Democracy Spraffa

Agenda pack

North Lanarkshire Council · 17 February 2023
Back to Enterprise and Fair Work Committee — 17 February 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Our Ref:
Your Ref:
Contact:
Tel:
Fax:
E-Mail:
Date:
Clare Louise McDonald
01698302190
mcdonaldcl@northlan.gov.uk
8 Feb 2023    
Members of the
Enterprise and Fair Work Committee
Chief Executive’s Office
Archie Aitken
Chief Officer of Legal & Democratic
Civic Centre, Windmillhill Street
Motherwell ML1 1AB
DX 571701, Motherwell 2
www.northlanarkshire.gov.uk   
Notice is given that a Meeting of the ENTERPRISE AND FAIR WORK COMMITTEE is to be held
within the Council Chamber, Civic Centre, Motherwell  on Friday, 17 February 2023 at 10:00 am
which you are requested to attend.
The agenda of business is attached.
Chief Officer of Legal and Democratic
Members :    Councillors: A Bustard, D Crichton, P Di Mascio, K Docherty, K Duffy, H Dunbar,
J Hume, A Khan, J Leckie, G Lennon, J Logue, A Magowan, A Masterton, F McNally,
M McPake, L Nolan, P Patton, D Robb, G Robinson, A Smith, K Stevenson,
R Sullivan, J Toner, S Watson, C Williams.
Page 1 of 79

Page 2

Page 2 of 79

Page 3

AGENDA
(1) Declarations of Interest in terms of the Ethical Standards in Public Life Etc. (Scotland) Act
2000
OPERATIONAL
(2) Economic Regeneration Delivery Plan 2023-2028 (page 5 - 38)
Submit report by the Chief Officer of Place seeking approval of the refreshed Economic
Regeneration Delivery Plan (ERDP) 2023-2028 and associated annual ERDP Action Plan for
2023/24 (copy herewith)
(3) City Deal Update Report (page 39 - 48)
Submit report by the Chief Officer of Place detailing the current status and recent progress of
North Lanarkshire City Deal Infrastructure sub projects (copy herewith)
(4) Employability Update (page 49 - 54)
Submit report by the Chief Officer of Education (South) providing an update on the outcome of
the extension to the current EU funded Employability Programme and providing information on
the transition to the UK Shared Prosperity Fund and Labour Market in North Lanarkshire (copy
herewith)
(5) Vacant and Derelict Land Fund - Re-allocation of Funding (page 55 - 60)
Submit report by the Chief Officer of Place seeking approval of the re-allocation of Vacant and
Derelict Land Fund monies (copy herewith)
(6) External Funding - Update (page 61 - 68)
Submit report by the Chief Officer of Place providing an update on significant recent external
funding activity (copy herewith)
CONTRACT
(7) Contract Award - Braidhurst Industrial Estate Design Team (page 69 - 79)
Submit report by the Chief Officer of Place advising of action taken to award a contract for
Braidhurst Industrial Estate Design Team to Collective Architecture Limited (copy herewith)
Page 3 of 79

Page 4

Page 4 of 79

Page 5

North Lanarkshire Council
Report
Enterprise and Fair Work Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref    PH/DG Date 17/02/23 
Programme of Work PO18.1 - Economic Regeneration Delivery
Plan 2023-2028 
From  Pamela Humphries, Chief Officer of Place  
E-mail Greerd@northlan.gov.uk Telephone
David Greer, Growth
Programme Manager:
07583059816 
Executive Summary 
The purpose of this report is to seek approval for North Lanarkshire’s refreshed Economic
Regeneration Delivery Plan (ERDP) 2023-2028 and associated annual ERDP Action Plan
for 2023/24. 
The ERDP is a high-level economic development framework which is aligned to the
composite capital programme and delivers on the first priority of The Plan for North
Lanarkshire – improving economic outcomes and opportunities for all. 
The 2023-28 refreshed ERDP replaces the previous ERDP which was approved by
Enterprise and Growth Committee in August 2019 and covered the timeframe 2019-2023. 
As with the previous ERDP, the refreshed ERDP aims to ensure that the council continues
to focus on investment in physical regeneration across four inter-related themes: 
• developing housing that promotes improved quality of life and creates a better place
to live;
• reshaping our town centres to ensure that these provide modern and attractive
centres that meet the needs of our communities;
• improving our business and industrial infrastructure, creating opportunities for
investment and for companies to start-up or relocate here; and
• continuing to improve our connectivity and develop new opportunities by
transforming our road, rail and digital infrastructure 
A 2023/24 ERDP Action Plan has also been developed and is included within the
supporting documents of this report. As throughout the delivery of the 2019-23 ERDP, this
action plan will be subject to annual monitoring, review and update. 
AGENDA ITEM 2
Page 5 of 79

Page 6

1. Background 
1.1 In August 2019, the Enterprise and Growth Committee approved North Lanarkshire’s
Economic Regeneration Delivery Plan (ERDP) covering the period 2019-2023. 
1.2 The ERDP was developed based on significant consultation and engagement with
stakeholders including elected members, North Lanarkshire residents, businesses,
council officers, and key partner organisations and was developed to help co-ordinate
the physical regeneration of North Lanarkshire, ultimately aimed at growing the North
Lanarkshire economy and improving economic opportunities and outcomes for all. 
1.3 Since 2019, an annual ERDP Action Plan has been approved by committee each year
detailing key milestones and targets for the financial year ahead. In 2022 a wider
Economic Performance Framework was also approved by committee which details
progress against short, medium and longer-term economic targets. 
1.4 Since the inception of the ERDP, several significant milestones have been achieved
through the delivery of the New Supply, Growth and City Deal programmes. This has
been previously communicated to committee in annual progress updates. Another
performance report will be presented to committee in Cycle 3 2023, detailing progress
against the 2022/23 ERDP Action Plan and wider Economic Performance Framework. 
1.5 As the initial ERDP only covered the period between 2019-23, a refresh has been
necessary to ensure that this plan remains fit for purpose. 
Recommendations
It is recommended that committee: 
1. Approve the refreshed ERDP (2023-2028) and Action Plan (2023/24) which are
attached to this report as appendices. 
2. Note that the approved ERDP and Action Plan will be subject to final review and
consultation. 
3. Note that an annual performance report detailing progress against the 2022/23
Action Plan and wider ERDP Performance Framework will be presented to
committee in Cycle 3 2023. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (1) Ensure a housing mix that supports social inclusion and
economic growth 
(2) Refocus our town centres and communities to be multi-
functional connected places which maximise social, economic, and
environmental opportunities 
(3) Maximise the use of our marketable land and assets through
improved development in business and industrial infrastructure 
(4) Market and promote North Lanarkshire as the place to live,
learn, work, invest, and visit 
(5) Grow and improve the sustainability and diversity of North
Lanarkshire's economy
Page 6 of 79

Page 7

1.6 Due to the significant scale of ambition in North Lanarkshire, many of the existing ERDP
themes focus on longer-term programmes of work which will continue well beyond
2023. Moreover, internal stakeholder engagement has concluded that the revised
ERDP (2023-2028) should be a light touch refresh as we continue to progress our key
investments in housing, town centres, business and industry, roads, active travel and
digital infrastructure. 
2. Report 
2.1 Economic Regeneration Delivery Plan 2023-2028 
2.1.1 The refreshed ERDP continues to focus on the same four key inter-related themes as
the 2019-23 plan: 
• developing housing that promotes improved quality of life and creates a better place
to live;
• reshaping our town centres to ensure that these provide modern and attractive
centres that meet the needs of our communities;
• improving our business and industrial infrastructure, creating opportunities for
investment and for companies to start-up or relocate here; and
• continuing to improve our connectivity and develop new opportunities by
transforming our road, rail and digital infrastructure 
2.1.2 Our work in these areas will also be underpinned by several key policies and strategies
ultimately aimed at improving economic opportunities and outcomes for those who live,
learn and work in North Lanarkshire. These include: 
• North Lanarkshire’s Equality Strategy;
• The Workforce for the Future Strategy (and future updates);
• The Place, The Vision;
• Climate Plan, Action on Climate Together 2030; and
• The council’s Digital and IT Strategy.
2.2  Housing
2.2.1 Housing plays a key role in the health and wellbeing of North Lanarkshire’s people and
economy. Increasing housing supply and choice across all tenures will attract
investment, create jobs and reduce inequality.
2.2.2 To help deliver the homes that North Lanarkshire needs to grow over the next five
years, the revised ERDP recommends that the council will: 
• continue to focus investment in the council’s affordable housing stock to make sure
that the target of 5,000 new council homes for North Lanarkshire is reached by
2035;
• continue to support the delivery of the affordable housing programme including
intermediate tenures such as mid-market rent;
• enable private sector housing development to support the regeneration of strategic
sites such as Ravenscraig. 
Page 7 of 79

Page 8

2.3 Town Centres
2.3.1 Town Centres are vital for our sense of community and place and their attractiveness
and quality is strongly interlinked with the image and success of North Lanarkshire. 
2.3.2 North Lanarkshire has eight recognised town centres: Airdrie, Bellshill, Coatbridge,
Cumbernauld, Kilsyth, Motherwell, Shotts and Wishaw. Each town has its own
distinctive features and distinct mix of cultural, leisure and retail facilities.
2.3.3 To help reshape our town centres to ensure that these provide modern and attractive
centres that meet the needs of our communities over the next five years, the refreshed
ERDP recommends that the council will: 
• establish and commence delivery of town action plans for all eight town centres
(aligned with our approved town visions), agreeing short, medium and long-term
investment plans for each;
• continue to prioritise funding and secure external investment for the regeneration
of our town centres;
• review how the council can be more effective in addressing failing buildings in our
town centres, including potential use of Compulsory Purchase Orders where
required. 
2.4 Business and Industry 
2.4.1 North Lanarkshire has one of Scotland’s fastest growing economies and has huge
potential for future growth. To realise this potential, we need to enable our people and
businesses to thrive by continuing to invest in skills, in business and industrial space
and in marketing North Lanarkshire as the place to invest and work.
2.4.2 To help improve our business and industrial infrastructure and attract new investment
and employment, the refreshed ERDP will be supported through the delivery of a new
Business and Industry Strategy for North Lanarkshire. 
2.4.3 The revised ERDP also recommends that the council and our arms-length external
organisations (ALEOs) will focus on activities over the next five years which: 
• promotes a mix of development across our motorway corridors and accessible
business locations to support the development of our foundational economy as well
a high-end growth;
• continues to support enabling investment which brings our vacant and derelict land
and brownfield sites into commercial use;
• improves how we record and respond to enquiries from businesses to provide a co-
ordinated approach across relevant council services to help attract, retain and
expand businesses and employment opportunities; 
• builds upon work which supports innovation and skill development though the
development of sectoral learning academies; and
• supports investment, via our ALEOs, that will continue to improve, modernise and
expand commercial stock availability across North Lanarkshire. 
2.4.4 Added to these activities, it is also intended to undertake a full review of sites allocated
for business and industry within the current Local Development Plan (LDP) to inform
the preparation of the next LDP and ensure that we have suitable sites available to
attract and retain businesses and employment opportunities. 
Page 8 of 79

Page 9

2.5 Connectivity
2.5.1 Our existing roads, railways and digital infrastructure provide gateways to inclusive
growth and prosperity but there remains a need to better connect North Lanarkshire to
markets and employment opportunities by improving our strategic infrastructure.
2.5.2 To help improve our connectivity, the refreshed ERDP recommends that over the next
five years, the council will:
• continue to deliver the City Deal programme;
• ensure that inclusive economic growth remains at the heart of opportunity to support
affordable and accessible transport systems (via the Local Transport Strategy due
to be launched in 2024); 
• invest in the delivery of the council’s Active Travel Strategy to ensure a
comprehensive connection of active travel routes to key places across North
Lanarkshire;
• support the delivery of Electric Vehicle Charging infrastructure across North
Lanarkshire; and
• work with the council’s digital partner to install and invest in infrastructure that helps
create one of the best and most affordable/accessible digital provisions in the UK. 
2.6 ERDP Action Plan 
2.6.1 An action plan for 2023/24 has been devised to help progress delivery of the priorities
set out in the refreshed ERDP. This and future ERDP action plans will continue to be
subject to annual review, update and committee approval. This will allow for changes
to be made in response to any changing or arising challenges and opportunities facing
the North Lanarkshire economy at any given time. 
2.6.2 Whilst the ERDP 2023-2028 will remain a longer-term high-level framework for the
North Lanarkshire economy, the 2023/24 Action Plan outlines key targets and
objectives for the year ahead. 
2.6.3 The action plan will be delivered through the ERDP Steering Group (which comprises
key officers from contributing services across the council) and monitored through the
ERDP Board (which comprises senior officers across key services). 
2.7 Consultation and Briefings 
2.7.1 Following approval by committee, the finalised ERDP refresh will be subject to final
review (and potential minor amendment) by relevant services and wider stakeholders.
Once complete, an online briefing session on the finalised 2023-28 will be organised
for all members. 
3. Measures of success 
3.1  The annual ERDP Action Plan contains various targets, the delivery of such being key
to the success of the refreshed ERDP. 
3.2  A robust Economic Performance Framework has now also been established and
contains a series of key performance indicators, with short, medium, and long-term
targets attached as the operational measures of success. The next end-year
performance report is due to be presented to committee in Cycle 3 2023. This will
include progress against the 2022/23 ERDP Action Plan as previously approved by
committee.
Page 9 of 79

Page 10

4. Supporting documentation 
Appendix 1 Economic Regeneration Delivery Plan (2023-2028) 
Appendix 2 ERDP Action Plan 2023/24 
Pamela Humphries
Chief Officer of Place 
Page 10 of 79

