North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  GT/JMcG Date 15/02/23 
Revenue Monitoring Report – Enterprise and Communities 
From  Derek Brown, Depute Chief Executive  
E-mail telferg@northlan.gov.uk Telephone
Greg Telfer, Business
Finance Manager, 07583
010692 
1. Background 
1.1 The Council’s approved Financial Regulations require services to remain within their
approved budgetary provision, and to report all significant deviations – defined as the
higher of £100,000 or 5% - within their budget monitoring reports. Where significant
deviations are identified, services must provide explanatory commentary, outline the
action required to rectify such deviations and where relevant, must also highlight the
impact this has on other budget headings.
Executive Summary 
This report provides a summary of the financial performance of the Enterprise and
Communities service for the period 1 April 2021 to 6 January 2023 (Period 10). The report
illustrates the projected outturn as at 31 March 2023, with major outturn variances highlighted
and explained as per the Council’s approved Financial Regulations. 
In summary, the Enterprise and Communities Service is currently forecasting an overspend
of £3.342m. This is mainly attributable to inflationary pressures (£2.625m), which will be offset
by a corporate contingency, and the reallocation of DigitalNL savings to Services (£0.783m).
The Service continues to work with Business and Digital to progress plans for delivery of these
savings. Note these Period 10 figures exclude the impact of the agreed 2022/23 pay award
which is being reported corporately at this point in time. 
Recommendations
It is recommended that Committee: 
(1) Acknowledges the financial position of the 2023/23 Enterprise and Communities
revenue budget.  
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

1.2 The most significant financial risk facing Enterprise and Communities during 2022/23
is inflationary pressures across a number of service areas including fuel, utilities, food
costs, waste tonnage and contractual inflation on property and road maintenance
contracts. At Period 10 it is forecast that the impact of this is £2.625m and this will
continue to be monitored and reported through service budget monitoring reports
alongside the ongoing impact of the curtailment of non-essential expenditure with the
overall impact managed corporately.   
2. Report 
Summary of Financial Position 
2.1 The Council approved its General Fund Revenue Budget on 17 February 2022, of
which £146.298m (17%) represented the approved Net Revenue Budget for Enterprise
and Communities.  Since then there has been additional budget added for Scottish
Government funding for climate change (£0.075m) and reduction in relation to budget
transfers to other services (£0.168m), the transfer of DigitalNL savings (£1.535m) as
well as a reduction in the National Insurance budget to reflect chances in UK
Government tax policy (£0.140m). These changes result in a revised Enterprise and
Communities Net Budget of £144.530m. 
2.1.1 Enterprise and Communities is forecasting an overspend of £3.342m in relation to
inflationary pressures (£2.625m), and a delay in the delivery of savings linked to the
DigitalNL programme (£0.783m), offset in part with other minor service underspends
across the service (£0.067m). 
2.1.2 Like most organisations, the Council is facing significant pressures linked to the wider
economic outlook and high inflation.  Across the service the current forecast is
unbudgeted costs of £2.625m across energy, waste disposal, fuel, food and materials. 
The Council has set aside approximately £9.400m corporately to support unbudgeted
inflationary pressures faced by services. 
2.1.3 In addition, the Service faces a cost pressure attributable to the delay in implementation
of savings linked to the DigitalNL programme (£0.783m). The service continues to work
with Business and Digital to progress plans for the delivery of these savings. 
2.1.4 Section 2.2 provides commentary on the financial performance of the Service per
division excluding the impacts of inflation and digital savings.  In addition, Appendices
1 to 6 of this report provide further explanation of the significant budget variations
contributing to this outturn position. 
2.1.5 The 2022/23 Enterprise and Communities budget incorporates £3.080m of savings
previously approved by Council on 2 March 2021 with £0.905m of savings (29%)
deliverable within the current financial year. Further information regarding particularly
challenging savings is noted in paragraph 2.4 below. 
Analysis of Significant Variations 
2.2 Excluding the impact of inflation, digital savings and National Insurance changes, the
Enterprise and Communities service currently forecasts a year-end underspend of
£0.067m.  As at Period 10, there are largely compensating variances across the
divisions as follows:

