North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref SL/GT/AN Date 10/05/23 
Revenue Monitoring Report – Housing Revenue Account 
From  Stephen Llewellyn, Chief Officer (Housing Management)  
E-mail telferg@northlan.gov.uk Telephone
Greg Telfer, Business
Finance Manager, 07586
010692 
1. Background 
1.1 The Council approved its Housing Revenue Account Budget of £149m on 17 December
2021. This has increased to £154m with the utilisation of the £2.5m reserve set aside
for use within housing repairs, currently under pressure as a result of higher than
anticipated contract inflation (see 2.2.2) and Ambition related virements. 
1.2 The Financial Regulations require Services to remain within their approved budgetary
provision, and to report all significant deviations – defined as the higher of £100,000 or
5% - within their budget monitoring reports. Where significant deviations are identified,
Services must provide explanatory commentary, outline the action required to rectify
Executive Summary
This report provides a summary of the Housing Revenue Account financial performance
for the period 1 April 2022 to 3 March 2023 (Period 12). The report illustrates the projected
outturn as at 31 March 2023, with major outturn variances highlighted and explained in
accordance with the Council’s approved Financial Regulations. 
The service is currently projecting an underspend of £1.067m for the financial year. This
projected year end surplus will be allocated to the Rent Assistance Fund in line with the
Council’s HRA budget decision on 23 February 2023. 
It is currently anticipated that £1.849m of savings (100%) will be delivered by the financial
year-end. 
Recommendations
It is recommended that Committee:
1) Acknowledges the financial position of the HRA revenue budget 2022/23. 
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

such a deviation, and where relevant, must also highlight the impact this has on other
budget headings. 
2. Report 
2.1 Summary of Financial Position 
2.1.1 The service is currently projecting an underspend of £1.067m for the financial year.
This projected year end surplus will be allocated to the Rent Assistance Fund in line
with the Council’s HRA budget decision on 23 February 2023. 
2.2 Analysis of Significant Variances 
2.2.1 The Housing Revenue Account currently anticipates an underspend of £1.400m within
Employee Costs due to increased turnover / vacancy savings. This also includes an
additional saving of £0.055m due to the UK Government’s decision to reverse the
increase in National Insurance Contributions. 
2.2.2 In addition, an overspend of £2.607m is anticipated within Property Costs mainly as a
result of increased repair costs (£4.500m) due to the current economic climate and
contract inflation, however with the drawdown of the repairs earmarked reserve of
(£2.500m) this will be reduced to (£2.000m). Other overspends include utilities
(£0.306m), void rent loss (£0.120m), grounds maintenance (£0.215m) and rents
(0.050m). These are partially offset by savings within Council Tax (£0.140m) and other
minor savings (£0.070m). 
2.2.3 An underspend of £0.300m is projected within Administration Costs as a result of
reduced legal fees (£0.100m), sheriff officer fees (£0.140m) associated with the
restrictions placed on evictions partially offset by a combination of minor variances
(£0.030m). 
2.2.4 An overspend of £0.120m is projected within Apportioned Expenses due to additional
ICT related costs partially offset by savings within First Stop Shops (£0.275m) and
Customer Contact Centre (£0.020m). 
2.2.5 The service projects an underspend of £1.634m on borrowing costs as a result of both
proactive treasury management activity reducing average loans funds interest rates
and lower than anticipated capital expenditure during the previous financial year. In
addition, Members should be aware that consideration is currently being given to the
implementation of the option of a loan debt holiday, which is one of the fiscal flexibilities
introduced by the Scottish Government, initially to support the cost of COVID.  If
implemented this will generate a further one-off saving in 2022/23.  However, it should
be noted that this does not change the overall debt to be repaid and any benefit
generated will need to be repaid within the shorter of either the remaining period of the
loans fund advance or twenty years. The decision on this will be reviewed by the Chief
Officer (Finance) as part of the year end closedown. 
2.2.6 An anticipated underspend of £1.107m is anticipated within Ambition funding. Ambition
funding represents budget increases from previous rent rises not yet applied to service
spending linked to increased capital investment. 
2.2.7 An under-recovery of £0.670m is being projected within rental income. This is mainly
due to the number of properties brought back into use through the Open Market
Purchase Scheme being lower than budgeted due to increased demand on the open
market and a reduced number of HRA properties being utilised for homelessness.

