North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  SL/ MK/ AMcK Date 15/02/23 
Local Housing Strategy 2021-2026 Annual Progress Review 
From  Stephen Llewellyn, Chief Officer Housing Management  
E-mail llewellyns@northlan.gov.uk Telephone 01698 274192 
1. Background 
1.1 The Housing (Scotland) Act 2001 places a statutory requirement on local authorities
to produce a Local Housing Strategy (LHS) that sets out its strategy, priorities, and
plans for the delivery of housing and related services. 
1.2 Local authorities are expected to review progress annually and to submit a copy of
the review to the Scottish Government More Homes Area Team. The review must
also be made available on the council’s website.
Executive Summary 
The purpose of this report is to advise committee of the progress made in delivering the
strategic priorities and actions set out in the Local Housing Strategy 2021-2026. 
The Local Housing Strategy is the main overarching strategy for housing and housing
related services in North Lanarkshire. It is an all-tenure document which sets the strategic
direction in key areas such as homelessness, house condition, housing delivery, specialist
provision, climate change and fuel poverty. The Local Housing Strategy for 2021-2026 was
approved by Committee in November 2021. Local authorities are required to report on
progress annually and to publish this on their website. This is the first annual progress
review since the strategy was approved. 
Recommendations 
It is recommended that Housing Committee: 
• Note the progress made to date in delivering the actions set out in the Local
Housing Strategy 2021-2026.  
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement All ambition statements

Page 2

1.3 North Lanarkshire’s LHS for 2021-26 was approved by Committee in November 2021.
The strategy plays an important part in delivering our ambition, set out in The Plan, to
make North Lanarkshire the place to live, learn, work, invest and visit. It is closely
connected and aligned to other key plans and strategies such as the Local
Development Plan, Town Visions, and the Economic Regeneration Delivery Plan. 
2. Report 
2.1 The vision set out in the strategy is: 
“To make North Lanarkshire the place to live, through provision of high-quality housing
and support in sustainable communities, that enables people to thrive and prosper” 
2.2 This vision is underpinned by seven priority outcomes which will be delivered over the
period 2021-2026: 
• We will increase the supply of high-quality sustainable homes across tenure 
• Our communities are vibrant, attractive, and sustainable
• We prevent and resolve homelessness effectively
• We have a range of housing options and supports which promote independence,
health, and wellbeing
• We will tackle climate change and fuel poverty
• Our homes will be fit for the future
• We contribute to improving the quality and accessibility of the private rented
sector 
2.3 The Action Plan contains 162 separate milestones, delivering on 41 actions, with the
LHS providing a framework for strategic monitoring and review. Of these milestones,
20 are complete and 126 are on track. Two milestones are slightly behind, twelve
milestones have not yet been started and two milestones are no longer applicable.
None are significantly behind. 
2.4 A full report on progress under each priority is included in the LHS Annual Progress
Report and corresponding Action Plan (which are attached in the Appendix). Some of
the key progress made to date includes: 
• 389 new affordable homes built in 2021/22
• Expansion of the Open Market Purchase Scheme (OMPS) to allow purchase of
the last remaining owner in mixed tenure flats, enabling common works to progress
• Further expansion of the OMPS to allow purchase of properties from private
landlords where there is a risk of homelessness, with tenants remaining in the
property as a council tenant
• Development of a Housing Asset Management Database to help inform demand
and investment decisions
• 75 homes brought back into use through our Empty Homes Purchase Scheme
and Open Market Purchase Scheme, bringing the total properties bought to date to
594
• 79 council homes delivered in town centres and edge of town centre locations
• 91% of properties in Phase 1 of the re-provisioning programme now vacant, with
209 properties demolished during 2021/22

Page 3

• First sites of the re-provisioning programme now under construction at
Northburn Avenue and Dykehead Road, Airdrie
• 41 long-term empty properties brought back into use in 2021/22
• Time spent in temporary accommodation by homeless households reduced by 8.1
days since 2020/21
• More than £562,000 of grant funding from the Covid-19 Tenant Grant Hardship
Fund administered to support people affected financially by the Covid-19 pandemic
who had fallen into rent arrears and were at risk of becoming homeless
• Modules 1, 2, 3, 5 & 6 of the Housing Options Toolkit released for use across the
country
• Homes previously earmarked for demolition through the re-provisioning programme
brought back into use to house refugees fleeing the war in Ukraine
• Implementation of our incentive to downsize scheme
• Over £17m invested in energy efficiency works in 2021/22
• Construction of 19 ‘Net Zero’ homes at Dykehead Road, Airdrie which feature
several low carbon technologies including air-source heat pumps, battery storage,
enhanced solar PV arrays and enhanced insulation
• Installation of our first electric vehicle charging points on a new build housing
development at Nobles View, Bellshill
• Low-income households at risk of fuel poverty were supported with almost £1m
of funding through the Tenant Hardship Payment Scheme
• Investment of more than £27m to improve the quality of our homes in the past
year, including £13 on roof and render, £6.5 on kitchens and bathrooms, and £4.2m
on home safety and security
• Private Landlord Forum re-established this year, the first time the event has been
held since 2017
• Several hundred inspections carried out by Private Sector Officers in support of
the Ukrainian Re-settlement Programme. 
2.5 The LHS is a five-year plan. Progress will continue to be monitored and reported
annually through the Local Housing Strategy Steering Group and Housing Committee. 
3. Measures of success 
3.1  Delivery of actions set out in the LHS Action Plan (attached in the Appendix).     
4. Supporting documentation 
4.1  Appendix – Local Housing Strategy Annual Progress Report 2022 
Stephen Llewellyn
Chief Officer, Housing Management

Page 4

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?  
The LHS has a positive impact on several protected characteristic areas, through
the provision of improved housing and related services to meet a broad range of
needs. 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒  
The LHS contains financial impacts.  As this report is a progress report, it does not
contain any direct financial impacts. 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact?

Page 5

5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
There are several actions in the LHS that have a positive impact on meeting our
climate change targets. Progress has been made on several key actions relating to
improving energy efficiency of housing stock which reduce our carbon emissions. 
Further detail is set out in out in the progress report. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
Risk is recorded on the Service Risk Register and managed accordingly.

Page 6

5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
Consultation and engagement with the Armed Forces Community was carried out
as part of the LHS development process.  This has directly informed the actions
and milestones set out in the strategy.

Page 7

LOCAL HOUSING STRATEGY 
ANNUAL PROGRESS REPORT 2022

Page 8

No embedded text on this page.

Page 9

3
Local Housing Strategy Annual Progress Report 2022
Contents
Introduction  ....................................................................................... 4
Housing delivery  ................................................................................ 6
Placemaking and communities  .......................................................... 8
Preventing and addressing homelessness  ......................................... 10
Specialist provision ............................................................................ 12
	
Fuel	poverty,	energy	efficiency	and	climate	change ............................ 14
House condition  ................................................................................ 17
Private sector housing  ....................................................................... 18
Strategic housing outcomes .............................................................. 19

Page 10

4
Local Housing Strategy Annual Progress Report 2022
Introduction
The Local Housing Strategy (LHS) is the main overarching plan for housing. It sets out our
housing priorities and the actions we will take to achieve our vision:
“To make North Lanarkshire the place to live, through provision of high-quality housing and
support in sustainable communities, that enables people to thrive and prosper”
The strategy plays an important part in delivering
our ambition set out in The Plan to make North
Lanarkshire the place to live, learn, work, invest
and visit, and is closely connected and aligned to
other key plans and strategies such as the Local
Development Plan, the Town Visions, and the
Economic Regeneration Delivery Plan.
The strategy will help deliver real improvements to
people’s lives, by:
• Continuing to build much needed new affordable
homes, reducing poverty, boosting the local
economy and improving outcomes
• Improving	the	quality	and	energy	efficiency	of	
housing, helping reduce fuel poverty and helping
achieve our net-zero climate change target
• Delivering a range of support services to help
people achieve their potential, be healthy and
included
• Helping create sustainable and attractive
communities, through tackling empty homes and
low demand and regenerating areas and places
North Lanarkshire’s Local Housing Strategy for
2021-26 was approved by Committee in November
2021.	This	is	the	first	annual	update	on	progress	
since the strategy was approved and provides an
update on progress since the LHS was published,
featuring key highlights and achievements as well as
ongoing challenges.
Strategic Context
The Housing (Scotland) Act 2001 places a statutory
requirement on local authorities to prepare a Local
Housing Strategy supported by an assessment
of housing need and demand. The LHS provides
the strategic direction, together with policies and
plans to enable the council and its partners to
invest in the delivery of high-quality affordable
housing and housing related services, across all
housing	tenures,	to	meet	identified	need.	There	is	
a requirement to set out the contribution housing
can make towards the effective integration of health
and social care; as well as its approach to meeting
a range of statutory housing responsibilities such as
addressing fuel poverty, improving house condition
and homelessness.

Page 11

5
Local Housing Strategy Annual Progress Report 2022
Our Priorities
Our LHS has seven priority outcomes which will
be	delivered	over	the	five-year	period	2021-2026.	
These priorities are:
• Priority 1: We Will Increase the Supply of High-
Quality Sustainable Homes Across Tenure
• Priority 2: Our Communities Are Vibrant,
Attractive and Sustainable
• Priority 3: We Prevent and Resolve
Homelessness Effectively
• Priority 4: We Have a Range of Housing Options
and Supports Which Promote Independence,
Health and Wellbeing
• Priority 5: We Will Tackle Climate Change and
Fuel Poverty
• Priority 6: Our Homes Will Be Fit for The Future
• Priority 7: We Contribute to Improving the
Quality and Accessibility of The Private Rented
Sector
Progress on the seven priorities is outlined in this
report highlighting any key success and challenges.
The action plan indicates the status of each action.

Page 12

6
Local Housing Strategy Annual Progress Report 2022
Housing delivery
PRIORITY 1: WE WILL INCREASE THE SUPPLY OF HIGH-QUALITY
SUSTAINABLE HOMES ACROSS TENURE
New Supply Affordable Housing
Despite	ongoing	challenges	due	to	inflation	and	resource	availability,	we	
delivered 137 new affordable homes for rent in 2021/22 and are on track to
achieve the target of delivering 5,000 new, affordable rented homes by 2035.
This brings the total new council homes built in North Lanarkshire to 9701.
Site Name Area Number of Homes Completion Date
Caledonian Avenue Bellshill 8 April 2021
Dimsdale Road Wishaw 55 November 2021
Roberts Street Wishaw 16 February 2022
Lismore Drive Coatbridge 58 February 2022
Mossburn, Waterloo (20 units) and Plains Primary School have also been completed post- 31st
March 2022.
389 new
affordable
homes built
Scottish Government
funding of £32.9m
secured for 2023/24
22 wheelchair
liveable homes
SHIP planned delivery of 3,229
homes	over	the	next	five	years
25 MMR homes
planned by 2027
We have secured a number of new sites for our homes, including several town
centre sites as well as land linked to our tower re-provisioning programme. We
currently have 421 homes under construction.
Site Name Area
Number of
Homes
Scheduled
Completion Date
Lindsaybeg Road (former Chilterns Home) Chryston 21 February 2023
Community Road Bellshill 29 January 2023
Northburn Avenue (Re-provisioning) Airdrie 31 March 2023
South Bridge Street (Former Orrs Building) Airdrie 20 June 2023
Earls Rise (Gateside Farm) Stepps 30 August 2023
Dykehead Road (Re-provisioning) Airdrie 150 September 2023
Ravenscliff Road (Former BRE site) Motherwell 24 October 2023
Berwick Street Coatbridge 19 November 2023
Castlehill Road Wishaw 97 May 2024
1 As at November 2022

