Mears LLP- Operational and Financial Performance Monitoring Report to June 2022

North Lanarkshire Council · 31 August 2022
Back to Housing Committee — 31 August 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref BL/MH/KD/HD Date 31/08/21 
Mears LLP: Operational and Financial Performance
Monitoring Report to 30 June 2022 
From  Brian Lafferty, Head of Business (Housing Property and Projects)  
E-mail HendryM@northlan.gov.uk
DoohanK@northlan.gov.uk Telephone Michelle Hendry, 07960974797
Kevin Doohan, 07415477387 
Executive Summary
This report outlines Mears Limited Liability Partnership (LLP) performance against its
business objectives, Council priorities and the Housing and Corporate Repairs and
Maintenance service delivery contracts and the financial performance for financial years
2022 and 2023. 
Recommendations
It is recommended that the Housing Committee: 
(1) Acknowledge Mears LLP’s operational performance for 2022/23 for both
housing repairs and corporate repairs, from 1 April 2022 to 30 June 2022.
(2) Acknowledge Mears financial performance as of 31 March 2022, along with
assurance, or otherwise of the financial standing of the ALEO by Financial
Solutions;
(3) Acknowledge that the Head of Business and Digital submits a six-monthly
composite report to the Audit and Scrutiny Panel confirming that governance
and risk management arrangements are suitably robust within each
ALEO/partner:
(4) It is recommended that Committee acknowledge the one-off modification to
the existing conditions as referenced in 2.5.5 and the financial impact that
varying the calculation of the index has. 
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 2

1. Background 
1.1 In 2010 Morrisons Facilities Services Ltd successfully bid to become the
Council’s strategic partner to deliver housing and corporate repairs over a 10-
year period with the contract commencing on 21 January 2011. Mears PLC
subsequently bought Morrisons Facilities Services Ltd as a going concern, so
now own the 67% shareholding in the Mears Scotland LLP (Mears) strategic
partnership and the inherent North Lanarkshire service contract. North
Lanarkshire Council owns the remaining 33% of Mears Scotland LLP. 
1.2 At a strategic level, the MEARS Management Committee is responsible for
governance and oversight of the LLP’s statutory responsibilities in relation to
service delivery and management, staffing, financial control and reporting, health
and safety, performance monitoring and risk management. The Management
Committee meets quarterly and comprises up to four representatives from
MEARS Scotland and two representatives from North Lanarkshire Council with
these positions currently filled by the Vice Convener of the Housing and
Regeneration Committee and the Head of Housing Solutions. Senior officers from
both partners are also in attendance to provide professional, technical and
financial reports. 
1.3 The Council expected the partnership to secure local employment, source local
supplies and services, and ultimately secure continuous improvement in the
repair’s services delivered to North Lanarkshire residents and the council. 
1.4 The Year 8 Best Value Service Review (BVSR) of the MEARS contract, reported
to the Enterprise and Housing Committee in May 2018, included an assessment
of the corporate property repairs service including: Revenue Works Orders,
capital projects, Client-Contractor liaison arrangements; post-inspections; health
and safety; and performance reporting. The review found that works are carried
out safely and are conducted in accordance with the job specification, good
industry practice and the relevant quality standards. The opportunity was
identified, however, to improve feedback and ongoing communication between
MEARS and the relevant Services to ensure that the customer was kept up to
date on the progress of the repairs. Overall, the BVSR identified high levels of
service delivery across the partnership, with only a small number of improvement
actions identified, including the need for improved communications as referenced
above. 
1.5 Housing repairs, corporate property maintenance and capital investment
proposals are all currently in-scope for delivery through the new North
Lanarkshire Council Enterprise Project. To ensure continuity of service and
enable anticipated inclusion of housing and corporate property maintenance
within the North Lanarkshire Council Enterprise Project, the Housing and
(22) Facilitate a North Lanarkshire wide approach to asset
rationalisation, including with communities and partners 
(25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 3

