Democracy Spraffa

Agenda Document Pack - Planning Committee - 04/12/2025

North Lanarkshire Council · 4 December 2025
Back to Planning Committee — 4 December 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Clerk Name: Clare Louise McDonald
Clerk Telephone: 07350 435308
Clerk Email: committee@northlan.gov.uk
25 November 2025
Members of the
Planning Committee
Chief Executive’s Office
Rachel Blair
Chief Officer (Legal & Democratic)
Civic Centre, Windmillhill Street,
Motherwell ML1 1AB
www.northlanarkshire.gov.uk
Notice is given that a Meeting of the Planning Committee is to be held in the Council
Chamber, Civic Centre, Windmillhill Street, Motherwell, ML1 1AB on Thursday, 04 December
2025 at 10:00 AM which you are requested to attend.
The agenda of business is attached.
Rachel Blair
Chief Officer (Legal & Democratic)
Members :
N Shevlin, G Currie, A Beveridge, B Burgess, A Bustard, J Cairns, T Carragher, M Coyle, S
Coyle, K Docherty, T Fisher, M Hughes, L Jarvie, T Johnston, J Logue, H Loughran, J
McLaren, M McPake, A McVey, L Mitchell, D Robb, A Smith, G Woods.
Page 1 of 154

Page 2

Page 2 of 154

Page 3

Agenda
1 Declarations of Interest In Terms of the Ethical
Standards In Public Life Etc. (Scotland) Act 2000
Operational
2 Planning Applications Index
Submit Index
5 - 110
3 Development Plan Scheme & Participation
Statement 2025 Update
Submit report by the Chief Officer (Place) seeking
approval of the Development Plan Scheme &
Participation Statement (DPS) 2025 update.
111 - 140
4 Scheme of Delegation:  Local Developments
Submit report by the Chief Officer (Place) seeking
approval of the update to section 49.5 of the Scheme
of Delegation to Officers.
141 - 146
5 Notice of Planning and Enforcement Appeals
Lodged
Submit report by the Chief Officer (Place) advising of a
Planning Appeal recently lodged with the Scottish
Ministers.
147 - 150
6 Notice of Planning and Enforcement Appeals
Decisions
Submit report by the Chief Officer (Place) advising of a
recent decision in respect of Planning Appeals.
151 - 154
Page 3 of 154

Page 4

Page 4 of 154

Page 5

North 
Lanarkshire 
Council 
Planning Applications for consideration 
of Planning Committee 
Committee Date: 4th December 2025 
Ordnance Survey maps reproduced from Ordnance Survey 
with permission of HMSO Crown Copyright reserved 
Item 2
Page 5 of 154

Page 6

APPLICATIONS FOR PLANNING COMMITTEE 
4th December 2025 
Page No Application No  Applicant Development/Site Recommendation
8-18 24/00734/FUL Trustees for 
Major James
Towers-Clark
Residential Development of
3 Houses
250 Forrest Street
Clarkston
Airdrie
ML6 7AY  
Grant
19-45 24/01267/FUL Ravenscraig Ltd Extraction of Contaminated
Materials and Remediation
of Ground at Sites known
as Meadowhead and 
TC1-3 within Ravenscraig
Masterplan Area
Land to the South of
Ravenscraig Park
Robberhall Road
Motherwell  
Grant
46-60  25/00150/FUL DataVita Plant Extension to Data
Centre and Construction of
Generator Building
Including Alterations,
Infrastructure, Watercourse
Diversion, Biodiversity
Enhancement, Access and
Associated Development
DataVita Data Centre
York Road
Chapelhall
ML6 8HW   
Grant
61-72 25/00713/FUL Deerdykes
Bioenergy Limited
Proposed Re-Development
of an Existing Renewable
Biogas Facility and
Associated Works
Site At
Old Quarry Road
Westfield
Cumbernauld  
Grant
73-90 25/00794/FUL JGS Developments
(Lenzie)
Residential Development
(5no. Proposed Houses)
and Green Network
Enhancement
Land at
Dullatur Road and 
Refuse (P)
Page 6 of 154

Page 7

King's Drive
Dullatur
Cumbernauld  
91-98 25/00819/AMD  Nethan Access Erection of Two
Dwellinghouses:
Amendment Permission
24/00709/FUL
Land At
Hawthorn Avenue
Crindledyke
Newmains  
Grant
99-109 25/00901/FUL Duncan 
Caravans Ltd
Change of Use of an
Existing Caravan
Showroom and Shop to a
Storage Warehouse
Comprising Multiple
Internal Storage Units and
Change of Use of Caravan
Storage Yard to allow for
the Siting of Shipping
Storage Containers
Duncan 
Caravan & Camping
186 Wishaw Road
Waterloo
Wishaw
ML2 8ES  
Grant          
(P) 
25/00794/FUL – If permission is granted permission will not be issued until a legal agreement has           
been concluded to secure contributions in relation to affordable housing and play 
Page 7 of 154

Page 8

Application No:  
24/00734/FUL
Proposed Development: 
Residential development of 3 houses 
Site Address: 
250 Forrest Street
Clarkston
Airdrie
ML6 7AY 
Date Registered: 
29th July 2024 
Applicant:
Trustees For Major James Towers-Clark
190 St Vincent Street
Glasgow
G2 5SP 
Agent:
Bryce Associates Ltd
PO Box 7656
Glasgow
G42 2HY 
Application Level:
Local Application 
Contrary to Development Plan:
Yes
Ward:   
08 Airdrie North 
Alan Beveridge, Sophia Coyle, Henry Emerson
Dunbar, Richard Alan Sullivan,
Representations:
1 letter(s) of representation received.   
Recommendation: Approve subject to conditions 
Reasoned Justification: 
The development is contrary to Green Belt policies however due to the previous long-term use
of the site for standalone commercial storage the proposed dwellinghouses would be a more
appropriate use of a brownfield site on the edge of the urban area and therefore an acceptable
development within the Green Belt. 
Page 8 of 154

Page 9

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 24/00734/FUL 
Name (of applicant): 
Trustees for Major James Towers-Clark
Site Address: 
250 Forrest Street
Clarkston
Airdrie
ML6 7AY 
Development: Residential Development
of 3 Houses 
Page 9 of 154

Page 10

Proposed Conditions 
1.  That, except as may otherwise be agreed in writing by the Planning Authority, the development shall be
implemented in accordance with drawing numbers: 
4744/1 
2097_300 A 
2097_203 
2097_202 
2097_201 
2097_200 A
2097_120 
2097_110
2097_100 
2097_030 A  
2097_007 B 
2097_006 A 
2097_005 A
2097_004 A
2097_003 B 
2097_002 A
2097_001 A
13125-101 
Reason: To clarify the drawings on which this approval of permission is founded.   
2. That BEFORE the development hereby permitted starts, full details of the facing materials to be used
on all external walls and roofs shall be submitted to, and approved in writing by the Planning Authority
and the development shall be implemented in accordance with the details approved under the terms of
this condition. 
Reason: In the interest of the amenity of the site and the general area. 
3. That BEFORE the development hereby permitted starts, full details of the design and location of all
fences and walls to be erected on the site shall be submitted to, and approved in writing by the Planning
Authority. For the avoidance of doubt this includes the required acoustic fencing as set out in the Noise
Impact Report dated January 2025. 
Reason: In the interest of the amenity of the site and the general area. 
4. That BEFORE any of the dwellinghouses hereby permitted, situated on a site upon which a fence or
wall is to be erected, are occupied, the fence, or wall, as approved under the terms of condition 3 above,
shall be erected. 
Reason: In the interests of the visual amenity of the area. 
5. Notwithstanding condition 1 above, for avoidance of doubt the details contained within landscaping plan
2097 7B are hereby approved. Additional information regarding the detailed timetable for all landscaping
works which shall provide for these works being carried out contemporaneously with the development
of the site. This detailed timetable shall be submitted to, and approved in writing by the Planning
Authority. 
Reason: To enable the Planning Authority to retain effective control, in order to maintain the amenity of
the area. 
Page 10 of 154

Page 11

6. That all works included in the scheme of landscaping and planting, approved under the terms of
condition 5 above, shall be completed in accordance with the approved timetable, and any trees, shrubs,
or areas of grass which die, are removed, damaged, or become diseased, within two years of the full
occupation of the development hereby permitted, shall be replaced within the following year with others
of a similar size and species. 
Reason: In the interests of ensuring amenity of the area. 
7. That BEFORE the development hereby permitted starts, a management and maintenance scheme shall
be submitted to, and approved in writing by the Planning Authority, and it shall include proposals for the
continuing care, maintenance and protection of all soft and hard landscaping incorporated into the
development. Thereafter the management and maintenance plan shall be in operation prior to the
occupation of the final dwelling. 
Reason: RS07A To safeguard the residential amenity of the area. 
8. That BEFORE any works of any description start on the application site, unless otherwise agreed in
writing with the Planning Authority, a comprehensive site investigation report shall be submitted to and
for the approval of the said Authority.  The investigation must be carried out in accordance with current
best practice advice, such as BS 10175 : 'The Investigation of Potentially Contaminated Sites' or CLR
11.  The report must include a site specific risk assessment of all relevant pollution linkages and a
conceptual site model.  Depending on the results of the investigation, a detailed Remediation Strategy
may be required. Information on the required format of the report and how it should be submitted to us
can be found online: 
https://www.northlanarkshire.gov.uk/planning-and-building/planning-applications/how-discharge-
contaminated-land-planning-conditions 
Reason: To ensure the site is free of contamination. 
9. That any remediation works identified by the site investigation required in terms of Condition 8, shall be
carried out to the satisfaction of the Planning Authority.  A validation report (signed by a chartered
Environmental Engineer) shall be submitted to the Planning Authority prior to the occupation of either
house confirming that any remediation works have been carried out in accordance with the terms of the
Remediation Strategy. 
Reason: To ensure the site is free of contamination. 
10. That BEFORE development commences, an up to date Ecological Survey report prepared by a suitably
qualified ecologist shall be submitted to and approved in writing by the planning authority.  Such report
shall include any proposals for mitigation which may be appropriate, and shall also include proposals
for a scheme of ecological enhancements within the development and adjoining land so as to offset the
impacts of the development.  In the event of development not commencing within 12 months of the date
of the survey, an updated such survey shall be undertaken and its findings submitted to the planning
authority for approval as above.  The approved mitigation and ecological enhancements shall thereafter
be implemented as approved in accordance with the timescale specified in the agreed report. 
Reason: In order to ensure that up to date ecological information is provided prior to development
commencing, and to ensure that the development includes appropriate ecological mitigation and
biodiversity enhancements consistent with the requirements of NPF4 policy 3. 
11. The houses hereby approved shall not be occupied until such time as the vehicular and pedestrian
access, parking and turning spaces have been completed to their finished standard and made available
for use. 
Reason: In order to ensure that the development has suitable access and parking. 
Page 11 of 154

Page 12

12. That a visibility splay of 4.3 metres by 90 metres, measured from the road channel, shall be provided
on both sides of the vehicular access from the junction of Katherine Park Lane onto Forrest Street (A89)
before the development hereby permitted is occupied. Everything exceeding 1.05 metres in height
above the road channel level shall be removed from the sight line areas and, thereafter, nothing
exceeding 1.05 metres in height above road channel level shall be planted, placed, erected, or allowed
to grow, within these sight line areas. 
Reason: In the interests of traffic and pedestrian safety. 
13. That a visibility splay of 2.4 metres by 40 metres, measured from the road channel, shall be provided
on both sides of the vehicular access from the junction of the development onto Katherine Park Lane
before the development hereby permitted is occupied. Everything exceeding 1.05 metres in height
above the road channel level shall be removed from the sight line areas and, thereafter, nothing
exceeding 1.05 metres in height above road channel level shall be planted, placed, erected, or allowed
to grow, within these sight line areas. 
Reason: In the interests of traffic and pedestrian safety. 
14. That before the development hereby permitted commences details of a 2 m wide footpath along the
frontage of the site with Katherine Park Lane shall be submitted to, and approved in writing by the
Planning Authority. Thereafter this footpath shall be installed, levelled and properly drained prior to the
occupation of the development and shall thereafter be maintained. 
Reason: In the interests of traffic and pedestrian safety. 
15. The felling of any trees shall be undertaken outwith the bird breeding season, for the avoidance of doubt
this is between March and September. 
Reason: In the interests of protecting wildlife 
16. That BEFORE the development hereby permitted starts, tree protection measures in accordance with
British Standard BS 5837 shall be erected along the drip line of the trees, as shown on the approved
plans, and shall not be removed without the approval in writing of the Planning Authority. 
Reason: In the interests of the visual amenity of the area. 
17. That the noise mitigation measures identified in the submitted Noise Impact Assessment dated January
2025 shall be carried out to the satisfaction of the Planning Authority prior to the occupation of the
dwellings. A validation report from a suitably qualified person shall also be submitted verifying these
works have been carried out. 
Reason: For the amenity of future residents 
18. No above ground development shall commence until: 
a) a scheme of intrusive investigations has been carried out on site to establish the risks posed to the    
development by past shallow coal mining activity; and
b) any remediation works and/or mitigation measures to address land instability arising from past coal 
mining legacy, as may be necessary, have been implemented on site in full in order to ensure that 
the site is made safe and stable for the development proposed 
The intrusive site investigations, remedial works and mitigatory measures shall be carried out in
accordance with authoritative UK guidance. 
Reason: To ensure that matters relating to coal mining risk are adequately addressed. 
Page 12 of 154

Page 13

19. Prior to the occupation of the development, or it being taken into beneficial use, a signed statement or
declaration prepared by a suitably competent person confirming that the site is, or has been made, safe
and stable for the approved development shall be submitted to the Local Planning Authority for approval
in writing. This document shall confirm the methods and findings of the intrusive site investigations and
the completion of any remedial works and/or mitigation necessary to address the risks posed by past
coal mining activity. 
Reason: To ensure that matters relating to coal mining risk are adequately addressed. 
Background Papers: 
Consultation Responses: 
Scottish Gas Network 5th August 2024 
NLC Environmental Health (including Pollution Control) 6th August 2024 & 24th March 2025 
Coal Mining Remediation Authority 6th August 2024 
NLC Infrastructure and Transportation 26th August 2025   
Contact Information: 
Leigh Menzies at esplanning@northlan.gov.uk or 01236 632487 
Report Date: 
20 November 2025
Page 13 of 154

Page 14

APPLICATION NO. 24/00734/FUL 
REPORT 
1. Site Description 
1.1 The application relates to an area of land approx. 0.21ha in size. This is located to the northeast of the
junction of Forrest Street (A89) and Katherine Park Lane. The site has a long history of commercial
use for storage, the site has only recently been cleared of the structures relating to this. The
commercial use could recommence at any time. 
1.2 The immediate access to the application site is off Katherine Park Lane which is a single lane private
road which serves another two residential properties located to the southeast. Katherine Park Lane
then links onto Forrest Street (A89). 
1.3 The site is located on the edge of the urban area, with a clear boundary by historical fencing and
mature vegetation. To the north and east of the site is located an open grassy field. To the west is
located housing and to the south Katherine Park, which is public open space. 
1.4 The site is relatively flat, with a slight incline towards Forrest Street (A89). With the surrounding area
at the same level. 
2. Proposed Development 
2.1 The application for planning permission for the erection of 3 dwellinghouses that would be located in
an L shape. Access would be taken directly off Katherine Park Lane and links onto Forest Street (A89). 
2.2 The proposed development would consist of 3 dwellings split over two levels, with the upper
accommodation being contained mainly within the roof area. Each property would provide 3 bedrooms
with one detached property and the other 2 semi-detached. Each of the properties would have private
garden ground to the rear an open aspect and a communal parking area to the frontage. 
2.3 The proposed configuration of the housing looks to remove a limited number of trees from the site,
however the trees along the western boundary with Forrest Street would be maintained. 
2.4 In terms of the materials that are proposed the roof would be natural slate, with off white render and a
buff brick. 
3. Applicant’s Supporting Information 
3.1 The applicant has submitted the following information (along with some resultant follow-up
submissions) in support of their application: 
• Planning statement
• Site investigation
• Coal mining risk assessment
• Ecology appraisal
• Noise impact assessment
• Transport statement
• Tree survey 
4. Site History 
4.1 In terms of a formal planning history of the site planning permission was granted on 18 August 1995
(ref 95/00337/OUT) for the erection of a single dwellinghouse (variation to permission 92/280). 
4.2 With regards to the commercial storage area there appears to be no formal planning applications with
limited history of the site. However historically this area has been separate from the adjoining field and
with buildings previous located on the site prior to the use as commercial storage. 
Page 14 of 154

Page 15

5. Development Plan 
5.1 With regard to the proposal the following policies are relevant in terms of the development plan: 
National Planning Framework 4 (NPF4)
Policy 3 Biodiversity
Policy 8 Greenbelts
Policy 9 Brownfield, Vacant and Derelict Land
Policy 13 Sustainable Transport
Policy 14 Design, Quality and Place
Policy 15 Local Living and 20 Minute Neighbourhoods
Policy 16 Quality Homes  
North Lanarkshire Local Development Plan (LDP)
PP4 Policy Greenbelt
AD4 Amount of Development
EDQ 1, 2, 3 Environmental and Design Qualities 
6. Consultations 
6.1 NLC Infrastructure and Transportation have asked that the following elements be included within the
development
a. Visibility splay from Katherine Park Lane onto Forrest Street of 4.5m x 90m
b. Visibility splay of 2.4m x 40m requires to be provided from the development onto Katherine
Park Lane
c. 2m wide footpath to be provided along the length of the development on Katherine Park Lane
d. Provide a swept path analysis for refuse trucks 
6.2 The Coal Mining Remediation Authority have indicated that they have no objections so long as suitable
conditions are placed on any approval to ensure adequate investigation of the ground conditions. 
6.3 NLC Protective Services have provided comments in relation ground contamination and noise, these
are a follows: 
a. Ground contamination: a site investigation is required due to the previous commercial uses on
the site 
b. Noise: a noise impact assessment was requested and provided. Assessment of this report
indicated that the mitigation proposed was acceptable in relation to road noise. 
6.4 Scottish Gas Network: no objections to the development 
7. Representations 
7.1 Following the carrying out of the statutory notification and press advert 1 letter of representation was
received. This letter objected to the development due to the removal of trees. In response it should be
noted that a tree report was submitted as part of the application which indicates that the trees to be
removed are not worthy of retention either through disease or being of low-quality self-seeding. In
addition measures would be put in place tree protection and for replacement planting, which would be
ensured through condition. 
8. Planning Assessment 
Development Plan Policy 
8.1 In accordance with Section 25 of the Town and Country Planning (Scotland) Act 1997, planning
decisions must be made in accordance with the Development Plan unless material considerations
indicate otherwise. The development plan comprises National Planning Framework 4 (NPF4) and the
North Lanarkshire Local Development Plan 2022 (the LDP), with the former taking precedence in the
event of any conflict between policies. 
Page 15 of 154

Page 16

8.2 The application site is within the designated Green Belt in the North Lanarkshire Local Plan, however
the site in question is on the edge of the urban area and has a long history of being used for commercial
purposes, which most recently included a number of structures, containers and corrugated metal
fencing. 
8.3  With regard to NPF Policy 3 this seeks to protect biodiversity, reverse biodiversity loss, deliver positive
effects from development and strengthen nature networks. The site as it stands at the moment has
been recently cleared of structures etc but still has concrete pads which would hamper any long term
return to nature. To the north of the site there is a slim tree belt which is worth of retention. As part of
any planning permission the management and maintenance would be included in the required
conditions. In addition to this other ecological enhancements are proposed which would deliver the
positive benefits as required by this policy including bat boxes, tree planting etc. In this regard the
proposal would meet the requirements of Policy 3. 
8.4 The application site is within the designated Green Belt.  NPF4 policy 8 seeks to promote compact
urban growth by restricting development within the Green Belt to specified types and circumstances,
which in the case of residential development are limited to houses required for key workers in
countryside businesses and allowing incremental housing development on the edge of the settlement
boundary would undermine one of the purposes of the Green Belt, i.e. to protect the countryside
around town from unplanned encroachment. LDP policies PP4 and AD4 are substantially similar in
effect, in relation to housing development in the Green Belt.   The application proposal does not involve
a type of residential development allowed by these policies, and it is considered that the applicant has
not demonstrated a requirement for a Green Belt site. Accordingly, the proposal is contrary to NPF4
policy 8 and to LDP policies PP4 and AD4. 
8.5 Notwithstanding the above further consideration is given to the current permitted development of the
site and the potential impact that this could have on the surrounding area. The site has a long history
of being used for commercial purposes with various metal structures on the site including solid metal
fencing. The visual impact of such a use occurring again, unknown traffic generation and potential
noise concerns requires to be taken into consideration. 
8.6 In addition it is important to noted that the area being considered is a well defined, defendable area
and would not lend itself to further expansion into the Green Belt area. 
8.7 As previously indicated the site has been used for a commercial use for some considerable time and
has only just recently been cleared of the structures, containers and metal fencing. The site still has
some debris on the site including concrete pads. Given this Policy 9 (Brownfield, vacant and derelict
land) to encourage, promote and facilitate the reuse of brownfield land. It is considered that the
proposed development meets this policy in that it is utilising land that had been formally been in use
and retains permitted development uses for commercial purposes. 
8.8 In terms of Policy 13 (Sustainable Transport) of NPF4 this site is within 40m of an existing bus stop
and within 500m of Drumgelloch Station. Therefore it is considered that the development of this site
would meet the requirements of this policy to place developments in locations that supports
sustainable travel. 
8.9 Policy 14 of NPF4 (Design, Quality and Place) Places that consistently deliver healthy, pleasant,
distinctive, connected, sustainable and adaptable qualities. The current permitted use of the site is
commercial and the previous structures, containers and metal fencing could be reintroduced to the
site. It considered that the return of such a commercial use would be detrimental to the adjacent public
park but also to the overall amenity of the site and could impact the mature trees at the north of the
site, which are not protected through legislation. In addition to this the design and layout of the
proposed development looks to maintain as much of the mature planting as possible and providing a
sympathetic design, in both detail and materials, to the surrounding area. 
Page 16 of 154

Page 17

8.10  In addition LDP policies EDQ1 and EDQ3 collectively have similar requirements to policy 24 of NPF4,
specifying that development proposals be subject to an appropriate site appraisal and achieve a high
quality of development.  The proposed houses would be of a style and layout which is in keeping with
the existing mixture of building types in the vicinity, and the impact on existing neighbouring properties
and uses would be acceptable.  Overall, it is not considered that there would be any conflict with NPF4
policy 14 or with the LDP EDQ policies. 
8.11 With regard to policy 15 relating to Local Living and 20 Minute Neighbourhoods the site is located on
the edge of the local Clarkston area which has a number of local amenities within 200m of the site.
This includes local shops and Katherine Park, with Drumgelloch Station within 500m linking the
development to the wider Central Belt. Given this it is considered that the proposed development
complies with the Policy 15 in that the location has strong links with both nearby facilities and strong
transport to the wider area. 
8.12 National policy on new housing development is contained in NPF4 policy 16, which sets out the means
by which LDPs should establish a deliverable housing land pipeline to meet local housing needs. 
Proposals for new homes on land which is not allocated for housing in the LDP will only be supported
in limited circumstances, such as where the proposal is within an existing settlement boundary or is
consistent with the policy on rural homes, neither of which is the case for this proposal.  The proposal
is therefore contrary to both NPF4 policy 16 and also to LDP policy PROM LOC3 (although the latter
policy has in practice been superseded by NPF4 policy 16 for reasons which do not relate directly to
this proposal).   
Design and Amenity 
8.13 The proposed 3 dwellings would include one detached and a pair of semi detached. All of the dwellings
would be accommodated over two stories with the upper accommodation being contained mainly
within the roof area. The properties would be accommodate in an L shape and will have limited front
gardens, communal parking area, and each will have dedicated rear gardens. 
8.14 Overall the design of the properties is considered to be acceptable and will provide adequate parking
and private garden ground. 
8.15 The area to the west and south of the site has a significant number of mature trees lining both Forrest
Street and Katherine Park Lane. The northern portion of the site also contains the mature trees and
the proposed development looks to retain these to the benefit of the amenity of the local area. 
8.16 In terms of the traffic implications the sightlines from the site onto Katherine Park Lane can be achieved
and a condition would be placed onto any approval. In addition discussions have been undertaken
with the applicant in term of the sightlines onto Forrest Street. NLC’s Infrastructure and Transportation
team has stipulated that 4.5m x 90m requires to be achieved, however this would require the removal
of a mature tree which adds to the tree lined street scene. The applicant has shown that sightlines of
4.3m x 90m can be achieved and it is considered that this minor change is acceptable. 
8.17  NLC’s Protective Services required the submission of a Noise Impact Assessment due to the potential
impact of road noise. In general, it was assessed that the mitigations were acceptable and related to
fencing and window requirements. Relevant conditions would be placed on any approval to ensure
that these measures are undertaken. 
8.18 In terms of a site investigation NLC’s Protective Services require that this be carried out due to the
commercial history of the site. The relevant conditions would be placed on any approval requiring that
this be carried out along with any required remediation and subsequent verification. For information
the applicant has already submitted a site investigation for assessment. 
Page 17 of 154

Page 18

Representation 
8.19 Following the carrying out of the statutory notification and press advert 1 letter of representation was
received. This letter objected to the development due to the removal of trees. In response it should be
noted that a tree report was submitted as part of the application which indicates that the trees to be
removed are not worthy of retention, either through disease or being of low-quality self-seeding. In
addition, measures would be put in place tree protection and for replacement planting, which would
be ensured through condition. 
9. Conclusions 
9.1 It is appreciated that the proposed development is located within an area designated as Green Belt
however given that the site has a long-term history of being used for commercial storage and the
proposed use for housing would be more in keeping with the surrounding land uses and as such it is
recommended that planning permission be granted. 
Page 18 of 154

Page 19

Application No:  
24/01267/FUL
Proposed Development: 
Extraction of Contaminated Materials and Remediation of
Ground at Sites known as Meadowhead and TC1-3 within
Ravenscraig Masterplan Area 
Site Address: 
Land to the South of
Ravenscraig Park
Robberhall Road
Motherwell 
Date Registered: 
17th January 2025 
Applicant:
Ravenscraig Ltd
58 Morrison Street
Edinburgh
EH3 8BP 
Agent:
Ryden
Onyx
215 Bothwell Street
Glasgow
G2 7ED 
Application Level:
Major Application 
Contrary to Development Plan:
No
Ward:   
19 Motherwell Southeast and Ravenscraig 
Kenneth Duffy,Nathan Wilson,David Robb,
Representations:
0 letter(s) of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification:   
Meadowhead and TC1-3 form part of the wider Ravenscraig Regeneration Area. Ravenscraig
is one of 6 Strategic Town Centres and one of 5 Strategic Business Centres in the North
Lanarkshire Local Development Plan that will be given priority to deliver development of the
right quality to the right place. The current application, which proposes decontamination and
remediation of brownfield land, will ensure that two large sites within the Ravenscraig
Regeneration Area are prepared for future redevelopment in accordance with the aims and
objectives of the Ravenscraig Regeneration Area Strategy and approved masterplan. The
application is supported by sufficient information to demonstrate that with mitigation and
conditions in place, the proposed development can operate without unacceptable impacts on
ecology, air quality, the water environment, the road network and residential amenity. The
application is therefore supported on the basis that it complies with the Development Plan. 
Page 19 of 154

Page 20

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 24/01267/FUL 
Name (of applicant): Ravenscraig Ltd
Site Address: Land to the South of
Ravenscraig Park
Robberhall Road
Motherwell 
Development: Extraction of
Contaminated Materials and Remediation
of Ground at Sites known as
Meadowhead and TC1-3 within
Ravenscraig Masterplan Area   
Page 20 of 154

Page 21

Proposed Conditions:- 
DURATION OF PLANNING PERMISSION 
1. The development hereby approved shall subsist for a period of 14 years from the date of
commencement to be confirmed in writing to the Planning Authority. At the end of the period of 14
years, unless a further planning application is submitted and approved by the Planning Authority, the
development shall cease to operate and both the Meadowhead and TC1-3 sites shall be remediated
to a standard suitable for future development. 
Reason: To ensure discontinuance of the works at the end of the period specified. 
ACCESS AND TRANSPORATION 
2. Prior to commencement of the development, details showing the design and location of internal haul
roads, all site entrance/exit points, trackout routes and mud/wheel wash facilities and separate paved
parking areas for off-site vehicles, such as staff vehicles with no access to the working areas, for all
phases of the development shall be submitted to the Planning Authority for approval.  For the
avoidance of doubt: 
a) Internal haul roads shall maintain a minimum distance of 250m from sensitive receptors; where this  
is unachievable, semi-permeable boundary fencing should be installed in such areas to limit migration
of particles off-site. 
b) Mud/wheel wash facilities shall be located within the confines of the development site.
c) Haul route distance should be minimised, and haul vehicles should be covered. 
Reason: To ensure a system is designed and in place to remove soil, mud, and debris from the tires
and undercarriages of vehicles before they exit the site. 
3. Prior to the commencement of the development, the developer shall prepare a methodology for
undertaking a Dilapidation Survey of roads around the development site(s) and submit this in writing
to the Planning Authority for approval in consultation with NLC Infrastructure and Roads. 
The methodology shall contain details of all roads to be included in the survey, details and frequency
of site inspections, the output of inspections, including documentation which shall include but may not
be limited to a) high resolution photographic time/date stamped evidence showing the condition of
roads prior to the commencement of the development, during the operational period of the
development and on completion of the development, together with any defects clearly recorded,
including those caused by damage, heavy use, potholes, cracks and/or surface weathering, and b)
details of the method used for apportioning the costs of remedial work and/or for agreeing financial
settlement.  This may involve, for example, use of automatic traffic counters on roads to be included
within the survey. 
Reason: To permit a robust pre and post completion comparison survey to be undertaken for the
benefit of identifying any areas of footway or carriageway within the public domain that will require to
be ‘made good’ by the developer at the developer’s expense as permitted under Section 96 of the
Roads (Scotland) Act 1984. 
4. The approved Construction Traffic Management Plan (CTMP), by Sweco, dated 13 November 2024,
shall be updated annually and submitted to the Planning Authority in writing for approval. For the
avoidance of doubt, the updated CTMP shall address any potential changes to site access,
construction vehicle routing, staff numbers, traffic generation, site phasing and traffic management
proposals and, in the event that two-way trips exceed 40 per hour averaged throughout the working
day, the updated CTMP shall include details of additional controls and/or mitigation for delivery
vehicles. 
Reason: To minimise any adverse impacts on the surrounding network. 
Page 21 of 154

Page 22

NOISE 
5. The noise attributable to the proposed operations shall not exceed 55 dB LAeq 1-hour free field at any
noise-sensitive receptors in accordance with PAN 50 Controlling the Environmental Effects of Surface
Mineral Workings, Annex A, which provides a day time limit of LAeq (1hour), free field of 55 dBA at
noise-sensitive properties used as dwellings where 1- hour means any of the one-hour periods during
the defined working day. 
Notwithstanding the above for a specified temporary period, of no greater than 8 weeks of any given
year within the construction programme, and within agreed working hours during this temporary period,
noise limits may be increased subject to agreement with the Planning Authority in consultation with
NLC Protective Services.  For the avoidance of doubt this is to allow for construction activities relating
to soil stripping, removal of spoil heaps, routine operations and for the construction of new permanent
landforms and/or baffle mounds only, in accordance with paragraphs 41 and 60 of Planning Advice
Note 50: controlling the environmental effects of surface mineral workings (Annex A). Where
applicable, a request to modify normal noise limits above 55 dB LAeq 1-hour free field within any given
year, shall be made in writing to the Planning Authority at least 2 months prior to the commencement
of the above construction activities.   
Reason: To ensure the construction works do not give rise to unacceptable noise limits over a long
period or result in significant adverse effects on noise sensitive receptors. 
6. The hours of operation on the site shall be limited to 08:00hrs to 19:00hrs Monday to Friday and no
work shall take place on weekends or on public holidays. 
Reason: In the interests of protecting the amenity of noise sensitive receptors. 
7. Periodic noise monitoring requires to be carried out at noise sensitive properties used as dwellings.
This monitoring requires to be carried out for a minimum 1-hour period every month by a suitably
qualified person, using a Type 1 sound level meter that is calibrated in accordance with BS 6698
“Specification for Integrating Averaging Sound Level Meters” 1986.  Thereafter, annual noise
monitoring reports shall be made available for inspection by the Planning Authority for the duration of
the construction works on reasonable notice by the Planning Authority. 
Reason:  In the interests of protecting residential amenity. 
FLOODING AND DRAINAGE 
8. Prior to the commencement of the development, details of the Pollution Prevention Plan / Construction
Phase Plan (CPP) and Construction Method Statements to manage surface water runoff during
construction shall be submitted to the Planning Authority for written approval. Due to the more-
permanent nature of the works compared with a conventional temporary works site, the submitted
details must demonstrate that surface water runoff can be managed up to the 0.5% Annual
Exceedance Probability (AEP) (1 in 200-year return period) event plus climate change. Thereafter, the
approved details shall be agreed with the Planning Authority. For the avoidance of doubt all works
required under this condition must be completed and approved before the development commences. 
Reason: To ensure that the drainage strategy for the construction works is designed to accommodate
a longer site duration than expected of a typical construction project in the interest of flood and water
quality protection and to ensure compliance with Flood Risk Management (Scotland) Act 2009, CAR
regulations and National Planning Framework (NPF4). 
9. Prior to commencement of the development, evidence shall be submitted to the Planning Authority to
demonstrate that a construction CAR licence (or new equivalent) has been obtained from SEPA.   
Reason: To control the development in the interests of protection of the water environment. 
Page 22 of 154

Page 23

10. Prior to the commencement of the development, evidence shall be submitted to the Planning Authority
for approval to demonstrate that a viable surface water disposal point will be in place for the site.  This
may include for example: 
a) Confirmation that any assumed infiltration rates used in the hydraulic calculations are likely to be
realised on-site through infiltration testing (in accordance with BS EN 752-4 or BRE Digest 365 or
other) to ensure an appropriate conclusion of the underlying strata’s ability to infiltrate based on
understanding of ground water levels on the site and seepage OR
b) Evidence that any existing drain or sewer is suitable for use (i.e. operational and structurally sound).
This may take the form of a drainage survey to confirm the asset condition (structurally and
operationally), connectivity, sizing, gradient etc, together with evidence of permission to connect to the
existing drain or sewer along with agreed discharge rates from the asset owner OR
c) Details of the proposal for a new drain, sewer or culvert to drain the site and dispose of surface
water at an appropriate outfall point without increasing flood risk within or outside of the site, together
with evidence to demonstrate that the new surface water disposal point is appropriate and can serve
the design life of the site, together with evidence of permission to connect the new drain to any existing
drain or sewer along with agreed discharge rates from the asset owner OR
d) Other method as appropriate. 
Thereafter, the approved details shall be implemented to the satisfaction of the Planning Authority. For
the avoidance of doubt all works required under this condition must be completed and approved before
any part of the development commences. 
Reason: In the interest of Flood Risk Resilience. 
11. Prior to commencement of the development, further evidence in the form of a revised Flood Risk
Assessment and Drainage Strategy, shall be submitted to the Planning Authority for approval to
demonstrate that the proposed development does not create or increase flood risk to property/land
and/or sensitive/critical infrastructure on and off the application site for up to and including the 0.5%
AEP (1:200 year) plus climate change allowance storm event. 
For the avoidance of doubt, the revised Flood Risk Assessment and Drainage Strategy shall include:
hydraulic calculations; details of pre-and post-development runoff calculations and flood extents (if
applicable); construction/ design details and specification of proposed ditches, check dams and
attenuation basins, including dimensions, gradients, materials specification to take account of the
possibility of these elements becoming part of the permanent works for the developed site; a
completed SEPA Flood Risk Assessment Checklist; details of parties responsible for maintenance;
and maintenance responsibilities together with a maintenance schedule for the surface water and
SuDS. 
All works required under this condition must be completed and approved by the Planning Authority
before any part of the development commences. Thereafter, all works approved by virtue of this
condition shall be undertaken in perpetuity to the satisfaction of the Planning Authority. 
Reason: In the interest of a providing a sustainable design solution, flood risk resilience and to protect
amenity 
Page 23 of 154

Page 24

CONTAMINATED LAND 
12. Contaminated Land Part 1 of 4 (Site Characterisation): 
Prior to the commencement of the development and in accordance with the approved Indicative
Phasing Plan, the following details shall be submitted to the Planning Authority for approval in writing: 
a) Details of proposals for localised additional targeted investigation works and risk assessment to
further delineate the nature and extent of contamination within the Meadowhead and TC1-3 sites,
together with detailed plans as indicated in Section 4 of the submitted ‘Meadowhead and TC1-3,
Ravenscraig Initial Contamination Assessment’, by GDG, dated 19 August 2025. 
b) Details of the completed additional investigation works, including interpretation and delineation of
remedial areas and associated plans; the findings of which shall be prepared in a written report. The
investigation and risk assessment shall be undertaken by competent persons and be completed in
accordance set out in Stage 1 of the LCRM Guidance.
c) An appraisal of remedial options, and proposals for the preferred option(s) presented in a written
report. The options appraisal shall be undertaken by competent persons and be completed in
accordance with requirements set out in Stage 2 of the Environment Agency’s ‘Land Contamination
Risk Management Guidance (LCRM)’ and NLC’s “Contaminated Land - A Guide to Submitting
Planning Applications for Development of Contaminated Land”.
Reason: To ensure that risks from land contamination to the future users of the land, neighbouring
land, to the water environment, property and ecological systems, are minimised and to ensure that the
development can be carried out safely without unacceptable risks to workers, neighbours and other
offsite receptors. 
13. Contaminated Land Part 2 of 4 (Submission of Remediation Strategy): 
Prior to the commencement of each phase of the development as shown on the approved Indicative
Phasing Plan, any remediation works identified by the site investigations works required under
Condition 12 above, shall be detailed in a Remediation Strategy and submitted to the Planning
Authority in writing for approval. For the avoidance of doubt, the Remediation Strategy shall include
details of all works to be undertaken, the proposed remediation objectives and remediation criteria, a
timetable for the commencement and completion of works, together with details of site management
procedures. The Remediation Strategy shall ensure that the site will not qualify as contaminated land
under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after
remediation. 
Reason: To bring the site to a condition suitable for the intended use by removing unacceptable risks
to human health, buildings and other property, the natural and historical environment and to ensure
that risks from land contamination to the future users of the land, neighbouring land, the water
environment, property, ecological systems and other offsite receptors are minimised. 
14. Contaminated Land Part 3 of 4 (Implementation of Approved Remediation Strategy): 
Notwithstanding the general requirement for a Notice of Intention to Develop, two weeks prior to
undertaking any remediation works, in accordance with the approved Indicative Phasing Plan, written
confirmation shall be provided to the Planning Authority of the intention to commence these works.
Thereafter, the remediation works shall be carried out in accordance with the Remediation Strategy
approved under the terms outlined in Condition 13 above.   
Reason: To maintain effective control of the remediation process and to ensure that risks from land
contamination to the future users of the land, neighbouring land, the water environment, property and
ecological systems, are minimised, and to ensure that the development can be carried out safely
without unacceptable risks to workers, neighbours and other offsite receptors. 
Page 24 of 154

