Page 1

North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref:  BL/CB Date 10/05/23 
P014 Tower Strategy Update 
From  Brian Lafferty, Chief Officer (Housing Property Services)
Stephen Llewellyn, Chief Officer (Housing Management)  
Email stevensonjam@northlan.gov.uk Telephone 07583097785 
Executive Summary
The purpose of this report is to update Committee on current progress relating to the Tower
Strategy Programme of Work (PO14) and key achievements in the last reporting period. 
Recommendations
It is recommended that Committee: 
(i) Note the progress of the tower demolition programme (Ambition) 
(ii) Note the progress of the sprinkler installation & fire safety programme 
(iii) Note the progress of major refurbishment projects 
(iv) Approves the commencement of consultation with stakeholders in the second
phase of this re-provisioning programme as set out in Appendix 1 
(v) Notes the outcome of this phase 2 consultation will be submitted to committee
for approval in Cycle 3. 
The Plan for North Lanarkshire
Priority  Improve the health and wellbeing of our communities
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 2

1. Background 
1.1 Committee will be aware that in 2017 as part of the HRA budget motion, the council
announced its intention to commence consultation with stakeholders regarding the
potential re-provisioning of its tower estate over the next 25 years, with phase 1 of the
re-provisioning programme granted committee approval in May 2018. Significant
progress has been made to date with several high/low-rise blocks now demolished. 
1.2 Committee will also recall that in February 2018, the council approved proposals to
develop and deliver a programme to introduce enhanced fire safety measures within
high-rise towers that included retrofitting of sprinkler systems, improved fire
compartmentation, emergency lighting and installation of fire-doors to properties. 
1.3 Following committee approval in 2016 to undertake condition surveys including external
cladding assessment, internal fabric condition and structural integrity, the findings have
now been assessed with a strategic approach to remedial action in line with
government legislation developed.   
2. Report 
2.1 Demolition/Ambition 
2.1.1 The programme is progressing on schedule with 1588 from 1750 (91%) properties
identified within phase 1 now vacant. Following extensive negotiation with private
owners, only one now remains in-situ with the council exploring all options for purchase.
Detailed breakdown of the phase one programme as of October 2022 is provided in
table 1: 
Table 1
Tower Vacant Properties Status
Northburn Low-Rise, Airdrie 27 (100%) Complete
Holehills, Airdrie 138 (100%) Complete
Burnside Court, Coatbridge 44 (100%) Complete
Gowkthrapple Low-Rise 303 (99%) On Site
Shawhead Low-Rise  176 (100%) On Site
Coursington High-Rise 351 (100%) On Site
Jackson High-Rise 192 (100%)  On Site
Allershaw High-rise 41 (58%) Design Phase
Dunbeth High-rise 128 (69%) Re-programmed
High Coats  122 (64%) Re-programmed
Birkshaw High-rise 66 (94%) Re-programmed
TOTAL    1588 (91%) 
2.1.2 The contract to demolish the 19 low-rise blocks at Gowkthrapple, Wishaw has recently
been awarded and site establishment is underway. One private owner remains present,
and approval has been received at the Planning Committee in November 22 to
purchase the property via a compulsory purchase order (CPO). 
2.1.3 The contract to demolish 11 low-rise blocks at Shawhead, Coatbridge continues, and
a new haulage road aimed at reducing traffic congestion in nearby streets in complete

Page 3

and in use. Unfortunately, the contract has experienced delays due to contractor
performance and service disconnections which the council delivery team are managing
in accordance with the contract conditions. 
2.1.4 Demolition of the three high-rise tower blocks at Coursington, Motherwell has
commenced with demolition of 12-14 Draffen Street and surrounding structures.
Careful deconstruction of the tower superstructures is in progress with mast-climbers
in operation. Nearby residents are being notified of ongoing works. 
2.1.5 The contract to demolish Jackson Court, Coatbridge has been awarded with site
establishment and soft strip ongoing. This will be a landmark demolition project within
the programme and will transform the surrounding area. 
2.1.6 High Coats and Birkshaw Tower remain part of the phase 1 demolition programme with
proposed dates for demolition to be confirmed in due course. Details of repurposing of
these towers noted under section 2.3.3. 
2.1.7 It is proposed to undertake consultation regarding the next phase of this strategy. 
Following consideration of a number of factors, including waiting list demand; stock
turnover and investment requirements, the second phase of the proposed re-
provisioning programme has been identified and is attached at Appendix 1.  It is
proposed that consultation will be progressed with stakeholders affected by these
proposals using a range of methods, including newsletters, open days, meetings with
tenants and residents groups and surveys.  In addition to undertaking stakeholder
consultation, option appraisals will also be progressed for each of priorities identified in
Appendix 1, taking into account the future potential investment requirements of the
blocks, informed by the current survey programme, as well as factors such as demand;
availability of other housing stock and land.  The re-provisioning programme, subject
to consultation outcomes, continues to represent the long term strategy for the multi
storey flats. 
2.2 Sprinkler / Fire Safety Programme 
2.2.1 Phase 1 of the sprinkler installation programme at Burnside, Lodge & Doonside Tower,
Motherwell has now reached practical completion with snagging works ongoing. 
2.2.2 Phase 2 of the sprinkler installation programme comprising of towers at Glassford,
Woodside, Glen, Coltswood and Redbridge are currently in progress. Tenant
consultation continues outlining the impact of the works and access requirements. 
2.2.3 The fire safety programme which includes installation of emergency lighting, fire-doors
to properties and improved compartmentation/fire-stopping is now complete. In line with
recent change in legislation, interlinked smoke detection has also been installed within
properties. 
2.3.4 A contract to remove all spandrel panels to stairwells in 13 towers (recommendation
following the Grenfell report) is also in progress with completion scheduled for May
2023. 
2.3 Major Refurbishment Projects 
2.3.1 Refurbishment of the tower blocks at Blairgrove/Merryston (Lot 1) and Glen/Millbrae
(Lot 2) is complete, snagging works continue.

