Argyll and Bute Council · 30 January 2024
Back to Planning, Protective Services and Licensing Committee — 30 January 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Argyll and Bute Council 
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD 
23 January 2024 
NOTICE OF MEETING 
A meeting of the PLANNING, PROTECTIVE SERVICES AND LICENSING COMMITTEE will be
held ON A HYBRID BASIS IN THE STUDIO THEATRE, CORRAN HALLS, CORRAN
ESPLANADE, OBAN AND BY MICROSOFT TEAMS on TUESDAY, 30 JANUARY 2024 at 11:00
AM, which you are requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST 
3. MR SHAUN SINCLAIR: ERECTION OF CAFÉ WITH ASSOCIATED
LANDSCAPING INCLUDING A VIEWPOINT, SEATING, INTERPRETIVE SIGN
AND PLAY PARK: LAND WEST OF INVERLUSRAGAN, CONNEL (REF:
21/01583/PP) (Pages 3 - 52)  
Report by Head of Development and Economic Growth 
Planning, Protective Services and Licensing Committee 
Councillor John Armour Councillor Gordon Blair
Councillor Jan Brown Councillor Audrey Forrest
Councillor Kieron Green (Chair) Councillor Amanda Hampsey (Vice-Chair)
Councillor Daniel Hampsey Councillor Graham Hardie
Councillor Mark Irvine Councillor Andrew Kain
Councillor Paul Donald Kennedy Councillor Liz McCabe
Councillor Luna Martin Councillor Dougie Philand
Councillor Peter Wallace   
Contact: Fiona McCallum                  Tel. No. 01546 604392
Public Document Pack

Page 2

This page is intentionally left blank

Page 3

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Argyll and Bute Council
Development & Economic Growth   
Planning Application Report and Report of Handling as required by Schedule 2 of the
Town and Country Planning (Development Management Procedure) (Scotland)
Regulations 2013 relative to applications for Planning Permission or Planning
Permission in Principle 
Reference No: 21/01583/PP 
Planning Hierarchy: Local 
Applicant: Mr Shaun Sinclair 
Proposal: Erection of Café with Associated Landscaping including a
Viewpoint, Seating, Interpretive Sign and Play Park 
Site Address:  Land West of Inverlusragan, Connel 
DECISION ROUTE 
☐Delegated - Sect 43 (A) of the Town and Country Planning (Scotland) Act 1997 
☒Committee - Local Government Scotland Act 1973 
(A)  THE APPLICATION 
(i) Development Requiring Express Planning Permission 
• Erection of café building with incidental ‘drive-thru’ takeaway
• Installation of viewpoint 
• Installation of seating 
• Installation of interpretive sign
• Installation of private drainage system 
(ii) Other specified operations 
• Formation of vehicular access 
• Connection to public water infrastructure 
• Proposed landscaping 
(B) RECOMMENDATION: 
It is recommended that planning permission be REFUSED for the reasons appended
to this report. 
(C) CONSULTATIONS:   
Transport Scotland 
Finalised response dated 13/01/23 advising no objection to the proposed
development subject to conditions being imposed on the grant of permission to
Page 3 Agenda Item 3

Page 4

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
secure the appropriate construction of the access at the junction with the Trunk Road
and the clearance of the associated visibility splays. 
Argyll and Bute Council – Roads Authority 
Report dated 16/11/21 advising no objection to the proposed development subject to
a condition being imposed on the grant of permission to secure a suitable parking
and turning area to serve the development. 
Argyll and Bute Council – Environmental Health Service (EHS) 
Memo dated 17/02/23 advising no objection to the proposed development subject to
conditions being imposed on the grant of permission to secure a site traffic
management plan for the development, a noise limiting condition, and a condition to
regarding the specification for external lighting.   
Argyll and Bute Council – Biodiversity Officer (BDO)
Letter dated 08/06/22 requesting the submission of an Otter Survey and
Ornithological Survey in support of the proposed development.  Such surveys were
undertaken and submitted for consideration.  In an e-mail dated 02/08/22 the BDO
noted the contents of the reports including taking account of seasonality concerning
ornithological interest along with advice and mitigation for Otter and Bat species. The
BDO concurred with the recommendations to protect and enhance habitats and
species such pre-start checks for bird species, the provision of bat boxes and
landscaping with native trees and shrubs. The BDO advised that, if permission is
granted, planting of Ash- Fraxinus excelsior should be avoided due to Ash Die Back
being present in the area and the difficulty in purchasing this species.  The BDO
noted that Japanese Knotweed is evident and accordingly requests that a watching
brief is undertaken for the site. 
A further Otter and Breeding Bird Assessment, separate from that originally prepared
for the site, by another firm, was submitted to the Planning Authority.  In her response
to the further report, the BDO noted the contents, advising that the survey was carried
out on 1st December, outwith the optimum time of year, whereas the original
ecological report surveys were carried out over a 4 day period in early July.  The
BDO noted that the conclusions of the report are not unexpected and the
recommendations follow best practice including additional advice on the contribution
landscape planning (both planting and bird boxes) and implementation can make to
provide habitat for a variety of species.  The BDO recommended that both ecological
reports (July and January) are implemented in combination should planning
permission be granted. 
Argyll and Bute Council – Development Policy Team (DPT) 
Memo dated 14/01/22 advising that in terms of the adopted LDP Proposals Maps the
site is situated within an Open Space Protection Area (OSPA) which provides visual
amenity functions by helping preserve the open aspect on the seaward side of the
A85 and with it, public views across Loch Etive. 
Policy SG LDP REC/COM 2 sets out that the development of OSPAs will not be
permitted except where one of the five clauses set out in the policy are met. The DPT
advise that they do not consider that the proposal satisfies any of the five clauses
and as such the proposal is considered to be contrary to Policy SG LDP REC/COM
2.   
The DPT further state that the OSPA has been carried forward into pLDP2, which
was not objected to. 
Page 4

Page 5

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
In light of the comments from the DPT, the Agent submitted a report on the OSPA
which is discussed in more detail in the assessment of the application at Appendix A
where the further comments of the DPT in a memo dated 25/05/22 are detailed. 
Scottish Water 
Letter dated 16/11/21 advising no objection to the proposed development which
would be serviced from the Tullich Water Treatment Works.  Scottish Water do
however advise that further investigations may be required once an application for
formal connection is submitted to them for consideration. 
JBA Consulting Ltd (JBA) 
Report dated 01/12/21 advising no objection to the proposed development. 
Connel Community Council (CCC) 
Letter dated 01/12/21 advising, in summary, that the Local Development Plan (LDP)
allocates the site as an Open Space Protection Area and any decision to reverse this
for financial benefit of an individual landowner is not one that should be made.  If the
application is successful, it would seriously undermine the LDP going forward.  The
rules relating to these areas are set out in the LDP and there is nothing in the
application, in the opinion of the CCC, that remotely meets the criteria that would
enable the development to be supported. 
(D) HISTORY:   
03/01550/DET
Construction of new pumping station, septicity building, access road and ancillary
works (SPS 2) – Withdrawn: 31/12/03 
(E) PUBLICITY:   
The proposal has been advertised in terms of Regulation 20 and Neighbour
Notification procedures, overall closing date 16/12/01. 
(F) REPRESENTATIONS:   
At the time of writing, representations have been received by the Planning Authority
from 165 respondents in relation to this planning application. 44 respondents raise
objection, 120 provide support and 1 submits a representation. 
Of the 120 expressions of support, 51 of these comprise a pro-forma letter completed
with the respondents names and addresses with 66 comprising a pro-forma slip
submitted to the Applicant during a Community Council Meeting held on 09/05/22
and then passed to the Planning Authority.   
In addition to the above, a screenshot from Facebook with names and ‘likes’ for the
development on the Applicant’s personal Facebook page has been submitted. 
The names and addresses of those contributing to the application are contained
within Appendix B of this report with full copies of the representations published on
the planning application file available to view via the Public Access section of the
Council’s website.
Page 5

Page 6

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
(i) Summary of issues raised – Objection   
Validity of Application 
• Comments regarding the validity of the planning application in relation to
the Heads of Planning Scotland (HOPS) – Validation Guidance Note (the
submission provides extracts from the HOPS guidance along with
correspondence from various Scottish Public Services Ombudsman
cases in support of the comments provided). 
Officer Comment: With regards to the above, it should be noted that the
HOPS National Validation Standards document is an advisory as opposed
to a statutory requirement in the validation of planning applications.  The
HOPS document is endorsed by the Council as Planning Authority as an
example of good practice and published on the Council’s website to assist
prospective applicants on the preparation of their planning applications, and
is utilised to inform the standards sought by the Central Validation Team
when registering new applications. 
The content of the HOPS document is, however, provided as guidance to
assist applicants with the preparation of documentation that first and
foremost meets minimum Regulatory requirements, but also provides that
information within a consistent format to assist the Council with the
processing of the application, it is noted that the HOPS guidance promotes
an enhanced level of information that exceeds minimum Regulatory
standards. The HOPS document is advisory and accordingly is applied at the
sole discretion of the Council as Planning Authority in its validation of
applications submitted for consideration. 
Notwithstanding the above, it is considered that the information supplied with
the application and subsequently assessed by the Planning Authority is
sufficient in its scope, detail and accuracy so as to present an appropriately
clear description of the development proposed without being wilfully
misleading or ambiguous. 
Compliance with National and Local Policy 
• The proposal conflicts with NPF4 and LDP Policies 
Officer Comment:  The proposal is fully assessed against the relevant
NPF4 and LDP Policies in the assessment contained within Appendix A of
this report. It is recommended that planning permission be refused. 
Open Space Protection Area (OSPA) 
• The village of Connel’s character and amenity is significantly enhanced
by its visual relationship with both the sea and also, importantly, with
Connel Bridge which is reflected in the designation of the site in the Local
Development Plan as an OSPA, put in place to protect the character of
Connel and provide both amenity space and protection of vistas from the
village to both the sea and the bridge for residents and visitors. 
Page 6

Page 7

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
• The Community Council worked hard to ensure that all of the undeveloped
shoreline between the main road and sea, including the application site,
was covered by the OSPA designation. 
• The proposed development will be highly visible from the northern end of
Connel Bridge and also highly visible from the water of Loch Etive under
Connel Bridge, Connel Bridge and the North Connel/Bonawe road. 
• The application should be carefully considered, as, should permission be
granted, it will set a precedent for future development within the OSPA
and other OSPAs. 
• The loss of the OSPA to the proposed development will have a profound
impact on the character of Connel and its appeal as a place to live and for
tourists. 
• Policies contained within the Local Plan, specifically Policy LDP 8 and
Policy SG LDP REC/COM 2 preclude the development of OSPAs. 
Officer Comment: The proposed development, and its impact on the OSPA,
is fully considered in the assessment of the application within Appendix A of
this report. It is recommended that planning permission be refused. 
Critiquing the Agents Report on the OSPA 
• The stretch of shoreline to the West of Connel Bridge is not the only area
of shoreline of active open space as indicated in the report.  The wooded
area of shoreline to the east of Connel Bridge, between the site and
Connel Surgery and the foreshore of the application site are already used
by the community and tourists alike for walking, fishing, observing wildlife,
watersports, dog walking, and photography.  Contrary to the report, the
wooded foreshore is very accessible and, contrary to the report, there is
a very accessible access road to the foreshore from the main road to the
east of the site. 
• There are significant concerns regarding the proposed playpark being
located within the site with young children having to cross the main A85
trunk road.  The play park is situated near the Lusragan Burn estuary with
a steep embankment beside a tidal loch with strong currents, tidal surges
and flooding which will potentially leady to drowning fatalities. 
The existing playpark at Powell Place is available to all children in Connel
and can be accessed via a safe pedestrian route away from the A85.  The
proposed playpark cannot be compared the existing one at Powell Place. 
• Connel already has numerous options available for the community to
gather.  Permission has been granted to the Applicant for a café; there is
the community playing field at Achaleven, the Village and Church Halls. 
There are also outdoor and indoor eating facilities at the Oyster Inn and
Falls of Lora Hotel.  The Connel Surgery has a community café with
disabled access and extensive parking with Connel Village Shop
providing a takeaway food and drink service. 
Page 7

