 NLC Archaeology Service has no objection to the proposal so long as a condition is 
imposed to ensure that a Written Scheme of Investigation is carried out by the developer. This 
requirement has been attached as a condition. 
6.22 Strathclyde Partnership for Transport have no objections provided that suitable provision 
for public transport is made available within the overall site and recommend that developer 
contributions are secured via a Section 75 agreement. Appropriate conditions are imposed to 
control this matter. 
6.23 No response was received from SPEN or SUSTRANS. 
7. Representations 
7.1 Following the standard neighbour notification process and newspaper advertisement including
an advert in the Edinburgh Gazette as the application includes an Environmental Impact
Assessment, 72 letters of representation (71 objecting and one in support) have been
received including one from Carbrain and Hillcrest Community Council (objecting on grounds
of environmental damage and potential impact on society, local services and infrastructure)
as well as submissions from POPPA (People Opposing Palacerigg Planning Application). 
7.2    The following is a summary of the objections to the proposal: 
a) Loss of ‘Greenbelt’ Land / Greenspace 
‘The proposed development is on rural greenbelt land and is not allocated for development as
per NLCs own local development plan. A use of this greenbelt space in this way would be
non-compliant with NLCs own LDP. Not only this, but as residents of Cumbernauld, our
greenbelt spaces should be protected at all costs.’ ‘The facilities of Cumbernauld cannot
support a development of this size and the loss of natural green space is totally unnecessary.
Palacerigg is meant to be a country park not a town park and building on this scale near it
would ruin the nature of the surroundings.’ 
b) Traffic, Access and Road Safety Concerns 
‘Palacerigg Road and the surrounding area, do not realistically support a settlement of this
size with the traffic this will bring. Palacerigg Road can be dangerous owing to bends, tight
width of the road and also the fact it is frequently used by equestrians and cyclists, whose
safety should be paramount and will be endangered by an increase in volume of traffic.’
‘Palacerigg Road is a narrow, winding road down which people already speed at the moment
though traffic is not dense. However, since most households now have at least one car
according to Statistical Research data this will mean an extra 1000-2000 cars in the area.
There is no provision I see in the proposal for widening this road. Nor do the other access
roads appear any wider. This is a serious road safety issue.’ 
c)  Noise Impact and Privacy Concerns 
‘Noise and light pollution will have a direct effect on wildlife and ecosytems. Our cottage is
currently sited with a beautiful green panoramic view which will be blighted by noise and light
should this go ahead.’ ‘We live in a bungalow and although no fine detail has been received of
Page 23 of 88

Page 24

the proposed housing we will be overlooked if any house around us is more than one storey
high. From having no neighbours for 24 years and then having thousands will create a
massive disturbance.’ 
d)  Pressure on Existing Infrastructure and Services 
‘I have to support the comments on lack of infrastructure in the town to support a site of 12-
1500 homes. The local primary schools are under pressure, there are huge problems
accessing local GPs and the site will offer no amenities of any consequence in a town in
decline due to lack of investment for whatever reason.’ ‘To ensure the health of
Cumbernauld's' population, we require the infrastructure and amenities in place within our
communities. Dr Surgeries are full. Hospital is due to be moved further away. No dentists
nearby. Schools, where are the children, meant to be educated? If there are 1000 children
within this estate, are there plans for new Primary Education sites? 1000 children will not be
absorbed into the existing facilities.’ ‘The addition of further housing developments in the town
would place further pressure on already struggling services, such as schools, doctors,
nurseries and dentists. More pressure on such services could impact negatively on people's
health, wellbeing and education.’ 
e) Impact on Natural Environment and Biodiversity 
‘Consideration should be given to any opportunities to contribute towards restoring and
enhancing any habitats and species identified as national, strategic or local priorities…’ ‘Loss
of habitat for thousands of animals causing displacement, harm and distress to wildlife,
especially those who are already under threat.’ ‘The green space which will be obliterated by
the development is a part of the natural environment which can be accessed on foot from
central Cumbernauld. Having enjoyed many peaceful walks during which I have inevitably
spotted a variety of wildlife, I am angry to learn that habitats will be destroyed, leading to
further decline in already dwindling bird, mammal and insect populations.’ 
f) Drainage Concerns 
‘When a single house attached to the nearby stables was built it altered a water course
causing one of these roads to be constantly waterlogged leading to surface breaking up. More
houses would exacerbate the problem.’ ‘The land around this area over the years has had
severe drainage problems.’ 
g)  Engagement with the Local Community 
‘People are not empowered to shape their place if they do not have access to the knowledge
that a planning application has been submitted or that there is a Local Development Plan in
place… We respectfully suggest that due to the nature of the application, a further
consultation of the community is undertaken by North Lanarkshire Council prior to the
application being submitted.' 
7.3    These concerns will be considered later in the report. 
7.4    The letter of support raised a number of issues to be considered as part of the assessment 
of the application. In summary these related to safe pedestrian links, including through the 
industrial area to the train station and town centre, traffic control, active travel, safe routes to 
school, appropriate phasing of the development, placemaking and the provision of a range of 
house types. 
Response: Noted. Appropriate conditions are attached to ensure these matters are
addressed through the submission of forthcoming MSC applications. 
8.        Planning Assessment 
8.1 Section 25 of the Town and Country Planning (Scotland) Act 1997, states that planning
Page 24 of 88

Page 25

applications are to be determined in accordance with the Development Plan unless other
material considerations indicate otherwise. Upon its adoption on the 13th of February 2023,
National Planning Framework 4 (NPF4) became part of the statutory ‘Development Plan’. It
supersedes both Scottish Planning Policy (2014) and the Clydeplan Strategic Development
Plan (2017). As a result, the Development Plan in respect of this site now comprises NPF4
(2023) and The North Lanarkshire Local Development Plan (adopted 2022). On 8th February
2023, the Chief Planner for Scotland published Transitionary Arrangements Guidance which
set out further details regarding how NPF4 should be applied. This confirmed that adopted
Local Development Plans will continue to be part of the development plan. In circumstances
such as North Lanarkshire’s, where the Local Development Plan (LDP) has been adopted
prior to publication of NPF4, legislation states that in the event of any incompatibility between
a provision of NPF4 and a provision of an LDP, whichever of them is the later in date is to
prevail. Accordingly, the proposed development requires to be assessed against the
provisions and policies of both NPF4 and the North Lanarkshire Local Development Plan.   
Principle of Development 
8.2 The site is identified as an allocated Housing Development site. The North Lanarkshire Local
Development Plan (LDP) originally designated the site under Policy PROM LOC3. This policy
has been superseded by NPF4 Policy 16 (Quality Homes). Policy 16 supports developments
for new homes on land allocated for housing in the LDP. As such this allocated site meets the
terms of this policy in contributing to the Council's stated ambition in reaching its target for
housing within the area. It will not have a significantly detrimental impact on the area and is
compliant with the general principles of this policy. As such, the site is promoted in the Plan to
be brought forward through consideration of applications for planning permission and/or in
accordance with the Action Programme. The principle of residential development is therefore
established for this site. However, the application requires to be assessed against the other
relevant policies in NPF4 and the LDP. These assessments can be made under the following
subject headings. 
Ecology/Biodiversity
8.3 In terms of ecology and biodiversity, the applicant has demonstrated that the proposed
development can be carried out without unacceptably impacting on environmentally sensitive
sites and protected species. In this case, the relevant sites are the Luggieburn SINC (Site of
Importance to Nature Conservation), Palacerigg Country Park, the Slamannan Plateau Special
Protection Area (SPA), the West Fannyside Moss Special Area of Conservation (SAC) and the
North Bellstane Plantation Site of Special Scientific Interest (SSSI). Upon the advice of
NatureScot a Recreational Management Plan was produced which assessed the potential
impact of human activity within the existing and proposed footpath network on these
designated protected areas. Following the provision of an updated Recreational Management
Plan, NatureScot and the RSPB confirmed the withdrawal of their objections subject to
conditions that the Council carry out a Habitats Regulations Appraisal and the Council as the
competent authority carry out an Appropriate Assessment. The Appropriate Assessment has
been carried out by the Council which found that impacts on the conservation assets detailed
above can be satisfactorily managed by the identified mitigation measures. NatureScot has
also confirmed agreement with the findings of the Appropriate Assessment and the RSPB
confirmed the removal of their objection on the condition that the design solutions presented in
the updated Recreational Management Plan are implemented. Appropriate planning conditions
are attached to control this. 
8.4 It is noted that the proposed development platforms as shown on the illustrative masterplan
are located in the least sensitive parts of the site, these being open fields with existing
woodland to be retained. In terms of the relevant NPF4 policies, Policy 1 - Tackling the Climate
and Nature Crises states that when assessing development proposals, significant weight will
be given to tacking these crises and Policy 2 - Climate Mitigation and Adaptation seeks to
minimise greenhouse gas emissions, energy efficiency and renewable energy.  The
application site is an allocated housing site within the LDP. It is therefore considered to be a
sustainable site that can deliver energy efficient homes and as such can be seen to be
compatible in principle with the requirements of Policies 1 and 2 of NPF4. NPF4 Policy 3 –
Biodiversity indicates that proposals should contribute to the enhancement of biodiversity and
should only be supported where it can be demonstrated that the proposal will conserve,
Page 25 of 88

Page 26

restore and enhance biodiversity and it is noted that the application includes proposals for
landscaping and biodiversity enhancements. NPF4 Policy 4 – Natural Places seeks to ensure
natural places are protected and restored and that natural assets are managed in a
sustainable way. Conditions are proposed which will safeguard and protect the above
mentioned, designated areas as well as landscape enhancements being provided throughout
the site. NPF4 Policy 6 - Forestry, Woodland and Trees seeks to protect and enhance existing
woodland areas. In this case, existing trees within the site are to be retained. It is therefore
considered that the proposal accords with the above NPF4 policies. In terms of the LDP
policies, PROT A (Natural Environment and Green Network Assets) Category A3 (Local sites
and parks) and Category A5 (Protected Species), it is considered that the proposal complies
with these policies for the same reasons. 
Access and Connectivity
8.5 In terms of access and connectivity, the applicant has provided a Design and Access
Statement, also Chapter 9 of the EIA covers Transport and Access and the Recreational
Management Plan is also of relevance. The proposal involves the upgrading of the existing
access from Lenziemill Road onto Palacerigg Road as well as the formation of a new access
to the north and the overall design ethos of the proposal is to preserve and enhance the
existing footpath network. There are also two existing bus stops nearby and Cumbernauld
railway station lies to the west of the site. Furthermore, the proposed central loop road has
scope for bus stops to be located along its path and there will be suitably wide footways for
cyclists and pedestrians to share.  Any development brought forward will be required to
address Active Travel requirements.  The above supporting documents conclude that
sustainable transport solutions can be arrived at through the process of the subsequent MSC
applications and the overall masterplan layout has been designed with local living and 20
minute neighbourhoods in mind. 
8.6 The relevant policies within NPF4 are Policy 13 (Sustainable Transport) and Policy 15 (Local
Living and 20 minute Neighbourhoods. In terms of the LDP, the relevant policies are PROM
LOC4 (Green Network Improvements) and PROM ID1 (Transport Improvements). It is
considered for the reasons stated above that the proposal as described at this PPP stage and
through the subsequent submission of MSC applications can accord with these policies.   
Infrastructure
8.7 The key elements of infrastructure provision for the development are as follows: 
• New and upgraded access points into the site including a central access loop road -
this can be achieved through the process of each subsequent MSC application and
by condition as part of this PPP application.
• A retained and enhanced green woodland and hedgerows to contribute to the
landscape and an enhanced green footpath network within the site - this can be
achieved through the process of each subsequent MSC application and by condition
as part of this PPP application.
• Proportionate play provision throughout the site - this can be achieved through the
process of each subsequent MSC application and by condition as part of this PPP
application.
• A centrally located mixed use Community Hub - this can be achieved through the
process of each subsequent MSC application and by condition as part of this PPP
application.
• Affordable Housing provision – this can be achieved through the process of each
subsequent MSC application and by condition as part of this PPP application.
• Education Contributions – again this can be achieved through the process of each
subsequent MSC application and by condition as part of this PPP application as well
as applying Section 75 legal agreements with the appropriate MSC applications.
Where future phases or MSC applications are on Council owned land, the
contributions can be obtained by the internal transfer of funds.
• Blue and Green infrastructure – as shown on the parameter plan and landscape plan
contained within the Recreational Management Plan (RMP), there will be
approximately 44.6 Hectares of open space within the site including SuDS and
retained woodland planting. The RMP states that there is scope for a central play
Page 26 of 88

Page 27

space, a linear play route/wildlife corridor, community orchard, wildlife planting, cycle
and pedestrian paths and SuDS ponds. This can be achieved through the process of
each subsequent MSC application and by condition as part of this PPP application. 
8.8 The relevant policies within NPF4 are Policy 18 (Infrastructure first), Policy 20 (Blue and
Green Infrastructure), Policy 21 (Play, Recreation and Sport) and Policy 22 (Flood Risk and
Water Management). Within the LDP, the relevant policies are PROM ID1 (Transport
Improvements) and Policy CI (Contributions and infrastructure) which includes Affordable
Housing, Education contributions, transport improvements and green network solutions. It is
considered that for the reasons outlined in paragraph 8.7 that the proposal, in the context of
the PPP and subsequent MSC submission process complies with these policies. 
Landscape and visual impact
8.9 As previously outlined, design solutions within the RMP have been prescribed to mitigate
against landscape and visual impact and fundamentally, the proposed developable area of
the site is less than half of the overall site area (Site area 83 Hectares approximately and the
proposed developable area being 38.4 Hectares). The design solutions contained within the
RMP include: 
• New habitat and amenity landscape to be created;
• Existing vegetation to be retained and enhanced for habitat and recreation value;
• Landscape within the SINC to be enhanced for habitat value;
• Trees along the development to soften views;
• Proposed hedgerow with hedgerow trees to contain and filter views of the proposed
development;
• Proposed woodland planting to reinforce the existing woodland and soften views;
• Existing woodland to be retained. 
Furthermore, the submitted Environmental Impact Assessment included a section on
landscape and visual impact (LIVIA) which concluded that with the application of the
prescribed landscape enhancement measures and mitigation solutions that the visual impact
of the development will be within acceptable parameters. 
8.10 Within NPF4, Policy 6 (Forestry, Woodland and Trees) and Policy 14 (Design, Quality and
Place) are of relevance and in terms of the LDP, Policy PROT A (Natural Environment and
Green Networks Assets) are of relevance. For the reasons outlined above, it is considered
that the proposal complies with these policies. 
Design Quality
8.11 As part of the overall submission of this planning application, the following reports were
submitted: 
• Planning Statement
•  Design and Access Statement,
•  Illustrative Masterplan,
•  Recreational Management Plan Design mitigations 
These studies demonstrated that the proposed development would be sensitively developed
in terms of development platforms, residual open space with retained and enhanced
woodland and path network as well as the provision of key elements such as the centrally
located play space and mixed use community hub. Furthermore, that the subsequent phases
of development and the internal road layout would be designed in accordance with the
principles of ‘Designing Streets’ as published by the Scottish Government. 
8.12 The relevant NPF4 policies related to design quality are: 
Policy 1 (Tackling climate and nature crises)
Policy 2 (Climate mitigation)
Policy 12 (Zero Waste)
Policy 14 (Design Quality and Place)
Page 27 of 88

Page 28

Policy 15 (Local Living and 20 minute Neighbourhoods)
Policy 16 (Quality Homes)
Policy 19 (Heating and Cooling)
Policy 24 (Digital Infrastructure) 
and for the LDP they are: 
Policy PP3 (Purpose of Place)
Policy AD3 (Amount of Development)
Policy EDQ 1 (Site Appraisal) 
Policy EDQ 2 (Specific Features for Consideration – Category 2C) 
Policy EDQ 3 (Quality of Development) 
8.13 It is considered that the proposal complies in principle with these policies. These policies
however would require further consideration at the detailed design stage when subsequent
MSC applications are submitted for consideration. Appropriate conditions are attached to
control these matters. 
Flood Risk
8.14 Policy 22 of NPF4 (Flood Risk and Water Management) is the relevant policy in this case. As
described in section 6 above, SEPA are now satisfied that the site is not at flood risk subject
to the implementation of an appropriate Sustainable Urban Drainage scheme throughout the
site. It is therefore considered that the proposal through the PPP and subsequent MSC
applications will be able to satisfy the terms of Policy 22 and appropriate conditions are
attached to control this matter. 
8.15 In terms of the points of objection raised through letters of representations these are reviewed
as follows :- 
a) Loss of ‘Greenbelt’ Land / Greenspace 
Response: In the adopted North Lanarkshire Local Development Plan (‘LDP’) 2022, the
Palacerigg Village Site is allocated as part of the wider South Cumbernauld Community
Growth Area (‘CGA’). Therefore, the site is not designated as ‘greenbelt land’ and is instead
allocated for development. Therefore, the overall principle of development on this site is
considered to be accepted within the development plan. The housing identified as part of this
wider allocation has been included within the housing delivery figures for North Lanarkshire
Council and is therefore considered as 'necessary’ to help meet the local housing land
requirement for the local area. The submitted masterplan demonstrates that c.44.6ha of
woodland and open space will be retained and green space will be enhanced throughout the
site to protect biodiversity habitats and special designated environmental assets.
Furthermore, the proposed open space network will also enhance green space on site,
connecting Cumbernauld to Palacerigg Country Park. Chapter 13 of the submitted EIA Report
considers in detail the potential impact of the proposed development on the biodiversity of this
area and sets out a series of mitigation measures that can be employed on site and off site to
mitigate the impact of development, whilst also providing biodiversity enhancement.
Appropriate conditions are attached to control these matters. 
b) Traffic, Access and Road Safety Concerns 
Response: The submitted Transport Assessment and Chapter 9 of the EIA Report considers
the existing road network, identifying the existing flow of traffic and where there may be any
adverse impacts as a result of the proposed development. This Assessment identifies any
necessary mitigation to ensure that the impact is neutralised, whilst delivering an allocated
housing development and limits the number of dwellings to 1400. The proposed development
will introduce a new primary junction located at the northern end of the site off Lenziemill
Road. Traffic controls will be required to accommodate the proposed development, both on
Lenziemill Road and on Palacerigg Road, which will manage traffic flow accordingly. The
proposed development will promote a varied active travel network on site and in the
surrounding area through the retention of existing footways and the creation of new
Page 28 of 88

