ARGYLL AND BUTE COUNCIL  PLANNING, PROTECTIVE SERVICES AND
LICENSING COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH   24th January 2024 
OBAN AND HELENSBURGH STRATEGIC DEVELOPMENT FRAMEWORKS 
1.0 EXECUTIVE SUMMARY 
1.1 The Argyll and Bute Outcome Improvement Plan and LDP2 aim to reverse population
decline and promote economically driven growth across Argyll and Bute.
Notwithstanding many strengths and opportunities throughout Argyll and Bute, the
only two areas that can potentially deliver and sustain growth of any significant size,
particularly in terms of population are Oban and its hinterland, and Helensburgh &
Lomond. 
1.2 Oban is a Main Town within the Tobermory to Dalmally Growth Corridor having a
range of facilities, services and shops that support a strong hinterland including a
number of Key Rural Settlements. However, it is becoming increasingly physically
constrained and nearing its topographical capacity for growth
1.3 Helensburgh and Lomond enjoys proximity and connectivity with the central belt
and the development of HMNB Clyde is increasing the naval staff by 1700 and their
families, and brings further associated civilian population.  However growth of the
area is restricted by the Green Belt designation which was designed to contain the
settlements.
1.4 To achieve strategic growth within both these areas; LDP2 identifies commitments to
produce Strategic Development Frameworks which will plan for future development
over a 20-40 year time period.  Production of these is a complex task, but is essential
to delivering planned infrastructure investment, land release, and the resultant
growth.  It will also be a key part of addressing the housing emergency.
1.5 The report outlines the preliminary progress to date in developing the Frameworks,
and that a resource request is being made to Policy and Resource Committee to
drive forward these tasks.  Officers will report future progress regularly to PPSL, and
will engage with all Members at appropriate stages of the process. 
1.6 RECOMMENDATIONS 
It is recommended that PPSL
1: note the contents of the paper,

Page 2

2: endorse the resource requests to be made to Policy and Resources Committee to
assist in driving forward the Strategic Development Frameworks.

Page 3

ARGYLL AND BUTE COUNCIL  PLANNING, PROTECTIVE SERVICES AND
LICENSING COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH   24th January 2024 
OBAN AND HELENSBURGH STRATEGIC DEVELOPMENT FRAMEWORKS 
2.0 INTRODUCTION 
2.1 Two areas within Argyll and Bute that can potentially deliver and sustain growth of
any significant size, particularly in terms of population are Oban and its hinterland,
and Helensburgh & Lomond.  LDP2 identifies commitments to produce Strategic
Development Frameworks for both these areas.  This paper updates the committee
on progress to achieving this. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that PPSL
1: note the contents of the paper,
2: endorse the resource requests to be made to Policy and Resources Committee to
assist in driving forward the Strategic Development Frameworks.
4.0 DETAIL 
4.1 The overall objective of the Argyll and Bute Outcome Improvement Plan is that Argyll and
Bute’s economic success is built on a growing population.  LDP2 sets out a spatial strategy
which supports this objective and seeks to reverse population decline and promote
economically driven growth across Argyll and Bute. 
4.2 Notwithstanding many strengths and opportunities throughout Argyll and Bute, the
only two areas that can potentially deliver and sustain growth of any significant size,
particularly in terms of population are Oban and its hinterland, and Helensburgh &
Lomond. 
Oban
4.3 Local Development Plan 2 identifies the position of Oban as a Main Town within the
Tobermory to Dalmally Growth Corridor highlighting its range of facilities, services
and shops that support a strong hinterland including a number of Key Rural
Settlements. However, it also sets out that the town is becoming increasingly
physically constrained and nearing its topographical capacity for growth. LDP2