Page 8

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
• The report highlights the advantages of siting the café to the east of the
site, however, it does not highlight that there will be a prominent car-park
and vehicles affecting the visual amenity from the west, particularly at the
higher part of the A85, at Connel village loop road junction. 
• Visual amenity does not just apply to views merely from the A85, there
are other important viewpoints that need to be considered in this
application.  It is crucial to consider the wider panoramic views to
Muchairn, Ben Cruachan and the Kilmaronaig Islands, which will be
adversely affected by elevated views into the site. 
• Contrary to the report, there are no existing buildings adjacent to the west
of the site until you reach Connel Surgery and the doctor’s house.  The
site is not an infill opportunity as set out in the report. 
• Any mention of EPS in the report is conspicuous by its absence as is any
mention of mitigating measures to protect the bats, herons, seals, herring
gulls and shags from the detrimental effects of traffic noise, light pollution
and other associated café/car park disturbances. 
The area is well known for Otter, video evidence of which has previously
been submitted, furthermore, there are nesting swans adjacent to the site
and bats are in abundance using the site as a feeding ground.  The
engineering and landscaping works will adversely affect the river bank
and loch shore line with light pollution and vehicle noise impact on this
sensitive biodiversity site. 
Officer Comment: This critique of the report on the OSPA submitted by the
Agent is noted by the Planning Authority.  The proposed development, and
its impact on the OSPA, is fully considered within Appendix A of this report.
It is recommended that planning permission be refused. 
History of Shoreside Planning Applications 
• The issue of development on the shore side of the A85 has already been
the subject of previous planning applications as follows. 
05/00697/DET, 05/00698/DET and 05/00699/DET for three
dwellinghouses between the application site and Connel Surgery were
refused at appeal (non-determination) on 22/09/05 
In their determination to the three dwellinghouses, the Scottish
Government appointed Report recommended that the south shore of
Connel with views from North Connel, Connel Bridge, from leisure boats
and water sports enthusiasts in the loch should also be protected, by way
of an OSPA designation in the up and coming Local Plan at that time. 
This recommendation was supported by Argyll and Bute Council, Connel
Community Council, Visit Scotland and many Connel residents.   
Argyll and Bute Council Planning recommendation to the Report was that’
the proposal would if approved set a precedent for further development
on this rural strip which the Council would find difficult to refuse”.  The
Council should adhere to their previous permission and preserve and
Page 8

Page 9

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
protect the natural wildlife and scent environment by keeping it as an
OSPA and refusing planning permission. 
05/00523/OUT and 11/00536/PPP for the site for erection of a
dwellinghouse on land opposite Ards Guest House were withdrawn on
20/06/06 and 10/11/11 respectively. 
Officer Comment:  These comments are noted by the Planning Authority as
an accurate summary of the relevant planning history. It is recommended
that planning permission be refused.   
Impact on Wildlife, Biodiversity and Habitats 
• The application site is extensively used by local wildlife including otter,
water vole, bats and many different bird species, some of these being
European Protectected Species (EPS). 
• The proposed development will have a significant adverse impact on the
species detailed above as well as the wider biodiversity of the site. 
• No independent Environmental Impact Assessment has been carried out
in relation to the application and accordingly a video survey was submitted
by third parties. 
• Concerns regarding the validity of the Ecological Reports submitted in
support of the application. 
• The so called ‘Environmental Survey’ is not, as it claims, an
Environmental Impact Assessment (EIA). 
• The impact of the development on the tree and hedgerow on the eastern
boundary of the site has not been addressed. 
Officer Comment: Two separate Otter and Breeding Bird Surveys have
been submitted in support of the application, details of which have been
considered by the BDO and which are discussed in more detail in the
assessment of the proposal in the full report within Appendix A of this report. 
The reports have been prepared by suitably qualified ecologists and the
Planning Authority has no reason to doubt their validity. 
The application does not constitute EIA development requiring the
submission of an Environmental Impact Assessment. 
As the Planning Authority is not supporting the principle of the proposed
development, details of landscaping, hedgerow retention/protection and
biodiversity enhancement measures were not sought.  Should permission be
granted, such details could be secured by a suitably worded condition
imposed on the grant of permission. 
Existing Use of Site 
Page 9

Page 10

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
• The details provided in the planning application are erroneous, the area
of ground has not had grazing animals on it for approximately 5 years. 
Officer Comment: This comment is noted by the Planning Authority. 
Existing Planning Permission/Alternative Sites 
• Permission for a café in the village has already been granted and
therefore there is no need to intrude on the valuable OSPA. 
• It is puzzling why the Applicant is applying for planning permission for this
site when permission has already been granted for a café elsewhere in
the village. 
• There are less obtrusive and damaging sites available. 
Officer Comment: Whilst these comments are noted by the Planning
Authority, every planning application is considered on its own merits.  The
application is assessed in full in Appendix A of this report. 
Flood Risk 
• The site is at risk of flooding and therefore the development if approved
will be at risk of flooding. 
Officer Comment:  The application site is outwith the coastal and river flood
zones necessitating consultation with SEPA.  In their response to the
application, the Council’s flood advisors, JBA Consulting Ltd, raised no
objection. 
Road and Pedestrian Safety Issues   
• The access will affect the site’s flooding and visual impact, with
illustrations submitted by third parties showing the impact. 
• Over the years, traffic in the village has become heavier, with a further
access onto the road, there is the potential of accidents happening,
perhaps fatal. 
• The road network is unable to cope with the increased demand in Connel,
North Connel and Oban. 
• The building of a play park, on the opposite site of a busy main road,
without a crossing point, would encourage children to cross the road
unsupervised. 
• This stretch of road is increasingly being used to overtake slower vehicles
despite the 30mph signs being in place. 
• The Applicant is applying for a ‘departure’ from Transport Scotland
regarding access specifications.  If there are to be shoreline defences, re-
contouring or natural coastline features and/or landraising …. Are these
all yet more acceptable ‘departures’ from planning policy that can be
justified in an OSPA. 
Page 10

Page 11

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
• A further junction onto the A85 could be very hazardous. 
• The development will require a seawall of some form with railings for
safety and an assessment will have to be made as to how these measures
will affect the flood risk elsewhere. 
• The drive thru element will likely increase the use of private car trips to
the site. 
• The proposal makes no provision for low or zero-emission vehicle and
cycle charging points and there is no safe, secure and convenience cycle
parking to meet the needs of users. 
• The layout has not been designed in a way to incorporate safety
measures for safe crossing/walking/wheeling within the site. 
• The drive through aspect of the development will not make good use of
the site with customers sitting in their cars instead of using the space
effectively. 
• Car engines idling, releasing carbon, is not environmentally friendly given
the current emphasis and focus being placed on climate change. 
Officer Comment: The Agent has worked closely with Transport Scotland
to agree a suitable access regime to serve the proposed development and
has agreed a regime that does not raise any road or pedestrian safety issues. 
With regards to pedestrian safety relating to the play park, the Planning
Authority sought comments from Transport Scotland who advised that: 
“The associated viewpoint with play area would appear to be of a small scale.
Consequently, while it may be the intention to allow its use by the wider
community, it is more likely to be used by the children of visiting patrons of
the proposed development. We are also aware that there is existing
development on the same side of this 30mph section of A85 trunk road such
as the Connel Surgery and Pharmacy and Achaleven Primary School.  
Based on the above, and having discussed this matter further internally, we
do not have any specific road and pedestrian safety concerns with this
aspect of the proposal”. 
The Council’s EHS advised that, should permission be granted, a condition
be imposed to secure a site traffic management plan for the proposed
development. 
With regards to the drive through aspect of the development, this is an
ancillary part of the main development which is a sit in café facility. 
As the Planning Authority is not supporting the principle of the proposed
development, details of cycle parking etc. were not sought.  Should
permission be granted, such details could be secured by a suitably worded
condition imposed on the grant of permission. 
Page 11

Page 12

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Noise/Odour 
• The proposed development will result in a substantial increase in noise to
the detriment or residential properties. 
• No details of the proposed kitchen ventilation has been provided, this
could have an adverse impact on the neighbouring dwellinghouse. 
Officer Comment: The Council’s EHS raised no objection to the proposed
development subject to a noise limiting condition and a condition to regarding
the specification for external lighting being imposed on any permission
granted.  The EHS will deal directly with the Applicant regarding the kitchen
specification should permission be granted. 
Public Gathering 
• The Applicant organised a gathering of people to discuss the planning
application, however, the opinions voiced at this gathering reported in the
press are not representative of the village of Connel.  For example, the
press article and the gathering failed to mention that the Applicant already
had planning permission for a café elsewhere in the village. 
Officer Comment:  Whilst this comment is noted by the Planning Authority,
this public gathering was not part of the planning process relating to the
planning application. 
General 
• The proposed café would have an adverse impact on the viability of the
local shop. 
• Access to the foreshore must not be restricted by the proposed
development should it proceed. 
• The proposed development will undermine the neighbouring land 
Officer Comment: Business competition is not a material planning
consideration.   
Should access to the foreshore become an issue should the development
proceed, this would be a matter for the Council’s Access Officer. 
Structural stability will be addressed at Building Warrant stage should the
proposed development proceed. 
Mr and Mrs Pat Howe – Specific Objections 
• Specific comments submitted from Pat and Cheryl Howe relating to
concerns over inconsistencies in the drawings submitted to Transport
Scotland with regards to the access and visibility splay arrangements and
the proximity of the development to their boundary. 
Officer Comment:  As a result of these specific access comments, the
Agent and Transport Scotland were consulted who clarified the situation
Page 12

Page 13

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
between them advising that “Mr and Mrs Howe appear to have
misinterpreted the site plan (Dwg. Ref. 20100 01 J). The plan has been
plotted using Ordnance Survey base maps and have been plotted according
to the boundary fence marked thereon. The trees on the plan that Mr and
Mrs Howe claim that are existing within their property are actually proposed
landscaping to provide screening to the adjacent property and are not yet
planted. These are proposed entirely within the Applicant’s property. 
The Application Boundary therefore reflects the ownership certificate
submitted and no amendment to either the Application Boundary or the
Ownership Certificates is required. 
Following Mr Howe's initial objection and discussions with Transport
Scotland, we procured and received a topographical survey which highlights
that the height of the bridge parapet is below that of the 1.05m as shown on
drawing 0425-013-P03 [attached]. We would also note that this has been
scrutinised by Transport Scotland in line with CD-123, an additional
requirement was requested that a full visibility splay of between 0.26m and
2.0m from ground level at the extent of the visibility splay is to be required.
Which confirms that the bridge parapet is at a suitable height to comply with
both requirements”. 
(ii) Summary of issues raised – Support   
• Pro-forma letter of support 
Noting that the current application is proposed to replace the planning
permission approved for the café on the opposite side of the road with
the current proposal addressing concerns previously raised by the
Community Council and local residents regarding road safety, parking
and congestion as well as privacy and amenity issues.  The current
proposal addresses all of these matters. 
The proposed development will bring significant benefits to Connel,
without any of the potential adverse impacts of the other site.  The village
lacks a café facility of this kind, which will act as a social hub for local
residents.  It will allow locals to access café facilities without travelling
outwith the village, thereby promoting sustainable travel patterns and
supports social inclusion. 
The proposed café will also have wider economic benefits to the village
by supporting the visitor economy.  The new lochside location will be a
far more attractive destination for both locals and visitors than the original
scheme, making the most of the village’s scenic location. 
It is understood that the site is part of an OSPA in the LDP, which aims
to preserve amenity, in particular views across Loch Etive from the A85. 
It appears that the development will not impact on views from the A85
due to the position of the building.  It will in fact benefit the village’s
amenity by providing a play park and seating area by the loch shore, for
use by locals and visitors.  There is currently no access to the seaward
site of the A85 in this part of Connel. 
The Council are urged to support the application to secure these positive
benefits from Connel.  
Page 13

Page 14

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
• A café and community hub is sorely lacking in the village and will
contribute to the revival of a community which should be as vibrant and
thriving as others in North Argyll. 
• The proposal will create jobs in the village which has very few job
openings given the lack of business. 
• Although the community is hugely in favour of the development, the
Community Council’s stance is disappointing, which ignores the views of
the people they are supposed to represent. 
• A playpark which is not contained within a housing estate will surely be
an asset for families. 
• It would be good to see a disused piece of land used for the good of many
people rather than a few. 
Officer Comment:  These expressions of support are noted by the Planning
Authority.  The impact of the proposed development on the landscape and
its economic benefit are assessed in the full report in Appendix A. It is
recommended that planning permission be refused and it is not considered
that any limited community and economic benefit is sufficient to outweigh the
landscape and settlement strategy harm caused by development within the
OSPA. 
(iii) Summary of issues raised – Representation   
• While the ODAP is broadly supportive of the principle of this proposal, there
are a number of concerns that need to be addressed if the proposal is to be
“inclusive” and meet the requirements of the Scottish Government’s Planning
Advice Note 78 which contains an expectation that new developments should
be designed so that they can be used by everyone, regardless of age, gender
or disability. The issues that need clarification are: 
Provision of at least one dedicated disabled parking bay 5 x 3.7m located
with 40m of the entrance to the café and surfaced in a bound non-slip
material. 
Provision of a 2m wide pathway, again of a bound non-slip material linking
the said parking bay to the main entrance to the café. 
Confirmation that the path linking the car park to the viewpoint will be a
minimum of 2m wide and finished in a bound non-slip surfacing material. 
The “accessible toilet” shown on the floorplan would be inaccessible to
wheelchair users.  It should be a minimum of 1700mm x 2200mm. (BS8300). 
Confirmation that the café and decking areas will include flexible (as opposed
to fixed) seating to enable their use by wheelchair users and others with
mobility difficulties.   
Page 14