Page 13

7
Local Housing Strategy Annual Progress Report 2022
Community	benefits	are	built	into	every	council	new	build	contract,	helping	to	
secure work experience and job opportunities for local residents, providing
educational support via virtual school sessions, as well as supporting local
businesses through supply chain improvements.
Our RSLs partners have delivered 252 affordable homes over the past year,
increasing the total number of new affordable homes built in the past year to
389.
The	Pathfinder	Scheme,	which	allows	the	council	to	purchase	new	affordable	
homes directly from private developers, is progressing well. We are currently in
the process of purchasing 24 homes at Lorne Place in Coatbridge, 39 homes
at	the	former	DWP	offices	in	Coatbridge	and	20	homes	at	the	former	Orrs	
Department Store in Airdrie (where works are now on-site).
Over the past year we have brought 75 homes back into use through our Empty
Homes Purchase Scheme and Open Market Purchase Scheme, bringing the
total properties bought to date to 594. Despite current market pressures which
have reduced supply and increased costs, the scheme continues to be popular,
allowing us to increase the supply of affordable housing whilst also addressing
issues associated with property repair and long-term empty homes.
In 2021, committee approval was given to expand the scheme to allow the
purchase	of	properties	from	owners	in	blocks	of	flats	and	cottage	flats,	where	
all	the	other	flats	are	already	owned	by	the	council,	allowing	them	to	stay	in	
their	homes	as	tenants.	This	helps	to	progress	common	works	for	the	benefit	of	
our tenants. A further expansion of the scheme in August 2022 means that we
will also consider buying homes from private landlords and allow the tenant to
remain living in the home as a council tenant, helping prevent homelessness and
increase the council’s housing stock.
Our Strategic Housing Investment Programme (SHIP) for 2022/23-2026/27
was approved by Committee in August 2022 and subsequently submitted to
the Scottish Government in October 2022. The SHIP sets out plans to deliver
over	3,200	new	affordable	homes	in	the	next	five	years,	helping	regenerate	local	
communities and support the economy by creating new jobs.
Despite increased grant subsidy available from the Scottish Government, a
refreshed	feasibility	study	and	financial	analysis	has	shown	that,	at	present,	
delivery	of	Mid-Market	Rent	(MMR)	by	the	council	remains	financially	unviable.	
However, work is ongoing to establish a Housing Delivery Partnership to deliver
alternative tenures should market conditions allow. We are also exploring
options for delivery of MMR in town centres through the Town Centre Project
and Levelling-up Agenda.
Work on the third Glasgow and Clyde Valley Housing Need and Demand
Analysis is now complete and due to be submitted to the Centre for Housing
Market Analysis for ‘Robust and Credible’ status assessment. Further
discussions on setting the Housing Supply Target will commence thereafter with
anticipated completion in Spring 2023 for inclusion within the LHS.
North Lanarkshire’s Local Development Plan (LDP) was adopted by Scottish
Ministers in July 2022. The LDP includes a continuation of the Affordable
Housing Policy for the Cumbernauld Housing Sub-Market Area, with the
potential for this to be applied elsewhere on a case-by-case basis. Revision of
the Supplementary Planning Guidance now includes provision for Shared Equity
housing as a delivery option. A separate options report on the delivery of Shared
Equity is also now complete.
We have developed a Housing Asset Management Database which captures a
range of information to help inform demand and investment decisions. Work is
underway to test assumptions before weightings are applied and the information
is used to draw conclusions.

Page 14

8
Local Housing Strategy Annual Progress Report 2022
Placemaking and communities
PRIORITY 2: OUR COMMUNITIES ARE VIBRANT, ATTRACTIVE AND SUSTAINABLE
Our key Town Centre Ambition projects are on track to proceed this year subject to the
acquisition	of	The	Centre	in	Cumbernauld	Town	Centre	proceeding	this	financial	year.	
Significant	funding	has	been	provided	by	the	Scottish	Government	and	UK	Government	for	
regeneration projects.
During 2021/22, we delivered 79 council homes
in town centres and edge of town centre locations
bringing our total to 104 homes.
Town Centre visions have been developed for all
eight town centres in North Lanarkshire and work is
well underway to develop action plans for each of
the town centres. To help deliver our visions, work is
underway to prepare and submit bids to supplement
the council’s own capital investment. This includes
the	UK	Government’s	Levelling	Up	Fund,	the	
Scottish Government’s Place Based Investment
Programme and Regeneration Capital Grant Fund,
the Vacant and Derelict Land Fund and Vacant and
Derelict Land Investment Programme. Funding bids
have also been prepared seeking National Lottery
Heritage Fund and Historic Environment Scotland
support to deliver the heritage-led regeneration of
Airdrie town centre. The council is also exploring
opportunities to lever in external funding to deliver
mid-market rent in our town centres.
Some key progress over the period includes:
• Demolition of Bank Street, Coatbridge to enable
residential development
• Detailed designs and plans produced to convert
the	former	Municipal	Buildings	at	Kildonan	Street,	
Coatbridge into residential accommodation
• Completion of Broomknoll Street town centre
site in Airdrie, delivering 30 new homes by Clyde
Valley Housing Association
• Demolition of the former Orrs department store
for residential redevelopment
• Creation of a new active travel link connecting
Abronhill with Cumbernauld Town Centre
• Acquisition of the Old Town Hall in Motherwell for
conversion to residential use
• Acquisition of the Masonic Halls in Motherwell
for façade retention and redevelopment for
residential use
• Acquisition	and	demolition	of	the	former	office	
building	Kingshouse,	Wishaw	for	residential	
redevelopment
• Commencement of construction works on the
former Tesco site in Wishaw to create new
housing, scheduled for completion in early 2023
• Properties re-developed on Buchanan Street
and Graham Street in Airdrie to deliver both
commercial and residential accommodation

Page 15

9
Local Housing Strategy Annual Progress Report 2022
In line with our ambitions to develop integrated
community hubs throughout North Lanarkshire, we
have commenced work on three community hubs
this year:
• Newmains and St Brigid’s Community Hub which
will provide a shared campus for two primary
schools and a family learning centre, delivering
an inclusive learning environment and modern
facilities for all members of the community.
• Chryston Community Hub which will replace
the existing primary school and provide a new
Community Health Clinic, offering residents
access to state-of-the-art health and wellbeing
facilities.
• Riverbank Community Hub, Coatbridge which
will bring together two primary schools, Carnbroe
PS and Sikeside PS, along with an early years
class. The hub is designed to provide an exciting
and	flexible	learning	environment	which	will	
accommodate a wide range of requirements both
now and in the future.
The	local	community	is	set	to	benefit	through	
building of the hubs, as local contractors and
smaller businesses will be supported, and work
placements and training opportunities created.
All three hubs are anticipated to be complete by
Autumn 2023.
Good progress continues to be made on the
Ravenscraig Access Road, with the construction
of the rail bridge currently running ahead of
programme. In preparation for the following stages,
detailed	specifications	and	tender	documents	
for procurement of the new connection between
Motherwell and Ravenscraig have been developed.
The contract is expected to be awarded in summer
2023, following completion of the bridge.
Phase 1 of the re-provisioning programme is
progressing well with 1,600 out of 1,750 properties
now vacant. Only one owner remains in-situ.
Negotiations to purchase this property are ongoing.
Options for Phase 2 are currently being considered
using	findings	from	the	structural	survey,	demand	
analysis and the availability of housing for re-
provisioning.
Demolition of Coursington, Allan and Draffen Towers
in	Motherwell	and	the	Shawhead	flats	in	Coatbridge	
is progressing well. Site establishment at both sites
is now complete and meetings with nearby residents
have been held to inform them of proceedings.
A total of 209 properties were demolished during
2021/22 which met all year end targets.
The contract to demolish 8 low-rise blocks at
Gowkthrapple, Wishaw (Phase 1) has recently been
terminated due to a request from the contractor for
a	significant	uplift	to	the	original	tender	value.	We	
are now undertaking a revised procurement exercise
which will include all 19 blocks on the site including
the surrounding structures. This isn’t expected
to delay the programme, which is on track for
completion by 2025.
The	first	sites	of	the	re-provisioning	programme	are	
now under construction at Northburn Avenue and
Dykehead Road, Airdrie. These developments will
deliver	over	180	modern	and	energy	efficient	new	
build homes for the local area and are planned for
completion by the end of 2023.
Creation of 20-minute neighbourhoods with good
access to physical, digital and social infrastructure
continues to be progressed through several
ways. This includes the Town Centre Visions,
the Active Travel Strategy, the creation of Town
and Community Hubs as well as the New Supply
Programme, which includes the expansion of
the Open Market Purchase Scheme to increase
supply whilst addressing important issues such as
prevention of homelessness, mixed tenure repairs
to improve housing condition, as well as tackling
the blight of empty homes in communities. The new
Local Development Plan, which was adopted in
2022, sets out the Placemaking Policies which help
create 20-minute neighbourhoods.
A total of 41 long-term empty properties were
brought back into use in the private sector during
2021/22, with a further 4 brought back into
use as social housing through the Open Market
Purchase	Scheme.	The	Empty	Homes	Officer	has	
been working alongside colleagues from Building
Standards, Environmental Services and Planning
to bring properties back to habitable condition,
including one property in a conservation which has
been empty since 2009.

Page 16

10
Local Housing Strategy Annual Progress Report 2022
Preventing and addressing
homelessness
PRIORITY 3: WE PREVENT AND RESOLVE HOMELESSNESS EFFECTIVELY
In response to the COVID-19 pandemic, and to
protect	those	experiencing	financial	hardship,	the	
Scottish Government implemented temporary
legislation to suspend all evictions from both private
and social housing for a period of up to 6 months.
The effect of this is apparent in the reduction of
households made homeless due to rent arrears,
which fell by 72% between 2019/20 and 2020/21
and remained similar in 2021/22. Emergency
legislation brought into force in October 2022 will
extend the moratorium on evictions offering extra
protection	to	those	facing	financial	difficulty	due	to	
the cost-of-living crisis.
By	carrying	out	financial	health	checks,	Welfare	
Rights	and	Income	Maximiser	Officers	have	helped	
generate	more	than	£35m	in	additional	benefits	for	
residents over the past year, working in partnership
with the Council’s Tackling Poverty Team. We have
also established a Universal Credit Assistance Fund
to help tenants who fall into rent arrears due to built-
in waiting times for Universal Credit payments, and
a Rent Relief Fund for those facing hardship due to
furlough or other reasons.
(2021/22 was 76.98 days representing a
reduction of 8.1 days from the 2020/21
period where it was 85.08).
(down slightly since last year)
1,697
48 individuals90.9%
homeless applications
in 2021/22
supported through Homes First
Repeat applications
down 34%
of new tenancies sustained
for more than a year
Youth homelessness reduced 
from  29.24% in 2020/21 
to  27.51% in 2021/22
(since 2015/16 youth homelessness has
reduced by 8.2% from 35.75% in 2015/16
to 27.51% in 2021/22)
Average length of stay in
temporary accommodation
REDUCED
Average rent £74.58 per
week (12.6% below Scottish
average for social landlords).
9th lowest Local
Authority rent

