Revenue Budget Monitoring Report; Chief Executive's and Other Corporate Services 1 April - 22 July 2022 (Period 4)
North Lanarkshire Council · 14 September 2022
Back to Finance and Resources Committee — 14 September 2022 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
North Lanarkshire Council Report Finance and Resources Committee Does this report require to be approved? ☐ Yes ☒ No Ref NL/PF Date 14/09/22 Revenue Budget Monitoring Report; Chief Executives & Other Corporate Services 01.04.22 – 22.07.22 (Period 4) From Elaine Kemp, Head of Financial Solutions Email kempe@northlan.gov.uk Telephone 07939 280 601 Executive Summary This report provides a summary of the Chief Executive & Other Corporate Services financial performance for the period 1 April 2022 to 22 July 2022 (Period 4). The report illustrates the provisional outturn as at 31 March 2023, with major outturn variances highlighted and explained per the Council’s approved Financial Regulations. The Council approved its General Fund Revenue Budget on 17 February 2022, of which £93.763m currently represents the Net Revenue Budget for the Chief Executive & Other Corporate Services. The Service is currently projecting breakeven position for the financial year which includes £2.171m of approved COVID funding. In addition, the 2022/23 budget incorporates £3.290m savings in relation to Digital NL (2022/23 approved saving of £0.198m plus 2021/22 unachieved saving of £3.092m from 2021/22). In recognition of the challenges facing the implementation of this saving, Business and Digital were awarded £1.000m through the Ear Marked Reserve process resulting in a reduced savings target of £2.290m for 2022/23. However, Business and Digital will require to achieve the approved saving balance of £1.000m in 2023/24. The 2022/23 budget incorporates a further £0.163m of savings previously approved by Council. The Service is currently reviewing progress on achievement of all savings and will present an updated position in subsequent reports. The Service is currently reviewing progress on achievement and will present an updated position in subsequent reports. Recommendations It is recommended that Finance and Resources Committee: (1) acknowledge the financial position of the 2022/23 Chief Executive & Other Corporate Services revenue budget. The Plan for North Lanarkshire Priority Improve North Lanarkshire's resource base Ambition statement (25) Ensure intelligent use of data and information to support fully evidence based decision making and future planning
Page 2
1. Background 1.1 The Council’s approved Financial Regulations require the Chief Executive to remain within the approved budgetary provision, and to report all significant deviations - defined as the higher of £100,000 or 5% - within budget monitoring reports. Where significant deviations are identified, the Chief Executive must provide explanatory commentary, outline the action required to rectify such deviations and where relevant, must also highlight the impact this has on other budget headings. 2. Report 2.1 Summary of Financial Position 2.1.1 The Council approved its General Fund Revenue Budget on 17 February 2022, of which £93.565m (10.55%) represented the approved Revenue Budget for the Chief Executive & Other Corporate Services. Incorporation of the COVID Recovery budget of £2.171m and the realignment of Communities budgets have been included. Subsequent budget realignments in relation to the approved transfer of Services from Enterprise & Communities to Chief Executives of £0.198m has resulted in a revised budget of £93.763m. 2.1.2 The overall projected outturn position of the Service is a break-even position. Appendices one to five provide further information in respect of this position. 