Annual Review of Housing Asset Management Plan 2021 - 2022

North Lanarkshire Council · 31 August 2022
Back to Housing Committee — 31 August 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref BL/PH/SL/LS/BLaf Date 31/08/22 
Annual Review of Housing Asset Management Plan 2021-2022 
From  Brian Lafferty, Head of Housing Property and Projects
Stephen Llewellyn, Head of Housing Solutions
Pamela Humphries, Head of Planning and Regeneration 
E-mail laffertyb@northlan.gov.uk
llewellyns@northlan.gov.uk
humphriesp@northlan.gov.uk 
Telephone 01698 524758
01698 274192
01698 274174 
Executive Summary 
This report provides an overview of the progress achieved over the 2021/22 period in
delivering Homes Fit for the Future, the council’s Housing Asset Management Plan (HAMP)
2021-2026 and seeks approval on the annual progress report.   The Plan was approved in
February 2021 by the Housing and Regeneration Committee and formally adopted.  It sets
out our ambitions and priorities alongside key actions for asset management activities and
investment over the five-year period, 2021-2026.  The HAMP aligns with the Local Housing
Strategy and other key council strategies and supports several programmes of work:
• P001 (Enterprise Contract)
• P003 (Digital NL Transformation Programme)
• P013 (New Supply Programme)
• P014 (Tower Strategy)
• P015 (Housing Investment Programme)
• P017 (Fuel Poverty)
• P018 (ERDP)
• P020 (Town Centre & Community Regeneration)
• P021 (City Deal)
• P078 (Local Housing Strategy)
Recommendations 
It is recommended that Housing Committee:
(1) Note the progress achieved towards the delivery of the Housing Asset
Management Plan (HAMP) priorities and key actions.
(2) Approve the HAMP annual review and corresponding updated action plan
(attached as an appendix to this report).
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes

Page 2

1. Background 
1.1 The council produced in February 2021, Homes Fit for the Future, Housing Asset
Management Plan (HAMP) 2021-2026, which sets out the strategic asset management
approach in managing council housing in North Lanarkshire. The Plan aligns with the
priorities set out in North Lanarkshire’s Local Housing Strategy (LHS) and provides
strategic direction for the five-year investment programme. 
1.2 The HAMP is a cross service plan which supports the development and implementation
of several programmes of work for North Lanarkshire Council. 
1.3 The annual review of the HAMP for 2021/22 has now been prepared on progress made
in relation to the priorities and corresponding actions. 
2. Report  
Annual Review of Housing Asset Management Plan  
2.1 The vision set out in the HAMP, articulates North Lanarkshire Council’s ambitions. This
vision will be achieved by delivering on four key priorities: 
• We help deliver the homes North Lanarkshire needs to grow 
• We provide high-quality, well-maintained homes 
• We tackle climate change and fuel poverty 
• We improve our systems and our use of data 
2.2 The Covid-19 pandemic presented significant challenges on the delivery of services
over the 2021-2022 period and continues to do so.  Other impacts on programmes of
work include inflationary cost increases, material and labour shortages as well as the
wider effects of the current global situation.
2.3 The action plan contains 44 separate actions, delivering on 15 individual milestones
with the HAMP providing a framework for strategic review and reporting. Of these
actions, 37 actions are on track (green) and 7 actions have minor delays (amber). 
There are no actions which have significant delays (red). 
2.4 In terms of meeting key targets up to 2021/221 some of the highlights noted include: 
• 14942 new homes since 2010 
• 57 new wheelchair homes since 2010 
• 562 homes brought back into council ownership
• 588 council homes have had new kitchens installed and 822 council homes
have had a new bathroom during 2021/22 
• 1045 council homes have new heating systems in 2021/22
• 761 homes with roof and render improvement in 2021/22
• 3.2 average hours in completing emergency repairs - faster than previous years
(2019/20: 4.3)
• 0 failures to meet gas safety regulations during 2021/2022 
1 As at 31st March 2022
2 Includes homes acquired through the Open Market and Empty Homes Purchase Schemes
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 3

2.5  Other key successes have included the continued successful progression of the
Towers Reprovisioning Programme, with 209 properties demolished over the 2021/22
period, and the first two re-provisioning sites in Airdrie reaching construction stage,
which includes a pioneering net zero site in Dykehead Road, the first of its kind in
Scotland.   
2.6  Significant progress has also been made in relation to reshaping and repopulating our
town centres, with 79 new council homes in town centres/on the edge of town centres
delivered over the period, town centre visions developed and work to develop town
centre action plans well underway. 
2.7  Over £27m has been invested over the reporting period on improving existing homes,
including £13m on upgrading heating systems, £6.5m on new kitchens and bathrooms,
and £4.2m on home safety and security. Re-cladding in four of tower blocks is currently
underway in addition to an extensive programme of work to install interlinked smoke
and heat detectors to meet new legislative requirements.  Further information on the
extent of progress is outlined in the attached appendix. 
Governance 
2.8 The HAMP is reviewed on a quarterly basis by the HAMP Steering Group and progress
reported to the HAMP Board, comprised of Senior Management. Annual reviews of the
HAMP will continue to be provided to committee. 
3. Measures of success 
3.1  Approval of the annual review of the HAMP 2021/22 for continued implementation of
the HAMP actions and priorities.   
4. Supporting documentation 
4.1 Appendix – Annual Review of Housing Asset Management Plan 2021/22. 
Brian Lafferty      Pamela Humphries
Head of Housing Property and Projects  Head of Planning and Regeneration 
Stephen Llewellyn
Head of Housing Solutions

Page 4

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The equality impact assessment for the Annual Review of the Housing Asset
Management Plan has identified that there are no adverse impacts and some
equality groups such as older and disabled people will benefit from the actions set
out in the HAMP. 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☒ No ☐
5.2 Financial impact
Does the report contain any financial impacts? 
There are no direct financial implications as a consequence of this report.
Yes ☐ No ☒
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact?

