Page 1

North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref  TM/KD Date 15/02/23 
Future New Build Sites 
From  Pamela Humphries, Chief Officer of Place  
E-mail divink@northlan.gov.uk Telephone
Kevin Divin, Project
Development Co-ordinator     
07583 089 510 
Executive Summary 
The council has an approved target to deliver 5,000 new affordable rented homes by 2035.
To date 970 new build houses have been completed with a further 421 homes under
construction. To ensure an adequate supply of sites for the new build programme, potential
council owned sites continue to be evaluated for their suitability for inclusion within the
programme. The sites outlined within this report have been assessed and are
recommended for inclusion within the new-build programme subject to the conclusion of
detailed ground investigations, full title checks and appropriate statutory consents. 
Recommendations 
It is recommended that the Committee:
1) Approves the inclusion of the proposed sites, as outlined in section 2.1 and
Appendix 2 of this report, within the new-build programme.
2) Approves the potential off the shelf purchase of completed homes at Prospecthill
Road, Ravenscraig; Torrance Park, Newarthill and Springhill Road, Shotts as
outlined in section 2.3  
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth

Page 2

1. Background 
1.1 The council has an approved target to deliver 5,000 new homes by 2035, which
although predominantly new build homes also includes properties purchased through
the council’s Buy Back Schemes. To date, 970 new build homes have been completed,
with a further 421 homes under construction. In addition, 606 homes have been
purchased through the Buy Back schemes as at 9th January 2023.  A summary of
progress with the new build programme is attached at Appendix 1 .
2. Report 
2.1 To ensure an adequate supply of sites for the new build programme, potential sites
continue to be evaluated for their suitability for inclusion within the programme. The
sites outlined below have been identified and are recommended for inclusion within the
new-build programme subject to the conclusion of detailed ground investigations, full
title checks and relevant statutory consents. It is proposed that development be
considered at the following sites: 
• Dalzell Drive, Motherwell (former Taggarts Car Sales, Windmillhill Street) –
approximately 24 units (subject to the council concluding purchase of site)
• Former Thornlie Church Hall Site, Caledonian Road, Wishaw – approximately 6
units 
2.2 The proposed project at the former Thornlie Church Hall Site, Caledonian Road,
Wishaw is a priority town centre sites which support delivery of the Town Visions as
part of the council’s commitment to town centre regeneration. This project is at an early
stage of design development / feasibility. 
2.3 It is also proposed to progress the potential ‘off the shelf’ purchase at the following
locations: 
• 23 new homes (4 x 2apt/2p Cottage Flat, 4 x 3apt/4p Cottage Flat, 10 x 3apt/4p
Terraced House, 5 x 4apt/6p Terraced House) at Prospecthill Road, Ravenscraig
from O’Brien Properties Limited
• 6 new homes (6 x 3 bed 5p terraced houses to be purchased as agreed at Finance
and Resources Committee on 30 November 2022) – plus potential purchase of up
to 8 more homes at Torrance Park, Newarthill from Barratt Homes 
• Approximately 22 new homes (houses) over several phases at Springhill Road,
Shotts from Keepmoat 
The acquisition price will be subject to future reports to Finance and Resources
Committee. 
2.4 Site location plans are included for each of these sites within Appendix 2 to this report. 
2.5 Consultation with local elected members and North Lanarkshire Federation of
Tenants and Residents Associations has been undertaken for both the new build and
proposed off the shelf acquisitions and no objections to these sites have been
received.

Page 3

3. Measures of success 
3.1  The success of the council’s new supply programme is measured in terms of: 
• Achievement of target completions of 5,000 completions by 2035.
• Delivery of projects within budget.
• Quality of housing delivered.   
4. Supporting documentation  
Appendix 1  Summary of New Build programme
Appendix 2 Site Locations 
Pamela Humphries
Chief Officer of Place

Page 4

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?  
The new build programme includes measures that will help reduce inequalities of
outcome through certain design features including: 
• Housing for Varying Needs to make homes as accessible as possible;
• Secure by Design to make homes and the surrounding environment as safe
and secure as possible.
• Achieving the Scottish Government requirements for Greener Homes to
• reduce the incidence of fuel Poverty.
• Facilitating improved access to high speed internet capabilities including
installation of ‘fibre to the property’.  
The above features are also part of the specification requirement for off the shelf
properties. 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The cost of constructing or purchasing these homes will be contained within the
overall budget for the new build programme within the Housing Revenue Account. 
There is a grant from the Scottish Government towards the cost of the new homes
which is from a minimum of £71,500 per unit 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic?