Page 11

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes x No ☐ 
If Yes, please provide a brief summary of the impact?  
The primary aim of the refreshed ERDP 2023-28 is to support inclusive economic
growth and opportunities for all. In doing so it aims to support investment in
creating a more equitable and fairer place for residents of North Lanarkshire to live. 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The 2019-23 ERDP was funded through a mixture and a range of external funding
sources. It is envisaged that the 2023-28 ERDP will largely be funded in a similar
manner subject to available resources. 
An investment plan will be developed for the 2023-28 ERDP and opportunity will be
sought to use available funding for enabling works to try to help secure private
sector investment for proposals delivered through the ERDP. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Page 11 of 79

Page 12

Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The ERDP remains one of the council’s key strategies and will be promoted
accordingly through Corporate Comms and digital platforms. 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
Risks are recorded and managed within Corporate Risk Register. Key risk is failure
to deliver on ERDP and its objectives of helping co-ordinate physical and economic
regeneration activity across North Lanarkshire, increasing economic output and
helping address social and economic inequality. This would result in the loss of
economic and social benefits to residents and business across North Lanarkshire
and significant reputational damage to the Council given the widespread public
nature of the programme. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒
Page 12 of 79

Page 13

If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
Page 13 of 79

Page 14

Appendix 1
Economic
Regeneration
Delivery Plan 
2023-2028 
Page 14 of 79

Page 15

Foreword 
North Lanarkshire’s first Economic Regeneration Delivery Plan (ERDP) was launched in September
2019. The main focus of the plan was to help secure and direct capital investment in order to promote
inclusive economic growth, ensure community well-being and create a more prosperous place for
residents of North Lanarkshire to live. 
North Lanarkshire continues to be one of the fastest growing economies in Scotland. With our central
location, developing markets across construction, biotechnology, rail transportation and logistics,
North Lanarkshire has continued to re-profile its economy over the last decade. However, recent years
have thrown up many challenges with the economic impact of Brexit, Covid-19 and more lately the
cost-of-living crisis. 
To address this, North Lanarkshire needs to ensure that we are the best placed location in Scotland to
encourage investment, ensure that we have the homes and places where people want to live and the
digital and physical connectivity that attracts business and new opportunity. 
North Lanarkshire’s refreshed ERDP 2023-2028 builds upon the activity that the council and its
partners have been putting in place over the last 4 years. North Lanarkshire has consistently met
targets set out in previous annual ERDP Action Plans. However, the ERDP cannot be delivered as a
discrete strategy. It needs to be aligned with wider strategies for regeneration, digital, local housing
and investment. 
It needs to support our plans for net zero carbon emissions and environmental sustainability as well
as growth, whilst ensuring our communities have access to fair and equitable economic and
employment opportunities. 
Ayeshah Khan 
Convener, Enterprise and Fair Work Committee 
Page 15 of 79

Page 16

Introduction 
The North Lanarkshire ERDP sets out a high-level framework for improving economic opportunities
and outcomes for all. The 2019-23 ERDP (which the 2023-28 ERDP replaces) aimed to do this by trying
to direct capital investment towards four key goals: 
• developing housing that promotes improved quality of life and creates a better place to live;
• reshaping our town centres to ensure that these provide modern and attractive centres that
meet the needs of our communities;
• improving our business and industrial infrastructure, creating opportunities for investment
and for companies to start-up and relocate here; and
• continuing to improve our connectivity and develop new opportunities by transforming our
road, rail and digital infrastructure 
This framework was designed to focus activities and resources towards large-scale regeneration and
investment projects throughout North Lanarkshire. Nevertheless, since 2020, these goals to a certain
extent have been affected by wider economic issues and the global coronavirus pandemic. 
However, due to the significant scale of the planned investment and ambition in North Lanarkshire,
the previous ERDP themes were very focused on longer-term programmes of work which will continue
well beyond 2023. As such, internal stakeholder engagement has concluded that the refreshed ERDP
(2023-2028) should be a light touch refresh of the previous plan. This will allow the council to continue
to progress our key investments in housing, town centres, business and industry, roads, active travel
and digital infrastructure, whilst also at the same time being able to better reflect the current economic
environment. 
The core themes of the 2023-2028 ERDP will also continue to be underpinned by several principles
including skills, net zero and digital connectivity. This will be done by ensuring that the ERDP is aligned
to a number of key North Lanarkshire policies, strategies and plans which are already in place: 
• NLC’s Equality Strategy
• Workforce for the Future Strategy
• The Place, The Vision
• Climate Plan, Action on Climate Together 2030
• Digital and IT Strategy  
The 2023-2028 ERDP will continue to be supported by annual ERDP Action Plans which set out our
main objectives and targets related to physical infrastructure investments.  Action Plans will continue
to be subject to annual review and committee approval. This will allow for changes to be made in
response to any changing or arising challenges and opportunities facing the North Lanarkshire
economy at any given time. 
An Economic Performance Framework (EPF) was also developed in 2021 to try to measure the
economic outcomes of the ERDP and other associated activity being delivered through the council and
their partners. This framework contains a series of key performance indicators with short, medium and
long-term targets. The EPF will remain in place and annual performance reports will be presented to
North Lanarkshire Council’s Enterprise and Fair Work Committee. 
Page 16 of 79

Page 17

Key Strategic Links 
The Plan for North Lanarkshire sets the direction for the council and its partners. Its purpose is to
communicate our shared priorities and provide a focus for activities and resources. It is a high-level
strategic document that outlines a long-term vision for North Lanarkshire - a vision where North
Lanarkshire is the place to Live, Learn, Work, Invest, and Visit. 
The Plan for North Lanarkshire is underpinned by a number of strategies and plans which are closely
interlinked with the ERDP. As such, activity delivered through the ERDP annual action plans will aim,
where possible, to support the following: 
Equality Strategy
North Lanarkshire’s Equality Strategy focusses on furthering the council’s ‘We Aspire’ ambitions and
priorities. It recognises that the poverty, disadvantage and inequalities that exist for some people in
North Lanarkshire needs to be addressed. 
Addressing the disadvantage and inequality that some groups of people experience because of societal
constructs, prejudice, direct and indirect discrimination requires a strong, sustained strategic approach
directly aligned to The Plan for North Lanarkshire and other key plans such as North Lanarkshire’s
ERDP. ‘Employment’ and ‘Education’ are two of the five key themes of this strategy which need to be
embedded within the goals of the 2023-2028 ERDP. As such, and given current economic
circumstances, this ERDP will focus much more on opportunity and using investment to provide
chances to those most excluded. 
Workforce for the Future Strategy
Building a skilled workforce for the future plays a significant part in delivering our ambition for
North Lanarkshire. In economic terms, making sure that we have a skilled workforce will support
a more sustainable place that will help the council and its partners to continue to grow its economy
and create better opportunity for our residents and young people. 
The Workforce for the Future Strategy and ERDP Action Plans need to ensure that investment
plans continue to support future strategy that is focused on skills and community benefit. More
importantly, investment through the ERDP needs to be targeted and actively support skills
development across key growth sectors. 
The Place, The Vision
The Place, The Vision sets out an investment plan for North Lanarkshire focused on 4 key themes –
‘Town and Community Hubs’, ‘Town Centres’, ‘Country Parks’ and ‘Connectivity’. 
The refreshed ERDP needs to ensure that it remains closely linked to this vision and make sure that
investment being made in our housing, town centres, business and connectivity fits with wider plans
for our town and community hubs and greenspace and that these remain accessible to all. 
Climate Plan, Action on Climate Together 2030
This strategy encompasses the council’s climate emergency declaration and subsequent target to
achieve net-zero emissions by 2030. To do this, carbon efficiency has to be embedded in all future
investment decisions made by the council. 
Council decisions need to consider how new development can be offset against our plans for growth.
This not only means investment in council owned assets but consideration as to how the council can
drive forward carbon savings across the private sector and our third sector partners. 
Page 17 of 79

Page 18

Digital and IT Strategy
IT and digital are integral to the future success of The Plan for North Lanarkshire, Digital Communities,
a Digital Economy, and a Digital Council. Investment made through the ERDP offers opportunity for
digital infrastructure and better digital connectivity. 
Commsworld have been appointed as the council’s digital partner and there should be early
engagement with them in relation to all investment being made through the ERDP and other council
led capital investment plans to ensure that opportunity to improve digital infrastructure across North
Lanarkshire is not missed. 
Developing housing that promotes improved quality of life and creates a better place to live 
As of June 2021, there were more than 341,000 residents living in more than 153,00 homes across
North Lanarkshire’s towns and settlements. 
With over 30% of homes in North Lanarkshire socially rented (compared to a Scottish Average of 23%),
public sector investment in our housing stock remains critical to support population growth within
North Lanarkshire. This is reflected in part via the council’s commitment to delivering one of Scotland’s
most ambitious affordable housing programmes. In 2018 the council pledged to deliver 5,000 new
affordable homes by 2035 with 1,494 new council homes already completed and a further 267 in
development as of March 2022. Added to this, the council aims to support our partner social landlords
to deliver an additional 758 affordable homes by 2027/28. 
However, this is not simply just about constructing new properties but also about creating improved
quality of homes, following through on the council’s commitment to replace our ageing tower blocks
with modern, energy efficient and accessible property whilst recognising that young people, families
and our elderly population need the right homes in the right places. 
With only 70.3% of North Lanarkshire’s housing stock privately owned (owner occupied and private
rented), there is also a vital need to expand opportunity for people to be able to buy their own homes
and remain within or relocate to North Lanarkshire. With over 141ha of developable land available at
Cumbernauld Community Growth Area – (Cumbernauld CGA) and 140.46 available at Ravenscraig,
these two sites by far offer the most extensive opportunity for private sector build. 
While private sector housing in most areas of North Lanarkshire is generally affordable and in good
supply, businesses continue to highlight that there is lack of affordable rented accommodation for
those on short-term or temporary contract and who are unable or unwilling to commit to
homeownership. To address this issue, North Lanarkshire Council continue to review and assess
opportunity to support intermediate tenures such as mid-market rent. 
Lastly, whilst the total number of households in North Lanarkshire increased by 1,200, between 2019
and 2021, future projections to 2043 show significant growth. Nevertheless, since mid-2020, there has
been a number of issues which have affected development and provide challenges to the council to
ensure that our programme for housing development does not stall. 
Challenges Faced 
Covid, Brexit and the wider geopolitical landscape has had a significant impact on the council’s
construction and development programmes over the last three years. It has led to supply chain delays,
significant contract price increases and inflationary rises. This has in turn put significant pressure on
council budgets to deliver on its programme (with the average build cost of a new build council home
Page 18 of 79

Page 19

rising from circa £190-195k (pre-Covid) to £215-220k. This represents the average cost across all
property types and sizes and costs vary from site to site.   
Added to this, all social landlords face significant pressure on their resources, which may impact on
their ability to fund new build and other investment programmes. 
Private sector development has also been constrained by rising costs and financial uncertainty over
the last two to three years with only 492 new private sector homes completed in 2021/22 compared
to 926 in 2018/19. However, private sector development is also affected by other issues at key sites
such as Cumbernauld CGA (where infrastructure investment is required) and Ravenscraig (where
abnormal ground conditions has led to significant abnormal costs). 
Recommendations 
To help deliver the homes that North Lanarkshire needs to grow over the next 5 years, the council will: 
• continue to focus investment towards the council’s affordable housing stock to make sure that
the target of 5,000 new council homes for North Lanarkshire is reached by 2035;
• continue to support the delivery of the affordable housing programme including intermediate
tenures such as mid-market rent;
• enable private sector housing development to support the regeneration of strategic sites such
as Ravenscraig.  
Reshaping our town centres to ensure that these provide modern and attractive centres that meet
the needs of our communities 
Town Centres are vital for our sense of community and place and their attractiveness and quality as a
place to live is strongly interlinked with the image and perceived success of North Lanarkshire. North
Lanarkshire has eight recognised town centres: Airdrie, Bellshill, Coatbridge, Cumbernauld, Kilsyth,
Motherwell, Shotts and Wishaw. Each town has its own distinctive features and distinct mix of cultural,
leisure and retail facilities. 
However, as with most other areas across Scotland and the UK, vacancy rates continue to increase
across our towns as town centre shopping continues to be impinged by out-of-town retail parks and
in particular online shopping. North Lanarkshire’s town centres have a vacancy rate of almost 19%.
This vacancy rate is projected to continue to rise as retail continues to fail (a decline which has been
accelerated by the impact of Covid and the cost-of-living crisis). 
To address this decline, the 2019-23 ERDP highlights that town centres need a broader foundation for
success with a mix of uses sustained by a resident population. In doing so, one of the recommendations
of the 2019-23 ERDP was to develop aspirational visions for all of North Lanarkshire’s eight town
centres. Following a programme of public engagement and stakeholder consultation, as well as input
from a range of expert consultants, these visions, providing high level concept designs for our town
centres, were approved by the council’s Policy and Strategy Committee in September 2021. Whilst
these Visions are very specific to each town centre and their communities, they shared a number of
commonalities: 
• the need to consolidate retail within our town centres, increase residential footfall and address
vacancy through town centre housing development;
• a wish to promote local access to our town centres through active travel;
• an aspiration to, where possible, establish transport hubs connecting up bus and rail networks;
Page 19 of 79

