North Lanarkshire Properties LLP - Performance Indicators- 13 January 2022 - 27 July 2022 and Financial Performance as at 22 July 2022

North Lanarkshire Council · 30 November 2022
Back to Finance and Resources Committee — 30 November 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

North Lanarkshire Council
Report
Finance and Resources Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref NLP/IM/JMcK Date 30/11/22 
North Lanarkshire Properties LLP – Performance Indicators: 13
January 2022 – 27 July 2022 and Financial Performance as at 22
July 2022 
From  James McKinstry, Head of Asset and Procurement Solutions  
E-mail martini@northlan.gov.uk Telephone Ian Martin
Tel: 07966 397637 
Executive Summary 
This report provides details of North Lanarkshire Properties LLP’s (NLP LLP) performance
from 13 January 2022 to 27 July 2022 and provides an update on significant events and
service delivery highlights during the reporting period. 
The report also provides details of the financial performance for the period from 1 April
2022 to 22 July 2022. 
Recommendations 
It is recommended that the Finance and Resources Committee: 
1. Acknowledge NLP LLP’s operational performance against its 2021/22 targets for
the period 13 January 2022 to 27 July 2022; 
2. Acknowledge NLP LLP’s financial performance during the period from 1 April 2022
to 22 July 2022; and 
3. Acknowledge the Service delivery highlights detailed within the report;  
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (3) Maximise the use of our marketable land and assets through
improved development in business and industrial infrastructure

Page 2

1. Background 
1.1 NLP LLP is a limited liability partnership established in 2013 between the Council and
its wholly owned company, North Lanarkshire Property Investments Ltd. It undertakes
the marketing, leasing and management of the Council’s commercial property portfolio
(shop units, office accommodation, business centres, industrial yards and storage
units) and, on behalf of the Council, manages legacy properties which remain in the
Council’s investment property portfolio. It also delivers services in relation to externally
owned properties that the Council leases for its own operational use and provides
general advice on lease transactions. 
1.2 Governance, strategic direction and oversight of the limited liability partnership is
provided by the Management Committee which comprises four elected members and
one senior Council officer appointed by the Council and one member appointed by the
limited company, NL Property Investments Ltd. Members to the Board of Directors of
the limited company, NL Property Investments Ltd, are also appointed by the Council
with five elected members and one senior officer appointed. The Management
Committee meets quarterly and is responsible for ensuring NLP LLP’s services are
delivered in accordance with the approved Service Level Agreement and company
objectives. 
1.3 The Management Committee undertook a number of measures to implement
recommendations from the ALEO review completed in 2018/19, most significantly, the
establishment restructure and enhancement proposals approved in February 2019. 
1.4 The Management Committee at its meeting on 3 September 2020 approved a formal
Minute of Variation to the SLA which included details of the of the Strategic Business
Manager Support Services provided by Asset and Procurement Solutions and the
associated charge of £74,000. It was also agreed that a review of this service should
be completed by 31 March 2021. 
1.5 At its meeting on 11 February 2021 the management Committee agreed to continue
with the support services up to 31 March 2024. The service delivery model will be
reviewed annually or at the request of the Management Committee to ensure that it
continues to meet NLP’s requirements.   
2. Report 
Performance Indicators 
2.1 Following changes to the council’s Scheme of Administration, responsibility for
oversight of service delivery by arm’s length bodies now rests with the relevant service
committee. The functions delivered by NLP LLP on behalf of the council fall within the
Terms of Reference of this committee and a six monthly performance report is be
submitted in line with the Strategic Performance Framework considered by members
in November 2019. The report will confirm where NLP LLP is fulfilling its contractual
obligations and meeting the council’s service delivery expectations, as well as providing
information from Financial Solutions on financial performance and overall financial
standing within the company. This information will help give early warning of any
financial risks which may give rise to operational or reputational risks for the council. 
2.2 2022/23 Performance indicators are listed at appendix 1 along with actual performance
for the period 13 January 2022 to 27 July 2022, which fulfil the reporting requirements