Page 29

pedestrian and cycle network routes. This has been identified in the submitted Design and
Access Statement. 
c)  Noise Impact and Privacy Concerns 
Response: Chapter 11 Noise and Vibration of the submitted EIAR notes that construction,
road and operational noise all demonstrate minor adverse impact on the area. However,
mitigation measures will be in place to reduce the impact of noise from the development on
existing and future receptors. The detailed development area and block layout, in addition to
the mix of heights and densities similar to the local area will ensure that the privacy of
residential areas in the surrounding area will be respected through the detailed layout
proposals. Detailed layouts, which would come forward as part of any AMSC application
would require to comply with detailed policies and guidance on housing layout. Appropriate
conditions are attached to control these matters. 
d)  Pressure on Existing Infrastructure and Services 
Response: Chapter 6 ‘Socio Economics’ of the EIAR notes that the increase in population
will impact upon the availability of education and healthcare within the local area surrounding
the Site. It is recognised that current educational capacity is not sufficient to accommodate
the demand for places created by the proposed development. In terms of healthcare, the
proposed development is not expected to have a significant adverse effect. Education
contributions will be sought from developers to mitigate the impact of the proposed
development. In terms of supporting local infrastructure, the proposed mixed use community
hub has the potential to include a doctor’s surgery, if required and will provide some
employment on-site for uses that come forward, providing positive benefits to the local
economy and employment for local residents. In addition to the increase in local expenditure,
Council Tax income will also increase as the development progresses. Over the construction
period, an average of 147 direct FTE jobs per month will be created, of which 109 will provide
employment for residents of North Lanarkshire. Furthermore, the delivery of new areas for
formal and informal open/play space and local road, active travel and path networks will
support the health and wellbeing of the local population, and the proposed mixed use
community hub will offer the opportunity to serve local needs. 
e)  Impact on Natural Environment and Biodiversity 
Response: Chapter 13 of the submitted EIA Report considers in detail the potential impact of
the proposed development on the biodiversity of this area and sets out a series of mitigation
measures that can be employed on site and off site to mitigate the impact of development,
whilst also providing biodiversity enhancement. Whilst the proposed development may lead to
moderate impacts on the existing natural environment, the design aims to enhance
biodiversity offerings across the site, and within the local area. The proposed development
includes a mixture of retained woodland and areas of managed green open space, with
development parcels sensitively integrated into a natural setting. In terms of the SINCs that
affect the site, the Biodiversity Chapter of the EIAR states that ‘with respect to the Glencryan
Woods SINC, Glencryan Meadow SINC and the Luggie Water SINC and Luggiebank Wood
SWT Reserve, no direct loss of habitats are predicted’. The proposed open space network will
ensure the wide retention of the woodland and hedgerows and enhance the habitat
opportunities with bird boxes and bug hotels throughout. The proposed development will also
have an appropriate offset to the woodland, watercourse and SINCs, introducing recreational
active travel routes which run through the development and connect Cumbernauld to
Palacerigg Country Park. Areas for play will be provided within a rich landscape design and
dwellings will overlook to encourage natural surveillance. Furthermore, new SuDS features
will be incorporated which offer biodiversity opportunities. Across the development, there will
be an enhancement of existing notable landscape features, providing well considered new
tree planting as much as possible. Appropriate conditions are attached to control these
matters. 
Page 29 of 88

Page 30

f)  Drainage Concerns 
Response: The submitted Drainage Strategy outlines the various mitigation measures to
minimise the likely significant effects on the water environment. These include SuDS basins,
located along the southern and western boundary, at low points. There is also a SuDS pond
towards the eastern, higher part of the site. Along with other surface water drainage
measures, this will ensure sufficient treatment of surface water is achieved within the site.
Appropriate conditions are attached to control these matters. 
g)  Engagement with the Local Community 
Response: A full consultation process has taken place for this application, in accordance with
the Planning etc. (Scotland) Act 2006, the Town & Country Planning (Development
Management Procedures) (Scotland) Regulations 2013 as presented within the PAC Report.
During the consultation stage of the development proposal, the Applicant gained valuable
insight from the local community in relation to the proposed development. Concerns raised
were considered/addressed and led to changes in the final masterplan and development
proposal. During this time, the Applicant had shown willingness and commitment to engaging
with the local community, including local elected members, 3 Community Councils and
various Stakeholder Groups. 
9. Conclusions 
9.1 The proposed development is considered acceptable and in accordance with the South
Cumbernauld Community Growth Area (CGA) approved by the Council and the Concept
Statement and associated Strategic Development Framework (SDF). It is considered that the
proposal also complies with the relevant NPF4 and LDP policies. Due consideration has been
given to the representations of objection, however, for the reasons given above it is
considered that none raised merit the refusal of this application.  It is therefore recommended
that planning permission in principle be granted subject to the conditions set out above. 
9.2 Due to the complexities of the site it is considered necessary to grant permission with an
implementation condition of 10 years instead of the standard 5-year timescale for applications
of this type (planning permission in principle) in order to allow sufficient time for the additional
matters specified in conditions applications to be brought forward. 
Page 30 of 88

Page 31

Application No:  
24/00965/FUL
Proposed Development: 
Erection of a Dwelling 
Site Address: 
Land At
Baxter Brae
Cleland 
Date Registered: 
25th September 2024 
Applicant:
Mr Scott Forrest
35 Carlisle Road
Bellside
Cleland
ML1 5NX 
Agent:
Wilson Architects (Scotland) Ltd
4 Hareshaw Road
Cleland
ML1 5LZ 
Application Level:
Local Application 
Contrary to Development Plan:
Yes
Ward:   
20 Murdostoun 
Robert John McKendrick, Cameron
McManus, Louise Roarty, Nicky Shevlin.
Representations:
0 letter(s) of representation received.   
Recommendation: Approve Subject to conditions 
Reasoned Justification: 
Although technically contrary to the current local development plan, the proposed development
is an acceptable departure in this instance. This is due to the granting of planning permission
19/00624/FUL and the re-allocation of this land as a yard associated with the existing industrial
use so in usage terms is more akin to being General Urban Area in allocation. The construction
of a house on the site has been assessed and is considered to align with the principles of both
National Planning Framework 4 and the North Lanarkshire Local Plan (2022). 
Page 31 of 88

Page 32

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 24/00965/FUL 
Name (of applicant): Mr Scott Forrest
Site Address: Land at
Baxter Brae
Cleland 
Development: Erection of a Dwelling   
Page 32 of 88

Page 33

Proposed Conditions:- 
1. That, except as may otherwise be agreed in writing by the Planning Authority, the development
shall be implemented in accordance with the following drawing numbers or such updated
drawings as may be required to reflect the requirements of planning conditions 2-21 that follow:-   
2434-LP  Location Plan, 2434- SPA-01  Site Masterplan 2434-03A  Elevations and Floor Plans
and 2434-MSP-25 master site plan. 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That a visibility splay of 2.4 metres by 35 metres, measured from the road channel, shall be
provided on both sides of the vehicular access and before the development hereby permitted
is brought into beneficial use, everything exceeding 1.05 metres in height above the road
channel level shall be removed from the sight line areas and, thereafter, nothing exceeding
1.05 metres in height above road channel level shall be planted, placed, erected, or allowed to
grow, within these sight line area. 
Reason: To ensure adequate sight lines are achieved. 
3. Confirmation of the locations of bin stores and collection location/turning arrangements for the
refuse collection vehicles shall be submitted in the form of a drawing prior to any development
works beginning on site. 
Reason: To ensure that the development may be suitably serviced once brought into beneficial
use. 
4. That before any works of any description start on the application site, with the exception of
ground enabling works which includes land profiling and unless otherwise agreed in writing with
the Planning Authority, a comprehensive site investigation report shall be submitted to and for
the approval of the Planning Authority. The investigation must be carried out in accordance with
current best practice advice such as BS10175: ‘The Investigation of Potentially Contaminated
Sites’ or CLR 11. The report must include a site-specific risk assessment of all relevant pollutant
linkages and a conceptual site model. Depending on the results of the investigation, a Detailed
Remediation Strategy may be required. 
Reason: To establish whether or not site decontamination is required in the interests of the
amenity and wellbeing of future residents of the site. 
5. That any remediation works identified by the report agreed in terms of Condition 4 above shall
be carried out in accordance with an implementation timetable.  This timetable shall be agreed
in writing with the Planning Authority before any works start on site.  The shared campus shall
not be occupied until a certificate (signed by a chartered Environmental Engineer) has been
submitted to the Planning Authority confirming that any remediation works have been carried
out in accordance with the agreed Remediation Strategy. 
Reason: To ensure that any remediation identified has been implemented in the interests of
the amenity and wellbeing of users. 
6. That prior to the commencement of development, with the exception of ground enabling works
which includes land profiling, the applicant shall provide written confirmation to the Planning
Authority that all the requirements of Scottish Water can be fully met to demonstrate that the
development will not have an impact on their assets, and that suitable infrastructure can be put
in place to support the development. 
Reason: To ensure the provision of satisfactory drainage arrangements. 
Page 33 of 88

Page 34

7. That BEFORE the development hereby permitted starts, full details of the design and location
of all fences and walls to be erected on the site shall be submitted to, and approved in writing
by, the Planning Authority. The approved details will be implemented on site before the dwelling
is occupied. 
Reason: To enable the Planning Authority to consider these aspects in detail and in the
interests of amenity of future residents of the dwellings. 
8. That BEFORE the development hereby permitted starts, a scheme of landscaping shall be
submitted to, and approved in writing by the Planning Authority, and it shall include:- 
(a) details of any earth moulding and hard landscaping, boundary treatment, grass seeding and
turfing;
(b) a scheme of tree and shrub planting, incorporating details of the location, number, variety
and size of trees and shrubs to be planted;
(c) an indication of all existing trees and hedgerows, plus details of those to be retained, and
measures for their protection in the course of development;
(d) a scheme of biodiversity improvement measures to be undertaken on site
(d) a detailed timetable for all landscaping works which shall provide for these works being
carried out contemporaneously with the development of the site. 
Reason: To ensure the implementation and maintenance of the landscaping scheme in the
interest of amenity. 
9. That all works included in the scheme of landscaping and planting, approved under the terms
of condition 8 above, shall be completed in accordance with the approved timetable, and any
trees, shrubs, or areas of grass which die, are removed, damaged, or become diseased, within
two years of the full occupation of the development hereby permitted, shall be replaced within
the following year with others of a similar size and species. 
Reason: To ensure the implementation and maintenance of the landscaping scheme in the
interest of amenity. 
10. The occupation of the dwellinghouse shall be limited to a person employed full time in AE
Forrest Patternmakers, or a dependent of such a person residing with him or her, or the widow
or widower of such a person 
Reason: To enable the Planning Authority to retain effective control 
Background Papers: 
Consultation Responses: 
Coal Mining Remediation Authority   25.11.2024 and 26.02.2025.
Environmental Health (including Pollution Control) 26.11.2024.
Traffic & Transportation    18.12.2024 and 04.06.2025. 
Contact Information: Colin Bradley at esplanning@northlan.gov.ukor 01236 632487 
Report Date: 28th July 2025 
Page 34 of 88

Page 35

APPLICATION NO. 24/00965/FUL 
REPORT 
1. Site Description 
1.1 The proposed site is located at the northeastern end of Baxter Brae, within the settlement of
Cleland to the north of Wishaw. 
1.2 The site has been subject to a previous planning application (reference 19/00624/FUL) which
was approved and allowed the change of use of the site from Green Belt to industrial land. 
Therefore the value of the land as part of the Green Belt has been formally assessed and it has
been found that the land may be put to a different use without detriment to either the Green
Belt or access to the Green Belt. 
1.3 Although technically still identified within the Local Development Plan (2022) as ‘Green Belt’,
given the granting of permission reference 19/00624/FUL, the next rendition of the development
plan shall reflect this land as being part of the “General Urban Area” and controlled through
Policy 3 or the equivalent thereof. 
2. Proposed Development 
2.1 This application seeks permission for the erection of a dwelling house for occupation by a family
member who works in the business on to land immediately adjacent to a patternmakers’ family
business and within the envelope of their land ownership. 
2.2 The surrounding land use is predominantly residential in nature and it is intended to site a house
which is reflective of the local architectural vernacular featuring white wet-dash harl, grey roof
tiles, white fenestrations and black rain-water-goods. 
3. Applicant’s Supporting Information 
3.1 The applicant has supplied a drawing detailing site plan as existing, site plan as proposed,
elevations and plans, A separate Location Plan and a ‘Planning Statement’ along with a Mining
Stability report. 
4. Site History 
4.1 Two applications of relevance: 
• 19/00624/FUL - Change of use of land for the expansion of industrial premises –
Application Permitted – 16th December 2019.
• 24/01198/FUL - Side Extension to Existing Industrial Unit – currently under
consideration 
5. Development Plan 
5.1 The site is located within the Green Belt which is covered by Policy 4, Green Belt Policy which
features 2 elements that require to be satisfied, PP 4 (Purpose of Place) and AD 4 (Amount of
Development).  Policy PP4 Green Belt has the stated aim of protecting the setting of
communities, supporting regeneration by directing growth to urban areas, protect natural assets
and provide a high-quality environment”. Policy AD4 with regards to class 9 uses, Houses,
states that the amount of development should support the Green Belt appropriate Use. 
Page 35 of 88

Page 36

5.2 The site has, however, been subject to a previous planning application which granted the
change of use from Green Belt to industrial land effectively moving the land to sit within the
‘General Urban Area’ zoned land through the determination of application 19/00624/FUL. 
Therefore, the value of the land as part of the Green Belt has been formally assessed and it
has been found that the land could be put to an alternative use, in this instance the ‘General
Urban Area’, without detriment to the principles of the Green Belt Policy (4), most notably
“Protecting the setting of communities”. 
5.3 The ‘General Urban Area’ as controlled by Policy 3 of the NLLDP (2022), seeks to “…maintain
and improve the level of amenity in urban areas, by encouraging development that is in keeping
with their residential character…” and states there is no assessment of the amount of
development that is required. 
5.4 The site is also subject to the policies of NPF 4.  Of note within this document are the following
policies; 
Policy 1 - Tackling the climate and nature crisis
Policy 2 - Climate mitigation and adaptation
Policy 3 - Biodiversity
Policy 8 – Green belts
Policy 12 – Zero Waste 
Policy 14 - Design, Quality and Place
Policy 15 - Local Living and 20 Minute Neighbourhoods
Policy 16 - Quality Homes 
Policy 23 – Health and Safety  
6. Consultations 
6.1 The Coal Authority have been consulted with regards to this application and state that “…the
potential zone of influence of an off-site mine entry (shaft, CA ref.280658-023) encroaches into
the southwestern part [do] the site.” Subsequently the Coal Authority sought to object to the
proposal due to the lack of addressing of this issue within the initially submitted Mining Stability
Report and Coal Mining Risk Assessment. A further report was submitted which supplied
sufficient comfort to the Coal Authority to permit the withdrawal of their objection, subject to 3
informatives being included in any successful conclusion to this application.  These informatives
shall be carried over to the Decision Notice permission is approved. 
6.2 NLC Traffic & Transportation have requested that a drawing be submitted detailing parking and
turning for 3 vehicles, visibility splays of 2.4m x 35m with nothing placed or planted greater than
1.05m within the visibility splay and an agreement from both landowners.  Upon receipt of these
documents the Traffic & Transportation department were satisfied that the proposal could be
accommodated without detriment to road safety. 
It was noted however that “As there is already a mix of commercial and residential use within
the site it would not be appropriate to raise any concerns around conflict.  It should be noted
however that 3 residential properties being served from a single private access is the absolute
maximum permitted, and no further residential development can therefore be permitted within
this site. 
Please confirm locations of bin stores and collection location/turning arrangements for the
refuge collection vehicles.” It is considered these requests may be accommodated via a
planning condition requiring the submission of a drawing. 
6.3 NLC Protective Services requested that a Site Investigation be submitted with regards to the
site.  This document, along with the revised Coal Mining Risk Assessment, shall be reviewed
externally by a 3rd party providing a peer review. This may be conditioned to be undertaken
prior to any works commencing on site. 
Page 36 of 88

