North Lanarkshire Council
Report
Finance and Resources Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  EK/NL/PF Date 24/05/23 
Revenue Budget Monitoring Report; Chief Executives & Other
Corporate Services 01.04.22 –03.03.23 (Period 12) 
From  Elaine Kemp, Chief Officer (Finance)  
E-mail kempe@northlan.gov.uk Telephone 01698 302408 
Executive Summary
This report provides a summary of the Chief Executive & Other Corporate Services
financial performance for the period 1 April 2022 to 3 March 2023 (Period 12).   The report
illustrates the provisional outturn as at 31 March 2023, with major outturn variances
highlighted and explained per the Council’s approved Financial Regulations. 
The Council approved its General Fund Revenue Budget on 17 February 2022, of which
£98.483m currently represents the Net Revenue Budget for the Chief Executive & Other
Corporate Services. The Service is currently projecting a favourable position of £4.963m
for the financial year which includes £2.171m of approved COVID funding.  This is a
£3.792m movement from the previous committee report which includes increased
underspends in employee costs and contract costs along with over-recoveries in income
relating to PPP contributions, rent allowances and rent rebates overpayments. 
Recommendations
It is recommended that the Committee: 
(1) acknowledge the financial position of the 2022/23 Chief Executive & Other
Corporate Services revenue budget. 
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

1. Background 
1.1 The Council’s approved Financial Regulations require the Chief Executive to remain
within the approved budgetary provision, and to report all significant deviations -
defined as the higher of £100,000 or 5% - within budget monitoring reports. Where
significant deviations are identified, the Chief Executive must provide explanatory
commentary, outline the action required to rectify such deviations and where relevant,
must also highlight the impact this has on other budget headings.   
2. Report 
2.1 Summary of Financial Position
2.1.1 The Council approved its General Fund Revenue Budget on 17 February 2022, of
which £93.565m (10.55%) represented the approved Revenue Budget for the Chief
Executive & Other Corporate Services.  Incorporation of the COVID Recovery budget
of £2.171m and the realignment of Communities budgets have been included.
Following a number of budget realignments throughout the year there is a revised
budget for the service of £98.483m. 
2.1.2 The overall projected outturn position of the Service is a favourable position of
£4.963m.  This is a favourable movement of £3.792m since the previous report to
Committee which includes increased underspends in employee costs and contract
costs along with over-recoveries in income relating to PPP contributions, rent
allowances and rent rebates overpayments. Appendices one to five provide further
information in respect of this position.   
2.1.3 In light of the ongoing impact of COVID-19 and other financial pressures, Services have
been requested to continue to implement mitigating actions to ensure the position is
managed and the Council remains financially sustainable.  The mitigating action
includes vacancy management and the curtailment of non-essential expenditure.     
2.1.4 The 2022/23 budget incorporates a revised savings value of £0.361m previously
approved by Council. 
2.1.5 The Service is currently anticipating increased costs as a result of inflationary pressures
within ICT contracts of £0.088m in the current year, however these costs can be
managed within the current budget envelope.  Future year increases will be addressed
as part of the Budget Setting process. 
2.2 Analysis of Significant Variances
2.2.1 Employee costs are anticipated to result in a year end net underspend of £1.383m,
primarily as a result of vacancies, underspends in relation to the Cost of Living Grant
and pensions charges. 
2.2.2 Supplies & Services are projected to be underspent by £2.117m due to continuing
review of contracts across the service along with an in year saving due to the timing of
the transition to Cloud based solutions across the council.   
2.2.3 Transport costs are anticipated to be underspent by £0.080m primarily as a result of
decreased staff travel following the change to Hybrid working. 
2.2.4 Admin Costs are projected to be underspent by £0.095m due to underspends within
the MA programme / Workforce for the Future, printing, photocopying, training and