2.1.3 In light of the ongoing impact of COVID-19 and other financial pressures, Services have been requested to continue to implement mitigating actions to ensure the position is managed and the Council remains financially sustainable. The mitigating action includes a Council wide recruitment freeze and the curtailment of non-essential expenditure. 2.1.4 The 2022/23 budget incorporates £3.290m savings in relation to Digital NL (2022/23 approved saving of £0.198m plus 2021/22 unachieved saving of £3.092m from 2021/22). In recognition of the challenges facing the implementation of this saving, Business and Digital were awarded £1.000m through the Ear Marked Reserve process resulting in a reduced savings target of £2.290m for 2022/23. However, Business and Digital will require to achieve the approved saving balance of £1.000m in 2023/24. The 2022/23 budget incorporates a further £0.163m of savings previously approved by Council. The Service is currently reviewing progress on achievement of all savings and will present an updated position in subsequent reports. The Service is currently reviewing progress on achievement and will present an updated position in subsequent reports. Further information regarding savings is included in Appendix 5. 2.2 Analysis of Significant Variances 2.2.1 Employee costs are anticipated to be overspent by £1.000m as a result in the delay in Digital NL savings. In year management action has been taken by Business and Digital to support this overspend. 2.2.2 Supplies & Services are currently projected to be underspent by £1.000m due to management action taken by Business & Digital to support the delay in Digital NL savings. 2.3 Earmarked and One-Off Resources 2.3.1 In finalising the Council’s draft accounts to 31 March 2022, the service was given approval to earmark £5.519m of resources to fund key projects and initiatives profiled
Page 3
over a number of years. It is anticipated that £5.206m of the reserves balances will be utilised in 2022/23. A total of £0.312m of the remaining balance will be required for future years. Details of the Service’s earmarked funds are provided in Appendix 4. 2.3.2 It should be noted that the cost profiling for the DigitalNL approved £2.499m earmarked reserve has still to be completed and an updated position will be presented in subsequent reports. 2.3.3 Details of the Service’s earmarked funds are provided in Appendix 4. 2.3.4 The Service has not yet incurred any VRS costs relating to savings/restructures. There is therefore no requirement to utilise any of the Corporate Change Management fund at this time. Costs arising from 2022/23 savings/restructures will be reported in future reports as they are incurred 2.3.5 These costs are not included in the Service outturn position. 2.4 2022/23 Budget Savings 2.4.1 The Council approved savings of £3.290m savings in relation to Digital NL (2022/23 approved saving of £0.198m plus 2021/22 unachieved saving of £3.092m from 2021/22). In recognition of the challenges facing the implementation of this saving, Business and Digital were awarded £1.000m through the Ear Marked Reserve process resulting in a reduced savings target of £2.290m for 2022/23. However, Business and Digital will require to achieve the approved saving balance of £1.000m in 2023/24. The 2022/23 budget incorporates a further £0.163m of savings previously approved by Council. The Service is currently reviewing progress on achievement and will present an updated position in subsequent reports. 2.4.2 Appendix 5 provides a summary of the savings, including commentary in relation to challenging savings and any actions taken to address the funding gap which has arisen. 2.5 COVID-19 Costs 2.5.1 The approved COVID Recovery Budget has been incorporated with an additional net expenditure budget of £2.171m provided. This reflects anticipated increased costs of £1.982m, Lost income of £0.060m and additional investment of £0.129m. Details of the Service’s COVID Budget are provided in Appendix 6. 2.6 Management Actions 2.6.1 The Service is being pro-active to ensure expenditure is contained within its approved 2022/23 budget. 3. Measures of success 3.1 The Service continues to operate within approved budget resources. 4. Supporting documentation Appendix 1 Objective Summary Appendix 2 Subjective Summary Appendix 3 Payments to Other Bodies Appendix 4 Earmarked Reserves Appendix 5 Budget Savings Appendix 6 COVID Recovery Budget
