Page 1

North Lanarkshire Council
Report
Education, Children and Families Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref   GMcL/MD Date 28/02/23 
Proposals for statutory public consultation on the proposed new
build for Gartcosh Primary. 
From  Gerard McLaughlin, Chief Officer (Education - North)  
E-mail mclaughling@northlan.gov.uk Telephone  01236 812 221 
Executive Summary
This report outlines proposals for statutory public consultations on the proposed new build
for Gartcosh Primary. 
If approved, a statutory consultation will take place involving all statutory consultees, other
stakeholders and interested parties. 
The key reasons for this proposal are: 
• The council is progressing its Town and Community Hub programme and this
consultation proposal for Gartcosh Primary follows from the Committee Report on
Schools and Centres 21 Phase 3 Investment approved at Education Committee on
1st March 2017. 
• The pupils currently at Garcosh Primary School will benefit educationally by
attending a new build school which can offer a wider range of educational
opportunities. 
Recommendations 
It is recommended that the Education, Children and Families Committee: 
(1) Endorse the contents of the report;
(2) Agree that a formal consultation take place on the proposed new build for Gartcosh
Primary;
(3) Endorse the attached statutory consultation document appendix 1;
(4) Agree the timeline for consultation outlined in appendix 2 of this report.  
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (22) Facilitate a North Lanarkshire wide approach to asset
rationalisation, including with communities and partners

Page 2

1. Background 
1.1 Schools (Consultation) (Scotland) Act 2010 
The provisions of the above Act place a statutory duty on education authorities to carry
out formal consultations on new build proposals for schools when the proposal is to
build the school out with its current curtilage or when a joint campus is proposed
involving a non-denominational and a denominational primary school. 
1.2 The Act requires education authorities prepare an educational benefits statement, to
prepare (and publish) a proposal paper in respect of any proposal which falls within the
terms of the Act, give notice of the proposal to the relevant consultees (and invite
representations) in accordance with the Act, to hold (and give notice of) a public
meeting, involve Education Scotland. 
1.3 Following the period of consultation, the education authority must review the proposal
in accordance with the Act and prepare (and publish) a consultation report in
accordance with relevant sections of the Act. 
1.4 After publication of the education authority report, HMIE publish a report on the
consultation taking account of the previously published education authority report
before a final decision is made by the Council. 
1.5 The Service will undertake a statutory consultation on the proposed relocation of
Gartcosh Primary to a new location. Appendix 3. 
1.6 Proposals outlined in this paper have been developed by Education and Families
Managers including staff from the Early Learning & Childcare team, the Inclusion team,
Assets and Procurement and Corporate Finance. Key considerations derived from
these meetings have been incorporated into the models proposed, which include: 
• Quality and condition of the fabric of school buildings
• Possible savings/costs associated with estate re-purposing and school relocation
• Impact assessment and improvement planning for the ASN sector.   
1.7 The Service has adopted a formal project management governance structure to lead
and monitor the delivery of new build schools which will encompass the achievement
the programme and the savings. 
1.8 The final decision of the education authority is subject to review and possible call in by
the Scottish government which must operate to a strict timeline set out in Appendix 2. 
1.9 The timeline mentioned above may be subject to review due to unforeseen
circumstances. 
2. Report 
2.1. The council is progressing, through the Town and Community Hub programme budget
allocation, a new build Gartcosh Community Hub which will include 434 primary school
spaces at a new location and thereafter relocate Gartcosh Primary School to this new
Community Hub.  As members will be aware, Gartcosh is part of a Community Growth
Area and is experiencing increased demand to the school estate as a result.  The
current location does not have sufficient space on which to expand to create the
capacity required, therefore a new school, at a new location is proposed. A statutory
education consultation is required to relocate a primary school to the new location.