Page 4

2.3.2 Specialist consultants have now been appointed to provide design services in relation
to the recladding and internal refurbishment of Whifflet and Calder towers, Coatbridge. 
2.3.3 In order to support displaced citizens affected by the war in Ukraine, North Lanarkshire
Council committed to reinstate circa 200 properties on a temporary basis. The
properties, located within tower blocks in Coatbridge (High Coats) and Wishaw
(Gowkthrapple) are now refurbished with furniture fit out continuing. Several families
are now in place.   
3. Measures of success 
3.1 The plans contained within this report will help to improve housing conditions and
housing choice for our residents which contributes to addressing inequality.       
4.  Supporting Documents 
4.1 Appendix 1 
Brian Lafferty     Stephen Llewellyn               
Chief Officer (House Property Services)  Chief Officer (Housing Management)

Page 5

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Any financial impact of the measures implemented will be contained within the HRA
Capital Investment budget and will be drawn down via borrowing/CFCR as required
and reported to committee. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☒ No ☐
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Statutory compliance with Building Standards and recent fire safety legislation. 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk

Page 6

Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Upgrading of external building fabric to current energy standards. 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☒ ☐ No ☐
If Yes, please provide a brief summary of the impact? 
Reprovisioning of towers and low-rise blocks must be included in regular corporate
communications. 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
Risks are considered, frequently reviewed and recorded on project-specific risk
registers. Risks with an inherently high score are escalated to project board/service
level. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 7

Appendix 1
PA1:D19otential Phase 2 Reprovisoning
Sites     
Address Total No of
Properties 
No of
Owner
Occupiers
Motherwell/Bellshill    
Anderson Tower 67 1
Oakfiled Tower 67 0
Albion Tower 67 0
Airbles Tower 67 0
Whammond Tower 66 0
Shields Tower 104 0
Woodside Tower 104 0
1-56 McClurg Court 56 1
Total 598 2
Coatbridge/Kilsyth    
Witchwood Court 85  
24-32 Rennie Rd 5 1
34-42 Rennie Rd 5 1
44-50 Rennie Rd 4 1
73-81 Rennie Rd 5 0
83-91 Rennie Rd 5 1
93-101 Rennie Rd 5 1
103-111 Rennie Rd 5 0
113-121 Rennie Rd 5 1
123-131 Rennie Rd 5 0
133-141 Rennie Rd 5 1
143-151 Rennie Rd 5 0
153-161 Rennie Rd 5 0
Total 144 7
Airdrie/Cumbernauld    
53 - 62Kennedy Drive 10 0
63 - 72 Kennedy Drive 10 0
73 - 82 Kennedy Drive 10 0
83 - 92 Kennedy Drive 10 1
1 - 19 Glencraig Street 10 0
22 - 40 Kippen Street  10 1
42 - 60 Kippen Street 10 0
3-21 Kippen Street 10 2
23 - 41 Kippen St 10 0
43 - 61 Kippen St 10 1
63 - 81 Kippen St 10 2

Page 8

83 - 101 Kippen St 10 3
Total 120 9      
Wishaw/Shotts    
10 - 30 Greenfield Drive 11 0
32- 52 Greenfield Drive 11 0
54 - 74 Greenfield Drive 11 0
76 - 96 Greenfield Drive 11 0
382-410 Glasgow Rd 15 1
412 - 434 Glasgow Rd 12 0
436-464 Glasgow Rd 15 0
236 - 284a Main Street 26 0
TOTAL 112 1   
Overall Total 974 19