Page 37

7. Representations 
7.1 This application has not elicited any public representations.   
8. Planning Assessment 
The Principle of Development; 
8.1 Sections 25(1) (a) and 37(2) of the Town and Country Planning (Scotland) Act 1997 require
that this application be determined in accordance with the development plan unless material
considerations indicate otherwise. 
8.2 The site is located within the Green Belt which is covered by Policy 4, Green Belt Policy which
features 2 elements that require to be satisfied, PP 4 (Purpose of Place) and AD 4 (Amount of
Development).  This policy states that the council will protect the setting of communities and
support regeneration by directing growth to urban areas. 
8.3 In this instance, the proposed site is located on the very peripheral edge of the Green Belt and
is sat between a residential development and an industrial development, both of which are
defined as sitting within Policy 3 - General Urban Area. The precise design of this proposal
means that an access strip shall remain to allow the community to access the greenbelt land. 
8.4 This application seeks permission for the erection of a detached dwelling-house on an area of
ground at Baxter Brae which is part of the industrial premises (yard area) so in control of the
applicants. There are a number of houses to the west and north of the application site which
were granted permission in 2006. 
8.5 The site benefits from an extant permission (19/00624/FUL) and another planning application
has been lodged (24/01198/FUL) which is still under consideration (see above).  The existing
permission granted under reference 19/00624/FUL allowed an extension to the premises along
with the expansion of the yard into the green belt. As the yard has been formed, this permission
remains live, so the extension could still be built. This is of relevance in that the further removal
of part of the yard to build a house could have a bearing on the availability of yard space and
parking. With regards to the unbuilt extension and the extension under consideration the
applicant has supplied a drawing detailing 32 potential parking spaces with sufficient space,
(13.5m radius) to turn articulated lorries and storage space. As such NLC Infrastructure &
Transportation did not object to this proposal. 
8.6 Although this application intends to utilise an area of ground which is technically allocated as
Green Belt, the parcel of land has previously been granted planning permission for an industrial
expansion under application reference number 19/00624/FUL which sought to expand the
parking provision to the existing industrial unit on site. After consideration from NLC
Infrastructure & Transportation, it is considered that this land, now in industrial use, may be
altered to accommodate a residential development without detriment to the functioning of the
industrial unit, as per NLC Infrastructure & Transportation consultation response. 
8.7  Policy EDQ1 Site Appraisal of the LDP requires new development is to be appraised in relation
to its surroundings to ensure that it will integrate successfully with the local area. Similarly,
Policy EDQ3, Quality of Development of the LDP and Policy 14, Design, Quality and Place
NPF4 require development to provide high standards of site planning and sustainable design.
It is further intended to improve the quality of an area with a focus on the delivery of safety,
attractive natural and built spaces, accessibility, distinctiveness, adaptability and sustainability
(Policy 14, NPF4). The scale and design of proposed dwelling is modest and appropriate to its
location adjacent to the Baxter Brae residential area. 
8.8 The material palette associated with the proposal is that of white render to the external walls
and anthracite roof tiles to the roof will be in the local vernacular in this area and shall not
appear incongruous. The window fenestrations have been selected to be finished in anthracite
grey. All of which is considered to be acceptable. 
Page 37 of 88

Page 38

8.9 It is considered that the proposed siting is relatively compact in nature, respectful of the
immediate surroundings, including in scale and massing and the orientation of the building to
face into the existing street. The layout and position of the proposed dwelling allows for a
generous spatial setting around the dwelling which in turn will maximise opportunities for
landscaping and biodiversity enhancement whilst retaining many of the trees on there shall be
no impediment for existing residents of the Baxter Brae community with regards to accessing
the Green Belt land.   
8.10 Accordingly it is considered that the proposed dwelling complies with the design principles of
Policies EDQ1 and EDQ3 of the LDP and Policy 14 of NPF4. 
8.11 Policy PROT A Natural Environment and Green Network Assets (category 4) of the LDP aims
to protect trees and woodlands, watercourses and wetlands in existing Green Network
infrastructure and in other key locations, including new Green Network infrastructure. The policy
further seeks to ensure that adverse effects on protected species are mitigated through
planning conditions.  Policy 3 Biodiversity of NPF4 requires all development proposals to
contribute to the enhancement of biodiversity.  Tree retention and landscaping (including
biodiversity improvements) can be covered by planning condition. The site is currently a yard
area so not green belt. 
8.12 The proposal shall not result in a lack of access to the green belt as an access route shall be
retained to the west of the proposed site. As such it is considered that although contrary to
policy, the application may be supported in this instance. 
8.13 Policy EDQ3 Quality of Development of the LDP provides that new development should
address safe, secure, and convenient access into and through the development and
sustainable access for cars where required, being safe for all road users. Policy EDQ3 is
generally compatible with Policy 13 Sustainable Transport of NPF4 which requires
development to incorporate safety measures including those to adequately mitigate against any
impacts on local public access routes through, for example, reduction in the number and speed
of vehicles. In this instance, the ‘yard’ area of the associated business plays host to 2 existing
dwelling houses and it is considered that there shall be no additional risk to road safety through
the introduction of a third dwelling house. 
9. Conclusions 
9.1 The allocation of the land as green belt, (LDP Policy 4), has fundamentally been altered through
the granting and implementation of planning permission reference 19/00624/FUL which
effectively alters the usage of this parcel of ground to industrial (General Urban Area LDP Policy
3). 
9.2 The proposed dwelling house is respectful of the wider residential estate with regards to scale,
massing and material palette and access to the green belt shall be maintained via an existing
semi-formal desire line path to the west and south of the proposed dwelling site. 
9.3 Given the above, it is not considered that the proposal presents any issues with regards to
policy and therefore it is recommended that planning permission be granted, subject to
conditions.   
Page 38 of 88

Page 39

Application No:  
24/01039/FUL
Proposed Development: 
Part Change of Use of Former Peat Works Minerals Operation
(Sui Generis) to Form Open Storage Yard for Inert Material
(Class 6) with Use of Replacement Shed for Storage (Class 6)
and Ancillary Office/Administration Use (Class 4) (in Retrospect). 
Site Address: 
Land At
Peat Works
Cumbernauld Road
Moodiesburn 
Date Registered: 
10th December 2024 
Applicant:
Prime Acres Ltd
100 Cumbernauld Road
Moodiesburn
G67 0HE 
Agent:
Angus Design Associates
The Building Design Centre
125 Muir Street
Hamilton
ML3 6BJ 
Application Level:
Local Application 
Contrary to Development Plan:
yes
Ward:   
06 Gartcosh, Glenboig and Moodiesburn 
Greg Lennon, Michael McPake, Joanne Katy
Keltie,
Representations:
No letters of representation received.   
Recommendation:  Approve Subject to Conditions 
Reasoned Justification: 
The introduction of a class 6 use with ancillary Class 4 (building retrospective), when measured
against of the criteria within the polices of the Development Plan and other material
considerations presents an acceptable development in that a historic non-conforming use is
being replaced by an equivalent use resulting in a change not considered significantly material
as it does not undermine the robustness of Green Belt policy balanced against the principle of
Green Belt appropriate use and other policies assessed. 
Page 39 of 88

Page 40

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 24/01039/FUL 
Name (of applicant): Prime Acres Ltd
Site Address: Land at
Peat Works
Cumbernauld Road
Moodiesburn 
Development: Part Change of Use of
Former Peat Works Minerals Operation
(Sui Generis) to Form Open Storage Yard
for Inert Material (Class 6) with Use of
Replacement Shed for Storage (Class 6)
and Ancillary Office/Administration Use
(Class 4) (in Retrospect).   
Page 40 of 88

Page 41

Proposed Conditions:- 
1. That, except as may otherwise be agreed in writing by the Planning Authority, the development
shall be implemented in accordance with drawing numbers: -AL001,  AL002 , AL003,  AL005 
& AL004   
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That before the site and building hereby permitted is brought into use, unless otherwise agreed
in writing with the Planning Authority; full details of the proposed surface water drainage
scheme shall be submitted to the said Authority and shall be certified by a chartered civil
engineer experienced in drainage works as complying with the most recent SEPA SUDS
guidance. For the avoidance of doubt the drainage arrangements shall include a Pollution
Prevention scheme and detailed drainage Plan protecting the adjacent bog from contamination.
Thereafter the scheme shall be implemented certified by a chartered civil engineer experienced
in drainage works as complying with the most recent SEPA guidance. 
Reason: To prevent groundwater or surface water contamination in the interests of
environmental protection of the adjacent bog. 
3. The applicant will continue to support Caledonian Climates work to investigate the measures
that will be required to be undertaken on site to secure the restoration of the former peat bog
including the seeking of grant funding for this work in conjunction with Peatland ACTION. In the
event that grant funding is secured the applicant will allow access to the moss for the grant
funding works to be undertaken. 
Reason: in the interest of biodiversity and to facilitate peat bog restoration.     
4. That before the site and building is brought into use, a scheme of landscaping including
biodiversity enhancements, for the area identified in appendix 10 Planting for wild life of the
Preliminary Ecology Report by wild surveys 18th March 2025 shall be submitted to, and
approved in writing by the Planning Authority, and it shall include:-
(a) details of any earth moulding and boundary treatment;
(b) a scheme of tree and shrub planting, incorporating details of the location, number, variety
and size of trees and shrubs to be planted;
(c) an indication of all existing trees and hedgerows, plus details of those to be retained, and
measures for their protection in the course of development,
(d) details of the phasing of these works. 
Reason: In the interests of protecting the adjacent sensitive peatland habitat and the visual
amenity of the area. 
5. That all works included in the scheme of landscaping and planting, approved under the terms
of condition (4) above, shall be completed in accordance with the approved timetable, and any
trees, planting, which die, are removed, damaged, or become diseased, within two years of the
full occupation of the development hereby permitted, shall be replaced within the following year
with others of a similar size and species.
Reason: To ensure the provision of adequate biodiversity enhancement planting.  
Page 41 of 88

Page 42

6. That before the site and building hereby permitted is brought into use, a management and
maintenance scheme shall be submitted to, and approved in writing by the Planning Authority,
and it shall include proposals for the continuing care, maintenance and protection of:- 
(a) the proposed planted and landscaped areas identified in appendix 10 Planting for wildlife of
the Preliminary Ecology Report by wild surveys 18th March 2025;
(b) the proposed fences/walls to be erected. 
Reason: To ensure the ongoing maintenance of biodiversity enhancement planting. 
7. That upon commencement the use of the building and land hereby permitted, the management
and maintenance scheme approved under the terms of condition 6; shall be in operation.
Reason: To ensure the ongoing maintenance of biodiversity enhancement planting. 
8. That no trees within the application site shall be lopped, topped, felled, or otherwise affected,
without the approval in writing of the Planning Authority.
Reason: In the interests of protecting trees forming part of a sensitive peatland habitat and
the visual amenity of the area. 
9.  That before the site and building is brought into use, tree protection measures in accordance
with British Standard BS 5837 shall be confirmed for the trees identified in condition (4) and
shall not be removed without the approval in writing of the Planning Authority. 
Reason: In the interests of the amenity of the area, to ensure that necessary contingencies are
in place, to minimise impact on trees at this site. 
10. That a visibility splay of 2.4m x 215m, shall be provided on both sides of the vehicular access
and before the development hereby permitted brought into use, everything exceeding 0.6
metres in height above the footway level shall be removed from the sight line areas and,
thereafter, nothing exceeding 0.6 metres in height above the footway level shall be planted,
placed, erected, or allowed to grow, within these sight line areas. 
Reason: In the interests of road safety 
11. That before the land and buildings hereby permitted are brought into use a Construction Method
Statement shall be submitted to and approved by the Planning Authority. The Construction
Method Statement shall include: 
Details of all on site construction, including drainage, vehicle movements, traffic management
and types and post- construction restoration works. 
A full site-specific environmental management plan (Pollution Prevention Plan). For the
avoidance of doubt these works should accord with the SEPA Pollution Prevention Guidelines.
Thereafter the development shall be implemented in accordance with the approved
Construction Method Statement 
Reason: In the interests of road safety, the amenity of the area and to ensure that necessary
contingencies are in place, to minimise pollution risks arising from construction activities and to
prevent groundwater or surface water contamination in the interests of environmental protection
of the adjacent bog.  
Page 42 of 88

Page 43

12. That should 12 months or more after the current original ecological survey the Preliminary
Ecology Report by wild surveys 18th March 2025 and the site being brought into use, a further
Protected Species Survey shall be undertaken on the site to determine the presence of any
statutorily protected species, the said survey shall thereafter be submitted to and approved in
writing by the Planning Authority before any development commences on the site. As a result
of the study, should any mitigation measures be required for any protected species, this shall
be implemented in accordance with a species protection plan agreed in writing with the
Planning Authority in consultation with Scottish Natural Heritage before works commence on
the site. 
Reason: To ensure compliance with The Conservation (Natural Habitats & c.) Amendment
(Scotland) Regulations 2007 and the protection of Badgers Act 1992. 
13.    That the biodiversity enhancements specified within appendix 10 of the submitted Ecological 
Report by wild surveys 18th March 2025 shall be adhered to throughout this development. 
Reason: To comply with Policy 3 of National Planning Framework 4. and minimise impact on
and enhance the surrounding peatland identified in the Preliminary Ecology Report by wild
surveys 18th March 2025. 
14. That, notwithstanding the provisions of the Town and Country Planning (General Permitted 
Development) (Scotland) Order 1992 and the provisions of Class 6; of the Town and Country 
Planning (Use Classes) (Scotland) Order 1997, the site and ancillary building shall be used 
solely as a yard for the storage of inert materials. 
Reason: To enable the Planning Authority to retain effective control, in order to accord with the
provisions of the Planning etc (Scotland) Act 2006. 
15. That before the site and building is brought into use, full details of the design and location of all 
fences and walls to be erected on the site shall be submitted to and approved in writing by the 
Planning Authority. 
Reason: In the interest of the amenity of the site and the general area. 
16. That no materials or plant stored within the yard area of the application site shall be over 2 
metres in height, without the approval in writing of the Planning Authority. 
Reason: To enable the Planning Authority to retain effective control, in order to accord with the
provisions of the Planning etc (Scotland) Act 2006. 
17. That unless as may otherwise be agreed in writing by the Planning Authority, no operations of 
any kind shall be permitted on the application site between the hours of 11pm and 7am. 
Reason: In the interest of the amenity of the site and the general area 
18. That no lighting shall be installed within the site hereby approved unless full details have first 
been submitted to and approved by the Planning Authority 
Reason: In the interest of the amenity of the site and the general area 
Page 43 of 88

Page 44

Background Papers: 
Consultation Responses: 
Transport Scotland letter received 14th April 2025 
NLC Greenspace memorandum received 3rd April 2025 
Environmental Health (including Pollution Control) memorandum received 30th January 2025 
NLC Roads memorandum received 7th May 2025 
Contact Information: 
Gordon Arthur at esplanning@northlan.gov.uk or 01236 632487 
Report Date:  28th July 2025
Page 44 of 88

Page 45

APPLICATION NO. 24/01039/FUL 
REPORT 
1. Site Description  
1.1 The site was formerly used for peat extraction (Moodiesburn peat workings) closed 1980’s. The
wider area including the entire site area is currently designated as a Site of Importance for
Nature Conservation (Moodiesburn Moss SINC). The site is regular in shape and forms the
northern edge of the former peat extraction works. The application site covers 1.9 Hectares and
is bounded to the north by the A80 Trunk Road screened by a mature hedge line with residential
properties of Moodiesburn beyond a further hedge line on the opposite carriageway. The site
itself is characterised by self-seeding trees to the east, west and south where beyond lies of
the former peat extraction fields. The site is generally level and while consisting of grass land
has a ruderal appearance having the appearance of having been worked with imported
material. A building constructed mainly from corrugated steel stood on the site until as recently
as May 2023 and has recently been replaced by a building which forms part of this retrospective
application.
2. Proposed Development 
2.1 The application, which is in part retrospect, seeks to regularise the formation of a commercial
yard (hardstanding) for the subdivided open storage of undefined material (class 6) and the
construction of a replacement building for storage use (also class 6). The principal of the
development is considered to be a change of use from sui generis former peat works (mineral
extraction including ancillary building) to Class 6 storage and distribution.
3. Applicant’s Supporting Information 
3.1 Supporting information includes. 
o Planning Statement
o Preliminary Ecological appraisal
o Hydrology Report
o Moodiesburn Peat Works – Site Walkover Report by Caledonian Climate 
4. Site History 
4.1 Recent significant planning history includes the following: 
• 09/01019/MIN Importation of Inert Material for Infill and the Formation of a 2 Metre High Bund. 
Application Refused 21.10.2010 
5. Development Plan 
5.1 NPF4 forms part of the development plan. As such the proposed development requires to be
assessed against the provisions and policies of both NPF4 and The North Lanarkshire Local
Development Plan. The most relevant considerations some already enshrined in the North
Lanarkshire Local Development Plan policies are set out below.  This application can therefore
be considered against the policy provisions of the North Lanarkshire Local Development Plan
and the National planning Framework 4 as follows. 
Page 45 of 88