Page 5

5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
This report does not have a direct impact on technology or digital transformation.
However, the HAMP contains several actions within Priority 4 ‘We Improve Our
Systems and Our Use Of Data’ which have a positive impact on digital
transformation, inclusion and efficacy.  These include:
• Key Action 4.1 Deliver Digital NL programme to transform customer
engagement
• Key Action 4.2 Improve systems and processes to enable integrated asset
management approach
• Key Action 4.3 Make better use of data to drive investment decisions 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒ 
This report does not impact on any environment or carbon matters. However, the
HAMP itself has a direct impact on environmental and carbon matters through
several actions which seek to improve the energy efficiency of our homes to reduce
our carbon footprint and achieve our net zero target. 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact?

Page 6

5.9 Risk impact
Is there a risk impact?
Yes ☐ No ☒ 
There are no direct risk impacts as a consequence of this report. A risk register has
been developed and is reviewed by the HAMP Steering Group and HAMP Board on
a quarterly basis, with risk also recorded on the service’s risk register and managed
accordingly. 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g., Corporate or Service
or Project Risk Registers), and how they are managed?

Page 7

Homes Fit for The Future 
North Lanarkshire Council
Annual Review of Housing
Asset Management Plan 
2021/22

Page 8

Contents 
Introduction                                             3 
Strategic Policy Framework       4 
Our Priorities          4
Priority 1: We Deliver the Homes North Lanarkshire Needs to Grow 5
Priority 2: We Provide High-Quality, Well-Maintained Homes  6
Priority 3: We Tackle Climate Change and Fuel Poverty   6
Priority 4: We Improve Our Systems and Our Use of Data   7 
Action Plan          9

Page 9

Introduction
This is the first Annual Review of the Housing Asset Management Plan since the production
of Homes Fit for the Future, the Council’s Housing Asset Management Plan (HAMP) 2021-
2026.  The HAMP produced in 2021 is a high-level plan, which sets out our ambitions and
priorities with key actions for delivery over the next five years. 
This Annual Review and the action plan outline progress on these actions. Significant
progress has been achieved over the last year with some key highlights of progress made
on key indicators including: 
The Annual Review of the Housing Asset Management Plan has identified and reflected on
key considerations which impact on delivery including COVID-19, inflationary cost increases,
material and labour shortages. 
Strategic Policy Framework
Homes Fit for the Future is North Lanarkshire’s plan for managing its housing assets over
the five-year period 2021 to 2026 and aligns with The Plan for North Lanarkshire as well as
other key strategies, policies and plans.  The HAMP is closely aligned with the North
Lanarkshire’s Local Housing Strategy (LHS) providing the strategic framework for asset
management activities and investment over the next five years.
Our Priorities
Our housing asset management activities are focused around four key priorities over a five-
year period to ensure our homes are fit for the future: These priorities are:
• We deliver the homes North Lanarkshire needs to grow
• We invest in our housing stock and deliver high-quality, well-maintained homes 
• We tackle climate change and fuel poverty 
• We improve our systems and our use of data 
3 Includes homes acquired through the Open Market and Empty Homes Purchase Schemes
Highlights up to 2021/22
1494 New homes since 20103 
57 New wheelchair homes since 2010 
562 Homes bought back into council ownership
588 Of our homes have had a new kitchen installed in 2021/22
822 Of our homes have had a new bathroom fitted in 2021/22
1045  Homes with new heating systems in 2021/22
761 Homes with roof and render improvements in 2021/22
3.2 Average hours in completing emergency repairs faster than previous years
(2020/21: 4.3)
0 Failures to meet gas safety regulations during 2021/2022
99.2% Homes meet the Energy Efficiency Standard for Social housing in 2021/22

Page 10

The Housing Asset Management Steering Group and Board provide the governance
arrangements for monitoring progress of these priorities and actions on a quarterly basis
throughout the year.
Progress on these four priorities during 2021/22 are outlined below highlighting key
successes and challenges. The action plan indicates the RAG status of each action using
green (on track), amber (minor delays) and red (significant delays).
Progress on our key actions:
Deliver NL Homes Programme 
We have delivered 14944 new council homes and we will continue to deliver at pace to meet
our target of 1,730 new council homes by 2026 set out in the HAMP as well as our longer-
term target of delivering 5,000 council homes by 2035. Covid-19 and market changes
including inflation and resource availability continue to present challenges.  
A range of community benefits continue to be delivered through the council’s new house
building contracts, increasing employment opportunities, skills and training as well as local
business supply chain improvements.
Work has commenced to review options in relation to establishing a vehicle to deliver
alternative tenures. We are exploring a potential pilot in Airdrie Town Centre, with funding
secured to deliver a town centre demonstrator project.
Our Pathfinder Scheme, which allows us to purchase new affordable homes directly from
private developers, is progressing well. We are currently in the process of purchasing 24
homes at Lorne Place in Coatbridge, 39 homes at the former DWP offices in Coatbridge
and 20 homes at the former Orrs Department Store in Airdrie.
The Open Market Purchase Scheme continues to make a positive key contribution to
increasing the supply of council homes to meet housing need as well as tackling issues
associated with the blight of empty homes, as well as maintenance and improvement
works in mixed tenure blocks.  Over the course of 2021/22, 75 homes have been
purchased through the scheme and brought back into use. 
Develop and deliver the Towers Reprovisioning Programme 
We have demolished 209 properties during 2021/22 with the demolition programme
successfully achieving all year end targets. Phase Two of the Towers Reprovisioning
Programme will be developed, for implementation from 2025. An outline of proposals is
currently under review. Over the 2021/22 period the first two re-provisioning sites in Airdrie
have reached construction stage, with on-site development progressing well at Dykehead
Road and Northburn Place. 
4 As at 31st March 2022 and inclusive of council new build and properties acquired through the Open
Market Purchase Scheme.
Priority 1: We deliver the homes North Lanarkshire needs to
grow