Page 4
Elaine Kemp Head of Financial Solutions
Page 5
5. Impacts ( http://connect/report-template-guidance ) 5.1 Public Sector Equality Duty and Fairer Scotland Duty Does the report contain information that has an impact as a result of the Public Sector Equality Duty and/or Fairer Scotland Duty? Yes ☐ No ☒ If Yes, please provide a brief summary of the impact? If Yes, has an assessment been carried out and published on the council’s website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer- scotland-duty-impact-assessments Yes ☐ No ☐ 5.2 Financial impact Does the report contain any financial impacts? Yes ☒ No ☐ If Yes, have all relevant financial impacts have been discussed and agreed with Financial Solutions? Yes ☒ No ☐ If Yes, please provide a brief summary of the impact? The Service is being pro-active to ensure expenditure is contained within its approved 2022/23 budget. 5.3 HR policy impact Does the report contain any HR policy or procedure impacts? Yes ☐ No ☒ If Yes, have all relevant HR impacts have been discussed and agreed with People and Organisational Development? Yes ☐ No ☐ If Yes, please provide a brief summary of the impact? 5.4 Legal impact Does the report contain any legal impacts (such as general legal matters, statutory considerations (including employment law considerations), or new legislation)? Yes ☐ No ☒ If Yes, have all relevant legal impacts have been discussed and agreed with Legal and Democratic Solutions? Yes ☐ No ☐ If Yes, please provide a brief summary of the impact? 5.5 Data protection impact Does the report / project / practice contain or involve the processing of personal data? Yes ☐ No ☒ If Yes, is the processing of this personal data likely to result in a high risk to the data subject? Yes ☐ No ☐ If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e- mailed to dataprotection@northlan.gov.uk Yes ☐ No ☐
Page 6
5.6 Technology / Digital impact Does the report contain information that has an impact on either technology, digital transformation, service redesign / business change processes, data management, or connectivity / broadband / Wi-Fi? Yes ☐ No ☒ If Yes, please provide a brief summary of the impact? Where the impact identifies a requirement for technology, has an assessment been carried out (or scheduled) by the Enterprise Architecture Governance Group (EAGG)? Yes ☐ No ☒ 5.7 Environmental / Carbon impact Does the report / project / practice contain information that has an impact on any environmental or carbon matters? Yes ☐ No ☒ If Yes, please provide a brief summary of the impact? 5.8 Communications impact Does the report contain any information that has an impact on the council’s communications activities? Yes ☐ No ☒ If Yes, please provide a brief summary of the impact? 5.9 Risk impact Is there a risk impact? Yes ☒ No ☐ If Yes, please provide a brief summary of the key risks and potential impacts, highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service or Project Risk Registers), and how they are managed? All activities undertaken by the Council are subject to risk, and in acknowledging the Council’s approved Risk Management Strategy, Services manage these as part of their overall corporate and service planning processes. The current economic climate, in particular, has the potential to impact upon the Council’s ability to provide quality services within approved budget levels. Reflecting the risk analysis matrix included within the Risk Management Strategy, the Service considers delays or amendments to savings proposals could present an ongoing risk to the financial outturn for 2022/23. To minimise risk this report has been prepared by service based Financial Solutions personnel in consultation with budget managers, in accordance with the Financial Regulations.
