North Lanarkshire Council
Report
Housing Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref  GT/JM Date 15/02/23 
Enterprise and Communities – Capital Monitoring Report 
From  Derek Brown, Depute Chief Executive  
E-mail telferg@northlan.gov.uk Telephone
Greg Telfer, Business
Finance Manager, 07583
010692 
1. Background 
1.1 Financial year 2022/23 is the second year of the 5 year capital programme which was
initally approved by the Policy and Strategy Committee on 18 March 2021.   
Executive Summary 
This report highlights the financial performance of 2022/23 Enterprise and Communities
capital programme for the period ended 6 January 2023 (Period 10). 
In summary the Service has a total capital budget of £159.192m.  At this stage in the
financial year the service is currently reporting a requirement to reprofile £23.053m to future
years of the current capital planning period. The Council’s Strategic Capital Delivery Group
(SCDG) has approved these reprofiling requests under delegated powers and the impact
will be reflected in future reports. (see Appendix B).  The requirement to reprofile is largely
attributable to current market conditions on capital procurement processes resulting in later
than anticipated start dates for projects and continuing issues contracts are experiencing
with the availability of labour and materials. 
Further explanation of project variances and management action taken by the Service is
included within the main report and attached appendices. 
Recommendations
It is recommended that the Committee: 
(1) Acknowledges the financial position of the 2022/23 Enterprise and Communities
capital programme. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

1.2 The Enterprise and Communities 2022/23 capital programme of £157.168m was
approved by the Policy and Strategy Committee on 17 March 2022. The programme
has since been increased by £5.796m relating to carry forwards from 2021/22 and
reduced due to £14.505m reprofiling to 2023/24 approved at the Council’s SCDG on
15 September 2022.  In addition, a further £10.734m has been received in external
funding giving an overall working capital programme of £159.192m. 
1.3 The Community Investment Fund Annual Update was presented to Policy and Strategy
Committee on 29 September 2022. The report highlighted a reduction in projected
resources as a result of higher borrowing costs and lower than anticipated Council Tax
growth. Consequently, there was a requirement to reduce the current 5-year capital
investment programme by £22.076m. The programme amendments were approved at
Policy and Strategy Committee on 1 December 2022. SCDG will work with services to
identify the profile of expenditure reductions across the remaining years of the capital
programme which may have an impact on resources available during 2022/23. 
1.4 The Council’s approved Financial Regulations required services to remain within their
approved budgetary provision, and to report all significant deviations – defined as the
higher of £0.100m or 5% - within their budget monitoring reports.  Where significant
deviations were identified, services must provide explanatory commentary, outline the
action required to rectify such deviations and where relevant, must also highlight the
impact this has on other budget headings. 
2. Report 
2.1 At Period 10 the service is reporting a requirement to reprofile £23.053m of expenditure
to future years of the current capital planning period. This reprofiling request has been
approved at the Council’s SCDG on 2 February 2023 and will be refected in future
monitoring reports (see Appendix B).  Capital budgets and expenditure are summarised
into Project/Themes (see Appendix A) 
2.2 Assets and Procurement Solutions (£9.658m Underspend) 
The division has a number of in year variances across programmed activity. The most
significant variance relates to the profile of expenditure in the Community Hub projects
at Chryston and Carnbroe where updated contractor work programmes indicate
£2.286m of expenditure will now be incurred in the new financial year. 
In addition, an in year underspend of £1.610m is expected within Carbon Management
projects as the service has sought to finalise the programme of work and select a
preferred bidder. Expenditure will now be incurred during 2023/24. 
The ASN / Social Work Rationalisation is forecast to underspend by £2.009m this
financial year which is mainly for the Bothwellpark project.  The planning application for
this project has been submitted and progress has been made to formalise the design,
however, it is now anticipated this project will complete late 2023.  In addition, to allow
more accurate scoping works at the Children’s Houses, the cost profile of these works
have also been reprofiled to 2023/24. 
Within Demolitions there is a forecast underspend of £0.537m due to revised timing of
the demolition of the Fleming House following ongoing negotiations regarding
relocating the rooftop antennas.  There are also further in year underspends of £0.221m
forecast with the 1140 Programme and £0.276m within Sustainable Estate due to the
profiling of costs. In addition, an underspend of £0.211m is expected within future

