MINUTES OF THE MEETING OF THE PLANNING, PROTECTIVE SERVICES AND LICENSING
COMMITTEE HELD BY MICROSOFT TEAMS 
ON WEDNESDAY, 21 FEBRUARY 2024 
Present: Councillor Kieron Green (Chair) 
Councillor John Armour
Councillor Gordon Blair
Councillor Jan Brown
Councillor Audrey Forrest
Councillor Amanda Hampsey
Councillor Daniel Hampsey
Councillor Graham Hardie 
Councillor Mark Irvine
Councillor Andrew Kain
Councillor Liz McCabe
Councillor Luna Martin
Councillor Dougie Philand
Councillor Peter Wallace 
Attending: Fergus Murray, Head of Development and Economic Growth
Iain Jackson, Governance, Risk and Safety Manager
Stuart McLean, Committee Manager
Peter Bain, Development Manager 
Bryn Bowker, Area Team Leader – Mid Argyll, Kintyre and the Islands
Kirsty Sweeney, Area Team Leader – Helensburgh and Lomond/Bute and Cowal
Sandra Davies, Major Applications Team Leader 
Fiona Scott, Planning Officer
Derek Wilson, Planning Officer
Emma Shaw, Planning Officer
Steven Gove, Planning Officer
Stuart Watson, Assistant Network and Standards Manager 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillor Paul Kennedy. 
2. DECLARATIONS OF INTEREST 
Councillor Peter Wallace declared a non-financial interest in planning application
reference 23/00395/PP as he had a business relationship with the applicant in November
2023. He indicated that he would leave the meeting and take no part in the determination
of this application which was dealt with at item 8 of this Minute. 
3. MINUTES 
(a) Planning, Protective Services and Licensing Committee held on 24 January
2024 at 11.00 am 
The Minute of the Planning, Protective Services and Licensing Committee held on
24 January 2024 at 11.00 am was approved as a correct record. 
(b) Planning, Protective Services and Licensing Committee held on 24 January
2024 at 2.00 pm 
The Minute of the Planning, Protective Services and Licensing Committee held on
24 January 2024 at 2.00 pm was approved as a correct record.

Page 2

(c) Planning, Protective Services and Licensing Committee held on 24 January
2024 at 3.00 pm 
The Minute of the Planning, Protective Services and Licensing Committee held on
24 January 2024 at 3.00 pm was approved as a correct record. 
(d) Planning, Protective Services and Licensing Committee held on 24 January
2024 at 4.00 pm 
The Minute of the Planning, Protective Services and Licensing Committee held on
24 January 2024 at 4.00 pm was approved as a correct record. 
(e) Planning, Protective Services and Licensing Committee held on 30 January
2024 
The Minute of the Planning, Protective Services and Licensing Committee held on
30 January 2024 was approved as a correct record. 
Councillor Amanda Hampsey took over as Chair for the next item due to having Chaired
the discretionary hearing relating to this item. 
4. MR SHAUN SINCLAIR: ERECTION OF CAFÉ WITH ASSOCIATED
LANDSCAPING INCLUDING A VIEWPOINT, SEATING, INTERPRETIVE SIGN
AND PLAY PARK: LAND WEST OF INVERLUSRAGAN, CONNEL (REF:
21/01583/PP) 
The Development Manager spoke to the terms of the report. This application was first
presented to the Planning, Protective Services and Licensing (PPSL) Committee on 20
September 2023 at which time Members agreed to its continuation to a Pre-Determination
Public Hearing which was held on 30 January 2024. 
The Supplementary Report brought the planning file up to date to include details of a
representation submitted from Councillor Julie McKenzie noting her support prior to the
application being presented to the September PPSL meeting and also an error in the
original Report of Handling, details of which were presented verbally to Members at the
beginning of the presentation to the Committee on 20 September 2023. 
The Supplementary Report also details the withdrawal of an expression of support and the
submission of a late representation.
It was recommended that planning permission be refused for the reasons appended to the
report of handling. 
Motion 
I understand that this development is contrary to the stated intentions of NPF 4 Policy
9(b), and Argyll and Bute Local Development Plan 2015 Policies LDP 8 and SG LDP
REC/COM 2 and it is not possible to link the development to any of the exemptions that
relate to Policy SG LDP REC/COM 2 which would allow the development to comply with
the Local Development Plan (LDP) and LDP2. 
The OSPA has been designated because the open undeveloped space offered a high
degree of scenic amenity to the public with views left towards to Connel Bridge and the
Falls of Lora and right along Loch Etive.

