North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref PH/TM Date 16/11/22 
New Supply Programme - Update on Progress 
Programme of Work – P013 (1) 
From  Pamela Humphries, Head of Planning and Regeneration  
Email  mallaghant@northlan.gov.uk   Email mallaghant@northlan.gov.uk 
1. Background 
1.1 In May 2018 the Committee approved proposals to increase the new supply programme
to deliver 5,000 new homes by 2035.  This was specifically linked to the proposals for
the potential re-provisioning of all tower blocks (4,600 flats) over 20 years.  It was
estimated that around 2,300 new homes (50%) would be built on the sites of the tower
blocks following their demolition.  The target also included an assumption that the
council would purchase around 550 homes through an expanded empty homes
purchase scheme, which had proved popular and had enabled the council to buy back
a number of former council houses.   
Executive Summary
The purpose of this report is to update Committee regarding progress with the delivery of
the new supply programme which aims to deliver 5,000 new homes by 2035.  The report
provides an update on progress against the annual targets previously set; outline some of
the current challenges the programme faces, and seek approval for revised targets. 
Recommendations
It is recommended that the Committee: 
1) Consider the contents of the report regarding progress and challenges with the
delivery of the new supply programme.
2) Approve the proposed targets for delivery of the programme set out in 2.4.1.
3) Note that an update on overall progress with the delivery of the new supply
programme against targets will be reported to committee annually. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 2

1.2 In September 2019 the Committee approved proposals to pilot a proposed
‘Development Pathfinder’ scheme to enable the council to acquire completed housing
units from developers ‘off the shelf’.  The council already acquired units ‘off the shelf’
from developers in the North area where the Affordable Housing Policy applies, but the
committee agreed to extend this approach to the Motherwell, Bellshill, Coatbridge and
Airdrie areas.  It was noted that this could potentially act as a catalyst to enable private
development sites to be brought forward and therefore stimulate investment in these
areas and increase new housing provision.  In November 2020 the Committee
approved proposals to extend the ‘Development Pathfinder’ scheme to cover all of
North Lanarkshire.   
1.3 In November 2021 the Committee received an update on progress with delivery of the
programme and approved targets for the delivery of the programme up to 2035.  It was
also agreed that an annual update would be provided to committee regarding the
delivery of the programme.  This report therefore provides an update on progress to
date against the previous targets; outlines the challenges faced and the proposed
mitigation measures to address these issues and sets out proposed targets for the
coming years.   
1.4 The November 2021 committee also approved an expansion of the Open Market
Purchase Scheme to help facilitate common works by giving the option to the last
remaining owner in a block of flats to sell their flat to the council and remain in their
home as a council tenant. 
2. Report 
2.1 Progress to date 
2.1.1 New Build 
As at 31st October 2022, 970 new build homes have been completed with 421 on site
with 170 new build homes in total expected to complete in 2022/23.  Sites have been
identified and are at various stages of progression for a further 1,346 homes across
North Lanarkshire, including a number of town centre sites and Phase 1 tower re-
provisioning.  The vast majority of the sites are council owned and are brownfield,
which, while bringing their own challenges, also help to support wider place making
and regeneration objectives.   
The new build homes have also provided much needed accommodation for households
affected by disability, including purpose built wheelchair accommodation.  The council’s
specification for its new build homes also includes a higher energy
efficiency/sustainability standard than is required by current Building Regulations. 
Additionally, new build homes are also digitally enabled providing prewired connections
for broadband and Cat 5 Digital cabling to all rooms.    
2.1.2 Open Market Purchase Scheme 
As at 31st October 2022, 589 homes had been purchased through the Empty Homes
and Open Market Purchase Scheme to date.  The Open Market Purchase Scheme
(OMPS) has proven to be very popular and is providing much needed
accommodation to meet identified local need, while also enabling common works to
be progressed where the purchase of flats is providing full or majority ownership of
blocks of flats.  The OMPS also represents good value for money with an average
purchase and repair cost in 2022/23 of £83,698.  The number of applications for the