Page 3

2.2. There are various reasons why a new build is prioritised: “Legacy” projects which are
carried over from previous school build programmes such as “Schools and Centres 21”;
“Capacity” projects which are required due to significant increased pupil populations
and subsequent additional spaces required within catchment schools; and “Policy”
projects which are brought forward due to alignment with the prioritisation matrix linked
to the Town and Community Hub programme.  Gartcosh Community Hub is both a
legacy, and a capacity related project, and as such is prioritised within the 2021-2026
capital allocation for this programme of work. 
2.3. This report establishes the methodology by which the services redesign was envisioned
by officers, in response to the Council’s priorities. A core team of officers in Education
and Families assessed a range of propositions to establish their viability, using a RAG
status approach to highlight most promising options for implementation. 
2.4. A number of factors were used to establish an approach to prioritising potential
rationalisation activities. These are described in the following section. 
2.5. Strategic fit with the priorities of the Plan for North Lanarkshire; 
2.5.1 Whilst this project predates the creation of the Town and Community Hub programme,
all projects not yet designed will follow the six guiding principles attached to the Town
and Community Hub programme.  As such, in addition to the requested Statutory
Education Consultation, there will be effective engagement with both the school and
the wider community throughout the design stage of this project – should it be approved
to proceed following Statutory Consultation. It is proposed that the intelligent brief
process, which facilitates engagement with the stakeholders, would not wait until the
education consultation is concluded but will be ‘delivered at risk’.  It is not the case that
the outcome is predetermined – hence the ‘at risk’ proposal.  The council is looking to
deliver a new facility as soon as practically possible, due to pressures at the existing
establishment. However, it should be noted that should the outcome of the statutory
education consultation conclude that the proposal should not be progressed, the work
on the intelligent brief would cease. 
2.6. Alignment with the Community Growth Area proposal; 
2.6.1 It has been evident for many years that a new build primary school is required to
mitigate the impact of new housing on the school estate.  The issue to date has been
the lack of available land on which to build a new Community Hub. Due to the
constraints of the existing site, it would not be possible to create a school of sufficient
size to serve the needs of the growing school population.  Unfortunately, the council
did not own sufficient land in this area, and it has taken years of complex negotiations
with landowners to acquire a site suitable to build a new Community Hub.  The
proposed new location has been determined as the council now owns this land. 
2.7. Growth in the wider Northern Corridor area; 
2.7.1 Whilst there is extensive growth in Gartcosh, there has also been growth in other areas
of the Northern Corridor over the years, including in Stepps, Chryston, and
Moodiesburn.  This increased population places demand on other sectors within
education, in addition to primary provision.   
2.7.2 A new build primary school is near completion, and an extension to the high school is
expected to follow.  However, to serve the needs of both the Additional Support Needs
(ASN) community, and the early years community, it is proposed that spaces are
included in the Gartcosh Community Hub for both these sectors.  Whilst this does not

Page 4

form the need for a statutory education consultation, which is needed solely due to the
proposal to relocate the existing Gartcosh Primary School, it will form part of the
consultation with the school and wider community as part of the discussion in relation
to the Community Hub proposals. 
2.8. Relocation of Existing Establishments within Alternative/Higher Quality
Facilities 
2.8.1 In line with the policy established in the Plan for North Lanarkshire to ensure that young
people are catered for within high-quality facilities, it is also proposed that consultation
takes place to strengthen the provision experienced by pupils in Gartcosh Primary
School. Each of these propositions is outlined in what follows.  
3. Measures of success 
3.1 Stakeholder support for the options brought forward. 
3.2 Successful implementation of planned proposals. 
3.3 Achievement of budget savings target in line with approved budget savings agreed by
Council March 2020 
3.4 Greater alignment with Plan for North Lanarkshire community hub model. 
3.5 Improved quality of service and provision to effectively meet the needs of children,
young people and families 
3.6 Increased numbers of children and young people remaining within their local
community.   
4. Supporting documentation 
4.1       Appendix 1 Statutory Consultation Gartcosh Primary
4.2 Appendix 2    Statutory Consultation Timeline 
4.3 Appendix 3 Location plan 
Gerard McLaughlin
Chief Officer (Education - North)