Page 3

project budgets partially offset by an overspend within Liability Insurance and expected
credit losses. 
2.2.5 The service is currently projecting an underspend within Payments to Other Bodies of
£0.132m due to decreased spend for by-elections, the Grant Award Programme and
Children’s Panel Training offset by HRMC tax invoice relating to medical fees. 
2.2.6 As at period 12 the position on Council Tax Reduction Scheme remains under review
along with other elements of the Council Tax Product including household numbers and
council tax collection for the year.  The Council Tax Product will then be assessed for
expected credit losses as part of the year end process. It is currently anticipated there
will be no material variance overall. 
2.2.7 Within Other Expenditure the service is currently projecting an overspend of £0.118m
due to increased costs for the Modern Apprenticeship Levy. 
2.2.8  Income is currently projecting to over-recover by £1.334m.  This is due to an over-
recovery of income in relation to PPP Contributions, rent allowances / rent rebates
overpayments, recharges from building cleaning and trade waste, grant income relating
to the modern apprentice programme and blue badges.  This is partially offset by under-
recoveries within licencing (liquor and taxi) due to the continuing impact of Covid-19
and under-recoveries in recharges for areas such as printing and insurance and the
Learning Centre.   
2.3 Earmarked and One-Off Resources
2.3.1 In finalising the Council’s draft accounts to 31 March 2022, the service was given
approval to earmark £5.519m of resources to fund key projects and initiatives profiled
over a number of years. Following several realignments during the year, along with
identifying £1.870m to be deferred to future years there is a revised balance of £3.403m
within the Chief Executive’s service. It is anticipated that £2.635m of the reserve
balances will be utilised in 2022/23 with a total £0.768m of reserves identified as no
longer required.   
2.3.2  Details of the Service’s earmarked funds are provided in Appendix 4. 
2.3.3 The Service has incurred £0.107m of VRS costs relating to savings/restructures. 
Therefore, there is currently a requirement to utilise the Corporate Change
Management fund at this time.  Costs arising from 2022/23 savings/restructures will be
reported in future reports as they are incurred. 
2.3.4 These costs are not included in the Service outturn position. 
2.4 2022/23 Budget Savings
2.4.1 The 2022/23 budget incorporates £0.361m of savings approved by Council on 17
February 2022. 
2.4.2 The Service has not fully implemented the approved 2022/23 savings however there
has been management action taken to offset these in the current year:
• Business and Digital – there has been a planned reduction of spend within Contract
lines to support savings target of £0.198m,
• POD – there has been a proactive approach to vacancy management to support
the savings target of £0.163m in the current financial year. 
2.4.3 Appendix 5 provides a summary of the savings, including commentary in relation to
challenging savings and any actions taken to address the funding gap which has arisen.

Page 4

2.5 Covid-19 Costs
2.5.1 The approved COVID Recovery Budget has been incorporated with an additional net
expenditure budget of £3.088m provided.  This reflects anticipated increased costs of
£2.289m, and additional investment of £0.799m.  The Service is currently projecting
slippage of £0.847m to 2023/24 due to delays in recruitment of staff and has identified
£0.019m of funding no longer required.  Details of the Service’s COVID Budget are
provided in Appendix 6. 
2.6 Management Actions
2.6.1 The Service is being pro-active to ensure expenditure is contained within its approved
2022/23 budget. 
3. Measures of success 
3.1  The Service continues to operate within approved budget resources.   
4. Supporting documentation 
Appendix 1 Objective Summary 
Appendix 2 Subjective Summary 
Appendix 3 Payments to Other Bodies 
Appendix 4 Earmarked Reserves 
Appendix 5 Budget Savings 
Appendix 6 COVID Recovery Budget 
Elaine Kemp
Chief Officer (Finance)

Page 5

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The Service is being pro-active to ensure expenditure is contained within its
approved 2022/23 budget. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐

Page 6

5.6  Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
All activities undertaken by the Council are subject to risk, and in acknowledging the
Council’s approved Risk Management Strategy, Services manage these as part of
their overall corporate and service planning processes. The current economic
climate, in particular, has the potential to impact upon the Council’s ability to provide
quality services within approved budget levels. 
Reflecting the risk analysis matrix included within the Risk Management Strategy,
the Service considers delays or amendments to savings proposals could present an
ongoing risk to the financial outturn for 2022/23. 
To minimise risk this report has been prepared by service based Financial
Solutions personnel in consultation with budget managers, in accordance with the
Financial Regulations.
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 7

APPENDIX 1
[1] [2] [3] [5] [6] [8] [9] [10]
DIRECTORATE & SUPPORT 763,688 745,422 18,266 FAV 874,841 846,630 28,211 FAV 3.2% 6,174
FINANCIAL SOLUTIONS 20,545,213 19,998,965 546,248 FAV 46,397,878 45,545,357 852,521 FAV 1.8% 837,181
Underspends in employee costs (cost of living  and
vacancies) and agency fees plus over-recovery of rent
allowances / rent rebates overpayments, blue badge
income are offset by overspends within property and
liability insurance claims and expected credit losses.
AUDIT & RISK 512,789 489,153 23,636 FAV 579,364 546,727 32,637 FAV 5.6% (1,442) Vacancies partially offset by turnover.
LEGAL & DEMOCRATIC SOLUTIONS 2,230,979 2,431,918 (200,939) ADV 2,155,474 2,426,881 (271,407) ADV (12.6%) (32,196)
Under recovery in postage and printing income, legal
insurance fee and registrars partially offset by
underspend within printing and postage expenditure.
BUSINESS & DIGITAL 15,535,999 13,831,503 1,704,496 FAV 17,404,666 15,537,150 1,867,516 FAV 10.7% 1,260,025
Underspends within various contracts across the service
including the in-year underspend specific to the timing
of cloud migration.  There is also a net underspend
within employee costs due to vacancies.
PEOPLE & ORGANISATIONAL DEVELOPMENT 7,744,173 7,319,123 425,050 FAV 8,142,731 7,688,558 454,173 FAV 5.6% 208,281
Underspends due to vacancies, timing of the
implementation of the Workforce for the Future
programme plus receipt of Young Persons Guarantee
Grant income within MA programme resulting in
increased underspend within the core programme.
STRATEGIC COMMUNICATIONS 5,144,888 4,871,802 273,086 FAV 5,156,219 4,874,607 281,612 FAV 5.5% 150,442
Underspends predominately due to  vacancies,
advertising, printing, promotions, Queen's Jubilee,
Grants Award Programme partially offset  by an under-
recovery in income from the Learning Centre
OTHER CORPORATE SERVICES 2,649,861 2,266,901 382,960 FAV 3,684,556 1,966,654 1,717,902 FAV 46.6% 1,363,556
Over-recovery in income in relation to PPP
contributions, recharges from building cleaning and
trade waste plus transitional relief no longer applied to
previous CLNL properties, along with other minor
underspends across the service which are partially
offset by overspends within Elected Members
expenditure and MA levy costs.
JOINT BOARDS 12,430,489 12,430,489 0 14,086,971 14,086,971 0 0.0% 0
NET EXPENDITURE 67,558,079 64,385,276 3,172,804 FAV 98,482,700 93,519,536 4,963,165 FAV 5.0% 3,792,021
FAV = Favourable Variation, underspend etc ADV = Adverse Variation, overspend etc
[4] [7]
PROJECTED OUT-TURN
VARIANCE
PROJECTED
OUT-TURN % PERIOD
MOVEMENT ANALYSIS
NORTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report - Objective Analysis
Period 12 (01 April 2022 - 03 March 2023)
A - Chief Executive's
DIVISION OF SERVICE BUDGET TO
DATE
ACTUAL TO
DATE
YEAR TO DATE
VARIANCE
ANNUAL
BUDGET