Page 25

15. Contaminated Land Part 4 of 5 (Reporting of Unexpected Contamination): 
In the event of contamination, not previously identified, being found at any time during the remediation
works in accordance with the approved Indicative Phasing Plan, the developer shall notify the Planning
Authority of this in writing immediately. Thereafter, the developer shall carry out an investigation and
risk assessment in accordance with the requirements of Condition 12 above, and where remediation
is necessary, a Remediation Strategy shall be prepared in accordance with the requirements of
Condition 13 and 14 above and submitted to the Planning Authority in writing for approval.   
Reason: To ensure that risks from land contamination to the future users of the land and neighbouring
land are minimised, together with those to the water environment, property and ecological systems,
and to ensure that the development can be carried out safely without unacceptable risks to workers,
neighbours and other offsite receptors. 
16. Contaminated Land Part 5 of 5 (Validation of Approved Remediation Strategy): 
Following completion of the remediation works, in accordance with the approved Indicative Phasing
Plan, including remediation of localised areas identified as requiring remediation under the terms of
Condition 12 (and where applicable, Condition 15) above, a Validation Report signed by a Chartered
Environmental Engineer for the respective phase of development and/or localised area shall be
submitted to the Planning Authority for approval in writing to confirm that the remediation works have
been carried out in accordance with the terms of the Remediation Strategy. 
Reason: To ensure that the remediation works have been carried out in accordance with the approved
Remediation Strategy. 
17. Prior to the commencement of importation of fill materials, the proposed earthworks specification
including acceptance criteria for the imported materials shall be submitted to the Planning Authority
for approval.  The acceptance criteria shall be applicable to both the proposed site end use and any
interim period where the site is maintained as public open space prior to any subsequent development
applications. The presented criteria shall be derived in accordance with LCRM and industry best
practice and include consideration of risks to human health, the water environment, property and
ecological receptors. 
Reason: To ensure that risks from land contamination to the future users of the land, neighbouring
land, to the water environment, property and ecological systems, are minimised and to ensure that the
development can be carried out safely without unacceptable risks to workers, neighbours and other
offsite receptors. 
TREES 
18. Prior to the commencement of or on submission of a further application for development, a
Compensatory Tree Planting and Landscape Scheme, in accordance with Biodiversity Net Gain (BNG)
metrics or a Tree Valuation System, such as CAVAT method, shall be submitted to the Planning
Authority for approval. 
All replacement trees must be: 
• Native or climate-resilient species, appropriate to the local landscape character.
• Selected to enhance biodiversity, amenity value, and long-term canopy cover of the site.
• Avoid species known to be vulnerable to pests or diseases prevalent in the region (e.g., Fraxinus).
• Replacement trees must be sourced from a reputable nursery and grown in accordance with BS     
8545:2014 “Trees: From Nursery to Independence in the Landscape”.
• Trees should be supplied in the maximum girth that the landscape budget will allow. 
Reason: In the interests of visual amenity and biodiversity enhancement. 
Page 25 of 154

Page 26

19. Prior to the commencement of or on submission of a further application for development, an
Arboricultural Report shall be prepared and submitted to the Planning Authority for approval to
demonstrate that soil amelioration has or will be undertaken to ensure suitable rooting conditions,
together with an Aftercare Program which shall be enacted for two years after the completion of
compensatory planting.   
For the avoidance of doubt, soil amelioration shall include: soil testing to confirm suitability for tree
establishment, and amendment as required; decompaction of soil (no less than 3x pot size of trees to
be planted) and removal of potential contaminants; and incorporation of organic matter and soil
conditioners if required.  An Aftercare Program shall include: regular watering during dry periods;
provision of fertigation as required; mulching to suppress weeds and retain soil moisture; quarterly
inspections to identify ailing health, pests, diseases, and inadequate structural integrity; replacement
of any failed trees (within the maintenance period); and protection measures against vandalism and
mechanical damage (e.g., guards, fencing). 
Reason: In the interests of visual amenity and biodiversity enhancement. 
20. Tree removals shall be limited to those identified in the Tree Data Schedule in Appendix A of the
approved Arboricultural Impact Assessment, by LUC dated July 2025. 
Reason: In the interests of visual amenity and biodiversity. 
21. All retained trees, particularly those on the edge of development sites, shall be protected in accordance
with BS5837:2012 “Trees in Relation to Design, Demolition and Construction”. This shall include: 
• Temporary protective fencing (star pickets and bunting may suffice in this instance) shall be
installed to delineate the extent of the construction site (see AIA section 3.13 to 3.15), and isolate
retained trees from construction activity (see AIA section 2.15 to 2.17).
• Where fencing is impractical, ground protection measures (a thick mulch layer) must be enacted.
• No excavation, soil stripping, or level changes shall occur within the excluded tree areas.
• No storage of materials, machinery, or discharge of contaminants (e.g. concrete washings, 
machinery fuelling) shall occur within the excluded tree areas. 
• Other general protection advice as detailed in the approved Arboricultural Impact Assessment, by
LUC, at paragraphs 3.17 to 3.20. 
Reason: To ensure the protection of trees and tree root protection areas for the duration of the
development. 
22. Within one year of the completion of the development, details of a Project Arborist (with a minimum
Level 5 qualification in arboriculture) engaged to enforce the above conditions and to certify
compensatory planting at the end of the maintenance period and the replacement of any trees lost
during the construction programme, shall be submitted to the Planning Authority for approval. 
Thereafter, the appointed Project Arborist shall engage with the Planning Authority on matters relating
to compensatory planting, including a planting schedule and soil amelioration, as appropriate. 
Reason: To ensure compensatory tree planting measures are implemented in the interests of visual
amenity and biodiversity enhancement. 
Page 26 of 154

Page 27

AIR QUALITY 
23. Prior to commencement of development, a Dust Management Plan and Dust Monitoring Plan shall be
submitted to the Planning Authority for approval in writing and shall contain details of the following: 
a) A description of all NRMM and manufacturer guarantee of emission limits. Power generation for
NRMM should avoid the use of diesel generators wherever possible and evidence of connection to
electrical supply should be provided. 
b) A plan showing the location of haul roads with a minimum distance of 250m from sensitive
receptors; where this is not achievable, detailed mitigation as outlined in condition 2 a) above, shall
be provided accordingly. The plan shall also show all site entrance/exit points, trackout routes and
wheel wash facilities for each phase of work together with, one or more separate paved parking areas
for off-site vehicles such as staff cars with no access to the working areas.
c) Evidence that an adequate water supply is available, that bowser (s) can be readily deployed in
areas within 250m of sensitive receptors and that crushing plant includes spray bars to ensure
dampening of stockpiles prior to screening/crushing and dampening in other areas where wind speeds
are >5 m/s in the interests of inhibiting pathway effectiveness from source to receptors. 
d) Confirmation of whether seeding is proposed. 
e) Details of Process Supervision including name and contact details of persons responsible for
implementing the Dust Management Plan and for carrying out daily site boundary inspections for dust
deposition when works are within 250m of sensitive receptors. 
f) Details of emergency preparedness training to react quickly in case of any failure of the planned
dust mitigation. 
g) Location and installation of a meteorological station capable of measuring wind speed, direction
humidity and rainfall, which shall remain operational for the duration of the works. 
h) Details of Dust Monitoring Procedures. 
Reason: In the interests of air quality and protection of amenity. 
24. Dust Monitoring as required by condition 23 above, shall include the following procedures: 
a) Baseline air quality monitoring at the site boundary closest to the sensitive receptors for a minimum
period of three months. For the avoidance of doubt, this shall consist of three months of ambient PM10
and PM2.5 monitoring, preferably during autumn months, using a continuous analyser at 4 locations
in areas of free air flow not influenced by other sources, including: the southern boundary of TC1-TC3
adjacent to the College; the northern boundary of the Meadowhead site closest to the dwellings at
Roedeer Drive and Ravenscliff Road; the southwest of Meadowhead closest to Old Meadow
Walk/Rosebay Drive and, the south-east of Meadowhead closest to Meadowhead Road.  
b) Monitoring as specified for baseline assessment shall be carried out from the start of the period
when the mineral work activities are within 250m of the identified sensitive receptors within each of
TC1-TC3 and Meadowhead sites. The monitoring method shall be capable of raising an alarm when
an agreed trigger level is breached such that onsite actions, including additional water suppression or
cessation of operation of a particular activity can be implemented. 
c) Frisbee-type deposition gauges shall be deployed for three separate 4-week periods at the same
locations and analysed at an approved laboratory. 
d) All monitors are to be located in an area of free air flow not influenced by other sources such as
nearby roads. 
e) Results of monitoring during the operational phase shall be shared with the NLC Protective
Services on a monthly basis. Where more than six months of compliance monitoring is obtained in
conjunction with the absence of any complaints and activities are still within 250m of sensitive
receptors, it may be possible to cease site boundary monitoring until activities move to another part of
the site within 250m of sensitive receptors. 
f) Introduction of additional plant shall be notified to NLC Protective Services and the requirements
for monitoring to recommence examined. 
Reason: In the interests of air quality and protection of amenity. 
Page 27 of 154

Page 28

PHASING PLAN AND PROGRAMME OF WORKS 
25. Prior to the commencement of the development, a detailed Phasing Plan, Phasing Timetable and
detailed Programme of Works in the form of a report shall be submitted to the Planning Authority for
approval in writing.  Thereafter, any changes to the approved Phasing Plan, Phasing Timetable and
Programme of Works shall be submitted in writing to the Planning Authority for approval.   
Reason: To clarify the sequence of the site investigation and remediation works, to aid communication
between all parties involved and to allow flexibility within the phasing and programme of works. 
BIODIVERSITY AND LANDSCAPE PLAN AND AFTERCARE 
26. Prior to the commencement of or on submission of a further application for development, a Biodiversity
Report and Biodiversity/Landscape Plan, shall be submitted to the Planning Authority for approval in
writing.  For the avoidance of doubt, the Biodiversity and Landscape Plan shall contain details of
biodiversity enhancement, a planting schedule and details of management thereafter. 
Reason: In the interests of natural conservation and visual amenity. 
PROTECTED SPECIES SURVEYS 
27. If the development has not commenced on site within one year of the previous protected species
surveys, updated protected species surveys shall be undertaken and submitted to the Planning
Authority for approval in writing.  In any event, the following requirements shall be met prior to
commencement of the development:
a) Preworks surveys for badger shall be undertaken at each phase to check whether any new setts
have been created within 30m of the development. These shall be completed no more than six months
before construction works are scheduled to commence and shall be submitted to the Planning
Authority for approval. Thereafter, the Main Contractor should undertake periodic update badger
surveys to safeguard legal compliance during works.
b) Security lighting to be used at the site shall be directed away from woodland treelines to be retained
avoid disturbance of roosting and commuting/ foraging bats, in line with the Bat Conservation Trust
(BCT) bats and artificial lighting guidance. 
c) Should bats be identified at any stage of the proposed works, all activity within the vicinity must 
cease immediately and a qualified ecologist and/ or NatureScot must be contacted for further
assistance
d) Vegetation removal works shall, if possible, avoid the nesting bird season (beginning of March –
August, inclusive). If works cannot avoid the nesting season, a nesting bird check shall be conducted
by a suitably qualified ecologist prior to vegetation clearance (no longer than 48 hours before works). 
Reason: To safeguard and protect nature conservation interests 
COMPLIANCE OFFICER 
28. Prior to the commencement of the development, full details of the party to act as a Compliance Officer,
shall be submitted to and approved in writing by the Planning Authority. The Compliance Officer shall
undertake monitoring of the development and operations including archaeology, dust and air quality,
hydrology, hydrogeology, flood risk, noise, transportation, soils, waste management,
ecology/biodiversity and tree removal and retention for the duration of the development and shall liaise
with the Planning Authority on reasonable notice by the Planning Authority. 
Reason: To ensure liaison between the Developer and the Planning Authority is established in matters
relating to monitoring the works and evaluating compliance with this permission. 
Page 28 of 154

Page 29

COMMUNICATIONS STRATEGY AND APPOINTED LIAISON 
29. Prior to the commencement of the development, the developer shall establish a Communications
Strategy, such as a dedicated website to inform the public of the phasing and programming of the
development together with details of the party or persons to act as appointed liaison between the
developer and the community in respect to queries and/or complaints. The details of the
Communication Strategy shall be submitted to the Planning Authority in writing for approval.  The
appointed liaison shall also liaise with relevant council departments on reasonable notice by the
Planning Authority in respect to any complaints received by the Council concerning the development. 
Reason: To ensure clear and effective communication between the public, the developer and
relevant council departments. 
COAL MINING LEGACY 
30. Prior to the commencement of the development, a scheme of intrusive site investigations to establish
the risks posed to the development by past coal mining activity, shall be submitted to the Planning
Authority for approval in consultation with the Mining Remediation Authority: 
Reason: In order to inform the extent of remedial works required to facilitate further development at
this site. 
31.  Following, approval of the scheme of intrusive site investigations as required by condition 30 above,
and prior to or on submission of any further application for development of the site, any remediation
works and/or mitigation measures to address land instability arising from coal mining legacy, as may
be necessary, shall be submitted to the Planning Authority for approval or shall be shown to have been
implemented on site in full. This shall include the submission of a plan to illustrate the exact location
(and grid-coordinates) of any mine entry found within the site, including the calculated zone of influence
(no build exclusion zones) of any mine entry within or within influencing distance of the site. The
intrusive site investigations and remedial works shall be carried out in accordance with authoritative
UK guidance 
Reason: To ensure that the site is made safe and stable for the development proposed. 
32. Upon completion of the remediation works where required in accordance with condition 31, a signed
statement or declaration prepared by a suitably competent person confirming that the site is, or has
been made, safe and stable for future development shall be submitted to the Planning Authority for
approval in writing. This document shall confirm the methods and findings of the intrusive site
investigations and the completion of any remedial works and/or mitigation necessary to address the
risks posed by past coal mining activity. 
Reason: To ensure that the site is made safe and stable for the development proposed. 
BULK MATERIALS EXTRACTION, IMPORTATION AND WASTE MANAGEMENT 
33. Upon commencement of extraction works, the Planning Authority shall be provided with a copy of the
relevant SEPA authorisation covering the excavation and off-site removal or materials and the
subsequent importation of fill materials to complete the platforming works. 
For the avoidance of doubt, this condition relates to the extraction, processing and off-site removal of
materials that do not fall under the requirements and conditions relating to the Contaminated Land
Remediation Strategy as required by conditions 12 and 13 above and is considered to consist of
activities that fall under the Waste Management Licensing (Scotland) Regulations 2011 for which
SEPA are the lead regulator. The applicant will be required to liaise with SEPA to obtain authorisation
in this regard. 
Reason: To ensure compliance with Policy 12 (Zero Waste) of NPF4 and to control the development
and ensure that the operational working practices as indicated in the submitted method statements by
K &T Plant Hire Ltd, align with other regulatory controls. 
Page 29 of 154

Page 30

CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP) 
34. Prior to the commencement of the material extraction and importation works, a Construction and
Environmental Management Plan (CEMP) shall be submitted to the Planning Authority for approval of
acceptable working methodologies regarding hours of operation and mitigation requirements,
including but not limited to, dust, noise, nuisance, impacts to the road network and impacts on trees
to be retained and on protected species and on adjacent SINCS and ancient woodland.  Thereafter
the approved CEMP shall be implemented to the satisfaction of the Council 
Reason: To ensure that impacts and risks from works to the future users of the land, neighbouring
land, to the water environment, property and ecological systems, are minimised and to ensure that the
development can be carried out safely without unacceptable risks and impacts to workers, neighbours
and other offsite receptors. 
ADVISORY NOTES 
Extraction Works 
The applicant is required to liaise with SEPA to obtain authorisation for the extraction works programme which
is primarily a waste management activity.  NLC will support SEPA in agreeing acceptable working
methodologies for the extraction works with regards to the mitigation requirements for dust, noise, nuisance
and impacts to the road network.    
Importation Works 
The applicant is required to liaise with SEPA to obtain authorisation for the importation works programme
which is primarily a waste management activity.  NLC will support SEPA in agreeing acceptance criteria
/remedial targets for the imported materials to confirm that these are acceptable for the proposed site use to
ensure that the development can be carried out safely without unacceptable risks to end users, the water
environment, property and ecological systems in addition to workers, neighbours and other offsite
receptors.  NLC will also support SEPA in agreeing acceptable working methodologies for the extraction works
with regards to the mitigation requirements for dust, noise, nuisance, and impacts to the road network.    
Mine entries 
Any form of development over or within the influencing distance of a mine entry can be dangerous and raises
significant land stability and public safety risks. As a general precautionary principle, the Mining Remediation
Authority considers that the building over or within the influencing distance of a mine entry should be avoided.
In exceptional circumstance where this is unavoidable, expert advice must be sought to ensure a suitable
engineering design which takes account of all relevant safety and environmental risk factors, including mine
gas and mine-water. Your attention is drawn to the Mining Remediation Authority Policy in relation to new
development and mine entries available at:
Building on or within the influencing distance of mine entries - GOV.UK 
Ground Investigations 
Any intrusive activities which disturb or enter any coal seams, coal mine workings or coal mine entries (shafts
and adits) requires a Mining Remediation Authority Permit. Such activities could include site investigation
boreholes, excavations for foundations, piling activities, other ground works and any subsequent treatment of
coal mine workings and coal mine entries for ground stability purposes. Application forms for Mining
Remediation Authority permission and further guidance can be obtained from The Mining Remediation
Authority’s website at:www.gov.uk/get-a-permit-to-deal-with-a-coal-mine-on-your-property 
What is a permit and how to get one? - GOV.UK (www.gov.uk) 
Shallow coal seams 
In areas where shallow coal seams are present caution should be taken when carrying out any on site
burning or heat focused activities. 
Page 30 of 154

Page 31

Background Papers: 
Consultation Responses: 
NLC Greenspace & Country Parks: received 31.03.25 and 19.08.25
NLC Greenspace & Country Parks (Tree Asset Manager): received 15.08.25 and 30.09.25 
NLC Protective Services (ENV H Air Quality): received 11.06.25
NLC Protective Services (ENV H Noise): received 16.09.25, 3.10.25 and 28.10.25
NLC Protective Services (ENV H Contaminated Land):  received12.05.25, 22.07.25 and 11.09.25
NLC Infrastructure & Transportation: received 01.04.25
NLC Infrastructure & Water Management: received 11.06.25, 18.08.25 and 29.10.25
NLC City Deal: received 02.09.25
Scottish Gas Network: received 21.01.25 
Scottish Water: received 07.10.25 
Coal Mining Remediation Authority: received 29.01.25 
Contact Information: 
Any person wishing to inspect these documents should contact Ann McGregor at 01236 632500 
Report Date: 
19 November 2025
Page 31 of 154

Page 32

APPLICATION NO. 24/01267/FUL 
REPORT 
1. Site Description 
1.1 The application site consists of two large parcels of land, both of which are located on the footprint of
the former Ravenscraig Steelworks site and on land within Ravenscraig Regeneration Area. The first
site, known as Meadowhead, occupies an area of 75 hectares (185 acres). The second site, known
as Town Centre 1-3 site (TC 1-3) occupies an area of 17.5 hectares (43 acres). Ravenscraig
Regeneration Area lies within the established General Urban area to the east of Motherwell town
centre, south of Carfin and north/northwest of Wishaw and, is supported by a revised Masterplan which
was approved in March 2018 (Ref: 18/00463/PPP).  Both the Meadowhead and TC1-3 sites feature
in the Council’s register of Derelict and Vacant (2024). 
1.2 Meadowhead lies east of Ravenscraig Sports Centre and New Craig Road and is predominantly flat
across most of its area, with stockpiled bunds located in the northern section of the site. The site slopes
steeply towards Ravenscraig Community Nature Park in the west, also known as ‘The Craig’, and
towards Ravenscraig Sports Centre to the northwest.  The site rises approximately 1 metre to the
eastern boundary before reaching the edge of the railway embankment of the Wishaw Deviation
railway line. Residential development lies immediately northwest of the site.   The site is characterised
by a mix of self-seeded broadleaved scattered trees and woodland, semi-improved neutral grassland,
bare ground and hardstanding.  More mature broadleaved woodland is present along the site
boundaries to the north and south and to the east which is associated with the former railway sidings
and current railway line.  A section of the South Calder Water, a major tributary of the River Clyde,
flows east to west in culvert through the northwestern section of the site. Currently no buildings or
structures are present across this site.   
1.3 The site known as TC 1-3 is located immediately north of Enterprise Way and New College Lanarkshire
Motherwell Campus. The site is characterised by neutral grassland and scattered scrub, with several
sections of self-seeded immature broadleaved woodland. In addition, a section of broadleaved
plantation woodland is present along the eastern boundary of the site.  The site gently slopes uphill
along its eastern boundary, rising to meet the elevation of Robberhall Road in the east.  Generally,
however, the topography of the site is relatively flat, having been levelled in places, including periods
of excavation and reprofiling earthworks, as part of Aspinwall remediation. The site is bound to the
west by open ground, including a pumping station and electrical substation, beyond which lie two
sustainable urban drainage system (SUDS) ponds. Further north, high voltage overhead electrical
cables extend eastward across the site. As with Meadowhead, no buildings or structures are present
across TC1-3. 
1.4 During Phase 1 of the development (TC 1-3 Cells 4-6 and Meadowhead Cell 1), access to the sites
will be taken from Enterprise Way.  During Phase 2 of the development (Meadowhead Cells 2 & 3),
access will be taken via Robberhall Road and New Craig Road. 
2. Proposed Development 
2.1 The current application follows approval of the revised Ravenscraig Masterplan and application for
planning permission in principle (PPiP) approved on 18 November 2020 (Reference: 18/00463/PPP)
for a mixed-use development consisting of residential development, education and community
facilities, business and employment uses, open space, a new mixed use town centre including retail,
leisure, business, residential and hotel uses and associated transport infrastructure on the site of the
former Ravenscraig Steelworks. 
2.2 The application is submitted by Ravenscraig Ltd, a joint venture comprising Barratt Redrow, Scottish
Enterprise and Tata Steel, and seeks full planning permission for the next stage of land remediation
works on two large parcels of land within the boundary of the approved (revised) masterplan, known
as Meadowhead (75 hectares) and TC1-TC3 (17.5 hectares). The duration of the permission sought
is 14 years. 
Page 32 of 154

Page 33

2.3 Meadowhead (Phase 1 and 2) is split into three separate cells as shown on the Indicative Phasing
Plan (Drawing No. RAVC-ACM-MHD-XX-DR-CIV-002131). Meadowhead Phase 1 (Cell 1) covers a
site area of 28.7 hectares (71 acres); Phase 2 (Cell 2) covers an area of 19.8 hectares (49 acres) and
Phase 2 (Cell 3) covers an area of 17 hectares (42 acres). TC1-3 (Phase 1) is also split into three
separate cells; TC1 (Cell 4) is 4.2 hectares (10.4 acres), TC2 (Cell 5) is 6.5hectares (16 acres) and
TC3 (Cell 6) is 6.6hectares (16.3 acres). 
2.4 The remediation works involve two broad stages: 
1) Stage 1 - extraction, crushing, screening and removal of waste material (i.e. inert soil and
stones). This process involves the excavation of waste material to a depth of 4m in each cell,
where at the point of extraction the material will then be loaded onto a mobile crusher or mobile
screener by an excavator and processed. All waste materials will be imported to raise site
levels within the site and will be placed within the cells as engineered fill. Soils deemed
unsuitable or unacceptable for this purpose will be placed on an impermeable membrane on
a vacant area within the site boundary before being removed offsite to either the source site
for a temporary period only or to a suitably licensed facility. In the case of the latter, transfer
notes will be retained for soils removed offsite; a process that will be managed by SEPA.  The
importing of soils onsite will be an iterative process in order to achieve the proposed restoration
levels. Whilst the level of fill required across all cells will not be consistent due to the existing
topography of the site, adjoining cells will have no greater than 3m height difference between
them at finished restoration levels.  The amount of waste material recovered from TC1-3 is
expected to be in the region of 382,800 m³ and from Meadowhead, is expected to be around
2,350,000 m³; most if not all of this material will be crushed and screened for use as
engineered fill. 
2) Stage 2 - remediation and reinstatement of each cell.  Following extraction, reinstatement and
restoration with clean soils will be undertaken across the site. TC1-3 will be treated in Phase
1 and Meadowhead will be treated in two separate phases (Phase 1 and 2).   Each cell within
Meadowhead and TC1-3 will be restored before work commences on the next cell. Imported
soils will be spread and rolled in 1m layers in strips following the pattern of extraction.
Assessment of the suitability of the materials for use will be undertaken via validation testing
where necessary, and the works will be carried out in accordance with SEPA's Land
Remediation & Waste Management Guidelines. Details of the material being imported together
with verification will be agreed with SEPA as the lead regulator of waste management. The
amount of inert material expected to infill each site to the required levels is 2,260,000 m³ in
the case of Meadowhead and 410,000 m³ in the case of TC1-3. Finished site levels are shown
on Drawings Numbers: RAVC-ACM-TC-XX-DR-CIV-002103 (TC1-3) and RAVC-ACM-MHD-
XX-DR-CIV-0002103 (Meadowhead).   
2.5 The depth of clean soils that will be imported and placed as cover across the sites vary depending on
proposed site end use but are likely to range from 0.2m to 0.4m in landscaped areas, and 0.6m to
1.0m in private gardens and in places the depth of clean soil cover will be significantly thicker than
required.  The Applicant has advised that a full assessment of the clean cover requirements will be
undertaken as part of the future development design, including a review of surveys undertaken during
the platforming works. 
2.6 It is understood that a scheme of intrusive site investigations will also be carried out to establish the
risks posed to the development by past coal mining activity. However, it is noted that there are no
plans within the current proposal to remediate the site to address land instability arising from coal
mining legacy. 
Page 33 of 154

Page 34

3. Applicant’s Supporting Information 
3.1 The application is accompanied by the following supporting information: 
• Air Quality Impact Assessment, Airshed, 6 December 2024
• Design and Access Statement, Cooper Cromar, December 2024
• Drainage Assessment, Aecom, 11th December 2024
• Flood Risk Assessment, Aecom, 11 July 2025 updated 17 July 2025
• Ecological Appraisal Report, LUC, December 2024, updated Badger Report, LUC December
2025
• Health and Safety Plans, K&T Plant Hire Limited, 11th November 2025
• Method Statements Crushing & Screening, K&T Plant Hire Limited, 11th November 2025
o Method Statements Reinstatement & Restoration, K&T Plant Hire Limited, 11th November    
2025
• Noise Impact Assessment, Airshed, 26th November 2024 updated 24 July 2025
• Preapplication Consultation Statement, Ryden, November 2024
• Initial Contamination Assessment, GDG, 10th December 2024 updated 19th August 2025
• Construction Traffic Management Plan, SWECO, 13th November 2024
• Waste Management Strategy, Ryden, submitted 28 May 2025 and resubmitted 21 July 2025
• Arboricultural Impact Assessment, LUC, July 2025 
4. Site History 
• 02/00290/ADV Erection of a non-illuminated free-standing sign – approved June 2002
• 15/01697/AMD Section 42 Application for Non-Compliance with Condition 12 of Planning
Permission Ref. 01/00758/OUT for the Submission of an Area Planning Brief Covering the Ash
Hill Area of Ravenscraig – approved May 2016
• 18/01363/PAN Civic Park Incorporating informal Sport and Leisure Activities and Associated
Works. Support Future Residential Developments – comments September 2018
• 18/00463/PPP Revision of Mixed-Use Development Approved under Planning Permission
Ref:01/00758/OUT Comprising Residential Areas, Educational/Community Facilities,
Business and Employment Uses, Open Space including Town Park, Hotels, a New Town
Centre including Retail, Leisure, Business and Housing with associated Transport
Infrastructure – approved 18 November 2020.
• 18/01684/EIASCR Request for EIA Screening Opinion: Proposed Civic Park Development –
EIA not required. Decision November 2018
• 18/01829/FUL Development of a New Urban Park and Greenspace – approved February 2019
• 22/01063/PAN Remediation of land and creation of development platform including formation
of accesses, roads, drainage, utilities and associated works – approved September 2022.
• 24/01126/EIASCR Request for EIA Screening Opinion:  Proposed extraction and remediation
works at Meadowhead and TC1-3 – EIA not required. Decision November 2024.
• 25/01021/CLP Installation of a gate (max 1.9m agl) to secure an operational area west of the
existing park kiosk and match the height of adjacent screen fencing – approved September
2025. 
5. Development Plan 
5.1 The Development Plan consists of the National Planning Framework 4, Adopted on 13th February
2023 (‘NPF4’) and The North Lanarkshire Local Development Plan, Adopted 6th July 2022, (‘the LDP’). 
The following NPF4 and LDP policies considered relevant to the current application are as follows: 
• NPF4 Policy 1 Tackling the climate and nature crises
• NPF4 Policy 2 Climate mitigation and adaptation 
• NPF4 Policy 3 Biodiversity 
• NPF 4 Policy 4 Natural places
• NPF 4 Policy 6 Forestry, woodland and trees
• NPF4 Policy 9 Brownfield, Vacant and Derelict Land and Empty Buildings 
• NPF4 Policy 12 Zero Waste 
Page 34 of 154

Page 35

• NPF4 Policy 13 Sustainable Transport 
• NPF4 Policy 14 Design, Quality and Place
▪ NPF4 Policy 22 Flood Risk 
• NPF4 Policy 23 Health and Safety
• LDP Policy PROM LOC1 Regeneration Priorities 
• LDP Policy PROM LOC2 Business Development Sites
• LDP Policy PROM LOC3 Housing Development Sites
• LDP Policy PP1A Purpose of Place (Strategic Town Centres)
• LDP Policy PP2A Purpose of Place (Strategic Business Centres)
• LDP Policy PP3 Purpose of Place (General Urban Area) 
• LDP Policy PROT A Natural Environment and Green Network Assets 
• LDP Policy EDQ 1 Site Appraisal 
• LDP Policy EDQ 2 Specific Features for Consideration 
• LDP Policy EDQ 3 and Quality of Development 
5.2 Also material to the determination of the application is the following Council guidance: 
• Scottish Biodiversity Strategy to 2045
• PAN 50 Controlling the Environmental Effects of Surface Mineral Workings, Annex A,
• Ravenscraig Regeneration Area Strategy 
• NLC Active Travel Strategy 2021-2031
• NLC Planning and Noise Supplementary Guidance
• NLC Parking Standards Guidance 2024  
6.         Consultations 
6.1 NLC Greenspace & Country Parks has no objection to the proposed development subject to conditions
relating to the provision of compensatory biodiversity measures and further protected species surveys
if the development has not commenced within one year of the previous submitted surveys. 
6.2 NLC Greenspace & Country Parks (Tree Asset Manager) has no objection to the proposed
development subject to conditions relating to tree protection measures, soil amelioration measures,
compensatory tree planting scheme and certification of the replacement of trees by a Project Arborist
and, establishment of an aftercare and maintenance program.   
6.3 NLC Protective Services (ENV H Air Quality) has no objection to the proposed development subject
to conditions relating to dust mitigation including, a Dust Management Plan (DMP) and Dust Monitoring
Plan and evidence that an adequate water supply is or can be made available. 
6.4 NLC Protective Services (ENV H Noise) has no objection to the proposed development subject to
conditions relating to noise limits and the protection of amenity of noise sensitive receptors, hours of
operation and noise monitoring. 
6.5 NLC Protective Services (ENV H Contaminated Land) has no objection to the proposed development
subject to conditions to ensure submission of completed additional investigation works and localised
additional targeted investigation works including risk assessment, appraisal of remedial options, a
Remediation Strategy and validation report to provide evidence of completion of the remediation
works. 
6.6 NLC Infrastructure & Transportation has no objection to the proposed development subject to
conditions to ensure annual submission of an updated Construction Traffic Management Plan (CTMP),
submission of details to show the location and design of mud/wheel wash facilities, and details of a methodology
for carrying out a dilapidation survey or roads around the development site.   
Page 35 of 154

Page 36

6.7 NLC Infrastructure & Water Management has no objection to the proposed development subject to
conditions to address details of the pollution prevention plan / construction phase plan (CPP) and
construction method statements to manage surface water runoff during construction, evidence that a
construction CAR licence (or new equivalent) has been obtained from SEPA, evidence that a viable
surface water disposal point will be in place for the site prior to commencement and, to ensure
submission of a revised Flood Risk Assessment and Drainage Strategy to demonstrate that there will
be no increase in flood risk to property/land and/or sensitive/critical infrastructure on and off the
application site for up to and including the 0.5% AEP (1:200 year) plus climate change allowance storm
event. 
6.8 NLC City Deal has no objection to the proposed development subject to conditions to address an
overall masterplan for surface water drainage. This would ensure that the proposed new link road
through the Ravenscraig Masterplan site (Ravenscraig Access Infrastructure South) makes provision
for future development, including consideration of 1 in 200 year + climate change overland flow paths.
It is advised that without the strategy in place there is significant risk of the requirement to carry out
further construction works to the proposed link road to facilitate future drainage infrastructure, leading
to additional costs and disruption. 
6.9 Scottish Gas Network (SGN) has no objection to the proposed development and has confirmed that
SGN’s high pressure, transmission gas pipeline near the site will not be affected by the proposed
developed. 
6.10 Scottish Water has no objection to the proposed development. However, advises that it will not accept
any surface water connections to its combined sewer system except in limited exceptional
circumstances, including, for example, a legal or physical justification or due to technical challenges. 
6.11 Coal Mining Remediation Authority has no objection to the proposed development subject to conditions
to ensure submission of a scheme of intrusive site investigations and where necessary remediation
works and/or mitigation measures to address land instability arising from coal mining legacy followed
by a declaration prepared by a suitably competent person confirming that the site is, or has been made,
safe and stable for future development. 
7.         Representations 
No letters of representation have been received. 
8.          Planning Assessment 
8.1 Section 25 (1) of the Town and Country Planning (Scotland) Act 1997 as amended (‘the Act’) provides
that, where in making a determination under the Planning Acts, regard is to be had to the Development
Plan unless material considerations indicate otherwise. The Development Plan consists of the National
Planning Framework 4 (NPF4), February 2023, and the North Lanarkshire Local Development Plan
(LDP), July 2022. The determination of the application must be made in accordance with both and in
the event of any incompatibility between the two, NPF4 being later in date is to prevail (Section 24 (3)
of the Act). Statements in NPF4 are also material to the determination of the application. With regard
to decision making, development that accords with the Development Plan should be approved unless
the adverse effects of doing so would significantly and demonstrably outweigh any benefits that the
development could expect to deliver. 
Background 
8.2 Outline planning permission was granted in 2005 for redevelopment of the former Ravenscraig and Lanarkshire
Steel Works site in line with a comprehensive masterplan, which sought to provide a major leisure-led regional
retail development on the site. The recession of 2008 and changing market conditions meant that it was not
possible to deliver the scale of development originally envisaged and a revised masterplan (and planning
permission in principle Ref: 18/00463/PPP) was submitted to the Planning Authority in 2018 and approved in
November 2020.  Area Planning Briefs (APB) were subsequently brought forward to allow various elements of
the original masterplan to be developed, including housing, Ravenscraig Regional Sports Facility, New College
Lanarkshire together with various infrastructure elements that have also been implemented, including roads,
ground remediation works, installation of services and development platforming.  
Page 36 of 154

Page 37

8.3 Both sites to which this planning application relates (Meadowhead and TC1-3), fall within the site
boundary of the original masterplan (2005) and the revised masterplan (2018) and, are identified for
the delivery of a mix of uses including residential and mixed commercial uses in accordance with the
approved revised masterplan 2018. 
Preapplication Consultation 
8.4 The proposal is classed as ‘major’ development under the provisions of the Town and Country
Planning Hierarchy of Developments) (Scotland) Regulations 2009 and is therefore subject to statutory
pre-application consultation in accordance with the Town and Country Planning (Development
Management Procedure) (Scotland) Regulations 2013 as amended by the Town and Country Planning
(Pre-Application Consultations) (Scotland) Regulations 2021.  A Proposal of Application Notice (PAN)
was submitted on 2nd August 2024. Newspaper adverts promoting community consultation exhibitions
were placed in the Motherwell Times and the Wishaw Press. Thereafter, two in person public events
were held on 29th August 2024 and 26th September 2024 from 2.30pm to 8pm at the Ravenscraig
Regional Sports Facility. An online website was also hosted by the Applicant.  Following public
consultation, a Pre-application Consultation Report (PAC Report) was prepared to detail how the
community consultation was undertaken, together with issues raised during the consultation. The PAC
Report is submitted in support of the current application.  In summary, the first public consultation
event generated 22 feedback forms; 16 of which were supportive of the proposals, 5 of which were
unsure and 1 did not state a preference. The second public event generated 4 feedback forms; all of
which were supportive of the proposals.  Details of the consultation responses are contained in the
PAC Report produced by Ryden, dated November 2024. 
EIA Screening 
8.5 The proposed development covers a combined area of over 90 hectares (Meadowhead occupies an
area of 75 hectares and TC1-3  occupies an area of 17.5 hectares) and therefore requires to be
screened under Schedule 2 (10) (b) ‘Urban development projects exceeding 0.5 hectares’ of the Town
and Country Planning (Environmental Impact Assessment) Regulations 2017, to determine whether
the development would require an Environmental Impact Assessment (EIA). The development is not
located in a sensitive area in the context of the EIA Regulations and due to the nature, scale, and
location of the development, is unlikely to have significant adverse effects on the environment. The
development is not therefore considered to be EIA development.  This was confirmed in the Planning
Authority’s EIA Screening Opinion response (Ref: 24/01126/EIASCR). Whilst it is anticipated that the
development will generate some adverse effects during Stage 1 works (extraction, crushing and
screening and removal of waste material) it is considered that the effects can be appropriately
mitigated by conditions that would be attached to the grant of planning permission. 
Principle of the Development 
8.6 The redevelopment of the former steelworks site at Ravencraig is identified as a key redevelopment
project in Part 3, Annex C – Spatial Planning Priorities of NPF4 and is supported on the basis that it
will reduce the overall proportion of vacant and derelict land in Scotland to deliver a productive and
low carbon, 20-minute neighbourhood that includes improved transport connectivity.  Similarly, the
wider Ravenscraig site (and revised masterplan 2018) is identified for regeneration in the LDP
Ravenscraig Regeneration Area Strategy and is 1 of 6 Strategic Town Centres and 1 of 5 Strategic
Business Centres promoted in the LDP for priority through the following policies: 
• Policy PROM LOC1 (Regeneration Priorities) promotes the physical regeneration and
sustainable growth of the strategic centres.  The strategic centres will be given priority in order
that they can deliver development of the right amount and right quality to the right place for
the benefit of the communities that they affect; 
• Policy PROM LOC2 (Business Development Sites) promotes and directs business
development to the Strategic Business Centres identified in the Plan; and 
• Policy PROM LOC3 Housing Development Sites promotes housing development on sites
identified for housing in the Plan in order to maintain a sufficient supply of housing land. 
Page 37 of 154

