North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  GT/JM Date 10/05/23 
Enterprise and Communities – Capital Monitoring Report 
From  Derek Brown, Depute Chief Executive  
E-mail telferg@northlan.gov.uk Telephone
Greg Telfer, Business
Finance Manager, 07583
010692 
1. Background 
1.1 Financial year 2022/23 is the second year of the 5 year capital programme which was
initially approved by the Policy and Strategy Committee on 18 March 2021.   
1.2 The Enterprise and Communities 2022/23 capital programme of £157.168m was
approved by the Policy and Strategy Committee on 17 March 2022. The programme
has since been increased by £5.796m relating to carry forwards from 2021/22 and was
reduced by £14.505m reprofiling to 2023/24 approved at the Council’s Strategic Capital
Executive Summary 
This report highlights the financial performance of 2022/23 Enterprise and Communities
capital programme for the period ended 3 March 2023 (Period 12). 
In summary the Service has a total capital budget of £133.810m.  At this stage in the
financial year the service is currently reporting an in-year underspend of £14.934m which
will be requested to carried forward to 2023/24 to reflect when the expenditure is now
projected to be incurred. 
Further explanation of project variances and management action taken by the Service is
included within the main report and attached appendices. 
Recommendations
It is recommended that the Committee: 
(1) Acknowledges the financial position of the 2022/23 Enterprise and Communities
capital programme. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

Delivery Group (SCDG) on 15 September 2022.  Following approval at Policy and
Strategy Committee on 1 December 2022 £0.699m budget savings were identified for
Enterprise and Communities and this reduction has now been applied to the current
budget.  Further reprofiling of £15.046m was presented and approved at SCDG on 2
February 2023.  In addition, a further £1.096m has been received in external funding
giving an overall working capital programme of £133.810m. 
1.3 The Council’s approved Financial Regulations required services to remain within their
approved budgetary provision, and to report all significant deviations – defined as the
higher of £0.100m or 5% - within their budget monitoring reports.  Where significant
deviations were identified, services must provide explanatory commentary, outline the
action required to rectify such deviations and where relevant, must also highlight the
impact this has on other budget headings. 
2. Report 
2.1 At Period 12 the service is reporting an in-year underspend of £14.934m which will be
requested to carry forward to 2023/24 to reflect when the expenditure is now projected
to be incurred. Capital budgets and expenditure are summarised into Project/Themes
(see Appendix A) 
2.2 Assets & Procurement Solutions (£2.768m Underspend) 
The division has a number of in year variances across programmed activity. The most
significant variance relates to the profile of expenditure in the Community Hub projects
(£1.601m).  This includes the previously reported £1.500m for Chryston Community
Hub based on updated contractor work programmes which indicate this spend will now
be incurred next financial year. There is also £0.200m for works for the new site for
Newmains/St Brigids Community Hub which has now been handed over, this variance
is for final internal works not affecting the operational aspect of the site. There are also
small compensating variances across other projects. 
There are underspends in the Maintaining Existing Assets category (£0.406m) across
different themes. Re-roofing projects are expected to underspend (£0.410m) due to
weather and access issues. Contractor operation issues means £0.387m will now be
incurred in 2023/24 for the toilet upgrade programme Window projects also expecting
to underspend (£0.078m) due to delays in completion of project at Langloan Primary
School. These underspends are offset in part by an increased forecast for Re-Wiring
projects (£0.251m) due to good progress being made by contractors. Works through
Active & Creative are also expected to overspend (£0.171m) due to accelerated works
on Time Capsule and Bellshill Cultural Centre.  There are also various other minor
underspends across other categories totalling £0.147m. 
Within Sustainable Estate an in-year underspend of £0.329m is anticipated. Despite
now being in contract for the project at Taylor High School for temporary modular
accommodation, a contract dispute with the successful party has delayed this project
until next financial year. 
Within Demolitions there is a forecast underspend of £0.229m, this is due to the tender
being returned for the demolition of the Bellshill Depot that has come in lower than
anticipated. This project is also no longer anticipated to complete this financial year due
to delays with disconnection of the substation.