Page 17

11
Local Housing Strategy Annual Progress Report 2022
We administered more than £562,000 of grant
funding from the Covid-19 Tenant Grant Hardship
Fund, set up by the Scottish Government to
support	people	affected	financially	by	the	Covid-19	
pandemic and who have fallen into rent arrears
and are at risk of becoming homeless.  Initiatives
continue to be implemented through the Council’s
Tackling	Poverty	Officers	Action	Group	which	
involves the third and independent sector, NHS
Lanarkshire and Council services, working together
with local people and communities to tackle the
current unprecedented cost-of-living crisis.
Modules 1, 2 and 3 of the Housing Options Toolkit
were	finalised	and	released	for	use	across	the	
country in January 2022.  These modules cover
all housing activity including legislation, policy and
practice delivery.  Modules 5 and 6, which cover
employability	and	financial	advice,	were	completed	
in the Spring and have also been made available for
use. Module 4 which is around Health and Wellbeing
is due for completion by January 2023.
We continue to deliver the Family Plus Project in
partnership with Barnardos Scotland, funded by
North Lanarkshire’s Alcohol and Drugs Partnership
(NLADP), which provides housing support to
families and young people affected by domestic
abuse, addictions and other trauma.  Other Rapid
Rehousing Delivery Plan (RRTP) partnership projects
that continue to be delivered include the Youth Life
Coach Project, which aims to upskill young people
with the skills and experience they need to live
independently and Creative Faces, which provides
opportunities for therapeutic interventions to improve
health and wellbeing amongst young people.  
Bespoke housing options for Care Experienced
Young People (CEYP) to prevent homelessness
and improve housing options for when housing
crisis or periods of housing insecurity arise have
been developed and a revised CEYP protocol has
been developed in partnership with Health and
Social Care to improve pathway planning for CEYP
in North Lanarkshire.  Youth Housing Champions
have also been established across all our housing
localities, providing a key point of contact for advice
and information in relation to pathway planning for
services, whilst also helping improve awareness of
CEYP’s rights, wider rights for children (UNCRC)
and housing’s role as a Corporate Parent.  Progress
in relation to embedding Children’s Rights and
Wellbeing Impact Assessments into housing policy
and strategy has also been implemented since the
publication of the LHS, helping to mitigate adverse
impact and strengthen positive impact for children
and young people.
Actions contained within the RRTP continue to
be progressed, with the Housing First Team well
established and support scaled up over the course
of 2021/22 to increase capacity and reach of the
Housing First service.  As part of the work around
RRTP, we are also exploring development of a
crisis out-of-hours response service, alongside
assertive outreach to help meet the needs of people
who experience crisis and require an immediate
response, which will also support people not
currently linked in with services. A Trauma Informed
Practice Co-ordinator has been recruited to
implement a trauma training plan across the council
and wider partner workforce. So far, 59 housing staff
have been trained in trauma informed approaches,
with a training plan under development which will
incorporate tailored levels of trauma training for all
housing staff.
New policies have been developed
and implemented for tackling
domestic abuse and improving
tenancy sustainment, to help prevent
homelessness and ensure timeous
access to support, information and
advice, and training for staff.
Homes previously earmarked for demolition through
the re-provisioning programme have been brought
back	into	use	to	house	refugees	fleeing	the	war	in	
Ukraine. Thirty two families have moved into the
newly refurbished block at Birkshaw Tower, Wishaw
with an additional twelve families housed by Clyde
Valley Housing Association. The refurbishment of
Highcoats in Coatbridge is making good progress
and will be ready for residents in late January 2023.
Families have settled in well and have access to
a variety of supports including English language
classes, employment support through Routes
to Work, NHS Lanarkshire staff and daily on-
site support from our resettlement team. Work is
ongoing to identify and house additional families
within the towers which will, in total, provide 200
new homes for Ukrainian refugees.

Page 18

12
Local Housing Strategy Annual Progress Report 2022
Specialist provision
PRIORITY 4: WE HAVE A RANGE OF HOUSING OPTIONS AND SUPPORTS WHICH PROMOTE
INDEPENDENCE, HEALTH AND WELLBEING
All new build developments delivered by NLC
incorporate best practice, dementia design
principles to support those living with dementia or
with other support needs, including, but not limited
to:
• different coloured front doors to help with visibility
and navigation
• clearly visible entrances, level access and good
lighting
• clearly visible door numbers and doorbells that
contrast with the wall surface
• extended curtain plates to maximise natural light
from windows
• worktops/flooring	in	clear,	solid	colours	to	avoid	
confusion from pattens or speckles.
The remodelling of our linked corridor retirement
complexes has progressed over the last year, with
work at Dundyvan Gardens linked corridor complex
nearing completion and work at other linked corridor
retirement complexes scoped and planned over a
phased period.  This programme of improvements
in older people’s housing will help provide specialist
housing and communal facilities that enable
independence and promote health and wellbeing,
providing sustainable, future-proofed environments.
Our incentive to downsizing scheme has been
implemented	over	the	last	year,	with	a	financial	
package of assistance provided to tenants
under-occupying properties to help bring larger
homes back into allocation to meet the needs of
family households.  Despite the scheme being
implemented recently, popularity for the scheme is
evident and anticipated to increase as energy costs
and the cost of living continues to rise.  A targeted
communications campaign is planned to further
78 new council homes
suitable for older people
built in 2021/22.
3,137
adaptations
22 new homes built to
wheelchair standard
(15 NLC/ 7 RSL)
389 homes built
to HfVN standards
(total 970 NLC, 1,862
RSL to date)

Page 19

13
Local Housing Strategy Annual Progress Report 2022
increase awareness of the scheme amongst under-
occupying households, helping match housing
better to people’s housing needs.
Adapting for change training has continued to be
delivered via the development of an e-learning
module which is enabling increased access to
training on early intervention to prevent housing
crises from occurring.  The training continues to
be delivered across housing and health and social
care services, encouraging a collaborative approach
to	early	identification	of	housing	issues	to	achieve	
better housing, health and wellbeing outcomes.
New processes have been implemented over
2021/22 to help reduce delayed hospital discharge,
with weekly meetings established which involve all
locality housing, health and social care teams and
hospital discharge coordinators. The technology
flat	continues	to	be	promoted,	with	in-person	visits	
taking place again following Covid-19 restrictions. 
Discussions are ongoing in identifying alternative
accommodation	for	the	resource	flats,	which	
will help further improve options for enabling
swift hospital discharge and preventing delayed
discharge.
The Gypsy Traveller Strategic Group has continued
to make good progress against several key actions
over the course of the last year, with new data
collation methods implemented which helps capture
the housing and support needs of Gypsy Travellers
in North Lanarkshire in unauthorised encampments. 
Work is ongoing with Scottish Government and
COSLA on the national action plan, to develop a
housing need and demand toolkit for assessing
the housing needs of Gypsy Travellers and on
negotiated stopping.  North Lanarkshire Council
housing is represented on the national groups
and coordinates action at a local level through
partnership arrangements.
Engagement with private developers on an all tenure
wheelchair target has taken place, and work is
underway for a residents’ survey to further inform
the evidence base for the target.  Engagement
with developers to increase awareness amongst
developers on the need for wheelchair liveable
housing is planned to continue in 2023 with a view
to setting a target for the delivery of wheelchair
liveable homes in the private sector early in the year. 
Improvements in digital connectivity have been
made, with new smart technology being piloted in
homes which assists with maintenance and lowering
energy consumption, alongside new technologies
showcased in the Tech Flat, which supports
independence, health and wellbeing, improving
awareness amongst staff, services, providers,
people and communities of potential technological
solutions.

Page 20

14
Local Housing Strategy Annual Progress Report 2022
We published our Climate Plan – Act on Climate Together 2030 this year. The document
cements our pledge to achieve net-zero emissions in North Lanarkshire by 2030
and sets out the targets and next steps needed to achieve this. A recent change in
Governance has further embedded the agenda within the organisation, ensuring we
have a 360 perspective on climate change.
Fuel poverty, energy efficiency and
climate change
PRIORITY 5: WE WILL TACKLE CLIMATE CHANGE AND FUEL POVERTY
£275,500 funding received
from Social Housing Net
Zero Heat Fund.
1,045 council homes
fitted	with	new	
heating systems
99.2% of
homes meet
EESSH
100% of council new builds
meet NLC New Build
Sustainability Standards
Average	energy	efficiency	of	our	new	
build homes is currently Band B (above
the national average which is Band D)

Page 21

15
Local Housing Strategy Annual Progress Report 2022
We are reviewing our approach to space and water
heating in our new builds in line with the Scottish
Government’s Heat in Buildings Strategy, published
in October 2021, which sets out the Government’s
aim for all our homes and buildings to be net zero
by 2045. We are exploring both short- and longer-
term options for low emission heating, being mindful
of the potential negative impact these technologies
may have on social tenants due to the higher
running costs.
Construction has begun on 19 ‘Net Zero’ homes
at Dykehead Road, Airdrie which feature a number
of low carbon technologies including air-source
heat pumps, battery storage, enhanced solar PV
arrays and enhanced insulation. The measures are
designed to reduce energy costs for tenants, help
keep carbon-emissions low and help tackle fuel
poverty. It is expected that the homes will all achieve
an ‘A’ Energy Performance Rating. 
The pilot forms part of the larger Dykehead Road
re-provisioning site, where a total of 150 new
homes will be built. Data and tenant feedback will
be collected from both the Net Zero homes and
the homes heated by gas combination boilers.
This will allow us to assess the performance and
future viability of these options to help inform future
investment decisions.
In	2021,	we	installed	our	first	electric	vehicle	
charging points on a new build housing
development at Nobles View, Bellshill. We have
committed to providing an EV charging pillar within
each parking court of our new developments, where
the National Grid has capacity. In addition, we aim to
install individual charging points on each new build
home that has a private driveway.
Other examples of how we’re building greener
include:
• Minimising heat loss by using mineral wool
insulation and windows and doors exceeding
requirements set out in the Building Standards.
• On-site renewable energy. Photovoltaic provision
has recently been increased and homes currently
being built will have an in-roof photovoltaic array
which will reduce CO2 emissions, assist with
running costs for the home, and reduce demand
on the National Grid.
• Energy	efficiency	measures	which	see	over	99%	
of our new build homes achieve a ‘B’ Energy
Efficiency	Rating	and	over	90%	achieve	a	‘B’	EPC	
CO2 Rating.
We have commissioned consultants to develop
a route map to achieving EESSH2 compliance in
our existing social housing stock. The new EESSH
requires that all social housing meets EPC Band
B by the end of 2032, within the limits of cost,
technology and necessary consent. In addition,
no social housing below EPC Band D should be
re-let from December 2025, subject to temporary
specified	exemptions.	Currently	99.2%	of	our	stock	
is EPC Band D or above. This is a 1% improvement
on last year.
Our	drive	to	improve	energy	efficiency	in	our	existing	
council homes has seen us receive a top award for
Large Scale Project of Year at Scotland’s Energy
Efficiency	Awards.	By	installing	measures	such	as	
wall insulation, loft insulation, windows, roof, render,
as well as renewable technologies such as solar
panels, we have helped bring homes up to SHQS
and EESSH standards and reduce fuel poverty for
tenants.
We have been awarded a further £2,242,200 in
2022/23 from the Social Housing Net Zero Heat
Fund for the works to upgrade non-traditionally
constructed homes in Wishaw, Motherwell,
Newmains, Newarthill and Airdrie.
Over 3,000 energy efficiency measures
installed in 2021/22.
External Wall
Insulation
550
Windows
700
Heating
1,700
Solar Panels
130

Page 22

16
Local Housing Strategy Annual Progress Report 2022
Following on from the successful delivery of a
pilot scheme in Pather to install single room heat
recovery fans, we have installed these in our
mainstream programme where appropriate. These
work by extracting and using heat from stale air to
warm fresh air coming into the home, saving energy.
It is hoped that, if successful, this technology will be
rolled out to other properties in the future.
We have delivered around £9.5m of energy
improvements in North Lanarkshire since 2016,
with 1,284 private homes improved. In 2020/21
we upgraded 34 council homes and 35 private
homes through EES:ABS (formerly HEEP:ABS).
Uptake for the scheme has since been affected by
changes in legislation and external funding meaning
a percentage contribution from owners is now
required to carry out the improvement works. It is
anticipated that this will affect uptake for the scheme
going forward, unless there is a change in funding
parameters. Measures are being taken to encourage
owners to participate.
We are also working to encourage energy
improvements in the private sector. Current landlord
registration processes now require that all new and
renewal applications have a suitable EPC for the
property and work is ongoing to ensure compliance
at this stage.
Low-income households at risk of fuel poverty were
supported with almost £1m of funding through the
Tenant Hardship Payment Scheme. In the 6 months
from January to June 2021, more than 8,000
applications were received for the scheme which
was targeted at those at risk of fuel poverty but
unlikely	to	receive	financial	support	elsewhere.	The	
scheme has recently been reviewed with the income
threshold lowered in October 2022, increasing the
reach of the scheme to more working households in
fuel poverty.