Page 38

8.7 More generally, Ravenscraig Regeneration Area is located in the General Urban Area where Policy
PP3 Purpose of Place (General Urban Area) of the LDP applies. PP3 seeks to maintain and improve
the level of amenity in urban areas, by encouraging development that is in keeping with the residential
character of these areas and encouraging diversity in more mixed-use areas.   
8.8 In terms of the LDP housing land supply, Meadowhead is allocated for housing as follows: 
• NLMW0573L1 Ravenscraig P Phase (Nether Johnston) - indicative capacity 952 units.
• NLMW0573L2 Ravenscraig P Phase (Nether Johnston) - indicative capacity 105 units
• NLMW0573O1 Ravenscraig Craigneuk/Roman Road - indicative capacity 567 units
• NLMW0573O2 Ravenscraig Craigneuk/Roman Road - indicative capacity 63 units 
8.9 TC1-3 is allocated in the LDP for a mix of uses including, housing and a mix of Class 4 Business,
Class 5 General Industrial and Class 6 Storage or Distribution uses with limited ancillary uses
including, Class 1A Shops (Convenience), Financial and Professional Services, Class 3 Food and
Drink and, Class 7 Hotels and Hostels as follows: 
• NLMW1287A Ravenscraig New Town Centre - indicative capacity 270 units
• NLMW1287B Ravenscraig New Town Centre - indicative capacity 30 units
• NLS00458 Business Quarter, Prospecthill Road, Ravenscraig – mixed use development in
accordance with Policy PP2A Purpose of Place (Strategic Business Centres) 
8.10 The current application, proposing extraction, crushing and screening of waste material to use as
engineered fill followed by remediation of the Meadowhead and TC1-3 sites, aims to deal with the long
standing legacy of contaminated land at the former steelworks site and to reduce the overall proportion
of vacant and derelict land in preparation for future redevelopment of the sites for the above land uses.
The application therefore supports the aims and objectives of Part 3, Annex C spatial planning priorities
(reuse of brownfield land) of NPF4, and the respective regeneration, business and housing priorities
of Policies PP3, PROM LOC1, PROM LOC2 and PROM LOC3 of the LDP. 
Climate Mitigation and Adaptation 
8.11 Policy 1 (Tackling the climate change and nature crisis) and Policy 2 (Climate mitigation and
adaptation) of NPF4, both seek to encourage, promote and facilitate development that addresses
climate change, emissions and nature crisis.  The decontamination and remediation of Meadowhead
and TC1-3 sites will facilitate the sustainable redevelopment of a large proportion of brownfield land
in the General Urban Area, thereby conserving greenfield land, restoring natural assets, including soil,
water and biodiversity, and avoiding urban sprawl which is a major contributor to greenhouse gas
emissions. The reuse of excavated soil as engineered fill and utilisation of the existing transport (and
other) infrastructure in the area will significantly reduce the embodied carbon emissions associated
with construction in accordance with the over-arching requirements Policies 1 and 2 of NPF4. 
Access and Transportation 
8.12 Policy EDQ3 (Quality of Development) of the LDP provides that new development should address
safe, secure, and convenient access into and through the development, together with sustainable and
safe access for cars, where required. Policy EDQ3 is generally compatible with Policy 13 b)
(Sustainable Transport) of NPF4 which similarly requires development to incorporate safety measures,
including safe crossings for walking and wheeling and to adequately mitigate against any impacts on
local public access routes through, for example, reduction in the number and speed of vehicles. 
8.13 The application is accompanied by a Construction Traffic Management Plan (CTMP), by SWECO,
dated 13th November 2024 and a Construction Phase Health and Safety Plan (CPHSP), by K&T Plant
Hire Limited (Principal Contractor). The CTMP is a live document that would be developed throughout
the duration of the proposed development and would be updated and maintained as works progress.  
The CTMP provides details of vehicular access to each of the sites during the extraction and
remediation phases including construction traffic routing; details of the surrounding road network
including speed limits; active travel routes; and proximity to local bus stops and rail services, together
with bus service timetables; and trip generation data for construction vehicles to 2036 as follows: 
Page 38 of 154

Page 39

• Vehicular access to each site and construction traffic routing - access to TC1-3 is achieved
via Enterprise Way and, to Meadowhead is achieved via Robberhall Road and New Craig
Road as shown in Fig 2.1 of the CTMP. 
• Surrounding road network - Enterprise Way, providing access to TC1-3, has a speed limit of
40 mph. It is a two-way single carriageway road that connects to Robberhall Road. Robberhall
Road is a two-way single carriageway, with a speed limit of 40mph, providing access to the
A721 to the south and to New Craig Road to the north.  Robberhall Road would be used by
construction vehicles for both site entrances (TC1-3 and Meadowhead) but would primarily be
used by vehicles coming from the south due to the connection to the A721.  New Craig Road
is a two-way dual carriageway that will provide access to Meadowhead. It has a speed limit of
40 mph road and connects to the A723 and the B7029 to the north and to Robberhall Road in
the south. The direct connection between New Craig Road and the A723 will mean that it will
serve as a primary route for vehicles coming from the north. 
• Active travel routes - existing footways are on Enterprise Way, New Craig Road and
Robberhall Road. Therefore, pedestrian access to both sites is possible. Two new active travel
links exist on New Craig Road and Robberhall Road that offer access to both cyclists and
pedestrians to the respective sites. Pedestrians may use the shared use path between
Craigneuk and Ravenscraig Regional Sports Facility and the path between Craigneuk and
New College Lanarkshire. 
• Proximity to local bus stops and rail services – details of bus service provision are contained
in Table 3.3 of the CTMP.  There are frequent bus services (every 30 mins) from Motherwell
train station to Ravenscraig Sports Centre and New College Lanarkshire and from Hamilton,
Coatbridge and Glasgow to Vesuvius Drive (Craigneuk St), Motherwell which lies to the south
of the Meadowhead site.   
• Trip generation data – the estimated two-way trip data for TC1-3 over the construction period
of 3.5 years (Phase 1) is 41792 HGVs. Estimated two-way trip data for Meadowhead site over
the construction period of 11.5 years (Phases 1 and 2) is 261456 HGVs. This is shown in
Table 2 and 3 of the CTMP Addendum dated 17 November 2025. 
8.14 The CTMP and CPHSP provide details for the safe, secure, and convenient access into and through
the development, together with sustainable and safe access and crossings for walking and wheeling
where required in accordance with Policy EDQ3 of the LDP and Policy 13 b) of NPF4. NLC
Infrastructure and Transportation has been consulted and has no objection to the proposed
development subject to conditions; one of which requires the developer to submit a methodology for
the carrying out a Dilapidation Survey in order to identify any pre-existing defects on the local road
network surrounding the development sites. Surveys should preferably be carried out periodically for
the duration of the development to assess the rate of deterioration and should be repeated post-works
to apportion the costs of road deterioration.  In view of the duration of the proposed development (14
years) coupled with the anticipated trip generation data over the construction period, the requirement
for a Dilapidation Survey is considered to be reasonable in the circumstances and is in accordance
with Policy 13 g) (Sustainable Transport) of NPF4 which provides that development proposals that
have the potential to affect the operation and safety the road networks should be fully assessed to
determine their impact and where adverse impacts are anticipated, the cost of mitigation measures
required to ensure the continued safe and effective operation of the network should be met by the
developer. 
Page 39 of 154

Page 40

Ecology and Biodiversity 
8.15 Policy PROT A (Natural Environment and Green Network Assets Category 5) of the LDP provides that
development will only be permitted where an appraisal has demonstrated that protected species would
not be compromised and/or that any significant adverse effects on protected species can be mitigated
through planning conditions. Similarly, although broader in context, Policy 4 (Natural Places) of NPF4,
provides that unacceptable impacts on the natural environment will not be supported. Policy 3
(Biodiversity) of NPF4 requires that development proposals must contribute to the enhancement of
biodiversity whilst, the Scottish Biodiversity Strategy to 2045, a high-level Strategy setting out a 2045
vision for biodiversity in Scotland, includes statutory targets for nature restoration which aim to halt
biodiversity loss by 2030 and restore Scotland’s natural environment by 2045. 
8.16 The application is supported by an Ecological Appraisal Report by LUC, dated December 2024. The
Report contains details of an extended phase 1 habitat survey including a badger survey, preliminary
bat roost assessment survey and a Biodiversity Enhancement Statement.  An updated badger survey
was further submitted in September 2025.  A desk study was also undertaken to identify existing
records of statutory designated sites within 2km and non-statutory designated sites and protected/
notable species within 1km of the site.     
Existing Habitats 
8.17 There are no statutory or non-statutory designations that cover the site.  Habitats present within the
site are characteristic of ‘Open Mosaic Habitat’ on previously developed land. Due to the level of
remediation required, most of the open mosaic habitat will be cleared.  However, retention of existing
woodland corridors around the edges of the sites, will help to maintain wildlife corridors over the longer
term, allowing movement of species across the site. 
Adjacent Designated Sites 
8.18 Three non-statutory designated sites for nature conservation (SINC) and a section of ancient woodland
are located immediately adjacent to Meadowhead.  These are: 
• South Calder Water/ Ravenscraig Gorge SINC which is located immediately to the north of
the Meadowhead site and is designated for woodland and running water habitats. This
includes a section of ancient woodland of semi-natural origin. 
• Ravenscraig Railway Sidings East SINC which is located immediately to the south of the
Meadowhead. Although there was no feature listed in the designation, the area is dominated
by woodland habitat. 
• Ravenscraig Railway Sidings West SINC which is located immediately to the south of the
Meadowhead. Although there was no feature listed in the designation, the area is dominated
by woodland habitat 
8.19 The above designations are structurally and functionally linked to Meadowhead, due to the presence
of existing woodland habitat within the Meadowhead site. The proposed remediation works include
retention of woodland (in the north, south and eastern sections of Meadowhead) adjacent to the above
designations.  This will reduce the potential impacts of the development on the SINCS. Retention of
woodland within Meadowhead (and TC1-3) is shown in Appendix A, Figure 4 (Drawing Number:
13007-LUC-XX-XX-DR-L).     
Protected Species 
8.20 Field surveys were conducted for badgers, bats and nesting birds; the details of which are contained
in the Ecological Appraisal.  The Appraisal recommends precautionary mitigation via conditions, which
are detailed in conditions 26, 27 and 28 of this report. 
Page 40 of 154

Page 41

Biodiversity Enhancement 
8.21 Meaningful biodiversity and ecological enhancement cannot be incorporated at this stage of the
development due to the extent of the extraction and remediation works required to prepare each site
for future development.  However, the following habitats will be retained in order to maintain wildlife
corridors around the sites during remediation works.  The active travel route outside the application
site boundary to the west of Meadowhead will also provide some habitat connectivity through the wider
Ravenscraig site:  
• Existing woodland to the north and south and within the railway embankment to the east of
the Meadowhead site.
• Mosaic habitat to the north of the Meadowhead site.
• Woodland to the east of the TC1-3 site. 
8.22 On the basis of the mitigation proposed, which will ensure that wildlife corridors are maintained over
the long term to allow movement of species across the site, together with conditions in place to ensure
that any significant adverse effects on protected species can be mitigated and that the development
will make provision for biodiversity enhancement following completion of the works, the proposed
development is considered to be acceptable and is in accordance with the aims and objectives of
Policy PROT A of the LDP, Policies 3 and Policy 4 of NPF4 and the Scottish Biodiversity Strategy to
2045. 
Protection and Retention of Trees 
8.23 Policy EDQ1 (Site Appraisal) of the LDP requires proposals for development to be accompanied by
an appraisal that addresses the nature of features to be safeguarded or enhanced within the site to
ensure that the development integrates successfully with the local landscape character. Similarly,
Policy 6 c) (Forestry, woodland and trees) of NPF4 provides that development proposals will not be
supported where they would result in adverse impacts on native woodlands, hedgerows and individual
trees of high biodiversity value or in fragmentation or severing of woodland habitats, unless appropriate
mitigation measures are identified and implemented. Adequate provision of landscaped areas within
the development should also be provided in accordance with Policy EDQ3 (Quality of Development)
of the LDP and, landscaping should be designed to improve the quality of the area whether in an urban
or rural location and be consistent with the six qualities of successful places in accordance with Policy
14 (Design, Quality and Place) of NPF4. 
8.24 The application is supported by an Arboricultural Impact Assessment and Tree Survey Schedule
(Appendix A) by LUC, dated July 2025.  The tree survey recorded a total of 13 individual trees, and
72 tree groups across both Meadowhead and TC1-3. The survey notes that there was no presence of
any ancient or veteran trees on either site, that no parts of either site were found to be recorded on
Scottish Natural Heritage’s ‘Ancient Woodland Inventory’ and that no trees within the site boundary
are subject to a Tree Preservation Order (TPO).  To facilitate the extraction and remediation works,
the Applicant proposes removal of 11 individual trees, 46 groups of trees and parts of a further 4
groups of trees.  Meadowhead is dominated by self-seeded broadleaved scattered trees and groups
of trees which it is proposed will be removed. More mature broadleaved groups of trees are present
along the east, northern and southern boundaries of the site and it is proposed that those trees will be
retained.  TC1-3 is dominated by neutral grassland and scattered scrub, with several sections of self-
seeded young to semi mature broadleaved groups of trees, all of which will be removed. A section of
larger, more mature broadleaved trees is present along the eastern boundary of the site, and it is
proposed that those trees will also be retained.  Categories of trees to be removed are shown in Table
3.1 of the Arboricultural Impact Assessment and in the Tree Data Schedule in Appendix A. Protection
measures are also proposed to avoid any detrimental damage to tree canopies or tree roots and it is
recommended that this is secured by condition (see conditions 18-22).   
Page 41 of 154

Page 42

8.25 The proposed tree felling is considered to be necessary in order to facilitate the decontamination and
remediation of the site and to prepare the site for future redevelopment. It is recommended that
mitigation measures are incorporated and that appropriate conditions are attached to the grant of
planning permission to ensure the protection of tree canopies and tree roots during construction
activities and that prior to or on submission of any further application for redevelopment of the site, full
details of compensatory tree planting, biodiversity enhancement and a biodiversity/landscape plan and
aftercare plan. NLC Tree Assets Manager (Community Green Space) was consulted and has no
objection to the development subject to conditions detailed in this report (18-22). In view of these
measures, the proposed development does not raise any conflict with Policies EDQ1 and EDQ3 of the
LDP or Policy 3 and 6 of NPF4. 
Flood Risk and Drainage 
8.26 Policy EDQ1 (Site Appraisal) and EDQ2 (Specific Features for Consideration) of the LDP provides
that development shall take account of any impacts associated with the holistic water environment,
flood risk, public utilities and drainage systems and, as required by Policy 22 (Flood risk and water
management) of NPF4, all rain and surface water will be managed through sustainable urban drainage
systems (SUDS), which should form part of and integrate with proposed and existing blue-green
infrastructure. 
8.27 The application is supported by a Drainage Assessment, prepared by Aecom, dated 11th December
2024 and by a Flood Risk Assessment, Aecom, dated July 2025 (updated 17 July 2025).  Flooding
and drainage matters have been the subject of ongoing discussion with the Applicant in consultation
with NLC Infrastructure & Water Management and NLC City Deal. Internal consultees have no
objection to the proposed development subject to appropriate conditions relating to the submission of
details to the Planning Authority for approval, including a pollution prevention plan / construction phase
plan (CPP) and construction method statements to manage surface water runoff during construction,
evidence that a construction CAR licence (or new equivalent) has been obtained from SEPA, evidence
that a viable surface water disposal point will be in place for the site and further evidence in the form
of a revised Flood Risk Assessment and Drainage Strategy (Conditions 8-11 of this Report).  The
above conditions will ensure that the proposal meets the requirements of Policies EDQ1 and EDQ2 of
the LDP and Policy 22 of NPF4.   
Noise 
8.28 Policy 23 e) (Health and Safety) Development of NPF4 provides that development proposals that are
likely to raise unacceptable noise issues will not be supported. The noise impacts of development
proposals on residential amenity and health are also addressed in Policy EDQ3 e) (Quality of
Development) of the LDP and in Policy 23 d) (Health and Safety) of NPF4. Both policies are aligned
in that they seek to ensure that mitigation is provided where necessary to overcome any unacceptable
noise impacts. In recognition of the occurrence of noisier phases within surface mineral workings,
paragraph 41 of PAN 50 Controlling the Environmental Effects of Surface Mineral Workings, Annex A,
advises that it may be necessary to raise noise limits for a temporary period to permit certain noisier
activities to progress during extraction works, where these activities cannot meet the limits set. Such
activities include soil-stripping, removal of spoil heaps, routine operations and construction of new
permanent landforms, including baffle mounds.  Paragraph 60 of the guidance allows for noise limits
to be raised up to 70 dB LAeq,1h (free field) for a temporary period of up to 8 weeks per year, at the
discretion of the Planning Authority. 
Page 42 of 154

Page 43

8.29 The application is supported by a Noise Impact Assessment, prepared by Airshed, dated 26th
November 2024 (updated 24 July 2025). The assessment includes survey results at four locations
close to the nearest noise-sensitive receptors in order to obtain representative ambient and
background sound levels and to help determine the baseline noise in accordance with BS 5228:2009
+ A1:2014. This includes noise levels predicted at various receptors, including existing residential
areas (Ravenscliff Road, Old Meadow Walk, Rosebay Drive and Meadowhead Road), Firtrees Nursery
and New College Lanarkshire Campus. The assessment describes the potential noise impacts likely
to arise from the proposed development, based on the indicative phasing plans and suggests that it is
likely that noise limits will exceed the limits set by NLC Protective Services, particularly during crushing
and extraction operations.  It is likely therefore that a request to increase the noise limits (as set out in
condition 5 of this report), for a temporary period during nosier construction activities will be submitted
to the Planning Authority after the development has commenced. 
8.30 NLC Protective Services was consulted and has no objection to the development subject to conditions
relating to the following matters: control of noise limits at sensitive receptors; fixed hours of operation;
the requirement to carry out periodic noise monitoring and to retain annual noise monitoring reports,
together with the requirement that requests by developers to increase noise limits for a temporary
period are made in writing for the approval of the Planning Authority in consultation with NLC Protective
Services.  It is therefore considered that noise can be mitigated with appropriate conditions in place to
ensure protection of amenity in accordance with Policy EDQ3 of the LDP, Policy 23 e) of NPF4 and
PAN 50 Controlling the Environmental Effects of Surface Mineral Workings, Annex A. 
Air Quality 
8.31 Policy EDQ3 e) (Quality of Development) requires development to mitigate any likely air quality
impacts in or adjacent to Air Quality Management Areas (AQMA).  Equally, Policy 23 d) (Health and
Safety) Development of NPF4 provides that development proposals that are likely to have significant
adverse effects on air quality will not be supported. 
8.32 Motherwell Town Centre AQMA lies south of the West Coast Main Line and approximately 220m to
southwest of TC1-3.  The impacts on the AQMA and sensitive receptors close to the site have been
accounted for in the Air Quality Impact Assessment (AQIA) prepared by Airshed, dated 6 December
2024, submitted in support of the application. The Report assesses four potential worst-case scenarios
to determine the impacts of the development on sensitive receptors as follows: 
• Scenario 1: worst-case impacts when Phase 1 operations at Meadowhead are closest to the
dwellings to the northeast at Roedeer Drive and Ravenscliff Road. This scenario includes for
the potential combined impacts from removal and infill operations. 
• Scenario 2: worst-case impacts when Phase 2 operations are closest to the dwellings to the
south-west at Old Meadow Walk and Rosebay Drive. This scenario includes for the potential
combined impacts from removal and infill operations. 
• Scenario 3: worst-case impacts when Phase 2 operations are closest to the dwellings to the
south-east at Meadowhead Road. This scenario includes for the potential combined impacts
from removal and infill operations. 
• Scenario 4: worst-case impacts when operations at TC1-TC3 are closest to the College
campus. This scenario includes for the potential combined impacts from removal and infill
operations. 
8.33 The results of the assessment show that ‘Without Mitigation’ in place the worse-case impact descriptor
is Moderate Adverse at most receptors and Substantial Adverse at two of the College receptors. The
results of the assessment show that ‘With Mitigation’, the worse-case impact descriptor at all sensitive
receptors for PM10 is Negligible, with the exception of a residential dwelling on Meadowhead Road
where the impact descriptor is Slight Adverse in Scenario 3. 
Page 43 of 154

Page 44

8.34 NLC Protective Services has been consulted and has advised that the conclusions of the submitted
AQIA are acceptable with the proposed mitigation in place, including, inter alia, water suppression to
eliminate a large percentage of airborne particulate matter and a series of further measures relating
to dust management and dust monitoring procedures and the requirement for a Dust Management
Plan to be developed in consultation with the Planning Authority and NLC Protective Services. With
appropriate conditions in place (see Conditions 23 and 24), to mitigate any likely air quality impacts
on nearby sensitive receptors on or adjacent Motherwell Town Centre AQMA, the proposed
development is considered to be acceptable and is in accordance with the general requirements of
Policy EDQ3 e) of the LDP and Policy 23d) of NPF4. 
Contaminated Land 
8.35  Policy EDQ2 (Specific Features for Consideration) of the LDP requires consideration of development
in areas subject to hazards (Hazardous Zones), including in matters concerning contamination.  Policy
9 c) (Brownfield, vacant and derelict land and empty buildings) of NPF4 provides that where land is
known or suspected to be unstable or contaminated, development proposals should demonstrate that
the land is, or can be made, safe and suitable for the proposed new use. 
8.36 Following two rounds of consultation and submission of an initial contamination assessment detailed
in the report entitled, ‘’Meadowhead & TC1-3 Initial Contamination Assessment” prepared by GDG,
Ref: 22208-R-004-02, dated August 2025, NLC Protective Services has advised that the information
submitted meets the requirements of NLC Checklist 1 (Preliminary Risk Assessment/Desk study). 
However, it is noted that the Initial Contamination Assessment submitted by the Applicant goes beyond
the requirements of a Phase I Report (Preliminary Risk Assessment/ Desk Study) and incorporates
elements of the requirements of a Phase II Report (Quantitative Risk Assessment/ Site Investigation)
including remediation proposals and further investigation prior to/ as part of the proposed bulk
excavation and infilling works. It is the content of this supplementary Phase II Report (investigation
design and outline remediation and verification strategy) that is therefore the subject of conditions that
are recommended in this report (see conditions 12-17). 
8.37 The proposed development aims to decontaminate and remediate two large parcels of brownfield land
within the former Ravenscraig Steelworks site thereby removing any identified hazards that could
potentially constrain any future redevelopment of the site. Subject to the above conditions, the
proposed development is considered to be acceptable and is in line with Policy 9 c) of NPF4 and Policy
EDQ2 of the LDP and meets the requirements of NLC Checklist 1 (Preliminary Risk Assessment/Desk
study). 
Coal Mining Legacy 
8.38 Policy EDQ2 (Specific Features for Consideration) of the LDP similarly requires the Planning Authority
to consider development in areas subject to hazards (Hazardous Zones), including matters concerning
ground instability. Policy 9 c) (Brownfield, vacant and derelict land and empty buildings) of NPF4
requires land known or suspected to be unstable to be made, safe and suitable for the proposed new
use. 
8.39 As parts of the application site fall within the Coal Authority’s defined Development High Risk Area,
the application is accompanied by a Ground Investigation Report (WG878-12/MAK/CMB/AJB/NM/KM,
November 2023) by Johnson Poole & Bloomer, which was prepared for Plots TC1 – TC3 only.   Whilst
a Coal Mining Remediation Assessment (CMRA) has not been submitted for Meadowhead, the Coal
Mining Remediation Authority has advised, that as it was previously consulted by the Planning
Authority on planning permission in principle (Ref:18/00463/PPP) and did not object at that time based
on the Earthworks Strategy, by AECOM, dated March 2018 that was submitted in support of the PPiP
at the time, it has no objection to the current application subject to conditions 30 and 31 detailed in
this report (Coal Mining Remediation Authority consultation response dated 29 January 2025).   In
view of the above and subject to the undertaking of intrusive site investigations necessary to inform
the extent of any remedial works associated with mine legacy, the proposed development raises no
conflict with Policy EDQ2 of the LDP.  However, it is noted that remediation works, to ensure that the
ground is made safe and stable for future development, are not proposed at this stage (i.e. within
Phase 1 or 2 of the current application) and that remediation, where necessary, would be carried out
at a later stage prior to or on submission of a further application for development of the site.  
Page 44 of 154

Page 45

Waste Management 
8.40 Policy 12 a) and b) (Zero Waste) of NPF4 seeks to minimise and reduce waste in line with the waste
hierarchy.  Limb c) of the policy requires development proposals that are likely to generate waste when
operational to set out how much waste the proposal is expected to generate and how it will be
managed including the provision to maximise waste reduction and waste separation at source, and
measures to minimise cross-contamination of materials, through appropriate segregation and storage
of waste. 
8.41 A preliminary Waste Management Strategy prepared by Ryden is submitted in support of the
application. The Waste Management Strategy advises that the application does not include for any
waste treatment as all waste materials (i.e. inert soil and stones – waste code 17 05 04) will be
imported with the aim of raising site levels via the placement of soils as engineered fill.  However, the
Strategy also notes that if for any reason soils imported to the site are subsequently deemed
unacceptable following an initial visual assessment, they will be segregated via the use of an onsite
excavator and placed on an impermeable membrane within a vacant area of the site (to be determined
at the time and a record of this location to be retained). The soils will then be tested and if testing
confirms the soils to be in fact suitable, they will then be placed as originally intended. However, should
testing confirm the soils as unacceptable they will be removed offsite to the source site or to a suitably
licensed facility within one calendar month of being imported. Transfer notes will be retained within the
site records and a relevant licence or authorisation from SEPA will be obtained. 
8.42 To ensure that the development is compliant with Policy 12 a) and b) of NPF4, NLC Protective Services
has requested that a condition is attached to the grant of planning consent to require the developer to
provide a copy of the relevant SEPA authorisation covering the excavation and off-site removal of
materials and the subsequent importation of fill materials to complete the works. Subject to an
appropriate condition to this effect (as detailed in condition 33 of this Report), the proposed
development is considered to be in accordance with Policy 12 of NPF4. 
9. Conclusions 
9.1 The proposed development seeks to manage the legacy of contaminated land on two large parcels of
land within the former Ravenscraig steelworks site.  Remediation will take place over a period of 14
years and will involve extraction, crushing, screening and removal of inert material to use as
engineered fill followed by the spreading of clean soils across each site.  The volume of inert material
to infill each site to the required levels is approximately 2,260,000m³ in the case of Meadowhead and
approximately 410,000m³ in the case of TC1-3. Soils that are unsuitable for infill will be removed offsite;
a process that will be authorised by SEPA.  Intrusive site investigations necessary to inform the extent
of any remedial works associated with mine legacy will be carried out. However, it is noted that
remediation works to ensure that the ground has been made safe and stable for future development
is not planned within the current phases of the development and do not therefore form part of this
application.  It is likely that this work will be carried out prior to or on commencement of a further
application to redevelop the site for appropriate land use in accordance with the approved masterplan
(revised in 2018).  Therefore, whilst the current proposed works are not directly related to new
development or to a specific end use, they are considered necessary in order to prepare each site for
future redevelopment, which is critical to the regeneration of Ravenscraig.   
9.2 Subject to appropriate conditions, the proposed remediation works are considered to comply with the 
Development Plan and can be carried out without significant effects on ecology, air quality, the water 
environment, the road network and residential amenity.  Accordingly, it is recommended that the 
application is approved subject to the conditions detailed in this repor 
Page 45 of 154

Page 46

Application No:  
25/00150/FUL
Proposed Development: 
Plant Extension to Data Centre and Construction of Generator
Building including Alterations, Infrastructure, Watercourse
Diversion, Biodiversity Enhancement, Access and Associated
Development 
Site Address: 
DataVita Data Centre
York Road
Chapelhall
ML6 8HW 
Date Registered: 
25th February 2025 
Applicant:
DataVita
1 York Road
Chapelhall
ML6 8HW 
Agent:
MLA Architects
83A Candleriggs
Glasgow
G1 1LF 
Application Level:
Local Application 
Contrary to Development Plan:
No
Ward:   
12 Airdrie South 
Michael Joseph Coyle,Paul Di Mascio,Sandy
Watson,Michael McBride,
Representations:
1 letter(s) of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The proposal is complementary and compatible with the adjacent data centre and wider
strategic business setting. Whilst the proposed extension to the facility would result in
development in the green belt for a use outwith those supported within Policy PP4 (Green Belt
- Purpose of Place) of the North Lanarkshire Local Development Plan, it is considered to be
an acceptable departure. It is considered to align with the requirements of NPF4 and that of
NPF4 Policy 8 Green Belt. The assessment of appropriateness provided by the applicant has
also demonstrated the need for this location and is considered acceptable. It is not considered
that the development will have an adverse effect on the purpose of the Green Belt and it is
considered that impact on the environment and amenity can be controlled by the attached
planning conditions. 
Page 46 of 154

Page 47

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 25/00150/FUL 
Name (of applicant): DataVita
Site Address: DataVita Data Centre
York Road
Chapelhall
ML6 8HW 
Development: Plant Extension to Data
Centre and Construction of Generator
Building including Alterations,
Infrastructure, Watercourse Diversion,
Biodiversity Enhancement, Access and
Associated Development   
Page 47 of 154

Page 48

Proposed Conditions:- 
1. That, except as may otherwise be agreed in writing by the Planning Authority, the development shall
be implemented in accordance with drawing numbers: 
DV2-WHL-XX-XX-DR-C-9150 Revision P04 Indicative Scope of Works
DV2-WHL-XX-XX-DR-C-9200 Revision P04 Indicative Levels Strategy
DV2-WHL-XX-XX-DR-C-9201 Revision P04 Indicative Levels Layout - Sheet 1
DV2-WHL-XX-XX-DR-C-9202 Revision P04 Indicative Levels Layout - Sheet 2
DV2-WHL-XX-XX-DR-C-9400 Revision P04 Indicative Drainage Strategy
DV2-WHL-XX-XX-DR-C-9401 Revision P04 Indicative Drainage Layout- Sheet 1
DV2-WHL-XX-XX-DR-C-9402 Revision P04 Indicative Drainage Layout- Sheet 2
DV2-WHL-XX-XX-DR-C-9403 Revision P04 Indicative Drainage Layout- Sheet 3
DV2-WHL-XX-XX-DR-C-9410 Revision P01 Indicative Blue/Green Roof Layout
DV2-WHL-XX-XX-SK-C-002 Revision P03 Indicative Post-Development Overland Flow
DV2-WHL-XX-XX-SK-C-004 Revision P03 Proposed Vehicle Tracking - Sheet 1
DV2-WHL-XX-XX-SK-C-005 Revision P03 Proposed Vehicle Tracking - Sheet 2
DV2-WHL-XX-XX-SK-C-006 Revision P02 Proposed Access Line Diagram
DV2-WHL-XX-XX-SK-C-0010 Revision P02 Proposed Vehicle Tracking - Sheet 4
DV2-WHL-XX-XX-SK-C-0011 Revision P02 Proposed Vehicle Tracking - Sheet 5
DV2-WHL-XX-XX-SK-C-0012 Revision P02 Proposed Vehicle Tracking - Sheet 6
HFG7-MLA-XX-XX-DR-A-PL102 Revision A Site Plan as Proposed
HFG7-MLA-XX-XX-DR-A-PL103 Revision B Indicative Plant Enclosures as Proposed Level 1
HFG7-MLA-XX-XX-DR-A-PL104 Revision B Plant Gantry as Proposed Level 2
HFG7-MLA-XX-XX-DR-A-PL105 Revision B Plant Gantry as Proposed Level 3
HFG7-MLA-XX-XX-DR-A-PL106 Revision B Plant Gantry as Proposed Level 4
HFG7-MLA-XX-XX-DR-A-PL111 Revision B North Elevation as Proposed
HFG7-MLA-XX-XX-DR-A-PL112 Revision A East Elevation as Proposed
HFG7-MLA-XX-XX-DR-A-PL113 Revision B South Elevation as Proposed
HFG7-MLA-XX-XX-DR-A-PL114 Revision B West Elevation as Proposed
HFG7-MLA-XX-XX-DR-A-PL116 Revision B Section AA as Proposed
HFG7-MLA-XX-XX-DR-A-PL117 Revision B East and West Elevations Generator Enclosure as
Proposed
64123-SH-45-001 Revision P02 Planting Schedules
64123-SH-45-002 Revision P01 Planting Establishment & Maintenance
64123-45-100 Revision P04 Landscape Strategy
64123-45-101 Revision P05 Landscape Planting Proposals 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. No above ground development shall commence until; 
a) a scheme of intrusive investigations has been carried out on site to establish the risks posed to the
development by past shallow coal mining activity; and
b) any remediation works and/or mitigation measures to address land instability arising from past coal
mining legacy, as may be necessary, have been implemented on site in full in order to ensure that the
site is made safe and stable for the development proposed. 
The intrusive site investigations, remedial works and mitigatory measures shall be carried out in
accordance with authoritative UK guidance. 
Reason: To ensure the safety and stability of the proposed development. 
Page 48 of 154

Page 49

3. Prior to the occupation of the development, or it being taken into beneficial use, a signed statement or
declaration prepared by a suitably competent person confirming that the site is, or has been made,
safe and stable for the approved development shall be submitted to the Local Planning Authority for
approval in writing. This document shall confirm the methods and findings of the intrusive site
investigations and the completion of any remedial works and/or mitigation necessary to address the
risks posed by past coal mining activity. 
Reason: To ensure the safety and stability of the proposed development. 
4. That BEFORE any works of any description start on the application site, unless otherwise agreed in
writing with the Planning Authority, a comprehensive site investigation requires to be submitted to the
satisfaction of the Local Authority. The investigation must be carried out in accordance with the British
Standard Code of Practice BS 10175: 2001 "The Investigation of Potentially Contaminated Sites". The
report must include a site-specific risk assessment of all relevant pollution linkages, be carried out in
accordance with the Environment Agency publication, Model Procedures for the Management of Land
Contamination CLR11. Depending on the results of this investigation a detailed remediation strategy
may be required. 
A detailed mine gas risk assessment also requires to be submitted in accordance with CL:AIRE, 2021. 
Reason: To establish whether or not site decontamination is required in the interests of the amenity
and wellbeing. 
5. That any remediation works identified by the site investigation/mine gas risk assessment required in
terms of Condition 4, shall be carried out to the satisfaction of the Planning Authority.  A certificate
(signed by a chartered Environmental Engineer) shall be submitted to the Planning Authority
confirming that any remediation works have been carried out in accordance with the terms of the
Remediation Strategy. 
Reason: To ensure that the site is free of contamination in the interests of the amenity and wellbeing. 
6. That BEFORE the development hereby permitted starts, full details of the facing materials to be used
on all external walls shall be submitted to and approved in writing by the Planning Authority and the
development shall be implemented in accordance with the details approved under the terms of this
condition. 
Reason: In the interest of the amenity of the site and the general area. 
7. That BEFORE the development hereby permitted starts, full details of the design and location of all
fences and walls to be erected on the site shall be submitted to and approved in writing by the
Planning Authority. 
Reason: In the interest of the amenity of the site and the general area. 
8. That, unless otherwise agreed in writing with the Planning Authority, the SUDS compliant surface
water drainage scheme shall be implemented in accordance with the Drainage Strategy Report
Version V1 11 prepared by Woolgar Hunter Engineers and drawing refs: DV2-WHL-XX-XX-DR-C-
9401 REV P04 Drainage Layout - Sheet 1, DV2-WHL-XX-XX-DR-C-9402 REV P04 - Drainage Layout
- Sheet 2, DV2-WHL-XX-XX-DR-C-9403 REV P03 - Sheet 3. 
Reason: To ensure that the drainage scheme complies with best SUDS practice to protect adjacent
watercourses and groundwater and in the interests of the amenity and wellbeing. 
Page 49 of 154

Page 50

9. That the SUDS compliant surface water drainage scheme approved in terms of Condition 8 shall be
implemented contemporaneously with the development in so far as is reasonably practical.  Within
three months of the construction of the SUDS, a certificate (signed by a Chartered Civil Engineer
experienced in drainage works) shall be submitted to the Planning Authority confirming that the SUDS
has been constructed in accordance with the relevant CIRIA Manual and the approved plans. 
Reason: To safeguard adjacent watercourses and groundwater from pollution and in the interests of
the amenity. 
10. That BEFORE the development hereby permitted starts, the CAR Licence issued by SEPA under the
Water Environment (Controlled Activities) (Scotland) Regulations 2011 relating to works to the
watercourse shall be submitted. 
Reason: To ensure the works are licensed in the interests of protecting the watercourse from pollution
and to manage flood risk. 
11. That, unless otherwise agreed in writing with the Planning Authority, the noise mitigation measures
outlined in Section 9 of the Extension External Plant Noise Impact Assessment - Revision 2 by New
Acoustics shall be implemented before the development hereby approved is brought into use. 
Reason: In the interests of the amenity of the adjacent residents. 
12. That, unless otherwise agreed in writing with the Planning Authority, all tree retention, woodland
creation, planting, landscaping and biodiversity enhancements outlined in drawing refs: 64123-45-100
Revision P04 Landscape Strategy,  64123-45-101 Revision P05 Landscape Planting Proposals, 
64123-SH-45-001 Revision P02 Planting Schedules shall be completed. Any trees, shrubs, or areas of
grass which die, are removed, damaged, or become diseased, within two years of the full occupation
of the development hereby permitted, shall be replaced within the following year with others of a
similar size and species. 
Reason: In the interests of landscaping and biodiversity enhancement. 
13. That BEFORE completion of the development hereby permitted, the management and maintenance
scheme approved under the terms of drawing ref: 64123-SH-45-002 Revision P01 Planting
Establishment and Maintenance shall be in operation. 
Reason: In the interests of the proper management of the landscaping and biodiversity
enhancements. 
14. That BEFORE the development hereby permitted starts, details of the tree protection measures for the
retained oak tree (T1) and the trees adjacent to the application site shall be submitted to, and
approved in writing by the Planning Authority, and the works shall be implemented in accordance with
the details approved under the terms of this condition. For the avoidance of doubt the tree protection
measures shall not be removed without the written approval of the Planning Authority. 
Reason: In the interests of tree protection and nature conservation. 
15. That BEFORE the development hereby permitted starts, as recommended within the Preliminary
Ecological Appraisal, a pre-construction protected species survey shall be carried out, and submitted
for the approval of the Planning Authority. 
Reason: In the interests of Protected Species protection. 
16. That, unless otherwise agreed in writing with the Planning Authority, the mitigation measures outlined
in Section 5 of the Preliminary Ecological Appraisal by Wild Surveys Ltd shall be implemented. For the
avoidance of doubt these relate to a Toolbox Talk and on-site measures relating to nesting birds,
reptiles, mammals, foraging bats (lighting) and amphibians. 
Reason: In the interests of Protected Species protection.
Page 50 of 154