Page 5

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
An Equality Impact Assessment has been completed and will underpin planning for
these proposals, since a number of the young people involved are considered as
being from a protected group, due to disability. 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The Service is currently assessing the value of this capital investment with support
from colleagues in Asset and Procurement Solutions. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Affected staff will be managed in accordance with the appropriate Workforce
Change Policies and in with the signatory trades unions.  Considerations would
include Compulsory Transfer, Premature/Early Retirement,
Redundancy/Redeployment.
The Service would be required to follow the requirements for consulting as set out
in the Schools (Consultation) (Scotland) Act 2010. Further stakeholder, community
and parental consultation would be required in the event that the Service proceeds
with any of the recommendations. An indicative timeline for the consultation
process is outlined in Appendix 2.
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☒ No ☐ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
5.5 Data protection impact

Page 6

Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☒ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☒
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐  
The carbon footprint will reduce if the numbers of establishments operating was
reduced and pupils were catered for in our newer and more energy efficient
campuses. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
A Programme Board has been established for the Implementation of the ASN
Review. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 7

Appendix 1 
Statutory Consultation 
Proposal to build a new Gartcosh Primary School and to
incorporate a Language & Communication Support Centre (LCSC)
and Early Learning and Childcare (ELC) provision 
EDUCATION AND FAMILIES

Page 8

NORTH LANARKSHIRE COUNCIL: EDUCATION AND FAMILIES 
Proposal to build a new Gartcosh Primary School and to incorporate a Language &
Communication Support Centre (LCSC) and Early Learning and Childcare (ELC)
provision 
1.         INTRODUCTION 
Gartcosh Primary School is a non-denominational primary school which was built in
1913 and is located in Lochend Road, Gartcosh. Seven miles east of Glasgow City
Centre and seven miles west of Cumbernauld. The present school building was opened
in 1913; it is a traditional two storey stone construction with pitched and slated roof.
Within the building there are seven classrooms off the central hall. The administration
block is situated upstairs, and the school dinner hall is outside in the playground in what
was the original school building (dated 1875). There is also a modular until within the
school grounds which has temporary accommodation for two classrooms. 
The school capacity of the school is 188 with the current roll of 250, which includes 62
spaces created through the temporary two class modular unit. 
It is recommended that the proposed new building includes the existing Gartcosh
Primary School, a new LCSC and Early Learning & Childcare provision. 
The current site has no associated LCSC or nursery class within the current campus. 
2. CONSULTATION REQUIREMENTS 
2.1 In terms of the Schools (Consultation) (Scotland) Act 2010, the Education Authority is
required to publish details of, and consult on any proposal to establish a new school
and on any proposal to establish, terminate or otherwise alter the catchment area of a
school. 
2.2 North Lanarkshire Council will not make any decision, or put any changes into effect,
until the consultation period has been concluded in line with statutory requirements. 
2.3 The consultation period will be a minimum of 57 days, which include 30 school days.  It
begins on 1 March 2023 and finishes on 27 April 2023. 
2.4 The consultation will involve pupils, parent/carers, Parent Councils and staff of the
schools involved, as well as other associated stakeholder and statutory consultees. 
2.5       A public meeting will be held on week beginning 6th March 2023. 
2.6       Council officers will be present at the public meeting to discuss the proposal.  There
will be limited time at the meeting to discuss all issues fully. To ensure that all issues
are covered and that those who may be uncomfortable with speaking publicly are
heard, advance notice of specific questions or issues to be raised will be accepted in
writing up to two days in advance of the meeting – see contact details at 2.9. 
2.7 At the end of the consultation process, a report will be prepared for North Lanarkshire
Council detailing all responses received, summaries of their content and a statement
from Education Scotland on the educational aspects of the proposal.  Responses to the
issues raised through the consultation will also be incorporated in the report.  Copies
of the report will be available, prior to consideration by the council, in the affected