Page 15

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
The main entrance is only 750mm wide and the lobby between it and the
secondary entrance has insufficient length (taking account of the inner door
swing) for an assisted wheelchair user to comfortably enter and exit the
building (see BS8300 – 8.2.5.2). This should be addressed now as it will have
implications on the appearance of the building. Ideally the main entrance
should have 1m clear effective opening width. 
While the Panel is happy to support the principle of this exciting proposal we
strongly recommend that consideration be deferred until these issues have
been addressed and resolved.  
Officer Comment: These comments are noted and will be brought to the
attention of the Applicant should planning permission be granted against
officer recommendation.   
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
(i) Environmental Impact Assessment Report: ☐Yes ☒No 
(ii) An Appropriate Assessment under the
Conservation (Natural Habitats) Regulations
1994:   
☐Yes ☒No 
(iii) A Design or Design/Access statement:    ☒Yes ☐No A
Supporting Statement
has been submitted in
support of the application
which is discussed in
more detail in the
assessment of the
application within
Appendix A of this report. 
(iv) A report on the impact of the proposed
development e.g. Retail impact, transport
impact, noise impact, flood risk, drainage
impact etc:  
☒Yes ☐No Two
Ecological Assessments
have has been submitted
in support of the
application which are
discussed in more detail
in the assessment of the
application within
Appendix A of this report   
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:   ☐Yes ☒No 
(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30,
31 or 32:  ☐Yes ☒No 
Page 15

Page 16

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
(J) Section 25 of the Act; Development Plan and any other material considerations
over and above those listed above which have been taken into account in the
assessment of the application 
(i)  List of all Development Plan Policy considerations taken into account
in assessment of the application. 
National Planning Framework 4 (Adopted 13th February 2023) 
Part 2 – National Planning Policy 
Sustainable Places
NPF4 Policy 1 – Tackling the Climate and Nature Crises
NPF4 Policy 2 – Climate Mitigation and Adaption
NPF4 Policy 3 – Biodiversity
NPF4 Policy 4 – Natural Places
NPF4 Policy 9 – Brownfield, Vacant and Derelict Land and Empty Buildings (includes
provisions relevant to Greenfield Sites)
NPF4 Policy 12 – Zero Waste
NPF4 Policy 13 – Sustainable Transport 
Liveable Places
NPF4 Policy 14 – Design, Quality and Place
NPF4 Policy 18 – Infrastructure First
NPF4 Policy 22 – Flood Risk and Water Management
NPF4 Policy 23 – Health and Safety 
Productive Places
NPF4 Policy 28 – Retail
NPF4 Policy 29 – Rural Development 
‘Argyll and Bute Local Development Plan’ Adopted March 2015 
LDP STRAT 1 – Sustainable Development 
LDP DM 1 – Development within the Development Management Zones 
LDP 3 – Supporting the Protection Conservation and Enhancement of our
Environment 
LDP 5 –Supporting the Sustainable Growth of our Economy
LDP 7 – Supporting our Town Centres and Retail 
LDP 8 – Supporting the Strength of our Communities 
LDP 9 – Development Setting, Layout and Design 
LDP 10 – Maximising our Resources and Reducing our Consumption 
LDP 11 – Improving our Connectivity and Infrastructure 
‘Supplementary Guidance to the Argyll and Bute Local Plan 2015’ (Adopted
March 2016 & December 2016) 
Natural Environment 
SG LDP ENV 1 – Impact on Habitats, Species and our Biodiversity 
Landscape and Design 
Page 16

Page 17

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
SG LDP ENV 14 – Landscape 
Retail Developments (Including COU to and from Shops) 
SG LDP RET 3 – Retail Development in the Key Rural Settlements, Villages and
Minor Settlements 
Bad Neighbour Development 
SG LDP BAD 1 – Bad Neighbour Development 
Sustainable Siting and Design 
SG LDP Sustainable – Sustainable Siting and Design Principles 
Resources and Consumption 
SG LDP SERV 1 – Private Sewage Treatment Plants & Wastewater Systems
SG LDP SERV 2 – Incorporation of Natural Features / SuDS
SG LDP SERV 5(b) – Provision of Waste Storage & Collection Facilities within New
Development 
Addressing Climate Change 
SG LDP SERV 7 – Flooding and Land Erosion – Risk Framework 
Transport (Including Core Paths) 
SG LDP TRAN 2 – Development and Public Transport Accessibility
SG LDP TRAN 4 – New & Existing, Public Roads & Private Access Regimes
SG LDP TRAN 6 – Vehicle Parking Provision 
(ii)  List of all other material planning considerations taken into account in
the assessment of the application, having due regard to Annex A of
Circular 3/2013. 
• Third Party Representations
• Consultation Reponses
• ABC Technical Note – Biodiversity (Feb 2017) 
Argyll and Bute proposed Local Development Plan 2 (November 2019) – The
Examination by Scottish Government Reporters to the Argyll and Bute Local
Development Plan 2 has now concluded and the Examination Report has been
published (13th June 2023). The Examination Report is a material consideration of
significant weight and may be used as such until the conclusion of the LDP2
Adoption Process. Consequently, the Proposed Local Development Plan 2 as
recommended to be modified by the Examination Report and the published Non
Notifiable Modifications is a material consideration in the determination of all
planning and related applications. 
Spatial and Settlement Strategy 
Policy 01 – Settlement Areas
Policy 04 – Sustainable Development
Page 17

Page 18

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
High Quality Places 
Policy 05 – Design and Placemaking
Policy 08 – Sustainable Siting
Policy 09 – Sustainable Design
Policy 10 – Design – All Development
Policy 14 – Bad Neighbour Development 
Diverse and Sustainable Economy 
Policy 22 – Economic Development 
Connected Places 
Policy 35 – Design of New and Existing, Public Roads and Private Access Regimes
Policy 36 – New Private Accesses
Policy 39 – Construction Standards for Private Accesses
Policy 40 – Vehicle Parking Provision 
Sustainable Communities 
Policy 46 – Retail Development – The Sequential Approach
Policy 55 – Flooding
Policy 60 – Private Sewage Treatment Plants and Wastewater Drainage Systems
Policy 61 – Sustainable Urban Drainage Systems (SUDS)
Policy 63 – Waste Related Development and Waste Management 
High Quality Environment 
Policy 73 – Development Impact on Habitats, Species and Biodiversity
Policy 81 – Open Space Protection Areas 
(K) Is the proposal a Schedule 2 Development not requiring an Environmental
Impact Assessment:  ☐Yes ☒No 
(L) Has the application been the subject of statutory pre-application consultation
(PAC):  ☐Yes ☒No 
(M) Has a Sustainability Checklist been submitted:  ☐Yes ☒No 
(N) Does the Council have an interest in the site:  ☐Yes ☒No 
(O) Requirement for a pre-determination hearing: ☐Yes ☒No (if Yes insert details
below) 
In deciding whether to hold a discretionary hearing Members should
consider: 
Page 18

Page 19

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
• How up to date the Development Plan is, the relevance of the
policies to the proposed development, and whether the
representations are on development plan policy grounds which
have recently been considered through the development plan
process. 
• The degree of local interest and controversy on material
considerations, together with the relative size of community
affected, set against the relative number of representations and
their provenance. 
At the time of writing, representations have been received by the
Planning Authority from 165 respondents in relation to this planning
application. 44 respondents raise objection, 120 provide support and
1 submits a representation. 
Of the 120 expressions of support, 66 of these were submitted to the
Applicant during a Community Council Meeting held on 09/05/22 and
then passed to the Planning Authority.   
In addition to the above, a screenshot from Facebook with names and
‘likes’ for the development on the Applicant’s personal Facebook page
has been submitted. 
NPF4 was adopted on 13/02/23 which now represents the main policy
background against which proposed developments are assessed
underpinned by the Policy and Supplementary Guidance contained
within the adopted ‘Argyll and Bute Local Development Plan’ 2015
(LDP) 
NPF4 Policy 9(b) states that proposals on greenfield sites will not be
supported unless the site has been allocated for development or the
proposal is explicitly supported in the LDP.   
The site has been designated as an OSPA in the adopted LDP and
emerging pLDP2 where Policies SG LDP REC/COM 2 and Policy 81,
respectively, do not permit development on OSPAs except in a
number of very specific circumstances details of which are discussed
in more detail in the full report contained in Appendix A. 
The proposed development within the OSPA conflicts with both
National and Local Policy and therefore, in this instance, the proposal
represents a clear policy refusal and it is not considered that a hearing
would add anything to the planning process.  
(P)(i) Key Constraints/Designations Affected by the Development: 
• Open Space Protection Area 
(P)(ii) Soils
Agricultural Land Classification:  Unclassified Land 
Peatland/Carbon Rich Soils Classification: ☐Class 1
☐Class 2
Page 19

Page 20

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
☐Class 3
☒N/A
Peat Depth Classification: N/A  
Does the development relate to croft land? ☐Yes ☒No
Would the development restrict access to croft
or better quality agricultural land?
☐Yes ☐No ☒N/A
Would the development result in
fragmentation of croft / better quality
agricultural land?
☐Yes ☐No ☒N/A 
(P)(iii) Woodland  
Will the proposal result in loss of
trees/woodland?
(If yes, detail in summary assessment)
☐Yes
☒No 
Does the proposal include any replacement or
compensatory planting?
☐Yes
☐No details to be secured by condition
☒N/A  
(P)(iv) Land Status / LDP Settlement Strategy
Status of Land within the Application
(tick all relevant boxes)
☐Brownfield
☐Brownfield Reclaimed by Nature
☒Greenfield 
ABC LDP 2015 Settlement Strategy 
LDP DM 1 (tick all relevant boxes) 
☐Main Town Settlement Area
☐Key Rural Settlement Area
☒Village/Minor Settlement Area
☐Rural Opportunity Area
☐Countryside Zone
☐Very Sensitive Countryside Zone
☐Greenbelt
ABC pLDP2 Settlement Strategy
(tick all relevant boxes) 
☒Settlement Area
☐Countryside Area
☐Remote Countryside Area
☐Helensburgh & Lomond Greenbelt
ABC LDP 2015 Allocations/PDAs/AFAs
etc: 
N/A
ABC pLDP2 Allocations/PDAs/AFAs
etc: 
N/A 
(P)(v) Summary assessment and summary of determining issues and material
considerations 
The proposal the subject of this application is seeking to secure planning permission
for the erection of a cafe with incidental ‘drive-thru’ takeaway plus associated
landscaping including a viewpoint, seating, interpretive sign and play park. 
In terms of the Settlement Strategy set out in the adopted LDP, the application site
is situated within the defined Minor Settlement of Connel where Policies LDP STRAT
1 and LDP DM 1 might ordinarily be expected to give general encouragement to
small scale development on appropriate sites subject to compliance with other
relevant policies and Supplementary Guidance (SG). 
Page 20

Page 21

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
However, the site the subject of this application is within an Open Space Protection
Area (OSPA) where Policy SG LDP REC/COM 2 does not permit development on
an OSPA unless it satisfies one of the 5 criteria listed in Policy SG LDP REC/COM2. 
The OSPA the subject of this planning application provides visual amenity functions
rather than recreation functions and accordingly it is not considered that the proposed
development satisfies any of the 5 criteria set out in Policy SG LDP REC/COM 2 and
accordingly the proposal is considered contrary to the provisions of this policy. 
The application site is situated within the minor settlement of Connel comprising an
area of deliberately undeveloped and open land situated between the A85 Trunk
Road and the shores of Loch Etive. 
The site is bounded along its eastern boundary by Inverlusragan, a residential
dwellinghouse.  The site slopes down gently from the A85 to the shores of Loch Etive. 
The application proposes a contemporary designed, single storey flat roofed
structure sited along the western boundary of the site finished in natural stone
cladding with a dark grey coloured metal roofing.  The application shows the
proposed café oriented with its main elevation and external seating area north to take
advantage of views out towards Loch Etive.  The application shows the café dug into
the sloping site to help minimise its visual impact.   
An existing vehicular access is to be upgraded to serve the proposed development
with water supply via connection to the public water main and foul drainage by way
of a new private system due to the lack of public infrastructure within the vicinity of
the site. 
The proposed parking area is shown to the west of the proposed café building with
a turning circle adjacent to the building to facilitate the proposed ‘drive through’.  The
play park and view point are proposed to the north of the proposed café building
between the building and the shores of Loch Etive.   
The proposal has elicited representations from 165 respondents.  44 respondents
raise objection, 120 provide support and 1 submits a representation. 
The OSPA in this location helps preserve the open aspect of the land on the shore
side of the road and along with it the public views.  It should be recognised that the
OSPA forms part of the wider network of OSPAs alongside Loch Etive that, together,
provide the wider function of preserving the undeveloped aspect of the shore side of
the road.  Development within this OSPA with the proposal subject of this planning
application would represent the piecemeal erosion of the wider OSPA network and
would potentially lead to pressure for development within other designated OSPAs
either side of Loch Etive, thereby undermining their functions.
The development the subject of this application would introduce built development
and infrastructure into a greenfield site which has been designated as an OSPA for
its visual amenity functions as detailed above. 
The proposed development would result in an adverse environmental impact eroding
the open aspect of the site and the associated public views across it thereby
undermining the OSPA designation of the site. 
Page 21