Page 3

It is suggested in the report of handling that the proposed development will be highly
visible from the northern end of Connel Bridge and from the water of Loch Etive under
Connel Bridge and the North Connel/Bonawe road and while I accept that may be the
case, it is contended that such assessments are subjective and that as the main building
will be tucked in against existing development and the remainder of the development is at
a level where it will merge into the backdrop of Connel Village and as such the current
view from these locations towards the site will not be impacted detrimentally. 
The scenic amenity primarily encompasses views from and across the site towards
Connel Bridge, the Falls of Lora, and along Loch Etive. 
The open space is currently not easily accessible to the public and there is nothing to
suggest that members of the public do access it on a regular basis to take in these views.
That said, I am aware that the foreshore beyond the boundary of the site can be accessed
via a path to the east of the site. 
During the site visit, I found it difficult to see many aspects of the Connel Bridge and the
Falls of Lora from the pavement, on the main road, adjacent to the site due to the
existence of Connel Surgery, the House adjacent to it and the vegetation, trees etc along
the road which rises up at that point. It is also not possible to see much of the bridge and
the Falls of Lora when driving towards them. 
In a similar way, when travelling by car in the other direction from Connel Bridge towards
the site the road drops down and the views of the Falls of Lora are very limited and the
views along Loch Etive are unlikely to be hindered or affected for drivers or indeed people
walking along the footpath. It is also notable that the planning committee required to park
several minutes walk away from the site, as there is not currently safe parking places in
which to adequately view the scenic amenity. 
It is important to consider that this site visit was carried out during the winter month of
February when deciduous vegetation and trees are during a period of abscission, when
the leaves are naturally shed, with no examples of marcescence, where the leaves are
withering but remain attached to the stem, thus by, the scenic amenity during months
when trees and other vegetation are in full canopy or bloom, would be even more
restricted than that experienced by the committee during their site visit. 
The development will create a number of jobs in the area and the business will increase
the number of visitors to the area, which is likely to have a positive impact on trade for
other businesses in the area, which demonstrates economic benefit will be derived from
the development. 
As it stands, the OSPA creates no beneficial use of the location by the public and by
opening up the site with this development, consequently it will ensure direct access to
members of the public, locals and visitors and will offer the public the ability to enjoy all the
aspects of the OSPA area in a manner which has not previously been available to them. 
In conclusion, therefore I am of the view that the development has been designed to
minimise the impact on the OSPA to a level that will not detrimentally affect the scenic

Page 4

amenity of the location and will enhance it through providing access to the area and the
siting of the viewpoint. 
Therefore, on that basis, I move that the development is approved, subject to conditions
and reasons being delegated to the Head of Development and Infrastructure, in
consultation with the Chair and Vice Chair of the PPSL. 
For the avoidance of doubt, and in order to underpin the justification for departing from the
provisions of the Development Plan, such conditions shall include an appropriate
mechanism to secure the timely provision and ongoing maintenance of an accessible
footpath and viewpoint within the scheme of development, and to ensure that such
facilities will be made freely available to the general public without barrier to entry on a
permanent basis. 
Moved by Councillor Amanda Hampsey, seconded by Councillor Andrew Kain. 
Amendment 
The Committee refuse planning permission subject to the reasons appended to the Report
of Handling. 
Moved by Councillor Graham Hardie, seconded by Councillor Gordon Blair. 
As the meeting was being held remotely on Microsoft Teams, the vote required to be
taken by calling the Roll and Members voted as follows – 
Motion                               Amendment                     
Councillor John Armour  Councillor Gordon Blair
Councillor Amanda Hampsey Councillor Jan Brown
Councillor Andrew Kain  Councillor Audrey Forrest
Councillor Liz McCabe  Councillor Kieron Green
Councillor Dougie Philand  Councillor Graham Hardie 
Councillor Peter Wallace  Councillor Mark Irvine     
Councillor Luna Martin                                     
Decision 
The Amendment was carried by 7 votes to 6 and the Council resolved accordingly. 
(Reference: Report by Head of Development and Economic Growth dated 5 September
2023; supplementary report 1 dated 29 January 2024; Minute of the PPSL Committee
dated 30 January 2024; Supplementary report number 2 dated 20 February 2024;
submitted; Motion by Councillor Amanda Hampsey seconded by Councillor Andrew Kain,
tabled; and Amendment by Councillor Graham Hardie, seconded by Councillor Gordon
Blair, tabled)

Page 5

5. MS SHEENA FERRAND: SITE FOR THE ERECTION OF 10 DWELLINGHOUSES
(AS AMENDED 23.09.22): LAND NORTH OF ACHNAGARADH, CRAIGHOUSE,
ISLE OF JURA: (REF: 21/01037/PPP) 
The Planning Officer spoke to the terms of the report. The application was originally
submitted for the erection of 16 dwelling houses. Subsequent to the majority of the
representations, revised plans have been secured which have reduced the scale of
development to 10 dwellings. It is on this basis that the proposed development has been
assessed.
It was recommended that planning permission in principle be granted subject to the
conditions and reasons detailed in the report of handling.
Decision
The Committee agreed to grant planning permission in principle subject to the following
conditions and reasons:
Standard Time Limit Condition  (as defined by Regulation) 
Standard Condition on Soil Management During Construction 
Additional Conditions 
1 PPP - Approved Details & Standard Notes – Non EIA Development 
Plans and particulars of the matters specified in conditions 3, 4, 5, 6, 7, 8, 9,
10, 11, 12, 13, 14, 15, 16 and 17 below shall be submitted by way of
application(s) for Approval of Matters Specified in Conditions in accordance
with the timescales and other limitations in Section 59 of the Town and
Country Planning (Scotland) Act 1997 as amended. Thereafter the
development shall be completed wholly in accordance with the approved
details. 
Reason: To accord with Section 59 of the Town and Country Planning
(Scotland) Act 1997 as amended.  
2. PPP - Approved Details & Standard Notes – Non EIA Development 
The development shall be implemented in accordance with the details
specified on the application form dated 12.05.2021, supporting information
and, the approved drawings listed in the table below unless the prior written
approval of the planning authority is obtained for an amendment to the
approved details under Section 64 of the Town and Country Planning
(Scotland) Act 1997. 
Plan Title. Plan Ref.
No.
Version Date
Received
Location maps and croft plan 599/01  04.10.2023
Site Survey Plan  599/03  29.09.2023
Revised floor levels houses 9 and
10 
1 of 2 19.01.2024 
Reason: For the purpose of clarity, to ensure that the development is

