North Lanarkshire Council
Report
Enterprise and Fair Work Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  LN/PH  Date 12/05/23 
City Deal Update Report 
Programme of Work PO21 
From  Pamela Humphries, Chief Officer (Place) 
E-mail NobleLy@northlan.gov.uk Telephone  Lyndsay Noble
07970016256 
Executive Summary 
The North Lanarkshire City Deal Programme Update report seeks to inform the Enterprise
and Fair Work Committee of the current status of North Lanarkshire City Deal Infrastructure
subprojects.     
Recommendations 
It is recommended that the Committee: 
1)    Note the status and recent progress of North Lanarkshire City Deal infrastructure
subprojects.  
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (5) Grow and improve the sustainability and diversity of North
Lanarkshire's economy

Page 2

1. Background 
1.1 The Glasgow City Region (GCR) City Deal is an agreement between the UK and
Scottish Governments and the eight GCR Local Authorities, with the sole focus of
creating additional economic growth.  The 20-year GCR Deal was accepted by GCR
Council Leaders on 20 August 2014 and incorporated: 
• implementing a £1.13bn Infrastructure Fund to improve the regional transport
network, regenerate sites for economic use and improve public transport
provision;
• supporting growth in the life sciences sector;
• helping small and medium enterprises to grow and develop;
• establishing programmes to support the unemployed; and 
• piloting new ways of boosting the incomes of low wage employees.   
1.2 The City Deal programme for North Lanarkshire as part of the Infrastructure Fund
comprises the following projects:
• A8/M8 Corridor Access Improvements
o Strategic Active Travel 
o Orchard farm Roundabout
• Glenboig Link Road (complete)
• Pan-Lan Orbital Transport Corridor
o East Airdrie Link Road
o Ravenscraig Access Infrastructure
o Motherwell Town Centre Transport Interchange 
2. Report 
2.1 Motherwell Town Centre Transport Interchange (MTCTI) 
2.1.1  The redevelopment of Motherwell Rail Station by ScotRail’s appointed contractor,
Balfour Beatty, is now substantially complete.  The station has undergone
transformational change with the improvements providing a high quality experience for
rail passengers and railway employees at Motherwell. Transport and public realm
investment at Muir Street, led by the council, is substantially complete. These works
complement and support the major investment in Motherwell Rail Station, provide a
new access road to the station and taxi rank, expanded bus stop capacity on Muir Street
and public realm improvements.   
2.1.2 Together, the station investment and Muir Street improvements have created a
transport hub in the heart of Motherwell. This provides an improved gateway into
Motherwell and the Glasgow City Region by public transport and is a key part of
regeneration plans for Motherwell town centre. The Partnership between Scotrail, NLC,
SPT and Transport Scotland in delivering the joint project has been a success and is
now driving forward related active travel projects to connect Motherwell Rail Station
and surrounding communities to leisure facilities, employment and training
opportunities at Strathclyde Country Park, Braidhurst Industrial Estate and
Ravenscraig. 
2.1.3  Both the Motherwell Rail Station and Muir Street contracts were scheduled to be
complete by July 2022. However, primarily due to unforeseen structural issues with the
station building, completion of the station contract experienced a number of delays.
Interfaces with the station works, drainage and public utility issues within the Muir Street

Page 3

works area, also impacted on completion of the Muir Street works. Both contracts will
therefore be completed in May 2023. Throughout the project, joint communication
group meetings have been held to ensure that communication updates are coordinated. 
Planning is currently underway for a joint opening event in the summer. 
2.1.4  Community Benefit outcome delivery by both Balfour Beatty and ScotRail is now
complete. A number of skills, employability and training initiatives and community
projects have been delivered through community benefit commitments within the Muir
Street contract and through a funding agreement with ScotRail.  ScotRail have also
engaged in an initiative to promote opportunities within the rail industry. 
2.2 Ravenscraig Access Infrastructure 
2.2.1 The Ravenscraig Access Infrastructure project comprises three projects:
• a new road connection between Motherwell and Ravenscraig from Airbles
Road, passing under the West Coast Main Line railway, and on to the Regional
Sports Facility 
• completing the dualling of Airbles Road between Airbles Farm Road and
Hamilton Road and improving facilities pedestrians and cyclists  
• upgrading the A723 for three kilometres from the New Craig Road junction at
Ravenscraig to the M8 at Holytown to create a dual carriageway and shared
footway/cycleway 
2.2.2   Significant progress has been made by Story Contracting, with the construction of the
new bridge structure. Following its pre-construction during 2022 and early 2023, the
bridge was successfully installed in the railway during the 10-day track closure at the
start of April with the works completed and the railway re-opened on time. 
2.2.3 Story will now complete the works for Network Rail during May and June before
commencing the advance preparatory road works for the new dual carriageway within
the bridge structure on behalf of the Council. These works simplify the contractual
relationship with Network Rail and the Council during our main works and ensure
progress continues on site. 
2.2.4    In preparation for the next phase of works, the project team: 
• have issued the Invitation to Tender (ITT) for the Construction of the dual
carriageway into Ravenscraig.  The outcome of the procurement will be
reported to committee in due course.  It is intended that the contractor will be
appointed in the autumn following City Deal and Committee approval with
advance notices and preparation for works commencing before the end of 2023
and works getting underway in early 2024 and 
• commissioned the diversion of some public utilities in advance of the main
works. 
2.2.5 Related to this part of the project, works have progressed well for the relocation of the
Evans Halshaw Ford car dealership with the demolition and clearance completed and
construction works now commenced for the replacement showroom on the nearby
former Taggarts site. The new dealership will occupy the front part of the site with the
rear part of the site being made available for residential development, potentially as
part of the council’s new supply programme.