Page 51

17. That unless otherwise agreed in writing with the Planning Authority, within six months of the date of
approval, a feasibility report on the provision of appropriate infrastructure to service a heat network
outwith the application site shall be submitted for the written approval of the Council as Planning
Authority. Thereafter once approved the approved details shall be implemented to the satisfaction of
the Council. 
Reason: In the interests of decarbonised solutions to heat and cooling demand. 
18. Prior to the commencement of development, a Construction and Environmental Management Plan
(CEMP) shall be submitted to the Planning Authority for approval of acceptable working methodologies
with regards hours of operation, and mitigation requirements, including but not limited to, dust, noise,
nuisance, lighting, impacts to the road network and impacts on the environment. 
Reason: To protect the environment and amenity of the area. 
Background Papers: 
Consultation Responses: 
NLC Protective Services (Environmental Health) received 7th March 2025, 11th August 2025
NLC Infrastructure and Transportation (Roads) received 17th March 2025, 12th August 2025, 25th August
2025, 8th September 2025, 12th September 2025, 26th September 2025
NLC Greenspace Development received 2nd April 2025 and 2nd September 2025 
Scottish Gas Network received 14th August 2024
Scottish Water received 4th March 2025 and 1st August 2025
Coal Mining Remediation Authority received 18th March 2025
Scottish Environment Protection Agency received 13th March 2025, 25th August 2025, 29th September 2025,
9th October 2025
Nature Scotland received 7th April 2025 
Contact Information: 
Any person wishing to inspect these documents should contact Kirsten Devlin at devlink@northlan.gov.uk 
Report Date: 
18th November 2025
Page 51 of 154

Page 52

APPLICATION NO. 25/00150/FUL 
REPORT 
1. Site Description 
1.1 The application site consists of the existing HFD DataVita facility at York Road, Chapelhall. It is a
premium co-location, cloud and low-latency networking data centre. The facility is located on the south
side of Lancaster Avenue forming part of the existing York Road Strategic Business Centre. It is
positioned between residential development on the north side of Lancaster Avenue and an existing
business unit to the south. Directly south of the business centres lies the A8 (Glasgow and Edinburgh
Road) and the M8 motorway. While the existing facility and associated car parking and servicing areas
are located within the Strategic Business Centre, the land to the east of the existing facility, which
forms the application site, is located within the Green Belt and consists of a watercourse, grassland
and scattered woodland cover. The application site extends to approximately 1.76 Hectares. 
2. Proposed Development 
2.1 Planning permission is sought for a plant extension to the existing data centre and a separate
generator building. This is required to meet the power and cooling requirements of an expansion of
the data centre function. The plant enclosure is 24.5m x 85m giving a footprint of 2,082.5 square
metres. It is located directly east of the existing facility and is 18.23 metres in height. The generator
building is sited 16.6 metres from the plant extension and is 12.56m x 94.96m giving a footprint of
1,192.7 square metres; it is 12.43 metres in height. The proposal has been designed to be sympathetic
to the existing building envelope and massing. The facing materials (cladding, rainscreens panels and
louvres) have been designed to match those used on the existing facility. To accommodate additional
cooling plant and address acoustic issues, the parapet of the existing facility will be raised by 2.5m
where all equipment to be installed will sit below the parapet level of both the altered existing building
and new extension. A small transformer enclosure on the north elevation of the existing building is
also proposed. 
2.2 As a result of the constrained nature of the site the applicant has had to seek permission to expand
into the adjacent green belt land, which is characterised by a watercourse, grassland and scattered
woodland cover.  The existing watercourse (which was reengineered and culverted when the original
facility was built) will need to be diverted and a number of mixed quality trees will require to be felled.
Significant areas of compensatory woodland planting will be created on the eastern portions of the site
which will maintain a habitat corridor with the existing trees on the adjacent land. Also, extensive areas
of grassland enhancement will be introduced with native shrubs and wildflowers. Tree protection
measures will be required, this matter is covered by the imposition of a planning condition. The diverted
watercourse proposes a meandering channel to mimic natural watercourse hydrology with varied
profiled pools, over-deepened sections and shallow margins and gentle banks and benches. The
existing vehicular and pedestrian access and internal parking areas will not require to be altered. 
2.3 The application was submitted initially as a Planning Permission in Principle (PPiP). However, given
the extensive supporting documentation that accompanied the application and the need for detailed
surveys in relation to flood risk, noise and protected species it was agreed that the application be
changed from PPiP to Full Planning Permission upon receipt of the required surveys. 
3. Applicant’s Supporting Information 
3.1 The applicant has provided the following package of information in support of their application: 
• Design and Access Statement
• Greenbelt Framework
• Geo-environmental Desk Study & Mining Risk Assessment
• Coal Mining Report
• Preliminary Ecological Appraisal
• Protected Species Survey Report
• Arboricultural Impact Assessment
Page 52 of 154

Page 53

• Noise Impact Assessment
• Drainage Strategy Report
• Flood Risk Assessment
• Hydraulic Modelling Report 
4. Site History 
4.1 The following applications are of relevance to the application site: 
• 10/00604/FUL: Construction of Storage and Distribution Unit (Class 6) - Approved 05.08.2010
• 10/01399/AMD: Amendment to Approved Warehouse Car Park and Site Boundary (Amendment to
Permission 10/00604/FUL) - Approved 15.04.2011
• 24/00311/FUL: Installation of external plant including six transformers, creating new switchboard
rooms in a proprietary steel enclosure, installing six additional stand-by generators along with
minor alterations to the layout of the existing on-site parking and pedestrian access - Approved
10.09.2024 
5. Development Plan 
5.1 The development plan consists of National Planning Framework 4 (NPF4) and the North Lanarkshire
Local Development Plan (NLLDP) 2022. 
5.2 The policies within NPF4 that are relevant to the application are as follows: 
Policy 1 - Tackling the climate and nature crisis
Policy 2 - Climate mitigation and adaptation
Policy 3 - Biodiversity
Policy 6 - Forestry, woodland and trees
Policy 8 - Green belts
Policy 13 - Sustainable transport
Policy 14 - Design, Quality and Place
Policy 19 – Heating and cooling
Policy 22 – Flood risk and water management
Policy 23 – Health and safety
Policy 24 – Digital infrastructure
Policy 26 – Business and Industry 
5.3 In terms of the North Lanarkshire Local Development Plan 2022 the following policies are of relevance: 
PP 4 Green Belt, Purpose of Place
AD 4 Green Belt, Amount of Development
PROM LOC2 Strategic Business Development Site
Environmental Development Qualities (EDQ) 1: Site Appraisal
Environmental Development Qualities (EDQ) 2: Specific Features for Consideration
Environmental Development Qualities (EDQ) 3: Quality of Development 
6.          Consultations 
6.1 The following consultation responses have been received in connection with the application: 
NLC Protective Services (Environmental Health) confirmed a Site Investigation including a detailed
mine gas risk assessment requires to be submitted to ensure potential risks arising from previous land
uses around the site have been fully assessed. This matter is covered by the imposition of Site
Investigation/gas risk assessment and remediation (if necessary) planning conditions. 
A Noise Impact Assessment (NIA) was requested due to the proximity of the development to residential
dwellings. The NIA by New Acoustics Ltd was submitted and Environmental Health have confirmed
they are satisfied with the assessment methodology and findings which are based on the mitigation
measures outlined in Section 9 of the report being implemented (these measures include louvres,
Page 53 of 154

Page 54

chiller temperature control, parapet height/screening and routine testing). A planning condition
requiring the mitigation measures are implemented in accordance with Section 9 of the NIA is attached. 
Comments relating to construction noise, controlling site generated dust and external lighting were
also received. These matters can be controlled by a Constriction Environmental Management Plan. 
NLC Infrastructure and Transportation (Roads) initially recommended the application be deferred
subject to further information relating to impacts on paths and the requirement for the submission of
swept path details for the access and maintenance area. They further commented that the applicant
liaises with SEPA with respect to the watercourse diversion. No public footpaths, core paths or rights
of way will be affected by the proposal. A suite of swept path details and information on servicing were
provided to ensure existing disabled parking bays within the site will not be detrimentally affected.
Roads confirmed their acceptance of the submitted details and have no objection to the application.
They further commented that the drainage system should comply with Scottish Water and SEPA
guidance and surface water from private/non-adopted areas is not permitted to drain onto the adopted
road or footway. The proposed access and geocelluar water storage system require to remain under
private ownership and liaison with SEPA is required for the watercourse diversion. 
NLC Greenspace Development initially advised that a Preliminary Ecological Appraisal (PEA) and
biodiversity enhancement details require to be submitted. A PEA by Wild Surveys Ltd dated 15th April
2025 was received which recommended further surveys to establish the presence, or potential
presence of the following protected species were required given the characteristics of the site: otter,
bat, water vole, badger and great crested newt. The Protected Species Survey Report dated 22nd July
2025 confirmed the relevant surveys were carried out and no field signs were recorded (including
eDNA survey for Great crested newt). The findings are accepted by Greenspace who have requested
the recommendations and general considerations put forward within the report are taken forward. This
matter is covered by the imposition of a planning condition. Furthermore, a landscape plan and
landscape strategy which includes biodiversity enhancements and details of the watercourse
realignment were also received. Greenspace confirm the landscaping and biodiversity measures are
well thought out and that these matters are also covered by the imposition of planning conditions to
ensure all measures are implemented. 
Scottish Water has no objection to the application. There is sufficient capacity at Balmore Water
Treatment Works and Daldowie Waste Water Treatment works; it is to be noted that further
investigations may be required to be carried out once a formal application has been submitted to
Scottish Water. 
The Mining Remediation Authority confirms they agree with the conclusions of the submitted Geo-
environmental Mining Risk Assessment; that coal mining legacy potentially poses a risk to the
proposed development and that investigations are required, along with possible remedial and
mitigatory measures, to ensure the safety and stability of the proposed development. They have no
objection subject to the imposition of planning conditions requiring a scheme of Intrusive Investigations
and remediation works or mitigation measures (if required). Furthermore, a condition requiring
certification that the site has been made safe and stable for the approved development before
occupation is required. These matters have been attached as planning conditions. Informative Notes
relating to ground investigation/groundworks, incidental Coal Agreements and shallow coal seams
were requested and have also been attached.   
Scottish Environment Protection Agency confirm they have no objection to the watercourse
diversion and recommend the applicant reviews Section 6,’Engineering levels of authorisation’ of the
CAR Practical Guide and SEPA’s Position Statement ‘WAT-PS-02 ‘Culverting of Watercourses’. On
reconsulting SEPA (due to the application being changed from Planning Permission in Principle to Full
Planning Permission and SEPA Flooding maps being updated) they submitted a holding objection
relating to flood risk and requested a Flood Risk Assessment (FRA).The FRA was subsequently
received and through consultation with SEPA and the submission of a further updated FRA, hydraulic
modelling report and amended plans they withdrew their objection on flood risk grounds. 
Nature Scotland confirmed their consent is not required to undertake the proposed works. 
Page 54 of 154

Page 55

7.         Representations 
7.1 1 letter of representation has been received. The points raised and comments thereon are as follows: 
Points of Objection: There is a badger sett and bat roosts located on the site with the proposal therefore
having a detrimental impact on wildlife and species protection. Wildlife loss due to development is a
significant concern, with this being another example. 
Comments: A Preliminary Ecological Appraisal (PEA) dated 15th April 2025 by Wild Surveys Ltd.
highlighted the site had potential for protected species and recommended dedicated protected species
surveys be carried out for the following: Otter, Bats, Water Vole, Badger and Great crested newt. The
Protected Species Survey Report dated 22nd July 2025 confirmed the relevant surveys were carried
out and no field signs were recorded (including eDNA survey for Great crested newt). NLC Greenspace
Development accepted the findings of these surveys. Notwithstanding a condition is also attached to
ensure the mitigation measures outlined within the PEA are put in place. 
8.          Planning Assessment 
8.1 Under Section 25 of the Town and Country Planning (Scotland) Act 1997, planning decisions must
be made in accordance with the development plan unless material considerations indicate otherwise.
The development plan comprises National Planning Framework 4 (NPF4) and the North Lanarkshire
Local Development Plan 2022 (NLLDP).  Where there is any incompatibility between these, the
policies of NPF4 take precedence.   
8.2 The existing data centre facility and its curtilage are designated as part of a strategic business centre. 
The proposed extension to this facility seeks permission to incorporate additional land to the east of
the data centre and this is designated as Green Belt land within the local development plan.   
8.3 Policy 1 - Tackling the Climate and Nature Crisis establishes that when considering all development
proposals, significant weight will be given to the global climate and nature crisis. The intent of the
policy is to encourage, promote and facilitate development that addresses the global climate
emergency and nature crisis. 
8.4 Policy 2 – Climate Mitigation encourages, promotes and facilitates development that minimises
emissions and adapts to the current and future impacts of climate change. To satisfy the requirements
of NPF4 Polices 1 and 2 the development incorporates specific design measures and features that
ensures long-term flood risk from climate change has been addressed by ensuring suitable post
development blockage scenarios are adopted and flood resistant and resilient design measures are
incorporated. Design principles based on a ‘Be Lean, Be Clean and Be Green’ strategy have been
applied. To minimise lifecycle greenhouse gas emissions and reduce climate change impacts
measures such as use of ‘free cooling’ chillers/condensers for process cooling, waste heat from Data
Halls being used to condition circulation space, use of mechanical ventilation to provide cooling when
ambient conditions allow; reducing reliance and use of process cooling plant, high efficacy LED
lighting, lighting controls including presence and absence detection and daylight dimming will all be
implemented. 
8.5 Policy 3 – Biodiversity requires local development to include appropriate measures to conserve,
restore and enhance biodiversity. The measures should be proportionate to the nature and scale of
development with any impacts being minimized through careful planning and design. The proposal
involves the diversion of an existing watercourse and removal of a number of trees. The characteristics
of the site required the submission of a Preliminary Ecological Appraisal (PEA) which highlighted the
need for further surveys to establish the presence, or potential presence of the following protected
species: otter, bat, water vole, badger and great crested newt. The Protected Species Survey Report
confirmed the relevant surveys were carried out and no field signs were recorded (including eDNA
survey for Great crested newt). The findings have been accepted by NLC Greenspace Development
who have requested the recommendations and general considerations put forward within the report
are taken forward. A landscape strategy and plan were received which includes biodiversity measures
in the form of tree, hedgerow and shrub retention where possible and biodiversity enhancement
measures including woodland creation, grassland enhancement with native shrubs and native
wildflower meadows. The diverted watercourse proposes a meandering channel to mimic natural
Page 55 of 154

Page 56

watercourse hydrology with varied profiled pools, over-deepened sections and shallow margins and
gentle banks and benches. The riparian corridor will be planted with aquatic and marginal species with
deadwood, stone pile and gravel banks and side pool features created for habitat creation. Site wide
habitat creation will be formed by the construction of hibernacula and nesting features for
invertebrates, birds, bats, amphibians and reptiles. Partial tree retention e.g. stumps and roots and
wood piles will also be left on site where practicable. Finally, educational interpretation signage will be
erected near enhanced areas to educate visitors about the specific biodiversity improvements. NLC
Greenspace Development confirmed the landscaping and biodiversity measures are well thought out
and that these matters are covered by the imposition of planning conditions to ensure all measures
are implemented. 
8.6 Policy 6 - Forestry, woodland and trees aims to protect and expand forests, woodland and trees.
Development proposals involving the loss of ancient woodlands, ancient veteran trees or that have an
adverse impact on trees with high biodiversity value or identified for protection on the Forestry and
Woodland strategy will not be supported. Removal of woodland will only be supported where they will
achieve significant and clearly defined public benefits and where woodland is removed, compensatory
planting will be expected. The tree cover within the proposed extension to the application site is less
dense than the adjoining green belt land. Two small groups of category C (low quality) trees require
complete removal as do 2 x category B (moderate quality) tree groups. Part of a larger Category A
(high quality) tree group will also be required to be removed; the remainder of the group is located out
with the application site and this will be retained. The Arboricultural Impact Assessment outlines that
1 veteran oak which is a category A (high quality) specimen is located within the site and this will be
retained. While the trees to be removed are of landscape value, they are not covered by a tree
preservation order and having been surveyed by an ecologist no field signs of protected species were
found. Furthermore, a robust landscape strategy and planting details have been received which
provides both landscape and biodiversity enhancements in the form of significant woodland creation
to compensate for the loss of the trees. Partial tree retention e.g. stumps and roots and wood piles will
also be left on site where practicable to provide further biodiversity benefits. NLC Greenspace
Development have confirmed they are supportive of the landscaping and biodiversity improvements. 
8.7 NPF4 Policy 8 states that development proposals within a green belt designation will only be supported
if they relate to certain categories of development and this includes the provision of essential
infrastructure as well as where there is an intensification of established uses, including extensions to
an existing building where that is ancillary to the main use. 
8.8 NPF4’s description of essential infrastructure includes digital communications infrastructure and as an
existing data centre this facility forms part of the critical physical infrastructure that enables and
supports digital communication. It can therefore be considered to be essential infrastructure. In
addition to this as the proposal involves an ancillary extension to an existing facility it is also considered
to be an intensification of use. Another of the categories of development supported within NP4 Policy
8. 
8.9  In assessment of these categories of development NPF4 Policy 8 requires development proposals to
meet five further requirements. Each of these is considered in turn below, 
- Reasons have been provided as to why a green belt location is essential and why it cannot be located
on an alternative site outwith the green belt; 
Response - The location is essential as it relates to an intensification of an established use, comprising
ancillary extensions to an existing facility. 
- The purpose of the green belt at that location is not undermined; 
Response - The proposal is considered to be a small scale extension into the green belt and its impact
given adjacent topography and woodland cover is not considered to be significant. 
- The proposal is compatible with the surrounding established countryside and landscape character; 
Response - The extension of the data facility, while considerable in terms of both footprint and
massing, is compatible with the scale and massing of the existing data centre and is considered to
align with the character of the adjoining business centre and will not considerably alter the general
character of the surrounding area. 
Page 56 of 154

Page 57

- The proposal has been designed to ensure it is of an appropriate scale, massing and external
appearance, and uses materials that minimise visual impact on the green belt as far as possible; 
Response - The proposal has been sensitively designed to be in keeping with the design, scale and
materials of the existing data facility and to minimise impacts on the views as far as possible. While
the proposal involves the removal of trees a robust landscape strategy and plan were received which
includes biodiversity measures in the form of tree, hedgerow and shrub retention. 
- There will be no significant long-term impacts on the environmental quality of the green belt
Response  - While the proposal involves the removal of trees a robust landscape strategy and plan
were received which includes biodiversity measures in the form of tree, hedgerow and shrub retention. 
Landscape and biodiversity enhancement measures include woodland creation, grassland
enhancement with native shrubs and native wildflower meadows. The diverted watercourse proposes
a meandering channel to mimic natural watercourse hydrology with various biodiverse features and
planting having a beneficial impact on the existing site and wider green belt. 
8.10 Policy 13 - Sustainable Transport establishes development proposals will be supported where it can
be demonstrated that the transport requirements generated have been considered in line with the
sustainable travel and investment hierarchies. The site is accessible by sustainable modes of
transport, and as this is an existing facility integrates effectively with the existing footpath and transport
network. 
8.11 Policy 14 - Design, Quality and Placemaking states that development proposals should be designed
to improve the quality of an area whether in urban or rural locations and regardless of scale.  Proposals
will be supported if the development is consistent with the six qualities of successful places, namely: -
Healthy, Pleasant, Connected, Distinctive, Sustainable and Adaptable.  The development is of a
contemporary design and scale which is consistent with the immediate data centre. It provides a
pleasant setting by protecting trees and hedgerows where possible and enhancing the landscaping of
the site by the planting of native trees, shrubs and hedgerows. The site benefits from excellent
connectivity with the existing footway and public transport network and the building’s contemporary
design and enhanced biodiversity and landscaping will provide a distinctive development appropriate
for the features of the site. The proposal takes a proactive approach to the efficient use of resources
and integrates nature positive, biodiverse solutions. It is also considered to be adaptable in terms of
meeting the challenges of climate change. 
8.12 Policy 19 – Heating and cooling encourages, promotes and facilitates development that supports
decarbonised solutions to heat and cooling demand and ensure adaption to more extreme
temperatures. In order to reduce the reliance and use of process cooling plant the applicant proposes
to use measures such as use of ‘free cooling’ chillers/condensers for process cooling, waste heat from
Data Halls in order to condition circulation space and the use of mechanical ventilation to provide
cooling when ambient conditions allow. There will also be no additional domestic hot water
requirements and existing direct electric water heating will be retained. The development will
incorporate the use of a closed-loop cooling system using water cooled chillers and dry air coolers for
heat rejection. The chilled water closed-loop cooling system uses minimal water after initial fill to top-
up the system over time. A pessimistic estimate of the system means it would use 541m3 annually. In
comparison to a typical office setting with 200 staff and using Cibse Guide G consumption data, a
calculated consumption would be around 1750m3 annually. This demonstrates the low water usage
in comparison with a typical working environment. 
8.13 Whilst currently there is no adjacent District Heat Network suitable for connection. The applicant has
advised that the facility will be capable of supporting heat networks by utilising the rejected heat from
the applicant’s clients IT hardware. This rejected heat could potentially be used as part of a heat
network. A condition has therefore been attached seeking appropriate infrastructure is installed so that
DataVita’s heat network could be utilised should an appropriate heat network zone off site be brought
forward. 
8.14 Policy 22 – Flood Risk and Water Management aims to strengthen resilience to flood risk by promoting
avoidance as a first principle and reducing vulnerability of existing and future development to flooding.
Page 57 of 154

Page 58

Development proposals at risk of flooding or in a flood risk area will only be supported in certain
circumstances. In this case, Policy 22 a) i. applies as this is considered essential infrastructure where
the location is required for operational reasons. SEPA flood maps indicate parts of the site are at high
risk of flooding from surface water and small watercourse flooding. Given this SEPA submitted a
holding objection relating to flood risk and requested a Flood Risk Assessment (FRA). Through
consultation with SEPA and the submission of an updated FRA, hydraulic modelling report and
amended plans they withdrew their objection on flood risk grounds. 
8.15 Policy 23 - Health and Safety seeks to protect people and places from environmental harm. Mitigate
risks arising from safety hazards and encourage, promote and facilitate development that improves
health and well being. Development proposals that are likely to have significant adverse effects on air
quality or raise unacceptable noise issues will not be supported. It is not considered that the proposal
raises any issues in respect of air quality. A Noise Impact Assessment has been provided and it is
considered that appropriate mitigation can be put in place to control noise from the facility. Appropriate
conditions have also been imposed to ensure that noise is assessed and where required appropriate
mitigation is put in place. It is considered that the site can be developed in such a way that there are
no issues with this policy. 
8. 16 Policy 24 – Digital infrastructure encourages, promotes and facilitates the roll-out of digital
infrastructure across Scotland to unlock the potential of all our places and the economy. The proposed
data centre expansion supports and contributes towards enhanced digital infrastructure and as such
complies with this policy. Whilst not a national development it will assist in the delivery of NPF4
National Development 12 which supports the continued expansion of the Digital Fibre Network,
including its supporting infrastructure. 
8.17  Policy 26 – Business and Industry seeks to encourage, promote and facilitate business and industry
uses and to enable alternative ways of working. Development proposals for business uses out with
designated business areas in the Local Development Plan will only be supported where it is
demonstrated that there are no suitable alternative sites and the nature and scale will be compatible
with the surrounding area. The development proposal will require to take into account the impact on
surrounding residential amenity, sensitive uses and the natural and historic environment. Given the
constrained nature of the site and the need for expansion of the facility’s capacity there is no alternative
location for the proposed extension. The proposal has a large footprint and massing but is considered
to acceptably relate to the scale and massing of the existing data centre, aligning with the character
of the wider strategic business centre. NLC Protective Services (Environmental Health) have accepted
the findings of a Noise Impact Assessment based on mitigation measures being implemented (these
measures include louvres, chiller temperature control, parapet height/screening and routine testing)
and as such the proposal is not considered to have an unacceptable impact on neighbouring
residential amenity. The impact of the proposed development on the watercourse, trees, protected
species, biodiversity and the green belt have been assessed and with appropriate mitigation in the
form of the various landscaping and biodiversity measures, which includes a realigned watercourse
with meanders and replacement tree planting, the proposal is considered to result in positive
landscape and biodiversity measures that will benefit the site and surrounding locale. 
8.18 Within the North Lanarkshire Local Development Plan the existing data centre facility and its current
curtilage are designated as part of a strategic business centre and are covered by PROM LOC 2 within
the local development plan. However, whilst the proposed extension is considered to align with the
requirements of this land use as the additional land required to form the proposed extension to the
east of the data centre is designated as Green Belt land within the local development plan the
proposed development requires to be assessed against the local development plan’s green belt policy,
PP 4: Purpose of Place. This policy seeks to protect the setting of communities, support regeneration
by directing growth to urban areas, protect natural assets and provide a high-quality environment. This
policy also requires such proposals to be assessed against the criteria of policy AD 4: Amount of
Development where planning applications will be assessed for their implications related to the amount
of development proposed. All applications also require to be appraised in terms of Environmental and
Design Qualities (EDQ) policies: Policy EDQ 1 (Site Appraisal), EDQ 2 (Specific Features for
Consideration) and EDQ 3 (Quality of Development). 
8.19 Policy PP4 Purpose of Place seeks to protect the setting of communities, support regeneration by
directing growth to urban areas, protect natural assets and provide a high-quality environment. The
Page 58 of 154

Page 59

Council will support developments for agriculture, forestry, recreation or developments that need a
non-urban location, including, where appropriate, Visitor Economy Development and will seek to resist
development that is not for any of the above uses. Development that needs a green belt location will
need to be balanced against any adverse effects on the purposes of the green belt and applications
made will be subject to an assessment of appropriateness. Policy AD 4 (Green belt – Amount of
development) also requires to be considered and this sets out criteria for assessing the amount of
development proposed within the Green Belt and for this type of development it advises that this should
also be considered through an assessment of appropriateness. 
8.20 The applicant has submitted an assessment of appropriateness stating that the proposed development
relates to an existing facility, the curtilage outwith the green belt is unviable for expansion, the
extension would be ancillary to the main building and its delivery will allow for the upgrading of the
existing capacity for data management representing additional plant space to service the data centre
and address technological change associated with digital and fibre technologies which in turn would
support the facility’s ability to compete within this fast paced and competitive market. Furthermore it is
also recognised that as the proposal relates to an extension of a facility that is located within an existing
Strategic Business Centre it is therefore sequentially more appropriate than a new site. This is
considered to be acceptable and for the reasons detailed in paragraph 8.9 above it is not considered
that the proposed development would have an adverse effect on the purpose of the green belt.   
8.21 Policy EDQ 1 (Site Appraisal) requires the development to be appraised in terms of the site and its
surroundings to ensure it will integrate successfully into the local area and avoid harm to neighbouring
amenity. A number of matters require to be assessed; those most relevant to this proposal are: 
• massing, height, style, finishing materials of any buildings on the site and surrounding Land Use
Character Area
• orientation and topography of the site and surrounding Land Use Character Area 
• building lines, plot ratios, groupings, types of enclosure (e.g. fences, walls, hedges), landmarks in
the Land Use Character Area 
• ground stability and contamination on the site and surrounding Land Use character Area
• existence and quality of connections and access including site and building entrances, roads,
paths and visuals on the site and surrounding Land Use Character Area 
• Green Network, landscape character and quality on the site and surrounding Land Use Character
Area
• biodiversity of plants and animals on the site and surrounding Land Use Character Area 
• the potential for installation and operation of low and zero-carbon generating technologies in new,
refurbished or re-purposed buildings 
8.22 The proposal is considered to be acceptable in terms of its design, height, scale, massing, facing
materials and location when considering the scale and massing of the existing facility.  The site is
relatively flat immediately east of the existing facility and then rises further east. However, it also slopes
southernly for most of its length before it begins to rise. The residential development on the north side
of Lancaster Avenue sits at a higher level than the site. The buildings within the strategic business
centre sited closest to Lancaster Avenue are all set well back from the road with a strong building line.
Both the plant extension and generator building are located to respect the existing building line. The
matters of ground stability and contamination have been assessed, and planning conditions are
attached in this respect. There will be no alterations to the existing access or public footpaths required
because of the proposal. The proposal involves a loss of green belt land with trees, however
compensatory woodland will be planted, and many biodiversity measures will be introduced. Design
principles based on a ‘Be Lean, Be Clean and Be Green’ strategy have been applied and measures
to minimise lifecycle greenhouse gas emissions and to reduce climate change impacts will be installed.
Taking into account all of the above and the mitigation measures that can be applied to control noise
the proposal is considered to integrate successfully in the locale without negatively impacting
residential amenity. 
Page 59 of 154

Page 60

8.23 Policy EDQ 2 (Specific Features for Consideration) states the Council will consider development in
areas subject to hazards (Hazardous Zones) in accordance with plans and protocols of the relevant
managing agencies. The hazards relevant to the application are Flood Risk, Contaminated Land and
Ground Instability (coal mining). The matter of Flood Risk has been thoroughly assessed through
consultation with SEPA resulting in an updated Flood Risk Assessment, hydraulic modelling report
and amended plans which SEPA have accepted. Contaminated Land has been considered by NLC
Protective Services (Environmental Health) with the requirement for the imposition of a planning
condition requiring a Site Investigation including a detailed mine gas risk assessment and if required
remediation measures to ensure potential risks arising from previous land uses around the site have
been fully assessed. The Mining Remediation Authority have confirmed they agree with the
conclusions of the submitted Geo-environmental Mining Risk Assessment; that coal mining legacy
potentially poses a risk to the proposed development and that investigations are required, along with
possible remedial and mitigatory measures, to ensure the safety and stability of the proposed
development. Appropriate planning conditions are attached. 
8.24 Policy EDQ 3 (Quality of Development) states proposals will only be permitted where high standards
of site planning and sustainable design are achieved. The proposal is considered to comply with this
policy as it will result in a well-designed development with improved landscaping and biodiversity
enhancements. Access for all abilities will be maintained at the site and linkages to the wider footpath
network and sustainable modes of transport will not be affected. It is therefore considered that the
proposals comply with the Environmental and Design Qualities policies of the North Lanarkshire Local
Development Plan 2022.  
9.          Conclusions 
9.1 Taking account of the above, whilst it is recognised that the proposed extension to the facility would
result in development in the green belt for a use outwith those supported within Policy PP4 (Green
Belt – Purpose of Place) of the North Lanarkshire Local Development Plan it is considered to be an
acceptable departure. It is considered to align with the requirements of NPF4 and that of NPF4 Policy
8 Green Belt. The assessment of appropriateness provided by the applicant has also demonstrated
the need for this location and is considered acceptable. It is not considered that the development will
have an adverse effect on the purpose of the Green Belt and it is considered that impact on the
environment and amenity can be controlled by the attached planning conditions. It is therefore
recommended that planning permission is approved. 
Page 60 of 154

Page 61

Application No:  
25/00713/FUL
Proposed Development: 
Proposed redevelopment of an existing renewable biogas facility
and associated works 
Site Address: 
Site At
Old Quarry Road
Westfield
Cumbernauld
North Lanarkshire 
Date Registered: 
14th July 2025 
Applicant:
Deerdykes Bioenergy Limited
C/o Agent 
Agent:
Axis P.E.D. Limited
Barfield House
Alderley Road
Wilmslow
SK9 1PL 
Application Level:
Major Application 
Contrary to Development Plan:
No
Ward:   
02 Cumbernauld North 
Danish Ashraf, Tom Fisher, Alan Masterton,
Gordon Currie,
Representations:
No letters of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The principle of the proposed development is considered acceptable. The proposed
redevelopment of an existing renewable biogas facility and associated works is
considered acceptable in terms of the criteria set out in the relevant policies,
particularly PP2A (Strategic Business Centres), AD2A (Amount of Development) and
policies EDQ 1-3 of the North Lanarkshire Local Plan 2022. The proposal similarly
does not raise any issues with regards to National Planning Framework 4, particularly
Policy 1 Tackling the climate and nature crisis and Policy 2 climate mitigation and
adaption. The proposal shall assist with the Scottish Governments broader energy
policy which aims to transition to a net-zero energy system by 2030, with a focus on
renewable energy sources. 
Page 61 of 154

Page 62

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 25/00713/FUL 
Name (of applicant): Deerdykes
Bioenergy Limited
Site Address: Site At
Old Quarry Road
Westfield
Cumbernauld
North Lanarkshire 
Development: Proposed redevelopment
of an existing renewable biogas facility
and associated works   
Page 62 of 154

Page 63

Proposed Conditions:- 
1. That, except as may otherwise be agreed in writing by the Planning Authority, the development shall
be implemented in accordance with drawing numbers:- 
4244-PL02, 4244-PL03, 4244-PL04, 4244-PL05, 4244-PL06, 4244-PL06A, 4244-PL07, 4244-PL08,
4244-PL09, 4244-PL10, 4244-PL11, 4244-PL12, 4244-PL13, 4244-PL14, 4244-PL15, 4244-PL16 ,
4244-PL17, 4244-PL18, 4244-PL19, 4244-PL20, 4244-PL21, 4244-PL22, 4244-PL23, 4244-PL24,
4244-PL25, 4244-PL26, 4244-PL27, 4244-PL28, 4244-PL29, 4244-PL30, 4244-PL31, 4244-PL32,
4244-PL33, 4244-PL34 , 4244-PL35, 4244-PL36, 4244-PL37, 5010-01-01, 5010-CP-01, 5010-LOC-
01 and E2679-MCA-ST1-00-DR-C-1009. 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That no open-air storage of any digestate shall take place within the application site. 
Reason: In the interest of the amenity of the site and the general area. 
3. Prior to development being brought into beneficial use, an updated Traffic Management Plan,
comprising both construction phase and operational phase, shall be submitted to, and approved in
writing by, the Planning Authority in conjunction with our NLC Traffic & Transportation
colleagues.  This Traffic Management Plan shall include, but not be limited to, the following details; 
A) A drawing detailing an area for HGV’s to wait within site, with sight-lines for the entirety of Old
Quarry Road, shall be submitted to, and approved in writing by, the Planning
Authority.  Thereafter the HGV waiting area shall be maintained and retained in perpetuity for
the duration of the hereby approved development.
B) No vehicle leaving the site should deposit mud and debris onto the public road network.
Mandatory washing of the vehicles shall be required prior to entering the public carriageway for
all HGV’s.
C) All HGV vehicles require to be ‘sheeted’ when entering or exiting site and during their journey on
the public road network.
D) Further monitoring, in the form of a report dated one year from the site being brought into
beneficial use, shall be submitted to NLC Traffic & Transportation identifying additional traffic
management measures that may be required to assist with traffic flow and maintain safety.
E) No access to agricultural vehicles shall be permitted on site
F) A detailed plan for construction workers car parking shall be submitted. This shall detail
sufficient spacing to ensure there is no parking on the public highway / footpath network.
Reason: To ensure there is no vehicular conflict on the ‘Old Quarry Road’, to prevent debris and
mud entering the public road network, to maintain road safety and in the interests of pedestrian
safety. 
4. Before any construction works start on site, the applicant shall enter into an agreement with the
Council, (as Roads Authority) in terms of Section 96 of the Roads (Scotland) Act 1984 for
extraordinary expenses in repairing roads damaged by heavy vehicles during both the construction
and operational phases of the development. 
Reason: To ensure the public highway is fit for purpose and to prevent the Council being held
responsible for financial implications of any repairs required and brought about by heavy goods
vehicles. 
5. All details within the ‘Flood Risk Assessment & Drainage Strategy’, dated June 2025 and prepared
by Waterco, published by Jack Pugh, 16152-FRA and Drainage Strategy, shall be implemented
contemporaneously with the development, insofar as reasonably practicable.
Page 63 of 154

Page 64

Reason: In the interests of safeguarding the watercourse in close proximity to the development.  
6. That BEFORE any works of any description start within the site, unless otherwise agreed in writing
with the Planning Authority, a comprehensive site investigation report shall be submitted to and for
the approval of the said Authority. The investigation must be carried out in accordance with current
best practice advice, such as BS 10175: 'The Investigation of Potentially Contaminated Sites' or CLR
11.  The report must include a site specific risk assessment of all relevant pollution linkages and a
conceptual site model.  Depending on the results of the investigation, a detailed Remediation
Strategy may be required and this strategy will include details of the schedule for validation reporting
to confirm that the remediation works have been carried out before houses are occupied. 
Reason:  To establish whether or not site decontamination is required in the interests of the amenity
of the area. 
7. That any remediation works identified by the site investigations required in terms of Condition 6
above shall be carried out to the satisfaction of the Planning Authority.  A certificate (signed by a
chartered Environmental Engineer) shall be submitted to the Planning Authority in accordance with
the agreed schedule of validation reporting confirming that any remediation works have been carried
out in accordance with the terms of the Remediation Strategy. 
Reason:  To ensure that the site is free of contamination. 
8. Should no development commence within 1 year from the date of the Preliminary Ecological Surveys,
8th April 2026, further updates shall be provided for the written approval of the Planning Authority
before any development starts. Following written approval by the Planning Authority, opportunities for
biodiversity enhancements as identified within the relevant reports in respect to habitat, animal welfare
issues and protected species protection shall be complied with in full, including securing any licences
from Scottish Natural Heritage.  
Reason: In the interests of Nature Conservation. 
9. Unless otherwise agreed in writing with the Planning Authority, the construction hours shall be 8am –
7pm Monday to Friday and 8am to 1pm Saturday and there should be no audible noise associated to
construction at the site boundary out with these permitted hours. 
Reason: In the interest of the amenity of the site and the general area. 
Background Papers: 
Consultation Responses: 
Environmental Health (including Pollution Control) 
National Air Traffic Services (Safeguarding) Mailbox 25, 400 
Scottish Environment Protection Agency 
Traffic & Transportation 
Environmental Health (including Pollution Control) 
Estates Team 
NLC Greenspace 
Scottish Environment Protection Agency 
NLC Water Management Team 
Contact Information: 
Any person wishing to inspect these documents should contact Colin Bradley at 01236 632500 
Report Date: 12th November 2025
Page 64 of 154

Page 65

APPLICATION NO. 25/00713/FUL 
REPORT 
1. Site Description 
1.1 The Site measures circa 4.1 Hectares and shall be accessed from Old Quarry Road within the
Westfield Industrial Estate. There shall be a one-way roadway throughout the site to accommodate
both delivery and removal of the by-product material. 
1.2 Within the internal, one-way road system there will be a ‘Feedstock Reception’ building and a
‘Feedstock Storage Building’ immediately adjacent. This then feeds on to the ‘digestive tanks where
the biproduct is consumed.  To the Southeast and the Southwest of the site there is sufficient space
for 6 lorries, (3 at each corner) to collect the fertilizer.  The site also accommodates two
‘weighbridges’ one at the entrance and one prior to leaving site along with a wheel wash located
immediately adjacent to the latter weigh-station. 
1.3 There is an existing ‘Administration Building’ located to the North-West of site to accommodate all
administrative functions associated to the site along with various additional pieces of infrastructure
such as an enclosed ‘flare’ unit etc. 
2. Proposed Development 
2.1 It should be noted that this site formed part of the pre-application process with the Invest NL team and
the application has followed on from the findings and conclusions of the process. 
2.2 The proposed development seeks to expand the anaerobic digestion operations and processes
already undertaken at a previous Scottish Water treatment plant within the ‘Westfield Industrial Park’
in the settlement of Cumbernauld. 
2.3 Located at the southwest of the industrial estate and accessed via Old Quarry Road, immediately
adjacent to Deerdykes road, the Biogas Plant, is intending to process circa 200,000.00 tonnes per
annum. This equates to an intensification of 566% from current levels of processing and as such, this
application is considered to be equivalent to a Change of Use application. 
2.4 The feedstock mix shall comprise organic waste materials and by-products, (non-waste), from the food
and beverage sector. The out-puts are expected to comprise a mixture of Methane (circa 60%)
distributed directly into the national grid, and CO2 (circa 40%) which shall require to be transported off
site via vehicles. Any physical residue is intended to be sold off to the agricultural / horticultural sector
as fertilizer. 
3. Applicant’s Supporting Information 
3.1 Alongside a full suite of drawings, the applicant has provided the following documents;   
PLANNING, DESIGN AND ACCESS STATEMENT 
APPLICANT UPDATE PROPOSAL OF APPLICATION NOTICE 
PRE-APPLICATION CONSULTATION REPORT 
AIR QUALITY INCL ODOUR ASSESSMENT 
CLIMATE CHANGE ASSESSMENT 
ARBORICULTURAL REPORT 
POLICY BUSINESS COMMUNITY ALIGNMENT AND ECONOMIC IMPACT ASSESSMENT 
NOISE IMPACT ASSESSMENT 
LANDCAPE AND VISUAL APPRAISAL 
LVA APPENDIX A LVA METHODOLOGY 
LVA FIGURE 1 VISUAL CONTEXT PLAN 
LVA FIGURE 2 LANDSCAPE CONTEXT PLAN_FINAL 
LVA FIGURE 3-1 VIEWPOINT 1 EXISTING VIEW 
LVA FIGURE 3-2 VIEWPOINT 2 WIREFRAME VIEW_FINAL 
LVA FIGURE 3-3 VIEWPOINT 3 EXISTING VIEW
Page 65 of 154

