Democracy Spraffa

Agenda Document Pack - Communities Committee - 28/10/2024

North Lanarkshire Council · 28 October 2024
Back to Communities Committee — 28 October 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

17 October 2024 
Members of the 
Communities Committee
Chief Executive’s Office
Archie Aitken
Chief Officer (Legal & Democratic)
Civic Centre, Windmillhill Street,
Motherwell ML1 1AB
www.northlanarkshire.gov.uk 
Notice is given that a Meeting of the Communities Committee is to be held in the Council
Chamber, Civic Centre, Windmillhill Street, Motherwell, ML1 1AB on Monday, 28 October
2024 at 10:00 AM which you are requested to attend. 
The agenda of business is attached. 
Archie Aitken
Chief Officer (Legal & Democratic) 
Members : 
Clerk Name: Karen Swan
Clerk Telephone: 07919 730272
Clerk Email: swank@northlan.gov.uk 
G Woods, P Patton, D Ashraf, C Barclay, A Beveridge, B Burgess, D Crichton, K Duffy, F
Fotheringham, K Harmon, M Hughes, J Jones, J Keltie, A Khan, M McBride, B McCluskey,
B McCulloch, P McDade, L Mitchell, L Nolan, L Roarty, N Shevlin, A Smith, J Toner, C
Williams.  
Page 1 of 186

Page 2

Page 2 of 186

Page 3

Agenda 
1 Declarations of Interest In Terms of the Ethical
Standards In Public Life Etc. (Scotland) Act 2000   
Operational   
2 Active and Creative Communities and Community
Facility Usage and Footfall - Q2 24-25 and Q2 23-24
Submit report by Chief Officer (Operations) providing
an overview of a range of sports culture and leisure
venues and community facilities, comparing quarter 2
of 2024-25 and quarter 2 of 2023-24. 
5 - 18 
3 National Physical Activity for Health Framework
Submit report by Chief Officer (Community Operations)
providing an update on the Physical Activity for Health
Framework, recently approved by COSLA. 
19 - 24 
4 Community Board Local Development Programme
Submit a report by Chief Officer (Strategic
Communication and Engagement) providing an update
on the progress of the Community Board Local
Development Programme (LDP) projects. 
25 - 88 
5 Community Boards and Partnership
Communications Strategy
Submit report by Chief Officer (Strategic
Communication and Engagement) providing an update
on key progress linked to supporting the development
of the Community Boards model. 
89 - 98 
6 Access to Free Period Products (Period Dignity
Initiative)  Annual Update
Submit report by Chief Officer (Strategic
Communication and Engagement) providing an update
on the activity relating to the delivery and further
developments in respect of Access to Free Period
Products. 
99 - 134
Page 3 of 186

Page 4

7  Community Asset Transfer: Overtown Sports Pitch
and Pavillion
Submit report by Chief Officer (Strategic
Communication and Engagement ) providing an update
on details of a Community Asset transfer (CAT) and
seeking approval of the Community Ownership and
Management of Assets Leadership Group of Overtown
Sports Pitch and Pavillion. 
135 - 152 
8 Digital North Lanarkshire PoW Update Immersive
Experience Project
Submit report by Chief Officer (Business and Digital)
highlighting the steps taken in respect of the installation
of immersive rooms across the Council estate. 
153 - 170 
9 Democracy Matters 2
Submit report by Chief Officer (Legal and Democratic)
providing an overview of the Democracy Matters 2
consultation. 
171 - 186 
Page 4 of 186

Page 5

North Lanarkshire Council
Report
Communities Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref    LR/HL/AH Date 28/10/24 
ACC and Community Facility Usage and Footfall Q2 24-25 and Q2
23-24 
From  Lyall Rennie, Chief Officer (Community Operations)  
Email Liddleh@northlan.gov.uk Telephone 07973 726496 
Executive Summary 
For the information of elected members, this report provides an overview of usage of a range
of sports, culture and leisure venues and our community facilities, comparing quarter 2 of
2024-25 and quarter 2 of 23-24. 
Recommendations
It is recommended that Committee: 
(1) Acknowledges usage and footfall associated with the council’s sports, culture,
leisure and community facilities. 
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (24) Review and design services around people, communities,
and shared resources
Programme of Work Statutory / corporate / service requirement
Item 2
Page 5 of 186