Page 46

National Planning Framework 4
The policies within NPF4 that are relevant to the application are:
• Policy 3 Biodiversity
• Policy 4 Natural Places
• Policy 6 Forestry, Woodland and Trees
• Policy 8 Green Belts
• Policy 9 Vacant and derelict Land and empty buildings
• Policy 20 Blue Green Infrastructure 
North Lanarkshire Local Development Plan (2022)
• PROT A POLICY Natural Environment and Green Network Assets
• PP 4 POLICY Purpose of Place
• AD 4 POLICY Amount of Development
• EDQ1 Site Appraisal,
• EDQ2 - Specific Features for Consideration,
• EDQ3 - Quality of Development.  
6. Consultations 
6.1 Comments were received from the following consultees 
6.2 NLC Protective Services has no objection to the development advising on process should
contaminated land become apparent during on site works. This is recommended as an
informative on the decision notice. 
6.3 NLC Greenspace & Country Parks commented that the site is designated as a Site of
Importance for Nature Conservation (SINC) and that Moodiesburn Peat Working was
designated as peatland with a birch woodland area. They also note that although the bog is
disturbed or modified this would apply to most of the peat land within North Lanarkshire..   
6.4 They highlighted guidance on NatureScots website – Advising on peatland, carbon-rich soils
and priority peatland habitats in development management.  The approach set out in this
guidance aligns with the National Planning Framework 4 (NPF4) policies which are relevant to
development proposals on peatland, carbon-rich soils and priority peatland.  A key focus will
be on helping to ensure that development is designed and constructed to follow the mitigation
hierarchy set out in NPF4 and that, in addition, biodiversity enhancement is delivered through
peatland restoration.  In this case the applicant has provided information to demonstrate that
the use of the previously disturbed area can proceed without detriment to the peatland bog
itself and have confirmed that no development shall take place on the peat land.  Furthermore,
throughout the application process the applicant have themselves been liaising directly with
NLC Greenspace & Country Parks to investigate the opportunities to restore the bog.  To this
end they are working with a specialist consultant (Caledonian Climate) who have produced a
preliminary report which indicates that any meaningful restoration will involve significant
investment in time and finance way beyond the capacity of this landowner/applicant. However,
the applicant has provided a potential way forward through its agents Caledonian Climate who
indicate the works would meet the criteria for grant funding and that they are prepared to further
the cause in conjunction with Peatland ACTION. This can only be achieved through voluntary
partnership working. The nature of the grant funding is such that it cannot be used to fund
restoration works that are a requirement of a planning condition.  The applicants have already
committed themselves to exploring this avenue for funding the restoration of the bog and this
Page 46 of 88

Page 47

is to be welcomed. Proposed planning condition 3 requires that the applicant will continue to
support Caledonian Climates work to investigate the measures that will be required to be
undertaken on site to secure the restoration of the former peat bog including the seeking of
grant funding for this work in conjunction with Peatland ACTION and in the event that grant
funding is secured the applicant will allow access to the moss for the grant funding works to be
undertaken. 
6.5 Concern was expressed that the works would impact on the peatland however having assessed
the submitted Hydrology Survey determined that the proposed development would have no
direct impacts on peat, as the development is fully located over an area of made ground and
therefore it is assumed it will not require any excavation of peat. The development is also
located at least 2m above the level of the surrounding peat body and therefore will not affect
water levels within the bog. An interception filter drain around the perimeter of the proposed
development is recommend to treat site derived runoff and discharge this to a drainage channel
that bypasses the network of drains associated with the bog. With the adoption of this measure
no direct or indirect impacts are expected on the remnant raised bog and associated peat
deposits. 
6.6 They advise that NPF4 (National Planning Framework 4) states that planning, and development
will help to achieve a net zero, sustainable Scotland by 2045. This includes securing positive
effects for biodiversity. Furthermore, Nature Scots guidance on Developing with Nature refers
to the inclusion of “appropriate measures” not only to mitigate and compensate for the loss of
biodiversity but also to enhance biodiversity nature Scot provides advice on information that
applicants could include within a planning application in order to provide confidence that
enhancement will be achieved. 
6.7 A Pollution Prevention and detailed Drainage Plan needs to be put in place in order to protect
the adjacent bog. 
6.8 NLC Greenspace & Country Parks accepts the finding of the Preliminary Ecological Survey and
ask that all mitigation within the survey report is taken forward. If works have not commenced
within 18 months of this survey updated survey should be submitted. Also, that Biodiversity
Enhancements put forward within the PEA should be undertaken on the site. 
6.9 A number of planning conditions are recommended that will address the matters highlighted by
Greenspace & Country Parks covering drainage and pollution prevention, biodiversity and
protected species. 
6.10 Transport Scotland do not advise against granting permission. 
6.11 NLC Infrastructure & Transportation has no objection to the development in so far as
comments relating to the vehicle size using the site, visibility splays demonstrated and in
curtilage arrangements were implemented. A planning condition is recommended to address
these points notwithstanding the application being retrospective. 
Page 47 of 88

Page 48

7. Representations 
7.1 No representations were received although we did receive correspondence from a local
resident regarding timescales for comment and questioning the neighbour notification
processes. We clarified this and no representation was received. There was some dubiety in
the initial correspondence as to whether the individual concerned was looking to speak to the
committee. Clarification was sought on this point, but no confirmation was provided by the
individual although in response to our email they did question the status of the applicant and
the application.  In any event, in terms of the protocol, to address the committee you first need
to have commented on the application. Furthermore, Members should note that the actual
requirement for holding a hearing in relation to developments that are contrary to the
development plan (such as this one) require a total of 6 representations or an objection by a
community council all objecting on valid planning grounds. Neither have been met in this case
so a hearing is not required. 
8. Planning Assessment 
8.1 As submitted the application, which is in part retrospect, seeks to regularise the formation of a
commercial yard (hardstanding) for the subdivided open storage of undefined material (class
6) and the construction of a replacement building for class 5 (Industrial) and Class 6 (Storage
and distribution). Whilst noting the applicant’s position in relation to the use of the building for
both classes 5 & 6 our view was that this would not be appropriate and therefore we have
assessed the development as being the ‘Part change of use of former peat works minerals
operation (sui generis) to form open storage yard for Inert material (Class 6) with use of
replacement shed for storage (Class 6) and ancillary Office/Administration use (Class 4) (in
retrospect)’.
8.2 Sections 25(1) (a) and 37(2) of the Town and Country Planning (Scotland) Act 1997 require
that this application be determined in accordance with the development plan unless material
considerations indicate otherwise. While the application is of a local nature the proposed
development requires to be assessed against the provisions and policies of both NPF4 and the
North Lanarkshire Local Development Plan. The most relevant considerations some already
adopted in the North Lanarkshire Local Development Plan policies are set out below have been
updated by the introduction of NPF4.  This application can therefore be considered against the
policy provisions of the North Lanarkshire Local Development Plan and the National Planning
Framework 4
8.3 National Planning Framework 4
Policy 3 Biodiversity Proposals for local development will include appropriate measures to
conserve, restore and enhance biodiversity, in accordance with national and local guidance.
Measures should be proportionate to the nature and scale of development.
Policy 4 Natural Places has the intention of protecting, restoring and enhancing natural assets
making best use of nature-based solutions resulting in natural places that are protected and
restored. Development proposals which by virtue of type, location or scale will have an
unacceptable impact on the natural environment, will not be supported. 
4c) Development proposals that affect a site designated as a local nature conservation site or
landscape area in the LDP will only be supported where: 
i. Development will not have significant adverse effects on the integrity of the area or the
qualities for which it has been identified or
ii. Any significant adverse effects on the integrity of the area are clearly outweighed by social,
environmental or economic benefits of at least local importance. 
Page 48 of 88

Page 49

4e) The precautionary principle will be applied in accordance with relevant legislation and
Scottish Government guidance. 
4f) Development proposals that are likely to have an adverse effect on species protected by
legislation will only be supported where the proposal meets the relevant statutory tests. 
Policy 5 soils is intended to protect carbon-rich soils, restore peatlands and minimise
disturbance to soils from development. 5c) Development proposals on peatland, carbonrich
soils and priority peatland habitat will only be supported for: (v). Restoration of peatland
habitats.
Policy 6 Forestry, Woodland and Trees is intended to protect and expand forests, woodland
and trees. Woodland and trees on development sites should be sustainably managed.
Policy 8 Green Belt exists to encourage, promote and facilitate compact urban growth and
use the land around our towns and cities sustainably.
a) Development proposals within a green belt designated within the LDP will only be
supported if: 
• intensification of established uses, including extensions to an existing building where that
is ancillary to the main use. 
Policy 9 Vacant and derelict Land and empty buildings encourages, promotes and
facilitates the reuse of brownfield, vacant and derelict land and empty buildings, and to help
reduce the need for greenfield development.
8.4 In considering the foregoing, NPF4 policies, it should be noted that while the site lies within the
designated Green Belt and is surrounded by an ecological designated area it is also recorded
as having been previously developed and is within the vacant and derelict land register 2024.
As such, as a former peat works, and an area of compacted ground it may reasonably be
considered a continuation of activities associated with this former use and latterly as a yard
area for construction plant and vehicles albeit transient as evidenced by the applicant. The
immediate site therefore while limited in its contribution to biodiversity represents an opportunity
to investigate the opportunities for some biodiversity enhancements within the site along with
measures to protect the bog. The applicant in conjunction with NLC Greenspace & Country
Parks and Caledonian Climate are committed to the further investigation (including the seeking
of funding) to progress a bog restoration scheme for the surrounding peatland habitat. We have
explored fully a mechanism for securing this restoration work through this planning permission.
The applicant has argued that the significant investment in time and finance is way beyond their
capacity but that they have provided a way forward through its agents Caledonian Climate who
are prepared to further the cause in conjunction with Peatland Action.  As the funding avenues
can only be used for restoration works that are not a requirement of a planning condition it has
not been possible to condition this matter.  The applicant has argued that with the imposition of
conditions to protect the bog (in particular drainage and pollution prevention) they have been
able to demonstrate that the development undertaken can proceed without detriment to the
peat land habitat.  We have conditioned that the applicant continue to work with Caledonian
Climate including their bid to secure funding for the peat land restoration works and that they
will allow access to carry out the works in the event that funding is secured. 
Page 49 of 88

Page 50

8.5 Overall, the intention is to enable the development which is part retrospect and on derelict land
with the intention of protecting and hopefully allowing the restoration and enhancement of
natural assets (peat bog). As such, the proposal is considered to comply with the relevant NPF4
polices.
8.6 North Lanarkshire Local Development Plan (2022)
PROT A POLICY Natural Environment and Green Network Assets
With regards to Sites of Importance for Nature Conservation (SINC) this policy advises that
planning permission will only be granted for proposals potentially affecting Local Sites if it can
be demonstrated to the Council’s satisfaction that there will be no adverse impact or that any
impacts can be mitigated in environmental terms relevant to the impact.
PP 4 POLICY Purpose of Place
North Lanarkshire Council will protect the setting of communities, support regeneration by
directing growth to urban areas, protect natural assets and provide a high-quality environment,
by promoting a Green Belt as defined on the Promote Map.
North Lanarkshire Council will support developments for agriculture, forestry, recreation, or
developments that need a non-urban location, including, where appropriate, Visitor Economy
related development.
Where specified by this Policy, applicants will normally be expected to provide the identified
appraisals or assessments, which should be submitted with any planning application to allow
consideration of the proposal.
The purpose of the Green Belt is to protect the setting of communities, support regeneration by
directing growth to urban areas, protect natural assets and provide a high-quality environment.
North Lanarkshire Council will encourage development appropriate for a Green Belt location by
resisting development that is not for agriculture, forestry, recreation, tourism, or needs a Green
Belt location, whilst allocating appropriate land for urban expansion. Regarding development
that needs a Green Belt location, the need will be balanced against any adverse effects on the
purposes of the Green Belt.
8.7 While the Council will resist other forms of development, through the full range of Policies in
the Plan. In this instance the applicant is proposing to replace a historic non-conforming use
(sui generis) with non-conforming use class 6 with ancillary replacement building. Both uses
clearly do not conform with Green Belt policy in the LDP a matter which the applicant has not
attempted to dispute. That being the case, assessment of the proposed change and impacts
through the limits defined in the Amount of Development policy (Policy AD4) becomes
inconsequential being a previously developed vacant/brownfield site used for a sui generis use
which has many similarities with the proposed use . The applicant has submitted information to
confirm that the development can proceed without detriment to the SINC and this has been
accepted by NLC Greenspace & Country Parks. The requirements of Policy PROT A have
therefore been complied with.  The application is therefore determined on Environmental and
Design Qualities and other material considerations.  .
8.8 Whether the change is appropriate therefore comes down to the nature and scale of the
development and whether the proposal is an intensification of use. This is determined by the
following Environmental and Design Qualities policies:
EDQ1 Site Appraisal,
EDQ2 - Specific Features for Consideration,
EDQ3 - Quality of Development.
Page 50 of 88

Page 51

8.9 The Local Development Plan identifies distinct Land Use Character Areas within North
Lanarkshire. Development proposals should relate well to the existing setting and avoid
adverse impact on existing or proposed properties. Appraising the existing features of a site
and how it relates to its surroundings is an important first step in ensuring this.
8.10 Policy EDQ1 Site Appraisal states that a proposed development will be appraised in terms of
the site and its surroundings to ensure it will integrate successfully into the local area and avoid
harm to neighbouring amenity. The matters to be addressed in the appraisal include
surrounding Land Use Character Area. In this respect while the site lies within the Green Belt
it is an area of Green Belt that has been developed in part retrospect, seeks to regularise the
formation of a commercial yard (hardstanding) for the subdivided open storage of undefined
material class 6 and the construction of a replacement building for storage and the
administration of the class 6 use. The principal of the development is considered to be the Part
change of use of former peat works minerals operation (sui generis) to form open storage yard
for Inert material (Class 6) with use of replacement shed for storage (Class 6) and ancillary
Office/Administration use (Class 4) (in retrospect). As such, the applicant argues that the site
has been repurposed and will not give rise to a significant loss of existing levels of amenity.
The site therefore can be integrated successfully into the local environs avoiding harm to
neighbouring amenity and is therefore supported by Policy EDQ1.
8.11 Policy EDQ2 (Special Features for Consideration) does not generally apply as it refers to
specific features on appeal sites or within the proximity such as Health and Safety Executive
Consultation Zones, Flood Risk, Air Quality/Noise Quality Management Areas. Here are no
significant constraints identified under Policy EDQ2 (Special Features for Consideration).
8.12 Policy EDQ3 - Quality of Development - only permits development where high standard of site
planning and sustainable design and development are achieved. This includes a number of
matters appropriate to the site from the various sub paragraphs stated in Policy EDQ3. The
application in replacing site structures equivalent to that demolished is able to continue
acceptable standards of site planning and sustainable design required by Policies EDQ 1 and
EDQ 3.
8.13 Other material considerations
As the application is retrospective on a Green Belt Site the applicant has explored the possibility
of restoring part of adjacent peat land. An initial report was submitted identifying restoration
potential concluding that works will involve significant investment in time and finance on the
part if the landowner. As it stands, the applicant has suggested a way forward through its agents
Caledonian Climate who are prepared to further the restoration in conjunction with Peatland
Action.  The applicant considers that this can only be achieved through voluntary partnership
working. The applicants have already committed themselves to this action and would be happy
for officers to engage directly with the authors of the report (Caledonian Climate) at any stage.
A condition has been imposed requiring the applicant to continue to support the work being
undertaken by Caledonian Climate including allowing them access to the land to implement the
works should the grant funding be secured. 
Correspondence was received from an individual commenting that the applicant for the site,
Prime Acres Ltd., is no longer in business and has been dissolved by compulsory strike off by
Companies House.  In development management terms, procedurally this information would
require a change on the application form (to be updated) before presenting the application to
committee providing new details of applicant and landowner and has no bearing on the planning
assessment. However, the applicant’s agent subsequently confirmed that there is no change
in site ownership or applicants. Through an administrative error confirmation statements for
Companies House were inadvertently missed which is in the process of being rectified by the
applicants appointed Chartered Certified Accountants. 
Page 51 of 88