Page 20

• a desire to incorporate proposals for town or community hubs within our town centres where
possible; and
• proposals to create new bespoke gateways to our towns. 
The next stage of bringing these visions to life involves developing action plans for each town that will
specifically identify short, medium and long-term activity to help promote and support the concepts
identified within the town centre visions. This work, co-produced with local communities and
residents, is already underway and will be completed for all eight towns by mid-2024. 
However, although the action plans for our town centres are still in development, the council has
continued to work to address key issues which impact upon the image of our centres and which
communities have identified as prolonged blight within our towns. As such, over the last four years of
the 2019-23 ERDP, more than £70m investment has been made in regenerating our town centres
funded through the council’s capital programme and a range of external town centre and place making
funds. 
Challenges Faced 
The work undertaken through the delivery of the 2019-23 ERDP, together with wider macro-economic
factors, has given rise to a number of practical challenges in relation to the regeneration of our town
centres.   
It was already well recognised that complex property ownership patterns within town centres and
development constraints constituted two of the main barriers to the redevelopment of our towns.
However, what has presented a greater challenge to the council more recently is owners’ unrealistic
expectations of town centre property value, which is often higher than the current market value that
the council is able to pay.  In most of these cases, the buildings being sought by the council are in poor
condition, with little or no ongoing maintenance, and will continue to fall into further disrepair due to
failure to agree their acquisition price. 
Added to this, there has been a number of other issues which have impacted on bringing other town
centre projects forward. These include: 
• the extended timescales and resource requirement needed to establish the justification and
implementation of compulsory purchase orders;
• medium to long-term lease agreements of individual units tying up the acquisition of larger
retail properties;
• energy efficiency and building regulation requirements, especially for conversion of property
to flatted accommodation above commercial premises; 
• finding an alternative use for vacant retail properties within our town centres where these are
not suitable for residential use; and
• the cost of conversion of town centre vacant properties. 
In addition to these project specific barriers, elevated inflation levels have not only given rise to
increased construction costs but has also led to increased pressure on council budgets. Moreover, one
of the key annual funding streams which is available to support town centre regeneration, the Scottish
Government’s Place Based Investment Programme, is only currently guaranteed up until 2024/25. As
such, longer-term funding plans still need to be put in place to support the delivery of the emerging
town centre action plans and ensure our ambitions for transformative town centre change can be met
in full. 
Page 20 of 79

Page 21

Recommendations 
To help reshape our town centres to ensure that these provide modern and attractive centres that
meet the needs of our communities over the next five years, the council will: 
• establish and commence delivery of town action plans for all eight town centres (aligned with
our approved town visions), agreeing short, medium and long-term investment plans for each;
• continue to prioritise funding and secure external investment for the regeneration of our town
centres;
• review how the council can be more effective in addressing failing buildings in our town
centres, including potential use of Compulsory Purchase Orders where required. 
Improving our business and industrial infrastructure, creating opportunities for investment and for
companies to start-up or relocate here 
North Lanarkshire has one of the fastest growing economies in Scotland with GVA increasing by 118%
over the last two decades. The number of registered enterprises in North Lanarkshire has also
increased from 6,760 to 8,420 between 2010 and 2022. 
Businesses across the authority have a combined turnover of almost £16M (6% of all Scottish business
turnover), with nearly half of North Lanarkshire’s businesses within the retail, construction, scientific
and technical services industries and the remaining sectoral mix fairly evenly spread between a diverse
range of sectors such as administrative and support services, transportation and storage,
accommodation and food services and manufacturing. 
Demand for commercial space in North Lanarkshire is high and, whilst our office market remains
relatively weak (due to historic oversupply), with almost 25million sqft of industrial floorspace, the
rate of vacant industrial units is at a historic low of 3.5%. Added to this, North Lanarkshire has over
half (53%) of all available marketable land in the Glasgow City Region. 
To support continued business growth across North Lanarkshire, the council took forward a number
of initiatives via the 2019-23 ERDP. These include:
• the development and delivery of the 2020-23 ‘Workforce for The Future Strategy’ which aims
to align workforce skills with future jobs demand and promote access to higher skilled
employment in order to help address ‘in-work poverty’;
• the preparation of North Lanarkshire’s Economic Recovery Plan which was designed to sustain
and support business recovery through the covid pandemic;
• the establishment of Invest in North Lanarkshire, a bespoke online marketing campaign
focused on promoting investment in North Lanarkshire and opportunities for companies to
locate here;
• £4.809m Vacant & Derelict Land Funding provided to Fusion Assets (NLC’s arms-length
economic regeneration and property development company) to help kick-start industrial
development at Gartcosh Business Interchange, Ravenscraig Industrial Park and Link Park
Business Park (Newhouse);
• securing funding for the development of the Smart Hub Lanarkshire, a new manufacturing
innovation hub at New College Lanarkshire (Ravenscraig Campus) used to promote new
technology and incorporation of automation within North Lanarkshire’s manufacturing
industries; and
Page 21 of 79

Page 22

• securing £5m external funding for the regeneration and redevelopment of Braidhurst
Industrial Estate to be used as a pilot for the renewal of more marginal estate within North
Lanarkshire
In addition to activity undertaken though the council, the Glasgow City Region Economic Strategy was
launched in 2021, setting out a vision where by 2030 Glasgow City Region will have the most
innovative, inclusive and resilient economy in the UK. This regional strategy highlights three key
priorities which should be used to help guide future business and industry investment in North
Lanarkshire. These are:
• promoting an inclusive economy by addressing worklessness and creating accessible
employment opportunity;
• improving productivity through upskilling, innovation, fostering key growth sectors and the
continued expansion of the region’s ‘foundational economy’; and
• supporting investment and activity which promotes wider goals for net zero. 
Challenges Faced
Due to its close proximity to Glasgow and the draw that this has for financial and administration
sectors, the office market in North Lanarkshire is oversupplied and currently relatively weak with
vacancy rates of 15.4% and average rental values of 23% below the Glasgow regional average. 
On the other hand, over the last decade, average rents for industrial space in North Lanarkshire have
risen by an average of +3.1% per annum, whilst the volume of industrial property sales in 2020 at
£106m has been a record high, pushing average prices up. However, rising construction costs and an
oversupply of older industrial properties across the region (at a much lower rental cost than modern
new facilities) is likely to start to constrain investment in new facilities. 
A report prepared by Co-star in 2022 also highlighted that industrial vacancies along key motorway
corridors such as the M8 is now at a record low (3%) with demand continuing to far outstrip supply
and level of available developable land continuing to fall.
These strategic business locations represent a vital investment opportunity for North Lanarkshire and
the potential to make available land via the development of the Orchard Farm roundabout access of
the A8 to open-up new industrial land at Mossend International Railfreight Park (MIRP). 
Although these motorway corridors provide North Lanarkshire’s main strategic business locations,
consultation undertaken as part of the development of the ERDP 2023-2028 has highlighted that for
those without cars, accessing these locations is difficult from towns and settlements across North
Lanarkshire due to a lack of public transport options (as is the case for those residents from smaller
and rural settlements trying to access employment opportunity in general). 
Lastly, this consultation also highlighted that, although information in relation to commercial property
or land enquiries that the council or its partners receive is generally well shared, there remains a
number of initial enquiry entry points (including  Enterprise, Growth, Planning and Place and Estates
Teams, Fusion Assets, North Lanarkshire Properties, Lanarkshire Business Gateway and Scottish
Enterprise) without a formal process for recording, sharing or reporting on these. 
Page 22 of 79

Page 23

Recommendations 
In order to promote growth and inclusive growth over the next five years, the refreshed ERDP proposes
the following recommendations: 
• promotes a mix of development across our motorway corridors and accessible business
locations to support the development of our foundational economy as well a high-end growth;
• continues to support enabling investment which brings our vacant and derelict land and
brownfield sites into commercial use;
• improves how we record and respond to enquiries from businesses to provide a co-ordinated
approach across relevant council services to help attract, retain and expand businesses and
employment opportunities; 
• builds upon work which supports innovation and skill development though the development
of sectoral learning academies; and
• supports investment, via our ALEOs, that will continue to improve, modernise and expand
commercial stock availability across North Lanarkshire. 
Added to these activities, it is also intended to undertake a full review of sites allocated for business
and industry within the current Local Development Plan (LDP) to inform the preparation of next LDP
and ensure that we have suitable sites available to attract and retain businesses and employment
opportunities. 
Continuing to improve our connectivity and develop new opportunities by transforming our road,
rail and digital infrastructure 
With key motorways (M8, M74, M73 and M80) running across and linking the local authority area, rail
freight depots and a new transport hub being built at Motherwell Train Station, North Lanarkshire is
the ‘best-connected’ place in Scotland. 
The new orbital route delivered through City Deal will help improve this connectivity even further,
linking Motherwell, Ravenscraig, Airdrie and Cumbernauld directly to the M8 and M74 motorway
corridors. New active travel routes are helping to create 20-minute neighbourhoods, connecting our
communities with our greenspace, town centres, travel hubs and public facilities whilst new access
infrastructure such as the City Deal Orchard Farm Roundabout on the A8 will open up new commercial
development opportunity. 
In addition to this access infrastructure, work is being undertaken to support the delivery of Electric
Vehicle (EV) charging across North Lanarkshire. Much of this work is now being undertaken at new
housing and commercial developments. However, in 2020, Project PACE was formed to trial the
approach of an electricity network provider leading on the planning and installation of public EV charge
points at a regional scale across Lanarkshire. Between its launch and 2022, Scottish Power Energy
Network, funded through the Scottish Government, installed 167 EV charging points at 44 EV hubs
across Lanarkshire including 23 hubs in North Lanarkshire with 22 standard, 30 fast and 32 rapid
charging points. 
Building on the works undertaken through initiatives such as Project PACE, the Scottish Government
launched a £30M EV Investment Fund (EVIF) in 2022 in order to support local authorities to draw in
private investment across Scotland and enable the implementation of a variety of public charge point
owner/operator models. Models for delivering future EV charging are currently being considered at a
regional level. However, this needs to be interlinked to our wider plans for town centre renewal,
Page 23 of 79

Page 24

housing supply, town and community hubs, parks for the future, business and community
regeneration. 
Digital connectivity also remains at the heart of renewing North Lanarkshire, ensuring that all our
residents and businesses have access to affordable full-fibre or fast-speed broadband. To support this,
the council has entered into a 15-year partnership agreement for digital connectivity services with
‘Commsworld’. This commercial partnership has been put in place to help deliver high-quality, reliable
fibre connections that will make a transformative difference to investment opportunities for
businesses in the area as well as tackling digital exclusion among our residents. 
It will achieve this by futureproofing North Lanarkshire’s digital backbone, enhancing the coverage and
reach of gigabit-capable networks to businesses, private and council-owned social housing and
residential households that are not currently served by existing networks. This will bring enormous
benefits including increased access to employment opportunities, improve health and social wellbeing
and economic growth.
Lastly, launched in 2021, North Lanarkshire’s Active Travel Strategy aims to direct the creation of a
wide range of connections across North Lanarkshire that can be utilised for everyday journeys such
as travelling for education, day to day needs and employment opportunity. Significantly, this
strategy provides a framework for the council to prioritise and bring forward active travel
interventions across North Lanarkshire that will improve links within our towns and planned town
and community hubs. 
In helping to deliver this, over the last four years, North Lanarkshire Council has made investment
in key routes such as Cumbernauld Greenlink and Ravenscraig Active Travel links. Added to this,
active travel plans are now being developed to deliver improved greenlinks to key employment
locations such as Eurocentral and Maxim. 
Challenges Faced
Although, North Lanarkshire has great road and rail infrastructure, access to and from many of our
rural communities and business locations is dependent upon car ownership. Car ownership across
most of North Lanarkshire is relatively low and, whilst pre-covid, commercial bus services across
many areas of North Lanarkshire was poor, post-covid, commercial routes have worsened. In 2019,
legislation was approved to permit local authorities to run public bus services. However, such
services, where most needed, are likely to be commercially unviable and would need to be heavily
subsidised. 
Whilst plans for City Deal Investment are ringfenced and on budget, as we progress with other
infrastructure investment plans across North Lanarkshire, as with all other capital programmes,
rising construction costs and inflation continues to impact on proposals. As such, there is a clear
need to prioritise this investment to help ensure that we best achieve our goals for inclusive
economic growth, net carbon zero and digital connectivity. 
Lastly, much of the land required for infrastructure development across North Lanarkshire falls
outside council ownership. This often results in the need to agree servitude rights or acquire land
or property through compulsory purchase orders, slowing development down and bringing about
higher costs (potentially making schemes financially unviable). 
Page 24 of 79

Page 25

Recommendations 
In order to continue to enhance connectivity across North Lanarkshire, it is recommended that the
council: 
• continue to deliver the City Deal programme;
• ensure that inclusive economic growth remains at the heart of opportunity to support
affordable and accessible transport systems (via the Local Transport Strategy due to be
launched in 2024); 
• invest in the delivery of the council’s Active Travel Strategy to ensure a comprehensive
connection of active travel routes to key places across North Lanarkshire;
• support the delivery of Electric Vehicle Charging infrastructure across North Lanarkshire; and
• work with the council’s digital partner to install and invest in infrastructure that helps create
one of the best and most affordable/accessible digital provisions in the UK. 
ERDP Action Plan 
The refreshed ERDP is a high-level five-year economic development framework which is aligned to The
Plan for North Lanarkshire. In order to support the delivery of this plan, the ERDP will be underpinned
by an Action Plan which will be subject to annual review, monitoring and update.
This Annual Action Plan will set clear targets and aims for each forth-coming year which will assessed
and measured bi-annually. This will allow for:
• amendments to be quickly made to plans in response to any changing or arising challenges
and opportunities facing the North Lanarkshire economy at any given time; and
• the impact of activity being delivered through the ERDP on North Lanarkshire’s wider
economic Performance Framework to be assessed. 
Page 25 of 79

