Page 1

North Lanarkshire Council
Report
Housing  Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref PH/TM Date 16/11/22 
Future Approaches to Heating Within New-Build Homes 
From  Pamela Humphries, Head of Planning and Regeneration  
E-mail mallaghant@northlan.gov.uk Telephone
Tony Mallaghan, Housing
Development Manager
07970 016251 
Executive Summary 
This report requests that the Committee consider and approve a new approach to
providing space and water heating to new-build homes, which complies with the Scottish
Government’s Heat in Buildings Strategy, published October 2021. 
The expectation of the Heat in Buildings Strategy is that emissions of greenhouse gases
from heating our homes and buildings will have all but disappeared by 2045.  This requires
energy demands to be greatly reduced, and space and water heating to be provided by
zero emissions heating systems. 
In the short to medium term, this report proposes that heat pumps are used in place of gas
combination boilers to provide space and water heating to new-build homes and to
conversions of older buildings to social housing.  To mitigate the possibility of fuel poverty,
this report proposes that large PV arrays coupled with energy storage (hot water tanks
and/or batteries) are provided to each property. 
In the medium to long term, this report proposes that newer technologies including heat
networks and hydrogen fuel should be examined as more information and evidence
becomes available. 
The current energy price increases are noted as a significant barrier to the successful
implementation of zero emissions heating systems. 
Recommendations
It is recommended that Committee: 
1) Approve the approach to heating new-build homes and conversions as outlined
within section 2 of the report. 
2) Note that future options to deliver energy efficient homes will continue to be
explored as set out in the report.

Page 2

1. Background 
1.1 The key milestones below are discussed in the Heat in Buildings Strategy to reduce
greenhouse gas emissions from Scotland’s homes, workplaces and community
buildings. 
https://www.gov.scot/publications/heat-buildings-strategy-achieving-net-zero-
emissions-scotlands-buildings/ 
Date Milestone
2024 Low or zero emissions heating systems1 required to all New Build Homes. 
This means that gas boilers will no longer be permitted in Building Warrant applications
submitted after 01/04/2024.   
2030 75% reduction in greenhouse gas emissions for heating our homes and buildings2 
2032 All social housing to achieve an Energy Efficiency Rating of Band B by the end of
December 2032 3 
2040 90% reduction in greenhouse gas emissions for heating our homes and buildings2 
2040 <5% households in fuel poverty (in 2015 prices) 4 
2040 <1% households in extreme fuel poverty (in 2015 prices) 4 
2045 Net Zero Greenhouse gas emissions for heating our homes and buildings 
Notes
1 Low and zero emission heating systems are systems that have zero direct greenhouse gas emissions,
such as individual electric heat pumps and connection to heat networks, or electric systems such as
storage heaters, and systems that have very low emissions such as those that use hydrogen. 
2 The Climate Change (Emissions Reduction Targets) (Scotland) Act 2019 
3 Energy Efficiency Standard for Social Housing (EESSH2).  NLC New Build Housing Specification
already exceeds this target 
4 The Fuel Poverty (Targets, Definitions and Strategy) (Scotland) Act 2019  
1.2 Currently, 88% of the council’s housing stock is heated using gas, compared with 80%
across Scotland.  11% are heated using electricity which is comparable to the rest of
Scotland. 
1.3 Details relating to the requirement for non-gas heating from 2024 and the proposed
pilot to examine and evaluate the use of an alternative to gas heating was reported to
the Housing and Regeneration Committee on 25 November 2020.   
The Plan for North Lanarkshire
Priority  Improve the health and wellbeing of our communities
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 3

2. Report  
2.1 The challenges of meeting the requirements of the Heat in Buildings Strategy
whilst keeping rents and heating bills affordable are discussed in The Scottish
Government Zero Emissions Social Housing Taskforce Report (August 2021). 
This report recommends a Just Transition including the need for social landlords
to:- 
• Mitigate against potential negative impacts for social tenants and
maximise potential opportunities such as jobs. 
• Promote a Fabric First approach as an essential step towards
decarbonisation. 
• Continue to evaluate their wider impacts and on-going contribution to
tackling the climate emergency, through systematic monitoring and
measurement. 
2.3  An options appraisal has been carried out to consider various options for zero emission
heating systems that could be used in new homes for social rent.  The options (set out
in table 1) include Air source pumps, electric storage heating and electric wet combi
boiler systems.  In each option, it is proposed that a PV array and battery storage are
provided to help offset the higher unit costs for electricity, and to mitigate the risk of fuel
poverty.  It should be noted that the combined cost of installing the new technologies
is around £15,000 higher per unit than the current specification.   
The preferred option is to use heat pumps because it is a proven technology in
Scotland; the extremely high efficiency will minimise energy consumption, and because
it will provide significantly lower running costs for the tenants given current costs of fuel. 
Ground source heat pumps (shared boreholes and small individual heat pumps within
homes), are expected to significantly outperform air source heat pumps in terms of
efficiency and running costs, but are not suitable in as many sites.  The viability of
ground source heat pumps is currently being investigated. 
Table 1 Space and Water Heating Options Appraisal 
Typical Capital, Maintenance and Operational Costs 
Heating Type Capital cost per
home
(Supply and Install
exc VAT)
Annual revenue
cost per home
(Annual
maintenance and
servicing)
Annual net utility
cost
Baseline
Gas Combination
Boiler Radiators &
Pipework
4kW PV array to
houses, 2kW to
cottage flats 
£8,800 £224.67 £1404 - £1974