Page 4

2.2.6 For the upgrading of the A723 the project team has completed the refinement of the
detailed proposals for the dualling of the A723 from Ravenscraig to the M8 at Holytown.
Information will be provided to the communities and the planning authority during May
and June, to confirm the proposed improvements to the earlier planning permission.
Following this the team will commence the preparation of the specifications and
documents for procurement during 2024. 
2.3  East Airdrie Link Road 
2.3.1  East Airdrie Link Road will provide a new strategic link between the M8 and south
Cumbernauld.   
2.3.2 As previously reported, a section of the preferred route has been realigned to
accommodate the proposed Monklands Hospital replacement project.  The project
team continue to liaise with NHS Lanarkshire to ensure coordination, secure
efficiencies and to maximise benefits. 
2.3.3 In line with previous approvals, the procurement for professional services for the
development of the preliminary design for the road, preparation of the planning
application and the collation of the outline Business Case has commenced. The ITT for
Stage 3 has been issued and it is intended to award the services contract in August
2023.  Approval for this contract award will be sought from the Depute Chief Executive
and the outcome of this procurement activity will be brought back to Committee in line
with General Contract Standing Orders. 
2.3.4  As reported to Committee, the programme for the development and delivery of the
EALR has been reviewed.  This is to accommodate complex design and planning
requirements and to allow for technical approvals and implementation of the land
acquisition strategy.  It is intended that the Outline Business Case is brought to
committee in February 2024 and subject to approval, is submitted to the GCR Cabinet
to secure further funding. 
2.4 Orchard Farm Roundabout 
2.4.1 The ‘A8/M8 Corridor Access Improvements’ Outline Business Case (OBC) including
the Orchard Farm Roundabout was approved by the GCR Cabinet on 30 August 2022. 
As reported, the scope of the Orchard Farm Roundabout project comprises a financial
contribution of £2m to the developer for the construction of the junction on the A8. 
2.4.2  The Orchard Farm Roundabout is a new junction on the A8 All Purpose Distributor
Road and critically supports the development of the Mossend International Rail Freight
Park (MIRP) and provides important access to a number of development sites to the
north of the A8/M8.   
2.4.3  The proposed Full Business Case (FBC) for the new junction will be underpinned by a
funding agreement between the council and the developer/s and will establish funding
arrangements, obligations and key milestones.  The remainder of the costs and any
associated delivery risks relating to the delivery of the infrastructure will be met by the
developer/s.  The infrastructure will form part of the strategic road network and will fall
under the responsibility of Transport Scotland.   
2.4.4   It is proposed to submit the Full Business case (FBC) for the Orchard Farm Roundabout
for approval to the GCR Chief Executive’s Group in August 2023, subject to sufficient
procurement progress by the developers.  The FBC will report on the procurement
outcome of the new junction and associated works and is the final stage in the funding