Page 3

programme has been lower so far this year compared to other years and more in line
with 2021/22.   Taking account of this, it is therefore projected that this year
approximately 50 homes will be purchased.  This is directly linked to the heated
housing market at present where homeowners in this sector of the market are able to
sell their homes at a value higher than the home report valuation quickly in the open
market and has badly affected the number of applicants for the programme.   The
market conditions have now been taken into account for the amended projections. 
The projections also account for the recent expansions of the scheme to allow in
some cases the final owners in blocks to sell their homes to the Council and remain
as tenants and for the purchase of homes from private landlords to ensure tenants do
not become homeless.  There has been an increase in enquiries from Landlords and
it is expected that the numbers will grow over time for this category. 
2.1.3 Off the shelf purchases (Affordable Housing Policy sites) 
There have been 78 homes purchased from private developers in the North as part of
their Affordable Housing Policy planning obligation, with a further 100 acquisitions in
the pipeline. In addition, 39 homes have been purchased from developers in
Ravenscraig.  These acquisitions continue to represent good value for money and are
a good option to help deliver much needed housing in an area of high demand.   
2.1.4 Development Pathfinder 
Work is now underway at the former John Orrs Building in Airdrie following
completion of demolition works and the acquisition of 20 flats on completion is
scheduled for 2023/24.  In addition, the committee has approved the acquisition of 39
homes at the former DWP Building at South Circular Road in Coatbridge and 24
homes at Lorne Place, Coatbridge. Both projects have planning permission and work
is due to commence following completion of missives. There have been further
enquiries from developers for potential projects throughout North Lanarkshire, with
every site being assessed on its merits.
2.2 Current challenges impacting on programme 
2.2.1 Availability/suitability of sites 
The availability of suitable sites, in areas where there is a demonstrable need for
housing remains a challenge.  The majority of council owned sites are brownfield sites,
the development of which help support sustainable communities and meet localised
need, but can be problematic, and in some cases unviable, to develop.     
Approximately half of the current programme assumptions were based on the re-
development of sites following demolition of the tower blocks.  It was always
acknowledged that these assumptions would be subject to on-going review to reflect
the timescales for the availability of the sites, and the proposed mix/ capacity of each
site.  It is likely that the density of replacement housing will be lower than 50% and
therefore alternative sites will require to be identified to support delivery of the
programme.  The council’s wider Ambition programme, including asset rationalisation
and town/community hub programmes will also result in sites (including school sites)
being released that may be suitable for the new supply programme.  Furthermore, any
sites being declared surplus by the council are assessed for their viability and there are
a number of town centre sites that have been identified that will be progressed as part
of the new supply programme.

Page 4

2.2.2 Scottish Water Drainage Policy 
As previously reported to committee in November 2020 and November 2021 Scottish
Water had been strictly enforcing their policy whereby developers must retain as much
surface water as possible within the site or connect directly to a surface water sewer or
directly to a water course.  Scottish Water have recently amended how they apply their
policy to allow more flexibility in assessing applications to connect to a combined sewer
if certain criteria showing betterment can be met by the applicant.   At present there are
now three sites being affected by this policy with an estimated additional cost to the
Council of £1.4million to be able to connect to Scottish Water systems. 
2.2.3 Procurement/ contractor capacity 
Due to the level of development activity in recent years by councils and housing
associations, as well as a healthy private sector market there are ongoing issues with
contractor capacity and availability of labour.  This combined with impacts of Brexit and
the ongoing war in Ukraine upon supply chains has also impacted on tender prices. 
The council has used every available procurement method from direct award and mini
competition through frameworks to open tender procedures and all approaches have
shown a significant increase in tender bid prices.  The procurement process itself is
also lengthy and resource intensive.  The council will continue to utilise available
frameworks including the Scotland Excel new build framework and the Scottish
Procurement Alliance (SPA) new build frameworks.   
2.3 Costs 
2.3.1 As outlined above the cost of the new build homes has increased significantly in recent
years.  The tender cost increases over the past 12 months are on average 16% to 20%
and this trend of tender price increases will extend into 2023. Comparing similar sized
projects the tender costs over past 18 months are on average 25% higher.   This is due
to a number of factors including ground remediation/ infrastructure costs; contractor
capacity/ shortage of skilled labour, scarcity of materials due to various reasons such
as the ongoing war in Ukraine and increased standards/specifications.  This has been
further exacerbated by high inflation this year of circa 10%.  The Building Costs
Information Service (BCIS) has reported that the housing construction price index is
showing a cost increase of 15.3% over the year from Quarter 2 in 2021.  They are also
indicating a further increase of 3.3% over quarter 3 of 2022/23.  At the end of 2021
BCIS reported that annual growth in material costs was at a 40-year high and since
then the pressures have become even more acute 
2.3.2 There are changes to legislation that have had an impact on the cost of the new build
homes, including: 
• From 2024 new build homes cannot be powered by gas and will require an
alternative heating system.  Alternative options, including a fabric first thermal
efficiency approach and the use of air source heat pumps combined with PV Cells
and battery storage are currently being piloted and evaluated to assess the most
cost effective options for the future, both in terms of installation; maintenance and,
crucially running costs.  There will inevitably be an increased construction cost per
unit which is currently costed at £20,000 and is rising with inflation. 
• Legislation has been in place as of March 2021 to make it a requirement that all
new build social rented homes will require to have a sprinkler fitted, at an average
cost of £4,000 per property which is also rising with inflation.

