North Lanarkshire Council
Report
Enterprise and Fair Work Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  LN/PH  Date 17/02/23 
City Deal Update Report 
Programme of Work PO21 
From  Pamela Humphries, Chief Officer of Place 
E-mail NobleLy@northlan.gov.uk Telephone  Lyndsay Noble
07970016256 
Executive Summary 
The North Lanarkshire City Deal Programme Update report seeks to inform the Enterprise
and Fair Work Committee of the current status of North Lanarkshire City Deal Infrastructure
subprojects.     
Recommendations 
It is recommended that the Committee: 
1)    Note the status and recent progress of North Lanarkshire City Deal infrastructure
subprojects.  
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (5) Grow and improve the sustainability and diversity of North
Lanarkshire's economy

Page 2

1. Background 
1.1 The Glasgow City Region (GCR) City Deal is an agreement between the UK and
Scottish Governments and the eight GCR Local Authorities, with the sole focus of
creating additional economic growth.  The 20-year GCR Deal was accepted by GCR
Council Leaders on 20 August 2014 and incorporated: 
• implementing a £1.13bn Infrastructure Fund to improve the regional transport
network, regenerate sites for economic use and improve public transport
provision;
• supporting growth in the life sciences sector;
• helping small and medium enterprises to grow and develop;
• establishing programmes to support the unemployed; and 
• piloting new ways of boosting the incomes of low wage employees.   
1.2 The City Deal programme for North Lanarkshire as part of the Infrastructure Fund
comprises the following projects:
• A8/M8 Corridor Access Improvements
o Strategic Active Travel 
o Orchard farm Roundabout
• Glenboig Link Road (complete)
• Pan-Lan Orbital Transport Corridor
o East Airdrie Link Road
o Ravenscraig Access Infrastructure
o Motherwell Town Centre Transport Interchange 
2. Report 
2.1 Motherwell Town Centre Transport Interchange (MTCTI) 
2.1.1  The redevelopment of Motherwell Rail Station by ScotRail’s appointed contractor,
Balfour Beatty, is due to complete in March 2023. Over recent months, work has
focussed on the new extensions to the station building, new roof structure and glazing.
Access to the station and platforms for passengers has continued to be maintained
throughout the improvements. The temporary ticket office in the station forecourt has
been removed and relocated into the new retail unit space, until the new travel shop is
complete. 
2.1.2 Committee will be aware that Balfour Beatty has also been appointed by the council to
undertake the improvement works to Muir Street comprising expansion of the bus stop;
provision of a new access road to Motherwell Rail Station with new taxi rank and public
realm improvements. 
2.1.3 Both the Motherwell Rail Station and Muir Street contracts were scheduled to be
complete by July 2022.  Due to delays primarily in delivering the station contract, the
station works are now expected to be complete in March 2023. Through joint working
with Balfour Beatty and ScotRail, it is anticipated that the Muir Street works will be
completed ahead of the station works, during February 2023. Due to the need to ensure
safe pedestrian access between the expanded bus stop and Motherwell rail station,
reopening of the bus stop occurred at the end of January. SPT have been notified and
have communicated this timescale to bus operators.