Page 3

Curriculum Development is expected to underspend by £0.227m, this is due to
mobilisation of contractor who will not take possession of site at St Maurice’s High
School until early March 2023. 
Capital receipts initiative is also expected to underspend by £0.128m, this is due to a
re-profile of programmed works between this financial year and next. Projects at Mid-
Forrest, Palacerigg and Napier will bridge financial years. 
2.3 Environmental Assets (£3.247m underspend)
Within the Roads Asset Management Theme there is an underspend of £1.663m
anticipated in this financial year. This mainly relates to Street Lighting replacement
(£1.057m) and LED upgrades (£0.709m) where although committed the spend is now
profiled into 2023/24.  Carriageway replacement works have been accelerated to
partially offset the in-year underspend.  
The Cemeteries/Tree Infrastructure theme is projecting an underspend of £0.888m
which is largely linked to the footpath works at Cambusnethan which will be carried out
early 2023/24. 
The Infrastructure and Transportation Improvements theme is forecasting an
underspend of £0.282m. This is mainly as a result of maximising external funding in
Traffic Signals and Pedestrian Crossings (£0.396m) and Drainage & Flood Risk
Management (£0.146m). There is also an underspend in staffing costs (£0.076m)
within this area due to recruitment issues which means there are a number of vacancies
within the design team. These underspends will be used to partially offset additional
costs within the Horsely Brae project of £0.357m.  
Within the Parks Master Plan £0.211m of works related to the reconstruction of
Bothwellhaugh Cottage and £0.047m of pavilion roof works will now take place in early
2023/24.  The Litter Bin Rationalisation is now expected to underspend of £0.102m.
2.4 Regulatory Services and Waste Solutions (£0.797m overspend)
Within this projection there is an overspend / acceleration due to updated contractor
cashflows for the new Bellshill Fleet Depot (£0.713m). A further £0.284m overspend
relates to the purchasing of electric vehicles that were previously leased and have been
deemed to still have a useful life as part of the ongoing review of fleet requirements.
An underspend in HWRC Equipment (£0.247m) is partly due to delays in procurement
for upgraded CCTV cameras.
2.5 Planning & Regeneration (£9.745m underspend)
The Policy and Strategy committee on 16 March 23 agreed to proceed with the
purchase of The Centre Cumbernauld.  The sale however is now likely to conclude in
the new financial year due to the timing of the finalisation of asset management and
property management arrangements.  This results in an in year underspend of £9.5m. 
There is also a further in year underspend of £0.137m as a result of maximising external
funding these funds will carry forward and be utilised in 2023/24.

Page 4

3. Measures of success 
3.1  The Service aim is to be in a balanced budget position at financial year-end 
4. Supporting documentation 
4.1 Appendix 1 Summary Expenditure by Project/Theme 
Derek Brown
Depute Chief Executive

Page 5

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The Service aims to operate within approved funding levels and utilise budget
virements to support emerging issues and mitigate variances across budget heads. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐

Page 6

5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
All activities undertaken by the Council are subject to risk, and in acknowledging the
Council’s approved Risk Management Strategy, Services managed these as part of
their overall corporate and service planning processes.  The current economic
climate, in particular, has the potential to impact upon the Council’s ability to provide
quality services within approved budget levels. 
To minimise risk this report was prepared by service based Financial Solutions
personnel in consultation with budget managers, in accordance with the Financial
Regulations. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 7