Page 22

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Whilst the potential economic and community benefit arising from the proposed
development is noted, it is not considered that this is sufficient to set aside the
detrimental impact that the proposed development will have on the open landscape
character of the area and the primary function of the OSPA to protect this together
with important public views of Loch Etive which give the settlement of Connel much
of its unique character. 
In light of the above it is recommended that planning permission is refused. 
A full report is provided in Appendix A of this report. 
(Q) Is the proposal consistent with the Development Plan: ☐Yes ☒No 
(R) Reasons why Planning Permission should be Refused 
See reasons for refusal below. 
(S) Reasoned justification for a departure to the provisions of the Development
Plan 
N/A 
(T) Need for notification to Scottish Ministers or Historic Environment Scotland:
☐Yes ☒No 
Author of Report: Fiona Scott  Date: 04/09/23 
Reviewing Officer: Tim Williams Date: 05/09/23 
Fergus Murray
Head of Development & Economic Growth 
Page 22

Page 23

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
REASONS FOR REFUSAL RELATIVE TO APPLICATION REF. NO. 23/01583/PP 
1. NPF4 Policy 9(b) states that proposals on greenfield sites will not be supported unless
the site has been allocated for development or the proposal is explicitly supported in
the adopted ‘Argyll and Bute Local Development Plan’ (LDP) 2015. 
In terms of the LDP, development of the site is not supported as the site is within an
adopted Open Space Protection Area (OSPA) where Policies LDP DM 8 and SG LDP
REC/COM 2 do not permit development unless it accords with five specific criteria. 
The OSPA in question is an area of land which is considered to provide visual amenity
functions rather than recreational functions and therefore the proposal does not satisfy
any of the criteria set out in SG LDP REC/COM 2. 
The OSPA has been designated to provide visual amenity functions by helping
preserve the open aspect on the seaward side of the A85 and with it, public views
across Loch Etive.  The OSPA forms part of the wider network of OSPAs alongside
Loch Etive that, together, provide the wider function of preserving the undeveloped
aspect of the shore side of the road.   
The development the subject of this application would introduce built development and
infrastructure into a greenfield site which has been designated as an OSPA for its
visual amenity functions which would result in an adverse environmental impact
eroding the open aspect of the site and the associated public views across it thereby
undermining the OSPA designation of the site contrary to the provisions of NPF4
Policy 9 as underpinned by LDP Policies LDP8 and SG LDP REC/COM 2 and Policy
81 of the emerging LDP2. 
It is not considered that the proposed development would constitute an appropriate
departure to National or Local Planning Policy. 
Page 23

Page 24

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
COMMITTEE REPORT
APPENDIX A – RELATIVE TO APPLICATION NUMBER:  21/01583/PP 
PLANNING LAND USE AND POLICY ASSESSMENT 
1. Introduction 
1.1. The proposal the subject of this application is seeking to secure planning permission for
the erection of a cafe with an incidental ‘drive-thru’ takeaway plus associated landscaping
including a viewpoint, seating, interpretive sign and play park. 
As a background to the current application, Members should note that planning
permission, reference 20/00038/PP, was granted to the Applicant in January 2021 for a
café on a site to the west of Dalrannoch, on the opposite side of the public road to the
current application. 
The Supporting Statement (SS) submitted with the application details that the proposal is
effectively for a replacement café on greenfield land located by the shore of Loch Etive. 
The SS details that, after careful consideration, the Applicant has decided that the location
of the proposed café approved under the aforementioned permission is not the best
proposal for Connel or its future business prospects.  Since permission was granted the
Applicant has obtained control of the site subject of the current application. 
The SS details that the Applicant is now of the opinion that this proposed site is a better
location for the proposed café venture.  As well as business reasons, the change in
location takes into account the feedback from neighbours and the Community Council
during the processing of the previous application in relation to access, parking, noise and
amenity issues. 
Officers do not accept that there is any good reason why the previous café permission
cannot be implemented and therefore rejects the claim that the current development is
somehow a ‘replacement’ café.  
2. Location of Development 
2.1. The application site is situated within the minor settlement of Connel comprising an area
of deliberately undeveloped and open land situated between the A85 Trunk Road and the
shores of Loch Etive. 
The site is bounded along its eastern boundary by Inverlusragan, a residential
dwellinghouse.  The site slopes down gently from the A85 to the shores of Loch Etive. 
3. Settlement Strategy 
3.1 In terms of the Settlement Strategy set out in the adopted LDP, the application site is
situated within the defined Minor Settlement of Connel where Policies LDP STRAT 1 and
LDP DM 1 might ordinarily be expected to give general encouragement to small scale
development on appropriate sites subject to compliance with other relevant policies and
Supplementary Guidance (SG). 
However, the site the subject of this application is within an Open Space Protection Area
(OSPA) where Policy SG LDP REC/COM 2 does not permit development on an OSPA
Page 24

Page 25

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
unless it satisfies one of the 5 criteria listed in the Policy and discussed below. 
The OSPA the subject of this planning application provides visual amenity functions rather
than recreation functions and accordingly it is not considered that the proposed
development satisfies any of the 5 criteria set out above and therefore the proposal is
considered to be contrary to the provisions of Policy SG LDP REC/COM 2. 
It is considered that there is sufficient alignment in the assessment of the proposal against
both provisions of the current LDP and the pLDP2 (as modified) that a decision can be
made under the current development plan without giving rise to fundamental conflict with
pLDP2 (as modified). 
In order to address the determining issues, the key considerations in this application are: 
3.1.1. Compliance with the Development Plan and other relevant planning policy
3.1.2. Any other material considerations. 
4. Proposal 
4.1. The application is seeking to secure planning permission for the erection of a cafe with
incidental ‘drive-thru’ takeaway plus associated landscaping including a viewpoint,
seating, interpretive sign and play park.   
The application proposes a contemporary designed, single storey flat roofed structure
sited along the western boundary of the site finished in natural stone cladding with a dark
grey coloured metal roofing.  The application shows the proposed café oriented with its
main elevation and external seating area north to take advantage of views out towards
Loch Etive.  The application shows the café dug into the sloping site to help minimise its
visual impact.   
The Supporting Statement (SS) submitted with the application details that the proposed
café will provide seating inside for 24 covers with a further 24 covers available on the
outdoor seating area.  The kitchen will be contained to the rear of the building along the
southern boundary of the site with the servery situated in the south western corner of the
building where an external servery hatch is proposed to serve drive through customers. 
The SS details that the proposed café will serve hot and cold food which will be for
consumption on the premises and also off the premises via the drive through facility
incorporated into the building.   
The proposed parking area is shown to the west of the proposed café building with a
turning circle adjacent to the building to facilitate the proposed ‘drive through’.  The play
park and view point are proposed to the north of the proposed café building between the
building and the shores of Loch Etive.   
An existing vehicular access is to be upgraded to serve the proposed development with
water supply via connection to the public water main and foul drainage by way of a new
private system due to the lack of public infrastructure within the vicinity of the site. 
5. Compliance with National Policy 
NPF4 was adopted on 13 February 2023 which now represents the main policy
background against which proposed developments are assessed underpinned by the
Policy and Supplementary Guidance contained within the adopted ‘Argyll and Bute Local
Development Plan’ 2015 (LDP).
Page 25

Page 26

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
The relevant NPF4 Policies are detailed below and grouped into topic areas. 
5.1. NPF4 Policy 1 – Tackling the Climate and Nature Crises 
NPF4 Policy 1 seeks to prioritise the climate and nature crises in all decisions; it requires
to be applied together with other policies in NPF4. 
Guidance from the Scottish Government advises that it is for the decision maker to
determine whether the significant weight to be applied tips the balance in favour for, or
against a proposal on the basis of its positive or negative contribution to climate and
nature crises.   
5.2. NPF4 Policy 2 – Climate, Mitigation and Adaption 
NPF4 Policy 2 seeks to ensure that new development proposals will be sited to minimise
lifecycle greenhouse gas emissions as far as possible, and that proposals will be sited
and designed to adapt to current and future risks from climate change. 
Guidance from the Scottish Government confirms that at present there is no single
accepted methodology for calculating and / or minimising emissions. The emphasis is on
minimising emissions as far as possible, rather than eliminating emissions. It is noted that
the provisions of the Settlement Strategy set out within Policy LDP DM 1 of the ‘Argyll and
Bute Local Development Plan’ 2015 (LDP) 1 promotes sustainable levels of growth by
steering significant development to our Main Towns and Settlements, rural growth is
supported through identification of Key Rural Settlements and safeguards more sensitive
and vulnerable areas within its various countryside designations. 
5.3. NPF4 Policy 3 – Biodiversity 
NPF4 Policy 3 seeks to protect biodiversity, reverse biodiversity loss and deliver positive
effects from development and strengthen nature networks. 
The application is accompanied by an Otter and Nesting Bird Survey Report undertaken
by Transtech Ltd dated 05/07/22.   
It should be noted that the Dr Garret Macfarlane and Barbara Macfarlane of Transtech
Ltd submitted expressions of support to the proposed development prior to being
contracted to undertake the Otter and Nesting Bird Survey Report sought by the Council’s
BDO. 
Third parties raised concerns regarding a potential conflict of interest in this regard and
accordingly the Planning Authority sought a comment from the Agent.  Barbara
Macfarlane of Transtech Ltd advised “As a company we are bound by a strict code of
conduct and it is our duty to report findings accurately. All our work is carried out to the
highest standard and we have never had our professional integrity questioned. 
As a qualified and experienced ecologist with a special interest in otters, including
membership of the International Union on the Conservation of Natures Otter Specialist
Group in recognition of my work to help conserve otters in Scotland and a holder of a
NatureScot licence in respect of otters, I will always do my utmost to ensure the protection
of the species and indeed any species, if it is apparent that it may be under threat. If it
has been suggested otherwise, this would be calling into question my professional
integrity. 
Page 26

Page 27

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
In summary, I do not believe that there is a conflict of interest in this case as our findings
strictly followed ecological survey protocol and we reported the facts entirely truthfully”. 
Notwithstanding the foregoing, the Agent commissioned a further Otter and Breeding Bird
Assessment prepared by JDC Ecology Limited dated December 2022 in support of the
proposed development. 
Both reports are summarised as follows. 
Transtech Ltd (July 2022) 
In summary, the report detailed that “An ecological field survey was undertaken to
establish the potential for the presence of otters within 250 m of the development site. It
was concluded that, while the habitat within the survey radius has moderate potential to
support otters, despite intensive searching no evidence of otter use, holts or resting
places was found. 
As such, it is unlikely that any work to the site will have any detrimental effect on otters.
Nor is it felt that the day-to-day operation of the café and playpark will impact upon any
otters which forage along the shoreline. Therefore, this work does not require a species
protection plan and no European Protected Species Licence in respect of otters need be
sought. 
However, given the known presence of foraging otters along the stretch of coastline
adjacent to the site, recommended mitigation measures and an emergency procedure for
otters is contained in the report. 
A targeted ground nesting bird survey was also carried out to establish the
presence/absence of ground nesting birds within the proposed development site, while
tree and scrub nesting birds were also considered. 
Several bird species were found to be nesting within the site or within 10 m of its boundary
and it is therefore recommended that no works, including site preparation and ground
clearance, be undertaken during the breeding bird season (March to August inclusive). 
It is recommended that a site walkover be conducted by a qualified ecologist, immediately
prior to works commencing and that a toolbox talk be given to site workers at that stage,
in order that all species are considered during the development stage of the proposal”. 
The report concluded that “given the evidence of the presence of nesting birds on the site,
it is the conclusion of this survey that there are nests which would be at risk of disturbance
if work was to be undertaken between March and August. Therefore, it is recommended
that works be undertaken only out with this period. 
Should this not be possible, checks will need to be made for nesting birds immediately
prior to works commencing and mitigation measures put in place should nests be
identified at that time. 
The report also set out opportunities for biodiversity gain within the proposed
development. 
JDC Ecology Ltd (December 2022) 
In summary, the report detailed that “While otters are present in the area, moving along
the adjacent burn corridor to and from the loch, there is no evidence for use of the Site by
Page 27