Page 66

LVA FIGURE 3-4 VIEWPOINT 4 EXISTING VIEW 
LVA FIGURE 3-5 VIEWPOINT 5 EXISTING VIEW 
LVA FIGURE 3-5 VIEWPOINT 5 WIREFRAME VIEW 
LVA FIGURE 3-6 VIEWPOINT 6 EXISTING VIEW 
LVA FIGURE 3-7 VIEWPOINT 7 EXISTING VIEW 
TRANSPORT ASSESSMENT 
CONSTRUCTION TRAFFIC MANAGEMENT PLAN 
FLOOD RISK AND DRAINAGE STRATEGY 
HERITAGE IMPACT ASSESSMENT 
HIA PLATES_FIGURES_ APPENDICES-COMBINED 
OVERVIEW NOTE OF ECOLOGICAL ASSESSMENTS UNDERTAKEN 
PRELIMINARY ECOLOGICAL APPRAISAL 
MAMMAL SURVEY 
BAT SURVEY REPORT AND SPECIES PLAN 
BIODIVERSITY STATEMENT 
PHASE 1 CONCEPTUAL SITE MODEL AND GEO-ENVIRONMENTAL RISK ASSESSMENT 
OUTLINE CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN 
OUTLINE CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN 
4. Site History 
4.1 25/00277/PAN Anaerobic digestion facility and associated works – comments given 20th March 2025
25/00477/EIASCR Proposed development of a new anaerobic digestion facility – Conclusion of EIA
Not Required- 13th May 2025. 
5. Development Plan 
5.1 Under Sections 25(1) (a) and 37(2) of the Town and Country Planning (Scotland) Act 1997, planning
decisions must be made in accordance with the development plan unless material considerations
indicate otherwise.  The statutory development plan for North Lanarkshire currently consists of
National Planning Framework 4 (NPF4) and the North Lanarkshire Local Development Plan 2022
(LDP).  
5.2 The following development plan policies are considered most relevant to the assessment of the
proposal:  
National Planning Framework 4  
Policy 1 - Tackling the climate and nature crisis
Policy 2 - Climate mitigation and adaptation
Policy 3 - Biodiversity
Policy 6 - Forestry, woodland and trees
Policy 11 - Energy
Policy 12 - Zero Waste 
Policy 13 - Sustainable Transport
Policy 14 - Design, Quality and Place
Policy 18 - Infrastructure First
Policy 19 - Heat and cooling
Policy 22 - Flood risk and water management.
Policy 23 - Health and safety
Policy 26 - Business and Industry 
North Lanarkshire Local Development Plan (2022) 
Policy PROM LOC1 (Regeneration Priorities) 
Policy PROM LOC2 (Business Development Sites) 
Policy PROM ID2 (Utilities Improvements) 
Policy 2A (Business Centres, Strategic Business Centres Area)
Policy CI (Contributions to Infrastructure) 
Prot Policies
Page 66 of 154

Page 67

EDQ Policies  
6. Consultations 
6.1 Consultations were undertaken with the following parties, a synopsis of their responses shall be
undertaken in the following paragraphs;    
NLC Protective Services
NLC Traffic & Transportation
NLC Greenspace
NLC Water Management
NLC Estates Team
National Air Traffic Services (Safeguarding)
SEPA (South) 
6.2 SEPA (South) initially responded to state that they wished to hold an objection to the proposal on
two principle grounds;  
1) Flood Risk, &
2) Waste Management & Permitting. 
The applicant provided a statement in response to the holding objection and upon receipt of that
response, the holding objection was withdrawn. The reason for the withdrawal of the objection with
regards to flood risk was based on “…the best understanding of long-term flood risk at the present
time and is in line with current policy and guidance.” 
With regards to point 2 of their holding objection, it was noted that there was an existing “PPC”
permit and that an alteration was being sought to this.  It was further noted that the applicant was
“…fully committed to early engagement with the SEPA Waste Permitting Team on this process. The
applicant met with SEPA Inspector in May to inform him of their plans and, upon determination of our
planning application, they said that they will begin the process of varying our PPC permit with the
SEPA permitting team immediately.” 
It is therefore concluded that SEPA do not seek to object to the proposal.  
6.3 NATS (National Air Traffic Services – Safeguarding) responded stating the “…proposed
development has been examined from a technical safeguarding aspect ad does not conflict with our
safeguarding criteria. Accordingly, NATS (En Route) Public Limited Company (“NERL”) has no
objection to the proposal.” 
6.4 NLC Estates have no objections to the development proposal.  
6.5 NLC Water Management Team stated that the Flood and Drainage Assessment, as supplied by the
applicants, is considered to be suitable and all recommendations there-in should be conditioned to the
granting of any permission. 
6.6 NLC Traffic & Transportation responded with a series of observations they sought to be conditioned
to any positive determination detailing a Traffic Management Plan featuring both construction and
operational phases. It was further sought that an agreement in terms of a Section 96 of the Roads
Scotland Act 1984 to allow the council to recover expenses concerned in repairing roads due to HGV
movements. 
6.7 NLC Protective Services have reviewed the ‘Noise Impact Assessment’ report (Noise and Vibration
Consultants Ltd, June 2025) and have concluded that the proposal does not present any issues that
would warrant any conditions or informatives to be added to the recommendation.  They further stated
that the reports submitted on ‘Air Quality and Odour’ would be within the remit of SEPA for
consideration.  They have however requested a condition that a Site Investigation report is submitted
and approved before development starts on site.  This has been added as a condition.  
6.8 NLC Greenspace stated that NPF 4 places a duty on planning and development will help to achieve
Page 67 of 154

Page 68

positive effects for biodiversity and advises that Nature Scots guidance on Developing with Nature
refers to the inclusion of “appropriate measures” not only to mitigate for the loss of biodiversity but also
to enhance biodiversity.  The Preliminary Ecological Assessment put forward Ecological Constraints
and Opportunities for biodiversity enhancements which should be incorporated into the development
in order to comply with Policy 3, Biodiversity, of NPF 4.  Suitable conditions have been included to this
recommendation to reflect this advice. 
7. Representations 
7.1 Following advertisement in the local newspaper and neighbourhood notification, no letters of
representation were received. 
8. Planning Assessment 
8.1 This application is seeking to repurpose a former Scottish Water, Waste-Water Plant which is located
between the Westfield Industrial Estate and the Northbound M73 Fly over prior to the confluence of
this road and the M80 (Northbound). It is intended to repurpose the site to be used exclusively for Bio-
Gas, an activity to which the site plays host to presently. 
8.2 Section 25 of the Town and Country Planning (Scotland) Act 1997 states that planning applications
are to be determined in accordance with the Development Plan unless other material considerations
indicate otherwise. Upon its adoption on the 13th of February 2023, National Planning Framework 4
(NPF4) became part of the statutory ‘Development Plan’. It supersedes both Scottish Planning Policy
(2014) and the Clydeplan Strategic Development Plan (2017). As a result, the Development Plan in
respect of this site now comprises NPF4 (2023) and The North Lanarkshire Local Development Plan
(adopted 2022). On 8th February 2023, the Chief Planner for Scotland published Transitionary
Arrangements Guidance which set out further details regarding how NPF4 should be applied. This
confirmed that adopted Local Development Plans will continue to be part of the development plan. In
circumstances such as North Lanarkshire’s, where the Local Development Plan (LDP) has been
adopted prior to publication of NPF4, legislation states that in the event of any incompatibility between
a provision of NPF4 and a provision of an LDP, whichever of them is the later in date is to prevail.
Accordingly, the proposed development requires to be assessed against the provisions and policies
of both NPF4 and the LDP. 
National Planning Framework 4 (NPF4) 
8.3 With regards to NPF4, the site is impacted by a variety of policies as highlighted in section 5.2 of this
report.   
Policy 1 (Tackling the climate and nature crises) establishes that significant weight must be given to
the global climate and nature crises in the assessment of all development proposals. It requires
planning authorities to consider how proposals contribute to reducing greenhouse gas emissions,
enhancing climate resilience and supporting nature recovery and restoration. 
Policy 2 (Climate mitigation and adaptation) requires that development proposals are sited and
designed to minimise lifecycle greenhouse gas emissions and adapt to current and future climate
risks. Proposals must demonstrate how they reduce emissions through location, design and
construction, and support climate resilience by avoiding vulnerable areas and enabling adaptation.
Retrofitting measures to existing developments that reduce emissions or improve resilience will be
supported. 
Policy 3 (Biodiversity) requires that development proposals contribute to the enhancement of
biodiversity, including the restoration of degraded habitats and strengthening of nature networks.
Proposals must integrate nature-based solutions where feasible and apply the mitigation hierarchy to
address potential adverse effects. Major developments and those requiring Environmental Impact
Assessment must demonstrate significant biodiversity enhancements, informed by best practice
assessment methods, and include long-term management arrangements. Proposals should be
based on an understanding of the site’s ecological context and consider community benefits. Local
development proposals must include proportionate measures to conserve and enhance biodiversity,
unless exempt.
Page 68 of 154

Page 69

Policy 6 (Forestry, woodland and trees) sets out that development proposals should protect and
enhance existing woodland and tree cover, and support expansion where appropriate. Proposals
that result in the loss of ancient woodlands, ancient or veteran trees, or adversely impact native
woodlands, hedgerows or trees of high biodiversity value will not be supported. Woodland removal
will only be permitted where significant public benefits are demonstrated, and compensatory planting
is expected. Proposals on sites with existing woodland or identified for woodland creation must
integrate enhancement and new planting into the design. 
Policy 11 (Energy) outlines that development proposals for all forms of renewable, low-carbon and
zero-emission energy technologies will be supported, including wind farms, solar arrays, energy
storage, and carbon capture. Proposals must demonstrate how they address potential impacts on
residential amenity, landscape, biodiversity, aviation, telecommunications, transport, and the historic
and natural environment. Wind farms will not be supported in National Parks or National Scenic
Areas. Significant weight will be given to the contribution of proposals to renewable energy targets
and emissions reduction. Grid capacity should not constrain development, and underground
connections should be considered. Proposals must include robust site restoration and
decommissioning plans. 
Policy 12 (Zero Waste) requires that development proposals must support the transition to a circular
economy by reducing, reusing and recycling materials in line with the waste hierarchy. Proposals
should minimise demolition, reuse existing buildings and infrastructure, and use low-emission,
recyclable or reusable materials. Developments that generate operational waste must demonstrate
how waste will be managed, including segregation, storage, and access for collection. Waste
infrastructure proposals (excluding landfill and energy-from-waste) will be supported where
environmental and amenity impacts are acceptable and restoration plans are in place. Energy-from-
waste facilities will only be supported where a national or local need is demonstrated, and the
proposal aligns with climate targets and circular economy principles. 
Policy 13 (Sustainable Transport) requires that development proposals must prioritise sustainable
and active travel in line with the sustainable travel and investment hierarchies. Proposals should
provide safe, direct and accessible walking, wheeling and cycling links, integrate with public
transport, and include infrastructure such as electric vehicle charging and secure cycle parking.
Significant travel-generating uses must be located where they do not increase reliance on private
cars and should be supported by a transport assessment and travel plan. Proposals with low or no
car parking will be supported in well-connected urban areas. Impacts on the strategic transport
network must be assessed, and mitigation measures funded by the developer where necessary. 
Policy 14 (Design, quality and place) promotes a design-led approach to development, requiring
proposals to improve the quality of an area, regardless of scale or location and be consistent with
the six qualities of successful places which are Healthy, Pleasant, Connected, Distinctive,
Sustainable and Adaptable. Poorly designed proposals that detract from the character or amenity of
the area, or fail to meet these qualities, will not be supported. 
Policy 18 (Infrastructure first) requires that development proposals must demonstrate that
infrastructure requirements are addressed in line with the Local Development Plan and its delivery
programme. Proposals should contribute to or provide necessary infrastructure and mitigate any
impacts on existing infrastructure. Planning conditions and obligations must meet legal and policy
tests, ensuring they are necessary, proportionate, and directly related to the development.
Infrastructure considerations should be integrated early in the planning process, prioritising low-
carbon solutions and aligning with national, regional and local infrastructure strategies. 
Policy 19 (Heating and cooling) requires that development proposals must support the transition to
low-carbon heating and cooling systems and promote climate resilience. Proposals within or
adjacent to designated Heat Network Zones must be designed to connect to existing or planned heat
networks or allow for future cost-effective connection. Retrofitting connections to heat networks is
supported. National and major developments generating waste or surplus heat should include a Heat
and Power Plan to demonstrate how energy will be recovered and used. Proposals should also
prioritise passive design measures—such as siting, orientation and materials—to manage
temperature sustainably.
Page 69 of 154

Page 70

Policy 22 (Flood risk and water management) promotes a precautionary approach to flood risk and
requires that development proposals must avoid areas at flood risk as a first principle and
demonstrate resilience to current and future climate impacts. Proposals in flood risk areas will only
be supported in limited circumstances, such as for essential infrastructure or redevelopment of
previously used sites, and must show that long-term safety and resilience can be secured. All
development must manage rain and surface water through sustainable urban drainage systems
(SUDS), minimise impermeable surfaces, and avoid increasing flood risk to others. Proposals should
support natural flood risk management and improvements to the water environment and be informed
by relevant flood risk and river basin management plans. 
Policy 23 (Health and safety) seeks to ensure that development proposals improve public health and
wellbeing and avoid significant adverse effects on health, air quality, and noise. Provide appropriate
infrastructure for health and social care, consider suicide risk and proximity to hazardous sites and
apply the agent of change principle to noise-sensitive developments. 
Policy 26 (Business and industry) seeks to ensure that development proposals for business and
industrial uses will be supported where they are located on sites allocated for such uses in the Local
Development Plan or where they are compatible with the surrounding area. Proposals for
homeworking, live-work units, and micro-businesses are encouraged where they do not adversely
affect residential amenity. Proposals out with allocated areas must demonstrate a lack of suitable
alternatives and be appropriate in scale and impact. Major industrial developments must include a
decarbonisation strategy. All proposals should consider impacts on amenity, the environment, and
include restoration plans where relevant. 
With regards to the policies of NPF 4 identified in Section 5.2 of this report, this application is not
considered to present any issues with regards to the individual policy intent nor with the overarching
aims of the NPF 4 as a whole. 
NLLDP (2022) 
8.4 The site is located within a Strategic Business Centres Area (Policy 2A) within the North Lanarkshire
Local Development Plan (2022) (LDP) which comprises policies PP2A Purpose of Place and AD2A
Amount of Development.  These policies seek to encourage large scale business users to locate in
these areas in order to safeguard their dilution by other inappropriate uses and support the
upgrading of premises, amenities, access, parking and green space. 
8.5 The proposed development would be located adjacent to an existing anaerobic digestion facility and
within the curtilage of a larger site. For proposals relating to classes 4, 5 or 6 of the Use Classes
Order, no assessment of the amount of development required is necessary within these areas.
However, for renewable energy and utilities infrastructure (waste management) the principle of the
development is accepted subject to the proposal meeting the requirements of LDP, EDQ, PROM and
PROT policies. On this basis the principle of the proposal is considered to be acceptable, but
requires further assessment against these other policies.  Further to this, as the proposed
development relates to renewable energy and waste management, these forms of development
come under the scope of Policy PROM ID2 Utilities Improvements. This advises that the Council will
support utilities development in principle, subject to assessment of the criteria in this policy and other
relevant policies in the local development plan. 
8.6 In terms of the assessment of the waste criteria of Policy ID2, the principle of the development is
considered to be acceptable as the site is at an existing waste management facility, in a designated
Business Centre and would be able to support the delivery of the Zero Waste Plan objectives. This
policy also states that the facility would also need to comply with the EU Waste Framework Directive,
National Waste Plan, regional guidance and issues of need and impact. 
8.7 In terms of the assessment of the renewable energy criteria of Policy ID2. The Council recognises
that there is a range of means of generating renewable energy and will support, where appropriate,
alternative technologies and associated infrastructure, subject to assessment against any relevant
legislation and other relevant policies in the local development plan. Planning applications will be
assessed for their suitability for being located in the Land Use Character Area in which they are
Page 70 of 154

Page 71

proposed along with any impact on the natural or historic environment and will be assessed against
the plan's Protecting Assets and Environmental and Design Qualities Policies.  Policy ID2 also
advises that proposals for renewable energy development must have regard to the considerations
set out in Scottish Planning Policy paragraph 169. SPP was replaced by NPF4. Legislation states
that in the event of any incompatibility between a provision of NPF4 and a provision of a LDP,
whichever of them is the later in date is to prevail. Accordingly, NPF4 policies will prevail over any
LDP policies and the policy advice provided within NPF4 Policy 11 Energy should be addressed, in
place of paragraph 169 of SPP. 
8.8 Finally, it should also be noted that Policy ID2 also seeks the removal of operationally redundant
generating equipment through a decommissioning process and the restoration of the location to the
council's satisfaction through Planning Conditions. 
8.9 Environmental Design Qualities are intended to improve the development and environment through
its 3 sub-policies, EDQ 1-3.  It is considered that this proposal aligns with the EDQ policies and
therefore these are not considered to be an impediment to development in this instance. 
Prot Policies seek to protect the natural assets of North Lanarkshire through protecting the Green
Network, Historic & Natural Environments and Mineral Resources.  This application does not conflict
with any of the Prot Policies. 
Design, Scale, Lay-Out and Character; 
8.10 The Lay-out of the site shall alter significantly, however the internal roadway and the existing
administration building shall remain in-situ as they currently are. The internal ‘loop’ roadway shall retain
its 2 weighbridges and 1 wheel-wash which are incorporated into the design of the ‘flow’ of the site.
The security gate at the entrance to the site shall also remain in-situ as is. The precise design, within
the ‘loop’ of the internal roadway, an area of flat hardstanding which is currently used for highway
maintenance signs, it is intended to provide a ‘feedstock reception hall’ and a ‘feedstock storage area
building (both of which shall feature a ‘negative pressure system’ to prevent odour escape). This shall
be located immediately after the 1st weighbridge upon entering the site.  Immediately adjacent to these
buildings shall be an ‘odour control building’ 
8.11 It is further intended to be fitted out with a series of Tanks and associated buildings/components to
assist with the running of the ‘digesting’ of the waste and non-waste product. It is intended to include
a series of large tanks within this area comprising 4 nr. ‘Digester tanks’, 1 nr. ‘Digestate tank’, a
‘Hydrolysis Buffer Tank’, ‘Liquid Feedstock Tanks’. Alongside these large tanks, various smaller
infrastructure units are required including ‘technical rooms’, ‘pasteurisation tanks’ and ‘heat
exchangers’.  Externally to the ‘loop’ of the internal roadway, and generally to the west of the site, shall
be various other pieces of essential infrastructure including a ‘gas grid entry unit’, ‘propane tank’,
‘biogas upgrade tank’, ‘combined heat power plant’ unit, ‘desulphurisation unit’, ‘boiler’, ‘flare units’
and CO2 liquefaction plant’. 
8.12 As the site has previously been used as a waste-water treatment plant, there are significant numbers
of large, infrastructure pieces that define the character of the site as being industrial in nature. The
precise make up of these industrial components shall be altered as a direct result of the granting of
this permission however it is not considered this shall result in a ‘character change’ to the site.  Overall,
and taking into consideration the various consultation responses, it is not considered that there shall
be a negative impact on the surrounding industrial land as a direct result of permitting the proposed
alterations as outlined above. The scale and massing, design and layout do not represent an
impediment to development. 
8.13 Residential Amenity, Odour Control, Noise; The closest residential dwellings are located in the
settlements of Moodiesburn, located some 1,500m to the west, Mollinsburn, located some 500m to
the south and the western end of Condorrat, located some 1,000m to the east.  All of these settlements
are located across from the M80 and M73 motorways from the proposed development site. The site
is considered to be sufficiently far enough away from residential properties that their amenity should
not be affected by the proposals.  It is considered that there are no issues in terms of noise expected
from the site.  SEPA are the regulatory authority and will assess any odour issue should it arise. 
Page 71 of 154

Page 72

8.14 Transport Access and Parking; It is anticipated that the vehicles visiting the site shall have a payload
of 24 tonnes and there shall be a total of 116 vehicle movements per day, (58 vehicle movements in
and 58 vehicle movements out per day).  The majority of these vehicle movements would be
undertaken between the hours of 07:00 to 19:00, however there may be the requirement for
occasional, additional vehicle movements outside of these hours due to the nature of the business.
Additionally, it is anticipated that there shall be 30 vehicle movements by private cars / light goods
vehicles for the staff movements. 
8.15 NLC Traffic & Transportation have been consulted with regards to this application and did not seek to
oppose the proposed development, subject to conditions.  The conditions requested relate to the
submission of a ‘Traffic Management Plan’ and an agreement with regards to Section 96 of the Roads
(Scotland) Act 1984, for extraordinary expenses in repairing roads damaged by heavy vehicles during
construction. The Traffic Management Plan should be split into two principle elements, the construction
phase and the post construction, operational stage, however they may be submitted as a single
document for review. The document should include the mandatory use of wheel washes, the use of
‘sheeting’ to prevent any material being deposited on the public road, the provision of internal stacking
to prevent vehicle conflicts on the Old Quary Road and construction staff parking provision. These
conditions have been carried over to this recommendation and shall be further carried over to the
decision notice in the event of a successful conclusion to this application 
8.16 Flooding and Drainage; The site sits in close proximity to the Luggie Water. Mapping generated by
SEPA indicates that some parts of the site may be affected by surface water and small watercourses
flooding. An appropriate assessment would therefore require to be carried out to demonstrate that
these matters can be addressed and if mitigation is required that this can be put in place effectively. 
SEPA (South) have been consulted with regards to this application and with regards to flooding in
general and any potential impact on the Luggie water and have concluded that the proposal does not
exacerbate the current flood risk. 
9. Conclusions 
The principle of the proposed development is considered acceptable. The proposed redevelopment
of an existing renewable biogas facility and associated works is considered acceptable in terms of
the criteria set out in the relevant policies, particularly PP2A (Strategic Business Centres), AD2A
(Amount of Development) and policies EDQ 1-3 of the North Lanarkshire Local Plan 2022. The
proposal similarly does not raise any issues with regards to National Planning Framework 4,
particularly policy 1 Tackling the climate and nature crisis and policy 2 climate mitigation and
adaption. The proposal shall assist with the Scottish Governments broader energy policy which aims
to transition to a net-zero energy system by 2030, with a focus on renewable energy sources. As
such, it is recommended that approval is given subject to conditions. 
Page 72 of 154

Page 73

Application No:  
25/00794/FUL 
Proposed Development: 
Residential Development (5no. Proposed Houses) and Green
Network Enhancement 
Site Address: 
Land at
Dullatur Road And King's Drive
Dullatur
Cumbernauld 
Date Registered: 
6th August 2025 
Applicant:
JGS Developments (Lenzie)
90 Mitchell Street
6th Floor Garden Chambers
Glasgow
G1 3NQ 
Agent:
S2 Architecture
Unit 3
5 Auchinairn Road
Bishopbriggs
G64 1RX 
Application Level:
Local Application 
Contrary to Development Plan:
Yes 
Ward:   
02 Cumbernauld North 
Danish Ashraf, Tom Fisher, Alan Masterton,
Gordon Currie,
Representations:
259 letters of representation received
(including from Jamie Hepburn MSP and 
Cllr Masterton)   
Recommendation: Refuse 
Reasoned Justification: 
Residential development on this site is not supported by the aims of the Development Plan as
this development will result in a significant reduction of the designated Green Network
established to connect natural, semi-natural, and man-made open spaces to support
biodiversity, protect and enhance habitats, including woodlands, and urban greenspaces. As
well as providing accessible spaces for recreation and physical activity in support of mental
health through access to nature and tranquil environments. In terms of place making and urban
design the site enhances the identity and quality of the urban area demonstrating how
settlements grow by integrating green infrastructure into development while supporting the
creation of attractive, sustainable places for people to live and work. The application does not
support the planning concept of integration by aligning with policies in the National Planning
Framework (NPF 4). 
Page 73 of 154

Page 74

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 25/00794/FUL 
Name (of applicant): 
JGS Developments (Lenzie)
Site Address: Land At
Dullatur Road and King's Drive
Dullatur
Cumbernauld 
Development: Residential Development
(5no. Proposed Houses) and Green
Network Enhancement   
Page 74 of 154

Page 75

Reasons for Refusal:- 
1. Proposed enhancements aside, the development will result in the significant erosion of this section of the
Green Network as such cannot reasonably be stated to strengthen this section of a wider strategic Green
Network as a nature network. The application submission cannot therefore reasonably be held to concur
with the stated policy intent or provide a justification to depart from with Policy on Biodiversity. NPF 4 Policy
3 – Biodiversity 
2. Fragmenting or severing woodland habitats by building on part of the connecting green network cannot
reasonably be held to concur with the stated policy intent or provide a justification to depart from with NPF4
Policy 6 on Forestry, Woodland and Trees. 
3. The development will result in a significant reduction of an existing attractive open space forming a long-
established part of the Green Network used by residents and recreational users of this place. The proposal
therefore will result in significant conflict with the aims of the intended purpose of this policy by significantly
eroding the established and designated Green Network and cannot reasonably be held to concur with the
stated policy intent or provide a justification to depart from with Policy on Design, Quality and Place. As
such is not supported by Local Development Plan Policy EDQ 3 POLICY Quality of Development or NPF
Policy 14 Design, Quality and Place. 
4. The development will result in the reduction of green infrastructure resulting in a deficit of planned and
designed townscape at a location impacting on a component part of the designated green network. The
application submission cannot reasonably be held to concur with the stated policy intent or provide a
justification to depart from with NPF4 Policy 20 on Blue and Green Infrastructure. 
5. A significant reduction in the area or quality of the site, which is proposed to be offset or justified through
enhancement measures elsewhere within the site, raises questions about the equivalence, effectiveness,
and spatial relevance of the claimed improvements. Consequentially, sufficient justification has not been
given to the loss placemaking, health and well-being impact or continuation of policy integration. As such,
the application does not concur with North Lanarkshire Local Development Plan Policies on protecting
assets PROT A POLICY Natural Environment and Green Network Assets 
Background Papers: 
Consultation Responses: 
NLC Infrastructure & Transportation memorandum received 23rd October 2025 
NLC Greenspace (Arboriculture) memorandum received 8th October 2025
NLC New Supply letter received 22nd August 2025
Coal Mining Remediation Authority letter received 22nd August 2025  
NLC Education memorandum received 11th September 2025    
NLC Archaeology Service memorandum received 28th August 2025 
NLC Protective Services Memorandum Received 15th October 2025 
NLC Community Partnership Team memorandum received 11th September 2025 
Contact Information: 
Gordon Arthur at esplanning@northlan.gov.uk or 01236 632487 
Report Date: 18th November 2025  
Page 75 of 154

Page 76

APPLICATION NO. 25/00794/FUL 
REPORT 
1. Site Description 
1.1 The site which is currently an established area of amenity space (aprox.1 Ha in area) lies on the
boundary between Dullatur and Westerwood area of Cumbernauld characterised by an area of mature
landscaped transition and residential area either side of Dullutar Road. The site is bounded east and
west by dwellings, separated in part by mature boundary planting, and are predominantly two storey
detached and semi-detached dwellings. An area of mature woodland area lies to the south and is
coterminous with the site southern boundary. To the north lies an area characterised by mature trees
and formal landscaping before breaking to open countryside and then a golf course. An existing
pedestrian pathway connection runs along the front of the site Dullatur Road. The site is currently an
area of amenity open space which is maintained grass, tree planting and adjacent footpath links,
serving the current residents of the adjacent residential area. Site access is proposed by way of
Dullatur Road (direct access for 4 of the 5 plots with one plot being accessed from Kings Drive) which
is currently used to access the settlement of Dullatur and residential areas described above. In terms
of topography north to south the site rises from 141m to 148m over 149m. Taken at its mid-point the
site is relatively level falling from 146m to 145m towards Dullatur Road contributing to part of the design
of the established residential estate surrounding.
2. Proposed Development 
2.1 The planning application is for a residential development, and the applicant has submitted a layout
demonstrating 5 dwellings and detail of house types which as annotated on the plans are (type 1) -21/2
storey 4 bedroom detached and (type 2) 21/2 storey 4 bedroom detached both with integral garage with
sedum roof. Materials consist of Buff facing brick, zinc cladding with dark grey interlocking roof tiles.
Garden ground and in curtilage parking.  In addition, both house types have 2 further attic rooms and
a self contained one bedroom ‘elderly persons’ annex – so potentially 7 bedrooms in total 
3. Applicant’s Supporting Information 
3.1 Supporting information includes the following documents: 
▪ Design statement
▪ Planning Statement
▪ Tree Report (including hedges)
▪ Drainage strategy
▪ Environmental study (Phase 1)
▪ Landscape Report
▪ Preliminary Ecological Appraisal
▪ Access Report
4. Site History 
4.1 The site has been the subject of multiple applications for residential development listed below. All
developments on this site refused and dismissed appeal by the Scottish Government. The latter
decision was subject to a challenge at the Court of session and is summarised below.
Significant planning applications associated with this site include the following: 
• 09/00851/PPP Residential Development (Potential Formation of 19 Residential Plots) (In-
Principle) Site at North Muirhead Farm Dullatur Road refused (dismissed on appeal) 17th
December 2009. 
Page 76 of 154

Page 77

• 15/02136/FUL Erection of 11 Dwellings Sites East of King's Drive, Westerwood, Cumbernauld,
refused (dismissed on appeal) 23rd March 2016. 
• 17/00191/FUL Proposed Erection of 11 No. New Dwellings to Vacant Site, Sites East of King's
Drive, Westerwood, Cumbernauld, refused (dismissed on appeal) 22nd March 2017. 
• 19/00909/FUL: Construction of 9 Dwellinghouses site to the east and west of Kings Drive and
North of Dullutar (appeal dismissed 6th September 2021).
4.2 A decision notice was previously issued on the appeal PPA-320-2139 (19/00909/FUL). However, that
decision was subject to a court challenge and was subsequently quashed. The Reporter for the
Scottish Government thereafter was appointed to re-determine the case, inviting the council and then
other parties to provide comments on the Court of Session ruling, progress on the examination of the
North Lanarkshire Local Development Plan Modified Proposed Plan and information on Tree
Preservation Orders covering any part of the appeal site. 
4.3 A summary of the Reporters reasoning in his decision to dismiss the appeal PPA-320-2139-1
(19/00909/FUL) is as follows. 
‘I therefore conclude that, for the reasons set out above and while the proposed development broadly
accords with the relevant provisions of the development plan, refusing to grant planning permission is
still justified because of the protection to be afforded to the site as part of a Green Network/Green Belt
as confirmed by a recent reporter’s examination of the proposed local development plan.’ 
The North Lanarkshire Local Development Plan was adopted after the last appeal. 
5. Development Plan 
5.1 The proposal is assessed in terms of the National Planning Framework (NPF4) as well as under the
terms of the North Lanarkshire Local Development Plan which identifies the site principally as PROM
LOC4 POLICY Special Landscape Areas & Green Network Improvements and falling within the
General urban Area with a portion of the site in the Green Belt.         
6. Consultations 
6.1  The following comments were received from consultees: 
NLC Infrastructure & Transportation confirmed that they have no objection to the development
subject to condition on in curtilage parking condition. 
NLC Protective Services provided comment on the site investigation (by Land wise consultants)
which was peer reviewed. It is recommended that should members be minded to approve the
application, a condition on the outstanding queries from that review and proposed remediation should
be attached.
NLC New Supply advise that in this instance, where site capacity is indicated as 5 units, the first
preference is for the affordable housing requirement to be met by way of commuted sum payment.
The value of the commuted sum to be determined following joint appointment of the District Valuer
Service (DVS). The applicant has agreed in principle to this process and therefore a legal agreement
should be concluded prior to issuing the decision notice should members be minded to approve the
application. 
NLC Education comment that given the small number of housing units proposed in relation to this
site it is anticipated that any pupil product will be minimal. The schools in the local area will be in a
position to absorb any pupil product from this development within the existing school estate. Ther
Service will not request a Developer Contribution in relation to this application at this time.
NLC Community Partnership Team comment that due to the proximity of the development to Dullatur
Road, and there being no proposal or scope within the constraints of the site to provide the required
Page 77 of 154

Page 78

play space a financial contribution in lieu of onsite provision will be required and used to upgrade an
existing Council Play Area in the local area. This is currently calculated at £500 per house. Therefore,
for a development consisting of 5 detached dwellings a total developer’s contribution of £2,500 would
be required. 
NLC Green Space & Country Parks (arboriculture) advise that Tree removals shall be strictly limited
to those identified in the Arboriculture Impact Assessment (AIA) prepared by Julian A. Morris (dated
July 2025), as shown on the Tree Protection Plan (Appendix 6). No additional trees shall be removed
without the prior written approval of the Arboriculture Team.
A compensatory tree planting scheme shall be submitted as part of the final landscape plan and is
recommended as a planning condition covering species, after care, biodiversity value and girth is
attached to the decision notice should members be minded to approve.
Coal Mining Remediation Authority team considers that the content and conclusions of the Site
Investigation report are sufficient for the purposes of the planning system and meet the requirements
of the NPPF in demonstrating that the application site is, or can be made, safe and stable for the
proposed development. They therefore have no objection to the proposed development. However,
further and more detailed considerations of ground conditions and/or foundation design may be
required as part of any subsequent building regulations application. 
Should planning permission be granted for this proposal, they have requested the inclusion of
Informative Notes to address this.
NLC Archaeology The proposed development lies in an area associated with known archaeological
remains. To the immediate west an earlier archaeological evaluation identified pits and features while
to the north lies the Antoine Wall, there is a reasonable chance that the development area may have
associated with agriculture associated with the Roman occupation. In addition, the area has been
arable since the mid-18th century which raises the potential for previously unknown archaeological
remains as identified to the immediate west. 
While as noted the Antonine Wall World Heritage Site lies to the north there is no setting impact due
to the existing settlement which has made the monument less sensitive to further change. 
The proposed development has the potential to damage previously unknown archaeological remains,
however as the scope and scale of such putative remains are unknown there are insufficient grounds
to object to the development. Therefore, if the development does proceed, it is recommended that in
advance of construction an experienced and suitably qualified archaeological contractor undertake the
following programme of archaeological works by way of mitigation regarding the potential loss of the
site. A Planning condition to cover these works is recommended should members be minded to
approve the application. 
Westerwood Community Council object on basis of adverse impacts on road and pedestrian safety
(given the persistent and serious speeding issue on this section of road) and the development being
contrary to planning policy in particular the adverse impact on the green network 
7. Representations 
7.1 Following neighbour notification procedure 259 letters of representation were received (244)
objections, (14) supporting and 1 Neutral). Representation included from Councillor Masterton and Mr
Jamie Hepburn MSP. 
7.2 The principal concerns expressed in objections relate to proposed development, referring to conflicts
with planning policy, loss of green space, biodiversity concerns, and infrastructure issues. Comments
in support the proposal, focusing on potential biodiversity enhancements, local economic benefits and
design quality. 
Page 78 of 154

Page 79

7.3 The objections can be summarised as follows: 
The development does not comply with NPF4 or local development plan policies 
Multiple references within the objection comments to the development being contrary to specific
policies within the development plan in, particular: 
North Lanarkshire Local Development Plan (LDP) – Policies PROT A, PROM LOC4, EDQ1 and EDQ3
National Planning Framework 4 (NPF4) – Policies 3, 6, 13, 14, 20(a) and 22 
Key concerns: 
• Proposal contradicts the designation of the site as part of the Green Network
• Previous applications have been refused, including a ruling at the Cout of session. 
Comment: The policy position is discussed in section 8 of the report. 
Loss of Green Space & Amenity 
The site is described by residents as a valued public amenity used for walking, commuting, and
recreation. 
Objections principally relate to: 
• Fragmentation of the Green Network
• Loss of safe pedestrian routes, especially for children going to school
• Visual impact and loss of openness 
Comment: Loss of Green space and amenity is discussed in section 8 of the report. 
Biodiversity & Environmental Impact 
A significant number of objections include: 
• Destruction of habitats, mature trees, and wildlife corridors
• Lack of ecological surveys
• Threats to protected species (e.g., Lesser Butterfly Orchids, wild birds) 
Supporters argue the development could enhance biodiversity through planting and landscaping. 
Comment: Biodiversity & Environmental Impact is discussed in section 8 of the report. 
Road saftey 
• Local residents have expressed concerns about road safety - specifically relating to:
• New driveways directly onto Dullatur Road
• Increased traffic hazards and visibility issues 
Residents consider that a Transport Statement or Road Safety Audit should have been submitted. 
Comment: Following consultation NLC Infrastructure & Transportation had no objection to the layout
on Road safety grounds. A Transport Statement or Road Safety Audit was not deemed by them to be
necessary and so was not requested by them     
Page 79 of 154

Page 80

Inadequate infrastructure 
Representations were received in relation to inadequate drainage, NHS services, school capacity, and
public transport. 
Comment: Drainage detail is discussed in section 8 of the report. In considering NHS services it
should be noted that NHS Lanarkshire are participants in the Local Development Plan Process and
are therefore aware that unallocated sites will come forward against which they will consider their
resource for health provision. Education have confirmed that they have capacity within their estate to
accommodate this level of proposed unallocated residential development. In terms of public transport
the site lies within the general urban area where an additional 5 dwellings are unlikely to merit
additional provision over the existing public transport arrangements. 
Design & Character 
Objections on this subject related to: 
• Incongruous building design (e.g., zinc-clad dwellings)
• Scale and massing not in keeping with surrounding homes 
Comment: The building design is indicative of surrounding house types and therefore otherwise
acceptable. 
Legal & Procedural Concerns 
Comments were received advising that: 
• Community Councils were not informed
• Residents were not notified
• Approval would breach statutory duties under various Scottish Acts 
Comment: The application received a substantial number of objections indicating that the notification
process and press advert was successful. The Community Council confirmed that they were aware of
the application. It is not clear in what manner the assessment of a planning application has constituted
breach of statutory duties. 
Flooding and Drainage 
• Risk of increased surface water runoff and flooding due to development. 
Comment: Drainage is considered in section 8 of the report. 
Impact on Community Character 
• Fear that the development will alter the semi-rural character of Dullatur.
• Visual impact and over development. 
Comment: It is not considered that the development would significantly alter the character of Dullatur
which has a number of large contemporary residential developments within its townscape. Similarly,
while approval of the development would alter the nature of the site and would erode and undermine
the green network given the site dimensions and proposed layout this could not be considered
overdevelopment. 
Planning Process Transparency 
Requests for clearer communication and more inclusive consultation. 
Comment: The planning service is constrained the processes and procedures set by the legislation
which was followed for this scale of development. 
Page 80 of 154

