North Lanarkshire Council
Report 
Education, Children and Families Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref SP/LP Date 23/05/23 
Community Asset Transfer Request – Cumbernauld Cottage
Trust 
From  Stephen Penman, Chief Officer – Strategic Communication and Engagement  
E-mail penmanste@northlan.gov.uk Telephone 07947997750 
Executive Summary 
The purpose of this report is to provide the Education, Children and Families Committee
with the details of a Community Asset Transfer (CAT) request relating to the Former
Cumbernauld Theatre and to provide information on the outcome of the assessment
process together with a recommendation for decision. 
Details of the application and supporting documentation can be accessed here. 
Recommendations 
It is recommended that the Education, Children and Families Committee: - 
1. Acknowledge the detailed assessment of the application against approved criteria
and the recommendation for rejection of the proposal by the CAT Leadership
Group; and 
2. approve the rejection of the proposal for Community Asset Transfer of the former
Cumbernauld Theatre (shown on map at appendix 1) as outlined in the
application which can be accessed here and reflecting the council’s Community
Asset Transfer Policy. This is based on the assessment findings summarised in
this report and set out in full in Appendix 2 of this report. 
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (22) Facilitate a North Lanarkshire wide approach to asset
rationalisation, including with communities and partners

Page 2

1. Background 
1.1 Part 5 of the Community Empowerment (Scotland) Act 2015 places a statutory duty on
local authorities and certain other public sector agencies to develop a clear process for
supporting community participation and ownership of assets. The associated guidance
for the delivery of Community Asset Transfer (CAT) articulates that the council’s
responsibilities are to: 
• establish, maintain, and make available a register of land owned or leased by the
council to the best of its knowledge and belief; 
• develop clear decision-making criteria, review, and appeals procedure for
Community Asset Transfer; 
• actively provide information and promote the process for Community Asset Transfer
and Participation Requests aligned to other participation opportunities; 
• assess the capacity of the organisation making a CAT request and provide support
to assist them to fulfil their aspirations around community empowerment and
participation outcomes; and 
• publish information relating to requests; and produce and publish annual reports. 
1.2 The council’s Community Asset Transfer (CAT) process and assessment criteria were
approved in 2019 by the then Community Empowerment Committee. The North
Lanarkshire Council Community Asset Transfer policy can be viewed here. 
2. Report 
North Lanarkshire Decision Making 
2.1 Following initial engagement with groups interested in submitting a CAT request
support is provided to the community organisation by key staff to assist them to
understand the process and requirements and to self-assess their ‘readiness’ and
capacity to take on an asset. 
2.2 Upon a formal application being made, the council is bound to carry out an assessment
of the request, establish that the applicant is a qualifying body and assess both the
sustainability and likely benefit of the asset transfer. Benefits can include social
wellbeing, economic benefit and provision of services and activities that would not
otherwise be provided. The council must adhere to the following process. 
• acknowledge the request and provide information regarding timescales – the
acknowledgement date is known as the validation date.
• the timescale for a decision relating to a CAT request is normally 6 months from
validation date. 
• the council and the group can mutually agree a different timescale if required (ie
linked to committee cycles, funding decisions, etc).
• If the CAT request is not approved, the group must be provided with information
relating to review and appeals procedures. 
2.3 On receipt of a CAT request made under the terms of Community Empowerment
(Scotland) Act 2015 a panel of senior officers from across council services undertakes
an assessment of the application. Thereafter the CAT Leadership Group made up of
the Chief Officers for Strategic Communication & Engagement and Assets &
Procurement are presented with the assessment information in order to consider and
make recommendations to the committee for the relevant holding service.