Page 28

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
otter and little suitability for this species to shelter on the Site due to proximity to human
disturbance. There were no holts or lying up places found on the surveyed stretch of the
adjacent burn or loch shores. 
Otters are not regarded as an issue for development of the Site, although a pre-start
check is recommended and a visual buffer between the adjacent burn and the west end
of the Site. 
The Site presents opportunity for a few bird species to nest although the number of
nesting pairs of any given species would be low given the size of the Site. If landscaping
provides some nesting opportunity in due course, and any vegetation removal either
avoids the nesting season or ensures that nesting birds are protected until nesting is
finished, breeding birds are not an issue in relation to any significant impact on local,
regional or national populations. 
While areas of Loch Etive are regarded as sensitive or notable for biodiversity reasons,
including waders and breeding seabirds, the area around Connel has no designations or
points of interest as noted on the Loch Etive Integrated Coastal Zone Management Plan.  
Birds that are known to use the Loch are less likely at or around the Site either for feeding
or nesting due to various factors mainly proximity disturbance and lack of suitable shore
habitat”. 
The report set out a number of recommendations for development of the site as follows. 
1. “Pre-start otter check to ensure that no holts or resting places have established within
licensable distance since the original survey.
2. Undertake vegetation clearance between October and February if possible. If
vegetation removal cannot be completed by the end of February, bird nest checks will
be needed from March to August. If a nest is found, or a bird building a nest, then this
area will need to be avoided until the nest or nests are no longer. Avoidance distance
would depend on species and location.
3. Design in bird nesting features around the Site whether on buildings or in landscaping,
and consider a visual buffer (shrub, tree etc) to the west end to buffer the burn (otter
passage).
4. All construction and operational lighting to be directed into the site, away from
adjacent habitats, and at as low-level spill and intensity as possible.
5. All landscaping should use native species or ornamentals that have a positive
biodiversity influence i.e. they are nectar, pollen or berry bearing as far as possible”. 
In her response to the Transtech report, the BDO noted the content of the report including
taking account of seasonality concerning ornithological interest along with advice and
mitigation for Otter and Bat species. The BDO concurred with the recommendations to
protect and enhance habitats and species such pre-start checks for bird species, the
provision of bat boxes and landscaping with native trees and shrubs. The BDO advised
that, if permission is granted, planting of Ash- Fraxinus excelsior should be avoided due
to Ash Die Back being present in the area and the difficulty in purchasing this species. 
The BDO noted that Japanese Knotweed is evident and accordingly requests that a
watching brief is undertaken for the site. 
In response to the JDC Ecology report, the BDO noted the contents, advising that the
survey was carried out on 1st December, outwith the optimum time of year, whereas the
original ecological report surveys were carried out over a 4 day period in early July.  The
BDO noted that the conclusions of the report are not unexpected and the
recommendations follow best practice including additional advice on the contribution
Page 28

Page 29

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
landscape planning (both planting and bird boxes) and implementation can make to
provide habitat for a variety of species.   
The BDO recommended that both ecological reports (July and January) are implemented
in combination should planning permission be granted. 
In the event that planning permission were to be granted, adequate and
proportionate measures for biodiversity enhancement and protection could be
delivered by planning condition as could compliance with the recommendations
and mitigation measures set out in both Otter and Bird Surveys, rendering the
proposal compliant with NPF4 Policy 3 as underpinned by LDP Policy LDP 3 and
SG LDP ENV 1 and Policy 73 of pLDP2. 
5.4. NPF4 Policy 4 – Natural Places 
NPF4 Policy 4 seeks to protect, restore and enhance natural assets making best use of
nature-based solutions. 
The proposed development is not within any designated European site of natural
environment conservation or protection, it is not located within a National Park, a National
Scenic Area a SSSI or RAMSAR site, or a National Nature Reserve. Neither is it located
within a local landscape area or a site designated as a local nature conservation site or
within an area identified as wild land.   
However, whilst the site is not within any of the aforementioned designations, it is
designated within both the adopted and emerging LDP as an OSPA and therefore it is
considered to have important landscape value which requires to be considered under
NPF4 Policy 4.   
The OSPA is detailed as providing visual amenity functions by helping preserve the open
aspect on the seaward side of the A85 and with it, public views across Loch Etive.  The
OSPA forms part of the wider network of OSPAs alongside Loch Etive that, together,
provide the wider function of preserving the undeveloped aspect of the shore side of the
road.  Development within this OSPA with the proposal subject of this planning application
would represent the piecemeal erosion of the wider OSPA network and would potentially
lead to pressure for development within other designated OSPAs either side of Loch
Etive, thereby undermining their functions. 
The development the subject of this application would introduce built development and
infrastructure into the OSPA which it is considered would erode the open aspect of the
site and the associated views across it. 
The OSPA is discussed in more detail at NPF4 Policy 9 below. 
The proposed development is considered to be contrary to the provisions of NPF4
Policy 4 as underpinned by LDP Policy 3. 
5.5. NPF4 Policy 9 – Brownfield, Vacant and Derelict Land and Empty Buildings 
NPF4 Policy 9 seeks to encourage, promote and facilitate the reuse of brownfield, vacant
and derelict land and empty buildings, and to help reduce the need for greenfield
development. 
Page 29

Page 30

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Part (b) of Policy 9 states that proposals on greenfield sites will not be supported unless
the site has been allocated for development or the proposal is explicitly supported by
policies in the LDP. 
The site the subject of this planning application is on a greenfield site designated in the
LDP as an OSPA and accordingly there is a direct conflict between the proposed
development and NPF4 Policy 9. 
In order to inform in the assessment of the proposal, comments were sought from the
Council’s DPT who advised that in terms of the adopted LDP Proposals Maps the site is
situated within an OSPA  which provides visual amenity functions by helping preserve the
open aspect on the seaward side of the A85 and with it, public views across Loch Etive. 
The DPT advise that Policy SG LDP REC/COM 2 sets out that the development of OSPAs
will not be permitted except where one of the five clauses set out in the policy are met, as
follows. 
(i) The proposed development is ancillary to the principal use of the site as a playing
field; Or; 
(ii) The proposed development involves a minor part of the playing field which would
not affect its use and potential for sport and training; Or, 
(iii) The playing field which would be lost would be replaced by a new playing field of
comparable or greater benefit for sport and in a location which is convenient for its
users, or by the upgrading of an existing playing field to provide a better quality
facility either within the same site or at another location which is convenient for its
users and which maintains or improves the overall playing capacity in the area; Or, 
(iv) A playing field and pitches strategy, prepared in consultation with SportScotland,
has demonstrated that there is a clear excess of sports pitches to meet current and
anticipated future demand in the area, and that the site could be developed without
detriment to the overall quality of provision; Or 
(v) In the case of valued recreational areas (public or private) it can be adequately
demonstrated that there would be no loss of amenity through either partial, or
complete development and that an alternative provision of equal benefit and
accessibility be made available. 
The DPT advised that they do not consider that the proposal satisfies any of the five
clauses and as such the proposal is considered to be contrary to Policy SG LDP REC/COM
2.  The DPT further stated that the OSPA designation has been carried forward into pLDP2
and has not been objected to. 
In light of the comments from the DPT, the Agent submitted a report on the OSPA in order
to demonstrate that the amenity value of the OSPA will not be affected by the proposed
development.  The report considers the statement provided by the DPT “This OSPA
provides visual amenity functions by helping preserve the open aspect on the seaward
side of the A85 and with it, views across Loch Etive”. 
The report considers the existing recreational use and visual amenity of the site and the
impact that the proposed development will have on the OSPA. 
In summary, the report concludes that the proposal will not impact on the visual amenity
value of the site in its role in ...helping preserve the open aspect on the seaward side of
the A85 and with it, views across Loch Etive.   
The report details that the application proposes the cafe building within the eastern part of
the site, adjacent to existing buildings to the west. The proposed cafe will be viewed in the
Page 30

Page 31

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
context of these existing buildings, and will not further impede views across the Loch more
than the existing condition. This is applicable in views both from the east and west along
the A85. Therefore, the report contends that the proposal does not impact on the visual
amenity of the site. 
The report states that the site is currently in agricultural use and not formally used as open
space. It is not open to the public and any use of the site for recreation is on an informal
basis. The proposal will provide a play area, viewing area and landscaped open space.
This will open the site to public use bringing an improvement in terms of formal open space
provision to the shoreline in the east of Connel. 
The report further states that the proposal also represents sustainable economic growth
that will provide four full-time jobs and three part-time jobs which will opportunities for local
residents which outweigh the site’s designation as an OSPA. 
The report concludes by stating that development of the site provides the opportunity to
provide a betterment to the existing condition in relation to the provision and protection of
open space and therefore accords with Policy SG LDP REC/COM 2. 
In their response to the report submitted by the Agent in regards to the OSPA, the DPT
advised that the additional submission assesses the proposal against clause ‘v’ of SG LDP
REC/COM 2 which relates to “valued recreational areas” and contends that it complies
with the clause and therefore the Policy.  However, the DPT advise that given that that the
land is considered to provide visual amenity functions rather than recreation functions, it
is considered that the proposal remains contrary to SG LDP REC/COM 2 as it does not
satisfy any of the 5 clauses. 
The DPT provided the following comments on the matters raised in the additional
information submitted by the agent as follows. 
“Improvements to public open space access and recreation
The development would potentially allow easier public access to the location of the
proposed view point area and interpretation panel than could currently be achieved.
However this area would still need to be accessed through the parking area and private
business curtilage of the café premises (and for those on foot, a potential crossing of the
A85 trunk road). Being set in close proximity to the café it needs to be considered to what
level the view point area would more function to serve the users of the premises rather
than the wider general public. It is also not clear what mechanisms are proposed to ensure
that the view point remains available for public use in perpetuity. There is also an existing
alternative viewpoint area situated within Connel to the west of the Connel Bridge and as
such the additional value of the proposal here should be considered. 
In terms of play space, the proposal would add to that provided by the existing facility at
Powell Place. However, from the information submitted it is not clear how many pieces of
equipment the proposed area would be able to accommodate once all siting requirements
for each piece had been met and as such how much it would add to the existing provision.
In assessing what weight this provision can be afforded it should also be considered to
what level the equipment would serve the customers of the café rather than the needs of
the local population. There is the potential for the equipment to reach capacity from café
customers during busier periods of operation. It should also be considered that access by
the local population would require users to cross the A85 trunk road. As with the view
point, it is not clear how the facility would remain available in perpetuity for the use by the
general public given that it would remain under the control of a private business (that
potentially could be owned by different proprietors over its lifetime). 
Page 31

Page 32

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Visual amenity
The sensitivity of the site can be seen through the outcome of 2009 Local Plan Enquiry
where the designation of the OSPA on the adjacent land to the west (and along with it, the
wider OSPA relating to coast side land at Connel) was confirmed by the Reporter. The
Reporter noted that due to its proximity to the Connel Bridge the Local Plan objection site
was one of the most valuable points where the A85 runs close to the water’s edge. Given
the proximity and similar characteristics, similar conclusions can be drawn regarding the
adjacent site subject to 21/01583/PP. 
The additional information submitted mostly assesses the impact of the café building itself
however the overall development of the site should be taken into account, this includes
the provision of a car park and turning area for up to 18 cars with what are significant areas
of hardstanding. Taken as a whole the proposal would erode the open aspect of the site
and the associated [public] views across it as these would be seen in the context of the
overall built development. 
The OSPA in this particular location helps preserve the open aspect of the land on the
shore side of the road and along with it the [public] views, however it must also be
recognised that it forms part of the wider network of OSPAs alongside Loch Etive that
together provide the wider function of preserving the undeveloped aspect of the shore side
of the road and the development of the OSPA would represent a piecemeal erosion of this.
It would also potentially lead to pressure for development within other designated Open
Space Protection Areas on either side of Loch Etive and potentially undermine their
functions. 
Economic benefits
The additional information provided also contends the economic benefit of four full time
and three part time jobs and whilst this would provide a benefit to the local economy this,
alongside the other justifications, need to be considered against the concerns set out
above”. 
Whilst the potential economic benefit arising from the proposed development is noted, it
is not considered that this is sufficient to set aside the detrimental impact that the proposed
development will have on the OSPA. 
The development the subject of this application would introduce built development
and infrastructure into a greenfield site which has been designated as an OSPA for
its visual amenity functions contrary to the provisions of NPF4 Policy 9 as
underpinned by LDP Policies 8 and SG LDP REC/COM 2 and Policy 81 of pLDP2. 
5.6. NPF4 Policy 12 – Zero Waste 
NPF4 Policy 12 seeks to encourage, promote and facilitate development that is consistent
with the waste hierarchy as defined within the policy document. 
The proposed development would generate waste when operational. Whilst the proposal
makes provision for three commercial refuse bins at the site, should permission be
granted, it would be considered appropriate to impose a condition to secure the details of
the proposed waste management at the site during the operational phase so as to accord
with the principles of sustainable waste management. 
In the event that planning permission was to be granted, a Waste Management
Statement for the proposed development could be secured by planning condition
rendering the proposal compliant with NPF4 Policy 12 as underpinned by LDP
Page 32