Page 5

Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☒ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☒ No ☒ 
If Yes, please provide a brief summary of the impact? 
There are no direct Technology/Digital impacts directly arising from this report. The
scope of the new homes includes Cat5e cabling to support home networking and
Fibre to the Premises (FTTP) for digital connectivity as part of the ‘future-proofing’ of
North Lanarkshire Council’s new housing stock.  This is also part of the specification
requirement for off the shelf properties. 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Intrusive ground investigations will be undertaken as part of the due diligence
associated with determining the suitability of sites for development. This is
undertaken in liaison with North Lanarkshire Council’s Environmental Health
(Pollution Control) to ensure that appropriate investigations are undertaken. 
The new homes are built to higher energy efficiency and sustainability standards,
which helps to reduce future carbon emissions from the properties. This is done via
a fabric first approach to development, while incorporating renewable technologies
where appropriate. 
The Council’s New Supply Programme will ensure that the impact on the Council’s
carbon footprint is mitigated. The specifications incorporated within the contract
documentation will: deliver reduced energy need; encourage sustainable
construction; promote health and wellbeing; reduce waste and resources through
effective storage, collection and composting of waste and recyclable materials and;
include measures which will reduce CO2 emissions). For off the shelf purchases all
such statutory consents would apply and other considerations are included in the

Page 6

negotiations including specification agreement between the Council and Developers
prior to acquisition. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
Risk associated with the New Supply Programme is managed within the Enterprise
& Communities Resources Risk Register process. By undertaking detailed Ground
Investigation and other relevant site assessments, prior to proceeding with the
development of any particular site, the council is mitigating the risk of unforeseen
costs relating to ground conditions, although this risk cannot be eliminated entirely. 
In the case of off the shelf purchases these risks are borne by the developer.
.  
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 7

Appendix 1 - New Build Sites Summary (as at 9th December 2022)
Area Location Units Comments
Completion
Year
Holytown Main St 10 Completed (Amenity) 2010/11
Holytown Spruce Way 10 Completed 2010/11
Motherwell
Ravenscraig (David Wilson
Homes) 18
Completed (off the
shelf) 2010/11
Airdrie Clarkston PS 19 Completed 2011/12
Millerston Coshneuk Rd 11 Completed (Amenity) 2011/12
Cumbernauld North Rd 29 Completed 2011/12
Wishaw Cambusnethan PS 20 Completed (Amenity) 2011/12
Viewpark Laburnum Rd (Phase 1) 12 Completed 2012/13
Viewpark Laburnum Rd (Phase 2) 28 Completed 2013/14
Moodiesburn Gartferry Road 50 Completed 2013/14
Cumbernauld Westfield Drive 30 Completed  2013/14
Airdrie Former Albert PS 14 Completed 2014/15
Chryston Lanrig Rd 27 Completed (Amenity) 2014/15
Coatbridge Corsewall St 14 Completed 2014/15
Bellshill Former Belvidere PS 20 Completed 2015/16
Kilsyth Fisher Ave 30 Completed 2015/16
Chryston
Old Lindsaybeg Rd
(Persimmon) 14
Completed (off the
shelf) 2015/16
Motherwell Glencairn Tower site 25 Completed 2016/17
Viewpark Former Tannochside PS 16 Completed 2017/18
Wishaw Walkerburn Dr, Coltness 20 Completed 2017/18
Cumbernauld Cardowan Drive 30 Completed 2017/18
Cumbernauld Kildrum Nursery 16 Completed 2017/18
Chryston Station Rd (Persimmon) 30
Completed (off the
shelf) 2017/18
Chapelhall
Former St Aloysius PS
(Phase 1) 24 Completed 2017/18
Chapelhall
Former St Aloysius PS
(Phase 2) 6 Completed 2018/19
Cumbernauld Brown Road 20 Completed 2018/19
New
Stevenston Former New Stevenston PS 15 Completed 2018/19
Chryston Greenlea Road 21 Completed 2018/19
Coatbridge Old School Court 20 Completed 2018/19
Airdrie Former Alexandra PS 14 Completed 2018/19
Harthill Former Harthill PS 20 Completed 2018/19
Motherwell
Cleekhimmin, Ravenscraig
(Barratt) 10
Completed (off the
shelf) 2019/20
Coatbridge Blair Road 40 Completed 2019/20
Motherwell Calder PS 30 Completed 2019/20
Gartcosh
Johnston Rd / Inchnock Ave
(Bellway) 16
Completed (off the
shelf) 2019/20

