North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref:  Date 10/05/23 
Housing Outline HRA Capital Programme 2023/24 
From  Chief Officer (Housing Property Services)  
E-mail BarrCa@northlan.gov.uk  Telephone 
1. Background 
1.1 Committee will recall in May 2020, a 5-year outline HRA Capital Programme from
2021/22 to 2025/26 was approved which proposed spending over £266million on the
housing stock during the lifetime of the plan. 
1.2 Further reports outlined that new priorities would be added as required based on new
priorities and further recommendations from groups such as the Scottish Government
Grenfell Inquiry Fire Safety Working Group (GIFSWG). 
1.3 In common with previous plans, the aim of the 2023/24 plan remains to ensure the
stock continues to meet the Scottish Housing Quality Standard (SHQS) as well as the
EESSH2 standard which requires all social housing meet EPC band B or is as energy
efficient as practically possible by the end of December 2032 (within the limits of cost,
technology and necessary consent). 
Executive Summary 
The purpose of this report is to seek approval from the Housing Committee for the
mainstream Housing Capital Programme (excluding new build) for 2023/24 
Recommendations 
It is recommended that the Committee: - 
1. Approve the HRA Capital Programme for 2023/24 as outlined in Appendix 1   
The Plan for North Lanarkshire
Priority  Improve the health and wellbeing of our communities
Ambition statement All ambition statements

Page 2

1.4 Significant challenges were faced by the council throughout 2022/23 in terms of the
lasting impact of the pandemic. This included issues with contractor availability as well
as the well documented nationwide issues relating to increasing costs. It is anticipated
these issues will continue to be seen throughout the 2023/24 investment programme. 
1.5 Increasing costs in all sectors have resulted in the current cost of living crisis where
specifically relating to fuel costs in a 2022 survey, Age Scotland highlighted 4 in 10
older people self-identified as feeling they were living in fuel poverty with 76% of
respondents always concerned about paying their fuel bills. 
1.6 The council has no ability to influence increasing global energy costs but committee
can be assured that actions to reduce, wherever possible, their impact are the forefront
of investment decisions proposed for tenants’ homes. More details of the type of works
proposed within the 2023/24 capital programme are provided in the report.  
2. Report 
Capital Resources – HRA Programme 
2.1 As part of the current 5-year investment plan, detailed spending proposals for 2023/24
have been prepared for Committee’s consideration as outlined in Appendix 1. 
2.2 As previously mentioned, the ongoing effect of the Covid-19 pandemic and Brexit on
the construction industry on the availability of materials and labour, has had an impact
on the phasing of the capital programme delivery and continues to do so. The 5-year
programme is summarised in the table below and demonstrates that the council
continues to aim to complete record investment in its housing stock during the 5-year
planning term. 
Table 1 
2021/22  2022/23 2023/24 Indicative
2024/26 
Total 
£000 £000 £000 £000 £000
Working Capital
Programme
74,379 60,745 70,260 141,064 346,448
Slippage  6,752 5,795 6,387 12,824 31,758
Current Capital
Programme
67,627 54,950 63,873 128,240 314,690
Reprofiled
Expenditure
(13,042) 1,916 (2,991) 14,117 -
Revised Capital
Expenditure
54,585 56,866 60,882 142,357 314,690 
2.3  Slippage allowances of approximately 10% have been added to the 2023/24
programme to arrive at a “working programme” as detailed in Section 2.4. 
2.4 The working programme (Table 2) considers the projected carry forward commitment
but may be subject to adjustment depending on the final outturn of the current 2022/23
programme.

Page 3

TABLE 2 – Resources 2023/24         
£000 
Prudential Borrowing       32,871           
Capital Funded from Current Revenue (CFCR)  22,476 
Total projected resources      55,347
Slippage allowance         5,535   
Working programme       60,882 
2.5  HRA Capital Programme details 
2.5 Heating  
2.5.1. The 2023/24 programme will see the continuation of the replacement of existing heating
systems based on their age. This programme involves installing gas condensing boilers
which, unlike older models which use energy all the time, modulate energy usage when
not needed which can save money on energy bills for users. This type of change is
important for tenants when according to the Office of National Statistics (ONS),
electricity prices in the UK rose by 66.7% and gas prices by 129.4% in the 12 months
to January 2023. 
2.5.2 The council’s programme for the installation of solar photo voltaic (PV) panels started
in 2022/23 and will continue throughout 2023/24. Such installations enable households
to use any electricity the PV panels generate for free and then pay for any further
electricity requirements they need. If households generate more electricity than they
need, it can be sold back to the National Grid. 
2.5.3 Other renewable technologies such as air source heat pump installations will also
continue to be utilised wherever appropriate to assist with the meeting of the council’s
EESSH2 and Net Zero compliance requirements. 
2.5.4 Within the 2023/24 programme there will also be an increase in the council’s loft and
cavity wall insulation programmes to improve the energy efficiency of properties. This
programme will also include for the installation of underfloor insulation to tenants’
homes where appropriate. 
2.6 Windows/Door Replacement 
2.6.1 The council experienced contractual issues relating to its triple glazing programme
within its 2022/23 programme.   
2.6.2 In February 2023, Committee approved the acceptance of new contracts for these
works meaning that the backlog of tenants for whom the programme was expected to
have new windows in 2022/23 will be prioritised throughout 2023/24 as well as
additional tenants’ homes also being able to benefit from these works. 
2.7 Roofing and Rendering 
2.7.1 The external insulation upgrading of non-traditional BISF properties continued in
2022/23 and the current programme is planned to complete in 2023/24.