Page 3

2.1.4 Some road closures of short duration have been put in place to date for the Muir Street
works to carry out some activities safely. For each road closure, advance notification is
provided to local businesses and the public (through signage on site, website updates
and other communication channels). Road closures have been arranged at weekends
to minimise disruption to the town centre. The majority of work requiring road closures
is now complete, however a further closure may be needed to install the new pedestrian
crossing from the east side of Muir Street to the bus stop area. 
2.1.5 Officers within the Enterprise Projects Team are working with the communication team
at Balfour Beatty and the Motherwell Rail Station Communications Group to ensure that
communications are coordinated across both contracts. 
2.1.6  Community Benefit outcome delivery by the contractor is progressing well. To date, a
number of skills, employability and training initiatives and community project have been
delivered. In recent months, a site visit has been held with local school children; local
groups have been supported via a volunteering day undertaken with Balfour Beatty
staff assisting to lay paving slabs and install a shed and foodbank voucher support and
materials have been donated to a local school. The provision of benches for a local
church and group will be completed in early January. 
2.1 Ravenscraig Access Infrastructure 
2.2.1 The Ravenscraig Access Infrastructure project comprises three projects:
• a new road connection between Motherwell and Ravenscraig from Airbles
Road, passing under the West Coast Main Line railway, and on to the Regional
Sports Facility 
• completing the dualling of Airbles Road between Airbles Farm Road and
Hamilton Road and improving facilities pedestrians and cyclists  
• upgrading the A723 for three kilometres from the New Craig Road junction at
Ravenscraig to the M8 at Holytown to create a dual carriageway and shared
footway/cycleway 
2.2.2    The project will be delivered in phases, beginning with the new rail bridge for the future
connection between Motherwell and Ravenscraig. 
2.2.3   Significant progress has been made by Story Contracting, with the construction of the
new bridge structure complete in December and ahead of programme. Whilst not
shortening the overall programme, this provides greater programme contingency for
the works that are required to take place over the winter months. Works during early
2023 ahead of the track closure will focus on preparations for works to the track and
associated reequipment.
2.2.4    In preparation for the next 3 phases of works, the project team: 
• have completed the Invitation to Tender (ITT) for the Construction of the dual
carriageway into Ravenscraig ready for publication during March.  The outcome
of the procurement will be reported to committee in due course.  It is intended
that the works will start in the autumn following City Deal and Committee
approval, and once the bridge is fully complete.  The delay to this tender has
been to allow design of additional works to improve safety for road users and
Non-Motorised Users at the existing roundabout by the Regional Sports Facility.

Page 4

• competed negotiations with the bridge contractor for advance preparatory works
for the new dual carriageway to both simplify the contractual relationship with
Network Rail and the Council during our works and to mitigate the impact of
time lost to the additional design work noted above
• negotiated to remove the one objection to the Compulsory Purchase Order to
allow the construction of the dual carriageway into Ravenscraig and continue to
seek to negotiate with all other owners and occupiers for the remaining land
required to deliver all parts of the Ravenscraig Infrastructure Access project.
Acquisitions are reported to, and approved as required by, Finance and
Resources Committee; and 
• have progressed refining and developing the detailed proposals for the dualling
of the A723 from Ravenscraig to the M8 at Holytown. 
2.2.5 Related to this project, a planning application has been approved, land acquired and
site clearance works commenced on the alternative location for the Evans Halshaw
Ford car dealership. The dealership will relocate to part of the nearby former Taggarts
site which has laid vacant for some time. This will allow the existing Evans Halshaw
Ford car dealership to be retained within Motherwell whist facilitating the new road
connection between Motherwell and Ravenscraig. The new dealership will occupy the
front part of the site with the rear part of the site being made available for residential
development, potentially as part of the council’s new supply programme. 
2.3  East Airdrie Link Road 
2.3.1  East Airdrie Link Road will provide a new strategic link between the M8 and south
Cumbernauld.  Following a detailed Stage 2 option appraisal, and a further review of
the emerging option, a preferred route has now been agreed.  Feedback from an earlier
Stage 2 public consultation was reviewed and additional options were assessed at the
northern section of the proposed link road.  Further public consultation has taken place
from 28 November to 23 January (8 weeks) on the preferred route and on the
environmental report as part of the Strategic Environmental Appraisal.  The feedback
and comments from this consultation will be full considered moving into Stage 3 as the
specimen design and planning application is developed.   
2.3.2 As previously reported, a section of the preferred route has been realigned to
accommodate the proposed Monklands Hospital replacement project.  The project
team continue to liaise with NHS Lanarkshire to ensure coordination, secure
efficiencies and to maximise benefits. 
2.3.3 In line with previous approvals, the procurement for professional services for the
development of the specimen design for the road, preparation of the planning
application and the collation of the outline Business Case has commenced. It is
intended that the ITT will be issued in March 2023 and awarded in August 2023, subject
to committee approval.  The outcome of this procurement activity will be brought back
to Committee in line with General Contract Standing Orders.   
2.3.4 The programme for the development and delivery of the EALR has been reviewed both
technically and following changes to the Monklands Replacement Hospital programme,
whereby the proposed hospital at Wester Moffat is anticipated be opened during 2031. 
The EALR programme now anticipates that the link road will be constructed between
2028 and 2030.  This is to accommodate complex design and planning requirements,
technical and business case approvals, land acquisition (both through voluntary and a
proposed compulsory purchase order) and critically to align with the Monklands
Hospital programme.  The revised programme will ensure that both projects are aligned
to minimise risk around funding approvals, technical consents and physical