Page 11

Our homes meet housing need and enable independent living 
We have installed FTTP Broadband and Cat5e cabling as standard requirement ensuring
there is digital infrastructure in all new developments, which supports telecare and telehealth
to support people to live independently in the community. We have also commenced a
technology pilot within supported accommodation and specialist older people’s housing to
identify technology solutions that can promote choice, independence and greater control for
tenants.
Reshape and repopulate our town centres  
Our key Town Centre Ambition projects are on track to proceed this year subject to the
acquisition of The Centre in Cumbernauld Town Centre proceeding this financial year.
Significant funding has been provided by the Scottish Government and UK Government for
regeneration projects.
During 2021/22, we delivered 79 council homes in town centres and edge of town centre
locations bringing our total to 104 homes.
Town Centre visions have been developed for all eight town centres in North Lanarkshire
and work is well underway to develop action plans for each of the town centres.   To help
deliver our visions, work is underway to prepare and submit bids to supplement the council’s
own capital investment.  This includes the UK Government’s Levelling Up Fund, the Scottish
Government’s Place Based Investment Programme, the Vacant and Derelict Land Fund and
Vacant and Derelict Land Investment Programme.  
Scottish Government funding has recently been confirmed to deliver a demonstrator town
centre project in Airdrie Town Centre, which will enable learning on a national scale and
support the progression of Town Centre living in North Lanarkshire.
Some key progress over the period includes:
• Demolition of Bank Street, Coatbridge to enable residential development
• Detailed designs and plans produced to convert the former Municipal Buildings at
Kildonan Street, Coatbridge into residential accommodation
• Completion of Broomknoll Street town centre site in Airdrie, delivering 30 new homes
by Clyde Valley Housing Association
• Demolition of the former Orrs department store for residential redevelopment
• Creation of a new active travel link connecting Abronhill with Cumbernauld Town
Centre
• Acquisition of the Old Town Hall in Motherwell for conversion to residential use
• Acquisition and demolition of the former office building Kingshouse, Wishaw for
residential redevelopment
• Commencement of construction works on the former Tesco site in Wishaw to create
new housing, scheduled for completion later in 2022
• Properties re-developed on Buchanan Street and Graham Street in Airdrie to deliver
both commercial and residential accommodation

Page 12

Progress on our key actions:
Ensure our homes are fire safe and meet new legislative requirements 
We undertake fire risk assessments for all properties that are at high risk.  These include our
towers and retirement housing complexes.  Fire and smoke alarms are installed in all of our
homes with work successfully completed over the period to meet the new legislative
requirements which require all homes to have interlinked smoke and heat alarms. We have
successfully installed fire stopping in all towers not earmarked for demolition overcoming
tenant non-access for initial installations and have completed this programme of work.
Sprinkler systems have been installed in 4 towers and we are on track to have a further 17
completed by 2025, despite tenant non-access, and material and labour shortages affecting
industry.  
Invest in high-quality homes 
We have invested £13m on roof and render, £3.8m on heating, £6.5m on kitchens and
bathrooms and £4.2m on home safety and security during 2021/22. The 5-year programme
of work has been affected by COVID-19, material and labour shortages as well as cost
increases, which further impacts on our 30-year capital investment programme of work. The
potential impact of the cost of achieving Net Zero remains a significant challenge.
Re-cladding in 4 of our tower blocks is currently underway and a further 2 towers will start on
site during 2022/23. Re-cladding is a priority for us considering the Grenfell report and the
fire safety bill.
We are nearing completion of the upgrade of one link corridor retirement complex 
completion, providing enhanced facilities and environments, incorporating dementia design
principles, that promote health, wellbeing and independence, with plans developed for
improvements in a second complex. Covid-19 has had an impact on the completion
timescale as well as market changes such as inflation and resource availability.
Progress on our key actions:
Meet the Energy Efficiency Standard for Social Housing post-2020 
We commissioned consultants who completed a report on Net Zero requirements during
2021 and a further report is commissioned for 2022 on EESSH requirements in order to
meet the Energy Efficiency Standard for Social Housing post-2020. 
We have 99.2% of our properties with an EPC rating of D (SAP 55 or above), which is a 1%
improvement on the previous year. By 2025, social landlords will be unable to rent properties
rated below an EPC ‘D’.
We have delivered around £9.5m of energy efficiency improvements in North Lanarkshire
since 2016, with 1,284 private homes improved.  We upgraded 34 council homes and 35
Priority 2: We provide high-quality, well-maintained homes
Priority 3: We tackle climate change and fuel poverty