Page 4

2.7.2 The upgrading of the roofs and insulation levels of non-traditional properties in the
Lomond Road area in Coatbridge also started in 2022/23 and will continue throughout
2023/24 subject to available decanting arrangements. 
2.7.3 Within 2021/22, the council introduced a significant change whereby it ended the
installing of just render to tenants’ home and introduced the fitting of external wall
insulation to tenants’ homes. The programme also introduced the installation of
integrated PV panels to re-roofing works wherever possible. These works will continue
in 2023/24 as part of the councils “fabric first” approach to improving the energy
efficiency of tenants’ homes. 
2.7.4 It should be recognised that with the change noted in 2.7.3, the costs for owners in
mixed tenure blocks that they would require to pay to have the work undertaken to their
homes have increased considerably even after the installation of any potential grant
aid. For a number of tenants in such blocks, owners’ inability to pay for such work may
have an impact on the council being able to undertake works to their homes. Wherever
possible the council will look to see if there are other options which may assist owners
to try to ensure that as many tenants as possible benefit from the installation of external
wall insulation to their homes. 
2.7.5 The council will continue to support the Scottish Government’s Energy Efficient
Scotland: Area Based Scheme (EES: ABS) for owners within its 2023/24 programme.
Following consultation with the Scottish Government on the programme, it is
anticipated that following agreement with a number of owners to pay the required
contribution towards the works, the programme will complete works to a number of
blocks also including tenants’ properties in Kilsyth in 2023/24 and look to start
discussions with owners in Bellstone non-traditional house types initially in the Wishaw
area. 
2.8 Lead pipe replacement 
2.8.1 The ongoing lead pipe replacement programme of external pipework will continue in
2023/24. 
2.9 Door Entries 
2.9.1 The council is aware the concern residents can have when door entry systems to their
blocks of flats are not working. New contractual arrangements put in place in 2022/23
will ensure that the programme for the replacement of door entry systems beyond repair
will continue throughout 2023/24. 
2.9.2 As with other works in mixed tenure blocks, owners’ inability to pay for such work may
an impact on the council being able to replace system to closes. As outlined previously,
the council will look to try to assist owners, wherever possible, in terms of their legal
requirement to maintain the common areas of blocks with options such as interest free
payment plans for up to 5 years subject to the amount of monies involved. 
2.10 Electrical Work 
2.10.1 The council will continue to ensure the safety of tenants through the undertaking of
electrical safety checks as now required as part of the Scottish Housing Quality
Standard (SHQS). An outcome of these checks could result in a number of tenants
requiring to have their homes rewired which will be undertaken as part of this proposed
2023/24 programme. Where it is deemed necessary to ensure a tenants continued

Page 5

safety these works may be undertaken via the forced entry process, previously
approved at committee in September 2021. 
2.10.2  The replacement of communal close lighting and electrical switchgear (where
appropriate) within blocks of flats will also continue in 2023/24 with works continuing to
focus initially on fully tenanted blocks and blocks with identified problems containing
owner occupiers who share repair responsibilities for these elements with the council. 
2.11 Kitchens and Bathrooms 
2.11.1 The programme for replacement kitchens and bathrooms within 2023/24 will continue
largely relating to properties where tenants have previously refused works and/or works
required in void properties. 
2.11.2 There is currently no change to the previous proposal to recommence the kitchen
replacement programme in 2025/26 based on a 20-year lifespan based on the previous
programme for replacements having started in 2005. 
2.12 Tower Strategy 
2.12.1 The replacement and refurbishment of lifts as required within our high-rise stock will
continue in 2023/24 in addition to the replacement of elements such as fans, pumps
and replacement tanks as required in terms of the council’s inspection regimes. 
2.12.2  The installation of a sprinkler system to the last remaining tower in the Flemington area
will complete in 2023/24 with the programme moving to Redbridge and Coltswood
Towers in Coatbridge later in 2023/24. 
2.12.3 The contract for upgrading works at Blairgrove/Merryston/Glen and Millbrae Towers in
Coatbridge which were significantly delayed due to the pandemic were completed in
2022/23 with additional follow-on works to the towers due to be completed within the
2023/24 programme. Work will also continue in 2023/24 with the development of the
project for the external upgrading works at Whifflet and Calder Towers in Coatbridge
with an aim of increasing the thermal efficiency of the flats for the residents of the
towers. 
2.13 Ambition 
2.13.1 The re-provisioning programme continues in 2023/24 with the completion of the
demolition of low-rise flats in Shawhead scheduled for the second quarter of 2023/24
and the continued work to demolish the high-rise towers at Coursington, Allan and
Draffen Towers in Motherwell. Contracts have also been awarded for the demolition of
low-rise blocks in Gowkthrapple and Jackson Court in Coatbridge 
2.14 Community Care 
2.14.1 Following completion of the upgrading works to the sheltered complex in Dundyvan Co,
design work continues on the development of upgrading plans for Phyllis Jane Court in
Wishaw which will be the subject of discussion with residents later in the 2023/24
financial year. 
2.14.2 It is also planned to commence work on the changeover of several existing warden call
systems to new digital system with increased service capacity in addition to the
upgrading of the electrical systems serving communal areas.