Page 52

9. Conclusions 
9.1 In conclusion, the applicant's justification and supporting information for a class 6 use, when
measured against of the criteria within the polices of the Development Plan and other material
considerations presents an acceptable development when balanced against the principle of
Green Belt appropriate use and other policies assessed. As a historic non-conforming use, the
subsequent replacement use is not considered significantly material in that it does not
undermine the robustness of Green Belt policy. Therefore, it is recommended that planning
permission be approved. 
Page 52 of 88

Page 53

Application No:  
25/00085/FUL
Proposed Development: 
Change of Use from Bus Depot to Traffic Management Depot
with Ancillary Administration Building 
Site Address: 
560 Stirling Road
Airdrie
ML6 7SS 
Date Registered:   
Applicant:
Diack & Macaulay Ltd
F.A.O Mr Stuart Diack
7 Gartferry Road
Chryston
G69 0LY 
Agent:
ADR ( Design ) Ltd
F.A.O David Rose
The Nurseries
5 Tak-Ma-Doon Road
Kilsyth
G65 0RS 
Application Level:
Local Application 
Contrary to Development Plan:
yes
Ward:   
08 Airdrie North 
Alan Beveridge, Sophia Coyle, Henry Emerson
Dunbar, Richard Alan Sullivan,
Representations:
No letters of representation received.   
Recommendation:  Approve Subject to Conditions
Reasoned Justification: While the application does not concur with the principal development
plan policy (Green Belt) other material considerations namely the sites planning history
combined with policies on Environmental and Design Qualities support the recommendation to
approve. 
Page 53 of 88

Page 54

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 25/00085/FUL 
Name (of applicant): Diack & Macaulay
Ltd
Site Address: 560 Stirling Road
Airdrie
ML6 7SS 
Development: Change of Use from Bus
Depot to Traffic Management Depot with
Ancillary Administration Building   
Page 54 of 88

Page 55

Proposed Conditions:- 
1. That, except as may otherwise be agreed in writing by the Planning Authority, the development
shall be implemented in accordance with drawing numbers: - 
441/01, 441/03, 441/05, 441/04 Rev C and 441/02   
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That before the construction of any revised internal arrangements, unless otherwise agreed in
writing with the Planning Authority; full details of the final surface water drainage scheme shall be
submitted to the said Authority and a certificate (signed by a Chartered Civil Engineer
experienced in drainage works) shall be submitted to the Planning Authority confirming that the
SUDS has been constructed in accordance with the relevant CIRIA Manual and the approved
plans. 
Reason: To ensure that the drainage scheme complies with best SUDS practice to protect
adjacent watercourses and groundwater, in the interests of the amenity and wellbeing of existing
and future residents adjacent to and within the development site. 
3. That the surface water drainage scheme approved under the terms of condition 2 above shall be
implemented contemporaneously with the development in so far as is reasonably practical. 
Within three months of the construction of the SUDS, a certificate (signed by a Chartered Civil
Engineer experienced in drainage works) shall be submitted to the Planning Authority confirming
that the SUDS has been constructed in accordance with the relevant CIRIA Manual and the
approved plans. 
Reason: To safeguard adjacent watercourses and groundwater from pollution and in the
interests of the amenity and wellbeing of existing and future residents adjacent to and within the
development site. 
4. That a visibility splays identified on drawing 441/04 Rev C shall be formed on both sides of the
vehicular access and before the development hereby permitted is brought into use, everything
exceeding 1.05 metres in height above the road channel level shall be removed from the sight
line areas and, thereafter, nothing exceeding 1.05 metres in height above road channel level
shall be planted, placed, erected, or allowed to grow, within these sight line areas. 
Reason: To ensure adequate sight lines are achieved. 
Background Papers: 
Consultation Responses: 
Traffic & Transportation memorandum received 5th March, 29th April, 30th May & 30th June 2025 
Environmental Health (including Pollution Control) memorandum received 17th March 2025. 
Contact Information: Gordon Arthur at esplanning@northlan.gov.uk or 01236 632487 
Report Date: 28th July 2025
Page 55 of 88

Page 56

APPLICATION NO. 25/00085/FUL 
REPORT 
1. Site Description  
1.1 The site has a rural location characterised by woodland to the east, enclosed field to the north
bound by Hulks Road and three single storey residential properties beyond. The site is bounded
and accessed from Stirling Road to the west and enclosed fields beyond. Beyond a mature
boundary hedge line to the south is open fields. The site is an existing bus depot consisting of
a large yard area of hardstanding with a single storey detached dwelling (used by the former
bus operation for administration) to the north a brick and render outbuilding occupies the area
immediately adjacent to the dwelling a larger profiled steel building lies to the east of the site.
There is a small domestic scale outbuilding positioned between both larger buildings. 
2. Proposed Development 
2.1 The application proposes a change of use from a bus depot to a depot to a traffic management
depot. Traffic management involves planning, implementation, installation of equipment to
maintain traffic control systems such as traffic lights, lane closures, diversions and 'stop & go',
that separate road workers from road users with minimum disruption to traffic flow. As such the
yard will be used for the storage of works vehicles and equipment used in traffic management.
The applicant also proposes to use the former dwelling for the ancillary administration of this
activity. It is the applicant’s intention to demolish the brick and render outbuilding which
ordinarily would not require planning permission. 
3. Applicant’s Supporting Information 
3.1 Supporting information includes a planning statement. 
4. Site History 
4.1 Recent significant planning history includes the following: 
• 06/01075/FUL Erection of Coach Garage (approved)
• 24/01249/CLP Existing house, office, shed and outbuildings used continually as a coach
depot and workshops use to continue as a class 4/6 commercial, light industrial and storage
(withdrawn) 
5. Development Plan 
5.1 NPF4 forms part of the development plan. As such the proposed development requires to be
assessed against the provisions and policies of both NPF4 and The North Lanarkshire Local
Development Plan. Given the scale and nature of this development the most relevant
considerations are already enshrined in the North Lanarkshire Local Development Plan policies
are set out below.  This application can therefore be considered against the policy provisions
of the North Lanarkshire Local Development Plan and National planning Framework 4 as
follows. 
Page 56 of 88

Page 57

National Planning Framework 4 
The policies within NPF4 that are relevant to the application are: 
• Policy 8 Green Belts
• Policy 9 Vacant and derelict Land and empty buildings 
North Lanarkshire Local Development Plan (2022)
Relevant polices are:
• PP 4 POLICY Purpose of Place
• AD 4 POLICY Amount of Development
• EDQ1 Site Appraisal,
• EDQ2 - Specific Features for Consideration,
• EDQ3 - Quality of Development.  
6. Consultations 
6.1 Comments were received from the following consultees 
NLC Protective Services has no objection to the development advising on process should
contaminated land become apparent during on site works. This is recommended as an
informative on the decision notice. 
NLC Infrastructure & Transportation has no objection to the development in so far as
comments relating to the closure of an access, visibility splays demonstrated and in curtilage
arrangements were implemented. The applicant responded positively to these requirements
submitting a revised drawing. 
7. Representations 
7.1 No representation was received following an advert in the local press. 
8. Planning Assessment 
8.1 The application which is for a change use of a bus depot (sui generis) to a Traffic Management
Depot (sui generis). The bus garage is an established albeit non-conforming use in the
designated Green Belt approved in 2006.
8.2 Sections 25(1) (a) and 37(2) of the Town and Country Planning (Scotland) Act 1997 require
that this application be determined in accordance with the development plan unless material
considerations indicate otherwise. The application is of a local nature and the policies of the
North Lanarkshire Local Development Plan 2022 would directly apply to the assessment. There
are no NPF4 policies that would affect or change an assessment of this proposal against the
requirements of the local development plan polices in this case. Therefore, the proposal will be
assessed primarily under the policies of the North Lanarkshire Local Development Plan 2022
8.3 North Lanarkshire Local Development Plan (2022)
PP 4 POLICY Purpose of Place
North Lanarkshire Council will protect the setting of communities, support regeneration by
directing growth to urban areas, protect natural assets and provide a high-quality environment,
by promoting a Green Belt as defined on the Promote Map.
Page 57 of 88

Page 58

North Lanarkshire Council will support developments for agriculture, forestry, recreation, or
developments that need a non-urban location, including, where appropriate, Visitor Economy
related development.
Where specified by this Policy, applicants will normally be expected to provide the identified
appraisals or assessments, which should be submitted with any planning application to allow
consideration of the proposal.
The purpose of the Green Belt is to protect the setting of communities, support regeneration by
directing growth to urban areas, protect natural assets and provide a high-quality environment.
North Lanarkshire Council will encourage development appropriate for a Green Belt location by
resisting development that is not for agriculture, forestry, recreation, tourism, or needs a Green
Belt location, whilst allocating appropriate land for urban expansion. Regarding development
that needs a Green Belt location, the need will be balanced against any adverse effects on the
purposes of the Green Belt.
8.4 While the Council will resist other forms of development, through the full range of Policies in
the Plan. In this instance the applicant is proposing to replace a historic non-conforming use
(sui generis) with another non-conforming use sui generis. Both uses clearly do not conform
with Green Belt policy a matter which the applicant has not attempted to dispute. That being
the case assessment of the proposed change and impacts through the limits defined in the
Amount of Development policy becomes inconsequential being a previously developed
vacant/brownfield site used for a sui generis use which has many similarities with the proposed
(which is also sui generis). The application is therefore determined on Environmental and
Design Qualities and other material considerations.
8.5 The site is a vacant site within the green belt and its reuse for the proposed use is considered
to comply in principle with the green belt policies in NPF4 and the Local Development Plan and
with NPF4 Policy 9 reuse of vacant and derelict land and empty buildings subject to an
assessment against the LDP Environmental and Design Qualities (EDQ 1-3)   
8.6 Whether the change is appropriate therefore comes down to the nature and scale of the
development and whether the proposal is an intensification of use. This is determined by the
following design policies:
EDQ1 Site Appraisal,
EDQ2 - Specific Features for Consideration,
EDQ3 - Quality of Development.
8.7 The Local Development Plan identifies distinct Land Use Character Areas within North
Lanarkshire. Development proposals should relate well to the existing setting and avoid
adverse impact on existing or proposed properties. Appraising the existing features of a site
and how it relates to its surroundings is an important first step in ensuring this.
8.8 Policy EDQ1 Site Appraisal states that a proposed development will be appraised in terms of
the site and its surroundings to ensure it will integrate successfully into the local area and avoid
harm to neighbouring amenity. The matters to be addressed in the appraisal include
surrounding Land Use Character Area. In this respect while the site lies within the Green Belt
it is an area of Green Belt that has been developed for a bus garage. As such, the introduction
of a traffic management depot where existing buildings will either be demolished or repurposed
will not give rise to a significant loss of existing levels of amenity. The site therefore can be
integrated successfully into the local environs avoiding harm to neighbouring amenity and is
therefore supported by Policy EDQ1.
Page 58 of 88

Page 59

8.9 Policy EDQ2 (Special Features for Consideration) does not generally apply as it refers to
specific features on appeal sites or within the proximity such as Health and Safety Executive
Consultation Zones, Flood Risk, Air Quality/Noise Quality Management Areas. Here are no
significant constraints identified under Policy EDQ2 (Special Features for Consideration).
8.10 Policy EDQ3 - Quality of Development - only permits development where high standard of site
planning and sustainable design and development are achieved. This includes a number of
matters appropriate to the site from the various sub paragraphs stated in Policy EDQ3. The
application in retaining site structures and demolishing others is able to achieve acceptable
standards of site planning and sustainable design required by Policies EDQ 1 and EDQ 3.
Similarly, the applicant has confirmed that drainage arrangements will make provision for
sustainable drainage of surface water. It is recommended that should members be minded to
approve a suitable planning condition is attached.
8.11 The applicant's justification and supporting information for a traffic depot, when measured
against of the criteria within the polices of the Local Development Plan and other material
considerations presents an acceptable development while its Green Belt location precludes
alignment with this policy in terms of supporting the principle of Green Belt appropriate use. As
a historic non-conforming use and subsequent replacement use is not considered significantly
material in that it does not undermine the robustness of Green Belt policy. 
9. Conclusion
9.1 Following detailed consideration of the proposal, it is considered that while proposal does not 
comfortably accord with the Green Belt policies in the development plan development plan. A 
special case has been presented for the siting of the proposed development within the Green 
Belt. The site has been developed and is currently vacant and partially derelict.  It is 
considered that the reuse of this previously developed and vacant site represents an 
acceptable departure from the plan in this instance. It should also be noted that no objections 
were received following an advert in the local press. Therefore, it is recommended that 
planning permission be approved for the reasons 
Page 59 of 88

Page 60

Application No:  
25/00219/S42
Proposed Development: 
Section 42 application to vary condition 11 (timing of
submission of landscaping scheme) of planning permission
21/01275/FUL for Roadside Services Area Comprising Petrol
Filling Station, Ancillary Retail Unit, Drive-Thru (Class 3) Units,
HGV And Car Parking Areas, Associated Facilities,
Landscaping, Infrastructure Works And New Junction Access 
Site Address: 
2 Hornshill Court
Stepps
G33 6QU 
Date Registered: 
25th March 2025 
Applicant:
EG On The Move
Waterside Head Office
Haslingden Road
Blackburn
BB1 2FA 
Agent:
N/A
Application Level:
Major Application 
Contrary to Development Plan:
No
Ward:   
05 Stepps, Chryston And Muirhead 
John McLaren, Josh Cairns, Claire Louise
Williams
Representations:
3 letter(s) of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: Given the minor nature of the changes proposed by the Section 42
application to the wording of Condition 11, which relate only to the timing of the submission of
a detailed planting timetable for the approved landscaping scheme, the proposal is considered
to accord with the development plan and that of the requirements of the relevant placemaking
policies. 
Page 60 of 88

Page 61

Reproduced by
permission of the
Ordnance Survey on
behalf of HMSO. ©
Crown Copyright and
database right 2009.  All
rights reserved.
Ordnance Survey
Licence number
100023396.
Planning Application: 25/00219/S42 
Name (of applicant): EG On The Move
Site Address: 2 Hornshill Court
Stepps
G33 6QU
Development: Section 42 application to
vary condition 11 (timing of submission
of landscaping scheme) of planning
permission 21/01275/FUL for Roadside
Services Area Comprising Petrol Filling
Station, Ancillary Retail Unit, Drive-Thru
(Class 3) Units, HGV And Car Parking
Areas, Associated Facilities,
Landscaping, Infrastructure Works And
New Junction Access   
Page 61 of 88

Page 62

Proposed Conditions:- 
1. That, except as may otherwise be agreed in writing by the Planning Authority, the
development shall be implemented in accordance with drawing numbers:- 
AL(0)001 RevA; 
AL(0)002 Rev A; 
AL(0)011; 
AL(0)012RevB; 
AL(0)003RevC; 
AL(0)004RevG; 
AL(0)101RevE; 
AL(0)102RevB; 
AL(0)103RevB; 
AL(0)104 RevD; 
AL(0)201RevB; 
AL(0)202RevB; 
AL(0)203RevA; 
AL(0)204 RevB; 
AL(0)301RevA; 
AL(0)302RevA; 
AL(0)303RevA; 
AL(0)304RevA; 
501 RevA 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That the Petrol Filling Station and Ancillary UNIT 1 herby approved shall come into operation
prior to the occupation and operation of either UNIT 2 or UNIT 3. 
Reason: To define and ensure delivery of key aspects of the permission in accordance with
the development plan. 
3. That within 3 months of the date of this permission a revised site layout plan (based on
approved plan AL(0)004Rev G shall be submitted to the Planning Authority for its written
approval which shall show: 
• The reconfiguration of the Jet Wash/Air/Vacuum Bay facility to improve manoeuvrability
and avoid conflict points with the HGV fuel area. 
• Full details of cycle parking provision 
• The 3m cycle/footway extended eastwards to the northeastern end of the site boundary. 
Reason: In the interest of vehicle and pedestrian safety 
4. Prior to the commencement of development, full details of the proposed site access, generally
as illustrated on ECS Drawing No.21033_007, shall be submitted to, and approved by the
Planning Authority after consultation with Transport Scotland. Thereafter, and prior to the
occupation of any part of the development, the site access shall be constructed in accordance
with the approved plans. 
Reason: To ensure that the layout of the site vehicular access complies with current design
standards. 
5. That, unless otherwise agreed in writing, prior to any part of the development first coming into
operation the vehicular access, internal road layout, parking areas, footpaths and cycleways
shall be finished to final wearing course to the satisfaction of the Planning Authority. 
Reason: In the interests of vehicle and pedestrian safety. 
Page 62 of 88

