North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref PH/TM Date 31/08/22 
New Housing Supply Programme – Procurement Report 
From  Pamela Humphries, Head of Planning and Regeneration 
E-mail mallaghant@northlan.gov.uk Telephone
Tony Mallaghan, Housing
Development Manager,
07970 016251 
Executive Summary 
The purpose of this report is to update the Committee on current procurement activity
relating to the new build housing programme and seek approval to progress procurement
arrangements as outlined in the report. 
Recommendations 
It is recommended that the Housing Committee: 
1) Approve the procurement of call off contracts in line with the Scottish Procurement
Alliance (SPA) H2 framework agreement conditions for the construction of new build
housing at Coshneuk Road, Millerston up to the value of £4.00M, including
contingency allowance.
2) Approve the procurement of call off contracts in line with the Scottish Procurement
Alliance (SPA) H2 framework agreement conditions for the construction of new build
housing at Main Street, Glenboig up to the value of £1.50M, including contingency
allowance.
3) Approve the award of a call off contract in line with the Scotland Excel New Build
Residential Framework for the construction of new build housing to CCG (Scotland)
Ltd at Ravenscliff Road, Motherwell up to the revised value of £5.40M, including
contingency allowance.
4) Approve the procurement of call off contracts in line with the Scottish Procurement
Alliance (SPA) H2 framework agreement conditions for the construction of new build
housing to Hadden Construction Limited at Graham Street, Wishaw, up to the revised
value of £3.25M, including contingency allowance.
5) Approve the procurement of call off contracts in line with the Scottish Procurement
Alliance (SPA) H2 framework agreement conditions for the construction of new build
housing to Hadden Construction Limited at Kings Street, Wishaw, up to the revised
value of £1.25M, including contingency allowance. 
6) Approve the procurement of call off contracts in line with the Scottish Procurement
Alliance (SPA) H2 framework agreement conditions for the construction of new build
housing to Hadden Construction Limited at Stewarton Street and Kings House, Kings
Street, Wishaw, up to the revised value of £4.25M, including contingency allowance.
7) Approve the procurement of call off contracts in line with the Scottish Procurement
Alliance (SPA) H2 framework agreement conditions for the construction of new build

Page 2

1. Background 
1.1 The Council has an approved target to deliver 5,000 new homes by 2035. The delivery
of such a large scale programme presents a number of challenges, not least of which
is the procurement of contractors to build the houses to the required standard, within
the timescale required and at a competitive cost. In order to increase the pace of
delivery, secure best value and minimise risk to the Council, a range of procurement
options have been utilised. 
1.2 The Council has also participated in the establishment of a new build framework
agreement through Scotland Excel, which has been available for use from August
2019. This framework agreement is for the delivery of new build housing projects for
Scottish local authorities, housing associations and other public bodies and includes a
number of lots covering different geographical areas and different sized developments. 
1.3 The Housing and Regeneration Committee on the 25 November 2020 approved the
procurement route for the next phase of the new build programme to commence
procurement activity with the Scottish Procurement Alliance (SPA) and Scotland Excel
New Build Residential framework to deliver the next phase of new build sites approved
by the Committee. As reported at the Housing and Regeneration Committee on the 8
September 2021, due to the current capacity issues in the market we intend to utilise
the ability in the SPA and Scotland Excel Frameworks to direct award to available
contractors, including to contractors who are not highest ranking. Justification for the
identification of a contractor can be made by complying with the direct award criteria
listed in the respective frameworks, with a contract award being subject to value for
money assessment against the framework rates. A benchmarking appraisal was
carried out for each project and is identified in each projects Sourcing Methodology. 
1.4 The requirements of the Contracts have never been contracted before by the Council
therefore historical contract information is not available. 
housing to Hadden Construction Limited at Former Methodist Church Site,
Caledonian Road, Wishaw, up to the revised value of £2.25M, including contingency
allowance.
8)  Approve the award of a call off contract in line with the Scotland Excel New Build
Residential Framework for the construction of new build housing to McTaggart
Construction at Glenacre Drive, Airdrie, up to the value of £3.550M, including
contingency allowance. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 3