Page 26

Appendix 2
ERDP Action Plan
2023-2024 
Page 26 of 79

Page 27

The Economic Regeneration Delivery Plan is a key strategic document which is aligned
to The Plan for North Lanarkshire and other key strategies, policies and plans. 
Together this strategic policy framework ensures
that work is aligned with our priorities and enables
the required resources and working practices needed
to facilitate delivery of the shared ambition. 
As a high-level investment framework,
the Economic Regeneration Delivery Plan will be
aligned with our composite capital programme and
will be refreshed again at the end of 2027/28. 
This Action Plan supports delivery of the Economic
Regeneration Delivery Plan. It will be monitored and
updated annually. Future updates can be found at
www.northlanarkshire.gov.uk/ERDP 
Improving
economic
opportunities and
outcomes for all
The Plan for
North Lanarkshire
Economic
Regeneration
Deliver Plan
NLC
Equalities
Strategy
Workforce
for the
Future
The Place,
The Vision
Climate Plan, Action
on Climate Together
2023 
Digital and IT
Strategy
Active Travel
Strategy
Page 27 of 79

Page 28

Theme: Live
ERDP Priority 1: Developing housing that promotes improved quality of life and creates a better place to live 
ERDP Action Baseline Target 2023-24 Lead Team
1.1 Deliver new build council homes via
NLC’s New Supply Programme.
Between 2010/11 and 2021/22 NLC
has delivered 934 new build homes
across the authority via the New
Supply Programme alone.
Complete 276 new build
council homes during
2023/24
New Supply
1.2 Bring homes into council ownership
via NLC’s Open Market /Empty Homes
Purchase Schemes, including homes
previously bought under the Right to
Buy scheme
As of 31 March 2022, NLC had brought
560 homes into council ownership
since the introduction of the Open
Market /Empty Homes Purchase
Schemes.
75 Open Market /Empty
Homes Purchase Scheme
completions during
2023/24
New Supply
1.3 Enable the private sector to support
the delivery of the New Supply
Programme, via off the shelf
purchases.
As of 31 March 2022, NLC has
acquired 117 new build homes from
the private sector
Progress the delivery of a
further 50 new build
acquisitions during
2023/24.
New Supply
1.4 Prepare and support the delivery of
the Strategic Housing Investment Plan
(SHIP)
Between 2010/11 and 2021/22, 1,494
affordable homes have been delivered
via the council’s New Supply
Programme and 1,862 by Registered
Social Landlords (RSL’s) 
Prepare the 2024/25 SHIP
which will identify sites to
meet Local Housing
Strategy priorities and
maximises the use of
available Scottish
Government grant
funding. 
Support the delivery of
sites within the current
2023/24 SHIP.
New Supply 
Page 28 of 79

Page 29

Theme: Invest
ERDP Priority 2: Reshaping our town centres to ensure they provide modern and attractive centres that meet the needs of our communities 
ERDP Action Baseline Target 2023-24 Lead Team
2.1 Co-produce a series of Town Action
Plans with local communities to
enable the realisation of the Town
Visions.
Eight Town Visions were approved by
committee in 2021.
Finalise the first four Town
Action Plans in Airdrie,
Cumbernauld, Motherwell
and Wishaw. 
Town Action Plans for
Bellshill, Coatbridge,
Kilsyth and Shotts in
development for
completion mid-2024.
Growth
2.2 Develop a sense of place by
protecting, repurposing or
redeveloping vacant, derelict or
unused priority buildings and sites
within our town centres and investing
in town centre regeneration activity
that will support the delivery of the
Town Visions
Since the Growth Team was formed in
2019, 15 town centre properties/sites
have been acquired across the
authority with a view to either
converting existing properties to
residential developments, building
new homes on cleared sites or
upgrading commercial premises.
Continue to engage with
local property/landowners
with a view to acquiring
key town centre
properties/sites
earmarked for
conversion/improvement.
Growth 
2.3 Between 2010/11 and 2021/22 there
were 1,460 new homes delivered
within North Lanarkshire’s 8 town
centres (including edge of town
developments). These properties have
been delivered via North Lanarkshire
Council and Registered Social
Landlords (RSL’s).
Deliver or support the
delivery of 52 new
affordable homes within
our town centres
(including edge of town)
during 2023/24
New Supply / Growth
Page 29 of 79

Page 30

2.4 Support new investment in North
Lanarkshire’s town centres.
£2.8m was secured via PBIP in
2021/22 and a further £2.4m in
2022/23.
Deliver the Scottish
Government’s Place Based
Investment Programme
allocation for 2023/24 (NB
allocation still to be
confirmed by Scottish
Govt).
Growth
2.5 North Lanarkshire has submitted
various funding bids over the course
of the previous ERDP (2019-2023)
including the UK Government’s
Levelling Up Fund and Community
Renewal Funds. 
North Lanarkshire secured more than
£3.7m during 2021/22 and 2022/23 as
part of the eighth and ninth rounds of
the Scottish Government’s
Regeneration Capital Grant Fund
(RCGF). 
In January 2023 the council was
awarded £9,225,000 from the UK
government’s Levelling Up Fund to
support the delivery of the
Cumbernauld Town Vision
Engage with local
community organisations
to enable applications to
third party regeneration
funds, where appropriate. 
Continue to support 2
existing community led
projects funded under
previous RCGF rounds. 
Submit bids to any
relevant regeneration
challenge funds
announced by the UK
Government, Scottish
Government, or other
relevant external funding
bodies.
Growth 
Page 30 of 79

Page 31

Theme: Work
ERDP Priority 3: Improve our business and industrial infrastructure, creating opportunity for investment and for companies to start-up or
relocate here 
ERDP Action Baseline Target 2023-24 Lead Team
3.1 Improve the provision of high-quality
business and industrial space either
directly or through our ALEOs or Joint
Ventures.
£1.334m invested in business and
industry zoned land or upgrades
to existing business and
industrial infrastructure
across North Lanarkshire between
2018/19 and 2021/22. 
This includes NLC and ALEO funding
only.
NLC and Fusion Assets to
invest a minimum of
£2.3m in key business and
industrial projects
Fusion Assets / Growth
3.2 £6.924m external, private or loan
funding secured for investment in
office and industrial developments
across North Lanarkshire between
2018/19 and 2021/22.
£3.45m external funding
(including private sector
funding) to be secured by
NLC/Fusion Assets for
business and industrial
infrastructure in 2023/24.
Fusion Assets / Growth
3.3 4.07ha of land remediated or
improved for business and industry
use across North Lanarkshire between
2018/19 and 2021/22.
2.0ha of land to be
remediated or improved
(by NLC or Fusion Assets)
for business and industry
use in 2023/24.
Fusion Assets/ Growth
3.4 69,910 sq.ft of commercial workspace
created or refurbished as a result of
investment by NLC, Fusion Assets or
NLP across North Lanarkshire between
2018/19 and 2021/22.
16,500 sq.ft of business
and industrial workspace
to be created or
refurbished by NLC, Fusion
Assets and North
Fusion Assets/ Growth
Page 31 of 79

Page 32

Lanarkshire Properties in
2023/24.
3.5 Ensure our investment opportunities
deliver economic opportunities and
outcomes for all
Stage 2 RCGF submission for
Braidhurst Industrial Estate approved
December 2021 
- £1.8M RCGF awarded to project
Progress delivery of a
regeneration scheme for
Braidhurst Industrial
Estate, including the
provision of new start-up
units and refurbishment
of existing units owned by
North Lanarkshire
Properties.
Growth
3.6 N/A Develop a Business and
Industry Strategy
in line with investment
opportunities, site
prioritisation and future
market demand.
Growth 
Page 32 of 79

Page 33

Theme: Invest
ERDP Priority 4: Improve our connectivity and develop new opportunities by transforming our road, rail and digital infrastructure 
ERDP Action Baseline Target 2023-24 Lead Team
4.1 Continue to deliver the City Deal
Programme
Planning approval granted. 
Full Business Case (FBC) for the West
Coast Mainline Crossing approved
with works on site 2022/23.
Continue to progress
delivery of Ravenscraig
Access Infrastructure to
support the
redevelopment of
Ravenscraig and
connect the M74 to M8
as part of Pan
Lanarkshire Transport
Corridor. 
Complete West Coast
Mainline Crossing. 
Full Business Case (FBC)
approval for the
Motherwell to
Ravenscraig access (new
roundabout at Airbles
Road/Windmillhill Street
junction; dual carriageway
from the junction to
Ravenscraig Regional
Sports Facility) 
Enterprise Projects
Page 33 of 79

Page 34

Commence construction
of Motherwell to
Ravenscraig access.   
4.2 Ground investigation works complete.
Preferred option for East Airdrie Link
Road route identified.
Continue to progress
delivery of the East Airdrie
Link Road (EALR). 
Procure and appoint
consultant team for Stage
3 (Detailed Design and
Planning Application). 
Commence detailed
design.  
Enterprise Projects
4.3 Contractor (Balfour Beatty) appointed,
and works have commenced on site.
Improve Motherwell
Town Centre transport
interchange to support
active and sustainable
travel.
Complete works at
Motherwell Rail Station
(ScotRail) and Muir Street
(NLC) during 2023/24.
Enterprise Projects
4.4 Outline Business Case (OBC) for
A8/M8 Corridor Access Improvements
project was approved by Glasgow City
Region City Deal Cabinet in 2022.
Full Business Case
approval for the Orchard
Farm roundabout. 
Enterprise Projects
Page 34 of 79

Page 35

Appointment of
contractor to deliver the
Orchard Farm Roundabout
to support the
development of key
business and industrial
sites on the A8/M8
corridor.
4.5 The OBC for the A8/M8 Corridor
Access Improvements project was
approved by Glasgow City Region City
Deal Cabinet in 2022. This included
sustainable transport improvements
and enables us to develop and design
our proposals.
Progress delivery of the
Eurocentral Strategic
Active Travel project. 
Appoint consultants to
develop detailed design
proposals during 2023/24.
Enterprise Projects
4.6 Support and enable investment in
active travel
Ravenscraig Active Travel Link (RATL)
phase 1 complete – providing a new
path enabling residents to walk, wheel
and cycle. The path runs north from
‘The Castings’ housing development
off Meadowhead Road to Ravenscraig
Regional Sports Facility and 'The Craig'
public park. 
Deliver phase 2 of the
RATL from Meadowhead
Road to Robberhall Road. 
Enterprise Projects
4.7  Funding secured via UK Shared
Prosperity Fund - £75,000 allocated
towards active travel feasibility
studies. 
Undertake feasibility
studies to support the
development of active
travel routes across North
Lanarkshire. 
Infrastructure &
Transportation /
Enterprise Projects
Page 35 of 79

Page 36

4.8 7.8km of active travel routes
enhanced or created between
2018/19 and 2021/22.  
A further 6km of active
travel routes to be
enhanced or created
during 2023/24, linking
communities, arterial
routes and transport hubs
with town centres
and key business locations
in North Lanarkshire. 
Infrastructure &
Transportation /
Enterprise Projects
4.9 Deliver a worldclass digital
Infrastructure across North
Lanarkshire
Commsworld Ltd were appointed to
deliver connectivity services in
February 2022. 
The project to deliver Full Fibre
connectivity through the Councils
Wide Area Network is progressing
well. To date, CommsWorld have
delivered 162k metres of Fibre
Infrastructure. 
3 apprentices were recruited during
2022 via the NLC/Commsworld Shared
Apprenticeship model.
Fibre infrastructure to be
fully delivered by June
2023. 
This infrastructure is key
to then enable other call
off contracts, one of which
is Public Wi-Fi, which
when delivered, will be
the single Public Wi-Fi
service that will
incorporate Town Centres
and any public use
buildings and spaces that
are deemed to require it. 
This new infrastructure
will be an enabler for
further digital
opportunities throughout
North Lanarkshire.
Business Solutions
Page 36 of 79

Page 37

Through the Community
Benefits and Added Value
elements of the contract,
key actions will be
delivered throughout
2023-24 including:
• Recruitment of
additional 3
apprentices through
the NLC/Commsworld
Shared Apprenticeship
model.
• Continued delivery of
SmartSTEM/ Young
Enterprise Scotland
programme in Schools
• Provision of work
experience
placements
• Delivery of a digital
showcase for
businesses 
• Development of
activity to maximise
the uptake of Scottish
and national
broadband voucher
schemes
• Development and
delivery of actions to
Page 37 of 79

Page 38

support community
engagement,
empowerment and
capacity building 
Page 38 of 79

Page 39

North Lanarkshire Council
Report
Enterprise and Fair Work Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  LN/PH  Date 17/02/23 
City Deal Update Report 
Programme of Work PO21 
From  Pamela Humphries, Chief Officer of Place 
E-mail NobleLy@northlan.gov.uk Telephone  Lyndsay Noble
07970016256 
Executive Summary 
The North Lanarkshire City Deal Programme Update report seeks to inform the Enterprise
and Fair Work Committee of the current status of North Lanarkshire City Deal Infrastructure
subprojects.     
Recommendations 
It is recommended that the Committee: 
1)    Note the status and recent progress of North Lanarkshire City Deal infrastructure
subprojects.  
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (5) Grow and improve the sustainability and diversity of North
Lanarkshire's economy
AGENDA ITEM 3
Page 39 of 79