Page 3

capital receipts, work contractors have now been appointed for Mid-Forrest Community
Growth Area and Napier Residential Site so these funds will be spent next financial
year. These are offset in part as projects have been accelerated within Office
Rationalisation (£0.455m) 
These underspends are also partially offset by a combination of compensating
variances within the Maintaining Existing Assets Category. Programme acceleration in
Health & Safety Works (£0.580m) due to increased costs via tender award and
acceleration of required power generator works. Toilet Upgrades are forecast to
overspend (£0.415m) as tender returns have come in higher than anticipated. In
addition, projects have been accelerated within major maintenance on the Time
Capsule Moveable Flooring (£0.300m), and café works at Bellshill Cultural Centre
(£0.197m) to assist in managing the overall variance. Re-wire works (£0.863m) and re-
roofing projects (£0.317m) are expected to underspend as jobs are now spanning the
financial years. 
The Outdoor Education and Outdoor Spaces theme is reporting an in-year underspend
of £3.165m relating to the receipt of additional one-off investment allocations where the
spend in now forecast to fall into 2023/24.  In addition, a request has been made to
approve a budget virement from the Demolitions theme (£0.500m) to support additional
costs associated with the pitch programme (See Appendix B). 
2.3 Environmental Assets (£7.196m underspend)
Infrastructure and Transportation Improvements theme is forecasting an underspend
of £2.506m.  This is mainly as a result of maximising external funding in Traffic Signals
and Pedestrian Crossings (£1.754m), Active Travel Infrastructure (£0.171m), Public
Transport Infrastructure (£0.462m) and Drainage and Flood Risk Management
(£0.117m). These underspends will be used to offset partly the overspend within the
Horsely Brae project of £0.357m.  The team are actively completing the tender process
and works within this theme will now be completed in 2023/24. There is also an
underspend in staffing costs (£0.360m) within this area due to recruitment issues which
means there are a number of vacancies within the design team. 
Cemeteries/Tree Infrastructure is projecting an underspend of £2.711m which is
directly linked to the Cemetery Development works at Pather Fam where ground issues
have meant a delay in the tendering process.  The tender is now expected to be
awarded February 2023 and works commencing early in the new financial year.
There is also an underspend of £1.973m anticipated in the Roads Asset Management
theme this financial year. Within Street Lighting and in-year underspend of £0.953m is
attributable to contractor cashflows following tender award. The works will now span
into 2023/24.  There has also been a delay in the works commencing at the A73 Carlisle
/ South Biggar Road project which has meant, although the contract has been awarded
this financial year, £0.629m of works is expected to slip to 2023/24.  In addition to this
£0.150m has been identified as a capital saving on this project due to tender prices
being lower than anticipated.  Works at The Loaning in Motherwell are also expected
to be completed next financial year as the service incorporates feedback from ongoing
public consultation (£0.240m).  
Greenspace is currently reporting an underspend of £0.134m. £0.112m has been
identified as a capital saving and the remaining £0.022m is being held to offset a
staffing pressure within Parks Masterplans due to the temporary recruitment of an
additional post this year.

Page 4

£0.106m is overspent within Replacement of Plant and Machinery and a request is
included within appendix B for these funds to be accelerated from 2023/24.
2.4 Planning and Regeneration (£2.981m underspend)
The service anticipates as in year underspend in the City Deal programme of £1.296m
mainly as a result of delivery timescales for the completion of required work for the
West Coast Main Line in partnership with Network Rail.  This expenditure forecast now
falls into the first quarter of 2023/24. 
In addition, there are a number of in year underspends in Ambition programmes
totalling £1.685m. Similar to other areas of the service, in order to maximise external
funding some of the Council funded elements of these projects will now occur later than
anticipated in the financial year and will now straddle into the 2023/24. 
2.5 Regulatory Services and Waste Solutions (£3.218m underspend)
The majority of the underspend relates to the Bellshill Depot (£1.818m) as a result of
delays in commencing construction with planned spend continuing into 2023/24. The
remaining underspend relates to the Vehicle Replacement Programme in Fleet
(£1.399m) and comes as a result of ongoing review of fleet requirements across the
Council and the timescales to get delivery of new vehicles.  A request has been made
to vire these funds into the Bellshill Depot project (See Appendix B). 
3. Measures of success 
3.1  The Service aim is to be in a balanced budget position at financial year-end 
4. Supporting documentation 
4.1 Appendix 1 Summary Expenditure by Project/Theme 
4.2 Appendix 2 Budget Virement Requests 
Derek Brown
Depute Chief Executive

Page 5

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The Service aims to operate within approved funding levels and utilise budget
virements to support emerging issues and mitigate variances across budget heads. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐

Page 6

5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
All activities undertaken by the Council are subject to risk, and in acknowledging the
Council’s approved Risk Management Strategy, Services managed these as part of
their overall corporate and service planning processes.  The current economic
climate, in particular, has the potential to impact upon the Council’s ability to provide
quality services within approved budget levels. 
To minimise risk this report was prepared by service based Financial Solutions
personnel in consultation with budget managers, in accordance with the Financial
Regulations. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 7

Appendix 1
Enterprise & Communities Capital Programme 2022/23 1.754
Theme Expenditure Summary
1st April 2022 - 6th January 2023 (PERIOD 10)
Thematic Category
Revised
Budget
£
Actual
£
Committed
£
Uncommitted
£
Projected
Outturn
£
Outturn
variance
£
ASSET & PROCUREMENT SOLUTIONS
Maintaining Existing Assets - windows, re-roofing, re-wiring
and condition survey works for the Council's building assets
8,857,868 3,977,165 8,491,779 533,174 9,024,953 (167,085)
Carbon Management 2,126,769 334,779 334,779 181,783 516,562 1,610,207
Office Rationalisation (16,849) 63,151 408,151 29,660 437,811 (454,660)
Shared Campus 0 0 0 0 0 0
Leisure Development 1,311,349 1,558,329 1,397,260 13,300 1,410,560 (99,211)
Health & Wellbeing & Digital Classrooms 411,693 201,509 424,282 38,490 462,772 (51,079)
Rationalisation including ASN & Social Work 3,599,432 974,229 1,560,316 30,000 1,590,316 2,009,116
Curriculum Development 863,951 512,572 806,408 0 806,408 57,543
Sustainable Estate 1,474,242 505,720 809,021 389,555 1,198,576 275,666
Outdoor Education and Outdoor Spaces 3,928,176 377,289 762,289 0 762,289 3,165,887
Future Capital Receipts Investments 985,791 153,715 774,434 0 774,434 211,357
Design Fees 1,525,383 582,415 1,469,176 0 1,469,176 56,207
1140 Early Learning and Childcare Expansion 2,191,802 1,208,798 1,298,546 672,189 1,970,735 221,067
Demolitions 1,010,383 83,002 170,640 302,691 473,331 537,052
TOTAL ASSET & PROCUREMENT SOLUTIONS 28,269,990 10,532,673 18,707,083 2,190,841 20,897,924 7,372,067
TOWN AND COMMUNITY HUBS
Town and Community Hubs 49,860,100 32,766,273 46,741,429 832,324 47,573,753 2,286,347
TOTAL TOWN AND COMMUNITY HUBS 49,860,100 32,766,273 46,741,429 832,324 47,573,753 2,286,347
ENVIRONMENTAL ASSETS
Infrastructure and Transportation Improvements 10,577,727 4,416,950 7,686,662 385,039 8,071,701 2,506,026
Greenspace infrastructure Health & Wellbeing 1,388,179 210,047 385,337 868,677 1,254,014 134,166
Parks Masterplans 2,911,807 1,270,652 1,505,565 1,428,786 2,934,351 (22,545)
Environmental Assets replacement of plant and machinery 666,997 507,901 719,981 52,620 772,601 (105,604)
Cemeteries/Tree Infrastructure 4,319,311 136,770 450,005 1,158,026 1,608,030 2,711,281
Road Asset Management including street lighting, road
improvements and gateway signage 14,590,454 6,267,830 10,901,604 1,716,322 12,617,926 1,972,528
Bin rationalisation project and replacement 137,742 36,374 137,742 0 137,742 0
Play Area Equipment and surface renewal 213,145 112,247 213,145 0 213,145 0
TOTAL ENVIRONMENTAL ASSETS 34,805,362 12,958,771 22,000,042 5,609,467 27,609,510 7,195,852
REGULATORY SERVICES & WASTE SOLUTIONS
Contaminated Land and Pollution Control 368,376 349,212 349,212 19,164 368,376 0
Vehicle Replacement Programme 1,448,444 49,040 49,040 0 49,040 1,399,404
Depot Rationalisation and Investment 3,509,776 731,095 1,691,465 0 1,691,465 1,818,311
HWRC Equipment 464,700 186,387 186,387 278,313 464,700 0
TOTAL REGULATORY SERVICES & WASTE SOLUTIONS 5,791,296 1,315,733 2,276,104 297,477 2,573,581 3,217,715
PLANNING & REGENERATION
Economic Regeneration 18,450,305 2,951,546 5,194,035 11,571,387 16,765,422 1,684,882
City Deal 18,453,423 9,971,646 16,657,815 803,622 17,461,437 991,986
Enterprise Projects 2,785,022 1,178,124 1,235,991 1,244,814 2,480,805 304,217
Antonine Wall Project 215,013 180,096 184,910 30,103 215,013 0
TOTAL PLANNING & REGENERATION 39,903,763 14,281,412 23,272,751 13,649,926 36,922,676 2,981,085
HOUSING PROPERTY & PROJECTS
Water Quailty / Ventilation 561,862 554,792 554,792 7,070 561,862 0
TOTAL HOUSING PROPERTY & PROJECTS 561,862 554,792 554,792 7,070 561,862 0
TOTAL ENTERPRISE & COMMUNITIES 159,192,373 72,409,655 113,552,201 22,587,106 136,139,306 23,053,066
YTD OUTTURN