Page 63

6. That BEFORE any works of any description start, unless otherwise agreed in writing with the
Planning Authority, a comprehensive site investigation report shall be submitted to and for the
approval of the said Authority. The investigation must be carried out in accordance with
current best practice advice, such as BS 10175: 'The Investigation of Potentially
Contaminated Sites' or CLR 11. The report must include a site specific risk assessment of all
relevant pollution linkages and a conceptual site model. Depending on the results of the
investigation, a detailed Remediation Strategy may be required and this strategy will include
details of the schedule for validation reporting to confirm that the remediation works have
been carried out before houses are occupied. 
Reason: To establish whether or not site decontamination is required in the interests of the
amenity and wellbeing of future residents. 
7. That any remediation works identified by the site investigations required in terms of Condition
6 shall be carried out to the satisfaction of the Planning Authority. A certificate (signed by a
chartered Environmental Engineer) shall be submitted to the Planning Authority in accordance
with the agreed schedule of validation reporting confirming that any remediation works have
been carried out in accordance with the terms of the Remediation Strategy. 
Reason: To ensure that the site is free of contamination in the interests of the amenity and
wellbeing of future residents 
8. That prior to any works commencing on site full details of the proposed surface water
drainage scheme shall be submitted to the Planning Authority. For the avoidance of doubt the
scheme shall be based on the surface water drainage scheme as described in report titled
Drainage Strategy and Flood Risk Assessment Part A produced by Goodson Associates
dated July 2021 and as shown on approved drawing no 501 Rev A Proposed Drainage
Layout. The scheme's compliance with the principles of Sustainable Urban Drainage Systems
(SUDS) in terms of the relevant CIRIA Manual and other advice published by the Scottish
Environment Protection Agency (SEPA) shall be certified by a Chartered Civil Engineer
experienced in drainage works. 
Reason: To ensure that the drainage scheme complies with best SUDS practice to protect
adjacent watercourses and groundwater from pollution. 
9. That the detailed drainage scheme approved in condition 8 above shall be implemented
contemporaneously with the development in so far as is reasonably practical. Within three
months of the construction of the SUDS, a certificate (signed by a Chartered Civil Engineer
experienced in drainage works) shall be submitted to the Planning Authority confirming that
the SUDS have been constructed in accordance with the relevant ClRlA Manual and the
approved plans. 
Reason: To safeguard adjacent watercourses and groundwater from pollution 
10. That PRIOR to the first occupation of any unit within the development, the applicant shall
provide written confirmation to the Planning Authority that all the requirements of Scottish
Water can be fully met to demonstrate that the development will not have an impact on their
assets, and that suitable infrastructure can be put in place to support the development. 
Reason: To ensure the provision of satisfactory drainage arrangements 
11. That within 3 months of the date of this permission a detailed timetable for the planting works
included in drawing Landscape Layout 01 REvB shall be submitted for the written approval by
the Planning  Authority. Thereafter the approved landscaping shall be completed in
accordance with the agreed planting timetable. Furthermore, any trees, shrubs, or areas of
grass which die, are removed, damaged, or become diseased, within five years of the site
becoming operational, shall be replaced within the following year with others of a similar size
and species. 
Reason: To ensure the timely provision of suitable landscaping to ensure that the
Page 63 of 88

Page 64

development sits satisfactorily within the wider landscape. 
12. That prior to works commencing on site, a management and maintenance scheme shall be
submitted to, and approved in writing by the Planning Authority, and it shall include proposals
for the continuing care, maintenance and protection of:- 
(a) the proposed footpaths; 
(b) the proposed parking areas; 
(c) the proposed external lighting; 
(d) the proposed grassed, planted and landscaped areas; 
(e) the proposed fences within the site (including the 2.5m acoustic fence). 
Reason: To ensure that adequate long term management and maintenance provisions are in
place in the interests of visual amenity. 
13. That BEFORE completion of the development hereby permitted, the management and
maintenance scheme approved under the terms of condition 12; shall be in operation. 
Reason: To ensure that adequate long term maintenance provisions are in place in the
interests of visual amenity. 
14. That prior to any works starting on site (including any site clearance works) the Extended
Phase 1 Habitat Survey shall be updated to determine the presence of any statutorily
protected species, the said survey shall thereafter be submitted to and approved in writing by
the Planning Authority before any development commences on that particular part of the site.
As a result of the studies, should any mitigation measures be required for any protected
species, this shall be implemented in accordance with a species protection plan agreed in
writing with the Planning Authority in consultation with Nature Scot before works commence
on the site. 
Reason: To ensure compliance with The Conservation (Natural Habitats & c.) Regulations
1994 (as amended); the Wildlife and Countryside Act (1981) as amended; the Protection of
Badgers Act 1992 (as amended); and the Nature Conservation (Scotland) Act 2004.' 
15. That prior to any works commencing on site (including any site clearance works) a Working
Method Statement in respect of Fossorial Water Voles shall be submitted to the Planning
Authority for its approval together with full details of the Ecological Clerk of Works. For the
avoidance of doubt this shall include the following actions as outlined in the Ecological
Addendum by Rachel Hacking Ecology Ltd. dated 14th January 2022: 
• Prior to site clearance commencing a suitable experienced ecologist (appointed as an
Ecological Clerk of Works (ECoW)) will deliver a toolbox talk to the site personnel,
detailing Water Vole identification, legislation and the Working Method Statement. 
• Prior to site clearance commencing the ECoW will walk over the entire site searching for
evidence of Water Vole. If Water Vole is found to be present on site, work will cease and
a Mitigation Strategy will be implemented and agreed with the Planning Authority in
consultation with Nature Scot to avoid or translocate the Water Voles. 
• The site clearance will take place from North to South. 
• The initial site strip will be overseen by the ECoW. Any evidence of Water Vole
uncovered will be marked and work will cease at that location until such time that a
Mitigation Strategy is agreed with the Planning Authority in consultation with Nature Scot. 
• During the development, the site personnel will be aware of Water Vole identification and
if a Water Vole is seen at any time during the development, works will cease, the ECoW
will be contacted and a Mitigation Strategy shall be agreed with the Planning Authority in
consultation with Nature Scot. 
Page 64 of 88

Page 65

Reason: To ensure compliance with the Wildlife and Countryside Act (1981) as amended. 
16. That prior to commencement of development, a Construction Method Statement shall be
submitted to and approved by the Planning Authority. For the avoidance of doubt, the
Construction Method Statement shall cover: 
• Details of how the development will be phased 
• Details of the location of site compound and management facilities; 
• Details of construction access, parking and manoeuvring areas. 
Reason: To ensure the satisfactory phasing of the development. 
17. That prior to any works commencing on site a Construction Environmental Management Plan
(CEMP) shall be submitted to and approved by the Planning Authority. In the interest of
clarity, the CEMP should adequately characterise the risks that the construction works pose
to the water environment or the key environmental receptors and incorporate detailed
pollution prevention and mitigation measures for all construction elements potentially capable
of giving rise to pollution during all phases of construction and reinstatement after
construction in line with SEPA guidance. 
Reason: To ensure suitable pollution prevention measures are in place prior to construction to
minimise pollution risks arising from construction activities in order to protect the water
environment and ecological interests of the Garnkirk Burn SINC. 
18. That prior to any works starting on-site (including site clearance works) a detailed Dust
Mitigation Plan for the construction period shall be submitted for the written approval of the
Planning Authority. For the avoidance of doubt this shall reflect the findings of the Air Quality
Assessment by Miller Goodall Ltd dated 16th July 2021. 
Reason: In the interests of residential amenity. 
19. That prior to works commencing on Unit 2 or Unit 3 full details of the odour control measures
and associated plant shall be submitted to the Planning Authority for its written approval. For
the avoidance of doubt these shall reflect the findings of the Air Quality Assessment and
Noise Assessment carried out by Miller Goodall Ltd dated 16th July 2021 and shall be fully
operational prior to occupation. 
Reason: In the interests of residential amenity. 
20. That prior to the Petrol Filling Station, HGV parking area and ancillary UNIT1 first coming into
operation the 2.5m high acoustic fence detailed in the Noise Assessment carried out by Miller
Goodall Ltd dated 16th July 2021 and shown on the approved plans shall be constructed and
a verification certificate (signed by a suitably qualified professional) shall be submitted to the
Planning Authority. 
Reason:  In the interests of amenity 
21. Prior to the commencement of any part of the development hereby permitted, a scheme of
advance directional signage shall be submitted to, and approved by the Planning Authority,
after consultation with Transport Scotland. Thereafter, and prior to the occupation of any part
of the development, the scheme of advanced directional signage shall be installed in
accordance with the approved plans. 
Reason: To maintain safety for both the trunk road traffic and the traffic moving to and from
the development. 
Page 65 of 88

Page 66

Background Papers: 
Consultation Responses: 
Traffic & Transportation 
Environmental Health (including Pollution Control) 
NLC Greenspace 
Transport Scotland 
Contact Information: 
Any person wishing to inspect these documents should contact Susan Hunt at 01236 632500 
Report Date: 
31 July 2025 
Page 66 of 88

Page 67

APPLICATION NO. 25/00219/S42 
REPORT 
1.  Site Description 
1.1 The application site lies to the south of Junction 3 (Hornshill) roundabout of the M80 to the
North East of Stepps. The site is irregular in shape but best described as roughly rectangular
extending to approximately 2.2 hectares in area. The site has an undulating landform and is
made up of rough grassland (generally marshy to the north and more improved rough grazing
to the south) with scrub vegetation and broken hedgerows running across the site. The
northern boundary is delineated with wooden fencing, the western boundary has remnants of
post and wire fencing together with individual mature trees adjacent to the former Hornshill
Farm site with the eastern and southern boundaries not physically delineated. The
roundabout to the north sits at a slightly higher level than the site, the M80 sits lower than the
site in a cutting and the site itself generally falling in level from the north west to the southern
boundary. 
1.2 The site is bound to the north by Junction 3 (Hornshill) roundabout of the M80 from which it
would take vehicular access. The A806 road lies to the east with intervening rough grass land
bounding the site. To the south is rough grassland beyond which is the Garnkirk Burn lined by
mature woodland known locally as Bluebell woods and designated as a Site of Importance for
Nature Conservation beyond which is the Gateside Farm housing development. The western
boundary is lined with a series of individual mature trees adjacent to the track forming part of
Right of Way (SS95) and the broken fence line of the former Hornshill Farm now demolished
and site cleared. 
2.  Proposed Development 
2.1 The proposed Roadside Services Area is located on the southern side of the M80 but would
serve both directions of travel on the motorway via Junction 3 Hornshill Interchange. The
development includes a Petrol Filling Station with associated retail amenity building offering
ancillary services (such as food to go facilities, toilets and showers for road users and a small
area of convenience/basket shopping goods); Two stand alone drive-through units (coffee
shop and restaurant) together with associated car, coach and HGV parking, electric vehicle
charging station, landscaping and infrastructure, including new junction access. 
2.2 Planning permission was granted for this development under 21/01275/FUL in April 2022.
The applicant is now seeking permission, through a Section 42 application, to amend the
wording of Condition 11 of this consent, to alter when the detailed planting timetable is
submitted. 
2.3 Condition 11 of 21/01275/FUL currently reads as: 
11. That prior to works commencing on site a detailed timetable for the planting works
included in drawing Landscape Layout 01 Rev B shall be submitted for the written approval by
the Planning Authority.  Thereafter, the approved landscaping shall be completed in
accordance with the agreed planting timetable.  Furthermore, any trees, shrubs or areas of
grass which die, are removed, damaged, or become diseased, within five years of the site
becoming operational, shall be replaced within the following year with others of a similar size
and species. 
2.4 Initially the applicant sought permission to amend the wording to say instead: 
11. Save for the installation of the access and highway works the development shall not be
constructed until a detailed timetable for the planting works included in drawing Landscape
Layout 01 Rev B shall be submitted for the written approval by the Planning Authority. 
Thereafter, the approved landscaping shall be completed in accordance with the agreed
planting timetable.  Furthermore, any trees, shrubs or areas of grass which die, are removed,
Page 67 of 88

Page 68

damaged, or become diseased, within five years of the site becoming operational, shall be
replaced within the following year with others of a similar size and species. 
2.5 However, during assessment of the application discussions were held with the applicant
regarding the works required to bring forward delivery of the development and the timescale
for the submission of the detailed planting timetable that ensured delivery of the landscaping
in a timely manner as well as its protection during construction. As a result, permission is
sought to amend condition 11 to state: 
11. That within 3 months of the date of this permission, a detailed timetable for the planting
works included in drawing Landscape Layout 01 Rev B shall be submitted for the written
approval by the Planning Authority.  Thereafter, the approved landscaping shall be completed
in accordance with the agreed planting timetable.  Furthermore, any trees, shrubs or areas of
grass which die, are removed, damaged, or become diseased, within five years of the site
becoming operational, shall be replaced within the following year with others of a similar size
and species. 
2.6 No changes are proposed to the layout, design of the development or its landscaping that
were approved under application 21/01275/FUL. In summary the Petrol Filling Station and
ancillary shop (UNIT 1) would be located on the western portion of the site and consist of: 
• 6 fuel pumps stations under the main canopy
• fuel pumps for LGVs adjacent to the HGV Rest Area
• 10 vehicle charging stations
• jet wash bays
• 2 Air, Water & vacuum bays
• Petrol Filling Station Kiosk and ancillary class 1 retail units with toilet facilities
• HGV Rest Area and carparking 
2.7   This building would have a footprint of approximately 38.6m by 25.5m (984 sqm) in a 
contemporary design with shallow mono pitch (a height of 6.5m along the principal elevation 
and 4.7m to the rear). It would be finished in light brown and dark grey cladding panels, 
composite metal panel roof, and grey aluminium glazed curtain walling. 
2.8 The stand-alone drive through restaurant (UNIT 2) and Coffee Shop (UNIT 3) would be
located to the eastern side of the access road with associated car parking. The drive through
restaurant (UNIT 2) measures approximately 11.5 m by 28.5m with a footprint of 333.5sqm
(including the enclosed external yard). The building is also of a contemporary design, utilising
shallow mono pitches on the roof structure (highest point 5.2m on the principal elevation to
lowest point of main roof structure 4.5m). The building would be finished in weatherboard
panelling with a palette of muted greys, taupe and white along with accent colour blocks, the
roof would be of a grey ply material. The principal elevation would have glazed curtain walling. 
2.9 The drive through coffee shop (UNIT 3) measures 21.5m by 10.5m with a footprint of 215.5
sq.m (including an enclosed external yard and serving projection). Again, in a contemporary
design with a flat roof (3.9m in height) with roof projection feature (6.9m in height). The
building would be finished in a mix of concrete fibre and timber cladding and aluminium
glazed curtain walling. 
3.  Applicant’s Supporting Information 
3.1  In support of the S42 application the applicant has provided the following information: 
• Supporting Letter
• Location Plan 
3.2  The applicant previously submitted the following documents in support of the original
application: 
Page 68 of 88

Page 69

• Design and Access Statement
• Planning Statement
• Pre-Application Consultation Report
• Transport Assessment with appended Parking Technical Note
• Noise Assessment
• Air Quality Assessment
• Extended Phase 1 Habitat Survey (with further Ecological Addendum)
• Drainage Strategy & Flood Risk Assessment
• Lighting Report
• Site Investigation Report
• Tree Survey
• Landscaping Plan
• Landscape Appraisal 
4.  Site History 
4.1    Planning application 05/01821/OUT for the Construction of a Motorway Services Area was
submitted in November 2005 and subsequently refused in December 2008. The decision was
appealed, and the appeal was dismissed in 2009 as it was considered contrary to the
provisions of the then local plan. 
4.2    An Environmental Screening Opinion (21/00636/EIASCR) under the terms of the Town and 
Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017 was 
issued in April 2021 which concluded that a formal Environmental Impact Assessment would 
not be required for the proposed Roadside Services Area on this site. 
4.3    Planning application 21/01275/FUL for the construction of a Roadside Services Area was 
granted planning permission at Planning Committee on 22 April 2022. This was after the site 
layout was amended, including a reduction to the development footprint and the proposed 
landscaping around the site was enhanced. This Section 42 application would accord with the 
approved site layout and landscaping plan associated with 21/01275/FUL as it seeks 
permission to solely alter the wording of condition 11 (landscaping) in relation to the timing of 
its submission. 
5    Development Plan 
5.1 The Development Plan consists of National Planning Framework 4 (NPF 4) and the North 
Lanarkshire Local Development Plan (LDP). NPF 4 was adopted by the Scottish Parliament in
February 2023 and prevails over any policies in the Local Development Plan that are
incompatible with its aims and objectives.  The policies relevant to the application are: 
NPF4 
• Policy 1 - Tackling the Climate and Nature Crises
• Policy 2 - Climate Mitigation and Adaptation
• Policy 3 – Biodiversity
• Policy 4 – Natural Places
• Policy 6 - Forestry, Woodland and Trees
• Policy 12 - Zero Waste
• Policy 13 - Sustainable Transport
• Policy 14 - Design, Quality and Place
• Policy 18 - Infrastructure First
• Policy 22 - Flood Risk and Water Management
• Policy 23 - Health and Safety
• Policy 27 – City, Town, Local and Commercial Centres 
North Lanarkshire Local Development Plan 2022 
• PROM ID1 – Transport Improvements
Page 69 of 88