Page 3

2.2.8 An under-recovery of £0.304m in Fees and Charges due to the temporary removal of
charges for laundry facilities as the service seeks to introduce new payment technology
(£0.105m), a reduction in court activity (£0.115m) and a reduced charge to HRA Capital
Programme (£0.092m). 
2.2.9 An over-recovery of £0.117m within Department Charges is due to recharges of HRA
staff costs to HEEPS/ABS programme.   
2.3 Earmarked and One-off Resources 
2.3.1 An update of the earmarked reserves is detailed in Appendix 2. When account is taken
of the £1.470m core reserve, and other previously earmarked reserves totalling
£12.871m, the remaining unallocated resources total to £5.155m. In line with the
2023/24 HRA budget decision, £3.088m of reserves will be utilised to support cost
pressures on a one-off basis during 2023/24. 
2.4 2022/23 Budget Savings 
2.4.1 The service uses a variety of information, records and processes to monitor
achievement of its approved budget savings of £1.849m. As at Period 12, it anticipates
100% of its approved savings will be delivered by the financial year-end. 
3. Measures of success 
3.1 Service is currently operating within approved budgeted constraints and meeting
required savings targets. 
4. Supporting documentation 
4.1 Appendix 1  HRA Summary 
Appendix 2  Earmarked Reserves / Balance Sheet Provisions 
Stephen Llewellyn 
Chief Officer (Housing Management)

Page 4

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The financial impacts are contained within the report and supporting appendices. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒

Page 5

If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
All activities undertaken by the council are subject to risk, and in acknowledging the
Council’s approved Risk Management Strategy (September 2012), Services manage
these as part of their overall corporate and service planning process. The current
economic climate, in particular, has the potential to impact upon the Council’s ability
to provide quality services within approved budget levels. 
Reflecting the risk analysis matrix included within the Risk Management Strategy, the
Service considers the impact of inflation on key service contracts and the cost of living
crisis presents an ongoing risk to the financial outturn for 2022/23 and this is an
ongoing focus of discussion within the Service and with Financial Solutions. 
To minimise risk, this report has been prepared by service-based Financial Solutions
personnel in consultation with budget managers, in accordance with the Financial
Regulations
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 6