Page 40

1. Background 
1.1 The Glasgow City Region (GCR) City Deal is an agreement between the UK and
Scottish Governments and the eight GCR Local Authorities, with the sole focus of
creating additional economic growth.  The 20-year GCR Deal was accepted by GCR
Council Leaders on 20 August 2014 and incorporated: 
• implementing a £1.13bn Infrastructure Fund to improve the regional transport
network, regenerate sites for economic use and improve public transport
provision;
• supporting growth in the life sciences sector;
• helping small and medium enterprises to grow and develop;
• establishing programmes to support the unemployed; and 
• piloting new ways of boosting the incomes of low wage employees.   
1.2 The City Deal programme for North Lanarkshire as part of the Infrastructure Fund
comprises the following projects:
• A8/M8 Corridor Access Improvements
o Strategic Active Travel 
o Orchard farm Roundabout
• Glenboig Link Road (complete)
• Pan-Lan Orbital Transport Corridor
o East Airdrie Link Road
o Ravenscraig Access Infrastructure
o Motherwell Town Centre Transport Interchange 
2. Report 
2.1 Motherwell Town Centre Transport Interchange (MTCTI) 
2.1.1  The redevelopment of Motherwell Rail Station by ScotRail’s appointed contractor,
Balfour Beatty, is due to complete in March 2023. Over recent months, work has
focussed on the new extensions to the station building, new roof structure and glazing.
Access to the station and platforms for passengers has continued to be maintained
throughout the improvements. The temporary ticket office in the station forecourt has
been removed and relocated into the new retail unit space, until the new travel shop is
complete. 
2.1.2 Committee will be aware that Balfour Beatty has also been appointed by the council to
undertake the improvement works to Muir Street comprising expansion of the bus stop;
provision of a new access road to Motherwell Rail Station with new taxi rank and public
realm improvements. 
2.1.3 Both the Motherwell Rail Station and Muir Street contracts were scheduled to be
complete by July 2022.  Due to delays primarily in delivering the station contract, the
station works are now expected to be complete in March 2023. Through joint working
with Balfour Beatty and ScotRail, it is anticipated that the Muir Street works will be
completed ahead of the station works, during February 2023. Due to the need to ensure
safe pedestrian access between the expanded bus stop and Motherwell rail station,
reopening of the bus stop occurred at the end of January. SPT have been notified and
have communicated this timescale to bus operators. 
Page 40 of 79

Page 41

2.1.4 Some road closures of short duration have been put in place to date for the Muir Street
works to carry out some activities safely. For each road closure, advance notification is
provided to local businesses and the public (through signage on site, website updates
and other communication channels). Road closures have been arranged at weekends
to minimise disruption to the town centre. The majority of work requiring road closures
is now complete, however a further closure may be needed to install the new pedestrian
crossing from the east side of Muir Street to the bus stop area. 
2.1.5 Officers within the Enterprise Projects Team are working with the communication team
at Balfour Beatty and the Motherwell Rail Station Communications Group to ensure that
communications are coordinated across both contracts. 
2.1.6  Community Benefit outcome delivery by the contractor is progressing well. To date, a
number of skills, employability and training initiatives and community project have been
delivered. In recent months, a site visit has been held with local school children; local
groups have been supported via a volunteering day undertaken with Balfour Beatty
staff assisting to lay paving slabs and install a shed and foodbank voucher support and
materials have been donated to a local school. The provision of benches for a local
church and group will be completed in early January. 
2.1 Ravenscraig Access Infrastructure 
2.2.1 The Ravenscraig Access Infrastructure project comprises three projects:
• a new road connection between Motherwell and Ravenscraig from Airbles
Road, passing under the West Coast Main Line railway, and on to the Regional
Sports Facility 
• completing the dualling of Airbles Road between Airbles Farm Road and
Hamilton Road and improving facilities pedestrians and cyclists  
• upgrading the A723 for three kilometres from the New Craig Road junction at
Ravenscraig to the M8 at Holytown to create a dual carriageway and shared
footway/cycleway 
2.2.2    The project will be delivered in phases, beginning with the new rail bridge for the future
connection between Motherwell and Ravenscraig. 
2.2.3   Significant progress has been made by Story Contracting, with the construction of the
new bridge structure complete in December and ahead of programme. Whilst not
shortening the overall programme, this provides greater programme contingency for
the works that are required to take place over the winter months. Works during early
2023 ahead of the track closure will focus on preparations for works to the track and
associated reequipment.
2.2.4    In preparation for the next 3 phases of works, the project team: 
• have completed the Invitation to Tender (ITT) for the Construction of the dual
carriageway into Ravenscraig ready for publication during March.  The outcome
of the procurement will be reported to committee in due course.  It is intended
that the works will start in the autumn following City Deal and Committee
approval, and once the bridge is fully complete.  The delay to this tender has
been to allow design of additional works to improve safety for road users and
Non-Motorised Users at the existing roundabout by the Regional Sports Facility. 
Page 41 of 79

Page 42

• competed negotiations with the bridge contractor for advance preparatory works
for the new dual carriageway to both simplify the contractual relationship with
Network Rail and the Council during our works and to mitigate the impact of
time lost to the additional design work noted above
• negotiated to remove the one objection to the Compulsory Purchase Order to
allow the construction of the dual carriageway into Ravenscraig and continue to
seek to negotiate with all other owners and occupiers for the remaining land
required to deliver all parts of the Ravenscraig Infrastructure Access project.
Acquisitions are reported to, and approved as required by, Finance and
Resources Committee; and 
• have progressed refining and developing the detailed proposals for the dualling
of the A723 from Ravenscraig to the M8 at Holytown. 
2.2.5 Related to this project, a planning application has been approved, land acquired and
site clearance works commenced on the alternative location for the Evans Halshaw
Ford car dealership. The dealership will relocate to part of the nearby former Taggarts
site which has laid vacant for some time. This will allow the existing Evans Halshaw
Ford car dealership to be retained within Motherwell whist facilitating the new road
connection between Motherwell and Ravenscraig. The new dealership will occupy the
front part of the site with the rear part of the site being made available for residential
development, potentially as part of the council’s new supply programme. 
2.3  East Airdrie Link Road 
2.3.1  East Airdrie Link Road will provide a new strategic link between the M8 and south
Cumbernauld.  Following a detailed Stage 2 option appraisal, and a further review of
the emerging option, a preferred route has now been agreed.  Feedback from an earlier
Stage 2 public consultation was reviewed and additional options were assessed at the
northern section of the proposed link road.  Further public consultation has taken place
from 28 November to 23 January (8 weeks) on the preferred route and on the
environmental report as part of the Strategic Environmental Appraisal.  The feedback
and comments from this consultation will be full considered moving into Stage 3 as the
specimen design and planning application is developed.   
2.3.2 As previously reported, a section of the preferred route has been realigned to
accommodate the proposed Monklands Hospital replacement project.  The project
team continue to liaise with NHS Lanarkshire to ensure coordination, secure
efficiencies and to maximise benefits. 
2.3.3 In line with previous approvals, the procurement for professional services for the
development of the specimen design for the road, preparation of the planning
application and the collation of the outline Business Case has commenced. It is
intended that the ITT will be issued in March 2023 and awarded in August 2023, subject
to committee approval.  The outcome of this procurement activity will be brought back
to Committee in line with General Contract Standing Orders.   
2.3.4 The programme for the development and delivery of the EALR has been reviewed both
technically and following changes to the Monklands Replacement Hospital programme,
whereby the proposed hospital at Wester Moffat is anticipated be opened during 2031. 
The EALR programme now anticipates that the link road will be constructed between
2028 and 2030.  This is to accommodate complex design and planning requirements,
technical and business case approvals, land acquisition (both through voluntary and a
proposed compulsory purchase order) and critically to align with the Monklands
Hospital programme.  The revised programme will ensure that both projects are aligned
to minimise risk around funding approvals, technical consents and physical
Page 42 of 79

Page 43

construction interface.  It is intended that the outline business case will be submitted to
Committee and GCR Cabinet in Q4 23/24 to secure the city deal funding for the
significant development work prior to full business case in Q3 27/28.   
2.4 Orchard Farm Roundabout 
2.4.1 The ‘A8/M8 Corridor Access Improvements’ Outline Business Case (OBC) including
the Orchard Farm Roundabout was approved by the GCR Cabinet on 30 August 2022. 
As reported, the scope of the Orchard Farm Roundabout project comprises a financial
contribution of £2m to the developer for the construction of the junction on the A8. 
2.4.2  The Orchard Farm Roundabout is a new junction on the A8 All Purpose Distributor
Road and critically supports the development of the Mossend International Rail Freight
Park (MIRP) and provides important access to a number of development sites to the
north of the A8/M8.   
2.4.3  MIRP is a low carbon rail-based infrastructure project with a significant co-located
logistic park development. Peter D Stirling Limited (railfreight terminal
operator/landowner) and Mount Park (new landowner) seek to develop the Mossend
Railfreight Terminal into a European scale railfreight terminal and distribution park with
all-electric facilities. MIRP is one of very few sites within the UK that can offer integrated
multi-modal logistics of this scale, quality and economic value. The MIRP supported
the bid for the Clyde Green Freeports. 
2.4.4  The proposed Full Business Case (FBC) for the new junction will be underpinned by a
funding agreement between the council and the developer/s and will establish funding
arrangements, obligations and key milestones.  The remainder of the costs and any
associated delivery risks relating to the delivery of the infrastructure will be met by the
developer/s.  The infrastructure will form part of the strategic road network and will fall
under the responsibility of Transport Scotland.   
2.4.5   It is proposed to submit the Full Business case (FBC) for the Orchard Farm Roundabout
for approval to the GCR Chief Executive’s Group in August 2023.  The FBC will report
on the procurement of the new Junction and associated works and is the final stage in
the funding approvals to allow for contract award and the delivery of the infrastructure
to progress.  Agreement will be sought from Committee to submit the FBC to the GCR
Chief Executives Group for approval.  This would allow for works to commence in late
autumn 2023, with the intention that the works would be complete in October 2024. 
2.5 A8/M8 Corridor Strategic Active Travel 
2.5.1 The provision of Strategic Active Travel Links, connecting Eurocentral/Maxim Office
Park/Newhouse and Mossend to surrounding local communities and local rail stations
was approved by GCR Cabinet on 30 August as the new preferred option for the
Eurocentral sub-project.   
2.5.2 The routes identified are to the south of Eurocentral between Bellshill Rail Station/town
centre and the M8 cycle route at North Road; Bellshill town centre, Mossend and
Holytown, connecting into Eurocentral from Holytown and between Holytown and
Newhouse. To the north of Eurocentral, a route has also been identified from Whifflet
rail station to the M8 cycle route at Shawhead. These routes are designated as
Strategic Network Routes within the North Lanarkshire Active Travel Strategy. 
Page 43 of 79

Page 44

2.5.3 In total, it is aimed to deliver 10km of shared use walking and cycling routes with City
Deal investment. The routes link with other planned active travel route improvements
as part of the Ravenscraig Infrastructure Access and East Airdrie Link Road projects
and with other projects being developed by the Infrastructure and Transportation
Service. There are also opportunities to seek match funding from other external funding
sources to expand the scope of the project to connect more communities to
employment opportunities. 
2.5.4 Further feasibility and design work has been taking place to develop the active travel
routes. It is planned to appoint consultants to progress detailed design work in early
spring 2023. It is then intended, subject to Committee approval, to submit the sub-
project Full Business Case in Spring 2024 and commence work on site in Summer
2024. 
3. Measures of success 
3.1 As the second largest Local Authority within the GCR, North Lanarkshire’s residents
and businesses will directly benefit from the City Deal through: 
• creation of 2,000 new workplace jobs, representing a 1.6% uplift in the future jobs
growth forecast for North Lanarkshire;
• a significant share of some 15,000 temporary construction jobs anticipated to be
generated by the development of the Infrastructure Investment Fund projects –
construction being a predominant local employment sector; 
• estimated 9.2% of North Lanarkshire working age residents having heightened
access to employment opportunities within the wider GCR area;
• additional tender opportunities as a result of GCR City Deal investment for North
Lanarkshire Business and SME’s;
• community benefits derived from all GCR City Deal contracts awarded over
£50,000; and
• a proportionate share of the £2.2bn per annum Gross Value Added (GVA) increase
in the GCR area over the lifetime of City Deal, equivalent to 4% uplift in the region. 
4. Supporting documentation  
4.1  No supporting document presented. 
Pamela Humphries 
Chief Officer of Place 
Page 44 of 79

Page 45

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The City Deal Cabinet has agreed that Inclusive Growth is to be fully embedded
within the GCR City Deal programme delivery and that it is also committed to
supporting the delivery of the Fairer Scotland Action Plan.  Future NLC subproject
OBC/FBC development will be scrutinised to ensure it meets the duties of the
Fairer Scotland Action Plan.   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The North Lanarkshire Council City Deal Programme approved funding allocation
across the 3 headline projects is as: 
• A8/M8 Corridor Access Improvements £6,478,521 
• Glenboig Link Road (complete)  £6,223,205
• Pan-Lan Orbital Transport Corridor  £224,696,493 
The City Deal funding comprises funding from the GCR City Deal Infrastructure
Fund (£148,956,293) and North Lanarkshire Council (£88,441,926). The financial
implications of the City Deal Programme are incorporated within the Council’s
Long-term Financial Plan and to date budgetary implications have been approved
by the Policy and Strategy Committee. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☒ No ☐
Page 45 of 79

