Page 1

North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☒ Yes ☐ No
Ref PH/TM Date 16/11/22 
New Housing Supply Programme – Procurement Report 
From  Pamela Humphries, Head of Planning and Regeneration 
E-mail mallaghant@northlan.gov.uk Telephone
Tony Mallaghan, Housing
Development Manager,
07970 016251 
Executive Summary 
The purpose of this report is to update the Committee on current procurement activity
relating to the new build housing programme and seek approval to progress procurement
arrangements as outlined in the report. 
Recommendations 
It is recommended that the Housing Committee: 
1) Approve the procurement of call off contracts in line with the Scotland Excel New
Build Residential Framework for: 
a) the construction of new build housing at Dunnottar Avenue and Burleigh Place,
Shawhead, Coatbridge up to the value of £26.50M, including contingency
allowance; and; 
b) the conversion and refurbishment of the former Masonic Hall, Hope Street,
Motherwell up to the value of £3.00M, including contingency allowance. 
2) Approve the procurement of call off contracts in line with the Scottish Procurement
Alliance (SPA) H2 framework agreement conditions for the construction of new build
housing at: 
a) the former St Marys Primary School, Hill Street, Caldercruix up to the value of
£6.50M, including contingency allowance. 
b) the former Thornlie Church halls, Caledonian Road, Wishaw up to the value of
£1.50M, including contingency allowance. 
c) Airdriehill Road, Airdrie up to the value of £16.90M, including contingency
allowance. 
d) The former Cumbernauld village school, Glasgow Road, Cumbernauld up to
the value of £2.00M, including contingency allowance.

Page 2

1. Background 
1.1 The Council has an approved target to deliver 5,000 new homes by 2035. The delivery
of such a large scale programme presents a number of challenges, not least of which
is the procurement of contractors to build the houses to the required standard, within
the timescale required and at a competitive cost. In order to increase the pace of
delivery, secure best value and minimise risk to the Council, a range of procurement
options have been utilised. 
1.2 The Council has also participated in the establishment of a new build framework
agreement through Scotland Excel, which has been available for use from August
2019. This framework agreement is for the delivery of new build housing projects for
Scottish local authorities, housing associations and other public bodies and includes a
number of lots covering different geographical areas and different sized developments. 
1.3 The Housing and Regeneration Committee on the 25 November 2020 approved the
procurement route for the next phase of the new build programme to commence
procurement activity with the Scottish Procurement Alliance (SPA) and Scotland Excel
New Build Residential framework to deliver the next phase of new build sites approved
by the Committee. As reported at the Housing and Regeneration Committee on the 8
September 2021, due to the current capacity issues in the market we intend to utilise
the ability in the SPA and Scotland Excel Frameworks to direct award to available
contractors, including to contractors who are not highest ranking. Justification for the
identification of a contractor can be made by complying with the direct award criteria
listed in the respective frameworks, with a contract award being subject to value for      
3) Approve the procurement of call off contracts in line with the Scottish Procurement
Alliance (SPA) PB3 framework agreement conditions for the conversion and
refurbishment of Old Motherwell Town Hall, Hamilton Road, Motherwell up to the
value of £5.500M, including contingency allowance. 
4) Approve the award of a call off contract in line with the Scotland Excel New Build
Residential Framework for the construction of new build housing to McTaggart
Construction at the former Petersburn PS, Petersburn Road, Airdrie, up to the value
of £9.40M, including contingency allowance. 
5) Note the award of a call off contract in line with the Scotland Excel New Build
Residential Framework for the construction of new build housing to CCG (Scotland)
Limited at Ravenscliff Road, Motherwell up to the revised value of £5.75M, including
contingency allowance. 
6)  Note the award of a call off contract in line with the Scotland Excel New Build
Residential Framework for the construction of new build housing to McTaggart
Construction at Glenacre Drive, Airdrie, up to the value of £3.726M, including
contingency allowance. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 3