Page 33

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Policies LDP 10 and SG LDP SERV 5 and 5(b) and Policy 63 of pLDP2 should
permission be granted.   
5.7. NPF4 Policy 13 – Sustainable Transport 
NPF4 13 seeks to encourage, promote and facilitate developments that prioritise walking,
wheeling, cycling and public transport for everyday travel and reduce the need to travel
unsustainably. 
The development the subject of this planning application seeks to secure permission for
a café with drive through facility.  An existing agricultural access at the junction with the
A85 Trunk Road is to be upgraded to serve the proposed development.  This small scale
development is not considered to be a significant travel generating use or a proposal
where it is considered important to monitor travel patterns resulting from the development. 
In their first submission in November 2021, Transport Scotland (TS) deferred their
decision due to insufficient information to allow them to provide a detailed response to the
consultation.  As a result of the comments from TS ongoing discussions took place
between the Agent and TS to agree a suitable access regime to serve the proposed
development.  In January 2023 TS provided a finalised consultation response for the
proposed development raising no objection subject to conditions being imposed on the
grant of permission to secure the construction of the access and clearance of the visibility
splays at the junction with the A85 in accordance with the finalised scheme agreed
between the Agent and the TS. 
It should be noted, that during the processing of the application the Agent was advised
that the proposal conflicted with LDP Policy regarding development within an OSPA and
that the Planning Authority were unable to support the proposed development, details of
which are provided below.  However, the Agent sought the application to be held to allow
the access issues to be resolved, a request which was agreed with the Planning Authority. 
The Agent submitted a statement addressing the requirements of NPF4 Policy 13 as
follows. 
“Policy 13 criterion a) is not relevant to the proposed use of the site. Policy 13 criteria c),
d), e) and f) are also not considered relevant as the proposal as it is not a significant travel
generating use, nor is it promoting a low/no parking approach. 
“The proposal site is located adjacent to the existing pavement and carriageway (A85).
Access to the site via walking, wheeling and cycling can be achieved via the existing road
and footpath network. 
The site is accessible by public transport. The proposal is located within approximately
350m walking distance of the bus stops on Main Street, 450m walking distance of Connel
Ferry Railway Station, and 750m of the bus stops on the A85 in the west of Connel. The
site therefore has good access to the local public transport network. 
The proposal includes parking for disabled drivers and has non-slip surface finishes to
the café entrance and to the viewpoint and playpark, ensuring that the needs of diverse
groups using the site are met. 
It is therefore considered that the proposal accords with NPF 4 Policy 13 b) as far as is
necessary for the nature and scale of the proposed use. 
Page 33

Page 34

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
The proposal site is located adjacent to the existing pavement and carriageway (A85).
Public access to the site will be via the existing footway and vehicular junction from the
A85. The A85 is a trunk road. Transport Scotland has been consulted as part of the
Application and have raised no objections to the proposed junction”. 
In the event that planning permission was to be granted, a suitable access regime
and parking and turning area to serve the proposed development could be secured
by planning condition rendering the proposal compliant with NPF4 Policy 13 as
underpinned by LDP Policies LDP 11, SG LDP TRAN 2, SG LDP TRAN 4 and SG
LDP TRAN 6 and Policies 35, 36, 39 and 40. 
5.8. NPF4 Policy 14 – Design, Quality and Place 
NPF4 Policy 14 seeks to encourage, promote and facilitate well designed development
that makes successful places by taking a design-led approach and applying the ‘Place
Principle’. 
The design and finishing materials of the proposed café is considered to be acceptable,
relating to the development within the surrounding area where there is a wide variety of
design and finishing materials with no distinct architectural style evident. 
The application is accompanied by a statement addressing the six qualities of successful
places set out in NPF4 Policy 14 as follows. 
“Healthy: Supporting the prioritisation of women’s safety and improving physical and
mental health. Pleasant: Supporting attractive natural and built spaces. Connected:
Supporting well connected networks that make moving around easy and reduce car
dependency.  Distinctive: Supporting attention to detail of local architectural styles and
natural landscapes to be interpreted, literally or creatively, into designs to reinforce
identity. Sustainable: Supporting the efficient use of resources that will allow people to
live, play, work and stay in their area, ensuring climate resilience, and integrating nature
positive, biodiversity solutions. Adaptable: Supporting commitment to investing in the
long-term value of buildings, streets and spaces by allowing for flexibility so that they can
be changed quickly to accommodate different uses as well as maintained over time”. 
In this regard, the development the subject of this planning application is
considered to be in accordance with the broad aims of NPF4 Policy 14 as
underpinned by LDP Policies LDP 9 and SG LDP Sustainable Siting and Design
Principles and Policies 5, 9 and 10 of pLDP2. 
5.9. NPF4 Policy 18 – Infrastructure First 
NPF4 18 seeks to encourage, promote and facilitate an infrastructure first approach to
land use planning, which puts infrastructure considerations at the heart of placemaking. 
The development the subject of this planning application proposes connection to the
public water supply with drainage via installation of a private system due to the lack of
public drainage infrastructure within the vicinity of the site.  In their response to the
application Scottish Water raised no objection to the proposed development which would
be serviced by the Tullich Water Treatment Works but did however advise that further
investigations may be required once a formal application for connection is submitted to
them for consideration. 
The proposal aligns with NPF4 Policy 18 as underpinned by LDP Policy LDP DM 11
and SG LDP SERV 1 and Policies 05, 08 and 60 of pLDP2 which seek to ensure
Page 34

Page 35

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
suitable infrastructure is available to serve proposed developments and the current
proposal would raise no issue of conflict should permission be granted. 
5.10. NPF4 Policy 22 – Flood Risk and Water Management 
NPF4 Policy 22 seeks to strengthen resilience to flood risk and to ensure that water
resources are used efficiently and sustainably. 
As detailed above the development proposes connection to the public water supply to
which Scottish Water has not objected to.  With regards to the management of rain and
surface water at the site, this could be controlled thorough a condition to secure a suitable
sustainable drainage system for the site should permission be granted.   
The proposal aligns NPF4 Policy 22 as underpinned by LDP Policies LDP 10 and
SG LDP SERV 2 and Policy 61 of pLDP2 and the current proposal would raise no
issue of conflict should permission be granted. 
5.11. NPF4 Policy 23 – Health and Safety 
NPF4 Policy 23 seeks to protect people and places from environmental harm, mitigate
risks arising from safety hazards and encourage, promote and facilitate development that
improves health and wellbeing. 
Part (e) of Policy 30 states that development proposals that are likely to raise
unacceptable noise issues will not be supported with a requirement for a Noise Impact
Assessment where the nature of the proposal or its location suggests that significant
effects are likely. 
Accordingly, as the application site is in close proximity to a residential dwellinghouse, in
order to inform in the assessment of the application, a consultation was undertaken with
the Council’s EHS. 
In their response the EHS noted that the site layout show areas where pedestrians and
vehicles could come into conflict and requested a site traffic management plan with details
on engineering controls to prevent pedestrian and vehicle conflict or a redesign of the site
layout to address pedestrian and vehicle conflict.  The EHS further noted that commercial
catering premises of this nature require the installation of external extraction from their
kitchens to assist with removal and treatment of kitchen fumes and hot air.  Accordingly,
in terms of amenity of the area, the EHS advised that a noise limiting condition should be
imposed on any permission granted which would cover noise from the aforementioned
extraction systems and limit the impact which these would have on neighbouring noise
sensitive premises.  Finally, the EHS advised that a condition should be imposed on the
grant of permission regarding any proposed external lighting to ensure no adverse impact
on the amenity of the area. 
Subject to conditions to secure the requirements of the EHS, the current proposal
would raise no issue of conflict with NPF4 Policy 23 as underpinned by LDP Policy
SG LDP BAD 1 and pLDP2 Policy 14 should permission be granted. 
5.12. NPF4 Policy 28 – Retail 
NPF4 Policy 28 seeks to encourage, promote and facilitate retail investment to the most
sustainable locations that are most accessible by a range of sustainable transport modes. 
Page 35

Page 36

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Policy 28(d) gives support to retail uses within rural areas where their use is ancillary to
other uses; serve local needs; has no impact on nearby town centres; provide a service
throughout the year; and has no adverse impact on traffic generation and parking
provision.  In this regard, the site, being a rural extension of the defined settlement,
benefits from support under Policy 28(d) representing an appropriate form of ancillary
retail use serving the village of Connel. 
The proposal aligns NPF4 Policy 28  as underpinned by LDP Policies LDP 7 and SG
LDP RET 3 and Policy 46 of pLDP2 and the current proposal would raise no issue
of conflict should permission be granted. 
5.13. NPF4 Policy 29 – Rural Development 
NPF4 Policy 29 seeks to encourage rural economic activity, innovation and diversification
whilst ensuring that the distinctive character of the rural area and the service function of
small towns, natural assets and cultural heritage are safeguarded and enhanced. 
Part (a) of Policy 29 supports development proposals that contribute to the viability,
sustainability and diversity of rural communities and local rural economy with Part (b)
requiring development proposals in rural areas to be suitably scaled, sited and designed
to be in keeping with the character of the area taking into consideration how the
development will contribute towards local living and taking into account the transport
needs of the development as appropriate for the rural location.  Part (c) affords support
to development proposals in rural areas where they will (i) support local employment; (ii)
support and sustains existing communities and (iii) is suitable in terms of location, access,
siting, design and environmental impact. 
The SS submitted with the application details that the proposal will provide four full-time
jobs and three part-time jobs which it is hoped will be for local residents.  The proposed
development includes a viewpoint with an interpretative sign providing information about
the history of Connel and Loch Etive. The proposal also includes a playpark for use by
patrons of the proposed café and also locals. 
Whilst it has been demonstrated that the proposed development, through consideration
of the Policies detailed above, that the development is of a suitable scale and design,
taking account of transport needs, and providing some economic benefit, it is not
considered that these aspects of the proposed development would outweigh the negative
landscape impact that would arise from the proposed development within the designated
OSPA, which is discussed in more detail above. 
The proposal conflicts with NPF4 Policy 29 as underpinned by LDP Policy LDP 5
and Policy 22 of pLDP2.   
6. Public Representation 
6.1. At the time of report, representations have been received by the Planning Authority from
165 respondents in relation to this planning application. 44 respondents raise objection,
120 provide support and 1 submits a representation. 
Of the 120 expressions of support, 66 of these were submitted to the Applicant during a
Community Council Meeting held on 09/05/22 and then passed to the Planning Authority.   
In addition to the above, a screenshot from Facebook with names and ‘likes’ for the
development on the Applicant’s personal Facebook page has been submitted. 
Page 36

Page 37

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
The names and addresses of those contributing to the application are contained within
Appendix B of this report with full copies of the representations published on the planning
application file available to view via the Public Access section of the Council’s website. 
As detailed above, NPF4 Policy 9(b) states that proposals on greenfield sites will not be
supported unless the site has been allocated for development or the proposal is explicitly
supported in the LDP.   
The site has been designated as an OSPA in the adopted LDP and emerging pLDP2
where Policies SG LDP REC/COM 2 and Policy 81, respectively, do not permit
development on OSPAs except in the specific circumstances detailed above. 
The proposed development within the OSPA conflicts with both National and Local Policy
and therefore, in this instance, the proposal represents a clear policy refusal and it is not
considered that a hearing would add anything to the planning process. 
7. Conclusion 
7.1. Notwithstanding the assessment above that the design and finishes of the proposed café
building is acceptable, and that suitable access and infrastructure could be provided to
serve the proposed development, there is a clear conflict with NPF4 Policy 9 as
underpinned by LDP Policies LDP 9 and SG LDP REC/COM 2 and Policy 81 of pLDP2
which seek to protect OSPAs from built development. 
As detailed above, the OSPA in this location helps preserve the open aspect of the land
on the shore side of the road and along with it the public views.  It should be recognised
that the OSPA forms part of the wider network of OSPAs alongside Loch Etive that,
together, provide the wider function of preserving the undeveloped aspect of the shore
side of the road.  Development within this OSPA with the proposal subject of this planning
application would represent the piecemeal erosion of the wider OSPA network and would
potentially lead to pressure for development within other designated OSPAs either side
of Loch Etive, thereby undermining their functions. 
The development the subject of this application would introduce built development and
infrastructure into a greenfield site which has been designated as an OSPA for its visual
amenity functions as detailed above. 
The proposed development would result in an adverse environmental impact eroding the
open aspect of the site and the associated public views across it thereby undermining the
OSPA designation of the site. 
Whilst the potential economic benefit arising from the proposed development is noted, it
is not considered that this is sufficient to set aside the detrimental impact that the
proposed development will have on the have on the open landscape character of the area
and the primary function of the OSPA to protect this together with important public views
of Loch Etive which give the settlement of Connel much of its unique character.   
In light of the above it is recommended that planning permission be refused. 
Page 37