Page 3

2.4 The legislation makes no distinction between operational and surplus assets. Where an
asset is operational or it has been declared surplus, and a current or alternative use is
identified as the most beneficial option for the council, a CAT application must
demonstrate that its proposed use brings a higher level of community benefit. This is a
key consideration in the council’s decision making, as is sustainability of the business
model, evidence of community support or community benefit and organisational
capacity to manage the asset. 
2.5 Cumbernauld Cottage Trust CAT application 
Cumbernauld Cottage Trust submitted a formal CAT request on 14th September 2022.
The application included all required supporting information and met the criteria for it to
be assessed under the terms of the Community Empowerment (Scotland) Act 2015
and in line with the council’s CAT policy and process. 
A panel of senior officers from key services met on 19th January 2023 to undertake an
initial assessment of the application. This included: 
• Estates (Assets and Procurement)
• Active and Creative Communities
• Community Partnership Team
• Community Facilities
• Financial Solutions   
The findings of the Officer assessment panel were reported to the CAT Leadership
Group on 1 March 2023 for consideration. 
The outcome of the assessment is attached as appendix 4. A summary of the
assessment is below. 
2.6 Assessment of CAT Request 
Summary Grading Very
Strong
Strong Moderate Weak Very Weak
1.Details of the asset    x 
2.Organisation information   x  
3.Type of Request   x  
4.Link to the NL Plan   x  
5.Community Proposal   x x 
6.Support     x
7.Financial Information     X
8.Risk/Social Impact     x 
2.7 Cumbernauld Cottage Trust are a not-for-profit voluntary group formed by local people
for the benefit of the local community. Underpinning the CAT request is an aim to retain
and restore the Former Cumbernauld Theatre site for use by individuals and
community groups. Details of the application can be accessed here. 
2.8 It is evident from the application that the Cottage Trust has in place a Board with a
range of skills, expertise, and experience around delivery of the proposed activity and
service provision. The governance arrangements meet the criteria for the submission of
the CAT to be considered by the council. However, several key factors led to the
conclusion that the community benefits of transferring this asset on the terms proposed

Page 4

do not outweigh the risk and concern identified through the assessment process. The
main risks identified are around the potential for duplication of service and therefore
both the possibility of detriment to the Trust and the successful implementation of their
business plan and to existing providers especially where the council has reprovisioned
and invested in a similar asset and service offer through the Lanternhouse Theatre site. 
2.9 An overview of areas of challenge are as follows:
Potential for duplication of service: The case for the transfer of the asset is built
upon a service delivery model that is likely to create duplication with existing services
that the council has already invested in. An operational decision was taken to close and
cease delivery from this site and to relocate provision previously delivered to the new
Lanternhouse Theatre site at Cumbernauld Academy Campus (approximately 1km
away). The capital investment in relocating the theatre and café provision to the new
campus has been significant (in the region of £37 million) and the council contributes a
further resource of approximately £110k recurring revenue supported through a Service
Level Agreement. The application does not adequately refer to how the services being
offered as part of the CAT proposal add value to those already being delivered via
other local venues and organisations in the Cumbernauld area, nor does it explore or
evidence through market research that the potential for competition regarding income
streams has been considered. The map of facilities at appendices 3 and 4 shows the
range of services and facilities currently available in the area. Any duplication could
undermine the financial projections and reduce the Trust’s ability to meet income
targets. 
Project Delivery: While there is reference to staffing and management around service
delivery at the point that the project is operational, it is unclear how the project would
be robustly managed throughout the early stages including attracting and securing
capital investment, procurement and construction. A project of this scale, risk and cost
requires to be carefully project managed. The submission does not reflect this or
provide full consideration of the operating model and ensuring that this is sustainable
and can balance the required generation of capital investment, building and
construction with the likely need for phased delivery and maintenance (including the
potential for further decline for areas of the site that resource may not allow to be
prioritised for delivery). 
Evidence of need/community benefit: There was some community engagement
through public meetings in 2018 and a survey in 2019. The survey received 1500
responses, (3% of Cumbernauld population). This was pre pandemic and prior to the
opening of the new theatre site in 2021. There is little evidence in the application of
more recent engagement or assessment of need reflecting current provision and
changes in behaviour/trends arising from the Covid-19 pandemic or indeed the impact
of the recent cost of living crisis. The council has witnessed a 50% drop in use post
pandemic in its own community facilities, with a slow rise in activities through recovery. 
This information could inform a negative impact on the ability of the Trust to meet
projected income targets from lets, hiring of space and community use of income
generating activity such as the café.
Financial viability: A site visit was undertaken by the assessment group and showed
the extent of the work required to bring this site to operational standard. This is further
evidenced in a condition survey undertaken in February 2023. The application does not
adequately evidence how the significant investment for capital works would be
resourced nor does it show how the community body will financially support the
operation of the building while the construction works are ongoing. The Trust has had

