North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref:  CB/JS Date 16/11/22 
P014 Tower Strategy Update 
From  Brian Lafferty, Head of Housing Property & Projects 
Email stevensonjam@northlan.gov.uk Telephone 07583097785 
Executive Summary
The purpose of this report is to update committee on current progress relating to the Tower
Strategy Programme of Work (PO14) and key achievements in the last reporting period. 
Recommendations
It is recommended that Committee: 
(i) Note the progress of the tower demolition programme (Ambition) 
(ii) Note the progress of the sprinkler installation & fire safety programme 
(iii) Note the progress of major refurbishment projects 
The Plan for North Lanarkshire
Priority  Improve the health and wellbeing of our communities
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 2

1. Background 
1.1 Committee will be aware that in 2017 as part of the HRA budget motion, the council
announced its intention to commence consultation with stakeholders regarding the
potential re-provisioning of its tower estate over the next 25 years, with phase 1 of the
re-provisioning programme granted committee approval in May 2018. Significant
progress has been made to date with several high/low-rise blocks now demolished. 
1.2 Committee will also recall that in February 2018, the council approved proposals to
develop and deliver a programme to introduce enhanced fire safety measures within
high-rise towers that included retrofitting of sprinkler systems, improved fire
compartmentation, emergency lighting and installation of fire doors to properties. 
1.3 Following committee approval in 2016 to undertake condition surveys including external
cladding assessment, internal fabric condition and structural integrity, the findings have
now been assessed with a strategic approach to remedial action in line with
government legislation developed.   
2. Report 
2.1 Demolition/Ambition 
2.1.1 The programme is progressing on schedule with 1212 from 1750 properties identified
within phase 1 now vacant. Following extensive negotiation with private owners, only
one now remains in-situ with the council exploring all options for purchase. Detailed
breakdown of the phase one programme as of October 2022 is provided in table 1: 
Table 1
Tower Vacant Properties Status
Northburn Low-Rise, Airdrie 27 (100%) Complete
Holehills, Airdrie 138 (100%) Complete
Burnside Court, Coatbridge 44 (100%) Complete
Gowkthrapple Low-Rise 303 (99%) Tender Period
Shawhead Low-Rise  176 (100%) On Site
Coursington High-Rise 308 (100%) On Site
Jackson High-Rise 181 (94%)  Tender Period
Allershaw High-rise 35 (50%) Design
High Coats / Dunbeth High-rise  Re-programmed
Birkshaw High-rise  Re-programmed           
2.1.2 The contract awarded to demolish 8 low-rise blocks to the south-west of the
Gowkthrapple site (phase 1) has recently been terminated by NLC due to the winning
contractor requesting a significant price uplift from the original tender. The council are
now undertaking a revised procurement exercise comprising all 19 blocks on the site
including the vacant community centre building and surrounding structures. One private
owner remains with negotiations ongoing to conclude purchase of the property however
it is the intention that the contract will proceed with this block excluded from the
contract.

Page 3

2.1.3 The contract to demolish 11no low-rise blocks at Shawhead, Coatbridge is underway
with site establishment complete and works progressing well. Proposals are being
considered to create a new haulage road to alleviate congestion to the surrounding
residential areas. The contract is due for completion in summer 2023.     
2.1.4 Demolition of the three high-rise tower blocks at Coursington, Motherwell has
commenced with site establishment complete and soft strip of internal materials
underway. A series of meetings have been held with nearby residents, informing of the
proposed deconstruction process, timescales and contact details should further
information be required throughout the project. 
2.1.5 Phase 2 of the demolition programme is being evaluated with findings of the structural
investigations, demand analysis and available housing for re-provisioning being
considered. A report will be brought to a future Committee for consideration. 
2.1.6 High Coats and Birkshaw Tower remain part of the phase 1 demolition programme with
proposed dates for demolition to be confirmed in due course. Details of repurposing of
these towers noted under section 2.3.3. 
2.2 Sprinkler / Fire Safety Programme 
2.2.1 Phase 1 of the sprinkler installation programme at Burnside, Lodge & Doonside Tower,
Motherwell has now reached practical completion with snagging works ongoing. 
2.2.2 Phase 2 of the sprinkler installation programme comprising of towers at Glassford,
Woodside, Glen, Coltswood & Redbridge are currently in progress. Tenant consultation
continues outlining the impact of the works and access requirements. 
2.2.3 The fire safety programme which includes installation of emergency lighting, fire-doors
to properties and improved compartmentation/fire-stopping is now complete. In line with
recent change in legislation, interlinked smoke detection has also been installed within
properties. To date, a relatively small amount of non-access properties remain on the
smoke detection programme (circa 23) which are now being progressed as a matter of
urgency via the forced access process. 
2.2.4 A contract to remove all spandrel panels to stairwells in 13 towers (recommendation
following the Grenfell report) is also in progress with completion scheduled for the
current financial year. 
2.3 Major Refurbishment Projects 
2.3.1 Refurbishment of the tower blocks at Blairgrove/Merryston (Lot 1) and Glen/Millbrae
(Lot 2) is nearing completion with external works such as scooter stores, charging
canopies and parking bays progressing. 
2.3.2 Feasibility work is ongoing for the recladding and internal refurbishment of Whifflet and
Calder towers, Coatbridge. A tender exercise to procure specialist consultants to assist
with the design is also underway. 
2.3.3 In order to support displaced citizens affected by the war in Ukraine, North Lanarkshire
Council have committed to reinstate circa 200 properties on a temporary basis. The
properties, located within tower blocks in Coatbridge (High Coats) and Wishaw
(Gowkthrapple) are scheduled to be released on a phased basis over the course of the
refurbishment programme.

Page 4

Birkshaw Tower is now complete with 57no properties reinstated to a high standard,
utilising enhanced fire safety works previously carried out including fire-doors, fire-
stopping, and sprinklers. Properties have also been fully fitted out with furniture and
white goods. 
High Coats Tower (North & South) is progressing well and due for completion in
December 2022. 
3. Measures of success 
3.1 The plans contained within this report will help to improve housing conditions and
housing choice for our residents which contributes to addressing inequality.       
4. Other supporting Documents 
4.1 There are no supporting documents with this report. 
Brian Lafferty                   
Head of Housing Property & Projects

Page 5

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Any financial impact of the measures implemented will be contained within the HRA
Capital Investment budget and will be drawn down via borrowing/CFCR as required
and reported to committee. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☒ No ☐
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Statutory compliance with Building Standards and recent fire safety legislation. 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk

Page 6

Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Upgrading of external building fabric to current energy standards. 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☒ ☐ No ☐
If Yes, please provide a brief summary of the impact? 
Reprovisioning of towers and low-rise blocks must be included in regular corporate
communications. 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
Risks are considered, frequently reviewed and recorded on project-specific risk
registers. Risks with an inherently high score are escalated to project board/service
level.