Page 3

2.2.1 Regulatory Service and Waste Solutions (£1.415m overspend) 
The projected overspend is largely attributable to increased agency and overtime costs
in Waste as a result of delays in recruitment (£0.535m) and a net under-recovery in
Special Uplifts as a result of reduced demand (£0.162m).  Within Fleet there are
increased leasing costs (£0.115m), increased external hire costs (£0.317m) and costs
for vehicle parts (£0.117m) partially offset by vacancy savings (£0.117m).   
2.2.2 Asset and Procurement Solutions (£0.058m overspend)
The division projects an overspend of £0.223m within property costs due to a delay in
the timing of office accommodation savings and loss of rental income (£0.580m) offset
by the use of an ear-marked reserve and employee vacancies. Within the provision of
school meals the service expects an under recovery in paid meal income (£0.142m)
which is fully offset by vacancies across the division. 
2.2.3 Planning and Regeneration (£0.897m underspend)
The underspend within Planning and Regeneration is related to vacancy savings
(£0.342m), additional grant income (£0.105m) and an over-recovery in planning fee
income (£0.403m). 
2.2.4 Environmental Assets (£0.509m Underspend)
The Environmental Assets division is forecasting net vacancy savings of £1.530m partly
offset by increased overtime of £0.350m. This underspend is as a result of difficulties
in recruiting key posts across the division.  Income is also forecast to over recover by
£0.107m mainly from charges in relation to road occupation and construction consents. 
This is partially offset by costs in relation to electric vehicle charging for which there
has been significantly increased demand and unit costs (£0.539m) and consultants
fees to support project delivery (£0.253m). 
2.2.5 Included within the reported outturn is the Council’s trading services. For 2022/23 the
Council approved a surplus budget of £0.596m. The Council must comply with a
statutory requirement to at least break-even over a rolling three year period. The
combined surplus in 2019/20, 2020/21 and 2021/22 was £0.380m. As at Period 10
there are no significant variations to report with regards to trading services. 
2.2.6 Payments to other bodies are detailed in Appendix 3. This expenditure category
accounts for £21.302m with a minor overspend of £0.107m forecasted for 2022/23. 
Earmarked and One-off Reserves 
2.3 Enterprise and Communities was given approval to earmark £17.503m of resources
during the completion of the 2021/22 annual accounts. It is forecast that £10.336m of
the reserve balance will be utilised in 2022/23. A balance of £6.915m is required for the
original purpose in future years. The remaining balance of £0.252m is no longer
required for Business Recovery/Growth. Appendix 4 details the individual Earmarked
Reserves. 
2022/23 Budget Savings and Growth 
2.4.1 The Service uses a variety of information, records and processes to monitor
achievement of its approved budget savings of £3.080m. As at Period 10, £0.905m
(29%) of its approved savings are achievable during the year. The gap of £2.176m
represents digital savings (£1.428m), which has been partially offset by use of an
earmarked reserves in 2022/23 (£0.644m).  A timing delay in office rationalisation

Page 4

(£0.580m) which has been fully offset in-year from temporary rates savings and other
in year property cost savings and vacancy savings within Asset and Procurement
Solutions.  The previously approved reduction in school cleaning (£0.200m) has also
been offset by use of earmarked reserves in 2022/23 and incorporated into the
Council’s Medium Term Financial Planning assumptions. The other staff saving
(£0.076m) is being offset by in year vacancy savings. 
2.4.2 As part of the Council’s investment budgets for 2021/22 and 2022/23, Enterprise and
Communities was allocated £9.228m towards a number of one-off investments.
Appendix 6 highlights in detail how these are being utilised across the Service. 
Management Actions 
2.5 The Service continues to take a range of corrective management actions to ensure it
manages cost pressures. This includes curtailment of non-essential spend and
monitoring of vacancies. 
Change Management 
2.6 The Service expects to use £0.423m of the Council’s Change Management Fund
mainly to support the supply of new bins and materials within Environmental Assets, as
well as redundancy.  Costs within the Change Management Fund are not included in
the Service outturn position 
3. Measures of success 
3.1  The Service continues to operate within the approved budget resources   
4. Supporting documentation 
Appendix 1  Objective Analysis 
Appendix 2  Subjective Analysis 
Appendix 3  Payments to Other Bodies Analysis 
Appendix 4  Status of Earmarked Reserves 
Appendix 5  Challenging Savings 
Appendix 6  One-Off Investments 
Derek Brown
Depute Chief Executive

Page 5

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The Service continues to curtail non-essential expenditure and take management
action to minimise the impact of cost pressures on the Council’s overall financial
position.  
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐

Page 6

5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
All activities undertaken by the Council are subject to risk, and in acknowledging
the Council’s approved Risk Management Strategy, Services managed these as
part of their overall corporate and service planning processes. The current
economic climate, in particular, has the potential to impact upon the Council’s
ability to provide quality services within the approved budget levels. 
To reduce other financial risks, this report was prepared by service based Financial 
Solutions personnel in consultation with budget managers, in accordance with the 
Financial Regulations. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 7