Page 5

2.3.3 The increased costs associated with the delivery of the new build programme will
continue to be factored in to the HRA 30 Year Business Plan, along with the most up
to date assumptions around availability of Scottish Government grant including the
recently increased level of grant funding for councils.  It is also hoped tender costs will
stabilise and plateau in the medium to longer term.  In the meantime progressing
acquisitions through off the shelf purchases and the open market purchase scheme will
continue to offer good value options to augment the traditional new build programme
and deliver new supply to meet housing need.
2.4 Programme Targets 
2.4.1 The new supply programme is continually monitored, reviewed and updated but as it
currently comprises over 30 approved sites, with further sites still to be identified, it is
difficult to establish accurate long term annual targets.  In addition, the ‘off the shelf’
acquisitions are difficult to forecast as they are reliant on the private developers’
delivery programmes which are out-with the control of the council.  The current
estimated targets for the current year and each of the next three years is set out in
Table 1 below, as well as the balance to be delivered by 2035.  
Table 1 New Supply Projections as at November 2022 
2.5 The targets for 2021/22 were not met mainly due to the following reasons that are
carrying forward into this year: 
• Difficulties with supply of materials and labour which impacted on completion dates
resulting in handovers being delayed.  This has been partially due to COVID having
an impact on labour availability at the early part of the year but mainly due to the
reasons detailed in 2.3.1 which has also increased costs.
• The heated housing market affecting the purchase of homes through the OMPS
as detailed in 2.1.2 and a slower than projected uptake to date of the option for the
last owner in a block to sell their home to the council and remain as a tenant.   
New Build New
Build
Council Off the
Shelf
2021/22 137 0 75 212 305
2022/23 170 0 50 220 413
2023/24 226 50 75 351 631
2024/25 261 87 100 448 407
2025/26 299 34 100 433 333
2026 - 2035 989 315 750 2054 2335
Total 2082 486 1150 3718 4424
Completions
(to March 2021)
Grand total 2762 603 1635 5000
Year OMPS (incl.
targeted
extension)
Total
680 117 485 1282
Approved
Targets
November
2021

Page 6

2.6 The projections this year have been adjusted in relation to the revised delivery
timescales provided by contractors reflecting the availability of labour and materials to
deliver each of the current projects.  The variance between the projected completions
in 2022/23 and the actual anticipated completions is mainly due to the following
reasons: 
• Difficulties with supply of materials which impacted on completion dates
resulting in handovers being delayed.  This has been a factor throughout the
construction industry as a whole with steel and timber being particularly affected
as detailed in 2.3.1.  This has also led to very high tender prices which have
required some projects to be retendered resulting in delays to the
commencement of those projects.
• The heated housing market affecting the purchase of homes through the OMPS
as detailed in 2.1.2. and a slower than projected uptake to date of the option for
the last owner in a block to sell their home to the council and remain as a tenant.  
• Projected acquisitions of off the shelf homes from developers not progressing
as projected with significant delays in the works at the former John Orr’s building
due to supply of materials and labour as well as the site at Lorne Place,
Coatbridge being delayed due to issues with securing connections to the
Scottish Water drainage system.
2.7 The delivery of the new supply programme will be closely monitored, and regular
updates reported to committee, including an annual update on progress against targets
and any adjustments to the programme that may be required 
3. Measures of success 
3.1  The measure of success will be the cost-effective delivery of the council’s new supply
programme which aims to deliver 5,000 homes by 2035 
3.2 The New Supply programme will also contribute to the regeneration of the town centres
within North Lanarkshire which is one of the main priorities within the council’s
Economic Regeneration Delivery Plan 
4. Supporting documentation 
Appendix 1 New Build Sites as at 27 September 2022   
Pamela Humphries
Head of Planning & Regeneration

