MINUTES of MEETING of PLANNING, PROTECTIVE SERVICES AND LICENSING COMMITTEE
held BY MICROSOFT TEAMS on WEDNESDAY, 22 NOVEMBER 2023 
Present: Councillor Kieron Green (Chair) 
Councillor John Armour
Councillor Gordon Blair
Councillor Jan Brown
Councillor Audrey Forrest
Councillor Graham Hardie 
Councillor Mark Irvine
Councillor Paul Donald Kennedy
Councillor Luna Martin
Councillor Dougie Philand
Councillor Peter Wallace 
Attending: Shona Barton, Governance Manager
Peter Bain, Development Manager
Bryn Bowker, Area Team Leader – Mid Argyll, Kintyre and the Islands
Kirsty Sweeney, Area Team Leader – Helensburgh and Lomond/Bute and
Cowal
Emma Jane, Planning Officer
Fiona Scott, Planning Officer
Tiwaah Antwi, Planning Officer
Marina Curran Colthart, Local Biodiversity Officer 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Amanda Hampsey, Daniel
Hampsey, Andrew Kain and Liz McCabe. 
2. DECLARATIONS OF INTEREST 
Councillor Mark Irvine declared a non-financial interest in planning application reference
22/00678/PPP, as he knew the Applicant personally and had been lobbied frequently over
the last few months.  He left the room and took no part in the determination of this
application which was dealt with at item 4 of this Minute. 
Councillor John Armour declared a non-financial interest in planning application reference
23/01018/PP as it concerned a farm neighbouring his own business and he had also been
lobbied by local residents.  He indicated that he would take no part in the determination of
this application which was dealt with at item 6 of this Minute, but would remain in the
meeting. 
3. MINUTES 
a) The Minute of the Planning, Protective Services and Licensing Committee held on 18
October 2023 at 11.00 am was approved as a correct record. 
b) The Minute of the Planning, Protective Services and Licensing Committee held on 18
October 2023 at 2.00 pm was approved as a correct record. 
c) The Minute of the Planning, Protective Services and Licensing Committee held on 18
October 2023 at 3.00 pm was approved as a correct record.

Page 2

Having declared an interest in the following item, Councillor Mark Irvine left the meeting at
this point. 
4. MR ROBERT MACINTYRE: SITE FOR THE ERECTION OF DWELLINGHOUSE:
LAND WEST OF RUANDA, SHORE ROAD, PEATON, HELENSBURGH (REF:
22/00678/PPP) 
The Planning Officer spoke to the terms of the report.  Planning permission in principle is
sought for the erection of a single dwellinghouse and installation of a septic tank.  The site
for the proposed dwellinghouse is located within the minor settlement boundary of
Coulport/Letter.  The proposal also includes the formation of a new access to serve the
proposed dwellinghouse.  The majority of this new access is out with the settlement
boundary and is located within the countryside zone.  The site is also located within the
MOD safeguarding zone of Coulport.   
The proposed site is located on the seaward side of the main road (B833) opposite an
existing dwelling know as Ruanda.  All development within the minor settlement boundary
of Coulport/Letter is located exclusively on the landward side of the main road and there is
no existing development to the seaward side of the road within the settlement boundary. 
It is considered that the proposals do not constitute an appropriate site within the
settlement zone, because they do not relate to this established settlement pattern of
Coulport/Letter. 
It is recognised that there is development on the seaward side of the main road in nearby
neighbouring Ardpeaton.  This development is either historical or is re-development on
brownfield sites and is not on a greenfield site.  The application site is a greenfield site,
considered to be natural foreshore and can be described as a mature aged broadleaved
woodland with areas of wet woodland within it.   
There have been 26 objections to this proposal received and one representation along
with objections from Cove and Kilcreggan Community Council and the Development
Policy Unit.  There have been no objections from other consultees, subject to conditions. 
The proposal was assessed against policies of the Local Development Plan (LDP) 2015,
National Planning Framework 4 and LDP2, as detailed at section P of the report and it
was recommended that planning permission in principle be refused for the reasons
outlined in the report of handling. 
Decision 
The Committee agreed to refuse planning permission in principle for the reasons detailed
below: 
1. LDP DM1 gives encouragement to sustainable forms of development within key
settlements on appropriate sites and within the countryside zone on appropriate infill,
rounding off and redevelopment sites and changes of use of existing buildings. There
is a presumption against development that seeks to extend an existing settlement into
the Countryside Zone. With regard to LDP DM1 the proposal includes an area of
settlement zone and countryside zone, the proposal does not constitute an appropriate
site within the settlement zone, because it does not relate to the established settlement
pattern at Coulport/Letter, where built development is located exclusively on the
landward side of the road.  The proposed access to the development is located within
the countryside zone and therefore does not accord with part E of LDP DM1. In