Page 4

identifies that growth could potentially be achieved through rationalisation and
restructuring within the town as well as within the wider Growth Corridor through
significant investment in road infrastructure and a partnership approach across a
range of stakeholders.
4.4 National Planning Framework 4 (NPF4) recognises the role of the Growth Corridor in
identifying areas for future growth and identifies the role Oban plays in providing
lifeline links to the islands as well as services to its wider hinterlands. It recognises its
position as a developing university town with the European Marine Science Park
providing local economic and educational opportunities. Also recognised are
opportunities for new infrastructure and repurposing of land to help shift industrial
activity towards supporting the off shore renewable sector as well as the
connectivity role played by the airport and opportunities there for investment in
compliance operations and future drone technology. 
Helensburgh
4.5 Local Development Plan 2 identifies Helensburgh and Lomond as a growth area in
the spatial strategy. It identifies the development of HMNB Clyde as the UK’s single
submarine base and resultant increase in around 1700 naval staff and their families
as well as the associated opportunities in civilian construction projects and supply
chain, servicing and support businesses. LDP2 also identifies the proximity and
connectivity of the area to Glasgow and the central belt coupled with its high quality
environment as an attractive location for commuters and growth in tourism.
4.6 However, it also recognises that opportunities for sustainable growth are potentially
limited by the green belt which was established to contain the expansion of
settlements and retain their landscape setting and that it is anticipated that the
green belt will come under pressure in the future as the population and employment
opportunities increase.
4.7 LDP2 sets out that whilst an immediate review of the green belt is not required, due
to there being sufficient development identified within the plan, there is a need to
consider how Helensburgh and Lomond can develop over a 20-40 year period in
order to plan for investment and infrastructure considered alongside the need to
review the green belt. 
Strategic Development Frameworks
4.8 To achieve strategic growth within both these areas; LDP2 identifies commitments to
produce strategic development frameworks for each as below:
LDP2 Proposal A – Oban Strategic Development Framework (OSDF)
“The Council will take forward a Strategic Development Framework for the wider
Oban area working with stakeholders including communities, key agencies,
infrastructure providers, landowners, the Scottish Government, housing associations

Page 5

and the private sector to deliver a co-ordinated approach to: the rationalisation of
existing land uses, improved traffic management and parking (including potential for
park and ride), identification of new development opportunities for housing and
economic uses, development of the Strategic Transport Hub, investigation of
development potential and improvements to network resilience associated with the
strategic road and rail network, including the possibility of the Oban Development
Road and the consented Dunbeg Half-Way Roundabout, in order to realise the full
potential of this strategically important area.” 
LDP2 Proposal B – Helensburgh Strategic Development Framework (HSDF)
“Argyll and Bute Council propose to carry out a review of the Helensburgh and
Lomond Green Belt boundaries through a Strategic Development Framework, to
provide a framework for the provision of infrastructure and future development,
whilst recognising and safeguarding the key environmental features of the Green
Belt, the landscape setting of settlements forming part of the Cardross – Helensburgh
– Garelochhead corridor, and the contribution which the green network around these
communities can make to providing for sustainable development.”
4.9 This ‘Strategic Development Framework’ approach is recognised as an appropriate
way to promote long term growth by the LDP2 Scottish Government Reporters and
NPF4 now also reflects this approach supporting planned population growth in a
growth corridor from Tobermory to Oban and on to Dalmally and a general
infrastructure first approach. 
4.10 The two Strategic Development Frameworks will be crucial bedrocks for LDP3 and
will be required to feed in to the Evidence Report which will be part on the new style
process for LDP production. 
4.11 Although long term, both frameworks are key to addressing the housing emergency,
as they are the only things that can lead to planned housing development at scale. 
Both areas are the places of greatest housing demand, and there are likely to be
pressures on the supply of housing land within the medium term. 
4.12 Draft and preliminary scoping work has already started and is ongoing. Initial analysis
of housing needs and demand assessment has been carried out to generate different
growth scenarios for the period of consideration.  A desk top land scoping exercise
has been carried out to identify theoretical growth areas which will require
assessment.  An initial identification of known constraints and characteristics has
been initiated.   This work is in draft and high level to date.