Page 46

If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The City Deal Team work closely with Legal Services on all sub projects focusing
on land acquisition and CPO, procurement and contract preparation and
management, funding agreements and any other related matters. 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
All infrastructure projects developed by the Council as part of the GCR City Deal will
be subject to relevant environmental and sustainability appraisal and as part of
subsequent planning application approvals and procurement.   
Furthermore, to adhere with HM Treasury Greenbook best practice, each iteration of
project business case seeking GCR City Deal funding will include a review of the
sustainability considerations, this will include carbon management, involving
categorisation, assessment and mitigation. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Page 46 of 79

Page 47

The City Deal programme and the delivery of the projects will continue to be
promoted through Corporate Communications and the Glasgow City Region’s
Communications team.   
Specific to Muir Street Improvements, a joint communications group with Scotrail,
Transport Scotland and North Lanarkshire Council has been set up to coordinate
communication and promote the Motherwell Station redevelopment and the City
Deal Muir Street improvements.   
In terms of East Airdrie Link Road, a joint communication plan will be developed
with NHS Lanarkshire and North Lanarkshire Council to coordinate communication,
stakeholder engagement and promote the projects as they develop.   
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
A key risk for the City Deal Programme is the current global economic climate and
its short and long term impacts on the delivery of the city deal projects.  This risk is
becoming a live issue for the Programme and will be assessed and recorded within
the City Deal Issues Register. This is not unique to City Deal and the approach to
this risk and issue management will be carried out in conjunction with Finance and
the Glasgow City Region Project Management Office.   
Risk management of North Lanarkshire’s City Deal activity is incorporated within
the council’s City Deal programme risk register which is reviewed by the City Deal
Manager and reported to the council’s City Deal Board.  The City Deal risks are
also integrated in the Planning and Regeneration Service Risk Register.  Each City
Deal sub project has a detail risk register and is managed by the Project Manager.   
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
Page 47 of 79

Page 48

Page 48 of 79

Page 49

North Lanarkshire Council
Report
Enterprise and Fair Work Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  JO’N/PK Date 17/02/23 
Employability Update 
From  Janie O’Neill, Head of Education & Families (South)  
E-mail oneillja@northlan.gov.uk Telephone   07790 894444 
1. Background 
1.1 Driving up the employment rate in North Lanarkshire is a cornerstone of The Plan for
North Lanarkshire and ensuring employability support is available to all is recognised
as a major contributor to both local economic development and tackling poverty. 
Reducing poverty is central to each of these programmes and, in line with The Plan for
North Lanarkshire, including all residents in the economic growth of our area is viewed
Executive Summary 
This report provides an update on the decision by Committee at its meeting of 29th August
2022 to approve that steps are taken by Council officers to secure an extension of the
current EU funded employability programme from December 2022 until June 2023 and the
outcome of those actions.   The report also provides information on the measures in place
to ensure that the transition from EU funding to the Shared Prosperity Fund, as a key
source of external funding allocated to employability, provide continuity of these services
and meets the needs of our communities.  It also provides a brief update on the current
labour market in North Lanarkshire and the current and forthcoming challenges. 
Recommendations
It is recommended that Committee: 
(1) Note the outcome of the proposal to the Scottish Government that the current EU
funded employability programme is extended from December 2022 until June
2023. 
(2) Consider the information provided on the transition to the UK Shared Prosperity
Fund and the labour market in North Lanarkshire.  
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement
(11) Increase economic opportunities for adults by understanding,
identifying, and addressing the causes of poverty and deprivation
and barriers to financial inclusion
AGENDA ITEM 4
Page 49 of 79

Page 50

as central to the work on employability.  Over half of the Council’s employability support
to residents is funded from its EU funded programme through an agreement with the
Scottish Government.  This funding comes from the European Social Fund (ESF) and
the current programme, known in North Lanarkshire as ‘Prospects for You’, had an end
date of December 2022.   
1.2 In North Lanarkshire the programme is led and co-ordinated by the Council’s
employability team which also provides the key function of engaging employers onto
the programme.  Routes to Work Ltd are funded to provide specialised case worker
support to unemployed residents as well as support with accessing vocational training
and the short-term costs associated with moving from benefits to employment such as
childcare and travel.  They also provide in-work support for up to 6 months for those
participants that require it. The External Funding team within Enterprise and
Communities are also funded through ESF to provide a compliance and verification role
on the distribution of the funding.  The programme is co-funded by the Council and EU
with 46% of funding coming from the EU and has an annual cost of around £4.5 million
and funds the 82.44 fte staff delivering the programme as well as the other costs
associated with training for participants, wage subsidies to employers, childcare, and
vocational qualifications. 
1.3 In recent years employability support has also been significantly bolstered by increased
levels of funding from the Scottish Government through its No One Left Behind,
Parental Employment Support and Young Persons Guarantee funding and these have
been integrated and aligned with the existing EU programme to broaden its range and
deepen its penetration into under-represented groups in the labour market.   
2. Report 
2.1 As reported to Committee in August 2022, the Scottish Government had indicated to
North Lanarkshire Council that there was an opportunity to extend the operational
delivery of the EU funded employability programme from December 2022 until June
2023.  The negotiation has been undertaken with a reprofiling of the budget and
additional outcomes from the programme submitted to the Scottish Government and
the new end date of the programme is June 2023. The total cost from January to June
2023 of the extension is £1,796,750.  The EU, via the Scottish Government, will fund
46% of this total cost.  Therefore, the extension costs consist of EU grant of £826,505
and Council match funding of £970,245 coming from existing budgets allocated to
supporting externally funded employability projects with an additional 360 people
supported into fair and sustained employment as a result.     
2.2 The UK Government’s replacement for EU funds is the Shared Prosperity Fund and
the recent approval of North Lanarkshire’s investment plan, as part of the Glasgow City
Region bid, has secured broadly similar levels of funding for employability support in
North Lanarkshire until March 2025.   With the support of the Council’s Workforce for
the Future Steering Group, discussions have begun with the Council’s key delivery
partner, Routes to Work Ltd, the Local Employability Partnership and other Council
services to identify opportunities which are available within the remit of the new fund
that could lead to innovation in services while maintaining an employability service that
can meet the needs of all unemployed or economically inactive residents.    Examples
of where these innovations may be drawn from are: 
(i) New initiatives based on experienced gained in the delivery of two recent
Community Renewal projects delivered by Routes to Work Ltd and the
Supported Employment team, one of which was a place-based community
Page 50 of 79

Page 51

project in Airdrie Central that tackled economic inactivity and the other which
sought to engage increased numbers of people with disabilities into work. 
Evaluations of these projects are almost complete with clear indications that
both are very positive and can inform future work. 
(ii) Recent work, funded by the Scottish Government, with the local third sector in
North Lanarkshire has demonstrated their unique ability to engage with their
communities and draw them into the pipeline of employability support funded
by the Council. 
(iii) Further alignment and integration with the Education and Families Pathways
Programme for school leavers who may enter a negative destination. 
(iv) Targeted support on young people with additional support needs who aspire to
enter employment on leaving school delivered by the Supported Employment
team. 
2.3 In terms of the labour market the story of North Lanarkshire over the last 18 months
has closely reflected that of the Scottish and UK markets over that period.  Far from
the high levels of unemployment and redundancies that were expected to result
because of the restrictions placed on the economy by the pandemic, a complete and
unprecedented reversal in the labour market occurred in the last 18 months resulting
in an inadequate supply of labour and with all sectors struggling to fill existing vacancies
and it became clear that a major factor in this shortage of workers was due to people
leaving the labour market.   
2.4 The North Lanarkshire claimant count, which acts as a measure of unemployment, was
14,415 (6.6%) people in March 2021 compared with 8,225 (3.8%) in March 2020, a
75% increase on the pre-pandemic level.   However, in December 2022 it had
decreased to 7,420 (3.4%) and average earnings in North Lanarkshire are now above
the Scottish and UK averages for the first time.  This is good news but real challenges
remain due to levels of economic inactivity.  The number reported as ‘long term sick’ in
North Lanarkshire has increased from 14,900 in the 12 months up to December 2019
to 28,400 in the 12 months up to September 2022 and the number reported as ‘looking
after family/home’ in the Council area increased from 8,500 to 9,600 in the same period. 
While unemployment is lower than pre-pandemic levels the number of people in the
workforce in North Lanarkshire has reduced from 174,000 (78.1%) in December 2019
to 156,500 (68.8%) in September 2022.   Throughout 2023 unemployment is expected
to rise again as the UK enters recession and high inflation continues to hinder economic
growth.  From an employability perspective this simply reinforces the need to continue
to support those further from the labour market in North Lanarkshire to gain the skills
needed to get a job and continue to work with employers to create opportunities for our
unemployed residents, including those who are economically inactive. 
2.5 In terms of the Council’s strategic response the Employability team play a role within
the Workforce for the Future, Programme of Work P077.1, which has a broad range of
workstreams focused on ensuring that every resident has access to the support and
advice they need to secure fair and sustained employment or training in North
Lanarkshire.  This group is also engaged with employers to make sure that the advice
and support delivered meets their current and future needs in terms of skills and labour
supply.   A key contribution made by the team is also to the Programme of Work P005.2,
Tackling Poverty through its work on increasing residents’ incomes from employment
and specifically through its work on Parental Employment Support to combat child
poverty.
Page 51 of 79

Page 52

3. Measures of success 
3.1 The extension to the EU funded programme is fully utilised to support employment in
North Lanarkshire. 
3.2       The transition to funding employability services from the UK Shared Prosperity Fund is
seamless for unemployed residents seeking support.   
4. Supporting documentation 
Janie O’Neill
Chief Officer for Education (South) 
Page 52 of 79

Page 53

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☒ 
If Yes, please provide a brief summary of the impact? Equality Impact Assessment
will be developed in tandem with the development of the Shared Prosperity Fund
project plan.   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
Council resources to match fund the EU activity is from NLC Match Funding
allocated to employability projects and these will also be used to support Shared
Prosperity activities. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
Page 53 of 79

Page 54

5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed?
The service risk register encompasses those risks related to external grant funding. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
Within all Council employability programmes ex-services personnel are
immediately eligible for support alongside other priority groups. 
Page 54 of 79

Page 55

North Lanarkshire Council
Report
Enterprise and Fair Work Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref    PH/DG Date 17/02/23 
Vacant & Derelict Land Fund 
From  Pamela Humphries, Chief Officer of Place  
E-mail Greerd@northlan.gov.uk Telephone
David Greer, Growth
Programme Manager:
07583059816 
Executive Summary
Since 2006, North Lanarkshire Council has received funding through the Scottish
Government’s Vacant and Derelict Land Fund (VDLF) Programme to support the
remediation and re-use of long-term vacant and derelict land sites within North Lanarkshire. 
The award of this annual grant is subject to the submission of a VDLF Local Delivery Plan
(LDP) and its approval both by committee and the Scottish Government. 
In 2020, the Scottish Government approved the award of £0.656M to be used to allow
Scottish Canals to take forward the restoration of Craigmarloch Stables (Kilsyth) for
potential end use as holiday accommodation. 
Due to funding implications, this project could not be taken forward. The council has
reviewed alternative opportunities for the regeneration of this building but any potentially
viable project could not be delivered within the timescales required by this fund. 
As such, it is proposed that this budget is reallocated to support enabling works for the
development of new industrial units at Link Park (Plot 1), Newhouse. This work would be
contractually committed before financial year end and ensure that this funding award is
safeguarded. 
This reallocation has been approved by the Scottish Government. A range of other
potential funding sources would be sought for the regeneration of Craigmarloch Stables if
a potential viable use for these buildings was to be identified. 
On January 17th 2023, the Scottish Government also confirmed that North Lanarkshire
would be allocated £1.841M VDLF for 2023/24 subject to the submission and approval of 
a 2023/24 VDLF Local Delivery Plan (LDP). This report outlines projects currently being
considered as part of this LDP and seeks approval to advance and submit this bid
accordingly by the end of March 2023. 
AGENDA ITEM 5
Page 55 of 79

Page 56

Recommendations
It is recommended that committee: 
1. Approve the reallocation of Vacant and Derelict Land Fund monies from ‘the
regeneration of Craigmarloch Stables’ towards enabling works for a new industrial
unit at Link Park, Newhouse Industrial Estate. 
2. Approve the projects which are being assessed for inclusion within the 2023/24
VDLF Delivery Plan which is to be submitted to the Scottish Government by the end
of March. 
3. Note that an update on the proposals for the 2023/24 VDLF funding allocation will
be reported to the next committee.   
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement 
(5) Grow and improve the sustainability and diversity of North
Lanarkshire's economy
Page 56 of 79