Page 3

addition, it would not be supported by LDP2 Policy 01 in relation to settlement areas
and Policy 02 out with settlement areas which is a material consideration. In relation to
Policy 01 – Settlement Areas, development will normally be acceptable where it is an
appropriate scale and fit for the size of settlement in which it is proposed and respects
the character and appearance of the surrounding townscape. In this regard the
proposal does not constitute an appropriate site within the settlement zone, because
the proposal does not relate to the established settlement pattern at Coulport/Letter,
and results in the development of a section of natural foreshore in a village where built
development is located exclusively on the landward side of the road. Regarding Policy
02, the proposal would not constitute as infill, rounding off, redevelopment or located
on a previously developed site and is therefore not generally supported. Policy 02
further notes that development adjacent to, but out with settlement boundaries which
are delineated in the proposals maps will not constitute infill, rounding off or
redevelopment. 
In addition, whilst it is believed that the site could accommodate a modest sized
dwelling, it has not been demonstrated that there would be sufficient land for the
required amenity space including; garden, parking and turning area. 
As the proposed development fails to pay regard to the established settlement pattern
in this location it is also considered to be contrary to NPF4 Policy 14. Furthermore,
based on the above the proposals would also be contrary to the provisions of Policy
LDP 9 and the Supplementary Guidance Sustainable Siting and Design Principles
(paras 4.1 and 4.2) and proposed LDP polices 05, 08 & 10 which are a material
consideration. 
2. Policy 9 of NPF4 does not support greenfield sites unless the site is allocated for
development or the proposal is explicitly supported by policies in the LDP. Given the
house is not supported by the settlement strategy policies within the adopted LDP (as
explained in point 1), then the proposal is also contrary to Policy 9 of NPF4. 
3. It is considered that the proposed development is contrary to NPF4 Policy 1 & 3 as
underpinned by LDP Policies LDP 3, SG LDP ENV 1, 6 & 14 and Proposed LDP2
Policy 73 given the disturbance to biodiversity is not acceptable. The construction of a
house and access would result in the loss of ground flora and fauna and individual
mature trees within an established native woodland and the potential impacts on
protected species. 
4. The proposal would be contrary to NPF4 Policy 6 part b) which notes that proposals
will not be supported where they result in adverse impacts on native woodlands
including individual trees of high biodiversity value or fragmenting woodland habitats.
In regard to potentially fragmenting woodland habitats, the preliminary ecological
appraisal has noted the site has good connectivity to further Ancient Woodland
Inventory and to the Local Nature Conservation Site at Peaton Glen. Also of relevance
is SG LDP ENV 6, which places importance on development impact on trees /
woodland whereby Argyll and Bute Council will resist development likely to have an
adverse impact on trees by ensuring through the development management process
that adequate provision is made for the preservation of woodland/trees. Policy 77 of
the proposed LDP notes that there is a strong presumption in favour of protecting our
woodland resources. Particular care will be taken to ensure that ancient semi-natural
woodland, native or long-established woods and individual trees of high nature
conservation value are safeguarded, conserved and, where possible, enhanced.
Removal of woodland resources will only be permitted where it would achieve