Page 13

private homes through EES: ABS during 2020/21. EES: ABS programme is being reviewed
due to an increase in technical requirements and an increased contribution from owners,
which resulted in a delay to the 2021/22 EES: ABS programme commencing. It is likely that
owner occupiers’ uptake will be reduced due to higher costs for works. 
Increase the number of homes fuelled by low carbon sources 
We are currently on-site at Dykehead Road in Holehills to pilot low-carbon technologies
utilising air source heat pumps, solar photovoltaic panels and battery storage. Building works
having commenced with initial completions anticipated between Autumn 22 and Spring 23
subject to the challenges of COVID-19, labour and material shortages and the global
economic conditions.
We are installing modern renewable technologies such as solar and PV panels as part of
roofing works. Linked batteries also being tested. Due to rising utility costs, it is now unlikely
that tenants will see a reduction in previous fuel bills.
We received Scottish Government Social Housing Net Zero Heat Fund during 2021 -22 for
£275,500 which will be utilised to provide low-carbon heat, improve energy efficiency or
tackle fuel poverty.
We developed an initial project linking to Active Travel at Dykehead Road. Active Travel
connections will be integrated to all future housing design approaches.
Progress on our key actions:
Deliver Digital NL programme to transform customer engagement 
We are undertaking digital work to deliver rents online, Common Housing Register (CHR)
online and report Antisocial Behaviour online. Additional work has been undertaken with our
Investment Team where efficiencies have been identified if technology was introduced using
online forms, online dairies and tablet devices. Work on this will continue to be progressed
over the course of the HAMP. 
We have started work on migrating performance reporting onto the new platform Power BI
for Repairs and Housing Solutions and dashboards are being developed for various parts of
the service such as Allocations, CHR and Homelessness. 
Improve systems and processes to enable integrated asset management
approach  
We continue to work on the development of a new IT system to be delivered by 2024, which
integrates asset and housing management having completed the specification of
requirements and are at the procurement stage. In the meantime, until the integrated asset
and housing management system is in place, Confirm IT system has been implemented as
an interim solution, which provides a single data repository for asset information and
surveying programmes. 
We have introduced new improvement frameworks with Senior Management giving a
strategic overview to review and determine priorities utilising performance information and
Priority 4: We Improve Our Systems and Our Use of Data

Page 14

recommending areas for audit.  Audit Plans for Housing Solutions and Housing Property and
Projects are in place and reviewed regularly to align to areas of priority within the HAMP and
risk. 
Support development of the Enterprise Strategic Commercial Partnership 
We have completed the specification for Investment and Repairs as part of the technology
workstream, which will improve asset reporting and decision making in relation to investment
for the Enterprise Strategic Commercial Partnership (ESCP). The ESCP approach will see a
single partner manage a full range of asset and infrastructure related services, from initial
feasibility, through design to delivery and construction, lifecycle maintenance and
management.

Page 15

Key Actions
Status key
Indicator Definition 
On track, budget, within scope and likely to deliver expected benefits 
Minor delays, cost overruns, changes to scope or reductions in benefits 
Significant delays, cost overruns, changes to scope or reductions in benefits  
PRIORITY 1: WE WILL DELIVER THE HOMES NORTH LANARKSHIRE NEEDS TO GROW 
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022 TIMESCALE LEAD RAG
STATUS PROGRESS UPDATE CHALLENGES
KEY ACTION 1.1 
Deliver NL Homes
Programme    
Contribute to
5,000 new
Council homes
by 2035
1,730 new
Council
homes
1,218
(estimate as at
March 2021) 
1282  1494 2026 New Supply   Completions on track to achieve
targets.
Covid-19; Market
changes including
Inflation and resource
availability.
Establish 
vehicle to deliver
alternative
tenures
Vehicle
established
Subject to
future
committee
report and
approval 
Some
research
undertaken
with SFT to
ascertain
viability of
alternative
tenures in NL 
On track –
see progress
update 
2023 Business
Development
& Support/
New Supply  
Work commenced to review
options; Joint working with BDS
& Growth regarding pilot in
Airdrie Town Centre being
progressed by the Growth Team.
Currently there is not a
viable financial model
that would support an
arm's length vehicle to
deliver alternative
tenures. This will be
further explored with
Scottish Futures Trust.
An interim strategy is in
place to support RSLs to
deliver Mid-Market Rent
in North Lanarkshire.

Page 16

PRIORITY 1: WE WILL DELIVER THE HOMES NORTH LANARKSHIRE NEEDS TO GROW 
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022 TIMESCALE LEAD RAG
STATUS PROGRESS UPDATE CHALLENGES
Review and
update
Development
Pathfinder
approach
Review
complete
2019/20 - pilot
launched  
Orrs (20) /
Lorne Place
(24)/ DWP
Offices (39)
2021 New Supply   Prior Information Notice (PIN)
refreshed 2020/21, 2021/2022.
Projects are Former Orrs
Department store, Airdrie
(Wilson Developments Ltd; 20
units) started onsite 04 April
2022, Lorne Place, Coatbridge
(Allanwater Homes; 24 units).
committee approval delivery
dates TBC. The former DWP
building, Coatbridge (ML5 Ltd;
39 Units) - committee approval
delivery dates TBC. New Supply
Team will continue to engage
with developers that register
interest in the scheme.  
KEY ACTION 1.2 
Develop and deliver
the Towers
Reprovisioning
Programme 
Deliver Phase
One, comprising
1,750
demolitions with
sites cleared for
future
investment
1,750
demolitions
with sites
cleared for
future
investment
2019/20 - 27
properties
demolished
2020/21 - 165
properties
demolished 
2021/22 -
209
properties
demolished 
2025 Investment/
New Supply  
Excellent progress has been
made with the demolition
programme achieving all year
end targets.
External factors
increasing project costs
and resource availability. 
Phase Two
developed, for
implementation
from 2025
Programme
developed
N/A Under
development
Outline
proposals
under review
2024 Investment/
New Supply  
Options appraisal issued to
Heads of Service for
consideration. 
Demand analysis vs
building condition.
Environmental
considerations.