Page 81

7.4  Supporting Comments 
Comments in support (14 in total) of the development were also received, as follows: 
• The site has low existing biodiversity
• Development offers a chance for biodiversity enhancement
• The proposal aligns with NPF4 goals for healthy, connected, and sustainable communities 
Environmental Improvement 
Supporters highlight the proposal’s potential to enhance the local green network, including tree
planting and biodiversity measures. 
Low-Density Development 
The plan for only five houses is seen as sympathetic to the existing character of the area, avoiding
overdevelopment. 
Design Quality 
Some comments praise the architectural design and layout, suggesting it complements the
surrounding landscape and built environment and that the design is high-quality, distinctive, and
sustainable. 
Community Benefit 
A few supporters mention that the development could bring modest economic and social benefits to
the area, including improved access and landscaping. 
Responsible Land Use 
There is support for the idea that the land is being used in a thoughtful and sustainable way, balancing
housing needs with environmental stewardship. 
Comment: These supporting comments are noted. 
8.       Planning Assessment 
8.1 Under the terms of Section 25 of the Town and Country Planning (Scotland) Act 1997, Planning    
Authorities are required that in determining planning application proposals, where regard is to be had
to the Development Plan, determination should be in accordance with this Plan unless material
considerations indicate otherwise. In this instance the proposal is assessed in terms of the National
Planning Framework (NPF4) as well as under the terms of the North Lanarkshire Local Development
Plan and any other material considerations.     
8.2 The National Planning Policies are intended to provide a policy direction when determining all
development requiring planning consent. National Planning Framework NPF4 is a component of the
Development Plan system and in accordance with Section 25 (1) of the Town and Country Planning
(Scotland) Act 1997 as amended and with the Local Development Plan forms part of the assessment
process. 
8.3 The considered National Planning Framework (NPF4) policies are as follows: 
NPF4 
Page 81 of 154

Page 82

8.4 Policy 3 – Biodiversity 
a) Development proposals will contribute to the enhancement of biodiversity, including where relevant,
restoring degraded habitats and building and strengthening nature networks and the connections
between them. Proposals should also integrate nature-based solutions, where possible.
b) Any potential adverse impacts, including cumulative impacts, of development proposals on
biodiversity, nature networks and the natural environment will be minimised through careful planning
and design. This will take into account the need to reverse biodiversity loss, safeguard the ecosystem
services that the natural environment provides, and build resilience by enhancing nature networks and
maximising the potential for restoration.
Policy Intent: To protect biodiversity, reverse biodiversity loss, deliver positive effects from
development and strengthen nature networks.
8.5 Proposed enhancements aside, the development will result in the significant erosion of this Green
Network as such cannot reasonably be stated to strengthen this section of a wider strategic Green
Network as a nature network. The application submission cannot therefore reasonably be held to
concur with the stated policy intent or provide a justification to depart from national Policy on
Biodiversity.
8.6 Policy 6 – Forestry, Woodland and Trees
a) Development proposals that enhance, expand and improve woodland and tree cover will be 
supported.
b) Development proposals will not be supported where they will result in:
i. Any loss of ancient woodlands, ancient and veteran trees, or adverse impact on their
ecological condition.
ii. Fragmenting or severing woodland habitats, unless appropriate mitigation measures are
identified and implemented in line with the mitigation hierarchy.
c) Development proposals involving woodland removal will only be supported where they will achieve   
significant and clearly defined additional public benefits in accordance with relevant Scottish
Government policy on woodland removal. Where woodland is removed, compensatory planting will
most likely be expected to be delivered.
Policy Intent: To protect and expand forests, woodland and trees. 
8.7 Fragmenting or severing woodland habitats by building on part of the connecting green network cannot
reasonably be held to concur with the stated policy intent or provide a justification to depart from
national Policy on Forestry, Woodland and Trees. 
8.8 Policy 14 – Design, Quality and Place (Liveable Places) 
a) Development proposals will be designed to improve the quality of an area whether in urban or rural
locations and regardless of scale.
b) Development proposals will be supported where they are consistent with the six qualities of
successful places:
• Healthy: Supporting the prioritisation of women’s safety and improving physical and
mental health.
• Pleasant: Supporting attractive natural and built spaces.
• Distinctive: Supporting attention to detail of local architectural styles and natural
landscapes to be interpreted, literally or creatively, into designs to reinforce identity.
• Sustainable: Supporting the efficient use of resources that will allow people to live, play,
work and stay in their area, ensuring climate resilience, and integrating nature positive,
biodiversity solutions.
Page 82 of 154

Page 83

Further details on delivering the six qualities of successful places are set out in Annex D of the policy
document.
c) Development proposals that are poorly designed, detrimental to the amenity of the 
surrounding area or inconsistent with the six qualities of successful places, will not be supported.
Policy intent – promote appropriate design within new development whist respecting the amenity of
the surrounding area.
8.9 This policy requires that development improves the quality of an area. It is considered that the
significant reduction of an existing attractive open space will be lost to the proposed development
resulting in a significant loss of long-established Green Network for residents and recreational users
of this place. The proposal therefore will result in significant conflict with the aims of the intended
purpose of this policy by significantly eroding the established and designated Green Network. The
application submission cannot reasonably be held to concur with the stated policy intent or provide a
justification to depart from National Policy on Design, Quality and Place. This is discussed in further
detail under Local Development Plan Policy EDQ 3 POLICY Quality of Development below. 
8.10 Policy 20 – Blue and Green Infrastructure
a) Development proposals that result in fragmentation or net loss of existing blue and green
infrastructure will only be supported where it can be demonstrated that the proposal would not
result in or exacerbate a deficit in blue or green infrastructure provision, and the overall integrity
of the network will be maintained. The planning authority’s Open Space Strategy should inform
this. 
b) Development proposals for or incorporating new or enhanced blue and/or green infrastructure will
be supported. Where appropriate, this will be an integral element of the design that responds to
local circumstances. Design will take account of existing provision, new requirements and network
connections (identified in relevant strategies such as the Open Space Strategies) to ensure the
proposed blue and/or green infrastructure is of an appropriate type(s), quantity, quality and
accessibility and is designed to be multi-functional and well-integrated into the overall proposals.
Policy Intent: - seeking to promote, enhance and preserve the elements of blue green infrastructure
that are present throughout both the urban and rural environments.
8.11 The development will result in the reduction of green infrastructure resulting in a deficit of planned and
designed townscape at a location impacting on a component part of the designated green network.
The application submission cannot reasonably be held to concur with the stated policy intent or provide
a justification to depart from national Policy on Blue and Green Infrastructure. 
North Lanarkshire Local Development Plan (NLLDP) 
8.12 PROM LOC4 POLICY Special Landscape Areas & Green Network Improvements
Any proposals affecting the Glasgow & the Clyde Valley Green Network in North Lanarkshire and other
natural areas and green spaces that contribute to the health and quality of life of local communities
will be required to satisfy the provisions of all EDQ and PROT Policies. Local level, small scale
improvements will be delivered through specific North Lanarkshire Partnership Local Development
Programme. Green Networks are a means of attracting people into their local natural environment by
improving community access, recreation opportunities, and environmental and ecological quality close
to and within communities. Green Networks, corridors and linkages are widely seen as a key
mechanism for reversing the effects of fragmentation on biodiversity. 
Page 83 of 154

Page 84

8.13 Integrated blue-green infrastructure – green and blue features of the natural and built environment that
are designed, integrated and managed to provide water management, access networks, habitat
enhancement and open space functions – is also important. Such infrastructure delivers economies
of environmental, economic and social multi-functionality unique to and within a single place. Green
features include parks, woodlands, trees, play spaces, allotments, community growing spaces,
outdoor sports facilities, churchyards and cemeteries, swales, hedges, verges, green roofs and
gardens. Blue features include rivers, lochs, wetlands, canals, ponds, porous paving and sustainable
urban drainage systems. Paths, cycleways and river corridors provide connections through and
between areas of green infrastructure. 
8.14 Within North Lanarkshire, opportunity maps have been created for each of the four Green Network
Priorities (Health and Wellbeing, Climate Change Adaption, Access to Greenspace, Habitat
Connectivity). From these strategically important areas that represent the greatest opportunity for
delivering each of the priorities was identified. 
PROT PROTECTING ASSETS 
8.15 PROT A POLICY Natural Environment and Green Network Assets 
North Lanarkshire Council will protect natural and resilient sustainable places by safeguarding natural
heritage assets. When considering future development affecting the natural environment and the
specific Green Network Assets identified in this Policy, the Council will seek guidance where
appropriate from NatureScot. NatureScot has produced a variety of policy and guidance documents
for aspects of the natural environment which the Council will utilise and will expect developers to
consider in preparing proposals. Site categories identified in this Policy are locations protected for their
importance for species or habitats, or other environmental value. 
8.16 Category A4 Urban Green Network 
Natural areas (including urban wildlife corridors, trees & woodlands, watercourses & wetlands and
flood plains), outdoor sports facilities and other green open spaces contributing to quality of life in local
communities 
8.17 The Council will maintain community wellbeing in residential areas by protecting the Urban Green
Network. Planning permission will only be granted for proposals potentially affecting the Urban Green
Network if it can be demonstrated to the Council’s satisfaction that there will be no adverse impact or
that any impacts can be mitigated in environmental terms. Policy EDQ3 will outline how new
development proposals may protect, enhance and manage existing Green Network infrastructure and,
in key locations, provide new Green Network infrastructure. 
8.18 In considering the purpose in protecting the Green Network it is worth clarifying what it is intended to
support. 
Environmental Enhancement 
• Connects natural, semi-natural, and man-made open spaces to support biodiversity.
• Protects and enhances habitats, including woodlands, and urban greenspaces.
• Helps mitigate climate change impacts by managing surface water, reducing urban heat, and
storing carbon.
Health and Wellbeing 
• Provides accessible spaces for recreation and physical activity.
• Supports mental health through access to nature and tranquil environments.
• Encourages active travel (walking, cycling) by linking paths and corridors. 
Placemaking and Urban Design 
• Enhances the identity and quality of urban areas.
• Influences how settlements grow by integrating green infrastructure into development.
Page 84 of 154

Page 85

• Supports the creation of attractive, sustainable places for people to live and work. 
Strategic Planning Integration 
• Forms part of national and regional development strategies.
• Aligns with policies in the National Planning Framework (NPF) and continues the work established
though Scottish Planning Policy (SPP).
• Used in local development plans (e.g. North Lanarkshire LDP) to guide land use and infrastructure
decisions. 
8.19 Comment: a partial reduction in the area or quality of the site, which is proposed to be offset or justified
through enhancement measures elsewhere within the site, raises questions about the equivalence,
effectiveness, and spatial relevance of the claimed improvements. Concurrently, sufficient
consideration in the application submission has not been given to placemaking, health and well-being
or policy integration. 
8.20 Category A5 (Protected species) 
Development that significantly affects a species protected by law will only be permitted where an
appraisal has demonstrated that the protected species would not be compromised; or any significant
adverse effects on the protected species are mitigated through planning conditions or use of planning
agreements to: facilitate protection of individual species members, reduce disturbance to a minimum
and provide appropriate alternative habitats to sustain at least the current levels of the species locally.
Not all locations important for species are identified. 
8.21 The applicants appointed ecologist confirmed that no evidence was found on Site to indicate the
presence of terrestrial protected species and no trees with Potential Roosting Features (PRFs) were
identified within the Site boundary. 
8.22 The application poses the proposition that you can enhance a green corridor by largely removing it.
While it is recognised that removal can be a form of enhancement depending on the context and intent.
In this application development on a designated green corridor is balanced against retaining the sites
ecological footprint. The applicant’s landscape architect proposes a series of landscape
enhancements encouraging and supporting biological diversity which he argues is possible in
strengthening a green network by linking together areas of protected woodland which surround the
site. The development footprint contains areas of hedgerow, grassland, and tree species vital for
ecological habitat. The design intends to retain and build upon these qualities of the site. 
8.23 And in doing so reinforce the local green network with 5 new homes development by retaining,
reconnecting and enhancing local woodland and grassland. The applicant’s landscape proposal has
ensured: 
• Significant existing trees are to be protected. 
• Local habitats are to be re-linked and enhanced. 
• Native plant species should be prioritised. 
• Green nature spaces, including community areas and woodland walks, are to be introduced. 
8.24 The design as proposed by the applicant is intended to reserve and reconnect the local green network,
strengthen the local biodiversity, and provide accessible green space to benefit the local community.
It is the case that the landowner could carry out biodiversity/landscaping improvements to the site
without the need for planning permission i.e. these works are not regarded as development. The
proposed improvements are not sufficient to offset the harm caused by building 5 houses on this
important green network site.   
Page 85 of 154

Page 86

8.25 It would be reasonable to argue that many of the trees are already protected, habitats linked and green
nature spaces including community areas linked, accessible and benefitting the local community
supported by the number and content of objections. This covering but not all the functions of the Green
Network discussed under the principle planning policy on this subject PROT A (Natural Environment
and Green Network Assets) by maintaining and improving the green corridor and outlining
opportunities to enhance suitable foraging and commuting habitat for wildlife. 
8.26 In considering construction on an area of green network the submitted preliminary ecological appraisal
has outlined several natural habitats which should be protected, maintained, and enhanced throughout
the development. 
8.27 The applicant’s appointed ecologist confirmed that no evidence was found on Site to indicate the
presence of terrestrial protected species and no trees with Potential Roosting Features (PRFs) were
identified within the Site boundary. 
8.28 In terms of significant connectivity, the submitted Preliminary Ecology Appraisal (PEA) commented
that Mainhead plantation is located 54m from the site in the southeast. Due to barriers to wildlife such
as walls and roads physical connectivity between the site and the woodland is reduced. There is also
functional connectivity between the site and the Mainhead plantation ancient woodland. The proposed
development and associated works therefore have the potential to impact the commuting and foraging
routes of wildlife through this site. This report recommends that connectivity between the sites is
maintained and improved where possible through the design process. The development should retain
open space which can continue to function as a wildlife corridor. 
8.29 The Site also contains three areas of neutral grassland of varying species composition. Neutral
grassland has the capacity to provided foraging and commuting habitat for a variety of species
including small mammals, birds, and insects. The grassland habitats to the southeastern extent ad
northwestern extent of the site are floristically diverse creating opportunities for a range of pollinators.
As such it is deemed that the habitat as moderate ecological value and should be retained and
enhanced where possible as part of the development. 
8.30 A series of biodiversity enhancements are also proposed relating to landscape planting, existing
woodland and trees, and existing grassland habitats. 
8.31 The PEA also advises that artificial lighting can often impact the foraging and commuting behaviour of
nocturnal mammals such as bats and badgers. Consequently, it is advised that lighting should be
directed to where it is needed and light spillage (whether direct/ or in-direct) should be avoided. It
should be noted that should the development be approved, the domestic lighting would be controlled
by the new residents. 
8.32 Whilst noting all of the above, returning to the initial proposition i.e. that you can somehow improve a
green network site by largely removing it by building houses on it the first point to make is that the
designation of a green corridor, while considering ecology and landscape, also supports elements of
placemaking and design and encourages health and well-being by retaining spaces for recreation and
physical activity. In a wider planning context, it supports a longer-term planning vision of strategic
planning integration principally to guide land use and infrastructure decisions. 
8.33 The proposition that the site requires reconnection appears to conflict not only with the policy
designation but also with the submitted landscape and ecology comments above. In that the site is
currently connected and functions as a component of the Green Network. While the application puts
forward that view that building on the Green Network will enhance it by introducing peripheral but
considered landscaping and by largely removing areas of it to be replaced by built form, on balance
this is a residential development largely resulting in the loss of established open space which currently
has an established and working function which not only includes ecology and landscape but also
supports elements of placemaking and design and encourages health and well-being by retaining
spaces for recreation and physical activity. In a wider planning context, it supports a longer-term
planning vision of strategic planning integration principally to guide land use and infrastructure
decisions. 
Page 86 of 154

Page 87

8.34 In conclusion a partial reduction in the area or quality of the site, which is proposed to be offset or
justified through enhancement measures elsewhere, raises questions about the equivalence,
effectiveness, and spatial relevance of the claimed improvements. 
8.35 The mitigation measures or actions proposed to reduce the negative impacts of development are being
offered by the applicant as Biodiversity Net Gain (BNG). That is to say, the development resulting in
part of a habitat being lost to modification is being offset as enhancements elsewhere (e.g. planting,
habitat creation) but within the developed site and thereby resulting in an overall gain in biodiversity.
However, the significant reduction in site area to built form will lead to a restricted landscape corridor,
a more fragmented landscape, closer human contact and thereby constraint on biodiversity,
notwithstanding the proposed biodiversity enhancements. While in some cases enhancements may
be aggregated elsewhere to support an overall improvement, it is considered that this is not what is
being proposed. Presumably as this approach can be spatially or functionally disconnected. On
balance the applicant is arguing the trade-off made between the loss of one asset (e.g. open space,
ecological value) and the gain of another (enhanced ecological value) with the loss of open space.
This when assessed results in no public benefit outweighing the impairment to the potential for
biodiversity. Therefore, the proposed mitigation for the loss of biodiversity is limited enhancement of a
developed space. It is not accepted that limited enhancement proposed can be balanced against the
existing spatial loss, while simultaneously aiming to improve conditions beyond the net gain baseline. 
8.36 The application therefore does not comply with Policies designed to protect and enhance the green
network. PROM LOC4 POLICY Special Landscape Areas & Green Network Improvements, PROT A
POLICY Natural Environment and Green Network Assets (Category A4 Urban Green Network). 
NPF 4 Policy 8 Green Belt and NLLDP Purpose of Place Policy PP4 Green Belt 
8.37 The application site in part lies within the designated Green Belt, and while the application is to
establish a residential development, the red line boundary of the site and current design excludes the
allocated green belt area from construction. The proposed development may therefore be considered
inconsequential by design by not significantly impacting on the intended of aims of Green Belt Policy
NPF 4 Policy 8 or NLLDP Purpose of Place Policy PP4 Green Belt.   
Environmental and Design Qualities EDQ 1-3
8.38 All developments require to be assessed against these 3 local development plan policies. However in
this instance EDQ2 is not relevant 
8.39 EDQ 1 POLICY Site Appraisal advises any proposed development will require to be appraised in
terms of the site and its surroundings to ensure it will integrate successfully into the local area and
avoid harm to neighbouring amenity. The matters to be addressed in the appraisal include but are not
limited to the listed criteria in the Local Development Plan.
8.40 Given the constraints of the site the design for residential development cannot achieve an acceptable
layout without significantly eroding this area of existing Green Network the application is overall is not
supported by Policy EDQ1. 
8.41 EDQ 3 POLICY Quality of Development advises development will only be permitted where high
standards of site planning and sustainable design are achieved. Planning Applications will need to
demonstrate that the proposed development takes account of the site appraisal carried out as a
requirement of Policies EDQ1 and, if appropriate, EDQ2, assets protected under Policy PROT, any
evaluation of design options, and achieves a high-quality development. 
Page 87 of 154

Page 88

8.42 The following observations under headings below are considered relevant. 
Considerations under policy EDQ 3 POLICY Quality of Development are measured against the
following: 
a. Providing a safe, pleasant, inclusive, convenient and welcoming development. If the
unavoidable and adverse impact on the green network and resulting loss of amenity were to be set to
aside it is considered that the development viewed in isolation could be assessed as meeting these
aims.  NLC Infrastructure and Transportation have provided comment on the access layout and design
and have no objection to this arrangement. 
b. Moving towards a low-carbon economy, addressing, resource efficiency, Mitigation of and
Adaptation for the effects of Climate Change energy and waste issues in order to create a
sustainable development with a low ecological footprint.
A preliminary ecological appraisal report was submitted which followed surveys based on standard
methodology as published by the Institute of Ecology and Environmental Management (IEEM), 2018.
The surveys aimed to assess the ecological value of the site and record any protected habitats or
species. The purpose of the assessments was to document the baseline ecological conditions of the
site. It is the report authors professional opinion the proposed development would have no adverse
impact on any protected species or habitats and that no further survey work is required.
Reports were submitted commenting on Green Network, landscape enhancements and quality on the
site and surrounding Land Use Character Area and biodiversity of plants and animals on the site.
In referring to EDQ 3 – these reports are discussed above in the context of policy PROT A POLICY
Natural Environment and Green Network Assets. 
In accordance with current building standards and in the interest of energy efficiency, the development
should be able to provide a variety of means to limit CO2 emissions in line with the current building
regulations.
c. Mitigating any likely air quality, noise, or pollution impacts particularly in or adjacent to Air
Quality or Noise Management Areas. In some circumstances, mitigation may not always be
possible, and avoidance may be required. The scale of the proposed development will not give rise to
any significant pollution impact requiring mitigation. That said, the applicant has submitted supporting
information on geo-environmental site conditions. As such, NLC Protective services following
consultation recommend that before the commencement of development, should members be minded
to approve the application, the outstanding queries should address. It is recommended that this should
be the subject of a planning condition in the event of members approving the application.
d. Ensuring that water body status is protected and, where possible, enhanced. Status includes
physical characteristics, so proposals such as culverting will only be considered where no other
practical option exists. Foul water should connect to the public sewer - alternatives to this will only be
permitted where no public system exists and the alternative does not pose an environmental risk.
Sustainable Urban Drainage Systems should be adopted within site design and appropriate details,
including during the construction phase, require to be submitted with any relevant planning application.
Buffer strips may be required in respect of the water environment between a development and each
watercourse.
Scottish Water is responsible under the terms of the Sewerage (Scotland) Act 1968, (as amended),
for provision of sewerage infrastructure for domestic sewerage, trade effluent and some categories of
surface water following agreement with the developer. This policy considers that foul water should
connect to the existing public sewer within the urban area. Alternatives to this will only be permitted
where no public system exists, and the alternative does not pose an environmental risk. In considering
Sustainable Urban Drainage Systems (SUDS), Policy EDQ1 outlines SUDS should be adopted within
site design and appropriate details require to be submitted with any planning application. A condition
on securing the detail and implementation of a Sustainable Urban Drainage Systems (SUDS) is
recommended should members be minded to approve the application. 
Page 88 of 154

Page 89

e. Adequate provision has been made for the development and maintenance of landscaped
areas and, and for linking to and enhancing open spaces and green networks. The application
fails to comply with section g of the policy given that it will result in the removal of an established
designed open space and green network link.
f. Existing features of Green Network or Historic Environmental interest or Resources,
protected under the terms of the Protect Assets Policies, and including features (e.g. traditional
stone buildings/structures) identified through the site appraisal required by Policy EDQ 1, will
be safeguarded or enhanced. (see PROM LOC4 POLICY Special Landscape Areas & Green
Network Improvements, PROT A POLICY Natural Environment and Green Network Assets (Category
A4 Urban Green Network) above. 
8.43 In respect to more technical assessment points, should members be minded to approve planning
permission, it must be accepted that, given the principle designation of the site as green network
remains in conflict with residential development and while appropriate design could be achieved in
terms of height, massing and materials could be achieved, this is largely at the loss of the designated
green network. The development proposal has therefore not demonstrated that it can meet the
adopted standards and is therefore contrary to Policy EDQ3 quality of development.
8.44 CI POLICY Contributions to Infrastructure advises North Lanarkshire Council will seek to secure
developer contributions for new developments that, individually or cumulatively, generate a
requirement for new or enhanced infrastructure or services, covering Affordable Housing in
Cumbernauld Housing Sub-Market Area.
Category Affordable Housing
For proposed residential developments in the Cumbernauld Housing Sub-Market Area (as shown on
Page 72 of the Policy Document) the Council seeks to secure 20% affordable housing provision in
continuation of adopted Council Policy on the advice of the Council’s Housing Strategy Service.
Justification is contained in the Affordable Housing Policy Background Report. Further Guidance is
contained in the Council’s Affordable Housing Guidance. The Council will consider the requirement for
the provision of affordable housing elsewhere on a case-by-case basis, where an identified need has
been demonstrated.
If minded to approve the application will be subject to a legal agreement for a commuted sum towards
affordable housing allocation. The level of commuted sum is currently with the Council’s new supply
team and District valuer to determine. 
9.          Other Material Considerations 
9.1 Planning History: The application has been subject to numerous refused applications and
subsequent appeals as set out in section 4 of this report. 
9.2 Supporting information (financial): the applicant has submitted supporting information advising the
following:
• The applicant commented that JGS Developments will be providing £4M of private investment
to realise this development. Financial benefits from this investment will impact on the local
economy within North Lanarkshire Council in the form of; salaries paid to those employed in
the development and materials supplied by local businesses together with tax revenues, an
Affordable Housing Contribution which directly relates to the impact of the development and
which will assist North Lanarkshire Council to deliver their programme of affordable housing.
• JGS Developments are a local business, all staff are resident within North Lanarkshire and
the company source construction materials principally from local suppliers. A positive
determination of this application will assist greatly in Castlecary Developments Limited (a
‘sister’ company of JGS Developments) to bring forward the development on an allocated
NLLDP housing site at Castlecary Road (North Lanarkshire Council Reference 0014/02) for
40 units.
Page 89 of 154

Page 90

Whilst noting these points these are not considered to be sufficient to set aside the harm that will arise
through the building of 5 houses on an important green network site 
10.        Conclusions 
10.1 The development will result in a significant reduction of the designated Green Network established to
connect natural, semi-natural, and man-made open spaces to support biodiversity, protect and
enhance habitats, including woodlands, and urban greenspaces. As well as providing accessible
spaces for recreation and physical activity in support of mental health through access to nature and
tranquil environments. In terms of place making and urban design the site enhances the identity and
quality of the urban area demonstrating how settlements grow by integrating green infrastructure into
development while supporting the creation of attractive, sustainable places for people to live and work.
Supports the planning concept of integration by aligning with policies in the National Planning
Framework (NPF 4). As such, residential development on this site is not supported by the aims of the
Development Plan specifically NPF 4 Policy 3 – Biodiversity, NPF4 Policy 6 on Forestry, Woodland
and Trees, Local Development Plan Policy EDQ 3 POLICY Quality of Development & NPF Policy 14
Design, Quality and Place, NPF4 Policy 20 on Blue and Green Infrastructure & North Lanarkshire
Local Development Plan Policies on protecting assets PROT A POLICY Natural Environment and
Green Network Assets. Accordingly, it is recommended that planning permission be refused. 
Page 90 of 154

Page 91

Application No:  
25/00819/AMD 
Proposed Development: 
Erection of Two Dwellinghouses: Amendment to Permission
24/00709/FUL 
Site Address: 
Land At Hawthorn Avenue
Crindledyke
Newmains 
Date Registered: 
4th September 2025 
Applicant:
NethanAccess
FAO Mr Drew Dingwall
209 Bonkle Road
Bonkle
Newmains
ML2 9AA 
Agent:
WB Properties Scotland Ltd.
Daldraco
3 Birniehill Road
Hareshaw
ML1 5GX 
Application Level:
Local Application 
Contrary to Development Plan:
Yes
Ward:   
20 Murdostoun 
Robert John McKendrick, Cameron McManus,
Louise Roarty, Nicky Shevlin
Representations:
0 letter(s) of representation received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
The principle of the development was approved by permission 24/00709/FUL and this
permission can still be implemented. However, the changes proposed by this application,
including the repositioning of one of the dwellings would reduce the amount of fill required due
to the current levels of the most easterly plot and is considered to be an acceptable change to
the approved permission. 
Page 91 of 154

Page 92

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 25/00819/AMD
Name (of applicant): NethanAccess
Site Address: 
Land at
Hawthorn Avenue
Crindledyke
Newmains 
Development: Erection of Two
Dwellinghouses: Amendment to
Permission 24/00709/FUL   
Page 92 of 154

Page 93

Proposed Conditions: 
1. That the development hereby permitted shall be carried out strictly in accordance with the approved
details submitted as part of the application and no change to those details shall be made without prior
written approval of the Planning Authority. 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That BEFORE any works of any description start on the application site, unless otherwise agreed in
writing with the Planning Authority, a comprehensive site investigation report shall be submitted to and
for the approval of the said Authority.  The investigation must be carried out in accordance with current
best practice advice, such as BS 10175 : 'The Investigation of Potentially Contaminated Sites' or CLR
11.  The report must include a site specific risk assessment of all relevant pollution linkages and a
conceptual site model.  Depending on the results of the investigation, a detailed Remediation Strategy
may be required. Information on the required format of the report and how it should be submitted to us
can be found online: 
https://www.northlanarkshire.gov.uk/planning-and-building/planning-applications/how-discharge-
contaminated-land-planning-conditions 
Reason: To ensure the site is free of contamination. 
3. That any remediation works identified by the site investigation required in terms of Condition 2, shall be
carried out to the satisfaction of the Planning Authority.  A validation report (signed by a chartered
Environmental Engineer) shall be submitted to the Planning Authority prior to the occupation of either
house confirming that any remediation works have been carried out in accordance with the terms of the
Remediation Strategy. 
Reason: To ensure the site is free of contamination. 
4. That BEFORE development commences, an up to date Ecological Survey report prepared by a suitably
qualified ecologist shall be submitted to and approved in writing by the planning authority.  Such report
shall include any proposals for mitigation which may be appropriate, and shall also include proposals
for a scheme of ecological enhancements within the development and adjoining land so as to offset the
impacts of the development.  In the event of development not commencing within 12 months of the date
of the survey, an updated such survey shall be undertaken and its findings submitted to the planning
authority for approval as above.  The approved mitigation and ecological enhancements shall thereafter
be implemented as approved in accordance with the timescale specified in the agreed report. 
Reason: In order to ensure that up to date ecological information is provided prior to development
commencing, and to ensure that the development includes appropriate ecological mitigation and
biodiversity enhancements consistent with the requirements of NPF4 policy 3. 
5. Notwithstanding condition 1 above, for the avoidance of doubt the details contained within landscaping
plan AL(0)21 Rev AB are hereby approved. To clarify this plan is considered to be equivalent to details
discharged under Condition 6 of permission 24/00709/FUL on 8 July 2025. The approved scheme of
landscaping shall thereafter be implemented in accordance with the approved timetable. 
Reason: To define the permission. 
6. For the avoidance of doubt the development hereby approved shall be implemented in accordance with
the Construction Method Statement (Revision A) submitted and approved under condition 7 of
permission 24/00709/FUL. 
Reason: In order to minimise the risks of damage to the environment during the construction of the
development, given its proximity to a watercourse and wildlife corridor.  
Page 93 of 154

Page 94

7. The houses hereby approved shall not be occupied until such time as the vehicular and pedestrian
access, parking and turning spaces have been completed to their finished standard and made available
for use. 
Reason: In order to ensure that the development has suitable access and parking. 
8. That BEFORE the development hereby permitted starts, full details of the facing materials to be used
on all external walls and roofs shall be submitted to, and approved in writing by the Planning Authority
and the development shall be implemented in accordance with the details approved under the terms of
this condition. 
Reason: In the interests of the visual amenity of the area. 
9. That BEFORE the development hereby permitted starts, full details of the design and location of all
fences and walls (including retaining walls) to be erected on the site shall be submitted to, and approved
in writing by the Planning Authority. 
Reason: In the interest of the amenity of the site and the surrounding area. 
Background Papers: 
Consultation Responses: 
Coal Mining Remediation Authority 25th September 2025 
Contact Information: 
Leigh Menzies at esplanning@northlan.gov.uk or 01236 632487 
Report Date: 
14 November 2025
Page 94 of 154

Page 95

APPLICATION NO. 25/00819/AMD 
REPORT 
1. Site Description 
1.1 The application relates to an area of undeveloped land at the end of Hawthorn Avenue, on the southern
edge of Newmains.  It borders the back gardens of houses on Bonkle Road to the north west, a small
parking area and further undeveloped land to the south west (with houses on Hawthorn Avenue and
a playing field a short distance beyond), and the steep-sided valley of the Auchter Water / Crindledyke
Burn to the east.  The site is roughly square in shape and extends to approximately 0.19ha.  It is
overgrown in long grass and rosebay willowherb with a few small trees and bushes.  The land falls
from its northern corner (adjacent to the parking area) down towards the watercourse to the east of
the site. 
2. Proposed Development 
2.1 The application seeks to amend a previous planning permission for two detached single storey houses
with associated garages, access and land engineering works. The house types retain a similar layout
to that initially approved, accommodating 3 bedrooms, the overall height of the proposed dwellings
would effectively be lower by approx. 0.5m. In addition, the dwelling to be located to the eastern edge
of the site is proposed to move approx. 5m closer to the northern boundary. 
2.2 It should be noted that the layout approved under 24/00709/FUL can still be implemented. The purpose
of this application would reduce the amount of underfill that would be required for the easterly plot. 
2.3 Within the curtilage each house would have a single garage, they are proposed to be built alongside
each other as a semi-detached pair.  The houses would still be accessed by a shared private drive
continuing from the car park at the end of Hawthorn Drive. One house would face north-west towards
the rear of houses on Bonkle Road, while the other would face south-west along Hawthorn Avenue.   
2.4 Due to the slope of the land some significant cut and fill is needed to create level ground for the
buildings, with the western house involving excavation of up to approximately 1m, and the eastern
house requiring land raising and underbuilding next to the valley, as well as two garden retaining walls
of up to 2m.  Details of precise materials and boundary treatments have not been specified at this
stage. The current application seeks to reduce the level of fill required at the east of the site. 
3. Applicant’s Supporting Information 
3.1 The application is an amendment to 24/00709/FUL and much of the required information was provided
and approved under that permission such as the access/parking, drainage strategy etc. This
application is limited to gaining approval for the modification to the house type and relocation of the
easterly dwelling approx. 5m further north. Proposed plans showing an updated block plan and
elevations in this regard have been provided. 
4. Site History 
4.1 An application for outline planning permission (02/01056/OUT) for residential development of a
substantially larger 1.5ha site along the western side of the Auchter Water burn, of which the current
application site forms a part, was called in by the Scottish Ministers and refused in 2004 on the grounds
that the site was within the Green Belt and a SINC. 
4.2 An application for two houses was submitted by the applicant in 2021 (reference 21/00545/FUL), this
was withdrawn due to lack of information required for validation.  An identical application
(23/00815/FUL) was then submitted in 2023.  Both of these applications were for a similar layout to
the present application but featured larger two-storey house types.  The second application was
refused by the Planning Committee in June 2024 due to it being contrary to Green Belt and natural
environment policies. 
Page 95 of 154

Page 96

4.3 Subsequent to the above applications planning permission was granted by the Committee on 12
September 2024 for the erection of two single storey 3 bedroom houses. 
4.4 The current application is very similar to the application which was previously granted in 2024, having
the same site boundary and a near-identical layout i.e. 3 bedroom bungalows.  The differences are: 
• The orientation of the eastern plot remains the same however it is proposed to locate this 5m
further north within the site;
• It is understood that it is still intended that the dwellings are to be occupied by two households
which both include disabled children
• In addition, the internal layout of the properties would remain the same (location of bedrooms and
living spaces) however there would be some changes to the type of openings associated to the
areas. 
5. Development Plan 
5.1 Relevant development plan polices are detailed below: 
National Planning Framework 4 – policies:
3 (Biodiversity)
4 (Natural places)
8 (Green belts)
14 (Design, quality and place)
16 (Quality homes) 
North Lanarkshire Local Development Plan 2022 – policies:
PP4 (Green Belt – Purpose of Place)
AD4 (Green Belt – Amount of Development)
PROM LOC3 (Housing Development Sites)
PROT A (Natural Environment and Green Network Assets)
EDQ1 to EDQ3 (Environmental and Design Qualities) 
5.2 All of the policies above are relevant to the assessment of the principle of such a development in the
Greenbelt. However, in this instance, it is considered that these were assessed as part of the previous
application which was granted due to the personal circumstances of the applicant. The information
provided indicates that circumstances have not changed and the matters for assessment as part of
this application are restricted to details relating to the location of easterly dwelling within the site,
reduction in upfill and a change to the house type. 
5.3 In addition to the above it is appreciated that this is a scale of development that would not normally be
put to the Planning Committee for determination. However, despite the previous approval of the
dwellinghouses the principle of the development remains contrary to the development plan and under
delegated powers this requires to be presented to committee for determination. 
6.       Consultations  
6.1 Limited consultations were undertaken given the relatively minor changes that were being sought
approval for, along with the short period of time since the original permission was approved. 
6.2 Due to the proposed change to the location of the easterly plot (although considered minor) the Coal
Authority was reconsulted. Coal Mining Remediation Authority has no objection to the application.   
6.3 It was also considered appropriated to reconsult NLC Protective Services, who have confirmed that it
has no objection subject to a condition requiring that comprehensive site investigation for potential
contaminated land be submitted and approved prior to development commencing. This process is
underway. 
6.4 NLC’s Archaeology service provider (commenting on the previous application) had no objection to the
application but noted that the site has potential to contain medieval remains on national significance,
and therefore a condition requiring archaeological investigations prior to any commencement of
Page 96 of 154

Page 97

development was placed as a condition on the previous approval. Under the previous permission, it
should be noted that the required investigations have been undertaken and the previous condition
discharged. 
6.5 NLC Infrastructure & Transportation when commenting on the previous application with an identical
road layout they had no objection subject to adequate pedestrian access and to car parking and turning
for bin lorries within the adjacent car park remaining unimpeded. This element of the proposal has
remained unchanged from the previous permission. 
7.       Representations 
7.1 Following the standard neighbour notification and press advert no objections to the planning
application were received. 
8.       Planning Assessment 
Development Plan Policy 
8.1 Under section 25 of the Town and Country Planning (Scotland) Act 1997, applications for planning
permission are required to be determined in accordance with the policies of the development plan
unless material considerations indicate otherwise.  The development plan comprises National
Planning Framework 4 (NPF4) and the North Lanarkshire Local Development Plan 2022 (the LDP),
with the former taking precedence in the event of any conflict between policies. 
8.2 The application site is within the designated Green Belt in the North Lanarkshire Local Plan, however
the principle of the dwellinghouses was approved by committee on 12 September 2024 and is not
being assessed. This application is only addressing the proposed alterations in relation to the layout
approved under 24/00709/FUL, specifically regarding location of the easterly property and minimal
changes to the house types. 
Design and Amenity 
8.3 The proposed properties would remain single storey and include 3 bedrooms. The changes from the
previously approved plans include: 
a) The easterly house location would move 5m north from the approved position. This equates to a
reduction of distance from the northern boundary from 14.2m to 9.1m. In addition, this is approx.
a reduction from 29m to 25m to the closest residential properties to the north.
b) It is proposed that the internal layout of the properties would remain similar to that approved,
however the revised drawings propose changes to the size of the openings, however those
openings would remain in the same approximate locations
c) The overall height of the revised dwellings would be reduced by approximately 0.5m in height from
that previously approved. The plans submitted show that the ground levels and cutting out of the
westerly property would be as previously approved. In terms of the easterly dwelling the amount
of land raising required would be reduced in volume. 
8.4 These changes are relatively minor in nature however it was not considered that a relocation of the
easterly dwelling 5m to the north could be treated as a non-material variation i.e. the change was
significant enough to require assessment by way of a planning application given the house was moving
closer to existing residential properties and thereby giving residents an opportunity to comment on the
change (no representations were received). 
8.5 The proposed houses would be positioned behind existing bungalows on Bonkle Road, but they would
not be readily visible from that street.  Rather, the houses would effectively become an eastward
extension of Hawthorn Avenue, with its existing two-storey terraced houses.  There is a mixture of
house types and sizes in the surrounding area and the design and layout of the proposal is not
considered to conflict with the amenity or character of the adjoining residential area.   
Page 97 of 154