Page 6

1. Background 
1.1 North Lanarkshire Council has made a commitment to ensure our residents have
access to a range of services and venues across the authority which support their ability
to maximise health and wellbeing and give access to areas where they are able to work
with others to participate in activities or take part in projects which seek to provide
overall community benefit.   
1.2 Within this context, the council has a range of venues provided by either Active and
Creative Communities or Community Facilities which are used by the community in a
range of different ways.  Some venues are better used than others and it is recognised
that people’s habits have changed, particularly in the period following the pandemic. 
1.3 In line with our commitment to ensure the best use of the limited resources we have,
usage of such facilities is closely monitored and presented within this report for the
information of elected members. 
2. Report 
2.1 Appendix One provides a breakdown of footfall during quarter 2 of 2023/24 as
compared to quarter 2 of 2024/25 for Active NL, Community Libraries, Creative
Resources and Venues and Museums.  Information for community facilities is gathered
in a different manner, recorded both by the number of bookings made (count) and the
duration of those bookings.   
2.2 Quarter two shows a mixed position of usage with some deterioration compared to last
year.  This is generally a quieter period in our centres, primarily due to a reduction in
users linked to summer holiday absences or the temporary reduction in clubs and
groups over the summer months.  Poor weather is likely to have affected some outdoor
activities. 
2.3 Members will be aware that the council has a total of 68 community facilities and 60
are available for use by the public. Quarter 2 figures outline some of the quieter periods
for the service due to the school summer holidays and many users stop operating from
the end of June to when the schools return in August. Overall, this quarter in
comparison to the same 3 month period in 2023/24, there is good news in the increase
in usage period. In July figures were up by 1190 hours, in August the figures were up
by 470 hours and in September an increase on last year of 876 hours. The colour
coding within the table demonstrates performance against the same period in 2023/24
as a RAG status. 
2.4 The council continues to work with a range of local groups to support increased use of
our facilities wherever possible.  Work with the Community Ownership and
Management Group continues to support community interest in all forms of access
including community asset transfer where this approach supports the aspirations of
local groups. 
Page 6 of 186

Page 7

3. Measures of success 
3.1  A thriving and sustainable council service which supports the delivery of culture, sport,
leisure, and community facility services. 
4. Supporting documentation 
4.1       Appendix 1      Usage and Footfall Q2 2023/24 and Q2 2024/25.   
Lyall Rennie
Chief Officer (Community Operations) 
Page 7 of 186

Page 8

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?
Page 8 of 186

Page 9

Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☐
Page 9 of 186

Page 10

Usage and Footfall Q2 2023/24 and Q2 2024/25                                                                                                               Appendix 1 
Active NL 
2023-24 2024-25 % Q1
2024-25
Comment
Venues Q2 Q2 Movement 
Airdrie Leisure Centre 59342 83000 +39.87% 94730  
Aquatec 5728 5258 -8.2% 5047 
Birkenshaw Sports Centre 1961 1203 -38.7% 1540 
Broadwood Leisure Centre 155213 125439 -19.2% 152806 Studios closed for renovation 9-22 Sept 24
Ian Nicolson Centre 14593 14377 -1.5% 17737 
John Smith Pool 17576 17280 -1.7% 15964 
Keir Hardie Centre 9402 12293 +30.7% 7985 
Kilsyth Swimming Pool 28061 23000 -18% 24842 
Lochview Golf Centre 17104 20371 +19.1% 17128 
Palacerigg Golf Course 10755 10141 -5.7% 10038 
Ravenscraig Sports Centre 112971 117494 +4% 141778 
Shotts Leisure Centre 15657 14124 -9.8% 18794 Pool closed since 22 August 24
Sir Matt Busby Sports
Centre 114381 87332 -23.6% 103324 
Time Capsule 175191 136323 -22.2%
130258 Waterpark closed for 5 days from 31/07/24
due to power outage in local area.  Ice rink
closed for one day on 31/07/24 due to
softening of the ice (power outage).
Townhead 23247 10807 -53% 25920 
Tryst Sports Centre 113823 132287 +18% 145048 
Wishaw Sports Centre 128003 117692 -8.1% 117608 
Total 1003008 930421 -7.2% 1030547 
Page 10 of 186

Page 11

Community Libraries 
23-24  24-25 %
Q1 
2024-25  Comment
Libraries Q2 Q2 Movement 
Abronhill 5482 5981 -9% 5971 
Airdrie 12324 15400 +24% 14976 
Bellshill 12454 16178 +29.9% 14519 
Chapelhall 3109 3726 +19.85% 4516 
Chryston 2531 2624 +3.67% 2769 
Cleland 3034 3117 +2.74% 3019 
Coatbridge 13654 14157 +3.68% 14413 2 x one day of closure for building works
Condorrat 5728 6405 +11.82% 5522 
Cumbernauld 18589 16424 -11.65% 16148 
Kilsyth 6270 5377 -14.24% 4895 
Moodiesburn 3355 3408 1.58% 3669 
Motherwell 23411 23197 -0.91% 24187 
New Stevenson 2294 3313 +44.42% 3732 
Newarthill 1785 1665 -6.72% 1410 
Newmains 4491 4570 +1.76% 4413 
Shotts 1603 2090 +30.38% 1746 
Stepps - 3329 -  -
Stepps Library has been closed and re-opened
in July 2024.
Viewpark 2783 3917 +40.75% 3692 
Wishaw 19973 20895 +4.62% 22733 
Total 142870 155773 +9.03% 152606 
Page 11 of 186