Page 6

implemented in accordance with the approved details. 
3 PPP - Provision of Adoptable Standard Service Road 
Pursuant to Condition 1. – no development shall commence until details of
the proposed service road and connection with the existing public road have
been submitted to and approved by the Planning Authority. Such details shall
incorporate: 
i) A vehicular access layout providing a Road over which the public has a
right of access in terms of the Roads (Scotland) Act 1984; 
ii) A junction with the existing public road formed with visibility splays of 
2.40 metres to point X by 75 metres to point Y formed from the centre
line of the junction; 
iii) A bus bay to be incorporated into the junction design with hardstanding
on constructed opposite the junction to provide for a bus drop off point; 
iv) The junction of adoptable standard development road is to be sited no
closer than 25 metres from the nearest existing junction; 
v) The development road is to have either 2.00 metre wide footways or
2.00 metre wide service strips; 
vi) The development road is to be no less than 5.50 metres wide; 
vii) A turning head for the public service vehicle at the end of the
adoptable standard road; 
viii) Roads design to incorporate Sustainable Urban Drainage (SuDS); 
ix) Hardstanding for the provision of two grit bins; 
x) Details for the provision of two village gateway signs to erected on the
public road; 
xi) Details for the provision of pedestrian on road signage to be provided
and erected between the development site; 
xii) Details for the provision of the existing public road verge to be widened
out to provide safe step offs for pedestrians between the development
and Craighouse School; 
xiii) Details for the provision of road name signs. 
Prior to work starting on site, the junction with the existing public road shall be
fully formed and surfaced and the visibility splays shall be cleared of all
obstructions such that nothing shall disrupt visibility from a point 1.05 metres
above the junction at point X to a point 0.6 metres above the public road
carriageway at point Y. The visibility splays shall be maintained clear of all
obstructions thereafter.

Page 7

All access roads, footways and step offs granted consent shall be
constructed to at least base course level prior to any work starting on the
erection of the buildings which they are intended to serve and the final
wearing surface of the roads, footways and step offs shall be applied
concurrently with the construction of the final building. 
Reason: In the interests of road safety and to ensure the timely provision of a
service road commensurate to the scale of the overall development and
having regard to the status of the proposed access as a residential service
road. 
Note to Applicant: 
Road Construction Consent under the Roads (Scotland) Act 1984 must be
obtained from the Council’s Roads Engineers and a Road Bond provided
prior to the formation of the access within the development site.  
4. PPP – Access/Parking/Turning for Multiple Buildings served by an
Adoptable Road 
Pursuant to Condition 1 – no development shall be commenced in respect of
any individual building until plans and particulars of the means of vehicular
access and parking/turning arrangements to serve that building have been
submitted to and approved by the Planning Authority. Such details shall
incorporate:   
i) Means of vehicular access to that building from the service road shall
be formed with  junctions of 90 degrees with visibility splays of  2.40
metres to point X by 25 metres to point Y formed from the centre line
of the junction or provision of 2.5m by 5m parking bays located behind
any footway/service strip; 
ii) The provision of parking and turning in accordance with the
requirements of policy LP TRAN 6 and Appendix C of the Argyll and
Bute Local Development Plan 2015. 
The approved means of vehicular access to the building shall be implemented
in full prior to the commencement of construction of the development which
the access is intended to serve and the visibility splays shall be cleared of all
obstructions such that nothing shall disrupt visibility from a point 1.05 metres
above the junction at point X to a point 0.6 metres above the public road
carriageway at point Y. The visibility splays shall be maintained clear of all
obstructions thereafter. 
The approved parking and turning layout to serve the building shall be
implemented in full prior to that building first being occupied and shall
thereafter be maintained clear of obstruction for the parking and manoeuvring
of vehicles. 
Reason: In the interests of road safety. 
Note to Applicant:

Page 8

Any parking bays provide will not be adopted. 
5. PPP BUILDING SITING, DESIGN & FINISHES – MULTIPLE BUILDINGS 
Pursuant to Condition 1 – no development shall commence until plans and
particulars of the site layout, design and external finishes of the development
for up to 10 dwellings within that plot have been submitted to and approved
by the Planning Authority. These details shall incorporate: 
i) A statement addressing the Action Checklist for developing design
contained within the Argyll and Bute Sustainable Design Guide 2006; 
ii) A statement addressing how the proposed development has been
designed to be consistent with the six qualities of successful places, as
defined within Policy 14 of NPF4; 
iii) Local vernacular design; 
iv) Maximum of 1.5 storeys in design; 
v) Rectangular footprint no greater than 100 square metres; 
vi) External building span no greater than 15 metres; 
vii) Symmetrically pitched roof angled between 37 and 42 degrees finished in
natural slate or good quality artificial slate; 
viii) External walls finished in natural stone or wet dash render or, a mixture of
both; 
ix) Details of finished ground floor levels relative to an identifiable fixed datum
located outwith the application site; 
x) Windows to have a vertical and symmetrical orientation. 
xi) A design and site layout that reflects the findings of survey work
associated with condition no 11 below, relating to reptile, amphibians, and bat
roost(s), including biodiversity enhancement measures. 
Reason: To accord with Section 59 of the Town and Country Planning
(Scotland) Act 1997 as amended, and in order to integrate the proposed
dwellinghouse with its surrounds. 
Note to applicant: The application lies with an NSA wherein the ability to
achieve a development that respects this designation is dependent on a
comprehensive and coherent high quality layout and design for the site as a
whole. This should be reflected in any submission to meet the terms of this
AMSC, with pre-submission discussions with planning officers strongly
encourage to help achieve this objective. 
6. PPP – Full Landscaping Scheme 
Pursuant to Condition 1 – no development shall commence until a scheme of
boundary treatment, surface treatment and landscaping has been submitted
to and approved by the Planning Authority. The scheme shall comprise a
planting plan and schedule which shall include details of: 
i) Existing and proposed ground levels in relation to an identified
fixed datum;
ii) Existing landscaping features and vegetation to be retained;
iii) Location design and materials of proposed walls, fences and
gates;

Page 9

iv) Proposed soft and hard landscaping works including the
location, species and size of every tree/shrub to be planted;
v) A biodiversity statement demonstrating how the proposal will
contribute to conservation/restoration/enhancement of
biodiversity, and how these benefits will be maintained for the
lifetime of the development;
vi) A programme for the timing, method of implementation,
completion and subsequent on-going maintenance.
vii) Identified areas of strategic landscaping with details of proposed
management arrangements; to include areas to the eastern
section of the site and land to the north of the application site as
a minimum. 
All of the hard and soft landscaping works shall be carried out in accordance
with the approved scheme unless otherwise approved in writing by the
Planning Authority. 
Any trees/shrubs which within a period of five years from the completion of
the approved landscaping scheme fail to become established, die, become
seriously diseased, or are removed or damaged shall be replaced in the
following planting season with equivalent numbers, sizes and species as
those originally required to be planted unless otherwise approved in writing by
the Planning Authority. 
The biodiversity statement should refer to Developing with Nature guidance |
NatureScot as appropriate.
Reason: To assist with the integration of the proposal with its surroundings in
the interest of amenity
Note to applicant: The application lies with an NSA wherein the ability to
achieve a development that respects this designation is dependent on a
comprehensive and strategic high quality landscaping scheme with
management arrangements. This should be reflected in any submission to
meet the terms of this AMSC with pre-submission discussions with planning
officers strongly encourage to help achieve this objective.  
7. PPP – Surface Water Drainage – Further detail required 
Notwithstanding the provisions of Condition 1, no development shall
commence until details of the intended means of surface water drainage to
serve the development have been submitted to and approved in writing by
the Planning Authority. 
The duly approved scheme shall be implemented in full concurrently with the
development that it is intended to serve and shall be operational prior to the
occupation of the development and maintained as such thereafter. 
Reason: To ensure the provision of an adequate surface water drainage
system and to prevent flooding.  
8. PPP – Archaeological Watching Brief

Page 10

Pursuant to Condition 1 - no development or ground breaking works shall
commence until a method statement for an archaeological scheme of
investigation has been submitted to and approved by the Planning Authority
in consultation with the West of Scotland Archaeology Service. The method
statement shall be prepared by a suitably qualified person and shall provide
for the recording, recovery and reporting of items of interest or finds within the
application site. Thereafter the development shall be implemented in
accordance with the duly approved details with the suitably qualified person
being afforded access at all reasonable times during ground disturbance
works. 
Reason: In order to protect archaeological resources. 
9 PPP - AFFORDABLE HOUSING 
Pursuant to Condition 1. - no development shall commence until a scheme
for the provision of affordable housing (as defined below) has been submitted
to and approved by the Planning Authority. The scheme shall: 
a) Provide that a minimum of 25% of the approved dwellings are
affordable homes; 
b) Define those properties to be used as affordable homes;
c) Establish the timing of their provision relative to the phasing of the
development, which shall ensure that the last 25% of the dwellings
within the development are not commenced until the affordable
housing phase has been completed for occupation;
d) Establish the arrangements to ensure the affordability of the affordable
homes for both initial and subsequent occupiers (including any
discount rate applicable in terms of (ii) below); 
For the purposes of this condition ‘affordable homes’ are defined as being
either: 
i) Social housing (rented or shared ownership or shared equity)
managed by a registered social landlord (a body registered under part
3 chapter 1 of the Housing (Scotland) Act 2001, or any equivalent
provision in the event of the revocation and re-enactment thereof, with
or without modification);
ii) Discounted low cost sale housing (subject to a burden under the Title
Conditions (Scotland) Act 2003), or any equivalent provision in the
event of the revocation and re-enactment thereof, with or without
modification).
iii) Housing for sale or rent without subsidy, which is designed to be
affordable and to meet the housing needs of the majority of those
households identified as in housing need in the Local Housing Strategy
or Housing Market Study i.e. one or two person households on
average income, with conditions attached to their missives to prevent
further extension, thereby helping to ensure that they are likely to
remain affordable to subsequent purchasers. 
The development shall be implemented and occupied thereafter in
accordance with the duly approved scheme for affordable housing.