Page 4

Option A
Air Source Heat Pump
Hot Water Tank
Radiators & Pipework
4kW PV array 
13.5kW Battery 
£23,700 £135.19 £612-£886
Option B
Storage Heating  
Elec Hot Water Tank 
4kW PV array
13.5kW Battery
£21,815  £125.90 £1382 -£1757
Option C
Electric Wet Combi
Boiler
Radiators & pipework
4kW PV array
13.5 kW Battery
£21,580  £125.90 £2184 -£2838 
2.4 Future Options that will be considered include thermal batteries, mechanical heat
recovery and ventilation, solar thermal panels, hydrogen ready boilers, and heat
networks.   
2.5 The Scottish Government announced the Heat Network Fund in February 2021.  This
is a fund of over £300million over this parliamentary session to support development
and rollout of zero emission heat networks across Scotland.  The use of communal
heating systems using air or ground source heat pumps for flatted developments may
be eligible for this fund.   
2.6  A pilot project for net zero emission heating is currently under construction at Dykehead
Road, Airdrie.  The first properties are due to hand over towards the end of 2022. 
This pilot project consists of 19 properties (out of a site total of 150 properties) being
built with the following additions to our standard New Build specification:-   
• Air Source Heat Pumps and Hot Water Cylinder in place of a gas combi
boiler;
• Extra 25mm insulation to external walls;
• Extra 50m insulation to loft spaces; 
• Triple glazed windows;
• 4kW PV array (13 panels); and
• 13.5kW battery storage. 
Data and tenant feedback will be collected from both the net zero homes and the
properties heated by gas combination boilers.  This will allow the council to assess the
performance and future viability of these proposals, with particular cognisance of the
current energy price increases, to help inform future investment decisions. 
2.7 It is proposed that the approach for achieving  low/ zero emissions  for space and water
heating systems to both new-build and regeneration / redevelopment projects should
be as outlined below:- 
▪ Continue to implement the Fabric First approach which will be reviewed and
amended as appropriate to focus on reduced energy consumption.

Page 5

▪ Make use of both air and ground source heat pumps (as appropriate to the
development) as the principal approach to an alternative to gas heating within new-
build and redevelopment projects. 
▪ Make use of appropriate supporting technologies, primarily Solar PV and energy
storage (hot water tanks, batteries), to support the reduction of tenant energy costs
within the council’s housing stock.  Solar Thermal Panels and Mechanical Heat
Recovery and Ventilation technologies will also be considered as appropriate to the
development. 
▪ Consider, where viable and appropriate, the use of Local Heat Networks and seek
support via applications to the Heat Network Fund. 
▪ Continue to examine new heating systems such as hydrogen as they arise for
further consideration. 
3. Measures of success 
3.1  The proposed approach to heating new-build homes detailed within this report will seek
to deliver the following outcomes: 
a) Compliance with Scottish Government Heat in Buildings Strategy. 
b) Compliance with EESH2 requirements. 
c) Maintaining similar or betterment of the Energy Performance Ratings performance
for New Build Homes. 
d) Tenant satisfaction. 
e) That best value for North Lanarkshire Council is both demonstrable and achieved.
4. Supporting documentation 
There are no Supporting documents. 
Pamela Humphries
Head of Planning and Regeneration

Page 6

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact?
The Scottish Government has made additional grant funding available for the
installation of heating systems which produce zero direct emissions at the point of use
- £4,000 per unit (3 person equivalent benchmark).  The net cost to the Council
installing the air source heat pump systems is therefore an increase of £10,900 per
home compared to installing a gas central heating system once the extra grant is taken
into account.
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐

Page 7

5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact?
Will introduce technologies that may transmit via SIM Cards data relating to Battery
Storage and Heat Pumps. These technologies have been used on properties
elsewhere. 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The proposed approach to heating new-build homes will remove the combustion of
fossil fuels from home heating to comply with the Heat in Buildings Strategy and
promote successful achievement of the council and Scottish Government goals on
Climate Change.
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
Risk associated with the New Supply Programme is managed within the New Supply
Risk Register process.  The risk register has been updated to reflect the impact of
the installation of the new technology in heating systems