Page 5

construction interface.  It is intended that the outline business case will be submitted to
Committee and GCR Cabinet in Q4 23/24 to secure the city deal funding for the
significant development work prior to full business case in Q3 27/28.   
2.4 Orchard Farm Roundabout 
2.4.1 The ‘A8/M8 Corridor Access Improvements’ Outline Business Case (OBC) including
the Orchard Farm Roundabout was approved by the GCR Cabinet on 30 August 2022. 
As reported, the scope of the Orchard Farm Roundabout project comprises a financial
contribution of £2m to the developer for the construction of the junction on the A8. 
2.4.2  The Orchard Farm Roundabout is a new junction on the A8 All Purpose Distributor
Road and critically supports the development of the Mossend International Rail Freight
Park (MIRP) and provides important access to a number of development sites to the
north of the A8/M8.   
2.4.3  MIRP is a low carbon rail-based infrastructure project with a significant co-located
logistic park development. Peter D Stirling Limited (railfreight terminal
operator/landowner) and Mount Park (new landowner) seek to develop the Mossend
Railfreight Terminal into a European scale railfreight terminal and distribution park with
all-electric facilities. MIRP is one of very few sites within the UK that can offer integrated
multi-modal logistics of this scale, quality and economic value. The MIRP supported
the bid for the Clyde Green Freeports. 
2.4.4  The proposed Full Business Case (FBC) for the new junction will be underpinned by a
funding agreement between the council and the developer/s and will establish funding
arrangements, obligations and key milestones.  The remainder of the costs and any
associated delivery risks relating to the delivery of the infrastructure will be met by the
developer/s.  The infrastructure will form part of the strategic road network and will fall
under the responsibility of Transport Scotland.   
2.4.5   It is proposed to submit the Full Business case (FBC) for the Orchard Farm Roundabout
for approval to the GCR Chief Executive’s Group in August 2023.  The FBC will report
on the procurement of the new Junction and associated works and is the final stage in
the funding approvals to allow for contract award and the delivery of the infrastructure
to progress.  Agreement will be sought from Committee to submit the FBC to the GCR
Chief Executives Group for approval.  This would allow for works to commence in late
autumn 2023, with the intention that the works would be complete in October 2024. 
2.5 A8/M8 Corridor Strategic Active Travel 
2.5.1 The provision of Strategic Active Travel Links, connecting Eurocentral/Maxim Office
Park/Newhouse and Mossend to surrounding local communities and local rail stations
was approved by GCR Cabinet on 30 August as the new preferred option for the
Eurocentral sub-project.   
2.5.2 The routes identified are to the south of Eurocentral between Bellshill Rail Station/town
centre and the M8 cycle route at North Road; Bellshill town centre, Mossend and
Holytown, connecting into Eurocentral from Holytown and between Holytown and
Newhouse. To the north of Eurocentral, a route has also been identified from Whifflet
rail station to the M8 cycle route at Shawhead. These routes are designated as
Strategic Network Routes within the North Lanarkshire Active Travel Strategy.