Page 11

Reason:  To accord with the provisions of the development plan in respect of
affordable housing provision.  
10 Prior to the commencement of development, a pre-construction survey shall
be carried out in respect of otters to checks for any new holts or resting
places that may have become occupied after the original survey.  This pre-
construction survey should be completed as close to the construction period
as possible and no more than 3 months before the start of work.  Full details
of the pre-construction survey shall be submitted to and approved in writing
by the planning authority prior to the commencement of development.  
11 PPP– Pre-commencement Survey 
No development or other work shall be carried out on the site until a pre-
commencement survey for the presence of reptile, amphibians, and bat
roost(s) has been carried out by an appropriately qualified person and has
been submitted for the written approval of the Planning Authority in
consultation with Nature Scot. In circumstances where species of interest are
identified as being present, or at risk from construction works, the survey shall
further provide suggested avoidance and or mitigation measures, including
timing constraints, to address such presence or risk. The development shall
be implemented in accordance with the measures identified in the duly
approved scheme. 
Reason: In the interests of protected species and nature conservation.  
12 No construction works shall be commenced until a Construction
Environmental Management Plan (CEMP) and a Site Waste Management
Plan (SWMP) have been submitted to and approved in writing by the
Planning. The CEMP shall inform the production of construction method
statements, and shall specify the siting of working areas, management
practices and measures to prevent pollution of the water environment.  The
CEMP shall also include a project specific Surface Water Management Plan
with appropriate protocols in place for the prevention of pollution entering the
sea during construction.
The SWMP shall identify all waste streams arising from construction and
proposals for their mitigation, including materials excavated on site and shall
also provide details of the proposed arrangements for the storage,
segregation, collection and recycling of waste arising during the operational
phase of the development.   The CEMP shall also include otter mitigation as
detailed in section 5.0 of the Otter Survey Report undertaken 26th July 2021
and provision for pre-start walk overs to check for ground nesting birds.
Reason: In the interests of pollution prevention, sustainable waste
management and protected species. 
13 No development shall commence until full details of a scheme for the
eradication of Rhododendron Ponticum has been submitted to and approved
in writing by the Planning Authority. The scheme shall include a timetable for
implementation and clearly identify the extent of the Rhododendron Ponticum
on a scaled plan.

Page 12

The scheme shall be implemented in accordance with duly approved details,
and prior to the commencement of development, a validation report
confirming details of the remediation treatment that has been carried out and
that the site is free of Rhododendron Ponticum shall be submitted to and
approved in writing by the Planning Authority. 
Reason: To eradicate Rhododendron Ponticum from the development site
and to prevent the spread of this non-native invasive species through
development works.  
14  PPP – Timescale to be Agreed for Completion 
Pursuant to Condition 1. – no development shall commence until details of
the proposed timescale for completion of the approved development have
been submitted to and approved by the Planning Authority. Thereafter, the
development shall be implemented in accordance with the duly approved
timescale for completion unless an alternative timescale for completion is
otherwise agreed in writing with the Planning Authority. 
Reason: In order to comply with the requirements of NPF4 Policy 16F  
15 PPP – Tree Retention and Protection 
No development shall commence until a scheme for the retention and
safeguarding of trees during construction has been submitted to and
approved by the Planning Authority. The scheme shall comprise: 
i) Details of all trees to be removed and the location and canopy
spread of trees to be retained as part of the development;
ii) A programme of measures for the protection of trees during
construction works which shall include fencing at least one
metre beyond the canopy spread of each tree in accordance
with BS 5837:2005 “Trees in Relation to Construction”. 
Tree protection measures shall be implemented for the full duration of
construction works in accordance with the duly approved scheme. No trees
shall be lopped, topped or felled other than in accordance with the details of
the approved scheme unless otherwise approved in writing by the Planning
Authority.
Reason: In order to retain trees as part of the development in the interests of
amenity and nature conservation.  
16 PPP – Availability of Connection to Public Water Supply 
No development shall commence on site until authorisation has been given
by Scottish Water for connection to the public water supply.  Confirmation of
authorisation to connect shall be provided in writing to the Planning Authority
before commencement of development. 
Reason:  To ensure that the development is adequately served by a public
water supply.