Page 8

APPENDIX 2
[1] [2] [3] [5] [6] [8] [9] [10]
EMPLOYEE COSTS 34,780,269 33,496,165 1,284,104 FAV 38,730,869 37,346,880 1,383,989 FAV 3.6% 981,174 Underspend due to vacancies and cost of living grant
across all services.
PROPERTY COSTS 1,873,294 1,916,714 (43,420) ADV 2,267,111 2,334,206 (67,096) ADV (3.0%) (3,531)
SUPPLIES & SERVICES 11,017,842 9,073,657 1,944,185 FAV 10,405,943 8,289,213 2,116,729 FAV 20.3% 868,746
Underspend primarily within Business and Digital  due
to in year savings on contracts, mainly those relating to
the cloud based solutions.
TRANSPORT & PLANT 136,531 65,142 71,389 FAV 164,630 84,421 80,209 FAV 48.7% 37,893 Decreased staff travel across all areas and spend within
school holiday club transport.
ADMINISTRATION COSTS 4,784,114 4,649,286 134,828 FAV 6,060,838 5,965,991 94,847 FAV 1.6% 51,123
Underspends within MA Programme, printing,
photocopying, postages, training and project budgets
partially offset by overspends within Liability Insurance
and Expected Credit Losses.
PAYMENTS TO OTHER BODIES 17,810,449 17,680,978 129,471 FAV 19,349,545 19,217,189 132,355 FAV 0.7% 38,731 Decreased spend relating to by-elections, Grant Award
Programme, Children's Panel (Training and
TRANSFER PAYMENTS 71,748,569 71,748,569 0 111,662,988 111,654,288 8,700 FAV 0.0% 0
CAPITAL FINANCING COSTS 400,000 403,353 (3,353) ADV 4,072,342 4,075,695 (3,353) ADV (0.1%) (3,353)
REVENUE FINANCING COSTS 0 0 0 0 0 0 0.0% 0
OTHER EXPENDITURE 3,036,743 3,152,484 (115,741) ADV 4,764,583 4,882,155 (117,572) ADV (2.5%) (34,762)
Projected overspend in relation to MA Levy partially
offset by historic underspends within miscellaneous
costs.
TOTAL EXPENDITURE 145,587,811 142,186,347 3,401,464 FAV 197,478,849 193,850,040 3,628,810 FAV 1.8% 1,936,021
INCOME (78,029,732) (77,801,072) (228,660) ADV (98,996,150) (100,330,503) 1,334,353 FAV (1.4%) 1,855,998
Over-recovery in relation to PPP Contributions, rent
allowances / rent rebates overpayments, recharges
from building cleaning and trade waste, receipt of
Young Persons Guarantee Grant (MA programme) plus
other minor over-recoveries partially offset by under
recovery in L&D postage and printing income, legal
insurance fee and registrars, Learning Centre income.
NET EXPENDITURE 67,558,079 64,385,276 3,172,804 FAV 98,482,699 93,519,537 4,963,163 FAV 5.0% 3,792,019
FAV = Favourable Variation, underspend etc
ADV = Adverse Variation, overspend etc
[4] [7]
PROJECTED OUT-TURN
VARIANCE
PROJECTED
OUT-TURN % PERIOD
MOVEMENT ANALYSIS
NORTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report - Subjective Analysis
Period 12 (01 April 2022 - 03 March 2023)
A - Chief Executive's
CATEGORY BUDGET TO
DATE
ACTUAL TO
DATE
YEAR TO DATE
VARIANCE
ANNUAL
BUDGET