Page 7

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The development of new affordable housing contributes to reducing inequalities
through the provision of good quality, energy efficient and accessible homes to meet
housing need. 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☒ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The cost of the new build programme has been increasing, and is now on average
around £190,000 per unit and can be higher on some more challenging sites,
including town centre projects. 
The new supply programme is funded through a combination of Prudential
Borrowing, Capital Funded from Current Revenue (CFCR), Scottish Government
Funding and Subsidy Income. The affordability of both the new build programme and
OMPS are reviewed each year and incorporated into the 30 year business plan. The
Scottish  Government’s new baseline benchmark assumptions have increased from
£57,000 to £71,500 per unit (base on 3 person equivalent as well as additional grant
funding available for additional quality measures benchmarks. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact?

Page 8

5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☒
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
In terms of the environmental impact, the New Supply Programme has been
considered through the Strategic Environmental Assessment (SEA) as required by
The Environmental Assessment (Scotland) Act 2005 and there are no major issues of
relevance identified.   
The new homes will be built to modern standards and as a result be more energy
efficient contributing to the reduction in CO2 emissions. 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact?
The implementation and delivery of the New Supply programme will be promoted
through the New Supply PR plan in conjunction with Corporate Communications,
and via communications with Local Members and local stakeholders 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed?

Page 9

Risk associated with the New Supply Programme is managed within the New Supply
Risk Register process.  The risk register has been updated to reflect the impact of the
current national issues affecting the costs and availability of materials and labour along
with general high inflation on programme timescales and costs  as well as how the risk
to the council will be mitigated as far as possible.  The council will also undertake
detailed ground investigation and other relevant site assessments prior to proceeding
with the development of any particular site to help mitigate the risk of unforeseen costs
relating to ground conditions, although this risk cannot be eliminated entirely.

Page 10

Appendix 1   New Build Sites as at 31 October 2022 
Area Location Units Comments
Completed Holytown Main St 10 Completed (Amenity)
Holytown Spruce Way 10 Completed
Motherwell Ravenscraig (David Wilson
Homes)
18 Completed (off the
shelf)
Airdrie Clarkston PS 19 Completed
Millerston Coshneuk Rd 11 Completed (Amenity)
Cumbernauld North Rd 29 Completed
Wishaw Cambusnethan PS 20 Completed (Amenity)
Viewpark Laburnum Rd (Phase 1) 12 Completed
Viewpark Laburnum Rd (Phase 2) 28 Completed
Moodiesburn Gartferry Road 50 Completed
Cumbernauld Westfield Drive 30 Completed 
Airdrie Former Albert PS 14 Completed
Chryston Lanrig Rd 27 Completed (Amenity)
Coatbridge Corsewall St 14 Completed
Bellshill Former Belvidere PS 20 Completed
Kilsyth Fisher Ave 30 Completed
Chryston Old Lindsaybeg Rd
(Persimmon)
14 Completed (off the
shelf)
Motherwell Glencairn Tower site 25 Completed
Viewpark Former Tannochside PS 16 Completed
Wishaw Walkerburn Dr, Coltness 20 Completed
Cumbernauld Cardowan Drive 30 Completed
Cumbernauld Kildrum Nursery 16 Completed
Chryston Station Rd (Persimmon) 30 Completed (off the
shelf)
Chapelhall Former St Aloysius PS
(Phase 1)
24 Completed
Chapelhall Former St Aloysius PS
(Phase 2)
6 Completed
Cumbernauld Brown Road 20 Completed
New Stevenston Former New Stevenston PS 15 Completed
Chryston Greenlea Road 21 Completed
Coatbridge Old School Court 20 Completed
Airdrie Former Alexandra PS 14 Completed
Harthill Former Harthill PS 20 Completed
Motherwell Cleekhimmin, Ravenscraig
(Barratt)
10 Completed (off the
shelf)
Coatbridge Blair Road 40 Completed
Motherwell Calder PS 30 Completed