Page 13

Note to Applicant:
In the event that a public water supply connection cannot be obtained an
alternative private water supply would constitute a material amendment
requiring the submission of a further planning application.  
17 PPP – Details of New Private Foul Drainage System 
Pursuant to Condition 1 – no development shall commence until details of the
proposed means of private foul drainage to serve the development have been
submitted to and approved by the Planning Authority. 
The duly approved scheme shall be implemented in full concurrently with the
development that it is intended to serve and shall be operational prior to the
occupation of the development. 
Reason: To ensure that an adequate means of foul drainage is available to
serve the development. 
Note to Applicant:
Private drainage arrangements are also subject to separate regulation by
Building Standards and SEPA. 
(Reference: Report by Head of Development and Economic Growth dated 1 February
2024, submitted) 
6. BEATON AND MCMURCHY ARCHITECTS LTD: SITE FOR THE ERECTION OF
DWELLINGHOUSE: LAND NORTH OF LYNBURN, ROWAN ROAD, OBAN:
(REF: 22/01986/PP) 
The Planning Officer spoke to the terms of the report. This planning application seeks to
secure planning permission in principle for the erection of a dwellinghouse at land north of
Lynburn, Rowan Road, Oban and the formation of a vehicular access. The application has
been submitted with indicative details of the footprint of the dwelling and its siting within
the plot.
It was recommended that planning permission in principle be granted subject to the
satisfactory conclusion of a section 75 agreement, and the conditions and reasons
detailed in the report of handling.
Decision
The Committee agreed to grant planning permission in principle subject to the satisfactory
conclusion of a section 75 agreement, and the following conditions and reasons:
Standard Time Limit Condition  (as defined by Regulation)  
Standard Condition on Soil Management During Construction  
Additional Conditions    
1. PPP – Matters Requiring AMSC Submission

Page 14

Plans and particulars of the matters specified in Conditions 3, 4, 5, 7, 8 and 9
below shall be submitted by way of application(s) for Approval of Matters
Specified in Conditions in accordance with the timescales and other limitations
in Section 59 of the Town and Country Planning (Scotland) Act 1997 as
amended. Thereafter the development shall be completed wholly in
accordance with the approved details.  
Reason: In accordance with Section 59 of the Town and Country Planning
(Scotland) Act 1997 (as amended).    
2. PPP - Approved Details 
The development shall be implemented in accordance with the details
specified on the application form dated 30.09.2022 supporting information
and, the approved drawings listed in the table below.  
Plan Title. Plan Ref. No. Version Date Received
Site Plan &
Section 
2034 02 B 13.10.2022
Site & Location
Plans 
2034 03 B 13.10.2022
Cross Sections 2034 04   01.12.2022
Site & Location
Plans Road
Improvements
Proposals 
2034 07 A 06.02.2024
Junction Site
Plan as
Proposed 
2034 11   06.02.2024  
Reason: To accord with Regulation 28 of the Town and Country Planning
(Development Management Procedure) (Scotland) Regulations 2013.    
3. Timescale to be Agreed for Completion 
Pursuant to condition 1 - no development shall commence until details of the
proposed timescale for completion of the approved development have been
submitted to and approved by the Planning Authority. Thereafter, the
development shall be implemented in accordance with the duly approved
timescale for completion unless an alternative timescale for completion is
otherwise agreed in writing with the Planning Authority. 
Reason: In order to comply with the requirements of NPF4 Policy 16F.

Page 15

4. Vehicular Access, Parking and Turning 
Pursuant to Condition 1 – no development shall commence until plans and
particulars of the means of vehicular access and parking/turning
arrangements to serve the development have been submitted to and
approved by the Planning Authority. Such details shall incorporate: 
i) The upgrade of the existing access at the connection with the public
road in accordance with the Council’s Roads Standard Detail Drawing
SD08/002a with visibility splays measuring 2.4 metres to point X by 25
metres to point Y; 
ii) The provision of a parking and turning area in accordance with the
requirements of Policy LDP 11 and Supplementary Guidance SG LDP
TRAN 6 of the adopted ‘Argyll and Bute Local Development Plan’
2015; 
iii) The provision of a footway to be provided over the total length of the
private road; 
iv) A road carriageway with a minimum width of 3 metres; 
v) The provision of passing places in accordance with Operational
Services Drawing 08/003a at locations approximately 50m, 90m and
180m from the junction with the public road; 
vi) The provision of a turning head in accordance with Figure 18 of The
Roads Development Guide to be provided at the location where the
private road separates to serve the dwellings leading to ‘Toriskay’ and
the dwellings leading to ‘High Acres’ / ‘Rowan Hill’, with a bin storage
area to the rear of the turning head; 
vii) The provision of street lighting ducting to be installed from the junction
with the public road to the location where the private road separates to
serve the dwellings leading to ‘Toriskay’ and the dwellings leading to
‘High Acres’ / ‘Rowan Hill’; 
Prior to work starting on site, the approved scheme of works shall be
completed, and the visibility splays shall be cleared of all obstructions such
that nothing shall disrupt visibility from a point 0.6m above the road
carriageway at point Y and the visibility splays shall be maintained clear of all
obstructions thereafter. 
Reason: In the interests of road safety. 
Note to applicant: 
• A Road Opening Permit under the Roads (Scotland) Act 1984 must be
obtained from the Council’s Roads Engineers prior to the
formation/alteration of a junction with the public road. 
• The access shall be constructed and drained to ensure that no surface
water is discharged onto the public road.