Page 5

the property valued at £45k, which is within an acceptable tolerance of the council’s
anticipated market value of £40k . An offer of £20k for purchase of the asset has been
made. Under the requirements of the Community Empowerment (Scotland) Act 2015
the group are entitled to make an offer at this level. An offer significantly below market
value should evidence substantial community benefit which balances with the level of
discount. The application in this case does not strongly enough evidence that the
planned ‘offer’ to communities adds value to, compliments or provides an alternative to
existing provision. The projected income generation does not reflect comparable
incomes levels of sites operated by the council providing similar service provision. In
terms of the council’s duties around best value, as outlined above there has been
significant investment through a funding agreement and capital works for the
Lanternhouse Theatre (building) and transfer of the asset at the offer price would
present financial risk. 
Overall the capital works to bring the building into operation and the expected income
generation from operation of the services planned are aspirational. The application did
not provide sufficient reassurance of the financial sustainability of the project to balance
the potential risk to the council of transferring the asset. There is no evidence that costs
provided have been assessed in the context of the current ‘cost of living and ‘energy’
crisis and how these may impact on the operating costs in the short/medium term. 
Potential for ongoing maintenance burden/revenue implications for the council:
The submitted request does not include the group taking on maintenance of the
associated car park and access road which service the site and provide access to the
parking provision for the buildings. The CAT application includes part but not all of the
car park area. Agreeing to these terms may create a maintenance burden and liabilities
for the council where there is not currently an operational budget associated with this
asset. The closure of the site was assumed following the relocation of the provision to
an alternative location. It would be challenging and complex to consider the transfer of
the building in isolation from the car park and access road. 
3. Measures of success 
3.1 Consideration is given to a Community Asset Transfer request in accordance with the
requirements of the Community Empowerment (Scotland) Act 2015, associated
Scottish Government Guidance and the Council’s Community Asset Transfer Policy.
Performance measures in respect of Community Asset Transfer and Participation are
included in the Plan for North Lanarkshire – Strategic Performance Framework. The
current performance. 
3.2 Measures cover the following: - 
• numbers of successful Participation and CAT requests; 
• number of community groups engaged in Participation and CAT requests; 
• support provided to community groups and organisations as a result of initial CAT
or Participation Request enquiries; and
• positive outcomes or referrals because of initial CAT or PR enquiries

Page 6

4. Supporting documentation 
4.1 Appendix 1 – Map
4.2 Appendix 2 – CAT Assessment report
4.2 Appendix 3 – Map of existing facilities 
4.4 Appendix 4 – Cumbernauld Asset Map 
Links 
• North Lanarkshire Council information on Community Asset Transfer
process 
• North Lanarkshire Councils Community Asset Transfer (CAT) Policy 
• Cumbernauld Cottage Trust CAT application 
• Condition survey 
•  Lanternhouse Theatre Service Level Agreement 
Stephen Penman
Chief Officer
Strategic Communication & Engagement

Page 7

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The Community Asset Transfer and Participation process assists the council to deliver on
both the Fairer Scotland and key equality duties. In particular, the policy will further the
public sector equality duties to advance equality of opportunity and foster good relations.
An integrated Fairer Scotland/Equality Impact Assessment has been undertaken in respect
of the CAT policy. No concerns have been highlighted as a result of the assessment. 
An EQIA will be undertaken to assess the impact of any decisions taken and published
accordingly 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☒ No ☐
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Financial Solutions have been involved in assessment. Concern and risk highlighted
regarding financial viability of the project and potential for duplication of service that
the Council has already reprovisioned and invested in from another site. Offer of
£20k is below anticipated market value of £45k. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
However may impact on and link with the development of the Council’s Volunteering
strategy and approach 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☒ No ☐
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?