Page 8

APPENDIX B
Enterprise & Communities Capital Programme 2022-23 - Committee Budget Virement Requests
1st April 2022 - 6th January 2023 (PERIOD 10)
Virement request
Virement
amount
£
Thematic category From Thematic category To Committee
approval required
Acceleration
Office Rationalisation 454,660 Office Rationalisation Year 3 Office Rationalisation Year 2 No
Maintaining Existing Assets - windows, re-roofing, re-
wiring and condition survey works for the Council's
building assets 167,085 Maintaining Existing Assets - windows, re-roofing, re-wiring and condition survey works for the Council's building assetsYear 3 Maintaining Existing Assets - windows, re-roofing, re-wiring and condition survey works for the Council's building assetsYear 2 No
Leisure Development 99,211 Leisure Development Year 3 Leisure Development Year 2
Environmental Assets replacement of plant and
machinery 105,604 Environmental Assets replacement of plant and machineryYear 3 Environmental Assets replacement of plant and machineryYear 2 No
Sub Total Acceleration 826,560
Transfers to future years
Town and Community Hubs 2,286,347 Town and Community Hubs Year 2 Town and Community Hubs Year 3 No
Rationalisation including ASN & Social Work 2,009,116 Rationalisation including ASN & Social Work Year 2 Rationalisation including ASN & Social Work Year 3 No
Carbon Management 1,610,207 Carbon Management Year 2 Carbon Management Year 3 No
Sustainable Estate 275,666 Sustainable Estate Year 2 Sustainable Estate Year 3 No
1140 Early Learning and Childcare Expansion 221,067 1140 Early Learning and Childcare Expansion Year 2 1140 Early Learning and Childcare Expansion Year 3 No
Future Capital Receipts Investments 211,357 Future Capital Receipts Investments Year 2 Future Capital Receipts Investments Year 3 No
Outdoor Education and Outdoor Spaces 3,200,000
Cemeteries/Tree Infrastructure 2,711,281 Cemeteries/Tree Infrastructure Year 2 Cemeteries/Tree Infrastructure Year 3 No
Infrastructure and Transportation Improvements 2,125,366 Infrastructure and Transportation Improvements Year 2 Infrastructure and Transportation Improvements Year 3 No
Road Asset Management including street lighting, road
improvements and gateway signage 1,822,527 Road Asset Management including street lighting, road improvements and gateway signageYear 2
Road Asset Management including street lighting,
road improvements and gateway signage Year 3 No
Depot Rationalisation and Investment 1,818,311 Depot Rationalisation and Investment Year 2 Depot Rationalisation and Investment Year 3 No
Vehicle Replacement Programme 1,399,404 Vehicle Replacement Programme Year 2 Vehicle Replacement Programme Year 3 Yes
Economic Regeneration 1,684,882 Economic Regeneration Year 2 Economic Regeneration Year 3 No
City Deal 991,986 City Deal Year 2 City Deal Year 5 No
Enterprise Projects 304,217 Enterprise Projects Year 2 Enterprise Projects Year 5 No
Sub Total Transfer to future years 22,671,734
Internal Virement
Demolitions 500,000 Demolitions Year 2 Outdoor Education and Outdoor Spaces Year 3 No
27,552,223
Budget Reductions
Design Fees 56,000
Infrastructure and Transportation Improvements 380,660
Greenspace infrastructure Health & Wellbeing 112,000
Road Asset Management including street lighting, road
improvements and gateway signage 150,000
Sub Totals Budget Reductions 698,660
Total Enterprise & Communities (50,096,057)