Page 6

2.14.3 Design work will also continue in 2023/24 regarding the installation of lifts between the
floors in the John Smith Court sheltered housing complex in Airdrie to improve the use
of all areas of the complex for residents. 
3         Measures of success 
3.1 Provide safe, improved and sustainable domestic properties for the tenants of North
Lanarkshire Council. 
3.2  Ensure the domestic properties within North Lanarkshire Council’s housing stock
continue to meet SHQS and improve compliance rates relating to EESSH2 and Net
Zero requirements. 
3.3 Meet the aspirations of tenants, families, and carers of residents of sheltered housing
complexes living with dementia. 
4. Supporting documents 
4.1 Appendix 1 – 2023/24 HRA Capital Programme 
Brian Lafferty
Chief Officer (Housing Property Services)

Page 7

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the
Public Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
It is anticipated that along with other proposed works that the programme
will help alleviate fuel poverty and provide warmer more affordable homes
for our residents. 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-
community/equalities/equality-and-fairer-scotland-duty-impact-assessments
Yes ☐ No ☒
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed
with Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Financial Solutions have been involved in the development of the
information contained within this report. 
Provision for the anticipated programme was noted within the 2023/24
revenue estimates process with the detailed programme included in
Appendix 1. 
As detailed in the HRA Report for 2020/21 in February 2020, new low
carbon technologies and potential procurement methodologies and
arrangements continue to be introduced into the mainstream investment
programme with the aim of ensuring EESSH2 compliance by 2032. For
2023/24 an allowance of £7.5million is included within the HRA Capital
programme in Appendix 1 which may be required to try to accelerate works
programmes subject to the restrictions detailed in Section 2.6.4. 
Use of this proposed allowance would be subject to an adjustment to each
year’s individual programme as reported to Committee and be the subject of
additional HRA borrowing. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with
People and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact?

Page 8

5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters,
statutory considerations (including employment law considerations), or new
legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with
Legal and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of
personal data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to
the data subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out
and e-mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology,
digital transformation, service redesign / business change processes, data
management, or connectivity / broadband / Wi-Fi?
Yes     ☐                   No ☒
If Yes, please provide a brief summary of the impact? 
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on
any environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The contracts awarded to deliver the HRA capital programme will assist in
promoting health and wellbeing of residents within North Lanarkshire as well
as helping reduce our carbon footprint and meet carbon management
targets. Contractors will adopt environmental and sustainability measures
and ensure environmentally friendly recycling practices are evidenced. 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed?

Page 9

Risk will be minimised and managed by designated Contract Administrators
and Managers in accordance with the works specification and the Council’s
agreed approach to Contract and Supplier Management. High level risk
reviews and risk logs will be recorded as part of the project management
process. 
5.10 Armed Forces Covenant Duty  
Does the report require to take due regard of the Armed Forces Covenant
Duty (i.e. does it relate to healthcare, housing, or education services for in-
Service or ex-Service personnel, or their families, or widow(er)s)? 
Yes     ☐                 No              ☒ 
If Yes, please provide a brief summary of the provision which has been
made to ensure there has been appropriate consideration of the particular
needs of the Armed Forces community to make sure that they do not face
disadvantage compared to other citizens in the provision of public services.

Page 10

Appendix 1 - 2023/24 HRA Capital Programme 
Programmes   TOTAL
Estate Regeneration    
Estate Regeneration Sub TOTAL £50,000      
Energy Efficiency    
Heating   £11,670,788
Windows & Doors   £6,155,530
Decarbonisation funding    £4,196,952  
Sub TOTAL £22,023,270      
Major Repairs     
Major repairs   £471,454
Roofing/Rendering   £14,330,634  
Sub TOTAL £14,802,087      
Home safety and security     
Lead Pipe replacement   £727,472
Door entry replacement   £1,119,187
Electrical work   £1,231,106  
Sub TOTAL £3,077,765      
Internal upgrading     
Kitchens   £1,231,106
Bathrooms   £2,260,758  
Sub TOTAL £3,491,864      
Tower strategy    
Tower Strategy   £10,509,212  
Sub TOTAL £10,509,212      
Community Care    
Community Care Sub TOTAL £1,377,501      
Fees/miscellaneous    
Fees/miscellaneous Sub TOTAL £5,550,000      
GRAND TOTAL   £60,881,700