Page 16

5. PPP – Availability of Connection to Public Water Supply 
Pursuant to Condition 1 - no development shall commence on site until
authorisation has been given by Scottish Water for connection to the public
water supply. Confirmation of authorisation to connect shall be provided in
writing to the Planning Authority before commencement of development. 
Reason: To ensure that the development is adequately served by a public
water supply. 
Note to Applicant:
• In the event that a public water supply connection cannot be obtained
an alternative private water supply would constitute a material
amendment requiring the submission of a further planning application.    
6. Sustainable Drainage System 
Notwithstanding the provisions of Condition 2, the development shall
incorporate a surface water drainage system which is consistent with the
principles of Sustainable urban Drainage Systems (SuDS) compliant with the
guidance set out in CIRIA’s SuDS Manual C753. The requisite surface water
drainage shall be operational prior to the development being brought into use
and shall be maintained as such thereafter.  
Reason:  To ensure the provision of an adequate surface water drainage
system and to prevent flooding.    
Note to Applicant: 
• Further advice on SuDS can be found in SEPA’s Standing Advice for
Small Scale Development – www.sepa.org.uk .    
7. Design and Finishes 
Pursuant to Condition 1 – no development shall commence until plans and
particulars of the site layout, design and external finishes of the dwellinghouse
has been submitted to and approved by the Planning Authority. These details
shall incorporate:

Page 17

i) A statement addressing the Action Checklist for developing design
contained within the Argyll and Bute Sustainable Design Guide 2006;  
ii) A statement addressing how the proposed development has been
designed to be consistent with the six qualities of successful places, as
defined within Policy 14 of NPF4;  
iii) Local vernacular design; 
iv) Maximum of one and three quarter storey in design;  
v) Rectangular footprint with traditional gable ends;  
vi) Symmetrically pitched roof angled between 35 and 42 degrees finished
in natural slate or good quality artificial slate;  
vii) External walls finished in white wet dash roughcast, white smooth
render, natural stone, timber cladding or a mixture of these finishes;  
viii) Details of finished ground floor levels relative to an identifiable fixed
datum located outwith the application site, along with details of the
existing and proposed site levels shown in the form of section
drawings, contour plans, site level surveys, or a combination of these;  
ix) Windows with a vertical emphasis; and 
x) Details of an area within the application site for the placement of
refuse/recycling bins.  
Reason: To accord with Section 59 of the Town and Country Planning
(Scotland) Act 1997 as amended, and in order to integrate the proposed
dwellinghouse with its surroundings.    
8. Landscaping and Biodiversity Enhancement  
Pursuant to Condition 1 - no development shall commence until a scheme of
boundary treatment, surface treatment and landscaping has been submitted
to and approved by the Planning Authority. The scheme shall include details
of:  
i) Location, design and materials of proposed walls, fences and gates;  
ii) Surface treatment of proposed means of access and hardstanding
areas;  
iii) Any proposed re-contouring of the site by means of existing and
proposed ground levels;  
iv) Proposed hard and soft landscape works; and  
v) A biodiversity statement demonstrating how the proposal will contribute
to conservation/restoration/enhancement of biodiversity, and how
these benefits will be maintained for the lifetime of the development.

Page 18

The development shall not be occupied until such time as the physical
biodiversity enhancement measures (bird nesting boxes, ‘swift bricks’, wildlife
ponds, bat and insect boxes, hedgehog homes etc), the boundary treatment,
surface treatment and any re-contouring works have been completed in
accordance with the duly approved scheme.  
All biodiversity enhancement measures consisting of new or enhanced
planting shall be undertaken either in accordance with the approved scheme
of implementation or within the next available planting season following the
development first being brought into use.  
All of the hard and soft landscaping works shall be carried out in accordance
with the approved scheme during the first planting season following the
commencement of the development, unless otherwise agreed in writing by the
Planning Authority.  
The biodiversity statement should refer to Developing with Nature guidance |
NatureScot as appropriate.  
Reason: To assist with the integration of the proposal with its surroundings in
the interest of amenity.    
9. Pre-commencement Survey 
Pursuant to Condition 1 - no development or other work shall be carried out
on the site until a pre-commencement survey for the presence of nesting birds
has been carried out by an appropriately qualified person and has been
submitted for the written approval of the Planning Authority. In circumstances
where species of interest are identified as being present, or at risk from
construction works, the survey shall further provide suggested avoidance and
or mitigation measures, including timing constraints, to address such
presence or risk. The development shall be implemented in accordance with
the measures identified in the duly approved scheme. 
Reason: In order to establish that the circumstances of the site have not
changed significantly between approval and implementation of the
development for the purpose of protecting natural heritage assets in the
interest of nature conservation.  
(Reference: Report by Head of Development and Economic Growth dated 9
February 2024, submitted)