Page 17

PRIORITY 1: WE WILL DELIVER THE HOMES NORTH LANARKSHIRE NEEDS TO GROW 
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022 TIMESCALE LEAD RAG
STATUS PROGRESS UPDATE CHALLENGES
KEY ACTION 1.3 
Our homes meet
housing need and
enable independent
living          
Carry out
options
appraisals for all
linked corridor
retirement
housing and
supported
accommodation
complexes
Appraisals
complete
N/A  Initial
appraisal
undertaken
Initial
appraisal
undertaken,
with
Dundyvan
Gardens
nearing
completion 
2023 Housing
Solutions 
GREEN Initial options appraisal exercise
complete for all linked corridor
complexes.  Further, more
detailed options appraisal
planned for 2023 to inform
investment requirements. 
Covid-19; Market
changes including
Inflation and resource
availability.
Develop and
implement
methods to
identify adapted
properties prior
to matching
New process
developed
and
implemented
N/A    See
progress
update 
2025/26 Housing
Solutions/
Repairs and
Maintenance 
GREEN Agilysis had prepared a
discovery action plan and
identified this as a requirement
of the new housing asset
management system. 
Automatic matching likely stored
asset information would require
to be part of a new integrated
housing management system,
which is part of key action 4.2
‘develop new I.T. systems that
integrate asset management’.   
Capacity already in place to
enable identification of adapted
properties prior to matching.  
. 
Develop
interactive smart
home standard
for use in new
build homes
New
standard
developed
2020 - in
development
Base digital
infrastructure
standard
adopted in
Employers
Requirement /
Specification 
Overarching
Digital
Standard in
Draft
2023 New Supply GREEN On-going determination to be
expanded with other services to
complete.

Page 18

PRIORITY 1: WE WILL DELIVER THE HOMES NORTH LANARKSHIRE NEEDS TO GROW 
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022 TIMESCALE LEAD RAG
STATUS PROGRESS UPDATE CHALLENGES
Ensure digital
infrastructure in
new homes
supports
telecare and
telehealth
Ensure
access to
high-speed
broadband
N/A FTTP & Cat5e
cabling
installed as
standard in all
new
developments 
Complete Ongoing New Supply  GREEN Complete.  
Pilot Smart
Homes
technologies at
Kerr Grieve
Court
Pilot
complete
2020 - in
development  
Working
group
established,
with some
aspects
progressed,
in addition to
other
technology
projects (see
progress
update)
2023 Housing
Solutions/
Investment 
GREEN Smart homes technology was
showcased in Allershaw mainly
due to COVID-19 via technology
flat but work continues to be
developed to test technology
options for improve health,
wellbeing and independence. 
Technology pilot underway in
supported accommodation,
piloting a range of ‘property’
sensors and technology to
improve choice, control and
capacity to manage. 
Impact of COVID-19.
Review policy for
adapting
unsuitable
properties
Review
complete
N/A   Work carried
out to
ascertain
extent/scale
of issues
2022 Repairs and
Maintenance 
AMBER Allocation policy review planned
to commence Oct 2022 which
will inform policy for adapting
unsuitable properties.  Some
preliminary work carried out to
date which identifies issues and
scope for improvement.

Page 19

PRIORITY 1: WE WILL DELIVER THE HOMES NORTH LANARKSHIRE NEEDS TO GROW 
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022 TIMESCALE LEAD RAG
STATUS PROGRESS UPDATE CHALLENGES
KEY ACTION 1.4 
Help reshape and
repopulate our town
centres  
Identify and
progress key
regeneration
projects
Invest at
least £14m in
key town
centre
Ambition
projects, with
a particular
focus on
residential
development
and
conversion
N/A    On track 2023 Growth  GREEN Target due to be met this year
subject to acquisition of The
Centre Cumbernauld Town
proceeding this financial year. 
Significant funding
provided by the Scottish
Government and UK
Government for
regeneration projects.
There are unrealistic cost
expectations when
acquiring sites,
regeneration tends to be
associated with difficult
development sites, and
rising costs.
Deliver and
enable new
homes in town
centre and edge
of town centre
location  
Contribute to
all-tenure
target for
housing in
the town
centre
2019/20 - 0 25 NLC
completions
79 NLC
completions -
providing
104 to date
2023 New Supply  GREEN Currently no further TC/EoTC
completions anticipated until
2023/24. 
Identification of Town
Centre sites, Utilities and
Market Price Increases. 
PRIORITY 2: WE PROVIDE HIGH-QUALITY, WELL-MAINTAINED HOMES  
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021  
UPDATE
2021/2022 TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
KEY ACTION 2.1 
Deliver planned and
cyclical maintenance
programme
Complete annual
gas safety
checks at all
gas-fuelled
homes
100% 2019/20 -
100%
compliance 
100%
compliance 
100%
compliance
Ongoing Repairs and
Maintenance 
GREEN  100% compliance.