Page 8

Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Legal representative involved in CAT process in an advisory capacity. This
application was submitted under the Community Empowerment (Scotland) Act 2015
and has been assessed in line with the associated statutory guidance. 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☒
Adequate procedures in place to manage the handling of personal information in line
with the data protection procedures 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐
No x 
☒
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Information linked to Community Asset Transfer applications, decision making and
outcomes require to be published on the Council’s website North Lanarkshire
Council information on Community Asset Transfer process 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐

Page 9

If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
The CAT process is reflected and managed as per the Council’s Risk Management
approach. Details of specific identified risks relating to this application around
outlined throughout the report. The main risk concerns are around potential
duplication of services, financial viability and maintenance burden on the Council,
project management and insufficient evidence of need. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 10

Appendix 1

Page 11

Appendix 2 
Assessment Report 
Assessment framework used to inform the recommendation on a Community
Asset Transfer Request
Name of Organisation/Applicant Cumbernauld Cottage Trust
Details of the Asset Former Cumbernauld Theatre 
Community Area/Ward  Cumbernauld East (Ward 4)
Date submitted 14 September 2022
Date of Assessment Panel 19th January 2023
Date of Leadership Group  1st March 2023
Date of committee decision  May 2023   
Summary comments from assessment panel 
Assessment undertaken by . • Community Partnership Manager
• Strategic Asset Manager
• Group Manager, Estates)
• Surveyor, Estates
• Active and Creative Communities
Manager
• Facility Support Services Manager
• Financial Solutions Manager
Final Recommendation from Leadership Group
based on outcome of assessment by Corporate
Assessment Panel
Reject 
CAT Leadership Meeting 1st March 2023,
3.30pm, MS Teams 
Summary Grading Very
Strong
Strong Moderate Weak Very Weak
1.Details of the asset    x 
2.Organisation information   x  
3.Type of Request   x  
4.Link to the NL Plan   x  
5.Community Proposal   x x 
6.Support     x
7.Financial Information     X
8.Risk/Social Impact     x

Page 12

1  Details of the Asset – Includes asset status and proposed use
This section asks the council to ensure they are in a position to transfer the asset 
ÿ  Very Strong:  The proposal has a cost saving, does not impact on council direct delivery or     
service and there are no restrictions on the asset transfer 
ÿ   Strong: The proposal is cost neutral to the council; it does not impact on council direct      
delivery of services and there are no restrictions on the asset transfer. 
ÿ   Moderate: the proposals present difficulties on the council in terms of one or two of the 
following – direct cost, council direct delivery of services and or restrictions on the assets     
transfer. 
x   Weak: the proposals present difficulties to the council in terms of cost, council direct 
deliver of services and restrictions on the asset transfer. 
ÿ   Very Weak: unlikely to proceed because of ownership restrictions on the asset this would      
prevent a transfer of responsibility or ownership to another organisation. 
Comments 
The transfer of this asset is likely to present challenge to the council in relation to  
• The case for the transfer of the asset is built upon a service delivery model that is likely
to create duplication with existing services that the council has already heavily invested
in. The asset was historically transferred to North Lanarkshire on a commercial basis as
part of the legacy estate and was previously leased to the theatre group to deliver
previously agreed provision. An operational decision was taken to close and cease
delivery from this site and to relocate provision previously delivered to another site
(specifically the new Lanternhouse Theatre site at Cumbernuald Academy Campus). The
investment in this site and relocation of provision was on the assumption that delivery
from the old theatre site would cease through closure. There has been significant capital
investment (£37million) in relocating the theatre and café provision to the new campus
and approximately a further £110k recurring revenue contribution from the Council
supported by a Service Level Agreement . 
• the request is for transfer of the asset and part of the car park. The request does not
cover the group taking on maintenance of the associated car park and access road which
both services the site and supports the parking provision of the buildings use. Agreeing
to these terms may create a maintenance burden and as outlined above the council has
not identified an operational budget associated with this asset as the closure of the site
was assumed following the relocation of the provision to an alternative location. It would
be challenging and complex to consider the transfer of the building in isolation from the
car par and access road. 
• A site visit undertaken by assessment group and the extent of the work required to bring
this site to operational standard was witnessed. This is further evidenced in a condition
survey (Feb 2023) and further highlights concern relating to the viability of the project.