Page 9

APPENDIX 3
[1] [2] [3] [5] [6] [8] [9] [10]
PAYMENTS TO OTHER BODIES GENERAL 464,452 412,897 51,555 FAV 581,180 515,180 66,000 FAV 11.4% (15,000) Underspend in relation to by-election costs
MEDICAL FEES 8,640 39,114 (30,474) ADV 9,359 57,582 (48,223) ADV (515.3%) (48,223) Higher than anticipated medical fees / HMRC invoice
AGENCY FEES 64,177 24,446 39,731 FAV 81,542 41,542 40,000 FAV 49.1% 40,000 Underspend based on historic spend patterns
TOWN TWINNING 2,350 1,683 667 FAV 3,533 2,790 743 FAV 21.0% 743
CHILDRENS PANEL 21,512 10,754 10,758 FAV 25,035 12,984 12,051 FAV 48.1% 12,051 Decreased uptake in Training and Safeguarding costs
COSLA ANNUAL LEVY 195,000 192,376 2,624 FAV 195,000 192,376 2,624 FAV 1.4% 0
COMMUNITY COUNCIL GRANTS 82,319 77,704 4,616 FAV 158,629 153,629 5,000 FAV 3.2% (5,000)
GRANTS TO ORGANISATIONS 1,046,620 996,626 49,994 FAV 1,207,773 1,153,613 54,160 FAV 4.5% 54,160
EXTERNAL AUDIT FEE (2,000) 86 (2,086) ADV 529,389 540,526 (11,137) ADV (2.1%) 0
ELECTION PROVISION 0 0 0 0 0 0 0.0% 0
TOURISM - VISIT NORTH LANARKSHIRE 36,458 36,458 0 72,145 72,145 0 0.0% 0
SCOTTISH WELFARE FUND 4,006,923 4,006,922 0 4,596,509 4,596,509 0 0.0% 0
SUB-CONTRACTOR PAYMENTS 0 0 0 1,869 1,869 0 0.0% 0
LOCAL TAX PAYPOINT COMMISSION 18,509 18,509 0 35,000 35,000 0 0.0% 0
COSLA MIGRATION SCOTLAND 150,000 150,000 0 150,000 150,000 0 0.0% 0
LANDS VALUATION CONTRIBUTION 1,927,670 1,927,670 0 2,105,910 2,105,910 0 0.0% 0
SPT CONTRIBUTION 5,424,912 5,424,912 0 5,453,118 5,453,118 0 0.0% 0
SPT CONCESSIONARY FARES CONTRIBUTION 571,907 571,907 0 572,943 572,943 0 0.0% 0
CUSTOMER FIRST CONTRIBUTION 3,789,000 3,789,000 0 4,100,000 4,100,000 0 0.0% 0
TOTAL EXPENDITURE 17,808,449 17,681,065 127,385 FAV 19,878,934 19,757,715 121,218 FAV 0.6% 38,731
FAV = Favourable Variation, underspend etc
ADV = Adverse Variation, overspend etc
[4] [7]
PROJECTED OUT-TURN
VARIANCE
PROJECTED
OUT-TURN % PERIOD
MOVEMENT ANALYSIS
NORTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report - Payments to Other Bodies
Period 12 (01 April 2022 - 03 March 2023)
A - Chief Executive's
CATEGORY BUDGET TO
DATE
ACTUAL TO
DATE
YEAR TO DATE
VARIANCE
ANNUAL
BUDGET