Page 57

1. Background 
1.1  The VDLF is a ring-fenced annual capital grant allocation which provides financial
support from the Scottish Government to assist with the regeneration of registered
vacant and derelict land (V&DL) sites across selected local authority areas. 
1.2  Funding provided through the VDLF Programme is subject to the submission (and
approval by the Scottish Government) of a LDP which sets out local authority
investment proposals to meet the objectives of the VDLF Programme. 
1.3  These objectives are to: 
• tackle long term vacant and derelict land (and in particular sites which have been
registered as vacant or derelict for at least 15 years);
• stimulate economic growth and job creation; 
• develop a diverse sustainable environment with a focus on temporary and permanent
greening; and 
• support communities to flourish and tackle inequalities 
1.4  There is a range of activity which this fund cannot support including: major
infrastructure works, retail and housing projects. 
2. Report 
2.1 In January 2020, the council was awarded a 2020/21 VDLF capital grant of £1.956M
subject to the submission of a VDLF Local Delivery Plan and its approval by the Scottish
Government. 
2.2 As part of this approval, both committee and the Scottish Government agreed that
£656,000 should be used to support Scottish Canals to take forward the regeneration
of the derelict Craigmarloch Stables (Kilsyth) for use as holiday homes. 
2.3 Scottish Canals were not able to take this forward. In turn, Scottish Government
approval has had to be sought twice to carry-forward this grant (terms and conditions
of grant require spend within financial year of approval unless dispensation is sought
to carry this forward). 
2.4 Given that the original project could not be carried out, North Lanarkshire Council has
investigated alternative proposals for the reuse of this building. However, with lack of
match-funding availability (given likely costs associated with the regeneration of this
derelict building) and timescales associated with securing funding and finalising design
and procurement, it was considered that any contractual commitment of this fund would
likely take several years. 
2.5 To avoid potential payback of this grant, it is proposed that this grant is used to address
a shortfall for enabling works for industrial development works at Link Park, Newhouse
Industrial Estate (works currently being taken forward by Fusion Assets – the council’s
arms-length economic regeneration and property development company). 
2.6 This reallocation would allow works to be completed in full at Link Park and ensure that
the £656,000 would be contractually committed by year end in line with the original
grant offer and permissions granted to extend this spend.  The Scottish Government
has approved the reallocation of this funding.
Page 57 of 79

Page 58

2.7 It should also be noted that there are currently a number of alternative funding sources
available that could support the future regeneration of Craigmarloch Stables (including
the Scottish Government’s Regeneration capital Grant Fund and Vacant and Derelict
Land Investment programmes, Historic Environment Scotland Grant Funding and
Heritage Lottery Funding) and the council will continue to work with the owners of this
building (Scottish Canals) to secure these when viable schemes are in place. 
2.8 On the 17th January 2023, and following the Scottish Government Budget
announcement in December 2022, £1.814M capital grant funding for the remediation
of V&DL was awarded to North Lanarkshire Council subject to the submission and
approval of a 2023/24 VDLF LDP. 
2.9 The Local Delivery Plan is currently being progressed and the following projects are
being assessed for viability:
• further enabling works at Ravenscraig Business Park to support the first phase of
industrial development at this site;
• further enabling works at Condor Park (Eurocentral) to support the first phase of
industrial development at this site; and
• feasibility studies (including ground investigation works) to support the potential future
development of vacant and derelict sites by Fusion Assets. 
These projects would be progressed and delivered by Fusion Assets, the council’s
arms length regeneration company. 
2.10 Approval is sought to finalise evaluation of the projects outlined in 2.9 above to enable
the submission of the 2023/24 VDLF Local Delivery Plan by the end of March.  An
update will be provided to the next Committee. 
3. Measures of success 
3.1  Future economic and employment benefit gained from the reallocation of VDLF from
the ‘restoration of Craigmarloch stables) towards the development of new industrial
units at Link Park. 
3.2  Future economic and employment benefit gained from the investment of the council’s
allocated 2023/24 VDLF award made from the Scottish Government. 
4. Supporting documentation 
N/A 
Pamela Humphries
Chief Officer of Place 
Page 58 of 79

Page 59

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes x No ☐ 
If Yes, please provide a brief summary of the impact? 
The reallocation of this funding will support the development of new industrial
infrastructure (via Fusion Assets) and in turn new local employment opportunity. 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☒
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
The award of a further year of VDLF funding will help support the delivery of the
Economic Regeneration delivery Plan, and specifically the remediation of vacant
and derelict land. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Page 59 of 79

Page 60

Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
If funding is not reallocated, potential exists that any non-contractually committed
funding could be reclaimed by the Scottish Government. This is identified as
general risk on service risk register 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
Page 60 of 79

Page 61

North Lanarkshire Council
Report
Enterprise and Fair Work Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref PH/DG Date 17/02/23 
External Funding - update 
From  Pamela Humphries, Chief Officer of Place  
E-mail humphriesp@northlan.gov.uk Telephone Pamela Humphries, 07939
280710 
Executive Summary 
This report provides an update on significant recent external funding activity, related to the
UK Government’s Levelling Up Fund, UK Community Renewal Fund and UK Shared
Prosperity Fund, Scottish Government’s Green Growth Accelerator programme and
Regeneration Capital Grant Fund and heritage funding programmes managed by Historic
Environment Scotland and National Lottery Heritage Fund.   
Recommendations 
It is recommended that committee acknowledges: 
a) The award of £9,225,000 from the Levelling Up Fund to support the delivery of the
Cumbernauld Town Vision.
b) The completion of UK Community Renewal Fund projects and the work currently
being undertaken to administer funds and evaluate projects.
c) Confirmation of the Council’s UK Shared Prosperity Fund allocation and plans for
its use.
d) Progress made towards submitting a final Business Case aimed at securing £10m
in revenue support from the Green Growth Accelerator programme.
e) The award of £215,000 from the Regeneration Capital Grant Fund to support
Motherwell FC Community Trust’s ‘The Well Hub’ project.
f) The submission of bids to both Historic Environment Scotland and National Lottery
Heritage Fund for the heritage-led regeneration in Airdrie. 
The Plan for North Lanarkshire
Priority  Improve economic opportunities and outcomes
Ambition statement (21) Continue to identify and access opportunities to leverage
additional resources to support our ambitions
AGENDA ITEM 6
Page 61 of 79

Page 62

1. Background 
1.1 The Council aims to secure external funding to support the physical, social and
economic regeneration of North Lanarkshire. This work is subject to regular reporting
to committee, most recently to the Enterprise, Fair Work and Growth Committee on 29
August 2022. 
1.2 There has been significant recent activity across a range of funding streams. This report
provides an interim update on progress towards securing a range of funds to support
the social, physical and economic regeneration of North Lanarkshire. 
2. Report 
2.1 This report provides an update on current external funding activity, including recent
funding bid submissions and decisions. 
Levelling Up Fund 
2.2 The Council submitted four bids to the second round of the UK Government’s Levelling
Up Fund (LUF), with one bid submitted for each of North Lanarkshire’s four UK
Parliamentary constituencies. 
2.3 A bid for £9.225m in UK Government support to acquire The Centre Cumbernauld and
demolish Fleming House was approved, which will enable the future redevelopment of
Cumbernauld town centre in line with the approved Cumbernauld Town Vision. 
2.4 Bids for funding to support town centre living in Airdrie; for the mixed-use
redevelopment of Ravenscraig, and for the redevelopment of Summerlee Museum of
Scottish Industrial life were unsuccessful. The UK Government has since confirmed
that local authorities would only be eligible for one successful project across the first
two rounds of the Fund. 
2.5 UK Government advises that a further round of LUF will be launched later in 2023. A
fuller update will be provided to committee when further details are available.   
UK Community Renewal Fund 
2.6 The UK Community Renewal Fund (UKCRF) was established following Brexit to
support the transition from European Structural Funds to the UK Shared Prosperity
Fund. It supports public, private and third sector organisations to deliver projects across
four themes (communities and place; employment; local business; and skills). NLC has
managed the UKCRF in North Lanarkshire, including assessing bids and administering
grant funding. 
2.7 Five projects were funded through the UKCRF with each completing by the end of
December 2022. The Council is currently conducting final due diligence, including
verifying financial claims.   
2.8 Each of the projects have procured independent consultants to conduct evaluations,
which must be submitted and approved before financial claims can be approved.
Reports for three of the five projects have been submitted to the UK Government and
the Council expects to submit the final two reports during February 2023, enabling
funds to be disbursed. 
Page 62 of 79

Page 63

UK Shared Prosperity Fund 
2.9 The UK Shared Prosperity Fund replaces the EU Structural Funds which come to an
end in 2023.  The council was allocated £13.871m from the UK Shared Prosperity Fund
(UKSPF) to deliver projects across four key themes (Communities and Place; People
and Skills; Supporting Local Business; and Multiply) for spend between 2022/23 and
2024/25, subject to approval of a UKSPF Investment Plan. North Lanarkshire’s
Investment Plan, which formed part of the wider Glasgow City Region Investment Plan,
was approved by the UK Government on 5 December 2022. 
2.10 Table 1 below sets out the proposed split of UKSPF funding over the three years of the
Investment Plan. The Investment Plan was approved by Enterprise, Growth and Fair
Work Committee on 29 August 2022.  It should be noted that support for adult
numeracy, through the Multiply programme, was allocated on a ring-fenced basis. 
Table 1: UK Shared Prosperity Fund: approved allocation by theme
Theme 2022/23 2023/24 2024/25 Total
Community and Place £506,427 £350,000 £2,265,000 £3,121,427
People and Skills £739,000 £1,577,854 £3,072,976 £5,389,830
Supporting Local
Business
£91,541 £746,083 £1,667,738 £2,505,362
Multiply £695,223 £802,181 £802,181 £2,299,585
Admin/Management £84,675 £144,838 £325,329 £554,842
Total £2,116,866 £3,260,955 £8,133,224 £13,871,046 
2.11 The arrangements for the delivery of the programmes will be the subject of future
reports to relevant committees as appropriate. 
Green Growth Accelerator 
2.12 The Green Growth Accelerator (GGA) programme will support local authorities to
deliver innovative green infrastructure projects which contribute to Net Zero objectives
and can stimulate the green economy. The Council made a successful application for
GGA pathfinder support for the low-carbon redevelopment of Strathclyde Country Park
during 2021, enabling NLC to commission design works and technical support to inform
a full application for up to £10m in GGA funding. 
2.13 A GGA Business Case in support of this application was prepared and submitted to
Scottish Government at the end of September 2022. This has been subject to a full
technical review by Scottish Government and its appointed consultants. Officers are
currently finalising a revised Business Case and formal application for GGA support,
which will be submitted during February 2023. It is anticipated that a formal decision on
this application will be made in the Spring. 
Regeneration Capital Grant Fund 
2.14 The Regeneration Capital Grant Fund (RCGF) supports physical regeneration projects
in local communities. It is open to local authorities, which can apply for funding for
Council projects and on behalf of community groups. 
Page 63 of 79

Page 64

2.15 Funding decisions for Round 10 of RCGF Council were announced in January 2023,
for projects commencing during 2023/24. The Council secured funding for one project,
with Motherwell FC Community Trust receiving £215,000 to establish ‘The Well Hub’ at
the astrograss pitches adjacent to Fir Park Stadium. The Council will work with the
Trust to administer grant funding and support the project’s delivery. 
2.16 Officers have invited expressions of interest from community groups for Round 11 of
the Fund, with ‘Stage 1’ bids due during June 2023, and will continue to engage with
prospective applicants in the coming months. 
Historic Environment Scotland/National Lottery Heritage Fund 
2.17 During 2022, Historic Environment Scotland (HES) and National Lottery Heritage Fund
(NLHF) aligned funding for place-based heritage interventions and invited applications
from constituted organisations and local authorities under their respective Grants for
Heritage (NLHF) and Heritage and Place (HES) programmes. 
2.18 The council successfully submitted expressions of interest to both funds for support to
deliver the heritage-led regeneration of Airdrie and were invited to make ‘development
phase’ applications by both funders, which were submitted in late 2022. These bids
sought a total of £150,000 funding to resource the council to develop full ‘delivery
phase’ bids over a 12-month period, with an indicative £2.65m sum identified for
delivery phase bids. These bids are currently being assessed with funding decisions
expected in March (NLHF) and April (HES). 
2.19 A further bid to NLHF to support redevelopment work at Summerlee Museum of
Scottish Industrial Life is currently being considered. This prospective bid will seek
funding for both capital works and for revenue funding to employ dedicated learning
and engagement staff. 
2.20 Officers will continue to engage with heritage funders with a view to securing further
investment into North Lanarkshire’s places and economy. 
3. Measures of success 
3.1  The primary measure of success arising from the work and updates outlined in this
report is to maximise external funding for investment in the regeneration of North
Lanarkshire and its places.   
4. Supporting documentation 
n/a 
Pamela Humphries
Chief Officer of Place 
Page 64 of 79

Page 65

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact?
The funding programmes outlined in this report are very much focused on promoting
inclusive growth and a fairer Scotland and will do so by: 
 Delivering physical regeneration projects that will improve the local
environment and tackle problems which continue to constrain community
regeneration
 Creating infrastructure that will help improve health and well-being and
provide North Lanarkshire’s most disadvantaged communities with new
leisure, learning and economic opportunity, and
 Ensuring that our place-based investments are shaped by the needs and
aspirations of all of our local communities. Consideration will also be given to
equalities issues as part of the bids and projects developed in response to
the identified funding opportunities whilst the council will also work closely
with ALEOs, partners and third-party organisations involved in the delivery of
these to ensure that equality considerations remain core throughout.
 Delivery of support to strengthen local communities, support local businesses
and support people to increase their employability and skills through the
UKSPF. 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☒
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Many of these funding opportunities outlined in this report require at least some
element of match funding.  Council match is identified in the Council’s capital
programme prior to the submission of any bids. The successful LUF bid for
Cumbernauld will require £1,025,000 in match from the council and provision has
already been made for this within the capital programme. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
Page 65 of 79

Page 66

5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☒ No ☐
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☒ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Work is underway with Legal Services to complete a DPIA for the UKSPF
Investment Plan 
Yes ☐ No ☒
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The UKSPF contains interventions which seek to improve connectivity for community
organisation, support digital transformation for businesses and to delivery digital
skills. 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Success in securing GGA, LUF and other funding can enable environmental
improvement. Subject to funding, the GGA project will provide a flagship low carbon
project for North Lanarkshire. 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact?
Page 66 of 79