Page 6

2.5.3 In total, it is aimed to deliver 10km of shared use walking and cycling routes with City
Deal investment. The routes link with other planned active travel route improvements
as part of the Ravenscraig Infrastructure Access and East Airdrie Link Road projects
and with other projects being developed by the Infrastructure and Transportation
Service. There are also opportunities to seek match funding from other external funding
sources to expand the scope of the project to connect more communities to
employment opportunities. 
2.5.4 Further feasibility and design work has been taking place to develop the active travel
routes. It is planned to appoint consultants to progress detailed design work in early
spring 2023. It is then intended, subject to Committee approval, to submit the sub-
project Full Business Case in Spring 2024 and commence work on site in Summer
2024. 
3. Measures of success 
3.1 As the second largest Local Authority within the GCR, North Lanarkshire’s residents
and businesses will directly benefit from the City Deal through: 
• creation of 2,000 new workplace jobs, representing a 1.6% uplift in the future jobs
growth forecast for North Lanarkshire;
• a significant share of some 15,000 temporary construction jobs anticipated to be
generated by the development of the Infrastructure Investment Fund projects –
construction being a predominant local employment sector; 
• estimated 9.2% of North Lanarkshire working age residents having heightened
access to employment opportunities within the wider GCR area;
• additional tender opportunities as a result of GCR City Deal investment for North
Lanarkshire Business and SME’s;
• community benefits derived from all GCR City Deal contracts awarded over
£50,000; and
• a proportionate share of the £2.2bn per annum Gross Value Added (GVA) increase
in the GCR area over the lifetime of City Deal, equivalent to 4% uplift in the region. 
4. Supporting documentation  
4.1  No supporting document presented. 
Pamela Humphries 
Chief Officer of Place

Page 7

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The City Deal Cabinet has agreed that Inclusive Growth is to be fully embedded
within the GCR City Deal programme delivery and that it is also committed to
supporting the delivery of the Fairer Scotland Action Plan.  Future NLC subproject
OBC/FBC development will be scrutinised to ensure it meets the duties of the
Fairer Scotland Action Plan.   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The North Lanarkshire Council City Deal Programme approved funding allocation
across the 3 headline projects is as: 
• A8/M8 Corridor Access Improvements £6,478,521 
• Glenboig Link Road (complete)  £6,223,205
• Pan-Lan Orbital Transport Corridor  £224,696,493 
The City Deal funding comprises funding from the GCR City Deal Infrastructure
Fund (£148,956,293) and North Lanarkshire Council (£88,441,926). The financial
implications of the City Deal Programme are incorporated within the Council’s
Long-term Financial Plan and to date budgetary implications have been approved
by the Policy and Strategy Committee. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☒ No ☐

Page 8

If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The City Deal Team work closely with Legal Services on all sub projects focusing
on land acquisition and CPO, procurement and contract preparation and
management, funding agreements and any other related matters. 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
All infrastructure projects developed by the Council as part of the GCR City Deal will
be subject to relevant environmental and sustainability appraisal and as part of
subsequent planning application approvals and procurement.   
Furthermore, to adhere with HM Treasury Greenbook best practice, each iteration of
project business case seeking GCR City Deal funding will include a review of the
sustainability considerations, this will include carbon management, involving
categorisation, assessment and mitigation. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?

Page 9

The City Deal programme and the delivery of the projects will continue to be
promoted through Corporate Communications and the Glasgow City Region’s
Communications team.   
Specific to Muir Street Improvements, a joint communications group with Scotrail,
Transport Scotland and North Lanarkshire Council has been set up to coordinate
communication and promote the Motherwell Station redevelopment and the City
Deal Muir Street improvements.   
In terms of East Airdrie Link Road, a joint communication plan will be developed
with NHS Lanarkshire and North Lanarkshire Council to coordinate communication,
stakeholder engagement and promote the projects as they develop.   
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
A key risk for the City Deal Programme is the current global economic climate and
its short and long term impacts on the delivery of the city deal projects.  This risk is
becoming a live issue for the Programme and will be assessed and recorded within
the City Deal Issues Register. This is not unique to City Deal and the approach to
this risk and issue management will be carried out in conjunction with Finance and
the Glasgow City Region Project Management Office.   
Risk management of North Lanarkshire’s City Deal activity is incorporated within
the council’s City Deal programme risk register which is reviewed by the City Deal
Manager and reported to the council’s City Deal Board.  The City Deal risks are
also integrated in the Planning and Regeneration Service Risk Register.  Each City
Deal sub project has a detail risk register and is managed by the Project Manager.   
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.