Page 13

2 Organisational Information – Includes governance and capacity to deliver 
Very Strong: Applicant has clearly evidenced that they are a robust and viable organisation 
with effective governance arrangements in place. 
ÿ   Strong: Applicant has provided adequate evidence that they are a robust and viable      
organisation with satisfactory governance arrangements. 
X    Moderate: Applicant has evidenced some signs of being robust and viable and partial      
information provided on governance arrangements. 
ÿ   Weak: Applicant has shown no evidence of being robust and viable and no/little information     
being provided on governance arrangements. 
ÿ   Very Weak: Applicant has provided no evidence of being robust or viable. Governance      
arrangement does not meet the criteria for asset transfer. 
Comments 
It is evident from the application that the Cottage Trust has a strong Board with a range of skills,
expertise, and experience particularly around delivery of the proposed activity and service
provision. They have robust governance arrangements in place that meet the criteria for the
submission of the CAT to be considered by the Council. However, there appear to be some gaps
identified in relation to evidence to suggest whether the Trust in its current format has the
capacity or resource to project manage the whole process for a project of such scale. For
example, there is reference to staffing around service delivery when the project is operational,
but it is unclear how the project would be robustly managed throughout the early stages
including attracting and securing capital investment, procurement and construction. A project of
this scale, risk and cost would ideally require a full time Project Manager. The submission does
not reflect this and appears to be grounded more in sentimental affiliation with the building itself
without full consideration of the actual operating model and future proofing for success in
relation to demand for the services they have to offer and that it is suggested may already exist
within a short proximity from the potential project.

Page 14

3 Type of request, payment, and conditions
This section confirms the type of request and seeks and whether or not the price reflects a
fair price for the asset taking into consideration community benefit 
ÿ   Very Strong: Applicant has proposed acceptable terms, with prices reflecting Market/Fair 
Value. (score would reflect acceptable terms; for example – the right timescale for being      
able to complete the sale or lease and funds are already in place) 
ÿ  Strong: Applicant has proposed terms, with prices reflecting Market/Fair Value. 
X   Moderate: Applicant has proposed terms, with prices well below Market/Fair Value. 
ÿ  Weak: Applicant has failed to propose terms or prices. 
ÿ  Very Weak: Applicant unsure of securing funding to afford costs. 
Comments 
The Trust has had the property valued at £45k in a similar region to the councils anticipated
market value of £40k. An offer of £20k has been made and the Trust are entitled to make an
application for this level of discount under the requirements of the Community Empowerment
(Scotland) act 2015. Given the status of the asset the offer in theory would not impact negatively
on the council from a financial perspective. However, an offer significantly below market value
should evidence substantial community benefit which balances with the level of discount. The
application in this case does not strongly enough evidence that the planned ‘offer’ to
communities adds value to, compliments or provides an alternative to existing provision. The
application and business plan references some community consultation pre pandemic and does
not provide a current assessment of need to justify the level of discount. 
The terms of the application excluding the access road and the carpark is likely to create a
maintenance burden on the council when the council decision to close the asset following its re-
location of the provision means that there is no operational budget associated with the site or its
maintenance. 
There is also concern around likely duplication of service across the activity associated with the
CAT proposal, which delivered by the Lanternhouse Theatre which the council has significantly
invested in and those available and delivered via other local venues and organisations in the
cumbernauld area. The application fails to mention these other facilities and competition
regarding income streams is a concern if they have not undertaken sufficient market research
before submitting the application. The attached map of facilities shows the range of services and
facilities available and how there is the potential for duplication of services in the area. This calls
into question the projected income generation outlined in the application as any duplication
could reduce the Trusts ability to meet income targets. 
The projected income generation does not reflect comparable incomes levels of sites operated
by the council which provided similar service provision.