Page 4

significant and clearly defined additional public benefits.  As noted above the adverse
impacts on native woodland and individual mature trees of biodiversity value would be
contrary to NPF4 Policy 6, SG LDP ENV 6 as well as Proposed LDP Policy 77 which is
a material consideration. 
5. NPF4 Policy 10 seeks to protect coastal communities and assets and support
resilience to the impacts of climate change, part B) notes; Development proposals in
undeveloped coastal areas will only be supported where they are necessary to support
the blue economy, net zero emissions or to contribute to the economy or wellbeing of
communities whose livelihood depend on marine or coastal activities, or is for essential
infrastructure, where there is a specific locational need and no other suitable site. In
addition, policy SG LDP CST 1 (Coastal Development) notes that the preferred
location for developments requiring a coastal location is the Developed Coast, which
consists of coastal areas within the Settlement Development Management Zone,
excluding the Natural Foreshore. This proposed site is a Natural Foreshore where
there is a presumption against development unless there is a specific operational
need; and ii) there is no effective alternative location for the development landward of
the natural foreshore; and iii) the development does not damage or undermine the key
features of the natural foreshore area. As the proposal for a single dwelling house fails
to demonstrate compliance with the above criterial the proposal would also be contrary
to SG LDP CST 1. Furthermore, as this proposal for a single dwelling is located within
an undeveloped coastal area it would also be contrary to NPF4 Policy 10. 
(Reference: Report by Head of Development and Economic Growth dated 6 November
2023, submitted) 
Councillor Luna Martin joined the meeting during consideration of the foregoing item. 
Councillor Irvine returned to the meeting at this point. 
5. OBAN BAPTIST CHURCH: DEMOLITION OF EXISTING BUILDINGS AND
ERECTION OF NEW CHURCH/COMMUNITY BUILDING WITH ASSOCIATED
LANDSCAPING WORKS: OBAN BAPTIST CHURCH, ALBANY STREET, OBAN
(REF: 23/00688/PP) 
The Planning Officer spoke to the terms of the report.  Planning permission is sought for
the demolition of the existing Oban Baptist Church and ancillary buildings to allow for the
erection of a replacement church/community building. 
The application site is situated within the defined Main town Settlement Zone of Oban. 
The site is currently occupied by three buildings, the main Church building, the Church hall
and a detached bungalow, all of which are used for various functions.  Whilst a historic
building, the Church is not covered by any statutory designation nor is it within any area
benefiting from statutory protection.  The proposed new building is a contemporary
designed, split level structure which presents as a single storey mono-pitched roof
structure to Albany Street, with a two storey pitched roof element presenting to Shore
Street.  The roof height would be lower than that of the existing Church building. 
The proposal has elicited 12 objections, 1 representation and 48 expressions of support. 
The main thrust of the objections relate to the demolition of the Church building.  However,
the demolition of the building would benefit from “deemed permission” under the Town
and Country Planning General Permitted Development Order 1992 (as amended) and

Page 5

therefore this aspect of the proposal is outwith the remit of the Council as Planning
Authority. 
With regard to the other concerns raised by objectors in relation to the access and
infrastructure arrangements to serve the proposed development, the site is already
operating a similar development to that proposed in the application.  No objections were
raised by any of the statutory consultees. 
As a minor departure to NPF4 Policy 9 with regards to demolition, which can be
undertaken without any input from the Planning Authority, the proposal is otherwise
consistent with the provisions of both Local and National Planning Policy and it was
recommended that planning permission be granted subject to the conditions and reasons
detailed in the report of handling. 
Decision 
The Committee agreed to grant planning permission subject to the following conditions
and reasons: 
Standard Time Limit Condition (as defined by Regulation) 
Standard Condition on Soil Management During Construction 
Additional Conditions 
1. The development shall be implemented in accordance with the details specified on the
application form dated 31/03/23, supporting information and, the approved drawings
listed in the table below unless the prior written approval of the planning authority is
obtained for an amendment to the approved details under Section 64 of the Town and
Country Planning (Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date
Received
Existing Drawings   01  03/04/23
Location & Block Plans  AL- 001 -A3  21/04/23 
Topographical Plan  AL- 002 1-125
A2 
03/04/23 
Existing Site Plan  AL- 003 A3  03/04/23 
Proposed Site Plan  AL- 004 A3  21/04/23 
Proposed Floor Plans  AL- 005 A1  03/04/23 
Proposed Elevations  AL- 006 A1  03/04/23 
Client Statement/Pre-
Application Consultation – 24
PAGES 
03/04/23 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details. 
Note to Applicant 
Please note the comments in the consultation response from Scottish Water and the
comments provided in the submission from the Oban District Access Panel, details of