Page 23

17
Local Housing Strategy Annual Progress Report 2022
House condition
PRIORITY 6: OUR HOMES WILL BE FIT FOR THE FUTURE
98.5% of reactive
repairs completed
“right	first	time”
Emergency repairs completed
within 3.18 hours on average
(below Scottish average, and year on year
improvement)
We have invested more than £27m to improve the
quality of our homes over the past year, including
£13 on roof and render, £6.5 on kitchens and
bathrooms, and £4.2m on home safety and security.
Despite a variety of ongoing challenges, including
labour/ material shortages and cost increases, we
still plan to invest over £50m in the coming year2.
The type of works being undertaken this year
include:
• roof upgrades
• external wall insulation
• windows, kitchens and bathrooms
• lift replacements
• lead water pipe replacements
• energy	efficient	heating	systems
• electrical rewiring of houses and common areas
of	low-rise	blocks	of	flats
We continue to invest in our tower blocks to ensure
they are safe, secure and attractive places to live.
Our structural survey programme, which began in
2016 and is now complete, has informed a wide-
ranging	programme	of	works	to	improve	fire	safety	
in our towers. The programme which includes
installation	of	emergency	lighting,	fire-doors	and	
improved	compartmentation/fire-stopping	is	now	
complete. In line with recent change in legislation,
interlinked smoke detection has also been installed
within properties and sheltered complexes.
The programme to install sprinkler systems within
individual properties is also progressing well with the
first	phase	now	complete	and	the	second	phase	on	
track for completion in Winter 2022.
We are nearing completion of the refurbishment of
Blairgrove, Merryston, Glen and Millbrae Towers in
Coatbridge with the installation of parking bays and
charging canopies underway.
Our average days to re-let homes increased to
31.81 days during the year mainly due impact of
the pandemic, however we performed well when
compared to the Scottish average of 51.6 days. Our
housing and repairs teams are working together and
liaising closely with our contractors to continually
improve these timescales with a view to bringing our
performance back to pre-pandemic levels.
Following approval at committee in November
2021, the council will now lead the large-scale
re-provisioning	of	privately	owned	flats	at	Millcroft	
Road, Cumbernauld. Intensive work during 2022
has ensured that all remaining owners have
been traced, concluding this workstream and
allowing	the	CPO	Order	Schedule	to	be	finalised	
and progressed. The Rehousing Strategy is now
underway	with	the	first	voluntary	acquisitions	taking	
place, allowing residents to move to Sanctuary’s
new development at Burns Road.
Non-emergency repairs
completed 30% quicker
than Scottish average (6.19 days)
2 subject to committee approval

Page 24

18
Local Housing Strategy Annual Progress Report 2022
Private sector housing
PRIORITY 7: WE CONTRIBUTE TO IMPROVING THE QUALITY AND ACCESSIBILITY OF THE
PRIVATE RENTED SECTOR
We re-established our Private Landlord
Forum	this	year,	the	first	time	the	event	has	
been held since 2017. By holding the event
online, through Microsoft Teams, we have
increased participation and made the event
more accessible for those unable to attend
an in-person event. The event was recorded
and made available on our website, allowing
landlords to access and replay the event at a
time convenient to them.
We hope to further increase engagement through our bi-annual Private Landlord
Newsletter which aims to provide landlords with clear information on their rights
and responsibilities, give relevant updates on policy and legislation changes, as
well as providing guidance on sources of support and assistance.
We	have	made	significant	progress	reviewing	and	redesigning	our	Landlord	
Registration processes and procedures. Initially this work has focussed on how
we approach landlords whose registration has expired but work also continues
in other areas of the registration process such as application and audit/
enforcement of regulations.
Our	Private	Sector	Officers	carried	out	several	hundred	inspections	in	support	
of the Ukrainian Re-settlement Programme, ensuring the properties of those
applying	to	the	Programme	were	of	a	suitable	standard	and	fit	to	house	those	
arriving from Ukraine.
We await publication of the new Rented Sector Strategy which is expected
to provide improved data on the Private Rented Sector. In the interim, we will
undertake further analysis using Home Analytics Data, as well as collaborative
efforts with the Private Sector Team to improve understanding.
We are planning research with NHS Lanarkshire and larger employers within
North Lanarkshire to establish gaps and demand for tenures such as Mid-
Market Rent, Shared Equity and Low Cost Home Ownership.  This will be
progressed in partnership with the Growth Team.
8,397 Registered Landlords
12,809 Approved Properties
Private landlord forum re-
established

Page 25

19
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 1: We increase the supply of high-quality sustainable homes across tenures
Action Baseline
2019/20
Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator
2021/22
KEY ACTION 1.1
Deliver alternative tenure housing
to meet a broad range of needs and
deliver sustainable, inclusive and
diverse communities
38 mid-market
homes delivered
to date
Enable RSLs to deliver Mid Market Homes in large
council developments to provide more mixed
tenure, sustainable and diverse communities and
support town visions and regeneration projects 3
Deliver Mid Market
Homes
NS Ongoing Number of MMR
homes in council
developments
Ongoing 25 MMR homes included in 2023/24-2027/28
SHIP.
-
Initial feasibility
report
Re-visit initial feasbility studies to determine
viability of council delivery of MMR
Re-freshed feasibility
study
BDS/NS 2023 Report Complete Refreshed feasibility study and financial modelling
complete. Council delivery of MMR remains
financially unviable despite new subsidy from
Scottish Government for council delivery of MMR.
- Establish a Housing Delivery Partnership to deliver
MMR and other alternative tenure to ensure
readiness should market conditions allow for
council delivery of alternative tenure
Establish HDP NS/BDS 2022 HDP established Ongoing Exploration of Housing Delivery Partnership
ongoing.  Council delivery of MMR remains
financially unviable but scope exists potentially
through the Town Centre Project and Levelling Up
Agenda to deliver mixed tenure within Town Centre
locations.
Initial feasibility
report
Explore use of Affordable Housing Policy to deliver
shared equity housing
Complete options
report
BDS/NS 2022 Report Complete The Affordable Housing Policy Supplementary
Planning Guidance is currently under review
following adoption of North Lanarkshire’s Local
Development Plan in 2022. The revised Affordable
Housing Policy SPG contains provision for Shared
Equity housing as a delivery option. A separate
options report on the delivery of Shared Equity
housing is also complete.
Initial
discussions held
Explore Build to Rent feasibility Build to Rent explored NS/BDS Ongoing Report Ongoing Initial discussions held with developers.
- Carry out engagement and analysis with key
workers and employers to identify further the future
housing needs of key workers
Engagement and
Analysis complete
BDS 2023 Engagement and
Analysis Report
Not yet
started
Not yet started. Engagement to be carried out
early 2023.
- Develop a self-build register to be published on the
council’s website
Self-build register
developed and
published
BDS/Pl 2022 Register Ongoing Initial discussions held.
- Consider ways in which planning policy and use of
public land can support delivery of self-build
Methods considered BDS/Pl 2022 Report Ongoing Ongoing
KEY ACTION 1.2
Improve our strategic understanding
of Covid-19 on housing need and
aspirations
- Undertake further analysis of housing needs and
aspirations as further evidence and data emerges
Analysis complete BDS Ongoing Analysis report Complete Research complete on impact of Covid-19 on
housing needs and aspirations.
3 This milestone has been revised to ‘enable RSLs to deliver Mid Market Rent Homes to provide more mixed tenure, sustainable and diverse communities and support town visions and regenerations projects’.

Page 26

20
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 1: We increase the supply of high-quality sustainable homes across tenures
Action Baseline
2019/20
Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 1.3
Contribute to the strategic planning
for housing in Glasgow and Clyde
Valley
HNDA2 Contribute to Housing Need
and Demand Assessment 3
Completion of HNA3 BDS 2021/22 HNDA3 Ongoing HNDA 3 sign-off in process and anticipated submission to
CHMA prior to year end for assessment for 'robust and credible'
status. Thereafter further discussion required on Housing Supply
Targets, and refresh of the current LHS.  Anticipated Spring
2023.
HLR 2021
(under
consultation)
Land available for private
sector Housing Supply
Target (HST)
759 units per annum
(based on HNDA2 to
be updated to reflect
HNDA3)
Pl 2026 HLA Ongoing 857 units per annum (based on HNDA2 to be updated to reflect
HNDA3)
HLR 2021
(under
consultation)
Land available for social
rented/below market rent
sector HST
300 units per annum
(based on HNDA2 to
be updated to reflect
HNDA3)
Pl 2026 HLA Ongoing 242 units per annum  (based on HNDA2 to be updated to reflect
HNDA3)
HLR 2021
(under
consultation)
Land available for all tenure
HST
1,059 units
(based on HNDA2 to
be updated to reflect
HNDA3)
Pl 2026 HLA Ongoing 1,099 units (based on HNDA2 to be updated to reflect HNDA3)
KEY ACTION 1.4
Maximise provision of affordable
homes, to meet a range of housing
needs
SHIP 2021/22
– 2025/26
Review and update
the Strategic Housing
Investment Plan (SHIP)
annually
SHIP updated annually NS/BDS Annually SHIP Complete Produced annually. SHIP 2022/23-
2026/27 submitted
to Scottish
Government
October 2022.
2024 council
and RSL units
delivered since
2010
Deliver Affordable Housing
Supply Target identified in
HNDA3
300 units per annum
but subject to change
following progression
of HNDA3
NS 2026 Number of
affordable homes
Ongoing 2,796 council and RSL units delivered since 2010. 389 units delivered
in 2021/22 (NLC =
137; RSLs = 252).
- Identify mismatch of supply
and demand in social
rented housing to inform
investment priorities (linked
to the council’s asset
management plan)
Analysis undertaken BDS 2026 Low demand
analysis and
additional reports
Ongoing Housing Asset Management Database and Indicator System
created, which captures a range of information on various
aspects to help better inform demand and investment decisions.
Work currently underway in relation to testing assumptions
before weightings implemented and initial conclusions drawn.
KEY ACTION 1.5
Evaluate the impact of the Affordable
Housing Policy to further understand
impact
- Undertake evaluation of the
Affordable Housing Policy
Evaluation complete BDS/NS 2023 Evaluation report Ongoing Affordable Housing Policy SPG underway which outlines a 20%
AHP policy contribution in the Cumbernauld HSMA in line with
the new Local Development Plan for North Lanarkshire. Some
initial analysis undertaken on pressure analysis in the North to
further understand impact of AHP on pressure.

Page 27

21
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 2: Our communities are vibrant, attractive and sustainable
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator
2021/22
KEY ACTION 2.1
Help re-shape and
populate our town centres
Town visions developed and
engagement ongoing
Identify and deliver
transformative town centre
projects to provide new
residential provision
• Kildonan St, Coatbridge
• Bank St, Airdrie
• Motherwell Town Hall
• Former Tesco Site, Wishaw
• Broomknoll St, Airdrie
• John Orrs Building,
Southbridge St, Airdrie
Complete projects NS 2026 Number of
projects complete
Ongoing The Whitehouse and Bromknoll Church complete. Former Tesco
site due for handover Jan/ Feb 2023. Orrs in progress.
Bank Street:
Due to the high costs of retaining the façade, and its close
proximity to the railway line leading to construction complexities,
it was decided at Board level to redesign the proposals and
seek permission from planning and Historic Environment
Scotland to remove the façade in favour of a complete new build
design. This is a more favourable design in terms of buildability,
functionality as well as being more economical. A new planning
application is being developed with submission expected in
Spring 2023. The proposals consist of 6 flatted homes for social
rent as well as supported accommodation.
Kildonan Street:
Stage 2 designs were valued higher than the expected value
approved at the committee in March 2020. Costs have
increased largely due to inflation, but also due to the revised
energy strategy required to meet the higher building regulations
for housing. In order to reduce the total costs towards the
agreed value of the project, and to deliver on the main objective
to refurbish and re-purpose the municipal building, it was
decided at Board Level to omit the 6 town houses. The footprint
of the town houses is instead planned to be a mixture of car
parking and a landscaped community garden (including planters)
for the residents to maintain. The current plans include 43 flats
for social rent and a large office space in the main building to
be utilised by the Council as part of its new HUB strategy for
Coatbridge. Planning submission is expected in 2023.
2 sites complete.
Engagement on town hubs
commenced
Develop town centre and
community hubs to support
the delivery of public
services and provide flexible
space
Complete hubs GT 2026 Number of town
centre hubs
Ongoing Community Hub progress:
Newmains/St Brigid's Community Hub, Wishaw will be compete
Q1 2023.
Chryston Community Hub (Northern Corridor) and Riverbank
Community Hub (Coatbridge) will be complete Q3 2023. 
Town Hub Progress:
There is insufficient funding in current five year capital plan to
progress a town hub. However, they are still planned to progress
within the programme as and when funding becomes available.
3 sites in
construction.