Regeneration Committee at its meeting on 20 May 2020 considered a report
recommending that provision is made for annual extensions to the strategic
partnership with MEARS, potentially up to January 2024. 
1.6 In relation to the contract extension, Mears are now in the second year, this
commenced on 22 January 2022 until 21 January 2023. It should also be noted
that the third year was recently approved at committee which is from 22
January 2023 to 21 January 2024. 
1.7 In line with the role and nature of the strategic partnership vehicle, performance
will continue to be reported to Committee during the extension periods. 
1.8 In February 2020, the arrangements were revised, and individual Heads of
Service now submit a six-monthly performance report to the relevant service
committee confirming that the ALEO is delivering services as per our
recommendations and expectations, and in accordance with the Service Level
Agreement of contract works agreement. Colleagues in Financial Solutions
provide the financial performance information along with assurance, or otherwise,
in relation to the financial standing of the company. 
1.9 In addition to this reporting, the Head of Business and Digital submits a six-
monthly composite report to the Audit and Scrutiny Panel confirming that
governance and risk management arrangements are suitably robust within each
ALEO. Information is also provided by the Head of Financial Solutions relating to
compliance with financial monitoring arrangements and identifying any matters
which may result in financial risk to the council. This financial information is
reported by exception. 
2. Report 
2.1 Performance Indicators 
2.1.1 It was agreed that performance against these targets should be reported to
committee on a six-monthly basis. As such a Partnership Performance report has
been submitted on a scheduled basis, with the most recent considered by the
previous committee at its meeting on 24 November 2021. 
2.1.2 Appendix 1 provides year to date housing performance in 2022/23 with
comparison figures from the previous year provided in Appendix 2. Emergency
and non-emergency timescales for housing repairs are shown in Appendix 3.
Appendix 4 provides year to date Corporate performance in 2022/23 with
comparison figures from the previous year provided in Appendix 5. Emergency
and non-emergency timescales for corporate repairs are shown in appendix 6. 
Further performance outcomes, demonstrating where Mears is supporting The
Plan for North Lanarkshire are provided at Appendix 7. Appendices 8 and 9
provide financial performance and overall Standing as of 31 March 2022. 
2.2 Housing Property Performance

Page 4

2.2.1 The timescale in completing emergency repairs for all 3 linked contractors, year
to date, is currently 3.22 hours. Mears year to date, average emergency
timescales are 3.38 hours. The 2021/22 Scottish average for all indicators has
still to be published and will be reported at the next committee. The 2020/21
Scottish average was 5.6 hours. 
2.2.2 The timescale for completing non-emergency repairs, for all 3 linked contractors,
year to date, is currently 6.30 days. Mears average non-emergency timescales
is 8.90 days.  The 2021/22 Scottish average for all indicators has still to be
published and will be reported at the next committee. The 2020/21 Scottish
average was 9.4 days. A full breakdown of year to date including emergency and
non-emergency performance for all contractors as well as Mears only, is included
in appendix 3 
2.2.3 It should also be noted that repairs carried out right first time has been reported
at 97.19 % over the same period. 
2.2.4 Current customer satisfaction level is 95.56% year to date. In 2021/22 it was
reported to the Scottish Housing Regulator that 94.79% of tenants were satisfied
with the repairs service. We continue to receive various methods of surveys
which include completed surveys online from tenants and also at the post
inspection stage of works, undertaken by our Technical Officers. We also receive
results from Mears text message survey which was introduced January 2021.
Customer satisfaction surveys continue to inform action and help ensure that any
areas of dissatisfaction are immediately followed up. 
2.2.5 Frontline resolutions - The number of Stage 1 complaints received for 2022/23
relating to all of Housing Property and Projects, have increased in comparison
with the same period last year (see table 1 below).  Of the complaints responded
to year to date, a total of 77.94% have been upheld or partially upheld, in the
same period last year 74% were upheld. 100.00% of complaints YTD have been
responded to within SPSO timescales, in comparison to 96.00% of complaints in
the same period in 2021/22. Twenty-two stage one complaints were received in
Q1 in relation to Mears, they were responded to within timescale and 21 (95.45%)
were upheld or partially upheld. An analysis of all complaints received is
undertaken by Local Homes to allow any re-occurring issues to be addressed
and associated service improvement actions to be progressed. 
2.2.6  Investigations- The number of Stage 2 complaints received for 2022/23, relating
to all Housing Property and Projects service, has decreased in comparison to the
same period last year (see table 1 below) A total of 57.14% of closed cases have
been upheld or partially upheld which is a decrease in comparison to 87.50%
upheld or partially upheld in the same period last year. 100% of complaints
received as stage 2 complaints were responded to within timescale YTD.  There
has been one stage 2 complaint received in relation to Mears within 2022/23 to
date. It was responded to within timescales and was upheld. 
2.2.7 It should be noted that in relation to the number of complaints as a comparison
to the number of emergency and non-emergency repairs, which equated to
24,577 from April to June 2022 this equates 0.03 as a % of complaints as a
comparison.