Page 9

schools and online.  It is envisaged that the report will be published on 29 June 2023.     
2.8  An online version of the document and other items related to the consultation can be 
found online at www.northlanarkshire.gov.uk/gartcosh-consultation 
2.9  Further information on the proposal can be obtained by sending an email to 
gartcoshconsultation@northlan.gov.uk 
2.10  All interested parties are invited to submit their comments on or before 27 April 2023. 
3.         PROPOSAL 
3.1     The proposal in this document is to build a new facility incorporating a new build
Gartcosh Primary School in addition to a Language & Communication Support Centre
(LCSC) and an Early Learning and Childcare (ELC) provision within the existing
catchment area. There are two main reasons for this proposal: 
• The pupils currently at Gartcosh Primary School and the new LCSC and new
Nursery Class will benefit educationally by attending new build schools which can
offer a wider range of educational opportunities (see Educational and Community
Benefits sections below). 
• The current Gartcosh Primary School needs replacement due to the levels of
housebuilding in the area.  The new school will be fully accessible and equipped
with modern technology to ensure the best learning opportunities are afforded to
every child. 
3.2 It is proposed that the school will be sited on an area of land between on the current
open space and football pitch located between Woodneuk Avenue and Johnstone
Road. 
3.3 If, following this statutory consultation, the Council proceeds with the proposed school,
then the statutory planning process will be followed as required until completion of the
new school. Prior to that, Gartcosh Primary will continue to operate on its current site. 
4.      EDUCATION BENEFITS STATEMENT 
4.1 Through the planned proposals it is expected that several education benefits will be
achieved on behalf of children and young people including: 
• Improved access to high quality facilities
• Improved access to a greater variety of different education experience
• Access to outdoor learning experiences
• Strengthened practice in pedagogy and learning and teaching 
• Increased opportunities for professional learning and sharing good practice 
4.2    Experience in new school buildings has demonstrated that a new and flexible learning
environment inspires staff and pupils and has a positive impact on the general health
and wellbeing of stakeholders.  
4.3  Improved high quality facilities for learning will be designated in such a way as to allow
a range of teaching styles and approaches, including active learning, interdisciplinary
learning and outdoor learning.

Page 10

4.4 The curriculum will provide the opportunity for learners to achieve across all curricular
areas and to develop skills, attributes and capabilities aligned with the design principles
of Curriculum for Excellence: challenge and enjoyment, breadth, progression, depth,
personalisation and choice, coherence and relevance. 
4.5   Children and young people will be provided with a broad range of opportunities
for personal achievement and interdisciplinary learning across all curricular areas
by building on best practice in curriculum design in North Lanarkshire Schools. 
4.6 The provision of high-quality technology for learning will provide the potential
to transform ways of learning and teaching by giving young people and staff flexible and
embedded access to a fully digital learning environment. 
4.7 The shared flexible learning and teaching spaces in the new joint campus school will
enable staff to work together in a collaborative manner and provide more opportunities
for co-operative working between pupils. 
4.8 The new school will be fully accessible to disabled learners as required by the Equality
Act (2010). This will be ensured through the delivery of the Council’s:- 
• Equality outcomes 
• Promoting Inclusive Design Protocol and 
• Partnership with North Lanarkshire Disability Access Panel. 
4.9 The new school will be designed in such a way as to promote accessible, inclusive
learning which will meet the needs of all learners including those with Additional
Support Needs. 
4.10 The new school will build on current, and facilitate new, opportunities for effective
integrated working with other services and partner agencies and will provide necessary
support to children and families in the new school catchment area. 
4.11 The new school’s design, construction and operation will be environmentally and
energy efficient; contributing directly to delivering the year-on-year reductions in
greenhouse gas emissions introduced by the Climate Change (Scotland) Act 2009 and
provide a rich context for learning for children and young people about sustainability
now and in the future. 
4.12 The inclusion of LCSC and Early years and Childcare provision in the new build
proposal will provide a fully up-to-date setting for LCSC and Early Years provision in
the Gartcosh area. 
5.      COMMUNITY BENEFITS STATEMENT 
5.1 The current council education estate framework has delivered added value through: 
• Several apprenticeships have been created on the construction of the new
schools.
• Local employment opportunities.
• Meaningful learning and engagement between the framework partners and
the project schools.
• Over 70% of the total investment is being procured through local supply chains.