Page 7
APPENDIX 1 [1] [2] [3] [5] [6] [8] [9] [10] DIRECTORATE & SUPPORT 221,147 221,147 0 876,892 876,892 0 0.0% 0 FINANCIAL SOLUTIONS 10,488,528 10,488,528 0 47,932,562 47,932,562 0 0.0% 0 AUDIT & RISK 155,450 155,450 0 581,134 581,134 0 0.0% 0 LEGAL & DEMOCRATIC SOLUTIONS 783,192 783,192 0 2,261,626 2,261,626 0 0.0% 0 BUSINESS & DIGITAL 6,287,124 6,287,125 0 12,564,934 12,564,934 0 0.0% 0 PEOPLE & ORGANISATIONAL DEVELOPMENT 2,350,147 2,350,146 0 8,063,406 8,063,406 0 0.0% 0 STRATEGIC COMMUNICATIONS 1,387,067 1,387,066 0 5,160,273 5,160,273 0 0.0% 0 OTHER CORPORATE SERVICES 1,102,353 1,102,353 0 3,684,556 3,684,556 0 0.0% 0 JOINT BOARDS 4,352,955 4,352,955 0 12,637,971 12,637,971 0 0.0% 0 NET EXPENDITURE 27,127,962 27,127,962 0 93,763,354 93,763,355 0 0.0% 0 FAV = Favourable Variation, underspend etc ADV = Adverse Variation, overspend etc [4] [7] PROJECTED OUT-TURN VARIANCE PROJECTED OUT-TURN % PERIOD MOVEMENT ANALYSISDIVISION OF SERVICE BUDGET TO DATE ACTUAL TO DATE YEAR TO DATE VARIANCE ANNUAL BUDGET NORTH LANARKSHIRE COUNCIL Revenue Budget Monitoring Report - Objective Analysis Period 04 (01 April 2022 - 22 July 2022) A - Chief Executive's
Page 8
APPENDIX 2 [1] [2] [3] [5] [6] [8] [9] [10] EMPLOYEE COSTS 8,012,544 9,012,544 (1,000,000) ADV 35,593,687 36,593,688 (1,000,000) ADV (2.8%) (1,000,000) Digital NL - delay in sprint releases offset by underspend within contract lines PROPERTY COSTS 922,906 922,906 0 2,262,784 2,262,784 0 0.0% 0 SUPPLIES & SERVICES 5,941,853 4,941,853 1,000,000 FAV 10,181,662 9,181,662 1,000,000 FAV 9.8% 1,000,000 Digital NL - management action within B&D to offset delay in sprint releases associated with saving TRANSPORT & PLANT 20,087 20,087 0 162,939 162,939 0 0.0% 0 ADMINISTRATION COSTS 1,488,306 1,488,306 0 7,971,307 7,971,308 0 0.0% 0 PAYMENTS TO OTHER BODIES 4,132,997 4,132,997 0 20,145,033 20,145,033 0 0.0% 0 TRANSFER PAYMENTS 22,758,331 22,758,331 0 121,872,879 121,872,879 0 0.0% 0 CAPITAL FINANCING COSTS 0 0 0 4,072,342 4,072,342 0 0.0% 0 REVENUE FINANCING COSTS 0 0 0 0 0 0 0.0% 0 OTHER EXPENDITURE 2,034,340 2,034,340 0 3,847,047 3,847,047 0 0.0% 0 TOTAL EXPENDITURE 45,311,365 45,311,365 0 206,109,680 206,109,680 0 0.0% 0 INCOME (18,183,402) (18,183,402) 0 (112,346,326) (112,346,326) 0 0.0% 0 NET EXPENDITURE 27,127,962 27,127,963 0 93,763,354 93,763,354 0 0.0% 0 FAV = Favourable Variation, underspend etc ADV = Adverse Variation, overspend etc [4] [7] PROJECTED OUT-TURN VARIANCE PROJECTED OUT-TURN % PERIOD MOVEMENT ANALYSISCATEGORY BUDGET TO DATE ACTUAL TO DATE YEAR TO DATE VARIANCE ANNUAL BUDGET NORTH LANARKSHIRE COUNCIL Revenue Budget Monitoring Report - Subjective Analysis Period 04 (01 April 2022 - 22 July 2022) A - Chief Executive's
Page 9
APPENDIX 3 [1] [2] [3] [5] [6] [8] [9] [10] PAYMENTS TO OTHER BODIES GENERAL 1,905 1,905 0 4,570,782 4,570,782 0 0.0% 0 MEDICAL FEES 278 278 0 9,637 9,637 0 0.0% 0 AGENCY FEES 3,306 3,306 0 81,542 81,542 0 0.0% 0 TOWN TWINNING 0 0 0 3,533 3,533 0 0.0% 0 CHILDRENS PANEL 1,919 1,919 0 25,035 25,035 0 0.0% 0 COSLA ANNUAL LEVY 0 0 0 195,000 195,000 0 0.0% 0 COMMUNITY COUNCIL GRANTS 18,897 18,897 0 158,629 158,629 0 0.0% 0 GRANTS TO ORGANISATIONS 561,507 561,507 0 1,285,191 1,285,191 0 0.0% 0 EXTERNAL AUDIT FEE 0 0 0 529,389 529,389 0 0.0% 0 ELECTION PROVISION 0 0 0 0 0 0 0.0% 0 TOURISM - VISIT NORTH LANARKSHIRE 0 0 0 37,000 37,000 0 0.0% 0 