Page 28

22
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 2: Our communities are vibrant, attractive and sustainable
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator
2021/22
KEY ACTION 2.2
Improve connectivity of
our communities through
investing in physical, social
and digital infrastructure
Progress made on
Ravenscraig Access Road
Deliver the City Deal
Programme
Projects complete GT 2026 Projects Ongoing RIA S FBC 1 approved for West Coast Mainline Crossing.  WCML
works on site and ahead of programme. 
RIA N Multidisciplinary Services contract Awarded and detailed
design in well underway.  
Tender for RIA S FBC 2 Dual Carriageway and new junction
(roundabout) in development.
WCML complete
May 23.
Connecting NL – a
Blueprint Project
Deliver new opportunities for
active and sustainable travel
New opportunities
identified
GT 2026 Active Travel
Strategy
Ongoing Logans Road: complete                                                     
The Loaning Stages 1-3: complete                             
Strathclyde Park: complete                                             
Minch Way: complete                                                       
A71 Horsley Brae: complete                                            
Newhouse to Salsburgh: substantially complete          
South Biggar Rd/ Craigneuk Ave: substantially complete
Petersburn Road/ Brownsburn Rd: design 90% complete                                            
Meadowhead Road: public consultation complete     
Alexander St: works tendered
8 projects
completed.
Implement fast, affordable
digital connectivity for
businesses and communities
Improved digital
connectivity
BS 2026 Number of
people digitally
connected
Ongoing Comms World partner now in place to progress implementation
of faster digital connectivity.
Fibre to the Premise and
Cat5e ethernet cabling
provided in council new
build homes
Continue to deliver digital
connectivity within new build
council homes
All council new build
homes delivered
will have digital
infrastructure
NS Ongoing Number of new
council homes
with digital
infrastructure
On Track Ongoing 137 council new
builds delivered
with digital
infrastructure.
KEY ACTION 2.3
Improve economic
opportunities and
outcomes for all
Economic Regeneration
Plan approved
Progress actions contained
within North Lanarkshire’s
Economic Regeneration Plan
(2019-23)
Actions complete NS/
GT/
BDS
2023 Annual review Ongoing 2021/22 Action Plan developed and predominantly delivered
(reported to committee August 2022). 2022/23 Action Plan in
progress.
KEY ACTION 2.4
Develop and deliver the
Tower Re-provisioning
Programme
3 tower blocks demolished
(Cheviot, Merrick and
Pentland Court)
Deliver Phase One
comprising 1,760
demolitions with sites
cleared for future investment
1,760 demolitions HP/NS 2026 Number of
demolitions
On Track Demolition of Coursington, Allan and Draffen Towers
(Motherwell) and Shawhead flats (Coatbridge) in progress.
Remaining sites at Gowkthrapple and Coatbridge on track for
demolition by 2025 target.
209 demolished
to date.
Phase Two developed for
implementation from 2025
Programme developed HP/NS 2024 Programme Ongoing Options for Phase 2 are currently being considered using
findings from the structural survey, demand analysis and the
availability of housing for re-provisioning.

Page 29

23
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 2: Our communities are vibrant, attractive and sustainable
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator
2021/22
KEY ACTION 2.5
Invest in council multi-
storey towers to ensure
continued safety and
security of tenants
Programme underway Continue to review
and implement where
appropriate fire stopping
and prevention measures
and re-cladding in multi-
storey towers
Works complete HP 2026 Progress reports Ongoing Fire doors and fire stopping works to all towers outwith the
Phase 1 demolition programme and 4 towers upgrade project
complete. Cladding replacement programme progressing at the
4 Towers in Coatbridge (Blairgrove / Merryston / Glen / Millbrae)
and designs team to be agreed for Whifflet / Calder.
KEY ACTION 2.6
Implement the Place-
Standard Tool across a
wider range of settings
Place-Standard Tool in use Incorporate use of the
Place-Standard Tool
in tenant participation
settings to identify areas of
improvement and improve
place
Place-Standard Tool
in use across tenant
participation groups
BDS 2023 Tenant
Participation
reports
Ongoing Ongoing
Implement use of the
Place-Standard Tool
in existing and future
housing consultation and
involvement opportunities
i.e. tenants conference,
housing forums etc.
Place-Standard Tool
used across the
range of housing
consultation activities
BDS 2024 Consultation
reports
Ongoing Ongoing
KEY ACTION 2.7
Incorporate the twenty-
minute neighbourhood into
community development
Further implement
high-quality 20 minute
neighbourhoods in North
Lanarkshire focussed on
provison of physical, digital
and social infrastructure
and mapping and review of
provision
High-quality
20 minute
neighbourhoods
implemented
BDS 2026 Report Ongoing Creation of 20-minute neighbourhoods with good access
to physical, digital and social infrastructure continues to be
progressed through several ways. This includes the Town Centre
Visions, the Active Travel Strategy, the creation of Town and
Community Hubs as well as the New Supply Programme, which
includes the expansion of the Open Market Purchase Scheme
to increase supply whilst addressing important issues such as
prevention of homelessness, mixed tenure repairs to improve
housing condition, as well as tackling the blight of empty homes
in communities. The new Local Development Plan has been
adopted in 2022, which also sets out the Placemaking Policies
which help create 20 minute neighbourhoods.
KEY ACTION 2.8
Increase the number of
empty homes brought back
into use
197 empty homes
purchased since scheme
established
Continue to deliver the
Empty Homes Purchase
Scheme
30 per annum NS 2026 Number of empty
homes purchased
On Track 285 empty homes purchased since scheme established. 41 empty homes
purchased in
2021/22
116 empty homes brought
back into use via the
empty homes officer since
2018-19
Continue to work with
owners and partners to
bring empty homes back
into use
35 per annum PS Ongoing Number of empty
homes brought
back into use
On Track 157 private sector empty homes brought back into use since
2018
41 private sector
empty homes back
in use in 2021/22

Page 30

24
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 2: Our communities are vibrant, attractive and sustainable
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator
2021/22
KEY ACTION 2.9
Tackle low demand within
council stock
Low Demand Analysis
complete 2019/20
Update Low Demand
Analysis and action plan
annually
Complete analysis BDS Ongoing Low demand
report
Ongoing Pressure analysis completed annually. Action plan to be
informed by HAMP Database analysis. Quarterly analysis also
completed for the Tower Re-provisioning Programme.
Identify options to address
low demand stock
Options identified BDS Ongoing Options appraisal Ongoing Considered through the Re-provisioning Programme.
Strategic Housing Outcome 3: We prevent and resolve homelessness effectively
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 3.1
Implement the RRTP
Homes First model
developed
Develop and implement
Homes First service
Homes First Service
implemented
BDS
HS/
H&SC/
2025 Number of people
accessing Homes First
service
On Track 48 Homes First individuals now being supported - 40 now
sustaining tenancies
8 individuals
awaiting suitable
rehousing
Forever Homes project
established
Carry out evaluation of
‘Forever Homes’ project
Evaluation complete HS/BDS 2023 Evaluation report On Track Second feedback survey complete August 2022. Homes First co-
production report
2022 complete.
Protocols in place Review shared protocols
for young care experienced
people and domestic abuse
Protocols reviewed HS/
BDS/
H&SC
2022 Revised Protocols Complete CEYP protocol reviewed and revised in partnership with
Health and Social Care. Domestic Abuse Protocol updated
and new Housing Domestic Abuse Policy developed and
implemented.
5 homeless young care
leavers
Number of homeless
young care experienced
people
On Track 1 YP homeless straight form a care setting in 2021/22. Continue to monitor
29% of homeless
presentations disputes
within household
(14.8% non-violent and
14.2%% violent)
Number of people
homeless due to domestic
abuse
Ongoing 246 (14.56%) homeless applicants identified an abusive
relationship in 2021/22.
Continue to monitor
- Number of people housing
services refer/signpost for
domestic abuse support
Ongoing 263 people referred
for domestic abuse
support.
105 homeless people
discharged from prison
Implement SHORE
standards
SHORE standards
implemented
BDS/
HS/
H&SC
2023 Number of homeless
people discharge from
prison
On Track 75 (4.4%) in 2021/22 Continue to monitor
Joint protocol and
procedure
Complete Process developed between PP Team and Operational
Housing to support needs of SHORE. No request made to
develop protocol as we are working within Shore Standards.

Page 31

25
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 3: We prevent and resolve homelessness effectively
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 3.1
Implement the RRTP
- Explore viability of
specific services to
support women with
poor mental health
and addictions
Services explored BDS/
H&SC
2024 Options report Ongoing Housing is represented on the Violence
Against Women Strategic and Operational
Partnership Groups, which have a key role in the
commissioning of services to meet needs.  Family
Plus Service established in partnership with
Barnardo's Scotland, funded by the ADP, which
provides housing support to families and young
people affected by domestic abuse, addictions and
other trauma.
Discussions
underway with RSL
partners
Agree and monitor
target lets for RSLs to
homeless households
Targets agreed and
monitoring system
in place
BDS/
HS/
RSLs
2022 Number of RSL homeless
household lets
On Track First RSL meeting held August 2022 to encourage
increase in % lets. New contacts established for
NLC & RSLs.
Continue to monitor
RRTP developed
and being
implemented
Prevent homelessness
from occurring and
where it does occur
resolve effectively
Homelessness
prevented, reduced
and resolved
HS/BDS Ongoing RRTP progress reports On Track Monthly RRTP RAG report in place. Flipped
tenancies declined in recent months.
8 tenancies flipped YTD. Report
circulated to localities quarterly to
increase
2,127 homeless
applications
Number of homeless
applications
On Track 1,697 homeless applications
192 assessed as
‘not’ homeless
Number of people
assessed as ‘not
homeless’
On Track 58 assessed as 'Not Homeless' in
2021/22. This was a fall from 71 in
2020/21 and 127 in 2019/20.
197 assessed
as ‘intentionally
homeless’
Number of people
assessed as ‘intentionally
homeless’
On Track 44 assessed as 'intentionally
homeless' which is a significant fall
since 2019/20 but is also reflective of
a 21% fall in Hl applications.
120 repeat
homeless
applications
Number of repeat
homeless applications
On Track 60 repeat homeless cases in 2021/22
which is a fall of 31 from 2020/21
when 90 repeat cases were recorded.
KEY ACTION 3.2
Review housing options
and prevention activity
S11 procedure in
place
Review S11 process
and procedures
S11 process and
procedures reviewed
BDS 2023 Number of S11
notifications
Complete Section 11 processes/ procedures reviewed in
2021 as part of RRTP Action Plan.
Continue to monitor
Development of
Housing Options
Toolkit underway
Deliver the Housing
Options Training
Toolkit
Housing Options
Training Toolkit
operational
BDS 2022 Housing Options Training
Toolkit
On Track 5 of 6 modules now complete - module 4 50%
complete. M1 to 3 already live and being used by
32 authorities and GHA.
Number of PAS
interviews leading
to homeless
applications –
65.4%
Embed new
approaches and good
practice for prevention
activity
Improved practice BDS/
HS
2024 Case Audits Ongoing PAS re-launched 2020-2021 with all staff briefed
re proper use of PAS. Monthly Monitoring reports
introduced to MCO.
Cleansing exercise being completed
Nov 2022-Feb 2023.  Improved use,
better auditing and reporting to be
developed. Action Plan underway
2022.