Page 11

5.2 In order to maximise the level of local community benefit regular meetings take place
with framework contractors and the council’s Estate Teams. As we move forward at the
pre-qualification stage contractors appointed to the framework and their supply chains
will be required to actively participate in the achievement of social, environmental and
sustainability policy objectives relating to local regeneration, social and economic
growth, recruitment and training along with local supply chain initiatives. In addition,
sustainability will be a key objective on the construction of the new schools thereby
contributing to the Councils target of reducing our carbon footprint. 
5.3 As well as the educational benefits allocated to the specific school projects there will be
wider educational benefits to the North Lanarkshire Community in that, with the
significant level of savings required to be made over the next few financial years, the
best value argument is that we would be utilising resources more efficiently and
effectively. This is in line with 2003 Best Value Legislation and also the demands of the
Education Scotland Act 1980. 
6. IMPLICATIONS OF THE PROPOSALS 
6.1 Rolls and Capacities 
The projected rolls exclude placing requests but include house building estimates. 
Table 3: Projected rolls and capacities for Gartcosh Primary School 2023 - 2028 
School Capacity Roll 2023 Roll 2024 Roll 2025  
Roll % Roll % Roll %
Permanent 188 235 125 308 164 351 187
Temporary 62       
The projected rolls exclude placing requests but include house building estimates. 
6.2 Transport to School 
Council Policy currently provides free transport to those pupils living more than one mile
from their zoned Primary School or where an appropriate walking route is not available.
Education & Families will arrange for an assessment of the walking routes to the site of
a new school and appropriate road crossing patrols will be established if considered
necessary. 
6.3 Staffing 
The proposal should not have significant implications for staffing, either teaching or non-
teaching. Any matter which arises will be dealt with within the terms of local and national
agreements. 
6.4 Secondary Education 
The current zoning arrangement for secondary education is that pupils attending
Gartcosh Primary School attend Chryston High School. No change to the primary to
secondary transfer arrangements will be required as a result of this proposal. Parents
who wish their children to attend an alternative secondary school will require to submit a
placing request for their preferred school.

Page 12

6.5 Class Sizes 
Class structures are decided by the head teacher in accordance with authority guidelines
and take account of a range of factors, including teacher deployment, school policies,
the available accommodation and pupil numbers at each stage. 
6.6 Future use of the existing school buildings 
Education & Families will declare the existing school buildings surplus to its requirements
should the proposal be approved. Thereafter, the council's Property Services will make
recommendations on its future use or disposal in line with council policy. 
6.7 Financial implications 
Based on previous experience of new build projects within North Lanarkshire, it is
anticipated this proposal will have a limited impact on school revenue budgets. 
6.8 Placing Requests 
It is anticipated that there will be no impact on pupils attending either school on a placing
request. The following options exist for pupils in this position. Firstly, they can transfer
to the new school. Secondly, they can enrol in their designated catchment area school
or thirdly, submit a placing request to another School. The parents of these pupils will
be given the opportunity to discuss their preference with Education & Families staff.
Parents remain responsible for transport costs where an existing placing request to the
new build school is continued. 
7.      EQUALITY IMPACT ASSESSMENT 
An Equality Impact Assessment has been completed and will underpin planning for these
proposals, since a number of the young people involved are considered as being from a
protected group, due to disability.   
8.      INACCURACIES OR OMISSIONS 
8.1 There is a statutory requirement for the Council to consider any allegation of an
inaccuracy or omission in the proposal paper and determine whether the allegation has
foundation.  Where inaccuracies or omissions are notified to, or discovered by, the
Council within this proposal document, the Council will determine if relevant information
has, in its opinion been omitted or whether there is in fact an inaccuracy. 
Notifiers of any omissions or inaccuracies will be informed of the Council’s decision and
the reasons for that decision.  Notifiers will also be informed of any action.  The Council
will invite the notifiers to make further representations to the Council should they disagree
with the Council’s determination or its decision as to whether to take action. 
8.2  If the Council has found, either itself or through a concern being raised, that there is an
inaccuracy or omission in the proposal paper, it must  decide  whether  this relates to a
material consideration relevant to the proposal. 
Where the confirmed inaccuracy or omission relates to a material consideration, there is
a duty on the Council to correct it. 
8.3 Appropriate action will then be taken by the Council depending on whether the
inaccuracy or omission relates to a material consideration.