SCOTTISH WELFARE FUND 845,803 845,803 0 2,759,844 2,759,844 0 0.0% 0 SUB-CONTRACTOR PAYMENTS 0 0 0 1,869 1,869 0 0.0% 0 LOCAL TAX PAYPOINT COMMISSION 2,427 2,427 0 35,000 35,000 0 0.0% 0 COSLA MIGRATION SCOTLAND 150,000 150,000 0 150,000 150,000 0 0.0% 0 LANDS VALUATION CONTRIBUTION 525,750 525,750 0 2,105,910 2,105,910 0 0.0% 0 SPT CONTRIBUTION 1,356,228 1,356,228 0 5,453,118 5,453,118 0 0.0% 0 SPT CONCESSIONARY FARES CONTRIBUTION 142,977 142,977 0 572,943 572,943 0 0.0% 0 CUSTOMER FIRST CONTRIBUTION 522,000 522,000 0 2,700,000 2,700,000 0 0.0% 0 TOTAL EXPENDITURE 4,132,998 4,132,998 0 20,674,422 20,674,422 0 0.0% 0 FAV = Favourable Variation, underspend etc ADV = Adverse Variation, overspend etc [4] [7] PROJECTED OUT-TURN VARIANCE PROJECTED OUT-TURN % PERIOD MOVEMENT ANALYSISCATEGORY BUDGET TO DATE ACTUAL TO DATE YEAR TO DATE VARIANCE ANNUAL BUDGET NORTH LANARKSHIRE COUNCIL Revenue Budget Monitoring Report - Payments to Other Bodies Period 04 (01 April 2022 - 22 July 2022) A - Chief Executive's
Page 10
APPENDIX 4 Value % Service Specific Earmarked Reserves: Support Plan for North Lanarkshire L&D 100 0 100 0 100 100.0% 0 100 Digitisation Reserve B&D 2,499 (180) 2,319 404 2,319 100.0% 0 2,319 Budget required in 2023/24 per original phasing Digital Savings B&D 1,000 0 1,000 1,000 1,000 100.0% 0 1,000 Family Firm POD 173 0 173 10 173 100.0% 0 173 Creation of Learning Academy POD 100 0 100 0 100 100.0% 0 100 Creation of Construction Academy POD 300 0 300 0 300 100.0% 0 300 Customer Services Hub SC 262 (132) 130 33 130 100.0% 0 130 Delay in appointment of staff, balance of EMR required in 2023/24 Cumbernauld Theatre SC 35 0 35 0 35 100.0% 0 35 VANL (New) SC 60 0 60 0 60 100.0% 0 60 LDP Prog Play Areas and additional projects SC 500 0 500 0 500 100.0% 0 500 Recover NL - grant award prog SC 172 0 172 0 172 100.0% 0 172 Ukraine Humanitarian Appeal MM 15 0 15 15 15 100.0% 0 15 Change Management / Non-Service Specific: CLNL Insourcing POD / B&D 168 0 168 37 168 100.0% 0 168 CLNL ICT Development 135 0 135 0 135 100.0% 0 135 TOTAL 5,519 (312) 5,206 1,499 5,206 100.0% 0 5,206 Reserves No Longer Required Reserves Required In Year Commentary Regards Usage NORTH LANARKSHIRE COUNCIL Revenue Budget Monitoring Report - Status of Earmarked Reserves Period 04 (01 April 2022 - 22 July 2022) A - Chief Executive's FINANCIAL YEAR - 2022/23 DESCRIPTION OF EARMARKED RESOURCE DIVISION Reserve Allocation Adjustments In Year Approved Reserve Total Spend to Date Projected Spend
Page 11
APPENDIX 5 £000 £000 £000 £000 £000 Digital NL B&D 198 0 198 Management action taken within other budgets in current year 198 0 Reduction of ESC Admin posts POD 163 163 0 0 0 TOTAL 361 163 198 198 0 CommentaryDESCRIPTION OF APPROVED SAVING DIVISION Target Value Value Deliverable Saving Gap APPROVED SAVINGS REPLACEMENT SAVING / FUNDING DESCRIPTION Value BUDGET GAP NORTH LANARKSHIRE COUNCIL Revenue Budget Monitoring Report - Savings Period 04 (01 April 2022 - 22 July 2022) A - Chief Executive's
Page 12
APPENDIX 6 £000 £000 £000 £000 Costs: Increased Costs 1,982 1,982 0 0 Reduced Costs 0 0 0 0 Lost Income 60 60 0 0 Income Over-Recovery 0 0 0 0 Delay in Achievement of Savings 0 0 0 0 Unavoidable Investment Commitments 0 0 0 0 Other 0 0 0 0 Investment Proposals Agreed 129 129 0 0 Contingencies 0 0 0 0 Service Costs Total 2,171 2,171 0 0 Income: Earmarked COVID Funding (2,171) (2,171) 0 0 Service Contributions 0 0 0 0 NLC Use of Reserves 0 0 0 0 21/22 COVID Funding - GRG 0 0 0 0 21/22 COVID Funding - RF 0 0 0 0 Service Income Total (2,171) (2,171) 0 0 TOTAL NET COSTS (0) (0) 0 0 NORTH LANARKSHIRE COUNCIL Revenue Budget Monitoring Report - Forecast COVID-19 Costs Period 03 (01 April 2022 - 24 June 2022) A - Chief Executive's CommentaryDESCRIPTION OF COVID-19 COSTS BUDGET PROJECTED OUT-TURN PROJECTED OUT-TURN VARIANCE PERIOD MOVEMENT