Page 10

APPENDIX 4
Value %
Service Specific Earmarked Reserves:
PWC VAT FS 27 0 27 27 27 100.0% 0 27
Support Plan for North Lanarkshire L&D 100 (100) 0 0 0 0.0% 0 0
Digital Savings L&D 45 0 45 45 45 100.0% 0 45
Digitisation Reserve B&D 2,499 (777) 1,722 845 965 56.0% 757 965 £777k has been identified as being needed within
2023/24 and £757k is no longer required.
Digital Savings B&D 1,000 (1,000) 0 0 0 0.0% 0 0
Family Firm POD 173 (173) 0 0 0 0.0% 0 0
Creation of Learning Academy POD 100 (100) 0 0 0 0.0% 0 0
Creation of Construction Academy POD 300 (300) 0 0 0 0.0% 0 0
ESC Resources Reserve POD 154 (61) 93 81 93 100.0% 0 93
Digital NL Post POD 36 0 36 33 36 100.0% 0 36
Customer Services Hub SC 212 (82) 130 124 130 100.0% 0 130
Customer Services Hub SC 50 (50) 0 0 0 0.0% 0 0
Cumbernauld Theatre SC 35 0 35 0 35 100.0% 0 35
VANL (New) SC 60 0 60 49 49 81.7% 11 49 £11k is no longer required.
LDP Prog Play Areas and additional projects SC 500 0 500 500 500 100.0% 0 500
Recover NL - grant award prog SC 172 (172) 0 0 0 100.0% 0 0
Cost of Living EMR SC 0 430 430 385 430 100.0% 0 430
Cost of Living EMR (comms) SC 0 15 15 4 15 100.0% 0 15
Ukraine Humanitarian Appeal MM 15 0 15 15 15 100.0% 0 15
Pakistan Flood Appeal MM 15 0 15 15 15 100.0% 0 15
Change Management / Non-Service Specific:
CLNL Insourcing POD / B&D 168 62 230 201 230 100.0% 0 230
CLNL ICT Development B&D 135 (84) 50 0 50 100.0% 0 50
TOTAL 5,796 (2,393) 3,403 2,324 2,635 77.4% 768 2,635
DESCRIPTION OF EARMARKED RESOURCE DIVISION Reserve
Allocation
Adjustments
In Year
Approved
Reserve Total
Spend to
Date
Projected Spend Reserves No
Longer
Required
Reserves
Required In
Year
Commentary Regards Usage
NORTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report - Status of Earmarked Reserves
A - Chief Executive's
FINANCIAL YEAR - 2022/23
Period 12 (01 April 2022 - 03 March 2023)

Page 11

APPENDIX 5
£000 £000 £000 £000 £000
Digital NL B&D 198 0 198 Management action taken within contract
lines in current year
198 0
Reduction of ESC Admin posts POD 163 0 163 Management action taken 163 0
TOTAL 361 0 361 361 0
NORTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report - Savings
Period 12 (01 April 2022 - 03 March 2023)
A - Chief Executive's
APPROVED SAVINGS REPLACEMENT SAVING / FUNDING
DESCRIPTION Value BUDGET
GAP CommentaryDESCRIPTION OF APPROVED SAVING DIVISION Target Value Value
Deliverable Saving Gap

Page 12

APPENDIX 6
£000 £000 £000 £000
Costs:
Increased Costs 2,289 2,047 242 12 £0.019m no longer required therefore the balance of
£0.233m to be carried over to 2023/24
Reduced Costs 0 0 0 0
Lost Income 0 0 0 0
Income Over-Recovery 0 0 0 0
Delay in Achievement of Savings 0 0 0 0
Unavoidable Investment Commitments 0 0 0 0
Other 0 0 0 0
Investment Proposals Agreed 799 175 624 75 Customer Service Hubs - Extension of Recover NL staff
to 31/08/2023 plus additional funding approved by CMT
08/11/22 funding required in 2023/24.
Contingencies 0 0 0 0
Service Costs Total 3,088 2,222 866 87
Income:
Earmarked COVID Funding (3,088) (2,222) (866) (87)
Service Contributions 0 0 0 0
NLC Use of Reserves 0 0 0 0
21/22 COVID Funding - GRG 0 0 0 0
21/22 COVID Funding - RF 0 0 0 0
Service Income Total (3,088) (2,222) (866) (87)
TOTAL NET COSTS 0 0 0 0
CommentaryDESCRIPTION OF COVID-19 COSTS BUDGET PROJECTED
OUT-TURN
PROJECTED
OUT-TURN
VARIANCE
PERIOD
MOVEMENT
NORTH LANARKSHIRE COUNCIL
Revenue Budget Monitoring Report - Forecast COVID-19 Costs
Period 12 (01 April 2022 - 03 March 2023)
A - Chief Executive's