Page 38

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
COMMITTEE REPORT
APPENDIX B – RELATIVE TO APPLICATION NUMBER:  21/01583/PP 
LIST OF CONTRIBUTORS 
OBJECTION 
Contributor Name  Contributor Address  Date
Received 
Planning Objections Scotland 
(on behalf of Pat and Cheryl
Howe)
By e-mail only  10/07/23
Mykhailo Andreiev Inverlusragan, Connel, PA37 1PG 29/06/22 
Tetiana Andreieva Inverlusragan, Connel, PA37 1PG 29/06/22
John Hamilton  Glen Cole, Connel, PA37 1SS 29/06/22
M.R. Cooper Conbrio, Feochan Gardens, Oban, PA34 4NJ 29/06/22
Dr Paul Yoxon IOSF, 7 Black Park, Isle of Skye, IV49 9DE 15/06/22
Julian Hedditch 2 Cook Avenue, Chard, Somerset, TA20 2JR  04/06/22
Dr Allison Davies  Craignaha, Connel, PA37 1PH 04/06/22
Mr Andrew Davies Craignaha, Connel, PA37 1PH  04/06/22 
Mr Dylan Howe Inverlusragan, Connel, PA37 1PG 02/06/22
Ann MacKenzie  1 Grosvenor Crescent, Connel, PA37 1PQ  01/06/22
Miss H.A. Steele  By e-mail only  01/06/22
Mr Andrew Davies  Craignaha, Connel, PA37 1PH  
Neil Stuart  Achaleven House, Connel, PA37 1PF 01/06/22
Mr David Williams  Allt na Craobh, Connel, PA37 1PT 01/06/22
Elise Cleaver-Smith  Tyndrum Lodges  31/05/22
Graham Irving  Loch na Beithe Cottage, North Connel 31/05/22
Andrew Crabb 7 Dalnabeich, North Connel, PA37 1QY  31/05/22 
Miss Sheila Cawthera Loch na Beithe Cottage, North Connel, PA37
1QX 
31/05/22
Mrs Janet B. Finlayson Etive Cottage, Connel 30/05/22
Mary Buchanan  Strathaird, Connel, PA37 1PH 28/05/22
Mr Derek Wilkinson  Lora House Upper, Connel, PA37 1PA 29/05/22
Mrs Gillian Cowan  Ards Cottage, Connel, PA37 1PT  28/05/22
Chris Hill  Barnstone, Great Street, Norton sub Hamdon,
Somerset, TA14 6SJ
27/05/22
Lynn Ashforth  By e-mail only  26/05/22
Mr William Cowan Ards Cottage, Connel, PA37 1PT 26/05/22
Helen Anderson  Ard Beag, Connel, PA37 1PT  25/05/22
John Anderson  Ard Beag, Connel, PA37 1PT  25/05/22
James Stewart  Dunavon, Connel, PA37 1PJ 25/05/22
Wendy Barbour  19 Barossa Place, Perth, PH1 5HH 25/05/22
Katy Buchanan 12 Etive Park, North Connel, PA37 1SJ 25/05/22
David Gates   21 Titchfield Grange, Fareham, Hants, PO15
5AR 
23/05/22
Eric Barbour  45 Taylor Drive, Bramley, Hamphsire, R$G26
5XB 
22/05/22
Lynda Carlin 15 Creag Bhan Village, Oban, PA34 4BF  22/05/22
Fiona Woodhouse Achacha, Barcaldine, PA37 1SF 22/05/22
Marie Geekie  115 Byng Drive, Potters Bar, Herts, EN6 1UJ 22/05/22
Page 38

Page 39

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Rowan Howe Inverlusragan, Connel, PA37 1PG 23/05/22
Tom Howe  Inverlusragan, Connel, PA37 1PG 20/05/22
Anna-Maria Darzeva 2/2, 16 White Street, Glasgow, G11 5RP 20/05/22
Clare Mattison  By e-mail only  03/02/23 
Paul Mattison  By e-mail only  03/02/23
Ann Buchanan  By e-mail only  09/12/21 
05/01/22
19/05/22
23/05/22
27/10/22
22/02/23 
Mrs Cheryl Howe  Inverlusragan, Connel, PA37 1PG 07/12/2
28/04/23
13/05/22 
16/05/22
21/02/23
Mr Pat Howe  Inverlusragan, Connel, PA37 1PG 03/12/21
01/04/22
28/04/22
05/05/22
13/05/22
16/05/22
02/06/22
27/09/22
13/11/22 
21/02/23 
SUPPORT 
Contributor Name  Contributor Address  Date
Received 
Mrs Susan Baillie  The Neuk, Connel, PA37 1PJ 02/06/22
Barbara Macfarlane  Caerthann House, Grosvenor Crescent, Connel, PA37
1PQ
20/05/22
Dr Garret
Macfarlane 
Caerthann House, Grosvenor Crescent, Connel, PA37
1PQ 
20/05/22
Duncan Baird  Leven House, Achaleven, Connel, PA37 1PE  11/05/22
Ian MacVicar  Fasgadh, North Connel, PA37 1RA  21/04/23 
Christine Hill Mo Dhachaidh, Connel, PA37 1QP  21/04/23 
Steven Hill Mo Dhachaidh, Connel, PA37 1PO 21/04/23 
Daniel MacVicar  8 Park Road, Oban 21/04/23
Matt Kelly Catalina, Oban  21/04/23 
Sara Stephenson  Carnoch, Connel, PA37 1PH 21/04/23 
Lesley Stone  Eilean Froaich, North Connel, PA37 1QX 21/04/23 
John Stone  Eilean Froaich, North Connel, PA37 1QX 21/04/23
Shona MacVicar  Oaklea, Ledaig, PA37 1RX  21/04/23 
Graeme MacVicar Oaklea, Ledaig, PA37 1RX  21/04/23 
Isla Robertson  Old Burnside Flat, Main Street, Connel, PA37 1PA  21/04/23 
Lorne Sinclair Old Burnside Flat, Main Street, Connel, PA37 1PA 21/04/23
Yvonne Clark  Lailt, Connel, PA37 1PF 21/04/23 
Allan MacKay 15 Kerrera Terrace, Oban, PA34 5AT  21/04/23 
Page 39

Page 40

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Claire MacKay  15 Kerrera Terrace, Oban, PA34 5AT  21/04/22
Vivien Smith  15 Kerrera Terrace, Oban, PA34 5AT  21/04/22
Clare Hampson  49 Achlonan, Taynuilt, PA35 1JJ 21/04/22 
Janine Johnson Bruach, Taynuilt, PA35 1HX 21/04/22
Karina MacPherson  19 Camus Road, Dunbeg, PA37 1QD 21/04/22
Gemma Campbell  12 Cruachan Cottages, Taynuilt, PA35 1JG 21/04/22
Katie Smith Glenview, Kilvaree, Connel, PA37 1QN  21/04/22
Connor Kerr Carnoch, Connel, PA37 1PH 21/04/22
Daniel MacIntyre 179 Lightburn Road, Cambuslang, G72 8XW  21/04/22
Robert H. Smith  24 Creag Bhan Village, Oban, PA34 4BF 21/04/22
Georgia Mitchell Balnakeil, Kirk Road, Dunbeg, PA32 1PP 21/04/22
Veronica Speirs,  Corran Brae, Oban, PA34 5AJ 21/04/22
Lucy Stewart  17c Corran Brae, Oban, PA34 5AH 21/04/22
Nadia Holenadl  Flat 3, 10 Stevenson Street, Oban, PA34 5NA 21/04/22
Scott Sinclair  6 Ferryfield Road, Connel 21/04/22
Calum MacLachlain Morven House, Oban 21/04/22
Kenneth Ferguson Morar House, Connel, PA37 1PA 21/04/22
George McKnight  No address  21/04/22
Cloudie Forsyth  White Lodge, Glencruitten Road, Oban, PA34 4EW  21/04/22
Owner/Occupier
(unreadable) 
13d Corran Brae, Oban PA34 5AJ  21/04/22
Lee Gallacher 10b Corran Brae, Oban 21/04/22
Marie-Louise Korke 5a Burnbank Terrace, Breadalbane Street, Oban,
PA34 5PB
21/04/22
Gavin MacKinnon 120 George Street, Oban, PA34 5NT  21/04/22 
Kimberly Bryce  6 Ferryfield Road, Connel 21/04/22
Shona Vajk  14 Achaleven Road, Connel, PA37 1PE  21/04/22
Elaine Smith, Keppoch, Croft Road, Oban, PA34 5JN 21/04/22
Eilidh Johnston Seilachveaich, Oban, PA34 4JG 21/04/22
Jamie Warnock 61 MacKelvie Road, Oban 21/04/22 
Andrew MacMillan 10 Benmore View, North Connel, PA37 1SN 21/04/22
Ann Campbell Andarach, Connel, PA37 1PQ  21/04/22 
Archie Campbell  Andarach, Connel, PA37 1PQ  21/04/22
Fiona Ferguson  Morar House, Connel, PA37 1DA  21/04/22 
Graham Campbell  12a Glencruitten Drive, Oban, PA34 4EP 21/04/22
David Cameron  11b Longsdale Terrace, Oban  21/04/22 
Blair MacFarlane  Darach Lodge, Inverawe  21/04/22 
Helen MacVicar  Oaklea, Ledaig, PA34 1RX  21/04/22 
In addition to the above, details of support submitted during a Community Council Meeting on
09/05/22 containing 76 signatures has also been submitted as follows.  Those shown in bold
have provide separate support as detailed above. 
Contributor Name  Contributor Address 
Scott Sinclair  6 Ferryfield Road, Connel 
Caitlen Fowler  Rockfield Road, Oban 
Paul Addison  15/7 Sloan Street, Edinburgh, EH6 8PL
G. MacFarlane Darach Lodge, Inverawe 
C. MacFarlane  Beachglade, Soroba, Oban 
Duncan Baird Leven House, Connel, PA37 1PE 
Ally Dickie Meadow View, Kilmore, PA34 4XX 
Matthew Kelly 2 Stranraer Road, Oban 
Page 40

Page 41

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Lauren Stewart  Innishail, Bridge of Awe 
Colin MacCallum 2 Stranraer Road, Oban 
Lucy Stewart  Keepers Cottage, Benderloch, PA37 1WS 
Hamish Buchanan Cregan, Benderloch 
Karen Baird  Leven House, Achaleven, Connel 
Connor Kerr  Carnoch, Connel, PA37 1PH 
Gayle Dickie  Meadow View, Kilmore, PA34 4XX
A. Silvester Flat, Greenacre, Connel 
Laura Carmichael  42 Morvern Hill, Oban, PA34 4NS 
Hazel Silvester  2 Greenacre, Connel
Helen Campbell  9 Castle Road, Dunbeg, PA37 1QH 
Peter MacGregor  Knysna, Glenshellach Road, Oban 
Robert MacPherson Riverside Lodge, Barcaldine 
Nico Minco  The Caravan, Achaleven, Connel 
Donald MacLean Riverdale, Connel 
Sarah Sinclair  Abernethys, Connel, PA37 1RN 
Lucy Plummer  Burnside, Connel 
Iona Sinclair  Abernethys, Connel, PA37 1RN 
C. Munro  Ferndene, North Connel, PA37 1RA 
Neil Carmichael  42 Morvern Hill, Oban, PA34 4NS 
William (Illegible)  39 Marine Court 
Isla Robertson  Old Burnside Flat, Connel, PA37 1PA
Allan Wright 3 Deirdre, Connel 
Alice Addison  Macvicar Court, Dunbeg, PA37 1AA
Chris Shotton 15/7 Sloan Street, Edinburgh 
Mairi Wright  2 Deirdre, Connel, PA37 1PL
Wendy Addison  10 Lunga Road, Oban, PA34 4NP 
Sara Stephenson Carnoch, Connel, Oban, PA37 1PH 
Shaun Abernethys, Connel 
John Campbell  9 Castle Road, Dunbeg, PA37 1QH 
Veronica Speirs  17c Corran Brae, Oban, PA34 5AJ
Jack Harper  Connel
Anna-May Woodhouse  Culnadalloch Bungalow, Achnacloich Farm, Connel, PA37 1PR 
Paul Ferguson 16 Achaleven 
Fiona Ferguson Morar House, Connel, PA37 1PA
Chrissie Thomson  6 Millpark Terrace, Oban, PA34 4JH
Jamie MacMillan Main Street, Connel 
Iain Scott  6 Grosvenor Crescent 
Ragen Kelly 2 Stranraer Road, Oban, PA34 4EU 
Kirsteen Clark 2 Stranraer Road, Oban, PA34 4EU
Kenny (Illegible) 5 Dalrigh, Oban, PA34 
F. Lockhart  The Oaks, Polvinster Road, Oban 
Jonathan MacKenzie  Achnacloich Farm, Connel, PA37 1PR 
Kathleen Anderson  Dal-Eite, Connel, PA37 1PA 
Kevin McCubbin 14 Park Road, Oban, PA34 4GZ
Jean Clark  Cuiluaine, Connel, PA37 1PF 
Sileas Sinclair Rhonelin, North Connel, PA37 1QX
Suzie Smith  1 Buchanan Terrace, Oban
Yvonne Clark Lailt, Connel 
Millie (illegible) Lailt, Connel 
K. Bryce  6 Ferryfield Road, Connel 
Janice McGhee  Allt an Sith, Achnacloich, Connel, PA37 1PR 
Georgia Mitchell 7 Balnakeil, Kirk Road, Dunbeg, PA37 1PP
Page 41