Page 70

• CI POLICY - Contributions to Infrastructure
• PROT A – Natural Environment and Green Network 
• EDQ1- Site Appraisal
• EDQ2 – Specific Features for Consideration
• EDQ3 – Quality of Development 
6. Consultations 
6.1 Transport Scotland was consulted and has no objection to the application.  The conditions
attached to the original permission 21/01275/FUL regarding access and signage shall be
carried forward to any s.42 permission. 
6.2 NLC Protective Services was consulted and has no objection subject to conditions being
applied in relation to site investigations, remediation, noise, odour, lighting, dust and securing
any required mitigation measures.  The conditions attached to the original permission
21/01275/FUL relating to these issues shall be carried forward to any s.42 permission. 
6.3 No issues were raised by NLC Greenspace or Traffic and Transportation in respect of this
application and conditions applied to the original consent to address their requirements are
therefore carried forward again. 
7. Representations 
7.1 Following standard neighbour notification and press advert procedures 3 representations 
have been received objecting to the application and the points raised can be summarised 
below: 
a) The original and proposed wording of Condition 11 was not made publicly available 
Response: The letter submitted with the application detailing the proposed wording was not
made publicly available on submission; however, it was made publicly available upon receipt
of this objection and the deadline for objections extended accordingly to ensure the proposed
alteration was clearly available and that all interested parties could make an informed
representation should they wish. 
b) The application should be considered by the Planning Committee 
Response: This type of application cannot be determined under delegated powers and as
such requires to be presented to the Planning Committee for determination. 
c)  Removing the pre-commencement requirement from Condition 11 leaves no clear
or enforceable deadline for when the landscaping timetable must be submitted or
implemented.    The following alternative wording is therefore suggested to
preserve the original intent of the condition ‘The landscaping timetable shall be
submitted within 2 months of this approval and implemented in full accordance
with the approved scheme prior to first use of the site or any further development’. 
Response: Consideration has been given to this suggested alternative wording for condition
11.  It is considered that a set period of time for the submission of the detailed planting
timetable would be a more appropriate and clearer trigger than the assessment and
monitoring of the progress of the development’s vehicular access works.  Discussions were
held with the applicant on this basis and it is agreed that a time period requiring the
submission of the detailed planting timetable be set at within 3 months of the date of any
permission would be appropriate and reasonable.  The purpose of the detailed planting
timetable is to secure the landscape buffer in early course (following any earthmoving works)
and ensure that the landscaping be implemented contemporaneously with the construction
programme of the site, but that it not be damaged during any early stages in preparation for
the development of the site.  The remainder of the wording of Condition 11 would remain the
same as 21/01275/FUL which would require the approved landscaping scheme to be fully
Page 70 of 88

Page 71

implemented and any diseased or dead landscaping to be replaced within the following 5
years.   
7.2 Stepps & District Community Council objected to the application. In summary it was
considered that altering the wording would allow the development not to implement the
planting which was unacceptable as the planting was introduced to safeguard visual amenity
and integrate the development within the landscape. 
Response: As noted, above the altered wording would still ensure that the developer
implemented the landscaping scheme in a satisfactory manner.  The landscaping scheme is
considered integral to the successful development of this site.  The altered wording as now
proposed requires the submission of the detailed planting timetable within 3 months of the
date of permission being granted and secures the implementation of the approved
landscaping scheme in a timely manner. 
8 Planning Assessment 
8.1 Sections 25(1) (a) and 37(2) of the Town and Country Planning (Scotland) Act 1997 require
the proposal to be determined in accordance with the development plan unless material
considerations indicate otherwise. The Development Plan is made up of National Planning
Framework 4 (NPF4) and the adopted North Lanarkshire Local Development Plan (LDP). In
terms of this application, Section 42 of the Town and Country Planning (Scotland) Act 1997
requires to be considered. It allows for the determination of applications to develop land
without compliance with conditions previously attached to existing planning consents and
although the application primarily seeks to change the wording of one condition, its approval
would also have the effect of renewing the consent again.  Therefore, it is necessary to
consider whether there have been any changes in planning policy since the previous
permission was granted that would have a bearing on approval of the application. On this
basis the introduction of NPF4 in February 2023 and the North Lanarkshire Local
Development Plan (LDP) in July 2022 means the policy requirements of these documents
need to be assessed. 
National Planning Framework 4 
8.2 NPF4 Policy 1 Tackling the Climate and Nature Crises states that when assessing
development proposals, significant weight will be given to tacking these crises and Policy 2 -
Climate Mitigation and Adaptation that development should minimise greenhouse gas
emissions and promote energy efficiency and renewable energy.  The application site is an
identified site within the LDP. It is therefore considered to be a sustainable site that supports
the development plan’s spatial strategy of compact urban growth. It is also strategically
located within the existing road network. As such it can be seen to be compatible with the
principles of Policies 1 and 2 of NPF4. 
8.3 In terms of the natural environment NPF4 Policy 3 Biodiversity requires major development
proposals to conserve, restore and enhance biodiversity; Policy 4 Natural Places requires
natural places to be protected and restored and that natural assets are managed in a
sustainable way and Policy 6 - Forestry, Woodland and Trees that existing woodland areas
are protected and enhanced.  The Extended Habitat Survey submitted with the original
application shows limited ecological value across the site due to its current use for agricultural
grazing.  In the absence of any matrix to assess Biodiversity Net Gain it is considered that the
landscaping scheme, secured by condition, will offer a proportionate net gain through the
introduction of additional habitat rich tree, shrub and grass species planting thereby
complying with Policy 3 as well as aligning with the requirements of Policies 4 and 6 of NPF4. 
8.4 NPF4 Policy 12 Zero Waste seeks to reduce, reuse or recycle materials in line with waste
hierarchy.  Whilst no detail has been provided on this aspect within the application it is
recognised that the site has an existing planning permission in place 21/01275/FUL and this
application seeks minor changes which would not materially alter the waste generation,
resource use, or waste infrastructure implications of the previously consented scheme.
Therefore, the proposals are considered acceptable.
Page 71 of 88

Page 72

8.5 NPF4 Policy 13 Sustainable Transport sets out to encourage, promote and facilitate
developments that prioritise sustainable travel. The nature of the proposed development as a
Roadside Services Area requires that it be located adjacent to the Strategic Road Network. It
is recognised that the site is a greenfield one, some distance from the village of Stepps.
However, it is identified as a Transportation Opportunity within the LDP and has been
assessed as a sustainable site that supports the development plan’s spatial strategy of
compact urban growth. Given the nature of the type of development proposed it has to be
strategically located within the existing road network and the siting of this proposal at this
location is supported by the LDP. As such it is seen as compatible with the principles of Policy
13. 
8.6 NPF4 Policy 14 Design, Quality and Place states that development proposals should be
designed to improve the quality of an area whether in urban or rural locations and regardless
of scale.  This matter was subject to extensive discussion in the assessment of the original
planning application 21/01275/FUL and found to be acceptable. Significant weight is given to
planning permission 21/01275/FUL int this regard.  This will be discussed in more detail in
terms of the associated policies applicable within the LDP (EDQ1-3) below; however, it is
considered that the development complies with Policy 14. 
8.7 NPF4 Policy 18 Infrastructure First states that development proposals which provide (or
contribute to) infrastructure in line with that identified as necessary in LDPs and their delivery
programmes will be supported subject to appropriate mitigation of any impacts. The site is
identified as a Transportation Opportunity within the LDP and planning consent was granted
in 2022 for this development. Subject to an assessment of the impact of the proposed
amendment to the wording of condition 11 of that consent (21/01275/FUL) to ensure there is
no adverse impact it is considered that the development in principle complies with Policy 18. 
8.8 NPF4 Policy 22 Flood Risk and Water Management supports development that will not
increase the risk of surface water flooding to others or itself be at risk and to manage all rain
and surface water through Sustainable Urban Drainage Systems (SUDS) whilst minimising
impermeable areas. A suitable drainage scheme was submitted with the original planning
application 21/01275/FUL and secured by conditions. Significant weight is attached to this in
the assessment of this Section 42 application.  This matter is further discussed in terms of the
LDP policies and the associated guidance applicable within SPG 09 (Flooding & Drainage)
below; however, it is considered that the development complies with Policy 22. 
8.9 NPF4 Policy 23 Health and Safety seeks to protect people and places from environmental
harm. Mitigate risks arising from safety hazards and encourage, promote and facilitate
development that improves health and wellbeing. NLC Protective Services have no objection
to this Section 42 application. Notwithstanding, conditions attached to the original application
21/01275/FUL to control noise, odour, lighting, potentially adverse effects during construction
and ground conditions are attached again to ensure that the potential for any environmental
harm is controlled. These matters are discussed in turn in terms of the associated LDP
policies below; however, it is considered that the development complies with Policy 23. 
8.10 NPF4 Policy 27 City, Town, Local and Commercial Centres seeks to encourage, promote and
facilitate development in our city and town centres, recognising that they are a national asset.
This is to be achieved by applying the Town Centre First Approach to help centres adapt
positively to long-term economic, environmental and societal changes and by encouraging
town centre living. Policy 27 part (d) states that Drive-thru developments will only be
supported where they are specifically supported in the LDP.  Clarification on this policy was
subsequently provided in a letter from the Chief Planner dated 8 February 2023 which
advises that that this policy wording does not represent a moratorium or ban on drive thru
development but rather was intended to ensure that this type of development is considered as
an integral part of the wider development plan and that each application be considered on its
own merits. It is acknowledged that there are no sites specifically designated in the North
Lanarkshire Local Development Plan for drive through facilities and no other Landscape
Character Areas specifically support such a proposal.  Given the support given by PROM 1D1
in the North Lanarkshire Local Development Plan it is not considered that the application
Page 72 of 88

Page 73

requires to be assessed in terms of sequential approach or impact on any town centres. The
Drive-Thru elements of the proposals are considered reasonable in terms of this location and
have been previously approved under the terms of the original application 21/01275/FUL.  It is
therefore considered that the development complies with Policy 27. 
North Lanarkshire Local Development Plan 2022 (Adopted) 
8.11 The original application 21/01275/FUL was assessed against the, then emerging, North
Lanarkshire Local Development Plan but could only be given limited weight as a material
consideration at that time as the plan had still to be adopted.  The proposal now requires to
be assessed against these policies. 
8.12 Policy PROM ID1 Transport Improvements supports transport improvements identified and
delivered through a number of Regional and Strategic Transport Strategies.   Spatially, the
site is identified as a Transportation Opportunity.  The Policy lists projects identified in the
Area Strategies. Whilst not specified for a Motorway Services Area (MSA) development,
further clarification on the acceptance of a MSA type of development on the site is provided
by the North Lanarkshire Local Development Plan Report of Examination published in May
2021. The Examination Report advises that the Modified Proposed Plan’s Transport
Improvement Area designation continues to reflect the removal of the site at Hornshill from
the Green Belt and its designation as a Motorway Service Area. The Report of Examination
also confirms that the implementation of an MSA at Hornshill is no longer a Development Plan
matter, that the site’s status has not changed from the NLLP and that the land remains
allocated for a MSA in the North Lanarkshire Local Development Plan. In terms of policy
PROM 1D1 it is considered that the proposed development is compatible with the designation
for a Motorway Services Area with the policy position noted above. Significant weight is also
given to the original planning permission 21/01275/FUL for the site. 
8.13 Given the above assessment of PROM 1D1 it is not considered that the application requires
to be assessed in terms of sequential approach or impact on any town centres. 
8.14 Policy CI reflects that of DSP3 in the previous North Lanarkshire Local Plan where no
contributions were identified through the consultation process in respect of the original
application 21/01275/FUL. Given the previous approval and the nature of this S42 application,
which is limited to the wording of condition 11, no contributions have been identified and the
application is considered acceptable. 
8.15 Policy PROT A 5 indicates that any development that significantly affects a species protected
by law will only be permitted where an appraisal has demonstrated that the protected species
would not be compromised or any significant adverse effects on the protected species are
mitigated through planning condition/planning agreement.  An Extended Phase 1 Habitat
Survey was submitted in support of the original application and concluded that the site offers
limited ecological value with no evidence of protected species. Due to the proximity to the
Garnkirk Burn the survey recommends that a Construction Environmental Management Plan
be put in place. NLC Greenspace reviewed the Extended Phase 1 Habitat Survey and
advised that if works have not commenced within 1 year of the survey work being undertaken
updated surveys would be required and agree that a Construction Environmental
Management Plan be secured. This requirement was secured by condition on the original
permission 21/01275/FUL and should remain. 
8.16 NLC Greenspace also advised that as fossorial water vole had been recorded in the Stepps
area that a survey should be undertaken prior to planning permission being issued. The
applicant submitted a further Addendum which concludes that no evidence of fossorial
mammals or any other evidence of water voles was found across the site. It also notes that
the site falls outwith the Grassland Water Vole Trigger Area. A Working Method Statement is
recommended and includes site clearance works being overseen by an Ecological Clerk of
Works. Given the findings of the Ecological Addendum a Working Method Statement and
appointment of an Ecological Clerk of Works was secured by condition on the original
permission 21/01275/FUL and this condition should remain. 
Page 73 of 88

Page 74

8.17 On this basis, it is considered that the application complies with policy PROT A5. 
8.18 The Environmental and Design Qualities policies EDQ1-3 within the North Lanarkshire Local
Development Plan apply to this application. Policies EDQ1-EDQ3 largely reflect criteria
contained in Policy DSP4 of the North Lanarkshire Local Plan against which the application
was originally assessed; however, to ensure completeness of the assessment of this
application they are taken in turn below: 
8.19 The supporting Planning Statement accompanying the original planning application provides
an acceptable site appraisal upon which the design has been developed and therefore
complies with EDQ1. 
8.20 In terms of EDQ2 a Site Investigation requires to be carried out prior to any works starting on
site due to historic and surrounding land uses. The Site Investigation submitted concluded
that there were no risks associated with ground contamination or ground gas. The Site
Investigation was reviewed by NLC Protective Services and further queries were raised with a
further report submitted. Given the findings of the initial Site Investigation and nature of the
further queries standard ground conditions and remediation strategy conditions are attached
to the original permission 21/01275/FUL and these shall remain. The site does not fall within
any other EDQ2A, 2B or 2C categories. Any local infrastructure within or adjacent to the site
requires the applicant to resolve or relocate directly with the guidance of the relevant
infrastructure providers. 
8.21 In respect of Policy EDQ 3 - Quality of Development, the proposed siting, overall layout,
density, form, scale, height, massing, proportion, detailing, colour and materials, whilst
considered to be of standard commercial design, are considered commensurate with a
modern Roadside Services Area.  The proposed site is located on part of a much larger area
designated as a Transportation Opportunity within the surrounding green belt area and as
such careful consideration must be given to the setting of the development itself and its
relationship to the surrounding landscape. The setting of the proposed development was the
subject of extensive deliberation during the original planning application 21/01275/FUL
assessment process which resulted in a landscaping buffer along the southern and western
boundaries of the site. The proposed individual building designs are of a contemporary fairly
minimalist design and they relate sufficiently with each other within the site. The site is of such
distance to other buildings within Stepps that they would not be read immediately alongside
other built development. The scale and height are considered acceptable and take account of
the altered ground level within the site. It was considered that with an appropriate level of
landscaping the buildings can reasonably be accommodated within the site and the area in
general.  Given that the proposed development under consideration relates only to the
wording of condition 11 and that no alterations are proposed to the original approved design
and layout of the site, or that of its landscaping, the application is considered to accord with
this policy and acceptable. 
8.22 During the assessment of the original application it was noted that the site does not meet the
NLC Active Travel Strategy which seeks to reduce reliance on private car trips and encourage
and promote other active travel through walking, wheeling and cycling for everyday travel
(including to local amenities or places of employment) across North Lanarkshire as the
proposal lacks physical measures to facilitate cycling and walking to the site especially for
employees and as such is not considered a sustainable development. 
8.23 In terms of pedestrian access and footpath links discussions have been held with the
applicant regarding the possibility of connecting to the Right of Way (SS95) which runs
parallel to the site for a short distance along the western boundary. The Right of Way runs
north from Hornshill Farm Road by means of a rough track to the former Hornshill Farm site
before returning west to Lenzie Road. The track is rough with a stile in place that requires to
be traversed. Its route whilst fairly straight follows the topography of the surrounding land
dropping down to the Garnkirk Burn and rising up towards the site. The track is unlit, remote
from housing bound in part by heavy tree cover with poor passive surveillance. Whilst it may
be physically possible to connect to the track from the development site it may not be
considered to be a welcoming or safe route for pedestrians to the site in its current form.
Page 74 of 88