Page 5

2.2.8 Table 1 below shows Housing Property and Projects complaints received via
Council between each financial year.  The final column shows the total received
with the carry forward from the previous year. 
Table 1 
2022/23 2021/22 (for comparison) 
Q1 Q2  Q3 Q4
YTD
Total Q1 Q2 Q3 Q4 Total
Stage
1
67   67 +
4 cf
85 56 50 55 62 223 
Stage
2
5   5 + 2
cf
10 10 6 9 9 34 
Total 72   72 +
6 cf
95 66 56 64 65 257 
2.3 Corporate Property Performance 
2.3.1 The timescale in completing emergency repairs year to date, April 2022 to June
2022 is currently 3.52 hours.   
2.3.2 The timescale for completing non-emergency repairs year to date is currently
8.58 days. A full breakdown of year to date, emergency and non-emergency
performance is included in appendix 5. 
2.3.3  Percentage of emergency jobs of day-to-day routine jobs is 54.80% April – June
2022 this exceeds the 34% target as set out in the Strategic Performance
Framework.  
2.3.4 99.57% of emergency jobs were completed within time scale YTD. This
surpasses the 97% target.  
2.3.5 Also surpassing the 97% target is the percentage of routine jobs completed within
timescale which currently sit at 98.57% YYD. 
2.4 Service Delivery Highlights 
A sample of service delivery highlights over the period include: 
• Installed Kitchen units to St Andrews Hospice Warehouse
• Collaborative working with NLC on World of Work Modules ‘Pathways to a
career, video recorded to be shown at careers fayres across schools that
shown success cases for apprenticeships’
• Collaborative working with supply chain to donate paint to Mother & Baby unit
in Airdrie
• NLC No Limits placement commenced on September 2021
• 444 Safer Homes items to 68 properties in Q1  
• 21 apprentices onboarded in August 2021 
2.5 Financial Impact – Public Accountability