Page 20

PRIORITY 2: WE PROVIDE HIGH-QUALITY, WELL-MAINTAINED HOMES  
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021  
UPDATE
2021/2022 TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES  
Ensure all
homes are
periodically
tested for
electrical safety
100% of
properties
have a test
within
previous 5
years
2019/20 -
100%
compliance
100%
compliance
70%
compliance
Ongoing Repairs and
Maintenance 
AMBER 70% compliance.
The additional tests required
have been added to the 2022/23
programme and will be
completed this financial year
2022/23.  
KEY ACTION 2.2 
Ensure our homes are
fire safe and meet
new legislative
requirements        
Inspect high-risk
properties
(retirement
housing
complexes,
supported
accommodation,
towers) and take
remedial action
as necessary
100% annual
inspection
2019/20 -
100%
compliance   
See
progress
update –
high risk
properties
assessed for
fire safety
Ongoing  Investment  GREEN Fire Risk Assessments for high
risk properties including towers
and retirement housing
progressed by in-house HS team
& issued on a monthly basis. No
Investment actions to date.    
Install fire and
smoke alarms in
all homes
100%
completion
2019/20 - 17
towers and
9,042 homes
complete   
97%
completion –
see progress
update
2022 Investment  AMBER 97% complete remaining 3%
being installed via forced
access.  
Install fire
stopping in all
towers not
earmarked for
demolition in
Phase 1 of tower
strategy
100%
completion
2019/20 - 17
towers
complete 
2020/21 - 12
towers
complete
2021/22 - All
towers out
with Phase 1
of demolition
programme
complete
2021 Investment  GREEN Programme complete. Tenant non-access for
initial installations and in
operation damage to
doors.  
Install sprinkler
systems in all
towers
100%
completion
2019/20 - 1
tower
complete 
2020/21 - 1
tower
complete
2021/22 - 4
towers
complete
2025 Investment  GREEN Programme on target. Contracts
for a further 9 towers in
progress.  
Tenant non-access,
material and labour
shortages affecting
industry.

Page 21

PRIORITY 2: WE PROVIDE HIGH-QUALITY, WELL-MAINTAINED HOMES  
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021  
UPDATE
2021/2022 TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
Survey all low-
rise blocks and
take remedial
action as
necessary to
ensure they are
fire safe
100%
completion
N/A    Survey
programme
in
development
2024 Investment  AMBER A survey programme is in
development to assess the fire
safety works required in low rise
blocks across the authority.
There is a risk to the timescales
for 100% completion due to a
number of impacting factors
including access, owner
occupier engagement and
access to materials.  
KEY ACTION 2.3 
Invest in high-quality
homes      
Deliver 5-year
capital
programme
• Planned
spend of
£295m
including: 
• £77.1m on
new roof and
render 
• £50.5m on
heating 
• £16.1m on
home safety
and security
• £10.2m on
kitchens and
bathrooms
2020 - 5-year
capital
programme
adopted  
£13m spent
on roof and
render.
£3.8m spent
on heating.
£6.5m spent
on kitchens
and
bathrooms
£4.2m spent
on home
safety and
security
2025 Investment  GREEN Outturn figures for 2021/22
available for next update. 
Changes to the previously
planned programme being
considered based on the
identified risks.
Overall, 5-year
programme affected by
COVID, material labour
shortages, and cost
increases. 
Develop and
review 30-year
capital
investment
programme
30-year
capital
investment
periodically
reviewed
N/A    On track 2022 Investment  GREEN Impact of above on 30-year plan
also being assessed.
As above plus potential
impact of the cost of
achieving Net Zero.

Page 22

PRIORITY 2: WE PROVIDE HIGH-QUALITY, WELL-MAINTAINED HOMES  
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021  
UPDATE
2021/2022 TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
Re-clad some of
our Tower
blocks
Number TBC 2019/20 - 0
complete 
2020/21 - 0
complete
2021/22 - 4
towers re-
cladding
underway. 
Design for 2
additional
towers
underway.
2026 Investment  GREEN Reclad 4 towers in Coatbridge
due for completion 2022. Design
work for over cladding of further
2 towers starting 2022.
Grenfell report and
Central Government fire
safety bill.
Upgrade our
linked corridor
retirement
complexes
Programme
developed
N/A  2020/21 - 1
complex in
progress.
2021/22 -
one complex
nearing
completion.
Consultants
for second
complex
being
procured
2022 Investment  GREEN First upgrading project started
on site in 2021 but affected by
COVID restrictions. Second site
identified and initial brief
prepared.
Market changes including
Inflation and resource
availability.
KEY ACTION 2.4 
Tackle challenges in
mixed tenure estate  
Develop Owner
Engagement
Approach &
Training
Training
developed 
N/A    On track –
see progress
update
2023 Investment/
Private Sector 
GREEN Training module on LearnNL for
staff and elected members on
owner engagement scenarios
including simple encouragement
to full enforcement.  
Review options
for addressing
disrepair and
lack of
maintenance,
including
developing
disposals policy  
Review
complete 
N/A    Policy
implemented
(see
progress
update)
2022 Investment/
Private Sector/
Business
Solutions 
GREEN Policy recently implemented that
enables the last owner occupier
in mixed tenure blocks to sell
their home to the council and
reside as a tenant to help
address mixed tenure disrepair
and maintenance issues.