Appendix 1
DIVISION OF SERVICE BUDGET ACTUAL ANNUAL PROJECTED MOVEMENT FROM ANALYSIS
TO DATE TO DATE BUDGET OUTTURN % PERIOD 9
(1) (2) (3) (5) (6) (8) (9) (10)
£ £ £ £ %
ENVIRONMENTAL ASSETS 23,747,538 23,765,204 47,357,455 48,022,576 (1.4%) (124,907) Overspend as a result of Utility Inflation/waste disposal/ Digital
savings (£1.148m) and increased usage and price for Electric Vehicle
Charging and consultant fees partly offset by vacancy savings and
increased income for Road occupations and construction consents.
REGULATORY SERVICES AND WASTE SOLUTIONS 25,097,823 25,649,228 37,123,707 39,609,856 (6.7%) (59,958) Overspend as a result of Inflation mainly for Waste Disposal costs
/Fuel/ Vehicles parts and digital savings (£1.071m).  Additional
spend in agency costs/overtime due to recruitment delays parly
offset by vacancies and also reduced demand for Special Uplift
resulting in an under recovery in income.
ASSETS & PROCUREMENT 31,759,645 31,236,648 38,272,520 39,289,023 (2.7%) 13,454 Overspend as a result of Utility and Food Inflation and Digital
Savings (£0.958m) and timing delays in Office Rationalisation
savings and lost rental income.  There is also an under recovery in
paid meal income which is offset fully by vacancy savings.
PLANNING & REGENERATION 4,496,069 3,966,960 9,545,283 8,647,959 9.4% 363,398 Underspend mainly as a result of Vacancy savings, and increased
planning fee income, as well as additional grant income.
HOUSING SOLUTIONS 1,120,851 1,041,532 5,330,715 5,364,201 (0.6%) 53,549 Overspend on Digital savings and Utility inflation (£0.141m),
partially offset by vacancy savings and other minor miscellaneous
budget savings.
HOUSING PROPERTY & PROJECTS 6,158,968 5,976,608 7,495,518 7,533,142 (0.5%) 10,000 Overspend as a result Utility inflation (£0.063m) partially offset by
vacancy savings.
TRADING (623,992) (615,341) (595,542) (595,542) 0.0% (1) Balanced budget
NET EXPENDITURE 91,756,902 91,020,839 144,529,656 147,871,215 255,535
(4) (7)
Enterprise & Communities
Revenue Budget Monitoring Report - Objective Analysis
1st April 2022 - 6th January 2023 (PERIOD 10)
YEAR TO DATE PROVISIONAL
VARIANCE VARIANCE
£
(665,121)
(1,016,503)
(2,486,149)
522,998
529,109
79,319
£
(17,666)
(551,405)
0
736,063 (3,341,559)
897,324
(33,486)
(37,624)182,360
(8,652)

Page 8

No embedded text on this page.

Page 9

No embedded text on this page.

Page 10

No embedded text on this page.

Page 11

No embedded text on this page.

Page 12

Budget 2022/23 Enterprise & Communities Appendix 6
One-off Investments Priorities
£'m £'m £'m £'m
Division Priority Area Council Motion Narrative 2022/23
Allocation
Actual To
Date
Projected
Outturn
Future EMR
Request
Approved in March 2022
APS Recover NL Pitch Improvement Programme Targeted investment in the Councils Pitch estate to
upgrade four existing pitches to synthetic surfaces at
Harthill, Moodiesburn, Cleland and Mossend and
replace existing synthetic pitches reaching the end of
their economic life.  This will support increased
participation and letting income.
2.200 0.000 2.200 2.200
Env Assets Community safety Investment in signage and community safety
improvements across North Lanarkshire to support 
the introduction of mandatory 20mph speed limits
around schools, early learning and childcare
establishments.
2.005 0.496 0.496 1.509
Env Assets Cemetery and Footpath Improvements Infrastructure improvements to existing cemeteries
and investment to improve footpaths and
accessibility across the Councils communities, active
travel routes and country parks
1.500 1.500 1.500
Planning & Regen Recover NL - Town Centre Improvements Augmentation of Place Based Investment Programme
to support community-led initiatives for town centre
revitalisation
1.000 0.141 0.141 0.8594
EA / RSWS Recover NL - Environmental Improvements Continuation of RecoverNL environmental
improvements including community led clean-ups,
action on fly tipping and pest control activity
0.850 0.167 0.683
Env Assets Community Sustainability Projects To focus on enhancing sustainability and reducing the
Councils carbon footprint a range of projects will be
delivered including wildflower planting across town
parks and the school estate.  The investment will
include exploring and delivering options for natural
play within communities and investment in green
energy interventions to promote carbon neutrality in
country parks
0.700 0.675 0.675 0.025
Sub Total 8.255 2.979 5.694 4.594
Approved in March 2021
Env Assets Festive Lighting Provision of Xmas Lights in Towns in 2021/22 and
2022/23 at a cost of £0.150 million per year.
0.150 0.114 0.150
Env Assets Road Improvements Targeted Improvement to provide additional
community benefit on schemes such as road
infrastructure improvements, resurfacing and pot
holes, road safety schemes, signage upgrades (i.e.
20mphs) and discrete road improvements
0.133 0.086 0.133
Housing Solutions Anti Social Task Force Provide Antisocial Behaviour Services for Private
Residents in both 2021/22 and 2022/23
0.321 0.11123 0.183 0.13823
RSWS PEST Control Treat defined priority areas over the summer period
to address local concerns.
0.127 0.056 0.127
RSWS Housing Grants to Owner Occupiers - Mixed TenureTo provide grants to owner occupiers in mixed tenure
settings to facilitate structural upgrades.
(£0.150m per year in both 2021/22 and 2022/23)
0.243 0.056 0.243
Sub Total 0.973 0.423 0.835 0.138
Total 9.228 3.403 6.530 4.732
One off Investment