Page 5

approvals to allow for contract award and the delivery of the infrastructure to progress. 
Agreement will be sought from Committee to submit the FBC to the GCR Chief
Executives Group for approval.  This would allow for works to commence in late autumn
2023, with the intention that the works would be complete by late 2024. 
2.5 A8/M8 Corridor Strategic Active Travel 
2.5.1 The provision of Strategic Active Travel Links, connecting Eurocentral/Maxim Office
Park/Newhouse and Mossend to surrounding local communities and local rail stations
was approved by GCR Cabinet on 30 August as the new preferred option for the
Eurocentral sub-project.   
2.5.2 The routes identified are to the south of Eurocentral between Bellshill Rail Station/town
centre and the M8 cycle route at North Road; Bellshill town centre, Mossend and
Holytown, connecting into Eurocentral from Holytown and between Holytown and
Newhouse. To the north of Eurocentral, a route has also been identified from Whifflet
rail station to the M8 cycle route at Shawhead. These routes are designated as
Strategic Network Routes within the North Lanarkshire Active Travel Strategy. 
2.5.3 In total, it is aimed to deliver 10km of shared use walking and cycling routes with City
Deal investment. The routes link with other planned active travel route improvements
as part of the Ravenscraig Infrastructure Access and East Airdrie Link Road projects
and with other projects being developed by the Infrastructure and Transportation team.
There are also opportunities to seek match funding from other external funding sources
to expand the scope of the project to connect more communities to employment
opportunities. 
2.5.4 Due to the scale of the project, a phased approach will be taken to design and delivery.
It is planned to appoint consultants to progress feasibility and design work for the first
phase of the project in Q1 2023. This will focus on the route into Eurocentral from
Holytown and between Holytown and Newhouse. Design work will be progressed over
2023 with it then intended, subject to Committee approval, to submit a sub-project Full
Business Case in Summer 2024 and commence work on site in Autumn 2024. 
3. Measures of success 
3.1 As the second largest Local Authority within the GCR, North Lanarkshire’s residents
and businesses will directly benefit from the City Deal through: 
• creation of 2,000 new workplace jobs, representing a 1.6% uplift in the future jobs
growth forecast for North Lanarkshire;
• a significant share of some 15,000 temporary construction jobs anticipated to be
generated by the development of the Infrastructure Investment Fund projects –
construction being a predominant local employment sector; 
• estimated 9.2% of North Lanarkshire working age residents having heightened
access to employment opportunities within the wider GCR area;
• additional tender opportunities as a result of GCR City Deal investment for North
Lanarkshire Business and SME’s;
• community benefits derived from all GCR City Deal contracts awarded over
£50,000; and
• a proportionate share of the £2.2bn per annum Gross Value Added (GVA) increase
in the GCR area over the lifetime of City Deal, equivalent to 4% uplift in the region.

Page 6

4. Supporting documentation 
4.1  No supporting document presented. 
Pamela Humphries 
Chief Officer (Place) 
5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The City Deal Cabinet has agreed that Inclusive Growth is to be fully embedded
within the GCR City Deal programme delivery and that it is also committed to
supporting the delivery of the Fairer Scotland Action Plan.  Future NLC subproject
OBC/FBC development will be scrutinised to ensure it meets the duties of the
Fairer Scotland Action Plan.   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The North Lanarkshire Council City Deal Programme approved funding allocation
across the 3 headline projects is as: 
• A8/M8 Corridor Access Improvements £6,478,521 
• Glenboig Link Road (complete)  £6,223,205
• Pan-Lan Orbital Transport Corridor  £215,696,493 
The City Deal funding comprises funding from the GCR City Deal Infrastructure
Fund (£148,956,293) and North Lanarkshire Council (£79,441,926). The financial
implications of the City Deal Programme are incorporated within the Council’s

Page 7

Long-term Financial Plan and to date budgetary implications have been approved
by the Policy and Strategy Committee.

Page 8

5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☒ No ☐ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The City Deal Team work closely with Legal Services on all sub projects focusing
on land acquisition and CPO, procurement and contract preparation and
management, funding agreements and any other related matters. 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
All infrastructure projects developed by the Council as part of the GCR City Deal will
be subject to relevant environmental and sustainability appraisal and as part of
subsequent planning application approvals and procurement.

Page 9

Furthermore, to adhere with HM Treasury Greenbook best practice, each iteration of
project business case seeking GCR City Deal funding will include a review of the
sustainability considerations, this will include carbon management, involving
categorisation, assessment and mitigation. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The City Deal programme and the delivery of the projects will continue to be
promoted through Corporate Communications and the Glasgow City Region’s
Communications team.   
Specific to Muir Street Improvements, a joint communications group with Scotrail,
Transport Scotland and North Lanarkshire Council has been set up to coordinate
communication and promote the Motherwell Station redevelopment and the City
Deal Muir Street improvements.   
In terms of East Airdrie Link Road, a joint communication plan will be developed
with NHS Lanarkshire and North Lanarkshire Council to coordinate communication,
stakeholder engagement and promote the projects as they develop.   
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
A key risk for the City Deal Programme is the current global economic climate and
its short and long term impacts on the delivery of the city deal projects.  This risk is
becoming a live issue for the Programme and will be assessed and recorded within
the City Deal Issues Register. This is not unique to City Deal and the approach to
this risk and issue management will be carried out in conjunction with Finance and
the Glasgow City Region Project Management Office.   
Risk management of North Lanarkshire’s City Deal activity is incorporated within
the council’s City Deal programme risk register which is reviewed by the City Deal
Manager and reported to the council’s City Deal Board.  The City Deal risks are
also integrated in the Planning and Regeneration Service Risk Register.  Each City
Deal sub project has a detail risk register and is managed by the Project Manager. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.