Page 23

PRIORITY 3: WE TACKLE CLIMATE CHANGE AND FUEL POVERTY 
STRATEGIC ACTION  MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022  TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
KEY ACTION 3.1 
Meet the Energy
Efficiency Standard
for Social Housing
post-2020    
Develop 'route
map' for EESSH
compliance
Route map
developed
and agreed
2020 
2020 -
consultants
commissioned  
Report
received 
2021 Investment  AMBER Report on Net Zero
requirements completed 2021.
Further report commissioned for
2022 on EESSH requirements. 
Homes meet
EPC D by
interim target
date
Homes meet
EPC D by
interim target
date
100%
compliance,
excluding
exemptions or
abeyances 
98.3% 99.2% % 2024/25 Investment  GREEN Slight increase.  
Enable energy
efficiency
improvements to
Council stock
through EES:
ABS
Enable
energy
efficiency
improvement
s to Council
stock
through EES:
ABS
2019/20 - 94
Council homes
upgraded,
enabled
through EES:
ABS funding
for 222 private
properties
34 Council
homes
upgraded,
enabled
through EES:
ABS funding
for 35 private
properties
No council or
private
homes
upgraded
Annual Investment  AMBER EES:ABS programme is being
reviewed due to an increase in
technical requirements and an
increased contribution from
owners, which resulted in a
delay to the 2021/22 EES:ABS
programme commencing. There
have also been changes to
funding as ECO 3 is finishing
and ECO 4 is due to begin. 
Owner uptake is likely to
be reduced due to higher
costs for works.
KEY ACTION 3.2 
Increase the number
of homes fuelled by
low carbon sources  
Develop new
low-carbon
homes including
trialling new
technologies on
new build sites
To deliver
pilot low-
carbon
development
utilising air
source heat
pumps, solar
photovoltaic
panels and
battery
storage
2019/20 -
plans in
development 
-  First net
zero pilot at
Dykehead
Road – see
progress
update
2023 New supply  GREEN On-site at Dykehead Road,
Holehills with building works
commenced. Initial completions
anticipated between Autumn
2022 & Spring 2023.
Works progressing
subject to impact on
labour / materials / cost
pressure from Covid-19
and global economic
conditions.

Page 24

PRIORITY 3: WE TACKLE CLIMATE CHANGE AND FUEL POVERTY 
STRATEGIC ACTION  MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022  TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
Install renewable
technologies to
existing homes
as part of
EESSH2
programme
To be
confirmed in
Housing
Energy
Strategy  
TBC  See
progress
update
TBC Investment  GREEN Modern technologies being
introduced to programmes.
Solar/PV panels being installed
as part of roofing works. Linked
batteries also being tested.
Costs of such
technologies for
mainstream programmes.
Due to rising utility costs,
tenants now unlikely to
see reduction in previous
fuel bills.
KEY ACTION 3.3 
Secure funding and
develop partnerships
to maximise impact
Apply for and
attract funding
for projects
which will
provide low-
carbon heat,
improve energy
efficiency or
tackle fuel
poverty
Funding
secured
where
available
2019/20 –
£154,500 from
Decarbonisatio
n Fund  
SG Social
Housing Net
Zero Heat
Fund 2021 -
22 £275,500
Ongoing All  GREEN 2019/20 - £35k claimed from
funding. Remaining funding
unable to be utilised due to
involvement of owners/COVID
lock down. Request made to
amend original bid to ensure full
spend refused by SG.  2021/22 -
Social Housing Net Zero Fund -  
grant claimed.  
Develop
strategic
partnerships to
innovate and
deliver on our
ambitions  
Partnerships
developed
with other
services and
external
partners
2019/20 –
Sustainable
Housing Group
established to
engage with
external
agencies   
Structures
established
internally and
externally to
explore
opportunities
and
challenges
Ongoing  Business
Development
and Support 
GREEN HAMP Steering Group and
HAMP Board oversee strategic
partnerships and priorities and
work being undertaken to
broaden and develop
partnerships to innovate and
deliver on our ambitions.

Page 25

PRIORITY 3: WE TACKLE CLIMATE CHANGE AND FUEL POVERTY 
STRATEGIC ACTION  MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022  TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
Improve
connections to
Active Travel
routes and
contribute to
delivery of the
Council's Active
Travel Strategy  
All new
development
s will link to
Active Travel
connections,
where
feasible
2021 - revised
specification
for contractors
prepared    
Initial project
linking to
Active Travel
at Dykehead
Road.
Active Travel
to be
integrated to
all future
design
approaches  
Ongoing New Supply  GREEN Active Travel to be integrated to
all future design approaches.