Page 13

Such action may include withdrawing the proposal and issuing a revised proposal
paper for the whole consultation period, or issuing a corrected proposal paper with, if,
an extension of the consultation period.  In any of these eventualities, all relevant
consultees (and, where applicable, the notifier(s) of any omissions or inaccuracies) and
HMIE (Education Scotland) will be advised of the action. 
Where inaccuracies or omissions are discovered within the proposal document, the
Council will determine whether relevant information has been omitted or if there has
been an inaccuracy.   action will then be taken by the Council, which may include
issuing corrections, issuing a corrected proposal document, or an extension of the
consultation period.  In any of these eventualities, all relevant consultees (and where
applicable, the notifiers(s) of any action) will be advised. 
8.4  Notifiers of any omissions or inaccuracies will also be given the opportunity to make
representations if they disagree with the Council’s determination of any action on the
matter, which may result in the Council making a further determination/decision on the
matter. 
9.        THE STATUTORY CONSULTATION PROCESS – ADDITIONAL INFORMATION  
9.1 The current requirements for consulting are set out in the Schools (Consultation)
(Scotland) Act 2010.  This consultation will be carried out in accordance with the Act. 
9.2 This consultation has been planned in order to meet the statutory requirements.  
9.3 The consultation document sets out the details of the proposal. 
• The proposal paper details the educational benefits of the proposal and other
relevant information. 
• The proposal paper will be published and widely advertised. 
• North Lanarkshire Council will seek to determine whether there are inaccuracies or
omissions within the proposal paper and take such action as it considers
necessary. 
• The consultation period will be a period of at least 6 weeks including at least 30
school days. 
9.4  Prior to the commencement of the consultation period, the authority will give notice of
the proposal to the relevant consultees.  The relevant consultees are defined in the
Schools (Consultation) (Scotland) Act 2010, and are as follows: 
(a) The parent council or combined parent council of any affected school
(b) The parents of the pupils at any affected school 
(c) The parents of any children expected by the education authority to attend the  
affected school within two years of the date of publication of the proposed paper  
(d)  The pupils at any affected school (in so far as the education authority considers
them to be of suitable age and maturity) 
(e) The staff (teaching and other) at any of the affected school(s) 
(f)   Any trade union which appears to the education authority to be representative
of the persons mentioned above 
(g) The community council (if any)

Page 14

(h)  The community planning partnership (within the meaning of section 4(5) of the
Community Empowerments (Scotland) Act 2015 for the area of the local
authority in which any affected school is situated 
(i)  Any other community planning partnership that the education authority
considers relevant 
(j)  Any other education authority that the education authority considers relevant 
(k) Any other users of any affected school that the education authority considers
relevant. 
9.5 During the consultation period, the authority will hold and be represented at public
meetings on the relevant proposal. 
9.6 The council will involve Education Scotland in the consultation process.  This will
culminate in Education Scotland preparing and submitting an independent report on
the educational aspects of the proposal.  
9.7 Following the consultation period, the council will prepare and publish a consultation
report.  The report will be published at least three weeks before a  final decision is
taken on the proposal. 
9.8 The consultation timeline provides further information on the timescales for various
staged in the statutory process. 
Please click on the link below to share your views on the proposal (Ctrl + Click to follow
link) 
www.northlanarkshire.gov.uk/Gartcosh-consultation

Page 15

Appendix 2   
Indicative Timeline for Reconfiguring Intensive ASN Systems and Services 
Stages   Timeline   Date  
1. Committee Date     Tuesday 28 February 2023  
2. Consultation Starts
Phase 1  
Minimum of 6 weeks
To include 30 calendar
days  
Wednesday 1 March 2023  
3. Public Meeting   Mid way through
consultation      
4. Consultation Ends   30 Days   Tuesday 11 April 2023  
5. Report to Education
Scotland Phase2  
3 weeks   Tuesday 2 May 2023 
6. Education Scotland produce
report  
3 weeks   Tuesday 23 May 2023 
7. Consultation report
published Phase 3  
No specified timescale      
8. Time for further
consideration  
3 weeks from publication
date      
9. Final Committee Decision     September 2023  
10. Implement proposal if   
approved by Committee  
3 weeks

Page 16

No embedded text on this page.

Page 17

Appendix 3