Appendix 1
Enterprise & Communities Capital Programme 2022/23
Theme Expenditure Summary
1st April 2022 - 3rd March 2023 (PERIOD 12)
Lvl 7 Thematic Category
Revised
Budget
£
Actual
£
Committed
£
Uncommitted
£
Projected
Outturn
£
Outturn
variance
£
ASSET & PROCUREMENT SOLUTIONS
CX2A
Maintaining Existing Assets - windows, re-roofing, re-wiring
and condition survey works for the Council's building assets 9,410,255 5,839,138 8,870,763 133,011 9,003,774 406,481
CX2B Carbon Management 516,562 422,270 422,270 116,472 538,742 (22,180)
CX2C Office Rationalisation 437,811 274,502 347,285 93,286 440,571 (2,760)
CX2D Shared Campus 0 0 0 0 0 0
CX2G Leisure Development 1,410,560 1,397,260 1,397,260 0 1,397,260 13,300
CX2H Health & Wellbeing & Digital Classrooms 411,693 274,633 425,580 35,126 460,705 (49,012)
CX2I Rationalisation including ASN & Social Work 1,590,316 1,701,823 1,631,375 4,654 1,636,029 (45,713)
CX2J Curriculum Development 863,951 494,565 637,101 0 637,101 226,850
CX2K Sustainable Estate 1,198,576 701,033 871,768 0 871,768 326,808
CX2L Outdoor Education and Outdoor Spaces 343,176 377,549 377,549 0 377,549 (34,373)
CX2F Future Capital Receipts Investments 774,434 366,503 645,891 0 645,891 128,543
CX2M Design Fees 1,469,383 835,597 1,469,176 0 1,469,176 207
CX2O 1140 Early Learning and Childcare Expansion 1,970,737 1,303,697 1,393,446 587,626 1,981,072 (10,335)
CX2E Demolitions 510,383 167,677 281,212 0 281,212 229,171
TOTAL ASSET & PROCUREMENT SOLUTIONS 20,907,837 14,156,248 18,770,675 970,174 19,740,850 1,166,987
TOWN AND COMMUNITY HUBS
CX2N Town and Community Hubs 47,573,752 39,006,783 45,322,161 650,385 45,972,546 1,601,206
TOTAL TOWN AND COMMUNITY HUBS 47,573,752 39,006,783 45,322,161 650,385 45,972,546 1,601,206
ENVIRONMENTAL ASSETS
CX9A Infrastructure and Transportation Improvements 8,485,014 6,466,952 8,088,778 114,671 8,203,450 281,564
CX10A Greenspace infrastructure Health & Wellbeing 1,005,630 267,258 961,181 15,289 976,470 29,161
CX11A Parks Masterplans 2,954,307 1,399,624 1,881,992 814,571 2,696,563 257,743
CX11B Environmental Assets replacement of plant and machinery 772,601 555,176 746,321 0 746,321 26,280
CX12A Cemeteries/Tree Infrastructure 1,608,030 208,494 608,762 111,675 720,437 887,593
CX13A Road Asset Management including street lighting, road
improvements and gateway signage 11,901,142 6,831,863 10,231,864 6,321 10,238,185 1,662,957
CX13B Bin rationalisation project and replacement 137,742 35,787 35,787 0 35,787 101,955
CX13D Play Area Equipment and surface renewal 213,145 122,660 213,145 0 213,145 0
TOTAL ENVIRONMENTAL ASSETS 27,077,611 15,887,814 22,767,831 1,062,525 23,830,357 3,247,253
REGULATORY SERVICES & WASTE SOLUTIONS
CX7D Contaminated Land and Pollution Control 368,376 396,197 416,109 0 416,109 (47,733)
CX7A Vehicle Replacement Programme 49,040 254,431 332,631 0 332,631 (283,591)
CX7F Depot Rationalisation and Investment 1,810,007 1,195,996 2,522,561 0 2,522,561 (712,554)
CX7C HWRC Equipment 464,700 217,718 217,718 0 217,718 246,982
TOTAL REGULATORY SERVICES & WASTE SOLUTIONS 2,692,123 2,064,342 3,489,019 0 3,489,019 (796,896)
PLANNING & REGENERATION
CX1C Economic Regeneration 15,002,499 4,448,629 5,173,288 129,216 5,302,504 9,699,994
CX15A City Deal 17,238,178 15,185,991 17,084,111 143,045 17,227,156 11,022
CX15B Enterprise Projects 2,546,020 1,136,394 2,294,403 248,610 2,543,013 3,007
CX1B Antonine Wall Project 210,199 180,096 180,096 0 180,096 30,103
TOTAL PLANNING & REGENERATION 34,996,896 20,951,110 24,731,897 520,871 25,252,769 9,744,126
HOUSING PROPERTY & PROJECTS
CX16A Water Quailty / Ventilation 561,862 586,258 586,258 4,515 590,773 (28,911)
TOTAL HOUSING PROPERTY & PROJECTS 561,862 586,258 586,258 4,515 590,773 (28,911)
TOTAL ENTERPRISE & COMMUNITIES 133,810,081 92,652,555 115,667,841 3,208,471 118,876,312 14,933,765
YTD OUTTURN