North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref AN/GT Date 10/05/23 
HRA Capital Monitoring Report – 1 April 2022 to 03 March 2023 
From  Brian Lafferty, Chief Officer (Housing Property Services)  
E-mail Telferg@northlan.gov.uk Telephone
Greg Telfer, Business
Finance Manager, 01698
302836 
Executive Summary
The purpose of this report is to review progress towards agreed spending plans within the
2022/23 HRA capital programmes. 
An overspend of £1.916m is projected for the Mainstream programme due to increased
material costs, approved contractor uplifts and the acceleration of some programmes,
including energy efficiency specific works, to offset contractual risks elsewhere in the
programme and support tenants due to increasing energy costs by improving the thermal
efficiency of their homes. 
The New Build Programme is projecting an overspend of £5.604m. This is mainly due to
the early availability and purchase of land and off the shelf developments not anticipated
in this financial year. This overspend has been partially offset by additional Scottish
Government grant. 
Lower than anticipated demand within the Council Buy Back and Mortgage to Rent
Schemes, an underspend of £2.206m is projected. 
Recommendations
It is recommended that Committee:
(1) Acknowledges the financial position of the 2022/23 HRA Capital Programmes.  
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

1. Background 
1.1. Mainstream Working Programme 
1.1.1 The Housing and Regeneration Committee on 16 February 2022 approved an outline
mainstream programme for 2022/23 based on targeted expenditure of £60.245m, this
has been enhanced by a further £5m to support the Ukrainian Resettlement
Programme tower refurbishment, with any additional costs fully funded by the Scottish
Government. The overall programme is funded as follows:  
£000
Prudential Borrowing  30,474
Capital Funded from Current Revenue (CFCR)
Scottish Government Grant (Net Zero) 
22,476  
2,000
Total projected resources  54,950 
Slippage allowance  5,295
Mainstream Working programme
Additional Scottish Government Grant (Ukraine) 
60,245       
5,000
Working Programme  65,245 
1.1.2 A grant of £2.242m has been awarded from the Scottish governments Net Zero Fund.
This will be utilised over two financial years with £2m allocated to 22/23 and the
remaining £0.242 included in the 23/24 programme of works. This year’s programme
has been updated to reflect the additional £2m funding. 
1.1.3 Committee also approved an additional £2.5m EESSH allowance to be utilised during
the year if conditions permit. 
1.2. New Build Programme 
1.2.1 The 2022/23 working programme for new build is £39.436m, with 170 completions
expected for the year and is funded as follows:  
£000
Prudential Borrowing 21,788
Capital Funded from Current Revenue (CFCR)   4,670
Scottish Government Grant 12,978
Total projected resources 39,436 
1.3 Council Buy Back Schemes 
1.3.1 As part of the 2022/23 Revenue Estimates, the budget provided for the continuation of
both the Council’s Empty Homes Purchase Scheme (EHPS) and the Open Market
Purchase Scheme (OMPS). This will allow approximately 130 properties to be brought
back into Council use.   
1.3.2 In addition to the EHPS and OMPS, the Mortgage to Rent scheme (MTR) was also
added to the overall Council Buy Back scheme and is anticipating an additional 3
properties to be brought back into council use in 2022/23. 
1.3.3 Funding requirements for 2022/23 for the Council Buy Back Scheme is made up as
follows:

Page 3

£000
Prudential Borrowing 6,828
Scottish Government Grant
Subsidy Income
3,900 
244
Total projected resources 10,972  
1.3.4 Approval was given at the Housing and Regeneration Committee held on the 24
November 2021 to expand the scheme to acquire homes where this would enable
planned common works to progress, with owner occupiers given the option to remain
as a Council tenant. It is estimated that this could enable a further 50 properties to be
purchased during the year. 
The target has currently remained at 130 properties due to the current buoyant property
market which may lead owners to sell on the open market, although every effort will be
made to secure as many suitable properties as possible.   
2. Report 
2.1 Mainstream 
2.1.1 A summary of the mainstream working programme and actual spend to 03 March 2023
(Period 12) is included within Appendix 1, highlighting that at this stage in the financial
year: 
• £56.865m (94% of the working programme) has been legally committed; and
• £47.362m (86% of the projected resources) has been spent. 
2.1.2 Legal commitments and spend to date are higher than historic trends and the
programme is projected to overspend by £1.916m due to increased material costs,
approved contractor uplifts and acceleration of energy efficiency related works. 
2.1.3 In order to support the Scottish Government’s Ukraine Resettlement Programme, the
Council is recommissioning two towers (Birkshaw, Wishaw and Highcoats, Coatbridge)
previously being prepared for demolition in 2023/24. Appendix 1 has been updated to
show the projected costs of £5.965m which will be fully offset fully by Scottish
Government funding with no additional cost to the Council.
2.1.4 It is anticipated that the full £2.242m Net Zero grant allocated to this financial year will
be fully spent.