Page 98

Technical Consultations 
8.6 The proposed drainage arrangements (a mains sewer connection for foul sewage and SUDS for
surface water) are appropriate, and the Coal Mining Remediation Authority is content with the
conclusion of the coal mining risk assessment that there are no shallow mineworkings under the site. 
NLC Protective Services has indicated that a site investigation for potential contaminated land would
be required, however that would normally be a matter capable of being addressed by a condition, with
information in this regard having already been submitted by the applicant for consideration. Overall,
the technical aspects of the proposal remain acceptable. 
9.       Conclusions 
9.1 It is considered that the changes to the previous approval are relatively minor in nature and do not
warrant a reassessment of the previous policy position. The previous layout can still be undertaken
however the applicant is looking to reduce the underbuilding required for the easterly dwelling and it
is not considered that the changes will cause detriment to the surrounding area.  Accordingly, it is
recommended that permission be granted for this amended layout. 
Page 98 of 154

Page 99

Application No:  
25/00901/FUL
Proposed Development: 
Change of Use of an Existing Caravan Showroom and Shop to a
Storage Warehouse Comprising Multiple Internal Storage Units
and Change of Use of Caravan Storage Yard to allow for the
Siting of Shipping Storage Containers. 
Site Address: 
Duncan Caravan & Camping
186 Wishaw Road
Waterloo
Wishaw
ML2 8ES 
Date Registered: 
27th August 2025 
Applicant:
Duncan Caravans Ltd
186 Wishaw Road
Waterloo
Wishaw
ML2 8ES 
Agent:
ET Planning
200 Dukes Ride
Crowthorne
RG45 6DS 
Application Level:
Local Application 
Contrary to Development Plan:
No
Ward:   
21 Wishaw 
Bob Burgess, Fiona Fotheringham, Jim Hume,
Frank McKay,
Representations:
7 letters of representation and a petition
with 5 signatures received.   
Recommendation: Approve Subject to Conditions 
Reasoned Justification: 
It is considered that the proposal is not so different from the current/previous use and
complies with the relevant policies of the development plan and can be accommodated on
the site without adverse impact on amenity and road safety. 
Page 99 of 154

Page 100

Reproduced by permission of
the Ordnance Survey on
behalf of HMSO. © Crown
Copyright and database right
2009.  All rights reserved.
Ordnance Survey Licence
number 100023396.
Planning Application: 25/00901/FUL 
Name (of applicant): 
Duncan Caravans Ltd
Site Address: 
Duncan Caravan & Camping
186 Wishaw Road
Waterloo
Wishaw
ML2 8ES 
Development: Change of Use of an
Existing Caravan Showroom and Shop to
a Storage Warehouse Comprising
Multiple Internal Storage Units and
Change of Use of Caravan Storage Yard 
to allow for the Siting of Shipping
Storage Containers    
Page 100 of 154

Page 101

Proposed Conditions:- 
1. That the development hereby permitted shall be carried out strictly in accordance with the approved
details submitted as part of the application and no change to those details shall be made without prior
written approval of the Planning Authority. 
Reason: To clarify the drawings on which this approval of permission is founded. 
2. That prior to the shipping containers being located on site, a scheme of landscaping and planting and
agreed timescale of works shall be provided for the written approval of the Planning Authority. This
should include the type, number and variety of species that would be proposed.
For the avoidance of doubt this is specifically for the existing fenced area around the rear perimeter yard
area of the site which borders the west, south and east of the site where the shipping containers would
be located. 
Reason: To enable the Planning Authority to consider these aspects in detail. 
3. That all works included in the scheme of landscaping and planting, approved under the terms of
Condition 2 above, shall be completed in accordance with submission of an agreed timescale and
approved timetable of works  to be agreed in writing with the Planning Authority, and any trees, shrubs,
or areas of grass which die, are removed, damaged, or become diseased, within two years of the
operation of the shipping container storage area of the development hereby permitted, shall be replaced
within the following year with others of a similar size and species. 
Reason: In the interests of the environmental amenity of the area. 
4. That BEFORE any works of any description start on the application site, unless otherwise agreed in
writing with the Planning Authority, a comprehensive site investigation report shall be submitted to and
for the approval of the said Authority.  The investigation must be carried out in accordance with current
best practice advice, such as BS 10175 : 'The Investigation of Potentially Contaminated Sites' or CLR
11.  The report must include a site specific risk assessment of all relevant pollution linkages and a
conceptual site model.  Depending on the results of the investigation, a detailed Remediation Strategy
may be required. Information on the required format of the report and how it should be submitted to us
can be found online: https://www.northlanarkshire.gov.uk/planning-and-building/planning-
applications/how-discharge-contaminated-land-planning-conditions 
Reason: In regards to the issues highlighted by the submitted GEO Investigate Coal Mining Risk
Assessment Report dated 5th June 2025. 
5. That any remediation works identified by the site investigation required in terms of Condition 4;, shall be
carried out to the satisfaction of the Planning Authority.  A certificate (signed by a chartered
Environmental Engineer) shall be submitted to the Planning Authority confirming that any remediation
works have been carried out in accordance with the terms of the Remediation Strategy. 
Reason: To ensure that the site is free of contamination in the interests of the amenity and wellbeing of
future residents. 
6. That the opening hours of the premises hereby granted planning permission shall be limited to between
8am and 8pm on Monday to Sunday. 
Reason: To retain effective planning control. 
Page 101 of 154

Page 102

7. That within 12 weeks of the approval being received or as otherwise agreed with the Planning Authority
before the development commences full details of the design and location of all fences and walls to be
erected on the site shall be submitted to, and approved in writing by the Planning Authority. For the
avoidance of doubt this should include specific details regarding the alteration to the existing northern
boundary wall/fence facing onto Wishaw Road which will require to be reduced to a height not exceeding
1 metre. 
Reason: To allow the Planning Authority to consider these aspects in detail and the consideration of
road safety.
8. Prior to the commencement of the development the agreed alterations to the existing northern boundary
wall/fence facing onto Wishaw Road which will see the reduction of this feature to a height not exceeding
1 metre shall be implemented and thereafter maintained. 
Reason: in the interests of road safety 
Background Papers: 
Consultation Responses: 
NLC Infrastructure and Transportation 29th September 2025
Coal Mining Remediation Authority 20th October 2025
NLC Protective Services  1st October 2025 
Contact Information:
Stewart MacCallum at esplanning@northlan.gov.uk or 01236 632487
Report Date:
19th November 2025  
Page 102 of 154

Page 103

APPLICATION NO. 25/00901/FUL
REPORT
1. Site Description 
1.1 The application site is located at Duncan Caravan and Camping, 186 Wishaw Road, Waterloo. This
site has been a long-established caravan display and showroom sales site and consists of two main
buildings with a larger rear yard/compound display area for the caravans, although there is also a
smaller display area at the front of the site. This is a historical lone commercial site amongst
predominantly residential properties and is accessed off the A721 Wishaw Road to the north. There
are two elements to the site, to the north are existing buildings which are showrooms/workspaces
relating to the sale and maintenance of caravans. This part of the site is bordered to the north, east
and west by residential properties. The southern area of the site is an open area of hardstanding which
is used for the storage of caravans, which is bounded to the south, south west and east by an open
field, with residential properties in close proximity to both the north, east and north west. However, at
the rear yard/compound area of the site it is bordered to the west, east and south by open fields. The
site is generally flat at the front though there is a mild gradient from north to south from the start of the
rear yard area towards where it borders open fields.
2. Proposed Development 
2.1 Planning permission is sought for the change of use of an existing caravan showroom and shop to a
storage warehouse comprising multiple internal storage units and change of use of caravan
storage/display yard area to allow for siting of shipping storage containers, Class 6 (Storage or
Distribution).
2.2 It should be noted that the intention is to retain one of the existing buildings to continue as a caravan
showroom/shop with a smaller caravan display area in front of this so the existing business would still
operate but at a significantly reduced operational scale to what it currently had been.
2.3 There would be a combined total of 113 shipping containers potentially on site (although this would
not be the initial amount on site). The applicant has indicated that the site would be gradually
developed as the business/demand grows. This consists of two types of sizes of shipping container,
the (40 feet) larger containers which measure 12.15 metres by 2.43 metres and reach a height of 2,59
metres. There would be 17 of these. There is then the smaller (20 feet) containers which measure
6.05 metre by 2.43metre and reach a height of 2.59 metres. There would be 96 of these. These would
be arranged in three rows within the rear compound area of the site.
2.4 In addition to the above, one of the existing site buildings would be altered internally to provide multiple
internal storage units and this would be on both the ground and upper floor levels. There are no
significant external alterations proposed to this building. Internally this would provide 46 ground floor
storage units with a further 54 on the first floor. These would be a mixture of storage space floor sizes
to cater for customer storage needs.
3. Applicant's Supporting Information 
3.1 The applicant submitted the following supporting information:
• Architectural Drawings
• Design and Access Statement
• Coal Mining Risk Assessment
• Supporting Statement/Details of Operation of the Business
• Road Sightline Drawings 
Page 103 of 154

Page 104

4.    Site History 
4.1 The site had an application to extend the rear yard area for a caravan display area (08/00157/FUL)
which was approved on 31st July 2008. There was also an application for an advertisement
(01/00922/ADV) approved on 26th September 2001 and erection of a canopy (01/00760/FUL)
approved on 17th September 2001. However, there is no other significant planning history on the site.  
5.  Development Plan
5.1 Section 25 of the Town and Country Planning (Scotland) Act 1997 states that a planning application
should be assessed against the relevant development plan policies unless material considerations
indicate otherwise.
5.2 The Development Plan consists of the North Lanarkshire Local Development Plan and the National
Planning Framework 4 (NPF4). NPF4 was adopted by the Scottish Parliament in February 2023 and
prevails over any policies in the Local Development Plan that are incompatible with its aims and
objectives.   
National Planning Framework 4 - NPF4 
5.3 NPF4 policy 2 Climate Mitigation and Adaptation looks for development proposals to be sited to
minimise lifecycle greenhouse gas emissions as far as possible, designed to adapt to current and
future risks of climate change development proposals to retrofit measures to existing developments
that reduce emissions or support adaptation to climate change will be supported.
5.4 NPF4 policy 9 Brownfield, Vacant and Derelict Land and Empty Buildings seeks to ensure that
development proposals that will result in the sustainable reuse of brownfield land including vacant and
derelict land and buildings, whether permanent or temporary will be supported. When land is known
or suspected to be unstable or contaminated, development proposals will demonstrate that land is or
can be made safe and suitable for the proposed new use. In this case it is a consideration due to being
located in a designated High-Risk Coal Area. Development proposals for the reuse of existing buildings
will be supported taking into account their suitability for conversion to other uses.
5.5 NPF4 Policy 12 Zero Waste requires to ensure development proposals will seek to reduce, reuse or
recycle materials. Development proposals will be supported where they reuse existing buildings and
infrastructure. In this case reusing an existing site and one of the buildings would be considered to
comply with this policy
5.6  NPF4 policy 13 Sustainable Transport sets out to encourage, promote and facilitate developments
that prioritise walking, wheeling, cycling and public transport for everyday travel and reduce the need
to travel unsustainably.
5.7 NPF4 policy 14 Design, Quality and Place seeks to ensure that developments are of a good design
that are not detrimental to the amenity of surrounding area and are consistent with the 6 qualities of
successful places - Healthy, Pleasant, Connected, Distinctive, Sustainable and Adaptable.
5.8 NPF4 policy 26 Business and Industry sets out to encourage, promote and facilitate business and
industry use and to enable alternative ways of working such as home working, live-work units and
micro-businesses.  
Page 104 of 154

Page 105

North Lanarkshire Local Development Plan 
5.9 The following policies are relevant within the North Lanarkshire Local Development Plan (NLLDP):
PP3 - General Urban Area 
AD 3 – Amount of Development
EDQ 1 - Site Appraisal
EDQ 2 – Specific Features for Consideration
EDQ 3- Quality of Development
5.10 PP3 – General Urban Area Under North Lanarkshire Local Development Plan the site is identified as
General Urban Area policy PP3. The council seeks to maintain and improve the level of amenity
appropriate to the local context and by encouraging development that is in keeping with their
residential character and encouraging diversity in more mixed-use areas. The maintenance of the
existing mix of other urban uses, or introduction of a limited range of ancillary uses and activities out
with Classes 8&9 of an appropriate scale within recognisably mixed-use areas can be appropriate to
maintain and support the operation of the General Urban Area. This requires a business plan or
statement justifying that the development is ancillary development designed to serve the area in which
it is located and that it has been assessed using the Town Centres First Sequential Approach. This
also requires as a statement on the mix of uses, scale and nature of existing development in the
General Urban Area, a statement on if it is an intensification of an existing use, its impact on the
attractiveness of the General Urban Area, evidence there is a specific locational need for the proposal,
evidence that the proposal will result in significant economic benefit and its impact on travel patterns
and accessibility by sustainable modes of transport. 
5.11 AD3 – Amount of Development This policy states that applications for new development will be
assessed for their implications related to the amount of development proposed. The need for an
assessment depends on the combination of type (use class) scale and location of development.
5.12 Environmental and Design Quality Policies EDQ1-3 These policies look for proposed
developments to create a successful place or enhance existing places by integrating successfully into
the local area and avoiding harm to neighbouring amenity. To do this a range of criteria is listed within
these policies which include amongst other things aspects of design, massing, topography and
aspects to protect the existing urban area and its specific characteristics, assets and attributes. They
consider hazardous zones, utilities infrastructure and management areas and look to promote
biodiversity and the environment whilst meeting the challenges of the climate change via suitable and
safe access for all users to promote sustainable public travel and other considerations.
6. Consultations
6.1  The following consultation responses have been received in respect of the application.
6.2 NLC Infrastructure and Transportation have reviewed information submitted to support the
application and have indicated that they do not object to the proposal. However, despite being a long-
established site with an existing access, they have raised concern about the existing sites front
boundary wall/fence facing onto Wishaw Road. It is requested that the application should be
conditioned should it be approved that details of suitable alterations would be sought to alter the height
of the existing wall/fence at the front of the site to show a reduction in height to enable adequate
visibility along Wishaw Road. 
6.3  NLC Protective Services have no objections to the proposal. They have requested a Site
Investigation/or detailed report that addresses potential gas mine issues, is to be submitted for review
and to be conditioned as part of any approval.
Page 105 of 154

Page 106

6.4 The Coal Mining Remediation Authority has reviewed a Coal Mining Risk Assessment submitted
for the application site and have confirmed that they have no objection to the development and have
not requested any planning conditions. However, they have requested that an informative note is
added to any planning permission to advise the applicant that consideration is given to any potential
mine gas and something which they should be aware of.
7.  Representations
7.1  During the public consultation period (neighbour notification and press advertisement) for this
application a total of 7 letters of representations and a petition with 5 signatories were received.
7.2 In summary, the objections to this application raise the following matters:   
• Current state of the application site, site maintenance and disrepair to the existing side
boundary wall.
• The visual impact of the containers/outlook from nearby properties.
• Potential late night site activity/potential impact of this on residential amenity and site security. 
• Impact of lighting on residential amenity.
• Increased volume of traffic/Larger Vehicles to Site/ Increased larger vehicles as a result of
bringing or removal of the shipping containers to the site and potential impact upon local
parking.
• The development is potentially likely to lead to future development into the Green Belt which
borders the site.
8. Planning Assessment 
8.1  Under Section 25 of Town and Country Planning (Scotland) Act 1997 requires that planning decisions
must be made in accordance with the Development Plan unless material considerations indicate
otherwise. The assessment will therefore identify the development plan policies relevant to the
proposal, will make an assessment against these policies and come to a conclusion on which decision
(grant or refuse) would accord with them. It will then look at other material considerations to establish
if there are any that would suggest a decision different from the one reached in relation to the
development plan. National Planning Framework 4 (NPF4), and the North Lanarkshire Local
Development Plan (LDP) make up the development plan. 
National Planning Framework 4
8.2 The National Planning Framework 4 (NPF4) a long-term plan for Scotland that sets out where
development and infrastructure is needed. NPF4 sets out policies in relation to creating a sustainable
place, a liveable place and a productive place. 
8.3 With regard to NPF4 policy 2, whilst this applies to all development proposals given the scale and
nature of the application these are of limited relevance albeit the development will have very limited
physical change to the site in regard to new structures or significant building works.
8.4 NPF Brownfield, Vacant and Derelict Land and Empty Buildings Policy 9 states that development
proposals that will result in the sustainable reuse of brownfield land including vacant and derelict land
and buildings, whether permanent or temporary will be supported. When land is known or suspected
to be unstable or contaminated, development proposals will demonstrate that land is or can be made
safe and suitable for the proposed new use. Development proposals for the reuse of existing buildings
will be supported taking into account their suitability for conversion to other uses. In this case, there is
a potential mine gas issue that can be dealt with by planning condition requiring the submission of a
site investigation for consideration by the NLC Protective Services.  The proposed use is considered
to have many similarities with the historic use of the site and buildings and the reuse if the land and
building for the proposed storage use is considered to gain the support of this policy.
Page 106 of 154

Page 107

8.5 NPF4 Zero Waste Policy 12 requires to ensure development proposals will seek to reduce, reuse or
recycle materials. Development proposals will be supported where they reuse existing buildings and
infrastructure. In this case the application seeks the reuse of an existing site and one of the existing
buildings, therefore it is considered that the proposal complies with this policy.
8.6 NPF4 Sustainable Transport Policy 13 seeks sets out to encourage, promote and facilitate
developments that prioritise walking, wheeling, cycling and public transport for everyday travel and
reduce the need to travel unsustainably. The proposal supporting information indicates it has local staff
and also envisages a local client base which would reduce travelling out with the local area. Therefore,
it is considered that the proposal complies with this policy.
8.7  NPF4 Policy 14 Design, Quality and Place requires proposals to be designed to improve the quality of
an area whether in an urban or rural locations and regardless of scale. Proposals will be supported if
the development is consistent with the six qualities of successful places namely Healthy, Pleasant,
Connected, Distinctive, Sustainable and Adaptable. The site is currently used for commercial
purposes, and it is considered that the proposed use would have minimal additional detrimental impact
with conditions proposed to mitigate impacts. Therefore, it is considered that the proposal complies
with this policy. 
North Lanarkshire Local Development Plan
8.8 Under North Lanarkshire Local Development Plan the site is identified as General Urban Area policy
PP3. The council seeks to maintain and improve the level of amenity appropriate to the local context
and by encouraging development that is in keeping with their residential character and encouraging
diversity in more mixed-use areas. The maintenance of the existing mix of other urban uses, or
introduction of a limited range of ancillary uses and activities out with Classes 8&9 of an appropriate
scale within recognisably mixed-use areas can be appropriate to maintain and support the operation
of the General Urban Area. In this instance, the site has been in commercial use for some considerable
time, and this is considered a comparative use in regard to general storage/caravan storage. There
are conditions to ensure that the development will cause little or no additional impact to the amenity of
the surrounding residential area. There is nothing to suggest it would create any detrimental impact
and conditions such as the landscaping to the rear of the site and alterations to the front boundary wall
would be considered features which would actually provide an improvement to the site.
8.9 The proposal requires to be assessed against policies EDQ 1(Site Appraisal), EDQ 2 (Specific
Features for Consideration) and EDQ 3 (Quality of Development
8.10 Policy EDQ 1 (Site Appraisal) sets out that development will only be permitted where high standards
of site planning and sustainable design are achieved. The proposal is using the current external
storage area and using this to site shipping containers instead of caravans however this would also
provide planting at the existing rear fencing for screening. Alterations are sought for the existing front
boundary wall which would see improved sightlines at this site. Adequate parking and turning is
provided within the site. Whilst much of the yard area is not readily prominent from directly in front of
the site(looking southwards from Wishaw Road), it is quite visible from the main road to the west/south
west and the east of the site and also from residential properties bordering to both the west and east
of this. The change from caravans to shipping containers is visually going to be different and provide
potentially a more industrial feel to the site which may be visually detrimental to the character of the
area. It is therefore proposed that a landscaping condition would be imposed in regards to planting in
this area and for details to be submitted of suitable planting scheme which would help to soften the
appearance of the site and provide an element of screening. 
Page 107 of 154

Page 108

8.11 Policy EDQ 2 (Specific Features for Consideration) has consideration in regards to areas subject to
hazards (Hazardous Zones) which in this case is ground instability (coal mining) though in this instance
it relates specifically to potential mine gas being located within an area identified as High Risk in the
historic coal zoning of the area. It should be noted that the Coal Authority have no objections, or
request of any planning conditions. However, they have requested an advisory note with any
permission granted in regard to ensuring the applicant considers potential mine gas on the site. NLC
Protective Services have advised that conditions relating to site investigation/or similar detailed gas
report (specifically relating to potential mine gas) should be attached to any permission.
8.12 Policy EDQ 3 looks to create areas which provide a sustainable, safe, secure and convenient access
to and from the development that makes it easy to move around, and is attractive to pedestrians,
cyclists and people with disabilities. Any development would need to integrate well with public
transport, green networks and wider links. The assessment of (and where necessary) the mitigation
of pollution impacts is also included within policy EDQ 3. In relation to policy EDQ 3 it is considered
that the nature, density of the storage containers and storage building use are acceptable and will
integrate successfully into the site and wider area. Due to the nature of the use as storage and the
sites previous use, it is considered that the containers and storage unit are not likely to affect the
amenity of the residential dwellings to the north, west and east of the site in regard to privacy,
overshadowing or indeed any detrimental noise or lighting concerns. Landscaping measures for the
yard perimeter of the site to help improve the visual appearance of the site are all covered by planning
condition.
8.13 With regards to Transportation aspects of policy EDQ 3 NLC Infrastructure and Transportation has no
objection to the proposal subject to visibility requirements being met and this will be conditioned. This
is in regards to improving the existing site entrance by seeking a reduction/alteration to the existing
wall/fence which borders Waterloo Road.
8.14 Policy EDQ 3 also includes the requirement for the assessment of and (where necessary) the
mitigation of noise or pollution impacts caused either by the development or within the development
site. Information was provided in regard to ground contamination was subject as part of the Coal Mining
Risk Assessment. NLC Protective Services have advised that conditions relating to site investigation/or
similar detailed gas report (specifically relating to potential mine gas) should be attached to any
permission. The Coal Authority whilst having no objections and not seeking any planning conditions
have however requested an advisory note be attached to any permission to ensure the applicant gives
consideration to any potential mine gas.  A condition is also intended covering operational hours to
between the hours of 8am to 8pm
8.15 Taking into account the above assessment, it is considered that the proposed development would be
consistent with Policies EDQ 1, EDQ 2 and EDQ 3.
8.16 A summary of the objections and our response thereon are detailed below: 
Comment: Current state of the application site, site maintenance and disrepair to the existing side
boundary wall.
Response: Any dispute over repair of a shared boundary wall would be a civil matter to resolve. The
current maintenance of the site is not a matter for this planning permission, however the wider visual
impact of the proposed development would be addressed through conditions relating to screening and
details of changes to the front boundary wall. However, it would be agreed that there is enough of a
change that would merit a suitable planting condition to minimise this impact.
Comment: Late night activity/potential noise impact upon residential amenity and site security.
Response: Site security would be up to the applicant, and this is already an existing operating
commercial site. There are existing metal palisade fences in place around the rear perimeter of the
Page 108 of 154

Page 109

site and there are also gates at the start of the yard area controlling entry to this area in-between the
two existing buildings where the access is taken to get to the rear yard area. In regard to late night
activity, it is indicated that the site would operate general daytime hours of 8am-8pm, which would not
be unreasonable operational hours, in regards to residential amenity. It should be noted that there is
currently no restriction in operating hours of the current use. 
Comment: Impact of lighting on residential amenity.
Response: No new/additional lighting is proposed at the site. NLC Protective Services were consulted
and are satisfied that there is no illumination concerns to raise and the applicant has indicated that
there is no new lighting intended.
Comment: Increased volume of traffic/larger vehicles to site/ increased larger vehicles taking away or
bringing containers to the site and impact upon local parking.
Response: In the first instance, the setting up of the site (delivery of containers) is not something that
can be addressed through the planning legislation due to the limited nature of this undertaking.
Planning legislation looks to any longer-term impacts that may occur and to assess these. The longer-
term issues regarding parking and volume of traffic have been assessed by NLC Infrastructure and
Transportation who have indicated that they have no objection.
Comment: The development is potentially likely to lead to future development into the Green Belt
which borders the site
Response: This proposal does not include any land outwith the site which is zoned in the Local
Development Plan as Green Belt. Any future application which involved expanding outwith the existing
curtilage of the site would be assessed against relevant Green Belt policy of the Local Development
Plan and also relevant NPF4 policies which are generally more restrictive of what type of development
may be permitted within Green Belt identified land. Any future application would be considered on their
own merits should these be submitted for assessment.
8.17 It is considered that the concerns raised by the objectors, whilst important, do not represent material
considerations that are so significant that would warrant refusal in this case.
8.18 In view of the above, it is considered that the proposal complies with the relevant policies of NPF4 and
complies with policies PP3, AD3, EDQ 1, EDQ 2 and EDQ 3 of the North Lanarkshire Local
Development Plan.
9.      Conclusions
9.1 The proposed change of use of the existing site from caravan display/sales/storage centre to internal
storage units and container storage yard is considered to be an acceptable use in regards of the
General Urban Area policy and the relevant policies of NPF4 and would not have a detrimental impact
on the amenity and character of the site or surrounding residential properties and the surrounding
countryside area. It is therefore recommended that planning permission be granted subject to the
conditions set out in this report.   
Page 109 of 154

Page 110

Page 110 of 154

Page 111

North Lanarkshire Council Report
Planning Committee
Does this report require to be approved? ☒ Yes   ☐ No
Ref     Date 04/12/25
Development Plan Scheme & Participation Statement 2025 Update  
From Pamela Humphries, Chief Officer (Place)
E-mail laingg@northlan.gov.uk Telephone Gordon Laing,
07970018874
1. Background
1.1 The current North Lanarkshire Local Development Plan (NLLDP) was Adopted in July
2022. The NLLDP sets out where development should and should not happen by
guiding the future use of land at a local level. It is also a key consideration in the
decision-making on planning applications.  
Executive Summary
The purpose of this report is to seek Committee approval of the Development Plan Scheme
& Participation Statement (DPS) 2025 update. The DPS outlines the Council’s programme
for preparing and reviewing the new North Lanarkshire Local Development Plan 2
(NLLDP2) and when, how and with whom consultation will take place.
Recommendations
It is recommended that the Committee:
1) Agrees the Development Plan Scheme and Participation Statement 2025
2) Notes the consultation undertaken and progress to date in the preparation of the
new North Lanarkshire Local Development Plan 2.
The Plan for North Lanarkshire
Priority Enhance participation, capacity, and empowerment across our communities
Ambition
statement
(7) Enhance collaborative working to maximise support and ensure all our
children and young people are included, supported, and safe
(10) Engage with children, young people, parents, carers, and families to
help all children and young people reach their full potential
(19) Improve engagement with communities and develop their capacity to
help themselves
(20) Improve the involvement of communities in the decisions, and development of
services and supports, that affect them
Programme
of Work All Programmes of Work
Item 3
Page 111 of 154

Page 112

1.2 Changes to the planning system in Scotland, led by the passing of the Planning
(Scotland) Act 2019 which sets out the future structure of the modernised planning
system, included changes to the arrangements for the preparation of development
plans. Subsequent secondary legislation The Town and Country Planning
(Development Planning) (Scotland) Regulations 2023 and Local Development
Planning Guidance came into force in May 2023.   
1.3 The DPS (including Participation Statement) is an important communication tool which
outlines the Council’s programme for preparing and reviewing the next North
Lanarkshire Local Development Plan (NLLDP2) and when, how and with whom
consultation will take place. The Council has a statutory duty to prepare and publish a
DPS annually.   
1.4 The DPS sets out a timetable which anticipates that NLLDP2 will be on track for
Adoption in advance of the Regulations and Guidance expectation of May 2028. 
2. Report 
2.1 Following the commencement of the Regulations and publication of Guidance in May
2023, the DPS was revised in line with these requirements and the current DPS was
approved by the council in September 2023. This also signalled the start of the new
process for NLLDP2. The Regulations and Guidance were used to help produce an
engagement strategy that is inclusive of all stakeholders and ensures that we are
engaging in the most effective way. 
2.2 As the council is required to update this document annually, an updated Development
Plan Scheme & Participation Statement for 2025 has been prepared. 
2.3 The DPS includes: 
• proposed timetabling, including timings for various key stages of NLLDP2
preparation, to be specified by the proposed year and financial quarter. Key stages
to be covered are: publication of the Evidence Report; publication of the Proposed
Plan; submission of the Proposed Plan to the Scottish Ministers; and expected
adoption of NLLDP2. 
• details of what is involved in each stage; and 
• a Participation Statement, outlining when consultation is likely to take place, with
whom and its likely form, including the steps to be taken to involve the public. 
2.4 Updated timescales 
The initial stage in preparing NLLDP2 involves compiling and submitting an Evidence
Report to the Scottish Government for review, known as a Gate Check. We continue
to monitor the outcomes of other authorities’ submissions, many of which have not
passed Gate Check, and will assess any implications for our own timeline. 
2.5 Following a review of these outcomes and identification of additional evidence and
consultation needs, it is proposed to revise the submission date for the Council’s
Evidence Report from January-March 2025 to April 2026. This extension will support
a more robust evidence base, incorporate the Local Housing and Transport
Strategies, and ensure meaningful stakeholder engagement. In addition, we are
awaiting some key evidence from consultancy, and the additional time allocated will
allow for this to be included. As a result, the overall timeline for the preparation and
adoption of NLLDP2 has also shifted by one quarter - from Quarter 4 of 2027 to
Quarter 1 of 2028 (April–June 2028). 
Page 112 of 154

Page 113

2.6 Review of progress
The updated DPS includes an appendix summarising consultation to date, including:
• Updates to elected members;
• Broad consultation on national planning policy topics;
• Targeted meetings with infrastructure providers and key agencies;
• Joint engagement with SLC;
• A Place Survey using the Place Standard Toolkit;
• Public drop-in sessions;
• Engagement with Access Panel, Voice of Experience groups and Youth
Parliament;
• Local Place Plan follow-up sessions;
• A site assessment workshop with key stakeholders;
• A widely distributed newsletter and social media promotion 
2.7 Next Stages
Remaining consultation activities include a schools conference and themed
stakeholder meetings to strengthen evidence gathering and support consensus on
the Evidence Report content. 
2.8 It is proposed that the Evidence Report be submitted for Gate Check following
approval at Full Council meeting in April 2026. To maintain momentum in preparing
NLLDP2, a Call for Ideas (formerly “call for sites”) will commence in early 2026 and
continue throughout the Gate Check process. Concurrently, work will progress to
finalise key supporting strategies and continue stakeholder engagement in
preparation for the Proposed Plan. 
2.9 Following Committee approval and adoption of the updated 2025 Development Plan
Scheme & Participation Statement, the document will be submitted to the Scottish
Ministers, published online, and made available in all North Lanarkshire public
libraries. 
3. Measures of success 
3.1  An effective engagement strategy which is inclusive of all our stakeholders, raising
awareness of and opportunity to contribute to the Local Development Plan among
stakeholders, key groups and the public at large. 
3.2  Implementation of a statutory function, as required by the Planning (Scotland) Act
2019.     
4. Supporting documentation 
4.1 Appendix 1 – Development Plan Scheme & Participation Statement 2025 
Pamela Humphries
Chief Officer (Place) 
Page 113 of 154

Page 114

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
The appropriate assessments will be carried out alongside preparation of the new
LDP, as noted within the DPS timescales. 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☒
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi?
Page 114 of 154

Page 115

Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☐ 
Page 115 of 154

Page 116

Appendix 1 
North Lanarkshire Local Development Plan 2:
Development Plan Scheme and Participation Statement 2025 
Enterprise & Communities
Page 116 of 154

Page 117

1   
Contents
Section1: Development Plan Scheme .................................................................................................................................................................. 2
1 What is a Development Plan Scheme (DPS)? ........................................................................................................................................... 2
2 The Statutory Development Plan for North Lanarkshire ............................................................................................................................ 2
3 Existing Local Development Plan .............................................................................................................................................................. 3
4 New Local Development Plan & Changes ................................................................................................................................................. 3
5 North Lanarkshire Local Development Plan 2 ........................................................................................................................................... 4
6 Timetable changes .................................................................................................................................................................................... 8
Section 2: Participation Statement ....................................................................................................................................................................... 9
1 What is a Participation Statement? ........................................................................................................................................................... 9
2 Our consultation aims ............................................................................................................................................................................... 9
3 Who can participate? .............................................................................................................................................................................. 10
4 When and how will we participate with you? ........................................................................................................................................... 10
5 How would you prefer to be contacted and involved? .................................................................................................................................. 17
6 Mediation .................................................................................................................................................................................................... 18
7 Contact and future participation ................................................................................................................................................................... 18
Glossary ............................................................................................................................................................................................................ 19
Appendix 1 - Progress to date (December 2025) ............................................................................................................................................... 21
Plan Preparation ............................................................................................................................................................................................ 21 
Page 117 of 154

Page 118

2   
Section1: Development Plan Scheme 
1 What is a Development Plan Scheme (DPS)? 
A Development Plan Scheme (DPS) is an important
communication tool which sets out the programme for
the preparation of our next Plan - North Lanarkshire
Local Development Plan 2 (NLLDP2) – and lets
stakeholders know when and how they can get involved
in the plan and keep informed of progress. This is
reviewed and updated annually and is available to view
on the council’s website. The second part of this
document also sets out a Participation Statement,
outlining how, when and with whom the council intends
to engage and consult on NLLDP2. 
2 The Statutory Development Plan for North Lanarkshire 
The Development Plan sets out where development
should and should not happen by guiding the future
use of land at a local, regional and national level.
These plans are a key consideration in the decision-
making on planning applications. 
Development planning in Scotland is undergoing significant change.
Previously, the development plan consisted of the Strategic
Development Plan (Clydeplan Strategic Development Plan) and the
Local (Development) Plan (North Lanarkshire Local Plan 2012) as
well as a suite of Supplementary Planning Guidance notes.
Changes introduced by the Planning (Scotland) Act 2019 statutory
Development Plan now consists of the National Planning
Framework (NPF4) and the Local Development Plan (NLLDP) as
demonstrated in figure 1.
Figure 1. Statutory Development Plan/Related Plans (Local Development
Planning Guidance, The Scottish Government)
Page 118 of 154

Page 119

3   
3 Existing Local Development Plan 
The council adopted the North Lanarkshire Local Development
Plan (NLLDP) in July 2022, replacing the North Lanarkshire Local
Plan 2012. It contains a spatial strategy, proposals map, action
programme for identified developments and schedule of the local
authority’s land interests affected by Plan policies or proposals. It
focuses on specific proposals for the period of 10 years from
adoption. 
NLLDP is integrated with Council and Partner statutory plans and
strategies affecting the development of land. 
The plan also identifies Supplementary Guidance (SG) to
complement existing policy within NLLDP and provide further
guidance on specific topic matters. Planning and Noise SG, 
Affordable Housing SG and Frontiers of the Roman Empire
(Antonine Wall) World Heritage Site SG have been adopted by the
Council and are available online. Education Contributions SG is
currently being prepared by the council. 
4 New Local Development Plan & Changes 
The new development planning system has introduced a new
process for the preparation of LDPs. The Local Development
Planning Guidance 2023 outlines 3 key parts to the Local
Development Plan process (also shown in figure 2 from the
guidance) – 
Evidence Gathering of data and information to inform the plan
followed by a Gate Check by the Scottish Government,
Plan preparation including production of a Proposed Plan and its
Examination, followed by;
Delivery including subsequent adoption of the plan and a Delivery
Programme as well as ongoing monitoring. 
Figure 2. LDP Process – Overview (Fig.4 of Local Development Planning
Guidance, Scottish Government) 
In addition, preparation of Local Place Plans, Strategic
Environmental Assessment and other Appraisals/Assessments are
also important statutory elements of an LDP. 
The requirement for the preparation of strategic development plans
(SDPs) is removed and instead introduces the requirement for
planning authorities, working alone, or in partnership with two or more
planning authorities to form strategic partnerships, to prepare and
adopt a Regional Spatial Strategy. A planning authority must adopt a
Regional Spatial Strategy as soon as practicable after this part of the
Act comes into force and the Government has the power to direct
planning authorities to prepare and adopt such strategies. 
Regional Spatial Strategies will inform the NPF and Local
Development Plans. The NPF and Local Development Plans are to
be prepared at least every 10 years rather than every 5 years.
Page 119 of 154

Page 120

4   
A further significant change is the introduction of the right for
communities to come together and prepare Local Place Plans
(LPPs). Before preparing a Local Development Plan, a Planning
Authority must invite local communities in their district to prepare
LPPs, stating the date by which they must be prepared and details of
the assistance available for local communities to prepare LPPs. In
preparing its LDP the planning authority must have regard to LPPs. 
Other changes introduced by the Act includes requirements for
Development Plans for the carrying out of Play Sufficiency
Assessments and preparation of Open Space Strategies to inform
the LDP. 
5 North Lanarkshire Local Development Plan 2 
Following adoption of the current NLLDP in 2022, preparation is
now underway for NLLDP2. The table below (Table 1: NLLDP2
Indicative Timetable) outlines the proposed key stages alongside
estimated timeframes for completion of each stage and what is
required at each stage. It should be noted that the Gate Check and
Examination process and time to complete each of these are
outwith the council’s control. Annual DPS updates will reflect any
impact of these stages as they are completed.
The stages outlined in Table 1 are those which are identified in the
Scottish Government’s Local Development Planning Guidance. 
Technical Reports & Impact Assessments 
As part of the Evidence Report and its preparation, a wide range of
topics will be covered. This will include preparing a number of
technical reports to support the evidence base. This list of reports
may include, but is not limited to:
SEA Scoping Report
Housing
Infrastructure & Services Capacity
Transport Appraisal
Play Sufficiency Assessment 
Additional assessments will also be undertaken to support the
NLLDP2 preparation. These will help to inform and be informed by
the plan whilst under preparation and includes:
Strategic Environmental Assessment;
Equalities Impact Assessment;
Public Sector Equality Duty Assessment;
Fairer Scotland Duty Assessment; and
Habitats Regulations Appraisal 
Table 1 below includes details of estimated timings for the SEA and
additional assessments.
In preparing the LDP the council will also have regard to the
following plans and strategies:
- the national waste management plan
- the national marine plan
- any regional marine plan
- any river basin management plan
- any flood risk management plan
- any local flood risk management plan
- any regional transport strategy
- any local transport strategy
- any local housing strategy
- any open space strategy;
Page 120 of 154