Page 26

PRIORITY 4: WE IMPROVE OUR SYSTEMS AND OUR USE OF DATA   
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022  TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
KEY ACTION 4.1 
Deliver Digital NL
programme to
transform customer
engagement  
Achieve
efficiencies and
improve service
through
automation and
digitisation
Achieve
efficiencies
and improve
service
through
automation
and
digitisation
Complete
‘Digital Sprints’
Digital NL
programme
started within
Housing
Solutions and
Housing
Property and
Projects
Various
project
continued
under Digital
NL (HSMS
replacement,
Field
Services
development
, Housing
Services
sprints and
Investment
discovery
work)
2021-23 Business
Development
and Support 
AMBER Digital work ongoing to deliver
rents online CHR online and
report ASB online. Additional
work done with Investment
where efficiencies have been
identified if technology was
introduced through the use of
dynamics forms online dairies
etc. and tablet devices. 
Scope of works
potentially
underestimated. Limited
Resources or same
resource required over a
number of workstreams. 
Migrate
performance
reporting on to
new platform
Review
processes
and
procedures
and integrate
with
Business
Intelligence
Hub and
PowerBI
N/A BI HUB
Steering
Group
commenced to
develop use of
Power BI
Platform. First
reporting
developed for
Repairs
information.
Continued
development
of Repairs
reporting and
commenced
development
of Housing
Solutions
reporting via
work with
Agilisys/BI
HUB.    
2022 Business
Development
and Support 
GREEN Data capture complete for
Allocations & ongoing for
Homelessness.  Allocations
Dashboards being built and
Homeless dashboards being
developed.  Full Repairs
reporting still to be completed.
Getting data matched for
Repairs reporting.
Data pipelining for
Housing Solutions
projects due to different
systems in use.  Could
not transfer directly for
Housing Allocations from
CHR to BI HUB.
Pace of work for HS
required dedicated
resource.

Page 27

PRIORITY 4: WE IMPROVE OUR SYSTEMS AND OUR USE OF DATA   
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022  TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
KEY ACTION 4.2 
Improve systems and
processes to enable
integrated asset
management
approach    
Develop new IT
system which
integrates asset
and housing
management
System
developed
and in use
N/A Work started
to gather
requirements
Work
continued to
develop
specification
2024 Business
Development
and Support 
GREEN Specification complete, final
parts of the procurement
process being completed. 
Procurement paused.  
Replacement housing
management system
procurement paused at
present to ensure
alignment with other
related projects around
review of asset
management systems.
Potential Impact on
service requirements by
non- inclusion of asset
management as part of
an integrated housing
management system will
be considered as part of
discovery process.
Implement
support data
repository for
asset
information and
surveying
programmes
Repository
developed
and
implemented
N/A    Interim
solution for
data
repository
implemented
2021 Business
Development
and Support/
Investment
GREEN Complete. 
Confirm implemented as interim
solution on 1 April 2022.
See above in terms of
establishing long term
solution requirements.

Page 28

PRIORITY 4: WE IMPROVE OUR SYSTEMS AND OUR USE OF DATA   
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022  TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
Review
performance
management
framework to
ensure reporting,
audits etc. is
effective and
aligns with
HAMP priorities
Review
complete
and
recommenda
tions
implemented
N/A Audit Plans in
place to review
Processes in a
planned way
ensuring all
legislative
duties
complied with
and meeting
HAMP
priorities
Review of
strategic
improvement
processes
for both
Housing
Solutions
and Housing
Property/Proj
ects to
ensure
improvement
groups focus
on
strategic/HA
MP priorities.
2021 Business
Development
and Support
GREEN Complete. 
New improvement frameworks
introduced which include Senior
Management Strategic overview
to review & determine priorities
utilising performance information
and recommending areas for
audit.  Audit Plans for both
Housing Solutions and Housing
Property and Projects in place
and reviewed regularly to align
to areas of priority and risk.
Some resource issues
meant some audits were
delayed, however
remapping ongoing in line
with areas of risk and
priority.   
KEY ACTION 4.3 
Make better use of
data to drive
investment decisions    
Carry out
research to
better identify
future demand,
making use of
available
demographic,
economic and
housing market
data
Research
programme
developed
and
completed
N/A   Pressure
analysis
undertaken
annually and
research
requirements
identified via
LHS key
actions
2023 Business
Development
and Support 
GREEN Work has started on research
surveys and demand analysis. 
Implement 'RAG'
modelling to
identify and
develop
solutions to
'cause for
concern' stock
RAG model
implemented
and reviewed
for
effectiveness
N/A    RAG
database
developed
Ongoing Business
Development
and Support 
GREEN Testing of RAG model during
2022.

Page 29

PRIORITY 4: WE IMPROVE OUR SYSTEMS AND OUR USE OF DATA   
STRATEGIC ACTION MILESTONE TARGET
BASELINE
2019/20 in
HFFF
UPDATE
2020/2021
UPDATE
2021/2022  TIMESCALE LEAD TEAM RAG
STATUS PROGRESS UPDATE CHALLENGES
Improve our
understanding of
tenants’
aspirations for
their homes
Carry out
research to
identify
tenants’
priorities for
investment
N/A    Work
underway –
on track
2022 Business
Development
and Support 
GREEN Work has started on survey
questionnaire.  
KEY ACTION 4.4 
Support development
of the Enterprise
Strategic Commercial
Partnership  
Identify
technology
requirements for
all asset
management
related activities 
Contribute to
Technology
workstream
for ESCP
tender
N/A Work ongoing
with
Investment
and Repairs
teams to
develop
specification
as part of
Technology
workstream
Complete 2021 Business
Development
and Support 
GREEN Complete. 
Requirements fed into contract
specification.  
Identify
requirements for
asset-based
activities
including
investment, new
supply and
repairs and
maintenance
Contribute to
all relevant
workstreams
for ESCP
tender
N/A    On track –
see progress
update
2021 Investment/
New Supply/
Repairs and
Maintenance 
GREEN 80% of all asset information has
now been uploaded to Confirm
to improve asset reporting and
decision making in relation to
investment.