2. Report 
2.1 The Housing and Regeneration Committee on the 8 September 2021 approved the
procurement route for the next phase of the new build programme to commence
procurement activity with the Scottish Procurement Alliance (SPA) and Scotland Excel
New Build Residential framework to deliver the next phase of new build sites to direct
award to available contractors, including to contractors who are not highest ranking,
subject to value for money assessment. 
2.2 The Council intends to engage with contractors on the Scottish Procurement Alliance
(SPA) H2 framework for the following two projects: 
• Main Street, Glenboig, (Up to 6 units), up to the value of £1.50M, including
contingency allowance
Feasibility costs will be obtained and analysed to ensure best value and, subject to
benchmarking against the appropriate framework rates, it is proposed that a final tender
price be agreed to allow the contract award. 
2.3 The Housing and Regeneration Committee in May 2021 approved the procurement of
a call off contract in line with the Scotland Excel New Build Residential Framework for
the construction of new build housing to CCG (Scotland) Ltd Construction at Ravenscliff
Road, Motherwell, (24 units), up to the value of £4.75M, including contingency
allowance. CCG (Scotland) Ltd have submitted a revised cost of £5.40M, including
contingency allowance.   The tender cost obtained is considered to represent best value
and, and the rates have been benchmarked against the appropriate framework rates
with an allowance for current market conditions, to allow the contract award to be made. 
2.4 As approved by the Housing and Regeneration Committee in November 2021 the
Council has engaged with Hadden Construction Limited, who were the highest ranking
contractor on the Scottish Procurement Alliance (SPA) H1 framework to deliver these
sites. The H1 framework has now expired, and the contract award will be made to
Hadden Construction Limited under the H2 framework conditions. Revised feasibility
costs have been received for Graham Street, Wishaw and the feasibility costs for the
three remaining sites are awaited. Projections have been made for these on the basis
of the Graham Street feasibility costs. 
• Graham Street, Wishaw (Up to 13 units), up to the revised value of £3.25M, including
contingency allowance. 
• Kings Street, Wishaw, (Up to 5 units), up to the revised value of £1.25M, including
contingency allowance  
• Stewarton Street and Kings House, Kings Street, Wishaw, (Up to 17 units), up to the
revised value of £4.25M, including contingency allowance. 
• Former Methodist Site, Caledonian Road, Wishaw, (Up to 9 units), up to the revised
value of £2.25M, including contingency allowance 
The feasibility costs are considered to represent best value and, subject to
benchmarking against the appropriate framework rates, it is proposed that a final tender
price be agreed to allow the contract award. 
• Coshneuk Road, Millerston, (Up to 16 units), up to the value of £4.00M, including
contingency allowance

Page 4

2.5 The Housing and Regeneration Committee in November 2021 approved the
procurement of a call off contract in line with the Scotland Excel New Build Residential
Framework for the construction of new build housing to McTaggart Construction at
Glenacre Drive, Airdrie, (16 units), up to the value of £3.255M, including contingency
allowance.  McTaggart Construction have submitted a revised cost of £3.550M,
including contingency allowance.  The tender cost obtained is considered to represent
best value and, and the rates have been benchmarked against the appropriate
framework rates with an allowance for current market conditions, to allow the contract
award to be made. 
Next Steps 
2.6 The next batch of sites will be reviewed, and a suitable procurement route will be
identified to progress these projects to deliver new build housing to align with the Plan
for North Lanarkshire. 
Price Savings / Increases 
2.7 There are no cashable savings attributed to the Contract. 
Price Stability 
2.8 The pricing mechanism is a Priced Contract with Activity Schedule offering a good level
of cost certainty. 
Community Benefits 
2.9 The Council is committed to maximising the delivery of community benefits. The
procurement included a community benefit requirement, this approach is designed to
deliver local community benefits where possible. 
The successful Tenderers have committed to delivering a range of community
benefits and these are awaited in the final submission. These are detailed in each
table below:
Ravenscliff Road, Ravenscraig, Motherwell 
OUTCOME  No of Mandatory
Outcomes
12 Month Job for Long Term
Unemployed
2
Work Experience Placement (16+
Years of Age)
5
Financial Support for a Community
Project
3
Non Financial Support for a
Community Project
3
TOTAL 13

Page 5

Glenacre Drive, Airdrie
OUTCOME  No of Mandatory
Outcomes
New Sustainable Jobs for entrants
from Key Priority Groups
1
Work Experience Placement (16+
Years of Age)
6
Careers Event 3
Supply Chain briefing with SMEs 1
Financial Support for a Community
Project
1
Non Financial Support for a
Community Project
4
TOTAL 16 
Fair Work First 
2.10 All contractors appointed to the New Build Residential Framework and the Scottish
Procurement Alliance (SPA) H1 framework have evidenced Fair Work practices and
demonstrated how they will promote them in the delivery of contract call-offs from the
Framework. 
Contract Strategy 
2.11 Officers from New Supply will be responsible for managing the Contract which will be
undertaken in accordance with the council’s agreed approach to contract and supplier
management. 
3. Measures of success 
3.1  The proposed contract awards detailed within this report will deliver the following
outcomes: 
a) The appointment of Contractors who have the experience and capability to deliver
new build social housing;   
b) The procurement procedure is compliant with the procurement legislation and
internal procedures; 
c) That best value is both demonstrable and achieved; 
d) That the Contract secures a range of community benefits; 
e) That the Contract supports payment of the real Living Wage to staff employed in
the delivery of the Contract; 
f) That the Contract performance is proactively managed against a number of Key
Performance Indicators.