Page 42

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 15.06.2023 
Jonathan Sayer  7 Balnakeil, Kirk Road, Dunbeg, PA37 1PP
Grace MacLean 10a Dalintart Drive, Oban, PA34 4EE
Amanda Hunter  Craigneuk, Benderloch, PA37 1RT 
Dr Garret MacFarlane  Caerthann House, Grosvenor Crescent, Connel, PA37 1PQ
Fiona MacFarlane  Darach Lodge, Taynuilt
Steve Hill  Mo Dhachaidh, Connel 
Christine Hill  Mo Dhachaidh, Connel 
Sarah Hill Mo Dhachaidh, Connel 
Archie Campbell  An Daroch, Connel 
Katie Sims  Dalrannoch Farm, Barcaldine 
Nigel Taylor  12 Powell Place, Connel, PA37 1AE 
Barbara MacFarlane  Caerthann House, Grosvernor Crescent, Connel, PA77
1PQ 
Lorne Campbell Sinclair  Old Burnside Flat, Main Street, Connel, PA37 1PA 
Anna McDonald  19 Creag (illegible) 
Ross Addison  MacVicar Court, Dunbeg, PA37 1AA 
In addition to the above, a screenshot from Facebook with names and ‘likes’ for the
development on the Applicant’s personal Facebook page has been submitted. 
REPRESENTATION 
Contributor Name  Contributor Address  Date
Received 
Oban and District Access
Panel 
By e-mail only  08/01/22 
Page 42

Page 43

Page 43

Page 44

This page is intentionally left blank

Page 45

Ref:  ABH1/2009 
ARGYLL AND BUTE COUNCIL 
PROCEDURE NOTE FOR USE AT 
HYBRID DISCRETIONARY HEARING 
HELD BY THE PLANNING, PROTECTIVE SERVICES & LICENSING COMMITTEE 
1. Hybrid meetings are those that will involve a physical location and facilitate
attendees joining virtually if they wish. 
2. The Executive Director with responsibility for Legal and Regulatory Support
will notify the applicant, all representees, supporters and objectors of the
Council’s decision to hold a Hearing and to indicate the date on which the
hearing will take place.  The hearing will proceed on that day, unless the
Council otherwise decides, whether or not some or all of the parties are
represented or not. Statutory consultees (including Community Councils) will
be invited to attend the meeting to provide an oral presentation on their written
submissions to the Committee, if they so wish. Details on how interested
parties can access the meeting will be referenced within the same notification. 
3. On receipt of the notification the applicant, all representees, including
supporters and objectors will be encouraged to appoint one or a small number
of spokespersons to present their views to concentrate on the matters of main
concern to them and to avoid repetition. Parties who wish to speak at the
meeting shall notify Argyll and Bute Council no less than 2 working Days
(excluding public holidays and weekends) prior to the start of the meeting. This
is to facilitate remote access (see note 1) and the good conduct of the
meeting.   
4. The Executive Director with responsibility for Legal and Regulatory Support
will give a minimum of 7 days’ notice of the date and time for the proposed
Hearing to all parties. 
5. The hearing will proceed in the following order and as follows. 
6. The Chair will introduce the Members of the Committee, confirm the parties
present who have indicated their wish to speak and outline the procedure
which will be followed. It is therefore imperative that those parties intending to
speak join the meeting at its commencement. 
7. The Executive Director with responsibility for Development and Economic
Growth’s representative will present their report and recommendations to the
Committee. 
Page 45

Page 46

Ref:  ABH1/2009
8. The applicant will be given an opportunity to present their case for approval of
the proposal and may include in their submission any relevant points made by
representees supporting the application or in relation to points contained in the
written representations of objectors. 
9. The consultees, supporters and objectors in that order (see note 1), will be
given the opportunity to state their case to the Committee.   
10. All parties to the proceedings will be given a period of time to state their case
(see note 3).  In exceptional circumstances and on good cause shown the
Committee may extend the time for a presentation by any of the parties at their
sole discretion. 
11. Members of the Committee only will have the opportunity to put questions to
the Executive Director with responsibility for Development and Economic
Growth’s representative, the applicant, the consultees, the supporters and the
objectors. 
12. At the conclusion of the question session the Executive Director with
responsibility for Development and Economic Growth’s representative, the
applicant, any consultees present, the supporters and the objectors (in that
order) will each be given an opportunity to comment on any particular
information given by any other party after they had made their original
submission and sum up their case. 
13. If at any stage it appears to the Chair that any of the parties is speaking for an
excessive length of time he/she will be entitled to invite them to conclude their
presentation forthwith. (see note 3) 
14. The Chair will ascertain from the parties present that they have had a
reasonable opportunity to state their case. 
15. The Committee will then debate the merits of the application and will reach a
decision on it.  No new information can be introduced after the Committee
begins to debate. 
16. The Chair or the Governance Officer on his/her behalf will announce the
decision. 
17. A summary of the proceedings will be recorded by the Committee Services
Officer. 
NOTE 
(1) If you wish to speak at the hearing you will require to notify the
Committee Services Officer no less than 2 working Days (excluding
public holidays and weekends) prior to the start of the meeting. This is
to facilitate remote access if required and the good conduct of the
meeting.
Page 46

Page 47

Ref:  ABH1/2009 
In the event that a party wishes to speak to a visual presentation, this
requires to be sent to Committee Services no less than 2 working days
(excluding public holidays and weekends) before the commencement of
the Hearing; this will not be shared with other parties prior to the
meeting but will ensure its availability for the commencement of the
Hearing. The Committee Services Officer will control the slides under
explicit instruction from the spokesperson(s), it would therefore be
helpful if the slides were individually numbered. It would also be helpful
if the file size of the presentations is kept to a minimum to mitigate
against any potential IT issues – guidance can be provided if required. 
If it is your intention to join the hearing to observe the proceedings,
please advise the Committee Services Officer no less than 2 working
Days (excluding public holidays and weekends) prior to the start of the
meeting to facilitate remote access if required.   
(2)   Councillors (other than those on the Committee) who have made
written representations and who wish to speak at the hearing will do so
under note 1 above according to their representations but will be heard
by the Committee individually. 
(3) Recognising the level of representation the following time periods have
been allocated to the parties involved in the Hearing. For the avoidance
of doubt the time allocated will be per party and will include for example
all supporters/objectors in the half hour slot except where additional
time is agreed by the Chair. 
The representative of the Executive Director with responsibility for
Development and Economic Growth – not more than half an hour
The Applicant - not more than half an hour. 
The Consultees - not more than half an hour. 
The Supporters - not more than half an hour. 
The Objectors - not more than half an hour.  
(4) The purpose of the meeting is to ensure that all relevant information is
before the Committee and this is best achieved when people with
similar views co-operate in making their submissions. 
(5) Everyone properly qualified as a representee recorded on the
application report who wishes to be given an opportunity to speak will
be given such opportunity subject to the requirements for notice herein.
(6) Should, for any reason, Members of the Committee who are joining
remotely lose connection or have any technical issues during the
meeting, they will be asked to contact the Governance or Committee
Support officer, if possible, by email or instant message. A short
adjournment may be taken to try and resolve the connection. If the
Members of the Committee are unable to re-join the meeting and a
quorum still exists then the meeting will continue to proceed. If a
Page 47

Page 48

Ref:  ABH1/2009
quorum does not exist the meeting will require to be adjourned. For the
avoidance of doubt Members of the Committee have to be present for
the whole hearing in order to take part in the decision. 
(7) Should, for any reason, participants joining the hearing remotely lose
connection or have any technical issues during the meeting, a short
adjournment may be taken to try and resolve the connection. In the
event the connection cannot be restored within a reasonable timeframe
consideration will be given to the continuation of the meeting. 
(8) Members of the Committee joining remotely will use the hands up
function to indicate to the Chair when they wish to speak to ask a
question or make a comment.  This function will be monitored by the
Chair and by governance staff in attendance.   
(9) Where a Councillor who is a member of the PPSL has made or wishes
to make a representation (on behalf of any party) during the meeting in
relation to the application under consideration, they should make their
position clear to the Chair and declare an interest. Having done so, they
may, at the appropriate time, make the relevant representation and
then must retire fully from the meeting room prior to deliberation of the
matter commencing.  A Councillor, not a member of the PPSL, may
make a representation (on behalf of any party) during the meeting in
relation to the application then must retire fully from the meeting room
prior to deliberation of the matter commencing. 
(10)  The Council has developed guidance for Councillors on the need to
compose a competent motion if they consider that they do not support
the recommendation from the Executive Director with responsibility for
Development and Economic Growth which is attached hereto. 
I:data/typing/virtual planning hearings/procedure note
Page 48

Page 49

Ref:  ABH1/2009
COMPETENT MOTIONS 
• Why is there a need for a competent motion? 
o Need to avoid challenge by “third party” to local authority decision which
may result in award of expenses and/or decision being overturned. 
o Challenges may arise from: judicial review, planning appeal, ombudsman
(maladministration) referral. Expenses may be awarded against
unsuccessful parties, or on the basis of one party acting in an unreasonable
manner, in appeal/review proceedings. 
• Member/Officer protocol for agreeing competent motion: 
o The process that should be followed should Members be minded to go
against an officer’s recommendation is set out below. 
• The key elements involved in formulating a competent motion: 
o It is preferable to have discussed the component parts of a competent
motion with the relevant Member in advance of the Committee (role of
professional officers).  This does not mean that a Member has prejudged
the matter but rather will reflect discussions on whether opinions contrary to
that of professional officers have a sound basis as material planning
considerations. 
o A motion should relate to material considerations only. 
o A motion must address the issue as to whether proposals are considered
consistent with Adopted Policy of justified as a departure to the
Development Plan.  Departure must be determined as being major or minor. 
o If a motion for approval is on the basis of being consistent with policy
reasoned justification for considering why it is consistent with policy contrary
to the Head of Development and Economic Growth’s recommendation must
be clearly stated and minuted. 
o If a motion for approval is on the basis of a departure from policy, reasoned
justification for that departure must be clearly stated and minuted. 
Consideration should be given to holding a PAN 41 Hearing (determined by
policy grounds for objection, how up to date development plan policies are,
volume and strength of representation/contention) 
o A motion should also address planning conditions and the need for a
Section 75 Agreement. 
o Advice from the Scottish Government as contained within Planning Circular
3/2013: Development management procedures on the definition of a
material planning consideration is attached herewith However, interested
parties should always seek their own advice on matters relating to legal or
Page 49

Page 50

Ref:  ABH1/2009
planning considerations as the Council cannot be held liable for any error or
omission in the said guidance.
Page 50

Page 51

Ref:  ABH1/2009
DEFINING A MATERIAL CONSIDERATION 
1. Legislation requires decisions on planning applications to be made in accordance
with the development plan (and, in the case of national developments, any
statement in the National Planning Framework made under section 3A (5) of the
1997 Act) unless material considerations indicate otherwise.  The House of Lord’s
judgement on City of Edinburgh Council v the Secretary of State for Scotland
(1998) provided the following interpretation.  If a proposal accords with the
development plan and there are no material considerations indicating that it should
be refused, permission should be granted.  If the proposal does not accord with
the development plan, it should be refused unless there are material
considerations indicating that it should be granted. 
2. The House of Lord’s judgement also set out the following approach to deciding an
application: 
- Identify any provisions of the development plan which are relevant to the
decision,
- Interpret them carefully, looking at the aims and objectives of the plan as well as
detailed wording of policies,
- Consider whether or not the proposal accords with the development plan.
- Identify and consider relevant material considerations for and against the
proposal, and
- Assess whether these considerations warrant a departure from the
development plan. 
3. There are two main tests in deciding whether a consideration is material and
relevant: 
- It should serve or be related to the purpose of planning.  It should therefore
relate to the development and use of land, and
- It should fairly and reasonably relate to the particular application. 
4. It is for the decision maker to decide if a consideration is material and to assess
both the weight to be attached to each material consideration and whether
individually or together they are sufficient to outweigh the development plan. 
Where development plan policies are not directly relevant to the development
proposal, material considerations will be of particular importance. 
5. The range of considerations which might be considered material in planning terms
is very wide and can only be determined in the context of each case.  Examples of
possible material considerations include: 
- Scottish Government policy, and UK Government policy on reserved matters
- The National Planning Framework
- Scottish planning policy, advice and circulars
- European policy
- A proposed strategic development plan, a proposed local development plan, or
proposed supplementary guidance
Page 51

Page 52

Ref:  ABH1/2009
- Guidance adopted by a Strategic Development Plan Authority or a planning
authority that is not supplementary guidance adopted under section 22(1) of the
1997 Act
- A National Park Plan
- The National Waste Management Plan
- Community plans
- The Environmental impact of the proposal
- The design of the proposed development and its relationship to its surroundings
- Access, provision of infrastructure and planning history of the site
- Views of statutory and other consultees
- Legitimate public concern or support expressed on relevant planning matters 
6. The planning system operates in the long term public interest.  It does not exist to
protect the interests of one person or business against the activities of another.  In
distinguishing between public and private interest, the basic question is whether
the proposal would unacceptably affect the amenity and existing use of land and
buildings which ought to be protected in the public interest, not whether owners or
occupiers of neighbouring or other existing properties would experience financial
or other loss from a particular development.
Page 52