Page 6

2.5.1 To satisfy the Council’s duty to ensure the organisation delivering property repairs
and upgrade services on its behalf is financially sound, the Council’s Section 95
Officer maintains appropriate and proportionate processes and procedures for
scrutinising Mears financial performance. 
2.5.2 The Council’s Legal Agreements with Mears specify the financial information
which it must submit to the Council including an annual business plan, quarterly
management accounts, audited financial statements etc., to enable Financial
Solutions to assess and report any financial risk likely to arise as a result of the
Council using Mears to deliver these services. 
2.5.3 The Council expends both revenue and capital resources annually with Mears to
deliver services which assist the Council in achieving its priority outcomes. Mears
operated a financial year ending 31 December 2021 with the majority of its
turnover anticipated from housing and property repairs, with the remainder
representing capital and other works. 
Based on their unaudited accounts to 31 December 2021, members may will wish
to note that Mears LLP reported a trading profit of £1.181m on an annual turnover
of £48.856m (2.4%). During January to June 2021, the company traded a no profit
/ no loss breakeven position as per the defined service agreement with NLC. The
budget assumed a delivery of works at previously derived run rates, which were
not possible to achieve during the pandemic, resulting in the reduced bottom line
profit position.   
2.5.4 As previously advised, the contract with Mears includes scope for the Council to
receive additional financial benefits, all of which have been impacted during the
year by the restrictions in place including: 
a) A “volume discount”, which gives the Council a 6.28% return on the value
of relevant works awarded through the partnership. For the financial year
2021/22, the Council had budgeted to receive £1.3m which was fully
achieved. 
b) The partnership agreement also makes provision for a Best Value
Efficiency Saving (BVES) to be applied to the schedule of rates paid by the
Council on 1st July each year.  The BVES receivable is dependent on
turnover achieved by Mears, with a rate of 2.75% applicable on works to
the value of £30m, a further 4.69% applicable on works between £30m and
£35m, and any turnover in excess of £35m attracting additional BVES of
7.69%.  Recognising the Council’s 2021-22 budget of £34.5m for housing
repairs, the partnership expected to deliver a minimum benefit of £0.825m. 
c) Scope also exists for the Council to receive dividends from this partnership
arrangement. However, as a result of the previous cumulative negative
trading position, there have been no dividends declared to date. 
d) In return for satisfactory service delivery and effective financial performance
through the LLP, Mears PLC is entitled to receive a management fee which
comprises both fixed and variable elements and is partially linked to level
of works delivered through the contract.

Page 7

2.5.5 Members will be aware of the well publicised inflationary pressures in the wider
economy linked to Covid-19, Brexit and the war in Ukraine. As a result, material
prices have risen significantly in recent times with the only way to address this
within the contract being through the index fluctuation.  Due to significant market
volatility there was a delay between the impact of current market conditions being
shown through the standard indices applicable in the contract.  
An ongoing exercise into price increase claims highlighted a more reasonable
approach would be to calculate the index figure at the point it was due to be
applied rather than forecast annually as stated within the contract. 
An earlier committee report to the Housing and Regeneration Committee on 20
May 2020 regarding the Mears Partnership Extension advised there would be no
change in the scope of the contract or the schedule of rates.  
This amendment may be considered a one-off modification to the existing terms
and conditions to deal with the unprecedented market conditions and ensure the
sustainability of a key strategic partner. 
Amending the calculation would have a consequential effect on the Schedule of
Rates and would equate to a payment for 2021/2022 of approximately £996k. 
2.6 Financial Performance as of 31 March 2022 
2.6.1  Mears Financial year runs from January to December. The LLP is budgeting to
receive a net profit of £1.833m on a turnover of £49.989m (3.7%).  The 2022
budget submission was based upon normal trading forecasts following the
conclusion of the defined service agreement. The budget is based on the pre-
defined service delivery run rates, taking into consideration anticipated reductions
in some planned work streams. Existing agreements on Covid19 support are
included in the first quarter to March 2022. 
2.6.2 The mix of turnover traded during Q1 has had more of a bias towards routine
repairs than originally envisaged. Planned works have been re-prioritised to
ensure the routine works are being completed. 
2.6.3 Based on Mears financial statements to 31 March 2022, it should note that the
Mears are showing a net profit of £0.205m on a turnover of £12.954m. Details of
performance against budget to31 March 2022 are detailed in Appendix 8. 
2.6.4 It should be noted that the partnership has experienced difficult trading conditions
during quarter 1. This has been because of the challenging issues within the
market, where material prices are increasing and in instances difficult to procure.
It should also be noted that recruitment is proving challenging due to a demand
on labour across the construction industry. 
2.7  Overall Financial Standing – Balance Sheet as at 31 March 2022 
2.7.1 Appendix 9 provides key balances to give members an update on the overall
financial standing of the company. Key balances and indicators worthy of specific
note include:

Page 8

a) The company had cumulative net assets of £0.857m 
b) A comparison of current assets to current liabilities equated to a current
net asset of £3.323m and a current ratio of 1.425. A current ratio less than
1 is an indication that the company may experience difficulty in meeting
its obligations. The partnership ratio is above 1, however there is a
continued reliance upon the parent company’s rolling facility which is up
to a maximum of £8.000m. 
The intra Group loan account stood at £2.535m as at 31 March 2022. 
3. Measures of success 
3.1  These reports detail the activities which are expected to support delivery of the
council’s priority outcomes, as well as the organisation’s performance against
these. This should ensure elected members have sufficient information to assess
how Mears’ service delivery supports the council in delivering against The Plan
for North Lanarkshire, as well as producing a high level of service delivery, legal
compliance and customer satisfaction.     
4. Supporting documentation 
6.1  Appendix 1 – Mears Housing Performance 22/23 
6.2  Appendix 2 – Mears Housing Performance 21/22 
6.3  Appendix 3 – Housing emergency and non-emergency performance 22/23
6.4 Appendix 4 – Mears Corporate Performance 22/23
6.5 Appendix 5 – Mears Corporate Performance 21/22
6.6 Appendix 6 – Corporate emergency and non-emergency performance 22/23
6.7  Appendix 7 – Mears Contribution to The Plan
6.8 Appendix 8 - Financial Performance as of June 2021
6.9 Appendix 9 – Overall Financial Standing as of June 2021 
Brian Lafferty
Head of Business (Housing Property and Projects)

Page 9

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒

Page 10

If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☐ No ☒
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed

Page 11

Appendix 1 MEARS HOUSING PERFORMANCE 2022/23 
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Cat 1a -
Emergency
within Hours
(95%)
Total
1019 1297 1146                  
%
Within
99.61% 99.69% 99.56%                  
Cat 1b -
Emergency
Outwith
Hours (95%)
Total
735 657 743                  
%
Within
99.86% 99.70% 99.33%                  
Cat 2 -
Routine 3
Day Works
(95%)
Total
634 675 638                  
%
Within
100.00% 100.00% 100.00%                  
Cat 3 -
Routine 7
Day Works
(95%)
Total
1 1 2                  
%
Within
100.00% 100.00% 100.00%                  
Cat 4 -
Routine 20
Day Works
(95%)
Total
2195 2198 2059                  
%
Within
99.91% 99.68% 99.95%                  
Empty House
Works - 3
Days (95%)
Total
309 339 303                  
%
Within
100.00% 95.87% 93.40%                  
Empty House
Works - 10
Days (95%)
Total
456 450 376                  
%
Within
99.78% 94.89% 93.35%                  
Routine
Works - P9
(95%)
Total
3 0 0                  
%
Within
100.00% N/A N/A                  
Glazing Pilot
Works (95%)
Total
111 139 85                  
%
Within
100.00% 100.00% 100.00%                  
Priority P -
Extended
Priorities
(95%)
Total
190 211 246                  
%
Within
100.00% 100.00% 99.59%                  
Adaptations -
40 Days
(95%)
Total
70 93 70                  
%
Within
100.00% 98.92% 100.00%                  
Rotworks - 40
Days (95%)
Total
41 63 41                  
%
Within
100.00% 100.00% 100.00%                  
Priority T - 1
Day  (100%) 
Total
246 294 198                  
%
Within
100.00% 100.00% 100.00%