Page 6

4. Supporting documentation 
Appendix 1 Summary of Procurement Procedures
Appendix 2 SME Status of all Tenderers 
Pamela Humphries 
Head of Planning and Regeneration

Page 7

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The Council’s new build programme helps reduce inequalities through a number
of design specifications including: 
• Housing for Varying Needs;
• Secure by Design;
• Achieving the Scottish Government requirements for “Greener Homes” to
reduce the incidence of fuel Poverty; and
• The inclusion of design standards relating to access to internet capabilities
including ‘fibre to the property’. 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☒ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The funding for all of the projects referred to in this report can be met from the
Council’s Housing Revenue Account budget for the New Supply Programme. Grant
support is also provided by the Scottish Government. The costs associated with
contract delivery will be contained within the New Supply budget. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☒ No ☐
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☒ No ☐ 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact?

Page 8

5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☒
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☒
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The proposed award of contracts detailed within this report will ensure that the
impact on the Council’s carbon footprint is mitigated. The specifications incorporated
within the contract documentation will: deliver reduced energy need; encourage
sustainable construction; promote health and wellbeing; reduce waste and resources
through effective storage, collection and composting of waste and recyclable
materials and; include measures which will reduce CO2 emissions. 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The implementation and delivery of the New Supply programme will be promoted
through the New Supply PR plan and via communications with elected members and
local stakeholders 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐

Page 9

If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
Risk associated with the New Supply Programme is managed within the New Supply
Risk Register process. By undertaking detailed ground investigation and other
relevant site assessments prior to proceeding with the development of any particular
site, the Council is mitigating the risk of unforeseen costs relating to ground conditions,
although this risk cannot be eliminated entirely. However, the main current risk to the
current procurement is the sharp increase in the cost of materials, fuel, energy fuelling
high inflation and the lack of available and suitably qualified and experienced
tradespersons resulting in higher labour costs.  The Building Cost Information Service
(BCIS) forecasts that the current trend of increases in costs will extend into the
1Q2023.

Page 10

Appendix 1 Summary of Procurement Procedures 
Construction of New Build Social Housing at Ravenscliff Road, Ravenscraig,
Motherwell 
Procurement Title Contractor Design and Construction of New Build Social 
Housing at Ravenscliff Road, Ravenscraig, Motherwell
Estimated contract start date September 2022 – October 2023
Initial Contract Period  13 Months 
Contract Defects Period  12 Months
Estimated Total Contract value £5,375,800 (£5,105,641 + £270,159)
Contract Reference Number NLC-CPT-21-061
Contract Notice Reference Not Applicable
Date Contract Notice Published  Not Applicable
Governing UK Regulations Procurement (Scotland) Regulations 2016
Procurement Procedure  Direct Award from a 3rd Party Framework
Evaluation approach adopted Not Applicable
Interest List – number of
Contractors that downloaded the
procurement documents from the
procurement portal
N/A
Number of selection stage
documents received N/A
Number of Contractors invited to
tender 1
Number of tenders received  1
Number of non-compliant tenders 0
Number of compliant tenders 1
Number of recommended
contractors 1
Basis of contract award Quality 40% Price 60%
Evaluation team names and job
titles of Evaluators and their role
in evaluation
New Supply

Page 11

Construction of New Build Social Housing at Glenacre Drive, Airdrie 
Procurement Title Contractor Design and Construction of New Build Social 
Housing at Glenacre Drive, Airdrie
Estimated contract start date October 2022 – November 2023
Initial Contract Period  13 Months
Contract Defects Period  12 Months
Estimated Total Contract value £3,550,000 (£3,353,718 + £196,282) Subject to checking
Contract Reference Number NLC-SLP-22-065
Contract Notice Reference Not Applicable
Date Contract Notice Published  Not Applicable
Governing UK Regulation Public Procurement Regulations (Scotland) 2015 
Procurement Procedure  Direct Award from a 3rd Party Framework
Evaluation approach adopted Not Applicable
Interest List – number of
Contractors that downloaded the
procurement documents from the
procurement portal
N/A
Number of selection stage
documents received N/A
Number of Contractors invited to
tender 1
Number of tenders received  1
Number of non-compliant tenders 0
Number of compliant tenders 1
Number of recommended
contractors 1
Basis of contract award Quality 40% Price 60%
Evaluation team names and job
titles of Evaluators and their role
in evaluation
New Supply

Page 12

Appendix 2 SME Status of all Tenderers 
Project Tenderers Name
Size of Tendering
Organisation
(Micro, Small,
Medium or Large)
Location
(Local
Authority /
Council
Area)
Ravenscliff Road, Ravenscraig,
Motherwell CCG (Scotland) Ltd Large  South
Lanarkshire
Glenacre Drive, Airdrie McTaggart
Construction Medium North
Ayrshire