Page 32

26
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 3: We prevent and resolve homelessness effectively
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 3.3
Improve housing support
and accommodation
services meet the needs
of homeless households
Housing support
services
commissioned
Re-design of housing support
services to meet needs and align
with RRTP
Re-design and
re-tender housing
support services
BDS 2024 Options appraisal and
Tender
On Track Re-design of Housing Support Services to
commence during 2023. 
83.9% of new
tenancies sustained
for more than a
year by source of let
(homelessness)
% of new tenancies
sustained for more than
a year by source of let
(homelessness)
Ongoing 2021/22 outturn was 87.61% of tenancies
sustained. This is a 3.71% improvement on the
2019 baseline.
Continue to monitor
87.3% of new
tenancies sustained
for more than a
year by source of
let (all waiting lists
combined)
% of new tenancies
sustained for more than
a year by source of let (all
waiting lists combined)
Ongoing 2021/22 outturn was 90.92% of tenancies
sustained. This is a 3.62% improvement on the
2019 baseline.
Continue to monitor
Review commenced Carry out temporary
accommodation review
Review complete BDS 2023 Temporary
accommodation strategy
Ongoing Initial modelling work on Temporary
Accommodation Strategy carried out but impacted
by Covid-19 in relation to reduced allocations and
increased void times. Modelling work to resume in
2023 to identify recommendations for temporary
accommodation, linked to RRTP.
Strategic Housing Outcome 4: There are a range of housing options and supports which promote independence, health and wellbeing
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 4.1
Increase the supply of
affordable wheelchair
housing.
43 new build
council wheelchair
homes built
Deliver wheelchair housing on
all council new developments
where feasible (where not feasible
provision should be increased on
other sites to achieve minimum
target)
10% NS 2026 Number/percentage of
council new build homes
built to wheelchair liveable
standard
On Track 61 new build council wheelchair homes built to
date.
15 new build council
wheelchair homes built in
2021/22 (11% of annual
council new builds)
32 new build RSL
wheelchair homes
built
Deliver wheelchair housing on
all RSL new build developments
where feasible (where not feasible
provision should be increased on
other sites to achieve minimum
target)
5% RSLs 2026 Number/percentage of
RSL new build homes
built to wheelchair liveable
standard
Slightly
behind
39 new build RSL wheelchair homes built to date. 7 new build RSL
wheelchair homes built in
2021/22 (3% of annual
RSL new builds)
Carry out review/ cost analysis
of council new build amenity
bungalows to determine scope
for increasing standard to full
wheelchair liveable standard
Review complete NS 2022 Review report Complete Cost comparison complete, estimated £20-25k
increase per unit.

Page 33

27
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 4: There are a range of housing options and supports which promote independence, health and wellbeing
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 4.2
Increase the supply of
wheelchair housing in
the private sector
- Engage and work with private
developers to increase awareness
of the need for wheelchair
accessible and liveable housing
and encourage development
*target to be
determined following
engagement with
developers
BDS 2022 Private Developer
Consultation Complete
Complete Consultation carried out with developers on the
delivery of wheelchair homes and potential target
approach.
2022 Target agreed Slightly
behind
Survey planned for tenants and residents in late
2022 to gather further information on needs to
supplement existing information on need and
demand, in addition to further engagement with
developers with a view to implementing a target
in 2023.
2022 Mechanisms in place to
monitor delivery
Complete Mechanisms for monitoring via LHS progress
reporting.
KEY ACTION 4.3
Increase the supply
of adaptable and
accessible housing
640 council new
build social rented
(HfVN) homes
(2019); 1,384 RSL
social rented (HfVN)
homes built (2019)
Deliver housing for varying needs
through the council and RSL new
build programme
5,000 by 2035 NS/
RSLs
2026 Number/percentage of
council and RSL homes
built to ‘Housing for
Varying Needs Standards’
On Track 934 council new build and 1,862 RSL new build
meeting HfVN standards to date.
389 homes built to HfVN
standards in 2021/22 (NLC
= 137; RSLs = 252).
3,463 adaptations
completed in
2019/20
Provide equipment and
adaptations across tenure
Increase H&SC 2026 Number of adaptations
and equipment provided
Ongoing 3,137 adaptations
complete across tenure.
Carry out analysis to identify
future demand for equipment and
adaptations in partnership with
health and social care
Analysis complete
and needs identified
BDS/
H&SC
2024 Analysis report Ongoing Data on equipment and adaptations provision
reported quarterly. Analysis not yet started,
although planned as part of further joint
assessment of needs with Health and Social Care.
KEY ACTION 4.4
Increase the supply of
older people’s housing
2,501 older people
homes (NLC and
RSL)
Deliver amenity housing in council
new build developments
Increase NS 2026 Number of new council
amenity homes built
On Track 78 new council homes
suitable for older people
(amenity & WC) built in
2021/22.
2,501 older people
homes (NLC and
RSL)
Deliver amenity housing in RSL
new build developments
Increase NS 2026 Number of new RSL
amenity homes built
On Track Improved monitoring arrangements planned for
2022/23.
Initial feasibility
exercise underway
Explore feasibility of delivering
shared equity for older people
linked to the Affordable Housing
Policy
Feasibility exercise
complete and
recommendations
made
BDS/
NS
2022 Feasibility and
recommendations report
Complete Feasibility report complete and Shared Equity
Housing provision set out within the Affordable
Housing Policy Supplementary Planning Guidance
as a delivery option with Cumbernauld HSMA area.

Page 34

28
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 4: There are a range of housing options and supports which promote independence, health and wellbeing
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator
2021/22
KEY ACTION 4.5
Improve the suitability
of existing housing to
meet the needs of older
people
Tender approved Complete the re-modelling/ refurbishment of
Dundyvan Gardens linked corridor retirement
complex
Remodelling
complete
HP 2022 Progress reports Complete Project complete as at October 2022 and in defects
liability stage.
Initial options
appraisal complete
Carry out options appraisal for remaining
linked corridor retirement complexes
Options appraisal
complete
BDS/
HP
2024 Options appraisal report Ongoing Initial assessment of linked corridor complexes
complete with recommendations identified for
investment. Further options appraisal exercise to
take place using supplementary indicator information
to inform investment decisions and priorities.- Develop investment strategy for linked
corridor retirement complexes to improve
long-term sustainability
Investment strategy
complete
BDS/
HP
2025 Investment strategy Ongoing
- Identify new fire safety and prevention
measures for implementation in retirement
housing linked to the new Fire Safety
Guidance for Specialist Housing
Fire prevention and
safety measures
identified and
implemented
HP 2026 Fire Safety
Recommendation Report
and Implementation
Progress Updates
Ongoing Recommendations have been reviewed and a
programme of works is currently being developed
- Implement downsizing incentives and support
to help older people down-size to more
suitable housing
Allocation policy
revised and
downsizing incentive
scheme implemented
HS 2022 Number of older people
assisted to down-size
Complete Allocation policy reviewed to increase level of priority
to households underoccupying social housing.
Incentive payment rolled out in July 2022.
Figures not
yet available.
- Carry out evaluation of impact of re-
classification of sheltered housing in meeting
needs
Evaluation complete BDS 2024 Evaluation report Ongoing Evaluation planned in 2023/2024 to enable sufficient
time for the new older people's housing model to
embed.
- Carry out review of RSL housing support for
sheltered housing and very sheltered housing
Review complete H&SC 2024 Review report Ongoing Not yet started.

Page 35

29
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 4: There are a range of housing options and supports which promote independence, health and wellbeing
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator
2021/22
KEY ACTION 4.6
Improve access to
specialist housing
Development of
housing options
training toolkit
underway
Incorporate specific housing options
information in relation to specialist provision
within the housing options training toolkit
Housing Options
Training toolkit
complete and rolled
out to staff
BDS 2023 Toolkit modular
progress updates
Ongoing Housing Options Toolkit has been rolled out to housing staff
within NLC. NLC continue to take a proactive lead role in the
development of the final component learning pathways and
ongoing learning impact assessment and review.  Recruitment of
Housing Options Toolkit Co-ordinator underway via the Scottish
Housing Network and Memorandum of Understanding agreed for
SHN to take forward the regular maintenance and updating of
the Toolkit going forward.
‘Making Life Easier’
developed with
some housing
information
incorporated
Incorporate further housing information in
‘Making Life Easier’
‘Making Life Easier’
updated
BDS 2024 Number of people
accessing ‘Making
Life Easier’
Ongoing MLE now includes some housing information. This will be
reviewed going forward and updated as required.
- Increase awareness amongst housing staff
of the wider opportunities in MLE for health
and wellbeing to encourage wider ‘good
conversations’ at service contact points by
housing staff around health and wellbeing
Awareness increased BDS 2024 Number of people
accessing ‘Making
Life Easier’
Complete Adapting for Change e-learning module created which includes
information on MLE and housing staff encouraged to complete. 
Pilot of ‘Adapting
for Change’ training
carried out
Progress ‘Adapting for Change’ bespoke
North Lanarkshire e-learning module and
group training to increase awareness of
prevention and early intervention
E-learning module
developed and rolled
out to staff
BDS/
H&SC
2024 Number of staff
completing training
Complete Adapting for Change bespoke North Lanarkshire e-learning
module developed and implemented. Group training carried out
pre-Covid.
KEY ACTION 4.7
Improve the use
of technology
to help enable
independence,
inclusion and
promote better
outcomes
Working group
established to
progress pilot
Complete SMART Homes pilot in Kerr Grieve
Court to identify potential technology options
for older people’s housing
Pilot complete BDS 2025 Smart Home Pilot
report
Ongoing Project was put on hold due to Covid and then was taken forward
by Health & Social Care. The showcase tech was later installed
into Allershaw Tower.
Initial scoping
exercise carried out
Develop interactive SMART Home standard
for council new build homes to ensure digital
infrastructure supports telecare, telehealth
and digital connectivity requirements for the
future
Standard developed NS 2026 New build technology
report
Ongoing Cat 5e cabling installed as standard in all council new build
homes which supports a range of technology and telecare to
support independence, health and wellbeing.  Work ongoing
to identify and test technology options as advancements in
technology progess.
Digital NL underway Engage in the Digital NL developments and
Digital Health and Care Strategy
Completion of Digital
NL
BDS 2026 Digital NL Strategy Ongoing Digital work ongoing independently of Health & Social Care.
‘Tech flat’
developed
Increase awareness and use of technology by
promoting the ‘tech flat’
Increase tech flat
viewings
BDS/
H&SC
2026 Number of people
visiting the ‘tech flat’
Ongoing Tech flat closed for a period of time due to Covid-19 restrictions.
Expected that numbers will increase in future years.
90 visitors
since
LHS was
published.
Working group
established
Transition from analogue to digital alarm
services across older people’s housing
Digital transition
complete
BDS/
HP
2026 Progress reports Ongoing Programme being developed and expecting to commence in
2022/23.