Page 8

Cumbernauld Cedar Road Nursery 14 Completed 2019/20
Chryston Main Street (Bellway) 18
Completed (off the
shelf) 2019/20
Wishaw
Meadowhead Rd,
Ravenscraig (Keepmoat) 11
Completed (off the
shelf) 2019/20
Bellshill
Caledonian Avenue (Phase
1 ) 19 Completed 2020/21
Wishaw Dimsdale Road (Phase 1) 6 Completed 2020/21
Bellshill 
Caledonian Avenue (Phase
2)  8 Completed 2021/22
Wishaw 
Dimsdale Road  (Further
Phases) 55 Completed 2021/22
Coatbridge 
St James PS / Lismore
Drive 58 Completed 2021/22
Wishaw
Roberts Street (Belhaven
House) 16 Completed 2021/22
Wishaw Mossburn St, Waterloo 20 Completed 2022/23
Plains Plains PS 16 Completed 2022/23
Sub total   970 Completed  
Chryston 
Former Chilterns Care
Home 21 On Site   
Airdrie Dykehead Road (Holehills) 150 On Site  
Airdrie Northburn Place 31 On Site  
Bellshill Community Road 29 On Site  
Airdrie 
Former Orrs Building
(Wilson) 20 On Site  
Wishaw
Castlehill Road,
Gowkthrapple (Phase 1)  97 On Site  
Coatbridge Berwick St 19 On Site  
Stepps Gateside Farm (Barratt) 30 On Site  
Motherwell
Former BRE, Ravenscliff
Rd, Ravenscraig 24 On site  
Sub total   421 On site  
Coatbridge Columba High School 130
Design development
underway  
Motherwell Mabel Street 20
Planning app
approved   
Glenmavis McArthur Ave 21
Planning app
approved  
Viewpark Laburnum Rd 26
Planning app
approved  
Coatbridge Bank Street 9
Planning app
approved  
Airdrie Glenacre Drive 16
Planning app
approved  
Chapelhall Gibb Street 25
Planning app
approved  
Wishaw Graham Street 13
Planning app
submitted

Page 9

Coatbridge Kildonan Street 49
Design development
underway  
Cumbernauld
Former Cumbernauld
Village PS 8
Planning app
approved  
Glenboig
Former Police Station, Main
Street 7
Planning app
approved  
Motherwell Brandon Street 48
Planning app
approved  
Wishaw King Street 5
Planning app
approved  
Wishaw
Stewarton Street & Kings
House 17
Design development
underway  
Motherwell
Former Motherwell Town
Hall 20
Planning app
approved  
Airdrie Calderigg Place  42
Design development
underway  
Airdrie  Former Petersburn PS  40
Planning app
approved  
Millerston Coshneuk Road 16
Design development
underway  
Wishaw  Caledonian Road  9
Planning app
submitted   
Coatbridge  Mitchell Street 100
Approved at
Committee - Aug
2022  
Caldercruix  Former St Mary's PS  25
Approved at
Committee - Aug
2022  
Bellshill Thorn Road  26
Approved at
Committee - Aug
2022  
Airdrie  Airdriehill Road  75
Approved at
Committee - Aug
2022  
Motherwell  Hope Street (Masonic Hall) 10
Approved at
Committee - Aug
2022  
Coatbridge  Main Street  40
Approved at
Committee - Aug
2022  
Sub total   797
Design
development
underway  
Coatbridge Shawhead 111 Re-provisioning site  
Coatbridge Dunbeth  170 Re-provisioning site  
Motherwell Coursington 60 Re-provisioning site  
Sub total   341
Re-provisioning
sites

Page 10

Cumbernauld
Community Growth Area -
Phases 1-3 (Bellway) 75
Off the shelf
Planning app
submitted  
Chryston Gartferry Road (Allanwater) 22
Off the shelf                                   
Purchase approved
at Committee  
Coatbridge  Lorne Place (Allanwater)  24
Off the shelf 
Purchase approved
at Committee  
Moodiesburn
Auchengeich, Gartferry
Road (Bellway) 12
Off the shelf 
Purchase approved
at Committee  
Cumbernauld
Kingfisher, Dowanfield Road
(Zoom) 24
Off the shelf
Purchase approved
at Committee  
Coatbridge 
Former DWP Offices, South
Circular Road (ML5 Limited) 39
Off the shelf
Purchase approved
at Committee  
Gartcosh 
Johnston Rd - Phase 2
(Bellway) 12
Off the shelf
Purchase approved
at Committee  
Sub total   208
Future off the shelf
purchases from
developers  
Total    2737

Page 11

Appendix 2 - General Outline of Site Locations
• Dalzell Motherwell – approximately 24 units: 
• Former Thornlie Church Hall Site, Caledonian Road, Wishaw – approximately 6 units:

Page 12

• Prospecthill Road, Ravenscraig – 23 units.

Page 13

• Torrance Park, Newarthill – Up to 14 units

Page 14

• Springhill Road, Shotts from Keepmoat – Approximately 22 units over several phases