Page 15

4 Link to Strategy– How the project links into the vision and ambitions set out in the Plan
for North Lanarkshire (TPFNL) 
ÿ   Very Strong: Applicant has clearly evidenced that their project links in to the key themes of      
TPFNL 
ÿ   Strong: Satisfactory evidence that the applicant understands the importance of linking to the      
outcomes of the TPFNL 
ÿ   Moderate: Limited evidence that the applicant understands the need to ensure the projects      
reflect one of more of the strands of the  TPFNL. 
X Weak:  Little or no evidence that the applicant has made a clear connection to the TPFNL 
ÿ   Very Weak: Applicant has no understanding of the TPFNL 
Comments 
The submission outlines how it will support the key priorities across TPFNL and maps how the
proposal fits with priority areas. This is however a desktop exercise that talks about how the
proposal in a more general sense supports the ambitions rather than specifying or evidencing
how the proposal provides additionality or a different offer that supports the vision for NL and
the future operating model. The offer at the Lantern house Theatre (approx. one km away) and
the range of existing community facilities in the area mean that the services as outlined in the
application could present competing pressures as it duplicates the service provision and fails to
align to the future hub operating model. The council has reprovisioned and invested in services
and capital improvement linked to the Lanternhouse site. Information relating to the funding
agreement with the Lanternhouse Theatre can be accessed hereatt96641.pdf (northlanarkshire.gov.uk).
As well as the ongoing annual investment from the Council of £110k outlined in the funding
agreement, the council has invested capital resources in the new Lanternhouse Theatre (to the
value of £37million.

Page 16

5 Community Proposal – Includes project aims, community engagement and community
benefit/need 
ÿ   Very Strong: Full consideration has been given to the aims, objectives, and vision with clear      
thought to the future direction of the proposal. The proposal provides, for example, a      
social/economic/environmental impact. Comprehensive evidence of need/demand provided       
including consultations, research, and surveys. 
ÿ    Strong: Adequate description of aims, objectives and vision for the proposal. A good       
understanding of the community benefits including adequate evidence. Need/demand 
evidence include some consultation and research. 
X Moderate: Limited description of the aims, objectives, and vision for the proposal. Some       
understanding of the community benefit but not underpinned by substantive evidence. Some       
evidence of need/demand provided including limited consultations, research, and surveys. 
X Weak: Inadequate or no description of aims, objectives and vision for the proposal. Limited      
reference to community benefit and associated opportunities. No evidence of need/demand       
provided. 
ÿ    Very Weak: No description of aims, objectives and vision for the proposal. No reference to       
community benefit. No evidence of need or demand provided. 
Comments 
While the aims of the Trust and the proposal are clear in terms of their aspirations, as outlined
throughout this assessment the main concern is around 
• duplication of services with the new theatre and school campus
• the management of the earlier stages of the project to balance generating capital
investment, building and construction and phased delivery and maintenance (including
the potential for further decline for areas of the site not prioritised for early work). 
There was some market evaluation with public meetings in 2018 and a survey in 2019. This was
pre pandemic and prior to the opening of the new theatre site in 2021. There is no evidence of
any more recent engagement or assessment of need reflecting current provision and changes in
behaviour/trends arising from the Covid 19 pandemic. There is little evidence of additionality in
the proposal. Overall, the application is light on evidence of current community engagement and
need. Survey completed in 2019 received with 1500 responses, (3% of Cumbernauld population).
The council within its own community facilities has witnesses a 50% drop in use post pandemic,
with a very slow rise in activities.  The council in light of this are currently reviewing their own
assets. With other third-party community activities, this is potentially a high-risk area for the
group to take on