Page 75

8.24 Consideration was also given to providing pedestrian links from A806 to the east of the site.
There is no footpath alongside the A806 for its length from Cumbernauld Road to Junction 3.
The applicant has considered this option as part of the supporting Transport Assessment and
concluded that the creation of such a pedestrian link adjacent to the A806 would not be
possible due to the topography of the land to the west of the safety barrier, the presence of
mature trees and the need for third party land. 
8.25 The Transport Assessment addresses access by cyclists and it is noted that the site could be
reached by cycling via the road network along the A806 and then by the new roundabout arm
into the development site. 
8.26 Based on the above discussion it is acknowledged that the site is not served well by
pedestrian or cycle links which is contrary to the aims of the Council’s Active Travel Strategy;
however, given the policy support from PROM ID1 Transport Improvements of the LDP and
the previous approval through planning permission 21/1275/FUL it is not considered that this
issue alone would merit the refusal of this S42 application especially as no alterations are
proposed to the approved development.   The conditions attached to the original permission
21/01275/FUL however shall be carried forward to this S42 permission and these include the
extension of the cycle way and provision for cycle parking. 
8.27 The site is not located in an Air Quality or Noise Management Area. However potential
nuisance has been assessed. Given the nature of the proposed development the Air Quality
Assessment largely focused on vehicle trip generation to and from the site together with
movement within the site and concludes that the local air quality impact of emissions from
traffic associated with the proposed development is predicted to be negligible. The report also
considered impact from adverse cooking odours from the drive through restaurant and
recommends that a high level of odour control is required but adequate mitigation measures
can be provided to ensure odour has a negligible impact. The report recommends that dust
mitigation measures be utilised during construction. The report has been reviewed by NLC
Protective Services and found to be acceptable in terms of methodology and conclusions.
The recommended dust and odour control measures could be secured by condition.  The
conditions in relation to dust and odour attached to planning permission 21/01275/FUL shall
remain. 
8.28 In terms of Noise, the Noise Impact Assessment submitted with the original planning
application considered noise generating activities from the proposed development including
vehicle movements (with a particular focus on HGVs as this is considered to be the most
intrusive noise element), fuel pumps, reversing alarms, order points at drive through units.
The report has been reviewed by NLC Protective Services and found to be acceptable in
terms of methodology and conclusions. Mitigation measures including a 2.5m high acoustic
fence around the HGV parking area and details of plant compound areas can be secured by
condition. The report has been reviewed by NLC Protective Services and found to be
acceptable in terms of methodology and conclusions. The conditions relating to noise and
mitigation implementation attached to planning permission 21/01275/FUL shall remain. 
8.29 The Drainage Strategy and Flood Risk Assessment advises that foul water would discharge
to an existing combined sewer to the south of the site and that surface water drainage would
be designed in accordance with Sustainable Urban Drainage Systems principles incorporating
methods for treatment and attenuation of surface water prior to discharge to the Garnkirk
Burn watercourse. The standard conditions relating to the submission detailed drainage
drawings and the certified implementation of the scheme can be used to secure suitable
drainage across the site. The site is considered low risk in terms of flooding due to the
topography of the site and distance from watercourses. The conditions relating to control of
these matters attached to planning permission 21/01275/FUL shall remain 
8.30 It is noted that there are no watercourses within the site and that the nearest watercourse (the
Garnkirk Burn) lies approximately 180m to the south of the application site. The Extended
Phase 1 Habitat Survey recommends that a Construction Environmental Management Plan
be put in place during construction which can be secured by condition. The conditions relating
Page 75 of 88

Page 76

to the construction environmental management plant attached to planning permission
21/01275/FUL shall remain. 
8.31 Due consideration has been given to the representations received in relation to the
application and the proposed amended wording.  As the proposal relates only to the variation
to the wording relating to when the detailed planting timetable has to be submitted there is no
implication that the original approved landscaping scheme would be altered as a result or that
it would enable the developer not to implement the landscaping.  As discussed above the
altered wording has been amended to include a more specific timing requirement of
submission within 3 months of permission being granted and the remaining wording of the
condition unaltered to that attached to the original permission. 
8.32 In conclusion, the proposal has been assessed against the current development plan and its
policies and remains acceptable.  Significant weight is given to permission 21/01275/FUL in
reaching a conclusion in this assessment.  The minor alteration to the wording of Condition 11
affects only the timing of submission of the detailed planting timetable and is considered
acceptable. It is therefore recommended that permission is granted. 
Page 76 of 88

Page 77

Application No:  
25/00444/FUL
Proposed Development: 
Change of Use from Office to Class 1A (Shops, Financial,
Professional and Other Services) and Training Academy (In
Retrospect) 
Site Address: 
Unit 13
3 Wardpark Road
Wardpark
Cumbernauld
G67 3JZ 
Date Registered: 
27th May 2025 
Applicant:
Mr Richard Hamilton
46A Main St
Chryston
G69 9JX 
Agent:
Enspire Architecture Studio Ltd
Office 29, Alloa Business Centre
Whins Road
Alloa
Clackmannanshire
FK10 3SA 
Application Level:
Local Application 
Contrary to Development Plan:
Yes
Ward:   
04 Cumbernauld East 
Claire Barclay, Tom Johnston, Barry McCulloch,
Adam Smith,
Representations:
No representations received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The proposed development is considered to be a compatible use within this Business Centre
that can be accommodated without detriment to the primary function of the area. It is therefore
considered to be an acceptable departure to the provisions of NPF4 and Local Business Centres
Policies PP 2B and AD 2A of the North Lanarkshire Local Development Plan 2022 and is
considered to comply with polices EDQ 1 and EDQ 3 of the North Lanarkshire Local
Development Plan 2022. 
Page 77 of 88

Page 78

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 25/00444/FUL 
Name (of applicant): Mr Richard Hamilton
Site Address: Unit 13
3 Wardpark Road
Wardpark
Cumbernauld
G67 3JZ 
Development: Change of Use from Office
to Class 1A (Shops, Financial,
Professional and Other Services) and
Training Academy (In Retrospect)   
Page 78 of 88

Page 79

Proposed Conditions:- 
1. That the development hereby permitted shall be carried out strictly in accordance with the
approved details submitted as part of the application and no change to those details shall be
made without prior written approval of the Planning Authority. 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That the premises will be used solely as an aesthetics/hair and beauty salon and training
academy and for no other uses within Class 1A of The Town and Country Planning (General
Permitted Development) (Scotland) Order 1992 (or permitted changes from this class) and
should the use hereby permitted cease then the use of the premises will revert back to office
use (class 4) 
Reason: To define the permission. 
Background Papers: 
Consultation Responses: 
No consultations required 
Contact Information: Kirsten Devlin at esplanning@northlan.gov.uk or 01236 632487 
Report Date:  28th July 2025
Page 79 of 88

Page 80

APPLICATION NO. 25/00444/FUL 
REPORT 
1. Site Description 
1.1 The application site is Unit 13, 3 Wardpark Road, Wardpark, Cumbernauld. The site is set within
a well-established Local Business Centre. The wider area is characterised by industrial uses,
whereas this part of the Business Centre is characterised by an office building with multiple
individual units. A dance academy and yoga studio are also located within the building. 
2. Proposed Development 
2.1 Retrospective permission is sought for a Class 1A (shop), in this instance an aesthetics/hair
and beauty salon. The proposal also seeks permission for the premises to be utilised as a
training academy to meet demand for vocational training in the personal care sector and to
consolidate the business’s position as a leading provider of bridal, beauty and advanced
aesthetics. 
3.  Applicant’s Supporting Information 
3.1 The applicant has provided the following information in support of their application: 
• Appropriateness Statement, Business Plan & Impact Justification 
4. Site History 
4.1 There is no planning history associated with this address. 
5. Development Plan 
5.1 The development plan consists of National Planning Framework 4 (NPF4) and the North
Lanarkshire Local Development Plan (NLLDP) 2022. 
5.2 Given the nature and scale of this development the most relevant considerations are already
enshrined in the North Lanarkshire Local Development Plan policies.  NPF4 Policy 26: Business
and Industry is relevant to the application. 
5.3 In terms of the North Lanarkshire Local Development Plan 2022 the following policies are of
relevance: 
PP 2B Local Business Centres: Purpose of Place
AD 2B Local Business Centres: Amount of Development
EDQ1 Site Appraisal
EDQ3 Quality of Development 
6. Consultations 
6.1 Given the nature and scale of the proposal no consultations were required. 
7. Representations 
7.1 No representations have been received. 
Page 80 of 88

Page 81

8. Planning Assessment 
8.1 Under Section 25 of the Town and Country Planning (Scotland) Act 1997, planning decisions
must be made in accordance with the development plan unless material considerations indicate
otherwise.   
8.2 In terms of National Planning Framework 4 (NPF4), Policy 26: Business and Industry is of most
relevance. 
8.3 Policy 26 - Business and Industry states development proposals for business and industry will
be supported where they are compatible with the primary business function of the area. Other
employment uses will be supported where they will not prejudice the primary function of the
area and are compatible with the business/industrial character of the area. The submitted
Appropriateness Statement, Business Plan & Impact Justification Report outlines that the
nature of the business (aesthetics and training academy) requires a discreet location not
available in town centre or high street premises. It is secure for storing licensed equipment and
does not conflict with the office/industrial setting as it is low-footfall, non-noise producing and
enhances the tenant mix (which includes a dance academy and yoga studio). While the site is
easily accessible from the M80 and there is free on-site parking it is also well served by local
bus routes and footpath network. The proposal is considered to be a low-impact use that while
non-conforming does not detrimentally affect with the business/industrial character of the area. 
8.4 Within the NLLDP the site is located within a Local Business Centre covered by Policy PP 2B
Purpose of Place which seeks to encourage small, medium and large sized enterprises to
locate in our Local Business Centres, safeguard their character from dilution by other
inappropriate uses and support upgrading of premises, amenities, access, parking and green
spaces.  Where specified by this Policy, applicants will be expected to provide the identified
appraisals or assessments, which should be submitted with any planning application to allow
consideration of the proposal. These locations can accommodate a full range of Class 4
Business, Class 5 General Industrial and Class 6 Storage or Distribution uses. Ancillary
Development is development in the following classes that supports the operation of an existing
use in the Centre, or the operation of the Centre, by providing uses at a scale appropriate to
the Centre: Class 1 Shops (Convenience), Class 2 Financial and Professional Services, Class
3 Food and Drink including sui generis: hot-food takeaway, Class 11 Assembly and Leisure. 
8.5 Proposals for non-ancillary development or changes of use will generally not be supported
however, for any non-ancillary or high-footfall generating uses the following information should
be supplied for assessment in justification of the suitability of this development for the Business
Centre in which it is being proposed: 
• the Town Centres First Sequential Approach assessment as defined in Policy PP1A.
•  a statement on the mix of uses, the scale and nature of existing development in the
Business Centre (all proposals require to satisfy the provisions of Policy EDQ 1). 
• its impact on the attractiveness as a location for industry and business (all proposals require
to satisfy the provisions of Policy EDQ 3). 
• evidence that there is a requirement for a building with use-specific characteristics (e.g.
roof height, layout, security).
• evidence that the proposal will result in economic benefit. 
• Its impact on travel patterns and accessibility by sustainable modes of transport. 
8.6 The Appropriateness Statement, Business Plan & Impact Justification Report states the
applicant initially explored several high street and town centre locations but were deemed
unsuitable for the nature of the business and brand ethos. Opportunities within Cumbernauld
Town Centre are also uncertain at this stage with the future redevelopment of the Town Centre.
The application site was chosen as it is discreet and provides security, privacy and long-term
certainty. It is also stated the business, which has a low-footfall and is non noise producing
complements the existing businesses in the locale and enhances the overall tenant mix. 
Page 81 of 88

Page 82

8.7 In light of the nature of the proposal and the supporting information provided it is accepted what
while technically a non-conforming use in a Local Business setting, the business can be
acceptably accommodated without detriment to the core business setting while complementing
the existing mixture of uses. 
8.8 Policy AD 2B Amount of Development also applies and requires planning applications will be
assessed for their implications related to the amount of development proposed. The need for
an assessment depends on the contribution of type (use class), scale and location of
development. An assessment is required as Class 1 A Sops (comparison) are a non-complying
use. The Appropriateness Statement, Business Plan & Impact Justification Report states
several high street and town centre locations were deemed unsuitable for the nature of the
business and brand ethos, with opportunities within Cumbernauld Town Centre uncertain with
its redevelopment. The application site was chosen as it is discreet and provides security,
privacy and long-term certainty. The existing aesthetics salon has operated without having a
detrimental impact on the business locale and wishes to diversify with the introduction of a
training academy. The unit, which is relatively small scale, is already operating successfully as
a salon without detriment to the core business setting and is considered to have a minimal
impact on land supply for industry and business. It is not of a scale or nature as to impact
adversely on the town centre or other local centres. 
8.9 As before, while technically a non-conforming use in a Local Business setting it is considered
the business can be acceptably accommodated without detriment to the core business setting
while complementing the existing mixture of uses. 
8.10 All planning applications require to be assessed against the criteria of policies EDQ 1 (Site
Appraisal) and EDQ 3 (Quality of Development) of the NLLDP. 
8.11 Policy EDQ 1 (Site Appraisal) requires the development to be appraised in terms of the site and
its surroundings to ensure it will integrate successfully into the local area and avoid harm to
neighbouring amenity. A number of matters required to be assessed; those most relevant to
this proposal are: 
• accessibility by a range of sustainable transport modes
• existence and quality of connections and access including site and building entrances,
roads, paths and visuals on the site and surrounding Land Use Character Area 
8.12 The proposed development, by virtue of its location, will not impact on residential amenity. The
small-scale nature of the proposal which has a relatively low footfall and is non-noise producing
will not have a detrimental impact on the existing business users. There is adequate parking
provision at the site, and it is easily accessible from the road network. It is also well served by
local bus routes and a local footpath network which leads to other parts of Cumbernauld,
including the town centre. As such this policy is considered to be complied with. 
8.13 Policy EDQ 3 (Quality of Development) states proposals will only be permitted where high
standards of site planning and sustainable design are achieved. The most relevant to this
proposal is providing a safe, pleasant, inclusive, convenient and welcoming development
addressing: integration with public transport, sustainable access for cars, being safe for all road
users and appropriate parking. The site is well served by the road network and is located close
to the motorway network. The office building has a dedicated car park for users. The site is also
well served by local bus routes and by a local footpath network. As the site provides
opportunities for travel by car and other sustainable modes of transport this policy is considered
to be complied with. 
Page 82 of 88

Page 83

9. Conclusions 
9.1 The proposed development is considered to be a compatible use within this part of the Business
Centre that does not prejudice the primary function of the area. It is therefore considered to be
an acceptable departure to the provisions of NPF4 Policy 26: Business and Industry and Local
Business Centres Policies PP 2B, AD 2A of the North Lanarkshire Local Development Plan
2022. Furthermore, it is considered to comply with polices EDQ 1 and EDQ 3 of the NLLDP. 
Page 83 of 88

Page 84

Page 84 of 88

Page 85

North Lanarkshire Council
Report
PLANNING COMMITTEE 
Does this report require to be approved? ☐ Yes   ☒ No
Ref    Index 2 Date 14/08/25 
NOTICE OF PLANNING AND ENFORCEMENT APPEALS
DECISIONS 
From  Pamela Humphries, Chief Officer (Place)  
E-mail humphries@northlan.gov.uk Telephone 01236 632487 
1. Background 
Application No. &
Proposal 
Applicant & Site  Appeal
Decision &
Date 
Note 
25/00013/LUC  Mr James Galhaney       Appeal            The Reporter found the 
Change of Use Building to the             Dismissed   evidence submitted did 
From Day Room Southwest Rear of        01/07/2025  not demonstrate that the
(Sui Generis) to Luggiebank     building has been used 
Dwelling  Mill Cottage     consistently for a period of   
Old Mill Road     at least four years. 
Allanton   
ML7 5BX 
25/00325/MSC WB Properties Ltd      Appeal   The Reporter found that
Construction of 88 Site North of            Dismissed    the proposed noise mitigation
Dwellings with     Bellshill Road       24/04/2025  would fail to prevent
Associated       Uddingston     significant adverse noise
Roadworks, SUDS       impacts and unacceptable
and Landscaping       noise for future inhabitants
(17/00518/PPP) of the appeal site. This would
bring a likelihood of          
Executive Summary 
1. Purpose of Report 
1.1      This report is to advise the Committee of the recent decisions in respect of the  
undernoted planning appeals. 
Recommendations 
It is recommended that the Committee note the decision in respect of this appeal. 
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement All ambition statements
Item 3
Page 85 of 88

Page 86

legitimate noise complaints
and current
industrial/commercial noise
to the detriment of the
existing nearby businesses.
2. Report 
N/A 
3. Measures of success 
N/A     
4. Supporting documentation 
DPEA website: Scottish Government - DPEA - Case List 
Pamela Humphries
Chief Officer (Place) 
Page 86 of 88

Page 87

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Page 87 of 88

Page 88

Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☒ 