Democracy Spraffa

Contracts Awarded Below Committee Approval Threshold

North Lanarkshire Council · 24 May 2023
Back to Finance and Resources Committee — 24 May 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

North Lanarkshire Council
Report
Finance and Resources Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref AT/JMcK Date 24/05/23 
Contracts awarded below Committee approval threshold 
From  Chief Officer (Assets and Procurement)  
Email mckinstryj@northlan.gov.uk   Telephone James McKinstry
07939 281102 
Executive Summary 
This report notifies the Committee of the contracts awarded between 1 January 2023 to 31
March 2023. It sets out those contracts awarded with a value below the financial threshold
requiring Committee approval. 
Recommendations
The Finance and Resources Committee are: 
• advised of the Contracts awarded below Committee approval threshold between 1
January 2023 to 31 March 2023 as per the process within the Council’s General
Contract Standing Orders.   
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (18) Ensure our digital transformation is responsive to all people's
needs and enable access to the services they need

Page 2

1. Background 
1.1 The Councils General Contract Standing Orders (the ‘GCSOs’) outline financial
approval thresholds for contracts for goods, works and services. Contract awards
above £500,000 for Supplies and Services and above £2,000,000 for Works require
approval by the Committee. These contract awards are considered by the Committee
on a case-by-case basis. 
1.2 Where the value of a contract award is between £50,000 and £500,000 for Supplies
and Services and between £500,000 and £2,000,000 for Works, GCSOs require that
the Chief Officer of Assets and Procurement award these contracts on behalf of the
appropriate Chief Officer. 
1.3 The Chief Officer of Assets and Procurement is required to notify Committee on a
regular basis of any such contracts awarded on behalf of Procuring Service Areas. 
2. Report 
2.1 The GCSOs require that contracts in excess of £500,000 for supplies and services and
£2,000,000 for works are approved, on a case-by-case basis, by the Committee before
award. 
2.2 The GCSOs require that contracts with a value above £50,000 but less than £500,000
for Supplies and Services and above £500,000 but less than £2,000,000 for Works are
awarded by the Chief Officer of Assets and Procurement on behalf of the appropriate
Chief Officer. 
2.3 The contracts awarded by the Chief Officer of Assets and Procurement that are under
the £500,000 Committee financial approval threshold for Supplies and Services and
£2,000,000 for Works in the period from 1 January 2023 to 31 March 2023 are detailed
in Appendix 1. 
3. Measures of success 
3.1 Contracts support the delivery of Council and service priorities. 
3.2 Appointment of contractors who have suitable experience and capability to deliver the
required supplies, services or works. 
3.3 Contracts awarded by the Council are compliant with GCSOs and procurement
legislation. 
3.4 The Council’s Contract Register is kept updated by services and management
information is comprehensive and accurate. 
3.5 Best Value is both demonstrable and achieved.     
4. Supporting documentation 
4.1 Appendix 1 - Summary of contracts awarded.

Page 3

James McKinstry
Chief Officer (Assets and Procurement)

Page 4

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public Sector
Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments 
Yes ☐ No ☒
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Where Financial impacts have been identified, they have been established and 
addressed in each specific Contract Strategy and incorporated into the project.   
The Council’s Procurement Strategy proposes methods of maximising the delivery of 
procurement benefits that could bring improved financial return to the Council and 
the areas wider economy. Certain benefits have a monetary value attached and
these will be monitored on a project-by-project basis.
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Where HR impacts have been identified, they have been established and addressed 
in each specific Contract Strategy and incorporated into the project.   
Contracts awarded by the Council are compliant with GCSOs and procurement
legislation.
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☒ No ☐ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal and
Democratic? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Where Legal impacts have been identified, they have been established and 
addressed in each specific Contract Strategy and incorporated into the project.   
Contracts awarded by the Council are compliant with GCSOs and procurement
legislation.

Page 5

5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject? 
Yes ☐ No ☒ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-mailed
to dataprotection@northlan.gov.uk 
Yes ☐ No ☒
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
All contracts listed have been assessed by the Enterprise Architecture Governance
Group (EAGG). 
Where the impact identifies a requirement for significant technology change, has an
assessment been carried out (or is scheduled to be carried out) by the Enterprise
Architecture Governance Group (EAGG)? 
Yes ☒ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Sustainable procurement is one of the key objectives of the Council’s Procurement
Strategy and will have a positive impact, including, embedding sustainable procurement
as business as usual and incorporating community benefits into the Councils contracts.
Supporting local businesses and SMEs through closer working with colleagues in the
Council’s Enterprise department and by making our processes more streamlined and
accessible. 
Where Environmental/Carbon impacts have been identified, they have been 
established and addressed in each specific Contract Strategy and incorporated into 
the project.  
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts, highlighting
where the risk(s) are assessed and recorded (e.g. Corporate or Service or Project Risk
Registers), and how they are managed? 
Where Risk impacts have been identified, they have been established and

Page 6

addressed in each specific Contract Strategy and incorporated into the project. 
Contract award procedures may be susceptible to legal challenge if they are not
discharged in accordance with GCSO and procurement legislation.
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e. does
it relate to healthcare, housing, or education services for in-Service or ex-Service
personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to ensure
there has been appropriate consideration of the particular needs of the Armed Forces
community to make sure that they do not face disadvantage compared to other citizens in
the provision of public services.

Page 7

APPENDIX 1 – SUMMARY OF BELOW THRESHOLD CONTRACT AWARDS
Contract Description Contract
Award
Date
Contract
Start   
Date
Contract
End Date
Contract
Extension
Contract
Value (inc
extension)
(£s)
Successful
Tenderer 
Supplies
Services
Works
No of
Tenders
Received 
Route*
Modular Units – Taylor High
School 19/01/2023 03/04/2023 03/11/2023 N/A £730,860.00 Sibcas Limited Works 2 FMC3
Bottled Water Coolers &
Associated Products 14/03/2023 10/03/2023 09/03/2027 09/03/2027 £136,000.00 Waterlogic GB Ltd  Services 4 FMC3
ArcGIS Maintenance & Support
2023-24 10/03/2023 01/04/2023 31/03/2024 N/A £72,651.00 ESRI (UK) Ltd Services 1 *DAF3
Banking Services & Merchant
Acquiring Solution - Lot 1
Banking Services & Lot 2
Merchant Acquiring
10/03/2023 01/04/2023 31/03/2024 N/A £221,000 RBS Scotland,
Lloyds Cardnet Services 2 EXT
Enterprise Project Options
Revalidation 31/03/2023 21/02/2023 31/07/2023 N/A £225,391.00 Grant Thornton
UK LLP Services 1 *DAF3 
*Direct Awards to best value Providers from Crown Commercial Services (CCS) 3rd Party Frameworks 
Key – Procurement Route
CO -   Contract Open Procedure
CR -   Contract Restricted Procedure
FO -   Framework Open Procedure
FR -   Framework Restricted Procedure
FMCC - Mini Comp Council Framework

Page 8

FMC3 - Mini Comp 3rd Party Framework
DAFC - Direct Award Council Framework
DAF3 -  Direct Award 3rd Party Framework
DAH&SC - Direct Award Health & Social Care Related Services
N -   Negotiated Contract
EXT -  Extension to Contract/Framework