Page 17

6 Support – Includes stakeholder engagement and partnership working
This section looks Including evidence community and stakeholders have been engaged 
ÿ    Very Strong: Applicant has clearly demonstrated links with relevant stakeholders and groups      
as well as strong local partnership and community engagement. Evidence of joint responsibility      
for delivery of other projects/service. 
ÿ    Strong: applicant has evidenced some partnership working arrangements. Relevant links with       
groups also evidenced along with strong community engagement activity. 
ÿ    Moderate: Applicant has demonstrated limited links with groups and community engagement       
activity. Some evidence of partnership working provided. 
X Weak: No/poor evidence of community involvement. No/poor evidence of partnership 
Working.
ÿ   Very Weak: No evidence of community involvement. No evidence of partnership working. 
Comments 
There was some market evaluation with public meetings in 2018 and a survey in 2019. This was
pre pandemic and prior to the opening of the new theatre site and there is no evidence of any
more recent engagement or assessment of need reflecting current provision and changes in
behaviour/trends arising from the Covid 19 pandemic. There is little evidence of additionality in
the proposal. Overall, the application is light on evidence of current community engagement and
need. Survey completed in 2019 received with 1500 responses, (3% of Cumbernauld population).
A bulleted list of partners has been provided. There are similarities between planned provision
linked to this proposal and current services and other than providing a list of partners and stating
that they do and will work in partnership there is limited evidence of how engagement with
potential partners has taken place to inform complementary approaches. Further information
would have been useful in relation to local partners providing similar types of services and how
these have been mapped to avoid duplication. Some detail could have been provided of how they
would work together to deliver complementary services and activities. There may be
opportunities for the Trust to provide some proposed services with existing organisations and
from existing buildings and facilities which would have more closely supported the councils
ambitions around the Community Hub and future operating model. The application could be
viewed as being more grounded in local heritage and nostalgia rather than need which is
admirable, but the council needs to consider the major investment in service and capital at the
Lantern house site and the risk associated with transferring this asset that could require
significant investment.

Page 18

7 Financial Information – Includes fundraising, financial planning, and management
We will seek clarification of funding being in place or any potential delay in funding being
in place in time for the final transfer deadline. 
ÿ    Very Strong: Clear Evidence that sufficient financial resources are/will be in place by the time       
of transfer and good resource planning for short/ medium/long term sustainability       
demonstrated. Detailed, realistic and achievable income and expenditure, cash flow       
forecast provided along with a comprehensive contingency plan. 
ÿ    Strong: Evidence indicates that sufficient financial resources are/will be in place by the time of       
transfer and some resource planning has been demonstrated. Satisfactory income and       
expenditure and cash flow forecast. Some consideration has been given to contingency 
planning. 
ÿ    Moderate: Applicant has demonstrated there are some financial resources in place but all       
finances may not be available within the timeframe. There is limited evidence of resource       
planning. Basic income and  expenditure and cash flow forecast induced with limited       
consideration given to contingency planning. 
X   Weak: Insufficient financial resources currently in place and unlikely to be ready within the       
Time frame. No evidence to demonstrate resource planning. No income and expenditure and       
cash flow forecast provided, and no contingency plan outlined. 
ÿ    Very Weak: No evidence of financial resources in place. No evidence of resources or financial 
forecast to predict cash flow. 
Comments 
The projected capital works to bring the building into operation and the expected income
generation from operation of the services planned are very aspirational raising some potential
concerns and gaps in the application around   
• A lack of evidence of contingency planning (re expected income if delays with build,
emergencies, Cost of Living, pandemic, scenario planning, impact on costs) 
•  etc)
• Potential for competing services and facilities and the impact on income have not been
factored into financial plans 
• Crowd Funding is mentioned which is not considered a reliable income stream 
• Capital investment is very significant and as outlined above it is unclear how the major
construction project will be operationally managed 
The business case and application moves straight to delivery and does not fully lay out the scale of
the project or how it will be financially managed in terms of 
• Set up costs
• Build costs 
• Future delivery costs 
• Contingency planning 
Some points noted about revenue income 
• High level Income and Expenditure Table presented. However, production of an indicative
cashflow (indicates income v expenditure on a month by month basis) would have

