Page 1

North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref GT/JM Date 31/08/22 
Enterprise and Communities – Capital Monitoring Report 
From  Derek Brown, Depute Chief Executive 
E-mail telferg@northlan.gov.uk Telephone
Greg Telfer, Business
Finance Manager, 07583
010692 
1. Background 
1.1 Financial year 2022/23 is the second year of the 5 year capital programme which was
approved by the Policy and Strategy Committee on 18 March 2021.   
1.2 The Enterprise and Communities 2022/23 capital programme of £157.168 was
approved by the Policy and Strategy Committee on 17 March 2022. The programme
has since been increased by £5.796m relating to carry forwards from 2021/22.  In
addition, a further £15.683m has been received in external funding giving an overall
working capital programme of £178.647m. 
Executive Summary 
This report highlights the financial performance of 2022/23 Enterprise and Communities
capital programme for the period ended 22 July 2022 (Period 4). 
In summary the Service has a total capital budget of £178.647m.  At this stage in the
financial year the service is currently forecasting a break-even position. 
Further explanation of project variances and management action taken by the Service is
included within the main report and attached appendices. 
Recommendations 
It is recommended that the Committee: 
(1) Acknowledges the financial position of the 2022/23 Enterprise and Communities
capital programme. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

1.3 The Council’s approved Financial Regulations required services to remain within their
approved budgetary provision, and to report all significant deviations – defined as the
higher of £0.100m or 5% - within their budget monitoring reports.  Where significant
deviations were identified, services must provide explanatory commentary, outline the
action required to rectify such deviations and where relevant, must also highlight the
impact this has on other budget headings. 
2. Report 
2.1 At this early stage in the financial year the Service is reporting a break-even position. 
2.2 However, Committee should be aware that the service continues to face programme
delivery challenges and risks including significant inflationary pressures that are outwith
its control. As a result of these inflationary pressures the Council’s Strategic Capital
Delivery Group will be reviewing the impact they may have on programme delivery at
its upcoming meeting. 
2.3 Capital budgets and expenditure are summarised into Project/Themes (see Appendix
1).   
3. Measures of success 
3.1 The Service aim is to be in a balanced budget position at financial year-end   
4. Supporting documentation 
4.1 Appendix 1 Summary Expenditure by Project/Theme 
Derek Brown
Depute Chief Executive

Page 3

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The Service aims to operate within approved funding levels and utilise budget
virements to support emerging issues and mitigate variances across budget heads. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐

Page 4

5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☒
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
All activities undertaken by the Council are subject to risk, and in acknowledging the
Council’s approved Risk Management Strategy, Services managed these as part of
their overall corporate and service planning processes.  The current economic climate,
in particular, has the potential to impact upon the Council’s ability to provide quality
services within approved budget levels. 
To minimise risk this report was prepared by service based Financial Solutions
personnel in consultation with budget managers, in accordance with the Financial
Regulations.

Page 5

Appendix 1 
Enterprise & Communities Capital Programme 2022/23
Theme Expenditure Summary
1st April 2022 - 22nd July 2022 (PERIOD 4)
Thematic Category
Revised
Budget
£
Actual
£
Committed
£
Uncommitted
£
Projected
Outturn
£
Outturn
variance
£
ASSET & PROCUREMENT SOLUTIONS
Maintaining Existing Assets - windows, re-roofing, re-wiring
and condition survey works for the Council's building assets 8,857,868 1,010,315 2,688,812 6,169,056 8,857,868 0
Carbon Management 2,126,769 19,812 19,812 2,106,957 2,126,769 0
Office Rationalisation (16,849) 32,577 32,577 (49,426) (16,849) 0
Shared Campus 0 0 0 0 0 0
Leisure Development 1,311,349 630,081 888,488 422,861 1,311,349 0
Health & Wellbeing & Digital Classrooms 411,693 57,215 57,215 354,478 411,693 0
Rationalisation including ASN & Social Work 3,599,432 256,127 703,625 2,895,807 3,599,432 0
Curriculum Development 863,951 137,138 482,341 381,610 863,951 0
Sustainable Estate 1,474,242 19,158 572,683 901,559 1,474,242 0
Outdoor Education and Outdoor Spaces 343,176 92,534 127,647 215,529 343,176 0
Future Capital Receipts Investments 985,791 0 236,281 749,510 985,791 0
Design Fees 1,525,383 0 0 1,525,383 1,525,383 0
1140 Early Learning and Childcare Expansion 2,191,802 554,949 554,949 1,636,853 2,191,802 0
Demolitions 1,010,383 15,159 15,159 995,224 1,010,383 0
TOTAL ASSET & PROCUREMENT SOLUTIONS 24,684,990 2,825,064 6,379,589 18,305,401 24,684,990 0
TOWN AND COMMUNITY HUBS
Town and Community Hubs 59,580,849 10,587,039 44,991,702 14,589,147 59,580,849 0
TOTAL TOWN AND COMMUNITY HUBS 59,580,849 10,587,039 44,991,702 14,589,147 59,580,849 0
ENVIRONMENTAL ASSETS
Infrastructure and Transportation Improvements 10,209,551 1,192,127 5,872,733 4,336,818 10,209,551 0
Greenspace infrastructure Health & Wellbeing 1,129,648 19,517 123,054 1,006,596 1,129,649 0
Parks Masterplans 2,673,895 405,831 1,409,810 1,264,086 2,673,895 0
Environmental Assets replacement of plant and machinery 666,997 123,818 580,823 86,174 666,997 0
Cemeteries/Tree Infrastructure 4,086,701 69,449 69,449 4,017,253 4,086,701 0
Road Asset Management including street lighting, road
improvements and gateway signage 12,275,727 1,103,954 7,276,764 4,998,963 12,275,727 0
Bin rationalisation project and replacement 716,512 135,134 237,074 479,438 716,512 0
Play Area Equipment and surface renewal 213,145 8,252 8,252 204,893 213,145 0
TOTAL ENVIRONMENTAL ASSETS 31,972,176 3,058,080 15,577,958 16,394,218 31,972,176 0
REGULATORY SERVICES & WASTE SOLUTIONS
Contaminated Land and Pollution Control 368,376 210,647 210,647 157,729 368,376 0
Vehicle Replacement Programme 1,448,444 0 0 1,448,444 1,448,444 0
Depot Rationalisation and Investment 3,509,776 32,049 3,509,776 0 3,509,776 0
HWRC Equipment 464,700 90,500 90,500 374,200 464,700 0
Landfill Provision (Aftercare) 0 0 0 0 0 0
TOTAL REGULATORY SERVICES & WASTE SOLUTIONS 5,791,296 333,196 3,810,923 1,980,373 5,791,296 0
PLANNING & REGENERATION
Economic Regeneration 24,440,066 490,534 3,285,165 21,154,901 24,440,066 0
City Deal 28,728,373 3,441,842 3,441,952 25,286,421 28,728,373 0
Enterprise Projects 2,856,931 471,888 624,050 2,232,881 2,856,931 0
Antonine Wall Project 30,103 82,258 0 30,103 30,103 0
TOTAL PLANNING & REGENERATION 56,055,473 4,486,522 7,351,167 48,704,306 56,055,473 0
HOUSING PROPERTY & PROJECTS
Water Quailty / Ventilation 561,862 450,002 450,002 111,860 561,862 0
TOTAL HOUSING PROPERTY & PROJECTS 561,862 450,002 450,002 111,860 561,862 0
TOTAL ENTERPRISE & COMMUNITIES 178,646,646 21,739,903 78,561,341 100,085,305 178,646,646 0
YTD OUTTURN