Page 4

2.2 New Build 
2.2.1 A summary of projected outturn spend on the new build programme is contained within
Appendix 2. Projected spend totals £45.040m, an overspend of £5.604m, and is funded
by Prudential Borrowing, CFCR and Scottish Government Funding. 
2.2.2   There are currently eleven projects on site at Lindsaybeg Road, Chryston; Dykehead
Road, Airdrie; Northburn Place, Airdrie; Former Orrs Building, Airdrie (off-the-shelf
purchase); Castlehill Road, Wishaw; Berwick Street, Coatbridge; Gateside Farm,
Stepps (off-the-shelf purchase); Ravenscliff Road, Ravenscraig.
2.2.3    Following a revision of Scottish Water’s surface water policy, the Council is continuing
to progress financially viable solutions for connection issues that will allow a contract
award to be made at Laburnum Road, Viewpark. 
2.2.4    To date, 1,005 new build homes have been completed as part of the Council’s
ambitious new supply programme of 5,000 new homes. Currently, 496 homes are
under construction, with 117 homes expected to complete in 2022/23, subject to current
delays. 
2.2.5    Sites have been identified and approved at Committee for a further 1,332 homes across
36 sites, with site investigations, title checks and design development on these sites
progressing. 
2.2.6    The Council has appointed contractors who are progressing layouts and designs for
several sites, with site investigations underway. 
2.3       Council Buy Back Scheme 
2.3.1   A summary of projected outturn spend on the Council Buy Back Schemes is also
contained within Appendix 2.  Projected spend currently totals £7.568m collectively
between the Council buy back schemes, £7.186m attributable to EHPS and OMPS and
£0.383m to the MTR scheme. This is funded by Prudential Borrowing, Scottish
Government Funding and Subsidy Income. 
2.3.2   The original target of 130 homes to be purchased through the OMPS in 2022/23 has
been revised and the current projection is now 70 homes. This is due to lack of demand
along with more homes selling on the open market. This will be reviewed over the
remaining periods. 
2.3.3   To date, 63 properties have been brought back into use as affordable housing in
2022/23. A Scottish Government grant contribution of £1.5m was initially secured for
2022/23, with a further £0.925m grant funding approved in February 2023. 
2.3.4    Agreement has been reached with the Scottish Government to apply a sliding scale for
buy back grant funding, based on property value as follows:
• £35k grant per unit, for homes up to an £80k purchase price
• £40k grant per unit, for homes with an £80-£90k purchase price
• £45k grant per unit, for homes with a £90-£100k purchase price
• £50k grant per unit, for homes with a purchase price above £100k

Page 5

Previously, any buy back purchases were eligible for a maximum grant contribution of
£30k per unit. The new scale is applicable to any buy back grant claimed from 6
December 2022.
2.3.5    The final revenue cost of borrowing will equate to a potential drawdown of £0.218m in
2022/23 from the amounts set aside for “Our Ambition” 
3. Measures of success 
3.1  The successful delivery of the HRA capital programmes, providing high quality housing
stock.     
4. Supporting documentation 
4.1 Appendix 1 – 2022/23 HRA Capital Programme – Mainstream Budget Monitoring
Period 12 
Appendix 2 – 2022/23 HRA Capital Programme – New Build / Council Buy Back
Scheme Budget Monitoring Period 12 
Brian Lafferty
Chief Officer (Housing Property Services)

Page 6

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The financial implications are outlined throughout the report. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☒ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒

Page 7

If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
All activities undertaken by the Council are subject to risk, and in acknowledging the
Council’s approved Risk Management Strategy (September 2012), Services manage
these as part of their overall corporate and service planning processes. The current
economic climate has the potential to impact upon the Council’s ability to provide
quality services within approved budget levels. 
To minimise risk this report has been prepared by service based Financial Solutions
personnel in consultation with budget managers, in accordance with Financial
Regulations.
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.