Page 36

30
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 4: There are a range of housing options and supports which promote independence, health and wellbeing
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 4.8
Enable swifter
discharge from
hospital and reduce
delayed discharge
Weekly meetings
established
Establish and maintain housing representation
at weekly discharge meetings to prevent
and resolve any housing related delayed
discharges
Maintain
representation and
identify solutions
HS 2026 Number of delayed
discharges
Complete Housing representation established at weekly
discharge meetings.
Resource flats
in place across
3 retirement
complexes
Replace resource flats within retirement
complexes with mainstream accommodation
to meet a broader range of hospital discharge
related needs
Replace flats
with alternative
mainstream
accommodation
BDS/
HS
2023 Resource flat
replacements
Ongoing Sourcing of replacement flats underway.
Monitoring system
in place with H&SC
review required
Monitor efficacy of resource flats in meeting
needs
Monitoring system
in place
BDS/
H&SC
2026 Number of people
accessing resource
flats
Ongoing Robust monitoring systems to be implemented when
replacement flats identified.
KEY ACTION 4.9
Improve our
understanding of
the housing and
related support
needs of ethnic
minority groups
and others who
experience
disadvantage and
inequality
- Implement collation of equality monitoring
information across tenants' and residents’
groups and people involved in tenant
participation processes
Equality monitoring
system in place and
analysis undertaken
BDS 2023 Monitoring report Ongoing Equality monitoring data template created and plans to
implement early 2023.
Ethnicity, Age and
Disability currently
gathered
Revise the Common Housing Register
Form to include collation of other protected
characteristics information
Common Housing
Register Form
revised
BDS 2023 Common Housing
Register Form
Ongoing Guidance reviewed and consistent approach to
questions agreed with Corporate equalities rep. IT
project required to enable storing and reporting of the
protected characteristics.
Online form
is currently in
development,
changes will be
requested to
incorporate the
requirements.
Corporate Equalities
Group established
Participate in the council’s Corporate
Equalities Group
Continuous
participation
BDS 2026 Meetings held Ongoing Housing represented on Council Equalities Structures
as required.
Housing Co-
production Group
established since
2010
Continue the Housing Co-production Group
and explore expansion of the group to
incorporate more members from under-
represented groups
Continue and expand
the Housing Co-
production group
BDS 2026 Housing Co-
production Group
meetings
Ongoing Covid-19 has had a significant impact on participation
of the Housing Co-production Group, with membership
declining. Further work planned to increase awareness
of the group, opportunities and increase membership.
LGBT module
developed
Ensure housing staff complete LGBT training
module to improve awareness of barriers
and improve housing information, advice and
support
All housing staff
complete training
BDS 2024 Number of staff
completing training
Ongoing 47 staff completed
training as of 19th
October 2022.
Pilots underway
across 3 local
authority areas
Explore negotiated stopping for Gypsy
Travellers
Negotiated stopping
procedure explored
and implemented if
feasible
BDS 2025 Negotiated Pilot
report
Ongoing Negotiated Stopping pilot ongoing with SG with
recommendations planned for Spring 2023. NLC
continue to explore negotiated stopping as part of the
Corporate Gypsy Traveller Group.

Page 37

31
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 4: There are a range of housing options and supports which promote independence, health and wellbeing
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
(cont.) KEY
ACTION 4.9
Improve our
understanding of
the housing and
related support
needs of ethnic
minority groups
and others who
experience
disadvantage and
inequality
Action plan
developed
Progress the actions contained within the
Gypsy Traveller Action Plan to improve
outcomes for Gypsy Travellers in North
Lanarkshire
Completion of actions BDS 2026 Action plan progress
reports
Ongoing Actions progressed as outlined in the Gypsy Traveller
Action Plan with bi-annual updates provided on
progress.
Violence Against
Women Group
established
Work with the Violence Against Women Group
to develop a Violence Against Women Strategy
Strategy complete BDS 2024 Meetings held and
progress reports
Ongoing Violence Against Women Draft Strategy developed. 
Pending approval.
‘Safe and Together’
training currently
provided to H&SC
staff
Roll out ‘Safe and Together’ training for
housing staff
Staff trained BDS 2024 Number of staff
trained
Ongoing Safe and Together Training rolled out to housing staff. 65 staff completed
training as of 14
November 2022.
DAART e-learning
now available
on the council’s
e-learning platform
Roll out Domestic Abuse Awareness Raising
Training (online – DAART) to all housing staff
Staff trained BDS 2023 Number of staff
trained
Ongoing 182 staff completed
training as of 19
October 2022.
Pathway plan
developed
Review Care Pathways for Care Experienced
Young People and for young people with
complex needs transitioning from care
Pathway reviewed BDS/
H&SC
2024 Review report Partially
complete
Care pathways for CEYP reviewed and revised CEYP
protocol implemented. Further work required on young
people transitioning from care with complex needs.

Page 38

32
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 5: We will tackle climate change and fuel poverty
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 5.1
We begin a just
transition towards
a Net Zero North
Lanarkshire
Pilots in progress Adopt ‘as standard’ non-gas heating
approaches for new council homes
Adopt new approach NS 2024/25 Approach and
process developed
Ongoing Pilot project of 19 homes in Airdrie under construction. Results of pilot will
inform.
3.8 (tCO2/year) Average CO2
emissions per home
Ongoing Pilot project of 19 homes in Airdrie under construction. Results of pilot will
inform.
Separate
specifications and
processes exist
Integrate approach to procuring and
maintaining renewable energy installations
Adopt joint technical
specifications for use
of Air Source Heat
Pumps
HP/NS 2021/22 Technical
specifications
Ongoing Ongoing
Establish process
for agreeing new
technical solutions
for alternative
heating systems
HP/NS 2021/22 Process for technical
solutions
Ongoing Ongoing
- Develop understanding of whole life costs
and issues associated with the transition to
low and zero carbon heat on the council and
its tenants
Evaluate impact of
Alternative Heating
pilots
HP/NS 2023/24 Evaluation report Ongoing Pilot project of 19 homes in Airdrie under construction. Results of pilot will
inform.
- Investigate opportunities for district heat
zones
Improved
understanding to
inform strategic
approach in LHEES
CE 2022/23 Options report Not yet
started
Discussions ongoing on who is best placed to lead
on LHEES, aligning this requirement with remit and
available resources.
Feasibility Study 
underway
We will work with our GCR partners to carry
out a feasibility study to outline a clear route
map to successfully deliver the large scale
retrofit programme
Route map BDS/
HP
2024 Route map Ongoing Feasibility study complete. Housing Portfolio Group
considering next steps and actions.
- To address skills gaps and meet the demands
of the City Region new homes and green
energy retrofit programmes we will develop
an integrated skills employment programme
for housing build and repair programmes in
the GCR
Skills development 
programme 
developed
BDS/
NS
2024 Integrated skills 
employment 
programme
Ongoing Glasgow City Council commissioned a report from
Grant Thornton in 2021. Following on from the report
GCC have arranged follow up meetings with the GCR
authorities to discuss funding and challenges, the
last meeting focused on skill shortages for energy
efficiency works.

Page 39

33
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 5: We will tackle climate change and fuel poverty
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 5.2
We improve the
energy performance
of our housing
stock
100% compliance All council new builds meet NLC New Build
Sustainability Standard (which is currently
for Silver Aspects 1&2)
100% compliance with
standards subject to
annual review
NS Annual New build
specifications
On Track 100% 100% of new
builds completed
in 2021/22 meet
standards (137
homes)
- Develop ‘route map’ for EESSH2
compliance
Route map developed HP 2021/22 Route map Ongoing Consultant appointed to support the development of
route map. 
82% of homes in
PRS meet EPC D
(home analytics
data)
Enforce private rented sector energy
efficiency regulations and engage with
private landlords to improve compliance
Local Energy Efficiency
in the PRS Strategy
developed
PSH 2021/22 PRS Strategy Ongoing Works on-going to ensure compliance at application
stage for landlords who renew, and also for new
applications.
Evaluation of new
processes
% of PRS homes
meeting EPC D
On Track Current application process ensures that all new
and renewal applications have a suitable EPC for the
property(s) within the landlord's portfolio.
£14.5 million of
EES:ABS funding
invested in homes
in North Lanarkshire
and 1,000 owners
assisted
Manage Energy Efficient Scotland: Area
Based Scheme (EES:ABS) in
North Lanarkshire
Dependent on annual
allocation of funding -
£2.78m allocated for
2021/22
HP Annual Number of
households assisted
Ongoing Uptake for the scheme has been affected by
changes in legislation and external funding meaning
a percentage contribution from owners is now
required to carry out the improvement works. It
is anticipated that this will affect uptake for the
scheme going forward, unless there is a change in
funding parameters. Measures are being taken to
encourage owners to participate.

Page 40

34
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 5: We will tackle climate change and fuel poverty
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 5.3
We help households
out of fuel poverty
ASHP installed in
316 existing homes
with further 40 new
builds planned for
ASHP/Solar PV/
Battery Storage
– data monitoring
agreed for future
contracts
Evaluate impact of low-carbon heating on
tenants’ energy use and costs to ensure
‘just transition’
Evaluate Energy Use,
Effectiveness and Tenant
Satisfaction
HP/NS 2024/25 Evaluation report Ongoing Pilot project of 19 homes in Airdrie under
construction.
Results of pilot will
inform.
23% Improve energy efficiency and fuel poverty
advice
Develop strategic
partnership with Home
Energy Scotland
BDS 2021/22 % of households in
fuel poverty
Ongoing Energy advice training being arranged with HES for
all housing staff.
Funding secured to deliver an Energy Advice Service
in North Lanarkshire for implementation in 2023.
20%
9% % of households in
extreme fuel poverty
7%
£620 Median (adjusted) fuel
poverty gap
£520
Limited
understanding
based on national
data sets
Improve understanding of the extent,
nature and location of fuel poverty
to enable better identification of fuel
poor households and target resources
effectively
Develop measures to
better identify fuel poor
households, enabling better
targeting of resources
BDS 2022/23 Fuel poverty
measures
Ongoing Liaising with HES and Fuel Poverty Sub-Group

Page 41

35
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 6: Our homes will be fit for the future
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 6.1
Ensure social
rented housing
continues to
meet regulatory
standards
- Deliver priority actions set out in Housing
Asset Management Plan
Actions progressed BDS 2025/26
with annual
review
Housing Asset
Management Plan
Annual Review
Ongoing HAMP Annual Review approved in August 2022 and
ongoing monitoring of actions.
- Develop route map to compliance for NLC
housing stock
Route map
developed and
implemented
HP 2021/22 Route Map Complete Consultant report on achieving NET Zero provided
2021. Financial implications for the stock presented
to senior management team. New EESSH report
commissioned.
89% SHQS
compliance
SHQS compliance Ongoing Compliance routes in place. Impact of changes
to SHQS for electrical compliance/smoke alarms
evaluated for 2021/22.
70%
90% EESSH
compliance
EESSH compliance Ongoing see above 99.2%
3.4% EESSH2
compliance
EESSH2 compliance Ongoing see above
KEY ACTION 6.2
Improve stock
condition in mixed
tenure and other
priority blocks and
estates
- Develop new owner engagement strategy for
mixed tenure estates
Strategy developed
and implemented
HP/PSH 2022 Engagement Strategy No longer
applicable
No longer applicable.
Engagement
underway
Complete CPOs at Millcroft and enable
transformation by Sanctuary (subject to
committee approval)
CPOs complete
and demolition
undertaken
NS Ongoing Number of CPOs Ongoing CPO scheduled to be submitted in early 2023.
Development now being delivered by New Supply.
Committee approval in
Nov 2021 for delivery of
new homes by NLC, rather
than Sanctuary.
- Pilot new approach to identifying and
responding to priorities, using landlord
registration powers to improve house
condition
Pilot complete PSH 2021/23 Pilot report Not yet
started
Not yet commenced, further information being
gathered on if a condition survey is feasible within
current resources.
- Explore development of a factoring support
system to assist owner occupiers who fail to
secure a factor
Development of
factoring support
system explored
PSH 2024 Factoring support
system
Not yet
started
Not yet started.
- Develop a new BTS statement BTS statement PSH 2026 BTS Statement Not yet
started
Not yet started.
- Explore the use of ‘missing shares’ powers to
assist owners to participate in works
Missing shares
powers explored
PSH 2024 Missing shares
powers report
Not yet
started
Not yet started.
- Explore the feasibility of carrying out a house
condition survey to gather better data in
relation to scale and extent of disrepair in the
private sector
Feasibility exercise
complete
BDS/
PSH
2026 Feasibility Report Not yet
started
Not yet started.