Page 6

which are available to view on the planning application file via the Public Access
section of the Council’s website. 
2. PP – Traffic Management Plan 
Notwithstanding the effect of Condition 1, no development shall commence until a
Traffic Management Plan has been submitted for the written approval of the Planning
Authority in consultation with the Roads Authority. The Plan shall detail approved
access routes, agreed operational practices (including avoidance of convoy
movements, specifying conduct in use of passing places, identification of turning
areas, reporting of verge damage) and shall provide for the provision of an appropriate
Code of Practice to drivers of construction and delivery vehicles.  The development
shall be implemented in accordance with the duly approved Traffic Management Plan.  
Reason: To address potential abnormal traffic associated with the development in the
interests of road safety.   
3. PP - Finishing Materials 
Notwithstanding the effect of Condition 1, no development shall commence until
samples of materials to be used in the construction of the development hereby
approved have been submitted to and approved in writing by the Planning Authority.
The development shall thereafter be completed using the approved materials or such
alternatives as may be agreed in writing with the Planning Authority. 
Reason: In order to integrate the development into its surroundings. 
4. PP - Reclamation of Materials 
No demolition works shall commence until a scheme for the reclamation of stone from
the Oban Baptist Church building, during or prior to demolition has been drawn up in
consultation with, and approved in writing by the Planning Authority. The stone shall be
satisfactorily set aside, stored and used within the redevelopment scheme in a manner
which shall first be agreed with by the Planning Authority, prior to any demolition taking
place. 
Reason: In order to protect and save materials and items which can reasonably be
retrieved, in the interests of the historical qualities of the building to be demolished. 
5. PP – Sustainable Drainage System 
Notwithstanding the provisions of Condition 1, the development shall incorporate a
surface water drainage system which is consistent with the principles of Sustainable
urban Drainage Systems (SuDS) compliant with the guidance set out in CIRIA’s SuDS
Manual C753. The requisite surface water drainage shall be operational prior to the
development being brought into use and shall be maintained as such thereafter. 
Reason: To ensure the provision of an adequate surface water drainage system and to
prevent flooding. 
Note to Applicant

Page 7

Further advice on SuDS can be found in SEPA’s Standing Advice for Small Scale
Development – www.sepa.org.uk 
6. PP - Waste Management 
Notwithstanding the effect of Condition 1, no development shall commence until a
Waste Management Strategy for the development has been submitted to and
approved in writing by the Planning Authority.   
The Waste Management Strategy shall include details of how much waste the
proposal is expected to generate and how it will be managed including: 
(i) Details of provisions to maximise waste reduction and waste separation at source;
(ii) Details of measures to minimise the cross-contamination of materials, through
appropriate segregation and storage of waste; convenient access for the collection
of waste; and recycling and localised waste management facilities. 
Thereafter the development shall be undertaken in accordance with the approved
Waste Management Strategy unless otherwise agreed in writing with the Planning
Authority. 
Reason:  In order to comply with the requirements of NPF4 Policy 12. 
7. PP - Landscaping and Biodiversity Enhancement 
Notwithstanding the effect of Condition 1, no development shall commence until details
of the proposed treatment of the soft landscaping areas within the development has
been submitted to and approved in writing by the Planning Authority. 
The scheme shall include details of: 
(i) Location, design and materials of proposed walls, fences and gates; 
(ii) Surface treatment of proposed means of access and hardstanding areas; 
(iii) Proposed hard and soft landscape works; 
(iv) A biodiversity statement demonstrating how the proposal will contribute to
conservation/restoration/enhancement of biodiversity, and how these benefits will
be maintained for the lifetime of the development. 
The development shall not be occupied until such time as the boundary and surface
treatment have been completed in accordance with the duly approved scheme. 
All physical biodiversity enhancement measures (bird nesting boxes, ‘swift bricks’,
wildlife ponds, bat and insect boxes, hedgehog homes etc) shall be implemented in full
before the development hereby approved is first brought into use. 
All biodiversity enhancement measures consisting of new or enhanced planting shall
be undertaken either in accordance with the approved scheme of implementation or
within the next available planting season following the development first being brought
into use. 
The biodiversity statement should refer to: Developing with Nature guidance |
NatureScot as appropriate.