money assessment against the framework rates. A benchmarking appraisal was
carried out for each project and is identified in each project’s Sourcing Methodology. 
2. Report 
2.1 It is proposed to engage with contractors on the Scotland Excel New Build Residential
Framework for the following two projects: 
• Dunnottar Avenue and Burleigh Place, Shawhead, Coatbridge (Up to 102 units) up
to the value of £26.50M, including contingency allowance. 
• Former Masonic Hall, Hope Street, Motherwell (Up to 10 units) up to the value of
£3.00M, including contingency allowance. 
Feasibility costs will be obtained and analysed to ensure best value and, subject to
benchmarking against the appropriate framework rates, it is proposed that a final tender
price be agreed to allow the contract award. 
2.2 It is proposed to engage with contractors on the SPA H2 framework for the following
three projects: 
• Former St Marys Primary School, Hill Street, Caldercruix (Up to 25 units) up to the
value of £6.50M, including contingency allowance. 
• Thornlie Church halls, Caledonian Road, Wishaw (Up to 6 units) up to the value of
£1.50M, including contingency allowance. 
• Airdriehill, Airdriehill Road, Airdrie (Up to 65 units) up to the value of £16.90M,
including contingency allowance. 
• The former Cumbernauld village school, Glasgow Road, Cumbernauld (up to 8
units) up to the value of £2.00M, including contingency allowance. 
Feasibility costs will be obtained and analysed to ensure best value and, subject to
benchmarking against the appropriate framework rates, it is proposed that a final tender
price be agreed to allow the contract award. 
2.3 It is proposed to engage with contractors on the SPA PB3 framework for the following
project: 
• Old Motherwell Town Hall, Hamilton Road, Motherwell (Up to 20 units) up to the
value of £5.500M, including contingency allowance. 
Feasibility costs will be obtained and analysed to ensure best value and, subject to
benchmarking against the appropriate framework rates, it is proposed that a final tender
price be agreed to allow the contract award. 
2.4 The Housing and Regeneration Committee in November 2021 approved the
procurement of a call off contract in line with the Scotland Excel New Build Residential
Framework for the construction of new build housing by McTaggart Construction at the
former Petersburn PS site, Petersburn Road, Airdrie, (40 units), up to the value of

Page 4

£8,290M, including contingency allowance. McTaggart Construction have submitted a
revised cost of £9.40M, including contingency allowance. The tender cost obtained is
considered to represent best value and, and the rates have been benchmarked against
the appropriate framework rates with an allowance for current market conditions, to
allow the contract award to be made. 
2.5  The Housing Committee in August 2022 approved the award of a call off contract in
line with the Scotland Excel New Build Residential Framework for the construction of
new build housing to CCG (Scotland) Limited at Ravenscliff Road, Motherwell, (24
units), up to the value of £5.40M, including contingency allowance. However due to
delays with concluding the site acquisition the tender cost has increased to £5.75M,
including contingency allowance. The tender cost obtained is still considered to
represent best value and, and the rates have been benchmarked against the
appropriate framework rates with an allowance for current market conditions, to allow
the contract award to be made. 
2.6 The Housing Committee in August 2022 approved the award of a call off contract in
line with the Scotland Excel New Build Residential Framework for the construction of
new build housing to McTaggart Construction at Glenacre Drive, Airdrie, (Up to 16
units), up to the value of £3.555M, including 10% contingency allowance. McTaggart
Construction have submitted a revised cost of £3.726M, including contingency
allowance.  The tender cost obtained was considered to represent best value and, and
the rates have been benchmarked against the appropriate framework rates with an
allowance for current market conditions, to allow the contract award to be made. 
2.7 The approval to commence procurement for the site at Airdriehill Road, Airdrie is being
sought to evaluate the site for the construction of new build housing for up to 65 units.
The site is not in council ownership but already has obtained planning approval for
approximately 50 units. The evaluation being undertaken is at no risk or cost to the
council and will include site suitability and feasibility costs. Should the site be
considered a viable option the site will be brought to a future committee to seek
approval to progress with site acquisition and tender award. 
Next Steps 
2.8 The next batch of sites will be reviewed, and a suitable procurement route will be
identified to progress these projects to deliver new build housing to align with the Plan
for North Lanarkshire. 
Price Savings / Increases 
2.9 There are no cashable savings attributed to the contracts outlined within this report. 
Price Stability 
2.10 The pricing mechanism is a Priced Contract with Activity Schedule offering a good level
of cost certainty. 
Community Benefits 
2.11 The Council is committed to maximising the delivery of community benefits. The
procurement included a community benefit requirement, this approach is designed to
deliver local community benefits where possible.