Page 42

36
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 6: Our homes will be fit for the future
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 6.3
Ensure owners
are engaged
and informed
about repair and
maintenance issues
New Scheme of
Assistance being
developed
Develop new Scheme of Assistance Scheme of
Assistance adopted
PSH 2022/23 Scheme of Assistance Complete A new Scheme of Assistance was not required.
Following additional funding for mixed tenure grants,
Scheme was reviewed and published.
28% homes in
urgent disrepair
Number of homes in
urgent disrepair
Ongoing 29%
48% homes in
critical disrepair
Number of homes in
critical disrepair
Ongoing 52%
8% of homes in
extensive disrepair
Number of homes in
extensive disrepair
Ongoing 8%
67% of homes in
any disrepair
Number of homes in
any disrepair
Ongoing 72%
Strategic Housing Outcome 7: We improve the quality and accessibility of the private rented sector
Action Baseline 2019/20 Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 7.1
Develop and deliver
new PRS access
scheme
- PRS access scheme developed Scheme developed
and approved
BDS 2022 PRS scheme Ongoing Options paper developed which requires further
discussion prior to implementation of pilot.
41 (2020) Scheme implemented and enabling better
access to the PRS
20 new tenancies
each year
BDS Ongoing
from 2022
Number of homeless
(or potentially
homeless) households
rehoused in the
private rented sector
Ongoing As above. 16
KEY ACTION 7.2
Improve private
sector housing
advice
- Develop and deliver e-learning training
module on the PRS and ensure completion by
all housing staff that deliver housing options
advice
Training developed
and staff trained
BDS 2023 Number of staff
trained
Ongoing E-learning module created and in draft form. Testing
planned prior to launch.
- Establish local PRS champions to encourage
wider improved PRS advice amongst locality
housing teams
At least one ‘PRS
champion’ in each
local housing office
BDS 2023 Number of PRS
champions
Not yet
started
To be progressed in 2023 in tandem with the launch
of the new e-learning module.
- Develop improved information for locality
housing teams on the PRS in North
Lanarkshire and at a locality level as part of
the housing options guide
PRS information
developed and
updated regularly
for locality housing
teams
BDS 2023 Localised information
produced and
updated on a regular
basis
Ongoing Locality information provided in the e-learning
module. This will be supplemented by area profile
information in a revised user friendly format in 2023.

Page 43

37
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 7: We improve the quality and accessibility of the private rented sector
Action Baseline
2019/20
Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 7.3
Develop and deliver
new PRS access
scheme
14,832 Improve registration compliance through targeting
unregistered landlords and landlords whose
registration has expired to ensure they register
Improved
registration
compliance
PSH Ongoing Number of private
landlords registered
Complete A full review of the expired processes for NLC has been
completed and new procedures have been implemented.
8,397 registered
landlords.
- Strengthen partnerships with Police Scotland and
Fire and Rescue to identify criminal activity and
to take multi agency action through the locality
community planning structures
Improved processes
for ensuring private
landlords are ‘fit
and proper’
PSH Ongoing Attendance at local
community groups
Complete Review of panel has been completed. Further, longer-
term work is ongoing in this area to strengthen and fully
review fit and proper and audit processes to strengthen
compliance. Full in depth review of current processes
scheduled to commence in early 2023.
- Work in partnership with Landlord Accreditation
Scotland to deliver training for private landlords
and letting agents in North Lanarkshire
Training delivered PSH Ongoing Number trained Ongoing Landlord Accreditation Scotland training is being delivered
and is ongoing.
143 landlords and
agents trained since
publication of LHS.
- Review the current information provision for
private landlords on the council website and
develop enhanced and improved information
which clearly outlines private landlords’
responsibilities and rights
Information
reviewed and
improved
PSH/
BDS
2023 - Ongoing Updates are carried out to existing published information
with further mailshots available via landlord registration
system where required.
- Re-establish the bi-annual private landlord forum Private landlord
forum held
biannually
PSH/
BDS
2022 Number of private
landlord forums and
number of people
attending
Ongoing Private landlord form re-established with first meeting held
in September 2022.
33 people attended
forum.
- Establish a process to regularly communicate with
landlords through the landlord registration team
on legislative or other policy changes of relevance
Process established PSH 2022 Number of
communications
Ongoing Process is in place to communicate with landlords via SMS
and email using the registration service.
- Develop and issue a bi-annual private landlord
e-newsletter
Newsletter issued BDS/
PSH
2023 Number of
newsletters issued
Ongoing First newsletter in development October 2022.
- Strengthen our outreach and engagement with
private landlords using online platforms
Improved outreach
and engagement
PSH Ongoing Number of
social media
and other online
communications
issued
Ongoing Newsletter published on website. 33 landlords attending
forum.
- Carry out regular surveys of private landlords to
understand challenges and potential solutions to
improve management and quality standards in
the PRS
Surveys carried out BDS Ongoing Number of online
surveys and survey
reponses
Ongoing Survey carried out as part of the LHS development process
which sought to understand the challenges and potential
solutions to improve management and quality standards
in the PRS. Further survey planned in partnership with the
Private Sector Housing Team and as part of the agenda for
the Private Landlord Forum.
499 responses to
survey.

Page 44

38
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 7: We improve the quality and accessibility of the private rented sector
Action Baseline
2019/20
Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 7.3
Develop and deliver
new PRS access
scheme
- Improve our understanding and intelligence of
the PRS to identify issues and target resources
effectively e.g. identifying properties most in need
of energy efficiency measures
Improved
intelligence on PRS
BDS Ongoing Improved data on
the PRS
Ongoing Improved data on PRS expected as part of the new
Rented Sector Strategy when published. In the interim
further analysis of Home Analytics Data required, as well
as collaborative efforts with the Private Sector Team to
improve understanding.
- Scope potential gains from ‘direct interventions’
in substandard PRS properties, such as purchase
and improvement in certain circumstances
Scoping exercise
complete
BDS 2023 Scoping report Ongoing Open Market Purchase Scheme recently expanded, which
includes purchase from a private landlord in certain
circumstances. 
- Develop an engagement strategy for improving
energy efficiency regulations in the PRS which
will include a communications and involvement
strategy and enforcement approach
Engagement
strategy developed
BDS/
PSH
2022 Engagement strategy Not yet
started
Not yet started.
KEY ACTION 7.4
Improve access to
the PRS
- Work with private landlords to improve access to
the PRS for people who are homeless and prevent
PRS households from becoming homeless
Improved outcomes
for homeless
households in the
PRS
BDS Ongoing Number of people
homeless from
PRS and number
of homeless people
rehoused in PRS
Ongoing Range of actions progressed via RRTP. 214 homeless
applicants from the
private the rented
sector.
- Establish a private landlord working group to
identify ways in which the PRS could better
contribute to meeting housing needs in North
Lanarkshire
Private landlord
working group
established
BDS/
H&SC
2023 Number of meetings Ongoing Reps invited to join group at Landlord Forum Event.
Minimal response received so will need to be followed up.
- Work with partner RSLs developing Private
Lettings Services in North Lanarkshire to meet
housing need better, exploring opportunities linked
to RRTP
RSL PSL service
linked to RRTP
BDS 2023 Number of homeless
people rehoused in
the private rented
sector
Ongoing Clyde Valley Housing Association have recently established
a private lettings company. Discussions ongoing as the
new private lettings company becomes further established.
16 homeless
applicants have
been rehoused in
the private rented
sector.
- Review the rent deposit guarantee scheme to
increase uptake
Rent deposit
scheme reviewed
BDS 2023 Number of people
accessing the rent
deposit scheme
Ongoing Review of scheme is currently underway
KEY ACTION 7.5
Improve
involvement of
tenants in the PRS
to improve our
understanding of
issues and help
shape policy
- Establish a PRS tenant panel as part of the tenant
participation activities to identify issues, develop
potential solutions and shape policy to improve
the PRS
Panel established BDS 2023 Number of meetings Ongoing Reps invited to join group at Landlord Forum Event.
Minimal response received so will need to be followed up.

Page 45

39
Local Housing Strategy Annual Progress Report 2022
Strategic Housing Outcome 7: We improve the quality and accessibility of the private rented sector
Action Baseline
2019/20
Milestone Target Lead Timescale Indicators Status Progress 2021/22 Indicator 2021/22
KEY ACTION 7.6
Improve advice and
information to PRS
tenants
- Review and improve the information available for
PRS tenants by working with the PRS tenant panel
to identify gaps and scope for improvement
Information
reviewed and
improved
BDS 2024 PRS tenant
information
Ongoing Not yet started.
- Develop a communications strategy which
involves greater use of social media and online
platforms to increase awareness of tenants rights,
responsibilities and housing options
Communications
strategy developed
BDS/
PSH
2024 Communication
strategy
Ongoing Not yet started.
KEY ACTION 7.7
Support Build to
Rent and Mid-
Market Rent to
deliver high-quality
homes in the PRS
- Work with employers to gather information on the
housing needs of key workers
Information
gathered
BDS Ongoing Information on
housing need
Ongoing Research on housing need planned with NHS Lanarkshire
and larger employers within NL to established gaps and
demand for tenures such as MMR, Shared Equity and
LCHO. Research being scoped in partnership with the
Growth Team.
- Engage with the Build to Rent sector Engagement with
the Build to Rent
sector
BDS/
NS
Ongoing Number of Build to
Rent homes delivered
Ongoing Discussions with developers ongoing. -
- Deliver Mid-Market Rent Homes with RSL partners Deliver Mid-Market
Rent homes
BDS/
NS
Ongoing Number of Mid-
Market Rent homes
delivered
Ongoing 25 MMR homes included in 2023/24-2027/28 SHIP. -
KEY ACTION 7.8
Develop a longer-
term strategic
approach to
improving the PRS
- Develop and implement PRS strategy, following
publication of the new national Rented Sector
Strategy, to outline issues and solutions in a more
detailed  longer-term plan for North Lanarkshire
PRS Strategy
developed and
implemented
BDS/
PSH
2024 PRS Strategy Not yet
started
Not yet started - awaiting publication of the final Rented
Sector Strategy.

Page 46

This document can be made available in a range of languages
and formats, including large print, braille, audio, electronic and
accessible formats.
To make a request, please contact Corporate Communications at:
corporatecommunications@northlan.gov.uk
’S urrainn dhuinn an sgrìobhaidh seo a chur ann an diofar chànanan agus chruthan, a’ gabhail
a-steach clò mòr, braille, cruth claisneachd agus cruthan dealanach agus ruigsinneach.
Gus iarrtas a dhèanamh, cuir fios gu Conaltradh Corporra aig: 
corporatecommunications@northlan.gov.uk
Niniejszy dokument można otrzymać w wielu różnych językach i formatach, w tym również
dużym drukiem, alfabetem Braille’a, w wersji dźwiękowej, elektronicznej i w innych
dostępnych formatach.
Prośby należy składać na ręce zespołu ds. komunikacji drogą elektroniczną na adres: 
corporatecommunications@northlan.gov.uk
此文件可以多种不同语言和格式提供,包括大字体、点字、音频、电子和易读格式。
如想提出请求,请联系企业传讯部:corporatecommunications@northlan.gov.uk
۔ ہے سکتا جا ایکیا ہمار
فر
� یمیں ںتورصو ئیسار بل�قا روا فر�ار ٹ یلیکٹرا ،وی�ڈآ ، ی�ربل� ،فوحر ےرٹبل� لبشمو ںتورصو روا ںنوابل�ز مختلف کو رفری�وستاد سا
corporatecommunications@northlan.gov.uk : ی
ئیں
�مار
فر
� بطہار پر سا سے رفر�فر�ش�ی�کی�فر�و یکمیو ٹ ی�رپورکا یلیے کے تستاخورد مکر ہاربل�
CC_2022_00321
Produced by
NORTH LANARKSHIRE COUNCIL
Enterprise and Communities
Housing Strategy Team