Page 121

5   
Table 1: NLLDP2 Indicative Timetable (stages as outlined in Local Development Planning Guidance) 
Stage 1 - Evidence Gathering Timetable* SEA Other Assessments
Early Preparation
Development Plan Scheme & Participation Statement preparation and
adoption
Invitation to local communities to prepare LPPs
Start Quarter 2
2023 (July-Sept
2023)  
Evidence Report
Gather and collate appropriate evidence
Seek views of key agencies, children and young people,
and the public at large in the preparation of the Evidence Report.
Prepare Evidence Report
Approval of Evidence Report by full Council
Submission to the Scottish Ministers
Quarter 1 2023
(April- June 2023) –
Quarter 1 2026
(April 2026)
Scoping workshop.
Collect Environmental
Baseline. 
Prepare Scoping
Report. 
Submit Scoping Report
to Consultation
Authorities. 
Gate Check
Scottish Ministers appoint person to assess Evidence Report. Gate
Check of Evidence Report
Requests for further information and / or hearings (where
appropriate)
If evidence considered sufficient, appointed person informs planning
authority and Scottish Ministers
If evidence not sufficient, appointed person prepares “assessment
report”
Quarter 1 2026
(April-June 2026) 
Page 121 of 154

Page 122

6   
Stage 2 - Plan Preparation Timetable* SEA Other Assessments
Informing the Proposed Plan
Develop spatial strategy incorporating an infrastructure first approach
and considering NPF4 spatial principles 
Early engagement (call for ideas)
Site assessment
Start Quarter 1
2025 (April-June
2025) 
Start Quarter 4 
2025 (Jan-March
2026)
Identification and
assessment of
reasonable
alternatives 
Site assessment
Undertake
transport appraisal
Proposed Plan (Drafting)
Preparation of Proposed Plan, including Spatial Strategy
Delivery Programme:
- Consult with key agencies, the Scottish Ministers and anyone named
in the Programme during preparation
- Approved by full Council before publication
Proposed Plan approved by full Council.
Start Quarter 1
2026 (April-June
2026)
Assess any local
policies. 
Prepare
Environmental Report.
Prepare required
Assessments (as
outlined above in
section 5)
Publication/Consultation
Publish Proposed Plan, Evidence Report and Delivery Programme
together. 
Consultation:
- 12 weeks statutory minimum
- consult with key agencies and Scottish Ministers
- consult with Central Scotland Green Network Partnership (where
appropriate)
Quarter 1 2027
(April-June 2027)
Consultation on
Environmental Report
alongside Proposed
Plan.
Publish transport
appraisal and
required
Assessments.
Page 122 of 154

Page 123

7   
Modification
Modification of Proposed Plan (where appropriate) and preparation of
Modification Report
TBC if required 
Quarter 2 2027
(July-Sept 2027) 
Revise Environmental
Report to reflect
modifications and
undertake further
consultation, if
required.
Revisit and update
assessments as
appropriate.
Examination
Publish Proposed Plan and Modification Report (where appropriate)
Preparation of summary of Unresolved Issues (Schedule 3)
Where unresolved representations, appointment of person to
examine plan
Examination of Proposed Plan
Preparation of Examination Report and Recommendations
Modification of LDP as necessary
Start Quarter 3
2027
(Oct-Dec 2027) 
Amend Environmental
Report as required
following Examination.
Submit amended
Environmental Report
to the Scottish
Ministers. 
Page 123 of 154

Page 124

8   
Stage 3 – Delivery Timetable* SEA Other assessments
Adoption/Publication
Adoption of LDP by planning authority.
Publish LDP
Publish Report on Modifications or ‘Recommended Modifications
Statement’ (where applicable)
Adopt and publish Delivery Programme within 3 months of LDP being
constituted
Quarter 1 2028
(April-June
2028) –
Quarter 2 2028
(July - Sept 2028)
Prepare Post Adoption
Statement. 
Publish Post Adoption
Statement 
Monitoring & Delivery
LDP kept under review – monitor changes in characteristics, monitor
impact of policies / proposals.
Delivery Programme: - kept under review and updated at least every 2
years, or if the Scottish Ministers direct the authority to update it  
Housing Land Audit: - prepared annually by each planning authority
Quarter 2 2028
(July - Sept 2028) –
ongoing
Monitoring 
* References to a “quarter” are to a quarter of the financial year (April- March) and means a period of three months ending at the end of June (“quarter 1”), at
the end of September (“quarter 2”), at the end of December (“quarter 3”) or at the end of March (“quarter 4”) (The Town and Country Planning (Development
Planning) (Scotland) Regulations 2023) 
6 Timetable changes 
The Local (Development Planning) (Scotland) Regulations 2023
and the Local Development Planning Guidance 2023 outline
expectations for the preparation of the North Lanarkshire Local
Development Plan 2 (NLLDP2). 
We continue to monitor the outcomes of other authorities’
submissions. Following a review of these outcomes and
identification of additional evidence and consultation needs, the
submission date for the Council’s 
Evidence Report has moved from Quarter 2 of 2025 (July–September  2025)
to Quarter 1 of 2026 (April–June 2026). This extension will support a more
robust evidence base and ensure meaningful stakeholder engagement. In
addition, we are awaiting some key evidence from consultancy, and the
additional time allocated will allow for this to be included. As a result, the
overall timeline for the preparation and adoption of NLLDP2 has also shifted
by one quarter—from Quarter 4 of 2027 to Quarter 1 of 2028 (April–June
2028). 
Page 124 of 154

Page 125

9   
Section 2: Participation Statement
1 What is a Participation Statement? 
Stakeholders, including the wider public, have an important role in
shaping their Plan and their views are an important aspect in the
preparation of the plan. This section will outline when consultation
is likely to take place, who we propose to engage with and how we
propose to undertake it.
2 Our consultation aims 
The North Lanarkshire Framework for Engagement reflects a
commitment to working with communities across a range of
engagement opportunities and approaches.
The updated National Standards for Community Engagement
reflect the developing policy and legislative context for community
empowerment in Scotland. This includes 7 Standards, outlined in
figure 3 as Inclusion; Support; Planning; Working Together;
Methods; Communication; and Impact. These standards can be
used for community engagement to develop a working relationship
between the council and community organisations to achieve
positive outcomes.
Our overall approach to engagement will be shaped by these
standards and we will strive to ensure that we work with all of our
stakeholders to engage in the most suitable way.
This Participation Statement identifies the key stages where we will
undertake consultation in the preparation of NLLDP2. At times there
may also be other significant consultations underway by other 
organisations or other departments within the council. We will aim
to take account of these where possible to reduce consultation
fatigue where the targeted stakeholders would result in a similar
audience to that of the NLLDP2 consultations. 
Figure 3. National Standards for Community Engagement – 7 Standards
Page 125 of 154

Page 126

10 
3 Who can participate? 
The council will aim to involve a wide range of stakeholders in the
preparation of NLLDP2. Figure 4 identifies a range of stakeholders
who we will aim to engage with and involve in the preparation of the
plan. This is not exhaustive and we are keen to involve anyone who
has in interest in the plan. 
4 When and how will we participate with you? 
In Table 2 below we have identified the key consultation stages,
when we will expect them to happen and who we wish to target. We
have also indicated possible engagement methods, however, we
would like you to engage with us by telling us how you would prefer
to be consulted by the council so that we can engage with you in
the most effective way. They greyed-out text indicate those stages
already undertaken. 
As the council progresses through the first stage of NLLDP2
preparation the consultation methods for publicity and engagement
will develop and evolve depending on the nature of topics which
require to be explored and the preferred methods and resources
available for doing so. 
Figure 4: LDP stakeholders         
Communities/
councils
Key groups
e.g. Children
& Young
People
National/
regional
agencies &
other
organisations
Kay Agencies LDP
Stakeholders
NLC internal
services
Businesses/
Investors
Infrastructure/
Service 
Land
Managers &
Developers
Page 126 of 154

Page 127

11 
Table 2: Participation Table 
LDP Stage 1 – Evidence Gathering  
Key Consultation Stage (When)
(For specific timescales see Table 1:
NLLDP2 Indicative Timetable above)
Consultation Type & Purpose Consultees & proposed engagement
methods (How and with whom)
Preparing Development Plan Scheme &
Participation Statement
Inform and involve all stakeholders by
seeking and having regard to views on the
Participation Statement.
Inform stakeholders that preparation for
NLLDP2 is underway. 
Consideration of online platforms/hub
for holding information in an easily
accessible location for engagement
and participation throughout all stages
of NLLDP2.
• Consult stakeholders via council
social media platforms, council
website and email contacts on how to
involve them.
• Consultation with community boards.
• Issue request for those interested to
register for updates via GovDelivery.
• Provide dedicated webpage for
consultation responses and further
LDP information.
• Finalise Development Plan Scheme &
Participation Statement and publish
online and hard copies in libraries.
Inviting communities to prepare a Local
Place Plan
Inform/involve community bodies by inviting
to prepare a local place plan as a means of
involvement in the preparation of the Local
Development Plan.
• Issue invitations to prepare Local
Place Plans to community councils
and Community Bodies.
• Provide information and contacts for
communities on a dedicated Local
Place Plans webpage and publicise.
Preparing the evidence report Undertake early and proactive engagement
with stakeholders as outlined in figure 4 (LDP
Stakeholders) on page 9 to ensure
collaborative and transparent evidence
gathering in the preparation of the Evidence
Report. 
Seek views of key agencies, key groups
(such as children and young people, older
people, Gypsies and Travellers, disabled
persons/groups) and the public at large in
the preparation of the Evidence Report.
• Consult and update stakeholders via
council social media platforms,
council website and email contacts.
• Internal council services and elected
member engagement to gather
views/issues and available data and
information via workshops and
meetings.
• Engage with key agencies,
organisations, and other stakeholders
to agree and gather key evidence.
Possible meetings and/or workshops  Page 127 of 154

Page 128

12   
online or in-person. Grouping of
particular topics may be helpful.
• Engage with community boards,
community councils and community
groups to include their views about
local places and assist aligning LDP/
LPP engagement. Use of online
platforms and meetings/workshops
as required alongside possible use of
toolkits (such as Place Standard) to
assist conversations and record
information about local areas when
consulting.
• Target specific key groups (including
children and young people, older
people, Gypsies and Travellers,
disabled persons/groups) to update
on process and preparation of new
LDP and capture views. Use of online
platforms and meetings/workshops
where required alongside possible use
of toolkits (such as Place Standard) to
assist conversations and record
information about local areas when
consulting.
• Joint working with South Lanarkshire
Council to reduce consultation fatigue
and share resources/best practice. 
• Use social media and council’s
website to publicise and update on
progress and  provide key documents/
information. Email to those registered
for updates via GovDelivery.
Page 128 of 154

Page 129

13   
Gate Check  Submit Evidence Report for gate check
process. The appointed person leading
the gate check may consult with certain
stakeholders either in writing or through a
hearing (this is only a consult where
necessary stage).
No consultation by the council at this stage
though submission of the Evidence Report     
and outcome of the gate check will be
publicised online using the webpage, social
media and an update emailed out to
participants. Publish Evidence Report online. 
The council will also take the opportunity to
review the consultation and engagement
methods used with a view to improve and
adapt these where necessary for the next
stage of NLLDP2 preparation and
consultation. 
Page 129 of 154

Page 130

14   
LDP Stage 2 – Plan Preparation  
Key Consultation Stage & Quarter
(When)
Consultation Type & Purpose Consultees & proposed engagement
methods (How and with whom)
Preparing the Proposed Local
Development Plan
Develop a spatial strategy building on the
Evidence Report and undertake a Call for
Ideas with all stakeholders to identify ideas
and sites for consideration for the Proposed
Plan.
• Consult and update stakeholders via
council social media platforms,
council website and email contacts
• Issue a call for ideas to stakeholders,
to include an online consultation for
identifying ideas/sites and submitting
relevant context.
• Engage with internal services,
members and external stakeholders
including those that are statutory and
identified as key groups using
workshops/meetings and online/digital
resources.
• Promote/facilitate the participation of
young people including schools,
youth councils and youth parliament
representatives, older people,
Gypsies and Travellers, disabled
persons/groups
Consulting on the Proposed Local
Development Plan
Publish the Proposed Plan (as well as
Delivery Programme) and seek formal
consultation responses.
• Consult and update stakeholders
via council social media platforms,
council website and email contacts
• Consult for a minimum of 12 weeks
on the Proposed Plan, proposed
Delivery Programme and
Environmental Report.
• Publish accompanying assessments
including Equalities Impact
Assessment, Public Sector Equality
Page 130 of 154

Page 131

15   
Duty Assessment, Fairer Scotland
Duty Assessment, Strategic
Environmental Assessment; and
Habitats Regulations Appraisal.
• Inform and consult with stakeholders
and communities on the proposed
plan allowing them to respond to the
content of the plan. Possible
events/meetings to publicise and
present the proposed plan.
• Undertake neighbour notification of
sites proposed for development.
• Consult with Key Agencies and the
Scottish Ministers.
• Consult directly with Central Scotland
Green Network Partnership (aims
currently being delivered by Green
Action Trust).
• Publish in local newspaper and
online. Copies available in a planning
authority office and public libraries in
NLC.
Modifying the Proposed Local
Development Plan and Examination
Following the consultation period,
modifications can be made to the Proposed
Plan. This can take account of:
• representations made;
• any matters arising from consultation with
key agencies and the Scottish Ministers; and
• any minor drafting or technical matters.
• Issue an update on plan progress to
all stakeholders and publish any
Modification Report.
• Advertise upcoming Examination in a
local newspaper and public libraries
and notify anyone who made
representations during the formal
consultation on the Proposed Plan.
• The form of the Examination is at the
discretion of the appointed person, for
example it may be in public, a hearing
or written submissions.
Page 131 of 154

Page 132

16   
LDP Stage 3 – Delivery (of the Plan)  
Key Consultation Stage & Quarter
(When)
Consultation Type & Purpose Consultees & proposed engagement
methods (How and with whom)
Adopting the Local Development Plan Inform people that the Local Development
Plan has been adopted.
Following adoption of NLLDP2:
• send two copies to the Scottish
Ministers;
• publish it;
• place a copy in any local public
libraries;
• notify anybody who commented on
the Proposed Plan; and
• place an advert in a local newspaper 
• Publish notification of Delivery
Programme and make copies
available (within 3 months of NLLDP2
adoption). 
*Greyed out text is consultation/engagement that has already been undertaken.
Page 132 of 154

Page 133

17   
5 How would you prefer to be contacted and involved? 
Table 2 above includes various proposed methods of engagement
and publicising. Figure 5 pulls together a list of these suggested
methods that we may use to keep you up to date and to consult
with you on the preparation of NLLDP2.
This is not exhaustive and whilst they are our suggested methods,
we welcome feedback how best to engage with you during the
preparation of NLLDP2.
We will aim to ensure that we will publicise key stages of NLLDP2
preparation as widely as possible, thereby informing the public at
large of key consultation stages to be able to have views on and
input to the Plan. Resources may also influence both input to the
plan by stakeholders and the methods used to engage.
Whilst more modern methods of engaging and providing information
are increasingly undertaken online, it is recognised that not
everyone may wish to engage in that way or indeed readily have
access to such facilities. We will endeavour to provide alternative
methods of consulting and engaging where possible. 
Figure 5: Contact methods
Our dedicated webpage for LDP2 will contain up-to-date
information and will provide an interactive method for
engaging
Social media platforms including Facebook and Twitter to
post updates throughout the plan preparation process and
links to further information
Email for updates and invite to participate. Sign up for updates
from NLC planning service here -
www.public.govdelivery.com/accounts/UKNLC/subscriber/new
Workshops & meetings can be set up at convenient times and
locations to present face-to-face and have discussions
Adverts will be placed in local newspapers at key stages in the
plan process as well as documents placed in libraries
Open drop-in or specific stakeholder events may be a method
of engaging with the general public or targeted groups
A more specific or targeted approach may be required for
certain harder to reach groups
Page 133 of 154

Page 134

18   
6 Mediation 
The Planning (Scotland) Act 2019 introduced powers for mediation.
Mediation can involve a range of techniques and is used to help
build bridges between stakeholders and resolve issues of dispute. It
is a voluntary process, generally between two parties, which can be
facilitated by a third, independent party.
Any requests for mediation will be considered and where necessary
have regard to such requests in preparing the Participation
Statement. Any potential use of mediation will be considered by the
council, having regard to the issue at hand and the possible
benefits of the mediation and the involvement of other parties. 
7 Contact and future participation
You can contact us at: localdevelopmentplan@northlan.gov.uk
If you would like to be kept up to date on the plan as well as other
aspects of the NLC planning service, please register here.
For further information about the Local Development Plan please
visit our website at www.northlanarkshire.gov.uk/planning-and-
building/development-plans
Page 134 of 154

Page 135

19   
Glossary
Delivery Programme
A document, approved by full council, which sets out how the LDP
will be delivered. 
Development Plan
The statutory basis of planning decision making, comprising NPF4
and the LDP. 
Development Plan Scheme (DPS)
A document setting out the planning authority's programme for
preparing and reviewing their LDPs. It is a statutory document and
communication tool that lets stakeholders know when and how they
can get involved in the plan and keep them informed of progress. It
must contain a Participation Statement (see below). 
Local Development Plan (LDP)
A local development plan (LDP) is a plan in which it is set out, for
land in the part of the district to which it relates:
a spatial strategy, being a detailed statement of the planning
authority's policies and proposals as to the development and use of
the land;
such other matters as may be prescribed; and
any other matter which the planning authority consider it appropriate
to include. It forms part of the statutory development plan. 
Local Place Plans
LPP is a community-led plan setting out proposals for the
development and use of land and a community’s aspirations for its 
future development. Once registered they are to be taken into account in the
preparation of the relevant LDP. 
National Planning Framework (NPF)
Scotland’s fourth National Planning Framework (NPF4) is a long term plan
looking to 2045 that guides spatial development, sets out national planning
policies, designate national developments and highlight regional spatial
priorities. It is part of the development plan, and so influences planning
decisions across Scotland. 
Open Space Strategy (OSS)
An open space strategy is to set out a strategic framework of the planning
authority’s policies and proposals as to the development, maintenance and
use of green infrastructure in their district, including open spaces and green
networks. It must contain; an audit of existing open space provision, an
assessment of current and future requirements, and any other matter which
the planning authority consider appropriate. 
Participation Statement
A document setting out the plan for engagement in the plan making process,
including when consultation is likely to take place, with whom and its likely
form. This will include the steps to be taken to involve the public at large. 
Play Sufficiency Assessment (PSA)
A play sufficiency assessment is the assessment of the sufficiency of play
opportunities for children in their area, carried out by a planning authority
under the duty as set out in Section 16D(1) of the
Page 135 of 154

Page 136

20   
Town and Country Planning Scotland Act 1997, as amended. Must be done by the planning authority in preparing an Evidence Report. 
Regional Spatial Strategy (RSS)
A long-term spatial strategy in respect of the strategic development of an area (or areas). It must specify the region it relates to and identify, in relation to
the region:
the need for strategic development;
the outcomes to which the authority (or authorities) consider that strategic development will contribute;
priorities for the delivery of strategic development; and
proposed locations for strategic development, which must be shown in the strategy in the form of a map or diagram. 
Strategic Environmental Assessment (SEA)
Strategic environmental assessment is a procedure to assess the environmental impact and sustainability of a proposed or existing policy, plan, or
programme. 
Page 136 of 154

Page 137

21   
Appendix 1 - Progress to date (December 2025) 
Plan Preparation
With reference to Table 1 above, the council has completed Stage 1, 'Early Preparation.' This stage involved preparing the first Development Plan Scheme
and Participation Statement in 2023 for the new North Lanarkshire Local Development Plan 2.  Over the last year, Stage 2 has also been completed.
Stage 2 identified and assessed evidence-related topic papers for each policy area outlined in NPF4 and the Scottish Government's Local Development
Planning Guidance. This allowed stakeholders to confirm whether we identified the most relevant evidence and to provide any additional evidence they
wished us to consider. Further engagement and consultation with stakeholders to collate, discuss, and agree on the evidence has been ongoing with a
view to finalising the Evidence Report for reporting to Full Council meeting in April 2026. 
Table 3 Engagement and Consultation Completed below shows what exercises have been undertaken to date.   
Table 3: Engagement & Consultation Completed  
Dates  Engagement Activity  Venue/Method Groups and Organisations 
September
2023    
Joint NLC/SLC Gypsy & Travellers
community engagement 
Hamilton  Gypsy & Travellers community, MECOPP,
Scottish Government, NLC/SLC 
Nov 2023 Development Plan Scheme &
Participation Statement 2023
approved 
Online/Email/Social Media  Wide consultation via social media,
GovDelivery, community groups, community
boards in preparing the DPS/PS
March
2024
Invitation to prepare Local Place
Plans issued and links shared to
online information and sources 
Online/Email/Social Media Community Councils, community groups,
Community Boards, Gov Delivery. 
April 2024 NLLDP2 Newsletter 1 published Online/Email Sent to key agencies/infrastructure providers,
internal contacts, Community Boards,
community groups, GovDelivery, Yammer
(internal), Elected Members
April 2024 Self-build Housing register -
information published online/link
sent out with newsletter update 
Online/Email Publicised via social media and GovDelivery 
May 2024 Presentation to elected members
on NLLDP2 key stages and update 
Civic Centre, Motherwell  NLC Elected Members
May 2024 Engaged with Gypsy & Travellers Hamilton MECOPP/ Scottish Government/
Page 137 of 154

Page 138

22   
community  COSLA/NLC/SLC
August
2024
Joint NLC/SLC Health & Wellbeing
event 
Civic Centre, Motherwell  NHS Lanarkshire, PHS, HSCP, NLC/SLC
June 2024
- ongoing
Updates provided to Access Panel
as and when required 
Attendance at monthly Access
Panel meetings 
Access Panel 
May -
June 2024
NPF4 related Topic Surveys Batch
1 published online for six weeks to
assist evidence gathering 
Online/Email/GovDelivery Survey sent to stakeholders including elected
members, key agencies, infrastructure
providers, community groups/Community
Boards and published online and shared via
social media platforms and GovDelivery. 
June-July
2024
NPF4 related Topic Surveys Batch
2 published online for six weeks to
assist evidence gathering
Online/Email/GovDelivery Survey sent to stakeholders including elected
members, key agencies, infrastructure
providers, community groups/Community
Boards and published online and shared via
social media platforms and GovDelivery.
July-Aug
2024
NPF4 related Topic Surveys Batch
3 published online for six weeks to
assist evidence gathering
Online/Email/GovDelivery Survey sent to stakeholders including elected
members, key agencies, infrastructure
providers, community groups/Community
Boards and published online and shared via
social media platforms and GovDelivery.
Sept-Oct NPF4 related Topic Surveys Batch
4 published online for six weeks to
assist evidence gathering
Online/Email/GovDelivery Survey sent to stakeholders including elected
members, key agencies, infrastructure
providers, community groups/Community
Boards and published online and shared via
social media platforms and GovDelivery.
Sep-Oct
2024
Landowner/housebuilder/developer
survey consultation
Online survey  Survey (prepared with Homes for Scotland)
issued to
landowners/housebuilders/developers
Oct 2024 Local Place Plan information
sharing event held with community
groups
Face-to-face session Community groups/Nick Wright Planning/NLC
Nov 2024 Update and Place Survey
awareness provided to Voice of
Experience Forum  
Attendance at VoE meeting Voice of Experience
Nov 2024 Update and Place Survey
awareness provided to Access
Attendance at Access Panel
meeting
Access Panel
Page 138 of 154

Page 139

23   
Panel 
Nov 2024
– Jan
2025
NPF4 related Topic Surveys Batch
5 published online for six weeks to
assist evidence gathering 
Online/Email/GovDelivery  Survey sent to stakeholders including elected
members, key agencies, infrastructure
providers, community groups/Community
Boards and published online and shared via
social media platforms and GovDelivery.
Dec 2024
– Mar
2025
Public/stakeholder Place Survey
ran over 4 months to raise
awareness and gather
understanding of community board
level area priorities 
Online/Email/GovDelivery/Social
Media  
Survey sent to stakeholders including elected
members, key agencies, infrastructure
providers, community groups/Community
Boards and published online and shared via
social media platforms and GovDelivery. 
Dec 2024 Place Survey circulated to all
children and young people within
schools via every parent and carer. 
Email/Online Children and Young People 
Jan 2025 Internal staff workshop for wider
Place service presenting
NPF4/NLLDP2 updates and
discussion of topics
Online Place Service session internally for staff.
Jan 2025  Further information issued to assist
communities in the preparation of
Local Place Plans. 
Email  Community Councils/community groups 
Jan 2025 Follow-up session - Local Place
Plan information sharing event
held with community groups
Face-to-face session  Community groups/Nick Wright Planning/NLC 
Jan 2025 NLLDP2 Newsletter 2 published  Online/Email  Sent to key agencies/infrastructure providers,
internal contacts, Community Boards,
community groups, GovDelivery, Yammer
(internal), Elected Members
Jan 2025 -
Ongoing
Key Agency topic-by-topic
engagement
Online/In-person Key Agencies
Feb 2025 Public drop-in sessions for Place
Surveys 
In-person  Public drop-in sessions in each of the
Community Board areas. 
Feb 2025 Tenants 'Food for Thought'
Conference 
In-person Tenants & Residents Associations/North
Lanarkshire Federations/Tenants Participation
Team
Feb 2025 Youth Councillors/Youth In-person Youth Councillors/Youth Parliament members  Page 139 of 154

Page 140

24   
Parliament Workshop to highlight &
assist with the Place Survey and
discuss the new NLLDP2. 
Feb 2025  Access Panel attendance to raise
awareness and understanding of
Place Survey 
In-person Access Panel 
May 2025
– Aug
2025 
Landowner and
housebuilder/developer survey
consultation to gather information
on the existing housing land supply
to inform Housing Land Audit and
Delivery Programme 
Online/Email  Landowners/Housebuilders/Developers/Homes
for Scotland 
Aug 2025  Site assessment workshop  In-person Workshop Key Agencies/Homes for Scotland/
Developers/
Landowners/Housebuilders/Agencies/Nick
Wright/ Internal (NLC) staff 
Sept 2025  Site assessment workshop and
LDP update 
Online Workshop Elected Members
Nov 2025 Community Board sessions x 2 -
events to share updates on the
Local Development Plan, present
findings from our recent Place
Survey, and introduce the
proposed site assessment
methodology for the upcoming
Call for Ideas.
Online Workshop Community Boards (community groups part of
the community boards) 
Nov 2025 Community Board sessions x 2 -
to update on and explore the
draft Open Space Strategy
Online Workshop Community Boards (community groups part of
the community boards) 
Page 140 of 154

Page 141

North Lanarkshire Council Report
Planning Committee
Does this report require to be approved? ☒ Yes   ☐ No
Ref     GMCK/PH Date 04/12/25
Scheme of Delegation: Local Developments  
From Pamela Humphries, Chief Officer (Place)
E-mail humphriesp@northlan.gov.uk Telephone 01236 632487
1. Background
1.1 The existing scheme of delegation was last updated and approved in March 2025.
Within the existing scheme there is a requirement to report back to committee on any
follow on applications that may arise following the granting of planning permission or
Executive Summary
As part of the work of the Planning Service it has become apparent that there are
circumstances where it may benefit the Council to alter its scheme of delegation in order
to deliver the Council’s Plan for North Lanarkshire and associated Programme of Work.
This alteration would allow the Council’s Planning Service to deal with follow on
applications for local developments where there is an existing consent and the applicant is
looking to make alterations or revisions to that development, discharge conditions or renew
the scheme. At present the current scheme of delegation requires that all follow on
applications for local developments that are contrary to the development plan require to be
reported back to Planning Committee. Allowing these applications to be delegated would
help improve and streamline the statutory consent process, improving performance as well
as supporting inward investment to North Lanarkshire.  
Recommendations
It is recommended: 
1. that the update to section 49.5 of the Scheme of Delegation to Officers as set out
in  Appendix 1 to this report, be approved; and
2. that subject to the approval of the Council the updated scheme be sent to the
Scottish Government for ratification.
The Plan for North Lanarkshire
Priority Improve economic opportunities and outcomes
Ambition statement (4) Market and promote North Lanarkshire as the place to live,
learn, work, invest, and visit
Programme of Work Invest in North Lanarkshire
Item 4
Page 141 of 154

Page 142

planning permission in principle for local developments that have been approved
contrary to the development plan (regardless of whether the permission was granted
by the Planning Committee, the Local Review Body or by Scottish Government). 
1.2 The impact of this is that our current scheme requires that, even where there is an
existing or extant permission for a local development approved contrary to the
development plan, these follow on applications to that development still require to be
reported to committee such as Matters Specified in Conditions Applications (MSC),
Renewals of Permission and Variation of permissions under S42 of the Act. 
1.3 Whilst it makes sense in relation to the consideration of such a development the first
time around, i.e. that the committee consider and determine if the development is an
acceptable departure to the development plan, it would be more efficient if follow on
applications could be dealt with under delegated authority.   It is considered that the
suggested change to the current scheme of delegation will speed up decision making,
provide more certainty for developers and those seeking to invest in North Lanarkshire.   
1.4 If this change is approved, it should be noted that an important safeguard and exception
would still continue to trigger committee reporting. Namely that any application which
raises significant objections would require to be reported i.e. when six or more
objections are lodged which raise material planning issues (multiple objections from
one person or one household will count as one objection), then the application would
continue to require to be reported to committee. 
2. Report 
2.1 Currently section 49.5 of the existing scheme of delegation which deals with local
developments says that:   
To determine any application for planning permission or any application for consent,
agreement or approval required by condition imposed on a grant of planning
permission, within the category of local developments as defined in the Town and
Country Planning (Hierarchy of Developments) (Scotland) Regulations 2009, subject
to the exceptions as listed below: 
(a) Any application made by a member of staff of the Place Service an Elected Member
or a Chief Officer of the Council
(b) Any application which, if approved, would require to be notified to the Scottish
Ministers
(c) Any application which raises significant objections (six or more all of which raise
material planning issues) (multiple objections from one person or one household will
count as one objection)
(d) Any application which, if approved, would be contrary to the Development Plan 
2.2 It is considered that part (d) above should be altered to read as follows: 
(d) Any application which, if approved, would be contrary to the Development Plan
unless there is an extant permission for the application site that has been granted
either by committee, the Local Review Body or the Scottish Government and the
application is for the same or similar development. 
2.3 With this change it will mean that the planning service will more quickly be able to deal
with follow on applications that may arise as delegated matters without having to refer
back to committee. 
Page 142 of 154

Page 143

2.4 By way of example the agenda for this committee has an application that illustrates the
point. Application 25/00819/AMD for the Erection of two dwellinghouses: Amendment
to permission 24/00709/FUL Land at Hawthorn Avenue, Crindledyke, Newmains.  This
application is seeking some relatively minor changes (repositioning of one of the
houses to reduce infill required to level the plot) to an existing planning permission that
was granted by Planning Committee.  There have been no objections to the application,
but this requires to be reported committee because, notwithstanding the existing valid
planning permission, in development plan terms, the site remains in the green belt i.e.
this development is contrary to the plan. 
2.5 With approval of the changes being sought the council will be better positioned to deal
with further applications in relation to sites that have a current or extant planning
permission. 
2.6 If approved this alteration will require to be presented to Full Council for confirmation
and then to the Scottish Government for ratification. 
3. Measures of success 
3.1  The Planning Service and the Council will be able to more efficiently and effectively
deal with planning applications to support the delivery of the Council’s ambition for
North Lanarkshire     
4. Supporting documentation 
4.1 Appendix 1 – Amendment to Section 49.5 of the Scheme of Delegation to Officers 
Pamela Humphries
Chief Officer (Place) 
Page 143 of 154

Page 144

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☒
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?
Page 144 of 154

Page 145

Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
An approved updated Scheme would require to be placed on the Council website.
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed?
If the suggested change is not approved then this could impact on Planning’s
performance and put inward investment to North Lanarkshire at risk.  
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☐ 
Page 145 of 154

Page 146

Appendix 1
Scheme of Delegation to Officers: Section 49.5
No. Delegation Officers with Delegated Authority
49.5 To determine any application for planning permission or any application for consent,
agreement or approval required by condition imposed on a grant of planning permission, within
the category of local developments as defined in the Town and Country Planning (Hierarchy of
Developments) (Scotland) Regulations 2009, subject to the exceptions as listed below: 
(a) Any application made by a member of staff of the Place Service an Elected Member or a
Chief Officer of the Council 
(b) Any application which, if approved, would require to be notified to the Scottish Ministers 
(c) Any application which raises significant objections (six or more all of which raise material
planning issues) (multiple objections from one person or one household will count as one
objection) 
(d) Any application which, if approved, would be contrary to the Development Plan.
Chief Officer (Place) 
Planning and Place Manager 
Planning Managers 
Senior Planning Officers 
Update to Section 49.5 
No. Delegation Officers with Delegated Authority
49.5 To determine any application for planning permission or any application for consent,
agreement or approval required by condition imposed on a grant of planning permission, within
the category of local developments as defined in the Town and Country Planning (Hierarchy of
Developments) (Scotland) Regulations 2009, subject to the exceptions as listed below: 
(a) Any application made by a member of staff of the Place Service an Elected Member or a
Chief Officer of the Council 
(b) Any application which, if approved, would require to be notified to the Scottish Ministers 
(c) Any application which raises significant objections (six or more all of which raise material
planning issues) (multiple objections from one person or one household will count as one
objection) 
(d) Any application which, if approved, would be contrary to the Development Plan, unless
there is an extant permission for the application site that has been granted either by
committee, the Local Review Body or the Scottish Government and the application is for the
same or similar development.
Chief Officer (Place) 
Planning and Place Manager 
Planning Managers 
Senior Planning Officers 
Page 146 of 154

Page 147

North Lanarkshire Council
Report
PLANNING COMMITTEE 
Does this report require to be approved? ☐ Yes   ☒ No
Ref    Index 1 Date 04/12/25 
NOTICE OF PLANNING AND ENFORCEMENT APPEALS LODGED 
From  Pamela Humphries, Chief Officer (Place)  
E-mail humphriesp@northlan.gov.uk Telephone 01236 632487 
1. Background 
1.1 Where a planning application has been refused by the Planning Committee, or Full
Council, the applicant may appeal the decision to the Scottish Government within 3
months.   
1.2 Applicants may also appeal against a planning condition which has been imposed
within a planning consent. 
2. Report 
2.1 The council has received notification that the following appeals have been submitted
to the Scottish Ministers. 
Application No.      Applicant         Date of Council Form of  Note
& Proposal          & Site           Decision    Appeal 
18/00890/PPP  Orchard Brae Ltd 12/06/2025  Written Submission
Proposed   Land to the North of
Residential-led  A8 & South of
Executive Summary 
The purpose of this report is to advice Committee of planning appeals that have been
recently lodged with the Scottish Ministers. 
Recommendations
It is recommended that the Committee notes the position regarding appeals lodged with
Scottish Ministers. 
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement All ambition statements
Item 5
Page 147 of 154

Page 148

Mixed Use   Sykeside Road &
Development  Calderbank Road
Masterplan including Airdre 
Residential (Mixed) 
Types/Tenures),
Employment Facilities,
Local Neighbourhood
Centre (Potentially 
Including Retail, 
Food and Drink Uses,
Public House, Leisure
Uses, Healthcare,
Community Facilities),
Education Facilities, 
Energy Centre, 
Parkland, Open 
Space and Landscaping,
with Associated Access
Roads, Parking and
Infrastructure 
25/00815/LUC  Mr James Gilhaney 17/10/2025        Written Submission
Change of Use  Building to the Rear 
from Day Room of Mill Cottage Old     
(Sui Generis) to  Mill Road Allanton
Dwelling  ML7 5BX               
3. Measures of success 
3.1 The outcome of appeals will be reported to Committee in due course. 
4. Supporting documentation 
4.1 Details of appeals submitted to the Scottish Ministers can be found on the DPEA
website: 
Scottish Government - Planning and Environmental Appeals Division (DPEA) 
Pamela Humphries
Chief Officer (Place) 
Page 148 of 154

Page 149

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?
Page 149 of 154

Page 150

Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☒ 
Page 150 of 154

Page 151

North Lanarkshire Council
Report
PLANNING COMMITTEE 
Does this report require to be approved? ☐ Yes   ☒ No
Ref    Index 2 Date 04/12/25 
NOTICE OF PLANNING AND ENFORCEMENT APPEALS
DECISIONS 
From  Pamela Humphries, Chief Officer (Place)  
E-mail humphriesp@northlan.gov.uk Telephone 01236 632487 
1. Background 
1.1 Where a planning application has been refused by the Planning Committee, or Full
Council, an applicant may appeal the decision to the Scottish Government within 3
months.  
1.2 Applicants may also appeal against a planning condition which has been imposed
within a planning consent. 
1.3 The Planning Committee is notified of appeals that have been lodged with the Scottish
Government, and also the outcome of these appeals once a decision has been made.   
2. Report 
2.1   The council has received notification that the following appeal has been decided by
the Scottish Ministers. 
Executive Summary 
The purpose of this report is to advise Committee of a planning appeal that has been
recently decided by the Scottish Ministers. 
Recommendations 
It is recommended that the Committee note the decision in respect of this appeal. 
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement All ambition statements
Item 6
Page 151 of 154

Page 152

Application No. &
Proposal 
Applicant & Site  Appeal
Decision &
Date 
Note 
24/00381/AMD    Keepmoat Homes       Appeal Allowed
Modification of  Land East of         In Part, 
Existing Section  Wellington Street       18/09/2025
75 Planning  Craigneuk
Obligation Relating Wishaw
to Permission
21/00464/FUL to 
Delete clauses 4 
(Education
Contribution), 5 (Play
Contribution) and 6 
(Community Facilities 
Contribution) 
2.2 The reporter allowed the appeal in part confirming that only the play contribution 
element of the legal agreement satisfied the relevant tests, but that the education and 
community facilities contributions did not. The reporter concluded that the education 
contribution could not be justified in this case given the current capacity in the primary 
schools, the current rolls, the pupil generation and when they are likely to enter the 
school system. This meant that in their opinion there was no impact to be mitigated. 
On the need for a community facility contribution, notwithstanding the consultation 
comment from SportScotland who supported this, the reporter was not convinced that 
the development had led to the loss of a sports pitch given it had been out of use for 
at least 15-20 years. 
3. Measures of success 
3.1   The Planning Committee is kept informed of the outcome of appeals made to the
Scottish Government.   
4. Supporting documentation 
4.1 Details of appeals decided by the Scottish Ministers can be found on the DPEA website: 
Scottish Government - Planning and Environmental Appeals Division (DPEA) 
Pamela Humphries
Chief Officer (Place) 
Page 152 of 154

Page 153

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?
Page 153 of 154

Page 154

Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☒ 
Page 154 of 154