Page 3

agreed between the organisation and the council and further demonstrate where NLP
LLP is contributing to the council’s strategic priorities. 
2.3 During the reporting period a total of 41 properties were let, renewed or assigned (19
Office; 3 Retail and 19 Industrial) and there were 14 lease terminations over the
corresponding period. 
2.4 The percentage of vacant properties across the NLP portfolio over the corresponding
period are shown at Section 12 in Appendix 1. The vacancy rates have decreased
slightly from 11.55% in P13 21/22 to 10.57% in P4 22/23. This demonstrates that
vacancy rates remain relatively stable coming out of the COVID-19 pandemic and in
light of the current economic challenges and the position will continue to be closely
monitored. 
Service Delivery Highlights 
2.5 NLP worked jointly with Housing Services on a project at Buchanan Street/Hallcraig
Street, Airdrie to refurbish the building including two retail units on the ground floor and
create flats on the upper floors. The project is now complete and NLP are currently
marketing the remaining retail unit for lease after successfully re-locating the existing
tenant to one of the newly refurbished units. This project was key in maintaining a
presence within the town centre for the retail units and NLP are supporting the existing
tenant within the property who has plans to expand his own business on the back of
the relocation into one of the refurbished units. 
2.6 NLP worked jointly with Housing to redevelop an existing prominent building on
Graham Street within Airdrie Town Centre with the former restaurant on the upper floors
of the building being converted to residential use by Housing and the refurbishment of
the ground floor commercial units by NLP.  The project commenced June 2020 and
was due for completion in June 2021, however the extent of repairs required to the
building exceeded the original scope of works and this necessitated a re-design of the
project, this resulted in a delay to the project which concluded in March 2022, subject
to final meter connections. As part of the redevelopment four new flats were created on
the upper floors and NLP have been able to alter one of the ground floor units to provide
additional space for an existing tenant and secure a new lease commitment as a result.
The tenant’s former premises have also now been refurbished and is currently being
marketed. 
2.7 NLP have partnered with NLP Growth Team to develop the existing Braidhurst
Industrial Site in Motherwell.  Funding in the region of £1.8m has been secured from
the Scottish Government Regeneration Capital Grant Fund (RCGF) for the construction
of around 10 incubator units to bring and support small to medium sized local
businesses. NLC and NLP will also contribute circa £980,000 and £250,000
respectively.  The project will also include the upgrading to the existing industrial units
within the site and forms part of a larger project with the formation of a transport link at
nearby Newhut Road and Bellshill Road.  The project is currently at the design stage
with works proposed to commence in early 2023. 
2.8 NLP is actively supporting the Council’s Ambition Plan for Town Centre regeneration.
This has taken the form of identifying properties which could be converted to residential
use in Motherwell and Airdrie and which can be sold to the Council to further its plans.

Page 4

Financial Impact 
2.9 Public Accountability Obligations – Financial year 2022/23 
2.9.1 To satisfy the Council’s duty to ensure the organisation delivering property
management services on its behalf is financially sound, the Council’s Section 95 Officer
maintains appropriate and proportionate processes and procedures for scrutinising
NLP LLP’s financial performance. 
2.9.2 The Council’s Legal Agreements with NLP LLP specify the financial information which
NLP must submit to the Council including an annual business plan, quarterly
management accounts, audited financial statements etc., to enable Financial Solutions
to assess and report any financial risk likely to arise as a result of the Council using
NLP LLP to deliver these services. 
2.9.3 The Council expends revenue resources annually with NLP LLP to deliver services
which assist the Council in achieving its priority outcomes. The Council has a duty to
continue to ensure this money is being properly used to deliver both the Council’s and
NLP LLP’s key objectives. 
2.9.4 For financial year 2022/23, the Council’s approved revenue spend includes property
management services (£0.198m) and rental charges for properties utilised by the
Council. 
2.10 Financial Outturn to 31 March 2022 
2.10.1 The 2021/22 Annual Financial Statements approved by the Board at the AGM on 30
September 2022 reported an Accounting Profit for the year of £2.395m which was a
favourable variance of £1.385m against a budget of £1.010m. This was a result of
increase in the annual revaluation of the property portfolio, FRS102 pension costs,
increased over-recoveries within rental and grant income coupled with underspends
within Supplies & Services and Admin costs.  However, this has been predominately
offset by increased repair charges with further details on financial performance are
given on Appendix 2. 
2.10.2  Appendix 3 provides key Balance Sheet balances at the 31 March 2022 along with the
previous year’s comparative figures and commentary. 
Indicators worthy of note include: - 
• Current asset ratio of 2.02:1 at 31 March 2022.  Values less than 1 indicate a
company may have difficulty meeting current obligations.  Therefore, Council
representatives should be assured  the company has a positive liquidity
position under a continued trading operation.
• Cash backed useable reserves are reviewed on an ongoing basis. 
2.11 Financial Performance 1 April 2022 to 22 July 2022 
2.11.1 Based on the financial performance 22 July 2022 a projected transfer out of reserves
of £0.652m is reported to 31 March 2023. This is a favourable movement of £0.036m 
against a budgeted transfer of £0.689m. A Projected Debt Service Covenant (PDSC)
of 0.68 to 1 is projected at 31 March 2023. This is in excess of the revised ratio agreed
with Barclays  of 0.5 to 1.  As detailed in section 2.13.1 discussions are underway with
Barclays to review this. Further details on financial performance are given in Appendix
4.