Page 12

Appendix 2 MEARS HOUSING PERFORMANCE 2021/22 
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Cat 1a -
Emergency
within Hours
(95%)
Total
1441 1491 1405 1391 1536 1539 1564 1536 1433 1301 1369 1419
%
Within
99.38% 99.46% 98.72% 99.21% 99.35% 99.03% 99.42% 98.83% 99.44% 99.69% 99.34% 99.37%
Cat 1b -
Emergency
Outwith
Hours (95%)
Total
910 966 779 928 947 762 907 766 824 826 791 724
%
Within
99.78% 99.28% 99.61% 99.57% 99.37% 99.21% 99.67% 97.39% 99.51% 99.76% 99.12% 99.72%
Cat 2 -
Routine 3
Day Works
(95%)
Total
507 804 791 821 875 767 838 783 730 741 677 748
%
Within
99.61% 100.00% 100.00% 100.00% 99.89% 100.00% 99.76% 99.87% 99.86% 100.00% 100.00% 100.00%
Cat 3 -
Routine 7
Day Works
(95%)
Total
1 1 0 1 0 0 1 1 0 0 1 1
%
Within
100.00% 100.00% N/A 100.00% N/A N/A 100.00% 100.00% N/A N/A 100.00% 100.00%
Cat 4 -
Routine 20
Day Works
(95%)
Total
916 2491 2820 2145 2006 1905 1871 2360 1794 1853 1857 2149
%
Within
100.00% 100.00% 99.96% 99.77% 99.85% 100.00% 99.95% 99.92% 99.94% 99.78% 99.84% 99.95%
Empty House
Works - 3
Days (95%)
Total
479 442 487 513 512 427 474 524 494 459 490 427
%
Within
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 99.79% 99.81% 100.00% 99.56% 99.80% 99.77%
Empty House
Works - 10
Days (95%)
Total
500 448 503 491 476 578 498 548 478 467 541 434
%
Within
100.00% 100.00% 99.80% 99.80% 100.00% 100.00% 100.00% 99.64% 100.00% 99.79% 99.82% 99.54%
Routine
Works - P9
(95%)
Total
1 1 1 0 2 3 4 13 5 8 3 6
%
Within
100.00% 100.00% 100.00% N/A 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Glazing Pilot
Works (95%)
Total
85 120 130 130 143 160 132 142 147 120 106 109
%
Within
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 99.08%
Priority P -
Extended
Priorities
(95%)
Total
154 154 232 349 527 599 671 836 291 192 195 189
%
Within
99.35% 100.00% 99.57% 99.71% 100.00% 100.00% 100.00% 99.88% 100.00% 100.00% 100.00% 100.00%
Adaptations -
40 Days
(95%)
Total
92 66 124 91 78 121 106 97 37 93 55 107
%
Within
100.00% 100.00% 100.00% 98.90% 100.00% 99.17% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Rotworks -
40 Days
(95%)
Total
41 62 80 57 61 39 65 57 53 54 66 56
%
Within
97.56% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Priority T - 1
Day  (100%) 
Total
387 307 280 283 341 391 355 394 414 411 324 314
%
Within
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

Page 13

Appendix 3 – Average timescales for housing emergency and non-emergency jobs 
Housing Emergency Repair Timescales – 2022/23 (All contractors) 
April May June July August September October November December January February March YTD
Total Time Taken 6598:47:10 8060:51:47 6856:43:09                   21516:22:06
Total Jobs 2080 2272 2030                   6382
Average Timescale 3:10:21 3:32:52 3:22:40                   3:22:17 
Housing Non-Emergency Repair Timescales – 2022/23 (All contractors) 
April May June July August September October November December January February March YTD
No. Of Non
Emergency Repairs 6332 6146 5717                   18195
Total Number of
Days Taken 45646 38260 30754                   114660
Average Length of
Time Taken 7.21 6.23 5.38                   6.30 
Housing Emergency Repair Timescales – 2022/23 (Mears only) 
April May June July August September October November December January February March YTD
Total Time Taken 6050:36:41 7522:28:15 6263:20:49                   19836:25:45
Total Jobs 1754 1952 1743                   5449
Average Timescale 3:26:59 3:51:13 3:35:36                   3:38:25