Page 19

provided reassurance that upward or downward trends in income and expenditure have
been considered, ensuring that obligations can be covered each month.
• Café/Bar projected revenue of £120k seems optimistic when compared to existing NLC
facilities as is let income for hire of spaces £10-20 p/h – there is no information provided
regarding what this has been benchmarked against or how these figures have been
reached 
• There is a projection of £300 per month from local businesses taking space however there
is already challenge in filling existing available empty space in Cumbernauld. Again it is
unclear if this is comparable to market evidence of need
• There is no evidence that costs provided have been assessed in the current ‘cost of living’
and ‘energy’ crisis and how this impacts on the operating costs in the short/medium
term? (Contingency planning) 
• There is no evidence in costings relating to assessment of technical support for delivering
arts and theatre activity as part of cost projections
• It is not clear how factoring of cost of owning/maintaining asset has been considered to
cover the period prior to mobilisation and generating income ( ie during construction,
early phases of delivery) 
As outlined above the council has invested through a funding agreement £110k revenue resource
as well as capital resources for the new Lanternhouse Theatre (building) to the value of £37
million 
The funding agreement can be accessed here att96641.pdf (northlanarkshire.gov.uk).

Page 20

8 Risk/Social Impact – Includes potential impact and barriers/challenges and 
understanding of managing the asset. 
ÿ   Very Strong: Full evidence that applicant has in place the necessary capabilities to manage the      
asset. Considerable awareness of the potential impact of the transfer on others, and      
barriers/challenges clearly identified. Comprehensive information provided on the anticipated      
social benefit/impact of the transfer and how this will be measured. 
ÿ   Strong: Satisfactory evidence that applicant has the necessary capabilities to manage the asset.     
Sufficient awareness of the potential impact of the transfer on others with consideration given     
to potential barriers/challenges. Adequate information provided on the anticipated social     
benefit/transfer. 
ÿ   Moderate: Limited evidence to demonstrate capabilities to manage the asset. Some awareness     
of the potential impact of transfer on others and consideration given to potential     
barriers/challenges. Minimal information provided on the anticipated social benefit/impact of     
the transfer. 
X Weak: Inadequate or no evidence of capabilities in place to manage the asset. Little or no 
awareness of the potential impact of the transfer on others or possible barriers/challenges     
identified. No social benefit/impact monitoring outlined. 
ÿ   Very Weak: applicant has provided no evidence of capabilities to manage the asset. No     
awareness of the potential impact of the transfer on others. No social benefit or impact    
monitoring in place. 
Comments 
As outlined at 7 and throughout assessment the business case and application does not fully
reflect the scale of the project or how it will be financially managed in terms of 
• Set up costs
• Build costs 
• Future delivery costs 
• Contingency planning 
The main risks are around 
• Potential duplication of service and therefore both the possibility of detriment to the
Trust and the successful implementation of their business plan and to existing providers 
especially where the council has reprovisioned and invested in a similar asset and offer
through  the Lanternhouse site. 
• Much of the income generation projected is linked to café, bar and letting of space. This is
an area that is still recovering from the pandemic and the cost-of-living crisis is impacting
further. Community use of leisure, recreation and social services and facilities has been
affected as previously stated. Participation in non-sport activities within the council remit
have dropped almost 50% post pandemic and social habits have changed. This is reflected
in the councils operating model plans and there is limited evidence that market need, and
trends have been assessed in the current climate

Page 21

Appendix 3 
Map of existing facilities

Page 22

Appendix 4
Cumbernauld Asset Map