Page 6

OSDF Stage 1
Identification of broad areas of land 
Presentation of initial opportunities and constraints 
Engagement Stage 1
Key Agencies, infrastructure providers, Council officers, local Councillors, landowners, community
groups. 
OSDF Stage 2 
Identification and publication of preferred options for locations for long term strategic growth. 
Engagement Stage 2 
Public engagement - preferred options 
OSDF Stage 3
Consideration of all Stage 1 & 2 engagement responses.
Selection and publication of identified option(s) as final OSDF
Identification of related wider actions and opportunities.
Publication of Action Programme.

Page 7

4.13 Production of the Strategic Development Frameworks is a complex tax, and will
predominantly need to adhere to a land use planning structure, as indicated in the
table above, supported by necessary transport and landscape assessment, with an
iterative process of site identification, consultation, refinement of proposals and
solutions, and further identification. Ultimately a settled proposal will need further
consultation, support of the Council, and assessment by Scottish Government,
before it can be incorporated into the next LDP3. In addition delivery will need to be
considered and the OSDF & HSDF should be accompanied by an action programme
for delivery which might include: land acquisition, further ground investigation,
funding identification, more detailed masterplanning, etc... 
4.14 In terms of timescale, there is an immediate priority to develop this work even
though the outcomes identified will be delivered in the medium term. Ultimately, for
the OSDF & HSDF to have maximum influence and leverage on investment, it will be
necessary for it to be incorporated into the next LDP which will be LDP3. The aim
would be to adopt LDP3 within five years. Adequate resourcing of the OSDF & HSDF
will be of significant importance to delivering within this timescale. Subject to more
detailed project scoping and planning, it is estimated that if fully funded with
consultancy support it would be possible to produce the OSDF & HSDF in a 2-3 year
time frame.  A separate report is being presented to Policy and Resources
Committee to request funding from the Council’s Priorities Budget.  Officers will
report progress regularly to PPSL, and will engage with all Members at appropriate
stages of the process. 
OTHER AREAS
4.15 It is important to note that whilst this report focuses on Oban and Helensburgh,
LDP2 provides a comprehensive growth and development strategy for the whole of
Argyll and Bute, focusing growth where possible on the Main Towns of
Campbeltown, Dunoon, Helensburgh, Lochgilphead, Oban and Rothesay.  The plan
also seeks to deliver a more flexible approach to development within the
Countryside where appropriate.  Additional but smaller Strategic Development
Frameworks are identified for Bowmore and Tobermory.  Strategic Masterplan Areas
are identified in Inveraray, Lochgilphead, Tobermory and Port Ellen.  Areas for Action
promoting regeneration include Rothesay, Dunoon, Port Bannatyne and Tarbert. 
5.0 CONCLUSION
5.1 LDP2 identifies Oban and Helensburgh as the centre of two areas with greatest potential
to deliver growth at a strategic scale which will help to reverse population decline.  To
deliver this LDP2 identifies the need to produce Strategic Development Frameworks for
both areas.  Theses Frameworks will underpin the identification and release of land and
infrastructure, and will form the bedrock of LDP3.  Moreover they will be key elements
to addressing the recently identified Housing emergency in the medium term. 
Production of these Frameworks is a priority for the Council, and funding to resource this
is being requested at the Policy and resources Committee.

Page 8

6.0 IMPLICATIONS
6.1 Policy – None as a result of this paper 
6.2 Financial – A linked paper making a request for resourcing is being taken to P&R
Committee requesting funds from the Council’s Priorities Fund. 
6.3  Legal – None as a result of this paper. 
6.4  HR - None
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics - None 
6.5.2   Socio-economic Duty - None 
6.5.3  Islands - None
6.6 Climate Change – None  
6.7 Risk – None at this moment 
6.8  Customer Service - None 
Kirsty Flanagan,
Executive Director with responsibility for Development and Economic Growth
Policy Lead Cllr Green
24th January 2024                                                 
For further information contact: 
Matt Mulderrig matt.mulderrig@argyll-bute.gov.uk