Page 8

Reason: To assist with the integration of the proposal with its surroundings in the
interest of amenity, and to comply with the requirements of NPF4 Policy 3. 
(Reference: Report by Head of Development and Economic Growth dated 6 November
2023, submitted) 
6. MR THOMAS IRWIN: FORMATION OF EARTH BANK SLURRY LAGOON AND
ASSOCIATED WORKS: LAND AT WEST DRUMLEMBLE FARM, WEST OF
ROWAN TREE COTTAGE, DRUMLEMBLE, CAMPBELTOWN (REF:
23/01018/PP) 
The Planning Officer spoke to the terms of the report.  This application seeks planning
permission to establish an earth bank slurry lagoon and associated works, including
erection of a 2m high security fence. 
The application site is accessible via a farm track off a private access to the U031 public
road.  The proposed development is in response to the updated Scottish Government
legislation on the Water Environment (Controlled Activities) (Scotland) Amendment
Regulations 2021, which requires all cattle and pig farmers to have a maximum slurry
storage capacity for a period of 22 and 26 weeks by 1 January 2026; and slurry storage to
be built in line with the Silage, Slurry and Agricultural Fuel Oil (SSAFO) requirements. 
The application site comprises a greenfield site located within the Countryside Zone.   
In this instance, the proposed erection of a slurry lagoon, whilst on a greenfield site,
represents an exceptional case (to comply with new regulatory requirements) requiring
this specific location (located within a reasonable distance from the existing functioning
agricultural buildings) to function as an integral part of the agricultural operations of West
Drumlemble Farm. 
At the time of writing the report a total of 29 representations had been received, 28 of
which were in objection and one neutral response.  An objection had also been received
from Laggan Community Council.  One objector, Leslie McGeachy, had since indicated
that he no longer objected to the proposal as his previous concerns had been addressed. 
The proposal, subject to conditions, is considered to be consistent with the relevant
provisions of the Development Plan, NPF4 and LDP2 and there are no other material
considerations of sufficient significance to indicate that it would be appropriate to withhold
planning permission. 
It was recommended that planning permission be granted subject to the conditions and
reasons detailed in the report. 
Decision 
In order to address Health and Safety concerns raised by Members, the Committee
agreed to continue consideration of this application to a future meeting and requested
Officers obtain from the Applicant the following further information: 
1. Details on the nature of the proposed fence in terms of size and design and signage
displayed in order to secure the site of the slurry lagoon; 
2. Clarification on the type of cover that will go over the slurry lagoon in terms of the
safety aspects of it; and

Page 9

3. Details of protocols that will be put in place in respect of the Health and Safety aspects
of the site, to ensure it was a safe place to work. 
(Report by Head of Development and Economic Growth dated 10 November 2023,
submitted) 
Councillors Paul Kennedy and Luna Martin left the meeting during consideration of the
foregoing item. 
7. SCOTTISH BIODIVERSITY STRATEGY - DELIVERY PLAN: TACKLING THE
NATURE EMERGENCY: CONSULTATION ON SCOTLAND'S STRATEGIC
FRAMEWORK FOR BIODIVERSITY 
The Scottish Biodiversity Strategy: Tackling the Nature Emergency consultation is seeking
views on a range of topics and actions to halt the loss of biodiversity and tackle the nature
emergency in Scotland.  An officer response will be submitted to the consultation, and as
the Scottish Biodiversity Strategy – Development plan progresses, further reports will be
brought forward to Committee with updates on what the implications are for the Council. 
A report summarising the actions that local authorities will be expected to deliver in the
Scottish Biodiversity Strategy Delivery Plan, which is a five year rolling plan, was
considered. 
Decision 
The Committee agreed to: 
1. recognise the implications for local authorities, as set out in paragraph 4.2 of the
report, in delivering the Scottish Biodiversity Strategy – Delivery Plan actions including
Nature Networks 30 x 30 in terms of resources, funding and timescales; and 
2. recognise the implications for local authorities, as set out in paragraph 4.5 of the
report, in meeting any of the targets (which have yet to be agreed) in the draft Natural
Environment Bill. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 26 October 2023, submitted) 
8. THE FIREWORKS AND PYROTECHNIC ARTICLES (SCOTLAND) ACT 2022 -
FIREWORK CONTROL ZONES IN ARGYLL AND BUTE 
The report to the PPSL Committee in September 2023 provided detail on the introduction
and provisions of the Fireworks and Pyrotechnics Articles (Scotland) Act 2022 and
particularly the matter of Firework Control Zones. 
A report setting out how the Council proposes to provide information on Firework Control
Zones and how community requests will be managed was considered. 
Decision 
The Committee agreed to endorse the proposals detailed in the report.

Page 10

(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated 27 October 2023, submitted)