Page 5

2.11.2 Appendix 5 provides key Balance Sheet balances at the 22 July 2022 along with the
previous year’s comparative figures and commentary. 
Indicators worthy of note include: - 
• Current asset ratio of 2.57:1 at 22 July 2022 which indicates that the company
continues to have positive liquidity under its continued operating trading.
• As per 2.10.2 cash backed useable reserves are reviewed each period. 
2.12 Projected Cashflow to July 2023 
2.12.1 Appendix 6 provides the projected cashflow to 31 July 2023. The minimum balance of
cash projected to be held was £6.464m in July 2022. This demonstrates that NLP will
continue to hold sufficient levels of cash. 
2.13 Bank Covenant 
2.13.1  Barclays Bank consented to relax the bank covenant ratio from 1 to 1 to 0.5 to 1 until
30 September 2022.  In recognition of the current cost of living crisis NLP are
entering into discussions with Barclays Bank with a view to extend the reduction in
the covenant to the end of the loan agreement. 
2.13.2 NLC continue to monitor NLP financial performance closely with updates provided to 
the Corporate Management Team. 
3. Measures of success 
3.1 The financial position of the company is being monitored closely and the temporary
reduction in the covenant ratio to the end of the loan agreement will ensure that NLP
LLP will continue to meet its loan obligations. 
3.2 The successful completion of the joint projects at Buchanan Street/Hallcraig Street,
Airdrie and Graham Street, Airdrie provides new social housing and refurbished
commercial space for rent. 
3.2 The re-development of Braidhurst Industrial Estate will provide new and refurbished
industrial units for let, supporting new and expanding business and contributing to the
overall vision for the area.     
4. Supporting documentation 
Appendix 1
Appendix 2
Appendix 3     
Appendix 4
Appendix 5
Appendix 6
Performance Update – 13 January 2022 to 27 July 2022
Financial Outturn to 31 March 2021
Overall Financial Standing – Balance Sheet as at 31 March 2022
Financial Performance Year to Date 22nd July 2022
Overall Financial Standing – Balance Sheet as at 22nd July 2022
NLP Cash Flow Forecast to July 2023

Page 6

James McKinstry
Head of Asset and Procurement Solutions

Page 7

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
The financial performance of NLP is closely monitored by the council’s Section 95
Officer and the financial performance from 1 April 2022 to 22 July 2022 along with
other key financial information detailed within the report.  As part of the audit process,
NLC confirmed that they will provide additional financial support if required. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐

Page 8

5.6  Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☐ No ☒
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed?

Page 9

No embedded text on this page.

Page 10

No embedded text on this page.

Page 11

No embedded text on this page.

Page 12

No embedded text on this page.

Page 13

North Lanarkshire Properties LLP Appendix 2
Outturn to 31 March 2022
Income & expenditure 2022 2022 2022 Commentary
Annual
Budget
Actual 
Outturn  Variance
£m £m £m
Rental, SLA income and Insurance Income 6.215 6.349 0.134 Favourable variance due to proactive
approach in relation to rental income
Investment and other income (0.060) (0.106) (0.046) Adverse variance in relation to proceeds
received from Motherwell Town Hall.
Total Income 6.155 6.243 0.088
Expenditure;
Employee costs (0.645) (0.666) (0.021) Minor adverse variance.
Property Costs (1.926) (2.711) (0.784) Adverse variance primarily as a result of
increased repairs charges.
Supplies & Services  & Admin Costs (0.677) (0.510) 0.168 Favourable variance is largely due to
decrease in bad debt provision coupled with
minor underspends within other budget
headings.
Financing Costs (1.896) (1.905) (0.008)
Total Expenditure (5.145) (5.791) (0.646)
Trading Profit 1.010 0.452 (0.558)
Year end Accounting adjustments not
included in budget (No Covenant impact):
Grant Income 0.000 0.232 0.232 Grant Funding for construction of Orbiston
Industrial Units
FRS102 pension costs 0.000 0.567 0.567 Provided by Strathclyde Pension Office
Unrealised gain/(loss) on investment
portfolio
0.000 1.144 1.144
Accounting Profit 1.010 2.395 1.385
Loan Principal Repayments (1.258) (1.258) 0.000
Profit Transferred to/(out) Reserves (0.248) 1.137 1.385
Covenant Ratio based on Cash Flow 1.05 1.05

