North Lanarkshire Council
Report
Finance and Resources Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref JMcG/JMcK Date 30/11/22 
Contracts with Variations 
From  James McKinstry, Head of Asset and Procurement Solutions 
E-mail mckinstryj@northlan.gov.uk  Telephone   07939281102 
1. 
2. 
3. 
Executive Summary 
In accordance with the Council’s Financial Regulations, this report notifies the Committee of
contracts completed between 1st April 2022 and 21st October 2022, where the expenditure
levels have exceeded the contract award levels by greater than 5% or £25,000. 
Recommendations 
It is recommended that the Finance and Resources Committee: 
• acknowledges the content of this report and the accompanying appendix.   
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement  (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

1. Background 
1.1 The Councils General Contract Standing Orders (the ‘GCSOs’) outline financial approval
thresholds for contracts for goods, works and services. This report details Works
(construction contracts) for above £5,000 but less than £2,000,000 where funding has
previously been approved in line with GCSO’s. 
1.2 The Councils Financial Regulation, (13.4) Significant Variations, details the threshold of
variances where reporting is required. 
1.3 The Head of Asset and Procurement Solutions is required to notify Committee on a
periodic basis of any such contracts containing variations as identified by the criteria in
1.1 above. 
2. Report 
2.1 The Councils Financial Regulation state, any variations where the outturn/expected costs
exceed the tendered contract price by the higher of £25,000 or 5%, or where the
outputs/outcomes achieved by the expenditure differ from those originally envisaged, shall be
reported by the Executive Director or appropriate Officer to the relevant Spending Committee
at the earliest opportunity. 
2.2 Contracts awarded by the Head of Asset and Procurement Solutions under the £2,000,000
Committee financial approval threshold for works in the period 1st February 2021 and 31st
March 2021 containing variations are detailed in Appendix.1. 
2.3 Due to the nature of construction contracts a flexible approach is required to manage contract
deliverables and desired outcomes and typically this is achieved by the inclusion of a
contingency allowance to address unknown quantities or abnormalities.
2.4 Any construction works undertaken within the Council’s portfolio may encounter issues that
can result in additional costs after work has commenced. The global pandemic resulted in
additional costs associated with the nationwide restrictions on construction works, whilst the
war in Ukraine drove up the cost of construction materials including the price of steel and
timber; asbestos is problematic and costly to address, especially within the Council’s ageing
property estate. The rerouting of service provisions is another contributing factor with other
expenditure being attributed to health and safety issues including addressing fire stopping
issues, rot treatment, contractual claims (exacerbated by COVID19). Additional client
instructions being added to the contract following contract award will also increase the overall
contract sum, but it should be noted that the scope of these instructions will be within the
parameters of the original tender documents and; rates will be a direct drawdown from those
already provided or a benchmarking exercise is undertaken to demonstrate value for money. 
3. Measures of success 
3.1  Contracts support the delivery of Council and service priorities. 
3.2 Robust contract monitoring with detailed documentation outlining variance’s that is fully
transparent and auditable.

Page 3

3.3 Contractors supplier management processes, fully aligned with the Councils Financial
Regulation, GCSO and procurement legislation. 
3.4 Contracts containing variances are managed by the Council and are compliant with Financial
Regulations, GCSOs and procurement legislation. 
3.5 The Council’s Contract Register and budgetary monitoring systems are kept updated by
services and management information is comprehensive and accurate. 
3.6 Best Value is both demonstrable and achieved.     
4. Supporting documentation 
4.1 Appendix 1 – Summary of construction contracts containing variations.   
James McKinstry 
Head of Asset and Procurement Solutions

Page 4

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If yes, please provide a brief summary of the impact? 
All variances will be managed from the current 5 year Capital Plan. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact

Page 5

Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact
Is there a risk impact?
Yes ☐ No ☒
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed?

Page 6

Appendix 1 – Summary of construction contracts containing variations 
Project Title Final Out-
turn
Tender
Amount Variation Reason
Re-roofing - Muirhouse Primary School,
Motherwell £504,657 £478,224
Additional essential works to roof finishes were required,
including renewal of the existing fascia's and soffits and
their underlaying support timbers. 
Motherwell, Our Lady High School - PE
Changing Facilities, £504,292 £384,284
On-site investigations confirmed problems with the existing
underground drainage system, resulting in unavoidable
renewal and repair work to the affected system lines. Other
additional works included installation of additional
firestopping at wall heads and new structural bracing for
internal walls at high level. 
Motherwell, Forgewood Bin Project £173,160 £132,726 Complex localised access issues resulted in payment of
additional time charges. Additional works were also
required to regrade kerb lines with existing road finishes.
Motherwell Library - Electrical Rewire and
Redecoration £479,407 £446,626 Price fluctuations for materials were agreed, mostly around
copper prices which had spiked around this time. 
Additional Nursery Provision: 1140 Hours
Programme -Shawhead Primary School,
Coatbridge (LLEY17099)
£613,000 £577,808 Extension of time required due to delays in sourcing
products as a direct result of Covid and additional drainage
requirement to address the increased capacity to school,  
Airdrie - Chapelhall FLC - New Build- 
(LLEY19049) £1,321,137 £1,259,221
Covid alterations and additional localised minor works
required at the request of Care Commission including;
screens to reception desks, Virgin media cabling &
ducting, small power & data changes, addition of push
plates to external gates. 
Airdrie - Petersburn FLC - New Build-
(LLEY19045) £1,730,834 £1,705,039
Covid alterations and additional localised minor works
required at the request of Care Commission including;
screens to reception desks, Virgin media cabling & ducting,
small power & data changes, addition of push plates to
external gates. 
Motherwell - Netherton FLC - New Build-
(LLEY19051) £1,337,147 £1,310,140
Covid alterations and additional localised minor works
required at the request of Care Commission including;
screens to reception desks, Virgin media cabling & ducting,
small power & data changes, addition of push plates to
external gates. 
Wishaw - Bonkle FLC - New Build-
(LLEY19050) £1,986,793 £1,954,762
Covid alterations and additional localised minor works
required at the request of Care Commission including;
screens to reception desks, Virgin media cabling & ducting,
small power & data changes, addition of push plates to
external gates. 
Wishaw - Coltness FLC - New Build-
(LLEY19046) £1,745,398 £1,685,320
Covid alterations and additional localised minor works
required at the request of Care Commission including;
screens to reception desks, Virgin media cabling & ducting,
small power & data changes, addition of push plates to
external gates. 
Clydeview School Relocation to Daisy Park
Centre £721,174 £493,674
A post tender request was received and approved to
broaden the scope of works to accommodate the ASN
review and address capacity issues. The contract
programme was also condensed to remain aligned with
school term time resulting in additional out of hours
payments.