Appendix 1 
FINANCIAL MONITORING REPORT DIVISION : HRA SUMMARY
01 April 2021 to 3 FEBRUARY 2022 (Period 11) Cost Centre: HRA [H]
COMMITTEE:  HOUSING
CATEGORY BUDGET ACTUAL YEAR TO DATE ANNUAL PROJECTED ANALYSIS
TO DATE TO DATE VARIANCE BUDGET OUTTURN
(1) (2) (3) (4) (5) (6) (10)
£ £ £ £ £
EMPLOYEE COSTS 23,528,123 22,603,489 924,634 FAV 29,312,183 27,912,183 1,400,000 FAV Underspend due to increased turnover savings and National
Insurance Contributions threshold changes
PROPERTY COSTS 44,441,017 44,941,119 (500,102) ADV 56,823,690 59,430,690 (2,607,000) ADV Overspend mainly due to increased repair, grounds maintenance,
utility, rental costs and void rent loss. These overspends are
slightly offset by underspends in the garden assistance scheme.
SUPPLIES & SERVICES 575,554 580,548 (4,994) ADV 782,400 782,400 0 - Balanced Budget
TRANSPORT & PLANT 301,340 307,177 (5,837) ADV 367,140 367,140 0 - Balanced Budget
ADMINISTRATION COSTS 1,758,866 1,497,697 261,169 FAV 5,490,900 5,190,900 300,000 FAV Underspends due to decreased legal and sheriff officer fees
PAYMENTS TO OTHER BODIES 101,876 100,112 1,764 FAV 231,120 231,120 0 - Balanced Budget
APPORTIONED EXPENSES 2,295,265 2,324,822 (29,557) ADV 7,279,960 7,399,960 (120,000) ADV Increased IT Support Costs
CAPITAL FINANCING COSTS 0 0 0 - 22,408,280 20,774,280 1,634,000 FAV Underspend due to proactive treasury management activity
C.F.C.R. 0 0 0 - 27,146,260 27,146,260 0 - Balanced budget
OTHER COSTS 0 17,787 (17,787) ADV 4,994,497 3,887,497 1,107,000 FAV Ambition
TOTAL EXPENDITURE 73,002,041 72,372,751 629,290 FAV 154,836,430 153,122,430 1,714,000 FAV
OTHER GRANTS 0 0 0 - 0 0 0 - Balanced budget
FEES AND CHARGES 452,587 299,624 (152,963) ADV 7,887,859 7,687,859 (200,000) ADV Under recoveries within laundry charges and court dues / fines
RENTS 105,666,201 105,441,345 (224,856) ADV 143,783,481 143,336,481 (447,000) ADV Under-recovery in Rental Income due to lower OMPS activity
INTEREST 0 0 0 - 15,000 15,000 0 - Balanced Budget
DEPARTMENTAL CHARGES 0 (4,633) (4,633) ADV 90 90 0 - Balanced Budget
SURPLUS 0 0 0 - 3,150,000 3,150,000 0 - Utilisation of Housing Repairs reserve
INCOME 106,118,788 105,736,336 (382,452) ADV 154,836,430 154,189,430 (647,000) ADV
NET EXPENDITURE (33,116,747) (33,363,585) 246,838 FAV 0 (1,067,000) 1,067,000 FAV
FAV = Favourable variation, underspend etc 362,119            
ADV = Adverse variation, overspend, income under-recovery etc
PROJECTED OUTTURN
VARIANCE
(7)

Page 7

Appendix 2 
DESCRIPTION OF EARMARKED
RESERVES
VALUE OF
EARMARKED
RESERVE
CARRY FORWARD ANALYSIS
VALUE %
(1) (2) (3) (4) (5) (6)
£ £ £
Ambition 5,054,483 889,000 82.4% 4,165,483 Balance required in future years
Welfare Reform 259,869 0 100.0% 259,869 Utilisation of balance to be considered
UCAF 739,880 381,179 48.5% 358,701 Balance of funding required in future years
Hardship Fund 82,423 82,423 0.0% 0 Fund fully utilised in 22/23
Rent Assistance Fund 497,990 497,990 0.0% 0 Additional funding approved for 23/24
Enterprise Contract 670,793 670,793 0.0% 0 Budget fully utilised
Rent Restructure 565,469 230,883 59.2% 334,586 Balance required in future years
Housing Repairs 2,500,000 2,500,000 0.0% 0 To fund 2022/23 repairs programme
HRA Capital Programme 2,500,000 0 100.0% 2,500,000 Allocated as part of the 23/24 HRA Revenue Estimates
SUB TOTAL 12,870,907 5,252,268 59.2% 7,618,639
Change Management/Risks & Uncertainty 5,154,712 0 0.0% 5,154,712 Available for future allocation
Core Reserve 1,470,000 0 100.0% 1,470,000 No call anticipated in 2022/23
TOTAL 19,495,619 5,252,268 73.1% 14,243,351
PROJECTED OUTTURN
North Lanarkshire Council
Housing Revenue Account - Earmarked Reserves
01 April 2021 to 3 MARCH 2022 (Period 12)