Page 67

The Council’s success in securing external funding for priority regeneration projects
is promoted and coordinated by Corporate Communications. 
Strict guidelines are in place for the promotion of funding through the UKCRF and
UKSPF. 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
External funding programmes do bring a measure of risk to the council particularly in
relation to potential budget overspend for projects and/or the requirement to repay
funds due to failure to deliver projects properly (a risk which is increased where
delivery is through a third party). To help reduce and mitigate risk, a full risk
assessment is undertaken for all funding programmes and/or externally funded
projects as part of the council’s project management process and where
complex/high risk projects are being developed or delivered, risk workshops will be
set up to ensure all service and partner risks are identified. 
Page 67 of 79

Page 68

Page 68 of 79

Page 69

North Lanarkshire Council
Report
Enterprise and Fair Work Committee 
Does this report require to be approved? ☐ Yes ☒ No
Ref: PH / DG Date: 17 February 2023 
Contract Award for Braidhurst Industrial Estate Design Team 
From  Pamela Humphries, Chief Officer of Place 
E-mail greerd@northlan.gov.uk Telephone David Greer, tel 07583 059816 
Executive Summary 
This report is to advise the Enterprise and Fair Work Committee (the ”Committee”) of the decision
taken in accordance with condition 21.3.2 of the Council’s General Contract Standing Orders
(GCSO’s) where outwith the committee cycle, the Depute Chief Executive approved the award of a
contract for Braidhurst Industrial Estate Design Team (the ‘Contract’) to Collective Architecture
Limited 
The Contract was approved by the Depute Chief Executive on 10 January 2023 and was formally
awarded on 11 January 2023. The Contract is for an initial period of 24 months and commenced
on 12 January 2023. The Council reserves the right to extend the Contract for additional periods up
to a maximum of a further six (6) months. 
The value of the Contract shall not exceed six hundred and thirty thousand pounds sterling
(£630,000) exclusive of VAT. 
Recommendations 
It is recommended that Committee:- 
1. notes the award of the Contract in accordance with GCSO 21.3.2 to Collective Architecture
Limited to the maximum value of six hundred and thirty thousand pounds sterling (£630,000)
exclusive of VAT. 
The Plan for North Lanarkshire 
Priority Improve economic opportunities and outcomes 
Ambition Statement (3) Maximise the use of our marketable land and assets through improved
development in business and industrial infrastructure 
AGENDA ITEM 7
Page 69 of 79

Page 70

1. Background 
1.1 Braidhurst Industrial Estate is a well-established 4.4-hectare estate situated off Bellshill Road
in a prominent location approximately one mile to the north-west of Motherwell town centre.  
1.2 The estate has a high occupancy rate with a range of trade and industrial units of varying
sizes. Some of the units are of poor quality and are tired and dated in appearance whilst the
surrounding environment is unappealing. 
1.3 An initial feasibility study for Braidhurst Industrial Estate was commissioned in 2019 to identify
the key elements for a regeneration project, the potential costs and an outline programme. 
1.4 The objective was to upgrade Braidhurst Industrial Estate by improving infrastructure and
facilities to make it a more attractive location for businesses due to the improved provision of
high-quality business and industrial space. 
1.5 There is also an area of vacant and derelict land at the end of Newhut Road that will be used
for the construction of 10 new start up industrial units. 
1.6 This information was utilised to inform an external funding application to the Scottish
Government’s Regeneration Capital Grant Fund (RCGF) in 2020. 
1.7 The initial application to the RCGF was rejected in early 2021 and feedback was sought from
the Scottish Government. This enabled specific areas of the application to be improved upon
and the revised enhanced application was subsequently submitted in late 2021. 
1.8 The revised application was approved in early 2022 with an award of £1.8m towards a total
project cost of circa £5m. It was a requirement of the award that the project be “contractually
committed” by the 31st March 2023. This requires a contract to be in place with a main
contractor to deliver the works prior to the end of the financial year. 
1.9 In order to fulfil this, a multi disciplinary design team led by an architect required to be
identified, appointed and undertake the required design works to enable a main contractor to
price the works and enter into a contract prior to 31st March 2022. 
1.10 The design team will include the following consultants:- 
• Architect / Principal Designer – Develop and prepare architectural drawings and
specifications, act as Principal Designer, production and submission of all statutory
applications, application for Health and safety (H&S) documentation, act as lead
consultant
• Quantity Surveyor – Preparation of detailed cost estimate, preparation and reporting
of cost reports, evaluation with recommendations of works contractor tender,
preparation of valuations for payment to contractor, agree final accounts
• Project Manager / Contract Administration – Co-ordination of design team, chair and
report on Design Team Meetings, undertake contract administration duties acting as
NEC Project Manager including issue of instructions as required, project risk analysis
and reporting, preparation of tender documentation for works contractor, programme
management, regular site inspections during construction, agree / monitor final
defects schedule, issues Certificate of Completion
• Structural / Civil Engineer – Develop and prepare structural / civil drawings and
reports
• Mechanical and Electrical (M&E) Engineer – Develop and prepare mechanical /
electrical drawings and reports 
Page 70 of 79

Page 71

• Energy Consultants – Assessment, evaluation and reporting of Net Zero Carbon
Modelling, preparation and reporting of Embodied Carbon Assessment
• Clerk of Works – Oversee site works, attend regular site inspection visits to ensure
works are carried out in general accordance with the contract drawings 
• H&S Advisor – Manage H&S compliance including review of Contractor’s Method
Statements and Risk Assessments 
1.11 The project will involve improving the infrastructure and facilities at Braidhurst Industrial
Estate to make it a more attractive location for businesses due to the improved provision of
high-quality business and industrial space. This will include new road and footpath, new
lighting, new car parking including EV charging points and improved boundary treatments for
the site. 
1.12 The existing occupied North Lanarkshire property (NLP) units will be refurbished and the area
of vacant and derelict land at the end of Newhut Road will be used for the construction of 10
new start up industrial units. 
1.13 The procurement of the consultant design team has followed an approval by the Head of
Planning and Regeneration (now Chief Officer of Place) on 27 May 2022 to commence
procurement, following agreement of the procurement strategy and funding approach. 
1.14 This report deals with the appointment of the design team and the appointment of the main
contractor will be the subject of a future report to committee. 
2. Report 
2.1 Following confirmation of the RCGF award, an internal user intelligence group (the ‘UIG’) of
technical and procurement representatives was formed following the confirmation of the
RCGF monies to review technical specifications, discuss trading processes, market
conditions and trends, ways to maximise community benefits and sustainability and to agree
the procurement strategy that would deliver maximum benefit for the Council via the Contract. 
2.2 The feasibility study had provided an initial estimated value of the Contract which detailed
that the procurement procedure would require to be undertaken in accordance with the Public
Contracts (Scotland) Regulations 2015. 
2.3 However, the timescales involved in a procurement process at this level would take a number
of months and would prevent the project from being “contractually committed” resulting in
the loss of the RCGF monies. In addition to this, the resources required to procure and
appoint individual consultants to provide the necessary specialist design and management
services required would also incur additional cost. 
2.4 Therefore, for the reasons outlined above, an appointment from an appropriate Framework
was considered to be the best approach in order to meet the Scottish Government funding
deadlines. 
2.5  Following consideration, the UIG identified the SPA Framework as being the most
appropriate framework to use. The procurement procedure was therefore undertaken as a
“Direct Award” from the Scottish Procurement Alliance (SPA) Construction Consultancy
(H1WS1) framework agreement (the “Framework”) 
2.6 Collective Architecture Limited are ranked 1st within the relevant lot for architecture led design
team on the SPA Framework. 
2.7 A scope of works was produced and issued to Collective Architecture for pricing for the
required services as outlined in points 1.9 to 1.12 above. The requirements of this particular
Page 71 of 79

Page 72

Contract have never been contracted by the Council before therefore exact historical contract
information was not available for consideration. 
2.8 However, the submitted tender was evaluated and confirmed overall as representing the most
economically advantageous tender for this Contract. 
2.8 Appendix 1 confirms the scoring achieved by Collective Architecture Limited within the SPA
Framework, further details of the procurement procedure is provided in Appendix 2 and the
SME status and location of all tenderers is located within Appendix 3. 
2.9 The value of the Contract is six hundred and thirty thousand pounds sterling (£630,000)
exclusive of VAT including any option to extend the Contract. 
2.10 The costs associated with contract delivery will be contained within the council’s capital
programme budget allocation for Planning and Regeneration. The RCGF monies will be
expended on the works. 
2.11 A full costed breakdown for the project will be provided following submission of the
contractor’s tender in February. 
Price Savings / Increases 
2.12 No savings are anticipated within the Contract. 
2.13 The Contract value is determined by the Framework fees and are calculated on the works
contract value. The works contract value for this project are £4m and the Framework band
that this project falls within is from £4m-£6m. 
Price Stability 
2.14 The prices are based on the Framework pricing schedule and are fixed for the entire duration
of the Contract. 
Community Benefits 
2.15 The procurement did not include a community benefit requirement as these will be included
in the associated works contract for the project which is being tendered for separately. 
Fair Work First  
2.16 Within their tender submission, Collective Architecture Limited advised that they will commit
to the Scottish Government’s “Fair Work First” initiative: 
Contract Strategy 
2.17 Officers from the Growth Team will be responsible for managing the Contract which will be
undertaken in accordance with the Councils agreed approach to contract and supplier
management. 
3. Measures of success 
3.1 The Contract will enable the delivery of the following outcomes; 
• Upgrade of Braidhurst Industrial Estate including the construction of 10 new start up
industrial units;
• upgrade of six existing North Lanarkshire Properties industrial units;
Page 72 of 79

Page 73

• provision of new car park with EV charging points;
• improved infrastructure including road and footpaths; and 
• lighting, drainage and installation of high-speed fibre broadband to improve the
economic viability of this industrial estate on the edge of Motherwell town centre. 
4. Supporting documents 
Appendix 1 Summary of Tender Evaluation Process
Appendix 2 Summary of Procurement Process
Appendix 3 SME Status and Location of All Tenderers 
Pamela Humphries
Chief Officer of Place 
Page 73 of 79

Page 74

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty  
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
Supporting Local Business
North Lanarkshire has lower levels of entrepreneurship than Scotland and UK on
average. Around 5.4% of people in employment in North Lanarkshire are classed as
self-employed. That’s about 8,100 individuals self-employed. This is significantly
lower than the Scottish rate of 10.3% and UK average of 12.4%. North Lanarkshire
requires a further 10,300 people to move into self-employment in order to level up to
the UK average. This project will provide 10 new start-up units which lend themselves
to use by new enterprises. 
Vacant and Derelict Land
North Lanarkshire has the largest area of Vacant and Derelict Land across
Scotland’s 32 local authorities with 1,354 hectares across 500 sites in 2021. This
represents a 14% share of the Scottish total. This project will remove 0.5 hectares
of Vacant and Derelict Land from the register. 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments 
Yes ☐ No ☒ 
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The project will require funding from North Lanarkshire Council and North
Lanarkshire Properties. The funding streams for both NLC and NLP have been
identified and secured and approval for spend has been obtained. The remainder of
the funding will come from the Scottish Government via the Regeneration Capital
Grant Fund, which was awarded in January 2022, and the Place Based Investment
Programme. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
Page 74 of 79

Page 75

5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The project will include the installation of high-speed fibre broadband to the
Industrial Estate which will help to secure the financial viability of the businesses on
the estate by future proofing the infrastructure improvements. 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The proposed upgrade works include an element to reduce carbon emissions by
insulating the existing six North Lanarkshire Properties industrial units, and the
provision of solar panels, smart lighting and low energy technology in the ten new
start up units being constructed. EV charging points will also be installed on the
estate. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact?
Page 75 of 79

Page 76

Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
The Scottish Governments Regeneration Capital Grant Funding and Place Based
Investment Fund have conditions attached that the works contractor must be
contractually committed by the end of March 2023 in order for the Council to be able
to draw down funding. 
This is recorded within the project risk register. We are on target to meet this funding
requirement. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
Page 76 of 79

Page 77

Appendix 1 – Summary of Tender Evaluation Process 
Final
Rank Tenderer Name
Total
Tender
Score (%)
Recommended
for Contract
Award (Y / N)
1 Collective Architecture Limited 94.63% Y 
Page 77 of 79

Page 78

Appendix 2 – Summary of Procurement Process 
Response
Procurement Procedure Utilised: Framework (Scottish Procurement
Alliance)
Governing Legislation / Regulations: Public Contracts (Scotland) Regulations
2015
Date Contract Strategy Approved: 27 May 2022
Date Contract Notice Published: Not Applicable
Number of Companies Invited to Take Part: 1
SME % of Expressions of Interest: 100%
NLC Based % of Expressions of Interest: 0%
Tender Return Deadline: 9 December 2022
Number of Tenders Received: 1
Where Only One Tender Is Received, Why?: Direct Award Call-off from Framework 
Tenders Received from SME’s: 1
Tenders Received from NLC Based Tenderers:  0
Number of Non−compliant Tenders: 0
Number of Compliant Tenders: 1
Number of Recommended Tenderers: 1
Basis of Contract Award: Quality: 75% Price: 25%
Evaluation Team:
Framework Scoring was utilised with
compliance checks etc. undertaken by
Officers of the Growth Team.
Anticipated Contract Start Date: 12 January 2023
Total Contract Period (Months): 24 months plus 6 month extension
Maximum Total Contract Value: £630,000 
Page 78 of 79

Page 79

Appendix 3 – SME Status and location of all Tenderers 
Name of Tenderer
Size of Tendering
Organisation
(Micro, Small,
Medium or Large)
Location
(Local Authority /
Council Area)
Collective Architecture Ltd Small Greater Glasgow 
Page 79 of 79