Page 14

Housing Non-Emergency Repair Timescales – 2022/23 (Mears only) 
April May June July August September October November December January February March YTD
No. Of Non
Emergency Repairs 3304 3358 2784                   9446
Total Number of
Days Taken 34378 29225 20493                   84096
Average Length of
Time Taken 10.40 8.70 7.36                   8.90   
Appendix 4 MEARS CORPORATE PERFORMANCE 2022/23 
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Cat 1a -
Emergency
within Hours
(95%)
Total
216 277 227                  
%
Within
100.00% 99.64% 99.12%                  
Cat 2 -
Routine 3 Day
Works (90%)
Total
66 140 105                  
%
Within
100.00% 99.29% 96.19%                  
Cat 3 -
Routine 7 Day
Works (90%)
Total
73 135 69                  
%
Within
100.00% 100.00% 97.10%

Page 15

Cat 4 -
Routine 20
Day Works
(90%)
Total
276 311 165                  
%
Within
98.91% 97.75% 98.18%                  
Programmed
Works  (95%)
Total
48 46 15                  
%
Within
95.83% 97.83% 93.33%                  
Cyclic Works 
(95%)
Total
21 27 31                  
%
Within
95.24% 100.00% 100.00%

Page 16

Appendix 5 MEARS CORPORATE PERFORMANCE 2021/22 
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Cat 1a -
Emergency
within Hours
(95%)
Total
195 263 187 91 232 273 267 324 248 226 254 235
%
Within
98.97% 98.86% 99.47% 98.90% 95.26% 99.63% 96.25% 99.07% 98.79% 97.79% 100.00% 98.30%
Cat 2 -
Routine 3
Day Works
(90%)
Total
71 152 114 49 130 149 141 129 95 93 120 79
%
Within
95.77% 96.05% 92.98% 100.00% 98.46% 100.00% 99.29% 100.00% 100.00% 96.77% 100.00% 100.00%
Cat 3 -
Routine 7
Day Works
(90%)
Total
62 98 74 46 92 100 76 87 44 48 65 43
%
Within
98.39% 97.96% 95.95% 100.00% 100.00% 98.00% 100.00% 100.00% 100.00% 95.83% 100.00% 100.00%
Cat 4 -
Routine 20
Day Works
(90%)
Total
329 316 365 242 300 395 440 458 309 286 309 237
%
Within
97.57% 99.37% 97.53% 98.76% 96.67% 97.72% 99.32% 98.69% 99.03% 99.65% 100.00% 99.16%
Programmed
Works  (95%)
Total
6 12 15 16 18 46 76 60 46 58 68 43
%
Within
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 97.37% 100.00% 100.00% 98.28% 100.00% 100.00%
Cyclic Works 
(95%)
Total
30 15 45 51 41 65 85 90 64 74 88 293
%
Within
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 98.98%

Page 17

Appendix 6 – Average timescales for corporate emergency and non-emergency jobs 
Corporate Emergency Repair Timescales – 2022/23 (Mears only) 
April May June July August September October November December January February March YTD
Total Time Taken 900:24:35 913:39:44 1026:43:15                   2840:47:34
Total Jobs 228 278 226                   732
Average
Timescale 3:56:57 3:17:12 4:32:35                   3:52:51 
Corporate Non-Emergency Repair Timescales – 2022/23 (Mears only)  
April May June July August September October November December January February March YTD
No. Of Non
Emergency
Repairs 507 573 335                   1415
Total Number of
Days Taken
5210 4582 2349                   12141
Average Length of
Time Taken 10.28 8.00 7.01                   8.58 
Appendix 7 Mears contribution to The Plan for North Lanarkshire      
Service Area Target Outcome/Purpose 2021/22
Actual 
Comments
Q1 Q2 Q3 Q4