Page 14

North Lanarkshire Properties LLP Appendix 3
Overall Financial Standing - Balance Sheet as at 31 March 2022
Balances/ Indicator As at 31 March
2022
As At  31 March
2021
Variance Commentary
£m £m £m
Fixed Assets 68.946 68.735 0.210 Cost of Construction offset by sales
and revaluations
Current Assets:
Trade Debtors 1.113 1.120 (0.007) Decrease year on year due to timing
of payments and COVID impact
Bad Debt Provision (0.274) (0.401) 0.127 Decrease primarily relates to a
reduced provision within COVID
related debt
Prepayment and Other Debtors 0.000 1.366 (1.366) 31 March 2021 balance contains
COVID grant debtor £0.300m,
Orbiston Grant Monies due £0.786m
Bank and short term investments 9.101 7.133 1.968 Increased rental income as part of
Covid recovery plan
9.941 9.218 0.933
Current Liabilities:
Creditors (2.610) (2.276) (0.334) Increase in creditors balances at year
end
Other Creditors inc. VAT & other taxes (0.946) (1.035) 0.089 Decrease in VAT liability at year end
offset by minor movements within
Other Creditors
Loan payments due in <1 yr (1.376) (1.258) (0.118) Loan Repayment Schedule agreed
with bank
(4.932) (4.568) (0.363)
Net current Assets/(liabilities) 5.009 4.650 0.359
Loan repayments due in > 1 yr (33.686) (35.062) 1.376 Loan Repayment Schedule agreed
with bank
Defined scheme pensions liabilities 0.000 (0.449) 0.449 Per Strathclyde Pension Office
Net Asset / (Liabilities) 40.268 37.874 2.394
Current Ratio 2.02 2.02 A current ratio exceeding 1 indicates
the company has sufficient resources
to meet its current commitments.

Page 15

North Lanarkshire Properties LLP Appendix 4
Year to date 22 July 2022
Income & expenditure 2022/23 2022/23 Year to date 2022/23 2022/23
Commentary:- 2022/23 Annual Budget vrs 2022/23
Projected Outturn
Annual
Budget Budget Actual Variance
Projected 
Outturn Variance
£m £m £m £m £m £m
Rental, SLA income and Insurance Income 6.104 1.967 1.983 0.016 6.103 (0.001)
Investment and other income 0.000 0 0 0.159 0.001 0.001
Total Income 6.104 1.967 2.142 0.174 6.104 0.000
Expenditure;
Employee costs (0.662) (0.169) (0.167) 0.002 (0.626) 0.036 Favourable variance is short term vacancies
Property Costs (1.905) (0.239) (0.431) (0.192) (1.905) 0.000
Supplies & Services  & Admin Costs (0.689) (0.137) (0.121) 0.017 (0.689) 0.000
Financing Costs (1.817) (0.430) (0.421) 0.009 (1.817) 0.000
Total Expenditure (5.073) (0.975) (1.139) (0.164) (5.036) 0.036
Trading Profit 1.031 0.992 1.002 0.010 1.068 0.036
Loan Principal Repayments (1.720) (0.348) (0.348) 0.000 (1.720) 0.000
Profit Transferred to/(out) Reserves (0.689) 0.644 0.654 0.010 (0.652) 0.036
Covenant Ratio based on Cash Flow 0.68 0.68

Page 16

North Lanarkshire Properties LLP Appendix 5
Overall Financial Standing - Balance Sheet as at 22 July 2022
Balances/ Indicator As at 22 July
2022
As At  31
March 2022
Variance Commentary
£m £m £m
Fixed Assets 68.946 68.946 0.000
Current Assets:
Trade Debtors 1.020 1.113 (0.094) Timing of payments received
Bad Debt Provision (0.274) (0.274) 0.000
Prepayment and Other Debtors 0.000 0.000 0.000
Bank and short term investments 8.482 9.101 (0.618) Timing differences
9.228 9.941 (0.712)
Current Liabilities:
Creditors (1.651) (2.610) 0.959 Part year charges
Other Creditors inc. VAT & other taxes (0.539) (0.946) 0.407 Year end prepaid income adjustments now
cleared
Loan payments due in <1 yr (1.407) (1.376) (0.031) Loan Repayment Schedule agreed with bank
(3.596) (4.932) 1.335
Net current Assets/(liabilities) 5.632 5.009 0.623
Loan repayments due in > 1 yr (33.307) (33.686) 0.379 Loan Repayment Schedule agreed with bank
Defined scheme pensions liabilities 0.000 0.000 0.000
Net Asset / (Liabilities) 41.271 40.268 1.002
Current Ratio 2.57 2.02 A current ratio exceeding 1 indicates the
company has sufficient resources to meet its
current commitments.

Page 17

Appendix 6 
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
Jul-22 Aug-22 Sep-22 Oct-22 Nov-22 Dec-22 Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23
Balance -£m
NLP Cash Flow Forecast to July 2023
Operating Accts
Rental Acct
Debt Service Reserve Acct
Total Balances
Short Term Investments