Page 5

The successful tenderer for contracts recommended for award within this report have
committed to delivering a range of community benefits and these are detailed in the
table below:
Petersburn Road, Airdrie 
OUTCOME  No of Mandatory
Outcomes
New Sustainable Jobs for entrants
from Key Priority Groups
3
Work Experience Placement (16+
Years of Age)
8
Careers Event 5
Supply Chain briefing with SMEs 3
Financial Support for a Community
Project
2
Non Financial Support for a
Community Project
4
TOTAL 25 
Fair Work Practices 
2.12 All contractors appointed to the SPA and Scotland Excel frameworks have evidenced
Fair Work Practices within their organisations as part of the procurement procedures
to be appointed to the respective frameworks and have further demonstrated how they
will promote them in the delivery of Council call-off contracts. 
Contract Strategy 
2.13 Officers from New Supply will be responsible for managing contracts which will be
undertaken in accordance with the council’s agreed approach to contract and supplier
management. 
3. Measures of success 
3.1  The proposed contract awards detailed within this report will deliver the following
outcomes: 
a) The appointment of contractors who have the experience and capability to deliver
new build social housing; 
b) The procurement procedure is compliant with the procurement legislation and
internal procedures; 
c) That best value is both demonstrable and achieved; 
d) That the contracts secures a range of community benefits;

Page 6

e) That the contract supports a variety of fair working practices to staff employed in
the delivery of the contracts; 
f) That the performance of contracts are proactively managed against a number of
Key Performance Indicators.     
4. Supporting documentation 
Appendix 1 Summary of Procurement Procedures
Appendix 2 SME Status of all Tenderers 
Pamela Humphries 
Head of Planning and Regeneration

Page 7

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The Council’s new build programme helps reduce inequalities through a number of
design specifications including: 
• Housing for Varying Needs;
• Secure by Design;
• Achieving the Scottish Government requirements for “Greener Homes” to
reduce the incidence of fuel Poverty; and
• The inclusion of design standards relating to access to internet capabilities
including ‘fibre to the property’. 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☒ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The funding for all of the projects referred to in this report can be met from the
Council’s Housing Revenue Account budget for the New Supply Programme. Grant
support is also provided by the Scottish Government. The costs associated with
contract delivery will be contained within the New Supply budget. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☒ No ☐
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☒ No ☐ 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact?

Page 8

5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data? 
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☒
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☒
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The proposed award of contracts detailed within this report will ensure that the impact
on the Council’s carbon footprint is mitigated. The specifications incorporated within
the contract documentation will: deliver reduced energy need; encourage sustainable
construction; promote health and wellbeing; reduce waste and resources through
effective storage, collection and composting of waste and recyclable materials and;
include measures which will reduce CO2 emissions. 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The implementation and delivery of the New Supply programme will be promoted
through the New Supply PR plan and via communications with elected members and
local stakeholders 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed?

Page 9

Risk associated with the New Supply Programme is managed within the New Supply
Risk Register process. The risk register has been updated to reflect the impact of the
current national issues affecting the costs and availability of materials and labour along
with general high inflation on programme timescales and costs as well as how the risk
to the council will be mitigated as far as possible. The tender cost increases over the
past 12 months are on average 16% to 20% and this trend of tender price increases
will extend into 2023 excluding the additional changes to legislation and meeting
Scottish Government energy targets. Comparing similar sized projects the tender
costs over past 18 months are on average 25% higher. The council will also undertake
detailed ground investigation and other relevant site assessments prior to proceeding
with the development of any particular site to help mitigate the risk of unforeseen costs
relating to ground conditions, although this risk cannot be eliminated entirely.

Page 10

Appendix 1 Summary of Procurement Procedures 
Construction of New Build Social Housing at Petersburn Road, Airdrie 
Procurement Title Contractor Design and Construction of New Build Social 
Housing at Petersburn Road, Airdrie
Estimated contract start date January 2023 – April 2024
Initial Contract Period  15 Months
Contract Defects Period  12 Months
Estimated Total Contract value £9,395,545 (£8,945,545 + £450,000)
Contract Reference Number NLC-SLP-22-066.
Contract Notice Reference Not Applicable
Date Contract Notice Published  Not Applicable
Governing UK Regulation Public Procurement Regulations (Scotland) 2015 
Procurement Procedure  Direct Award from a 3rd Party Framework
Evaluation approach adopted Not Applicable
Interest List – number of
Contractors that downloaded the
procurement documents from the
procurement portal
N/A
Number of selection stage
documents received N/A
Number of Contractors invited to
tender 1
Number of tenders received  1
Number of non-compliant tenders 0
Number of compliant tenders 1
Number of recommended
contractors 1
Basis of contract award Quality 40% Price 60%
Evaluation team names and job
titles of Evaluators and their role
in evaluation
New Supply

Page 11

Appendix 2 SME Status of all Tenderers 
Project Tenderers Name
Size of Tendering
Organisation
(Micro, Small,
Medium or Large)
Location
(Local
Authority /
Council
Area)
Petersburn Road, Airdrie McTaggart
Construction Medium North
Ayrshire