Page 11

Gartcosh Johnston Rd / Inchnock
Ave (Bellway)
16 Completed (off the
shelf)
Cumbernauld Cedar Road Nursery 14 Completed
Chryston Main Street (Bellway) 18 Completed (off the
shelf)
Wishaw Meadowhead Rd,
Ravenscraig (Keepmoat)
11 Completed (off the
shelf)
Bellshill Caledonian Avenue (Phase
1 )
19 Completed
Wishaw Dimsdale Road (Phase 1) 6 Completed
Bellshill  Caledonian Avenue (Phase
2) 
8 Completed
Wishaw  Dimsdale Road  (Further
Phases)
55 Completed
Coatbridge  St James PS / Lismore
Drive
58 Completed
Wishaw Roberts Street (Belhaven
House)
16 Completed
Wishaw Mossburn St, Waterloo 20 Completed
Plains Plains PS 16 Completed
Sub total   970 Completed
On Site  Chryston  Chilterns Care Home 21 On Site 
Airdrie Dykehead Road (Holehills) 150 On Site
Airdrie Northburn Place 31 On Site
Bellshill Community Road 29 On Site
Airdrie  Former Orrs Building
(Wilson)
20 On Site
Wishaw Castlehill Road,
Gowkthrapple (Phase 1) 
97 On Site
Coatbridge Berwick St 19 On Site
Stepps Gateside Farm (Barratt) 30 On Site
Motherwell Former BRE, Ravenscliff
Rd, Ravenscraig
24 On site
Sub total   421 On site
Design
Development
Underway
Cumbernauld Community Growth Area 75 Planning app
submitted
Motherwell Mabel Street 20 Planning app approved 
Glenmavis McArthur Ave 21 Planning app approved
Coatbridge Columba High School 130 Design development
underway
Viewpark Laburnum Rd 26 Planning app approved
Coatbridge Bank Street 9 Planning app approved
Airdrie Glenacre Drive 16 Planning app approved
Chapelhall Gibb Street 25 Planning app
submitted

Page 12

Wishaw Graham Street 13 Planning app
submitted
Coatbridge Kildonan Street 49 Design development
underway
Cumbernauld Former Cumbernauld
Village PS
8 Planning app approved
Glenboig Former Police Station,
Main Street
7 Planning app approved
Motherwell Brandon Street 48 Planning app approved
Wishaw King Street 5 Planning app
submitted
Wishaw Stewarton Street & Kings
House
17 Design development
underway
Motherwell Former Motherwell Town
Hall
20 Planning app approved
Airdrie Calderigg Place  42 Design development
underway
Airdrie  Former Petersburn PS  40 Planning app approved
Millerston Coshneuk Road 16 Approved at
Committee - Sept 2021
Wishaw  Caledonian Road  9 Planning app
submitted 
Coatbridge  Mitchell Street 100 Approved at
Committee - Aug 2022
Caldercruix  Former St Mary's PS  25 Approved at
Committee - Aug 2022
Bellshill Thorn Road  26 Approved at
Committee - Aug 2022
Airdrie  Airdriehill Road  75 Approved at
Committee - Aug 2022
Motherwell  Hope Street (Masonic Hall) 10 Approved at
Committee - Aug 2022
Coatbridge  Main Street  40 Approved at
Committee - Aug 2022
Sub total   872 Design development
underway
Re-
provisioning
Coatbridge Shawhead 111 Re-provisioning site
Coatbridge Dunbeth  170 Re-provisioning site
Motherwell Coursington 60 Re-provisioning site
Sub total   341 Re-provisioning sites
Off The Shelf Chryston Gartferry Road
(Allanwater)
22 Off the shelf                                   
Purchase approved at
Committee

Page 13

Coatbridge  Lorne Place (Allanwater)  24 Off the shelf 
Purchase approved at
Committee
Moodiesburn Auchengeich, Gartferry
Road (Bellway)
12 Off the shelf 
Purchase approved at
Committee
Cumbernauld Kingfisher, Dowanfield
Road (Zoom)
24 Off the shelf
Purchase approved at
Committee
Coatbridge 
Former DWP Offices,
South Circular Road (ML5
Limited)
39 Off the shelf
Purchase approved at
Committee
Gartcosh  Johnston Rd - Phase 2
(Bellway)
12 Off the shelf
Purchase approved at
Committee
Sub total   133 Future off the shelf
purchases from
developers  
Total    2737