Page 19

7. MR DOUGIE CRAIG: ALTERATIONS AND EXTENSION, SUB-DIVISION OF
EXISTING MAISONETTE AT FIRST FLOOR TO FORM SELF-CONTAINED 2
BEDROOM FLAT AT FIRST FLOOR AND 3 BEDROOM FLAT AT SECOND
FLOOR, REPAIR AND REPLACEMENT OF EXISTING ROOF: FLAT 1, 11
BATTERY PLACE, ROTHESAY: (REF: 22/02090/PP) 
The Planning Officer spoke to the terms of the report. Planning Permission is sought for
the subdivision of an existing five-bedroomed maisonette at 11 Battery Place, Rothesay,
Isle of Bute into a self-contained two bedroom first floor flat and a three-bedroom second
floor flat. Externally, the roof space is to be increased through the removal of the existing
dormer window on the front slope and its replacement with a mansard-type construction.
The existing extended roof on the rear slope is to be refurbished by a new external finish
and replacement windows. 
It was recommended that Planning Permission be granted as a minor departure to the
Local Development Plan 2015 and Proposed Local Development Plan 2 (as intended for
adoption) subject to the conditions, reasons and informative notes set out in the report of
handling. 
Decision
The Committee agreed that planning permission be granted as a minor departure to the
Local Development Plan 2015 and Proposed Local Development Plan 2 (as intended for
adoption) subject to the following conditions, reasons and informative notes:
Standard Time Limit Condition for Planning Permission (as defined by Regulation) 
Standard Condition on Soil Management During Construction 
Additional Conditions 
1. Unless otherwise directed by any of the conditions below, the development shall be
implemented in accordance with the details specified on the application form dated
17th October 2022; supporting information; and the approved drawings listed in the
table below unless the prior written approval of the Planning Authority is obtained for
an amendment to the approved details under Section 64 of the Town and Country
Planning (Scotland) Act 1997. 
Plan Title.  Plan Ref. No. Version Date
Received
Existing  Drawing No. 2207/001A   A  19.10.2022
Proposed Drawing No. 2207/002A A  18.10.2022
Proposed
First Floor 
Drawing No. 2207/003 - 18.10.2022

Page 20

Prop. Second
Floor Plan 
Drawing No. 2207/004 - 18.10.2022
Prop. Section
B – B  
Drawing No. 2207/005  18.10.2022
Prop. Section
C – C
Drawing No. 2207/006  18.10.2022 
Reason: For the purpose of clarity, to ensure that the development is
implemented in accordance with the approved details. 
2. Prior to the commencement of the development, full details of the
external finish of the new roofs and the new windows in the front and
rear roofs shall be submitted to and approved in writing by the Planning
Authority. Unless otherwise agreed in writing with the Planning Authority,
the new roofs and windows shall be installed in accordance with the
approved details. 
Reason: In order to successfully integrate the development with the
existing Listed Building and the wider Conservation Area and for the
avoidance of doubt. 
3. A facility for the storage of cycles, the details of which shall have been
previously submitted to and agreed in writing with the Planning Authority,
shall be provided within the rear curtilage of the application site prior to
the occupation of the first of the flatted dwellings hereby approved.
Unless otherwise agreed in writing with the Planning Authority, the
approved cycle storage shall be retained in perpetuity for this dedicated
purpose. 
Reason: In the interests of facilitating the use of cycles by the occupants
of the flatted dwellings hereby approved in accordance with the
provisions of National Planning Framework 4 Policy 13 ‘Sustainable
Transport’ and Supplementary Guidance policy SG LDP TRAN 2
‘Development and Public Transport Accessibility’ of the Argyll and Bute
Local Development Plan 2015. 
(Reference: Report by Head of Development and Economic Growth dated 5
February 2024, submitted) 
Having declared a non-financial interest in the following item of business, Councillor
Wallace left the room and took no part in discussion of this item. 
8. MRS KIRSTEEN MACDONALD: FORMATION OF VEHICULAR ACCESS,
FORMATION OF PARKING SPACE  AND REMOVAL OF WALL AND GATE: 4A
ARGYLE PLACE, ROTHESAY, ISLE OF BUTE: (REF: 23/00395/PP) 
The Planning Officer spoke to the terms of the report. The proposal seeks planning
permission for the formation of a vehicular access and the use of an existing hardstanding
in the front garden as a parking space at 4A Argyle Place, Rothesay, Isle of Bute. In order

Page 21

to achieve access and parking, the existing front boundary wall, railings and gate are to be
removed from the site.
It was recommended that Planning Permission be granted as a minor departure to the
Local Development Plan 2015 and Proposed Local Development Plan 2 (as intended for
adoption) subject to the conditions, reasons and informative notes set out in the report.
Decision
The Committee agreed to grant planning permission in principle subject to the following
conditions and reasons:
Standard Time Limit Condition for Planning Permission (as defined by Regulation)
Standard Condition on Soil Management During Construction
Additional Conditions
4. The development shall be implemented in accordance with the details specified on
the application form dated 26th February 2023; the Addenda dated 23rd March 2023
and 13th June 2023; supporting information; and the approved drawings listed in the
table below unless the prior written approval of the Planning Authority is obtained for
an amendment to the approved details under Section 64 of the Town and Country
Planning (Scotland) Act 1997. 
Plan Title.  Plan Ref. No. Version Date
Received
Location Plan  Ref. No.
TQRQM23074155036170  
- 13.06.2023
Site Plan 1:200  Ref. No.
TQRQM23074161329640 
- 13.06.2023
Site Plan 1:50   Drawing No. 202209-24 - 08.06.2023
Photographs and
Description of
Works  
Drawing No. 202209-25 - 08.06.2023 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details.
(Reference: Report by Head of Development and Economic Growth dated 5 February
2024, submitted)