North Lanarkshire Council
Report
Finance and Resources Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref    JMcG/JMcK Date 13/09/23 
Contracts with Variations 
From  James McKinstry, Chief Officer (Assets and Procurement)  
E-mail MckinstryJ@northlan.gov.uk  Telephone 07939 281102 
Executive Summary
In accordance with the Council’s Financial Regulations, this report notifies the Committee
of contracts completed between 1st January 2023 and 30th June 2023, where the
expenditure levels have exceeded the contract award levels by greater than 5% or
£25,000.
Recommendations
It is recommended that the Finance and Resources Committee: 
(1) Acknowledge the content of this report and the accompanying appendix.  
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

1. Background 
1.1 The Councils General Contract Standing Orders (the ‘GCSOs’) outline financial
approval thresholds for contracts for goods, works and services. This report details
Works (construction contracts) where funding has previously been approved in line with
GCSO’s. 
1.2 The Councils Financial Regulation, (13.4) Significant Variations, details the threshold
of variances where reporting is required. 
1.3 The Chief Officer of Assets and Procurement is required to notify Committee on a
periodic basis of any such contracts containing variations as identified by the criteria in
1.1 above. 
2. Report 
2.1 The Councils Financial Regulation state, any variations where the outturn/expected
costs exceed the tendered contract price by the higher of £25,000 or 5%, or where the
outputs/outcomes achieved by the expenditure differ from those originally envisaged,
shall be reported to the relevant Spending Committee at the earliest opportunity. 
2.2 Contracts awarded by the Chief Officer (Assets and Procurement) for works undertaken
in the period 1st January 2023 and 30th June 2023 containing variations are detailed in
Appendix.1. 
2.3 Due to the nature of construction contracts a flexible approach is required to manage
contract deliverables and desired outcomes and typically this is achieved by the
inclusion of a contingency allowance to address unknown quantities or abnormalities. 
2.4 Any construction works undertaken within the Council’s portfolio may encounter issues
that can result in additional costs after work has commenced. Asbestos is problematic
and costly to address, especially within the Council’s ageing property estate. The
rerouting of service provisions is another contributing factor with other expenditure
being attributed to health and safety issues including addressing fire stopping issues.
Additional client instructions being added to contracts following award will also increase
the overall contract sum, but it should be noted that the scope of these instructions will
be within the parameters of the original tender documents and rates will be a direct
drawdown from those already provided or a benchmarking exercise is undertaken to
demonstrate value for money. 
3. Measures of success 
3.1  Contracts support the delivery of Council objectives and service priorities. 
3.2 Contracts containing variances are managed by the Council and are compliant with
Financial Regulations, GCSOs and procurement legislation. 
3.3 The Council’s Contract Register and budgetary monitoring systems are kept updated
by services and management information is comprehensive and accurate. 
3.4 Best Value is both demonstrable and achieved.   
4. Supporting documentation 
4.1 Appendix 1 – Summary of construction contracts containing variations.

Page 3

James McKinstry
Chief Officer (Assets and Procurement)

Page 4

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?

Page 5

Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
Contract management procedures may be susceptible to financial claims and legal
challenge if they are not discharged in accordance with Contract Conditions,
Financial Regulations, GCSO’s and procurement legislation. 
Accumulation of contract overspends may impact on future Capital Programmes. 
Project risks are logged on the appropriate Risk Registers and managed by the
Service.
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☐

Page 6

APPENDIX 1
Summary of construction contracts containing variations:
Project Title Estimated
Final Out-turn Tender Amount Variation Reason
St Barbara’s Primary School,
Muirhead – 4 x classroom
refurbishments.
£268,401.00  £226,211.00 
Upgrade cubicle doors and ironmongery,
additional electrical works to replace, unforeseen
perished cables, agreed additional out of hours
working to reduce disruption when upgrading
cables and rerouting new water supply to
classroom sinks, access ramp specification
changed to concrete, include electronic panic bars
to both sets of fire escape doors.
Woodlands Primary School,
Cumbernauld - Provision of a New
Multi-Use Games Area (MUGA).
£153,196.00  £136,999.00 
Additional instructed works: install Community
access gate and associated footpaths. Instructing
these works enabled the use of the adjacent
carparking facilities. 
Demolition of Old Fleet Building,
Old Edinburgh Road, Bellshill. £181,876.00 £116,013.00
Unexpected asbestos found in gable cavity wall,
diversion and reconnection of water supply to
adjacent domestic properties.