Page 18

Improve Economic Opportunities and Outcomes
OBJECTIVE: Provide supported routes out of unemployment or underemployment
Number of trade and Modern
apprenticeships
Contribute to the long-term
economic sustainability of North
Lanarkshire         
51          
51          
21 apprentices recruited in August 2021.  Which will take us to
173 over the length of the contract.  
Apprentice Intake scheduled for August 2022 – 20 Craft
Apprenticeships.  
OBJECTIVE: Help current and incoming businesses to grow and create employment
Number of local suppliers Contribute to the long-term
economic sustainability of North
Lanarkshire.    34 suppliers with
a spend of
£7.12m  
20
Supplie
rs with
a
spend
of
£2.4 m          
Local supply chain spend.
Spend is per quarter (not cumulative). 
Improving the Health and Wellbeing of our Communities
OBJECTIVE: Enable more people to live longer at home and to live as independently as possible
Safer homes advice and
installations
To provide safety and security
measures to vulnerable groups
such as elderly and victims of
domestic abuse.  
1518 items fitted
to 262 properties  
279
items
fitted to
50
properti
es          
Schools work experience and
engagement
Provide young people with an
opportunity to get an insight into
a possible career             
0  
1  
Virtual Apprentice video sent to school to show at employability
event. (21/22).

Page 19

Trade Work Experience – Plumbing ½ day every week for the
month of June.    
On track to resume pre covid activity for 22/23.      
Recruitment fairs/career talks Provide young people with an
opportunity to get an insight into
a possible career and routes to
work               
1           2      
Attending meetings with Agyllis / Jennifer Lees to contribute to
World of Work Modules.  Work in Progress
Plains Primary School site visit to New Build.    
Dalziel High Mock Interview Sessions      
Apprenticeship projects to
support local communities
Provides apprentices with the
opportunity to work with local
communities to add value to
facilities as well as work with
local groups and events to
enable others to deliver
community benefits within their
area      
0 2            
2 apprentices carried out some groundwork at St Andrews
Hospice during Scottish Apprenticeship week.  
4 Apprentices volunteered at Mears Annual Golf Day to raise
funds for St Andrews Hospice  
Citizenship programme on track to return to pre covid run rate.    
Enhance Participation, Capacity and Empowerment Across Our Communities  
OBJECTIVE: Improve community participation and engagement in the planning and delivery of services

Page 20

Housing Tenant Conferences Positively promote the
partnership
0 0       Not applicable for 21/22.
Sporting Events Positively promote the
partnership
0 0       Not applicable for 21/22..
Best Value Efficiency Savings To positively support the
partnership, deliver efficiencies
to the Schedule of Rates
payable via the works
agreement.
£ £ £     Qtr 1 savings not available will be updated at next cycle

Page 21

Appendix 8
MEARS Scotland LLP
Financial Performance as at March 2022
Income & Expenditure 2022 2021
Budget Actual
Variance to
Budget
Full Year
Budget Actual Outturn
£m £m £m £m £m
Total Sales 13.545 12.944 -0.601 49.989 48.856
Total Direct Costs 10.958 10.616 0.342 40.405 39.753
Gross Margin 2.587 2.328 -0.259 9.584 9.103
Operational % 19.1% 18.0% 43% 19.17% 18.63%
Total Overheads 1.978 2.123 -0.145 7.751 7.922
Net Trading Profit 0.609 0.205 -0.404 1.833 1.181
Profit % 4.5% 1.58% 67.2% 3.7% 2.4%

Page 22

Appendix 9
MEARS Scotland LLP
Overall Financial Standing - Balance Sheet as at March 2022
Balances / Indicators 2022 YTD 2021 Final Outturn
£m £m
Total Fixed Assets 0.069 0.078
Stock 1.239 2.284
Trade & Other Debtors 1.950 0.408
Cash 7.952 7.727
Trade & Other Creditors -5.957 -6.113
Government Bodies - tax, VAT, NI -1.861 -2.079
Inter Company Trading loan -2.535 -1.663
Total Net Assets/ (Liabilities) 0.857 0.642
Current Ratio 1.425 1.272