Page 12

Outreach Services 23-24 24-25 % Q1
2024-25  Comment  Q2 Q2 Movement
Mobile 1 472 422 -10.59%  304
Regular periods of mechanical failure where
mobile off the road.
Mobile 2 (off road)     
Outreach Van 323 319 -1.2% 199 
Mobile 4 686 470 -31.4%  289
Regular periods of mechanical failure where
mobile off the road.
Total 1481 1211 -18.2% 792 
Creative Venues 
Creative
Venues 23-24 24-25 %
Q1
2024-25 
Q2 Q2 Movement  Comment
Airdrie Town
Hall 1064 11684 +998% 12584 
Bellshill
Cultural Centre 2014 2145 +6.5% 2837 
Cumbernauld
Theatre 8994 8695 -3.32% 16974 
Motherwell
Concert Hall &
Theatre
20527   
Venue closed
Total 32599 22524 -30.9% 32395 
Page 12 of 186

Page 13

Museums & Collections 
Museums 23-24 24-25 %
Q1
2024-25 
Q2 Q2 Movement
Comment
Summerlee 57392 49654 -13.48%
48022 
NL Heritage Centre 3566 4959 +39.06%
5233 
Total 60958 54613 +10.4%
53225 
Page 13 of 186

Page 14

Community Facilities 
Facility
Centre
Status
(weeks)
23-24 Q2
Count
23-24 Q2
Duration
(hours)
24-25 Q2
Count
24-25 Q2
Duration
(hours)
24-25 Q1
Count
24-25 Q1
Duration
(hours)
Average
Weekly
Hours in Q2
2024
Abronhill
Community
Facilty
52
141 214 138 276 151 239 63
Airdrie @ Home
Community
52
12 12 11 33 13 13 7
Allanton Cc 52 45 117 46 126 55 140 29
Andrew
Hamilton Cc
38
24 78 26 86 50 145 26
Antonine
Community
Sports
52
58 106 46 115 64 162 26
Auchinloch Cc 38 50 128 111 230 133 283 69
Beechbank Cc 52 72 224 88 292 99 308 67
Burngreen Cc 38 22 62 24 85 18 60 23
Burnhead Cc 52 115 258 157 655 142 377 150
Calderbank Cc 38 27 61 23 49 53 127 14
Caldercruix Cc 38 7 13 14 34 11 20 11
Chapelside Cc 52 495 1934 535 1700 709 2351 389
Charlotte Toal
Cc
52
214 989 236 1010 286 1087 231
Chryston
Cultural Centre
52
130 355 216 565 369 779 129
Page 14 of 186

Page 15

Cleland Cc 38 10 20 14 40 21 57 12
Coatbridge Cc 52 409 1437 697 2452 674 2553 561
Coltness Cc 52 165 474 137 352 157 432 81
Cumbernauld
New Town Hall
52
207 540 199 471 222 561 108
Forge Cc 38 74 210 24 58 71 196 17
Four Isles Cc 52 58 190 69 217 80 263 50
Frank Ferguson
Cc
52
84 311 84 326 90 332 75
Garrell Vale Cc 52 212 582 247 725 314 929 167
Gartcosh Cc 52 156 467 159 499 233 683 115
Facility
Centre
Status
(weeks)
23-24 Q2
Count
23-24 Q2
Duration
(hours)
24-25 Q2
Count
24-25 Q2
Duration
(hours)
24-25 Q1
Count
24-25 Q1
Duration
(hours)
Average
Weekly
Hours in Q2
2024
Gartlea Cc 52 257 806 256 952 282 1061 218
Glenmavis Cc 38 11 18 12 44 10 17 11
Gowkthrapple
Cc
38
20 55 19 79 35 131 24
Greenfaulds Cc 52 98 271 101 272 96 250 62
Harthill Cf 52 168 637 138 339 154 362 78
Hattonrigg Cc 38 25 83 47 160 66 203 45
Holytown Cf 38 83 225 92 265 127 353 79
Isa Money Cc 52 73 198 114 315 111 294 72
Jim Foley Cc 52 143 419 190 683 215 723 157
Page 15 of 186

Page 16

Joe McKay Cc 52 157 468 202 648 237 823 148
John
McCormack Cc
38
198 505 244 686 279 761 195
MacAuley Cc 38 100 253 89 247 98 250 71
Michael Sherry
Cc
52
50 126 31 90 62 162 21
Mount Pleasant
Cc
52
49 102 84 170 87 174 39
Netherton Cc 38 18 52 22 53 38 66 14
New Stevenston
Cc
38
36 81 37 95 46 104 27
Newarthill Cf 52 313 1258 305 1087 393 1340 249
Old Monkland C
Wing
52
65 135 62 122 106 214 28
Old Monkland
Cc
38
106 225 102 246 117 284 69
Overtown Cc 52 122 339 130 382 129 364 87
Pat Cullinan Cc 52 324 1343 325 1623 382 1895 372
Pather Cc 52 261 792 272 871 292 986 200
Pivot Cf 52 338 936 0 0 210 449 0
Plains Cc 52 57 115 56 149 52 129 34
Pollock Cc 38 33 122 37 118 66 217 36
Facility
Centre
Status
(weeks)
23-24 Q2
Count
23-24 Q2
Duration
(hours)
24-25 Q2
Count
24-25 Q2
Duration
(hours)
24-25 Q1
Count
24-25 Q1
Duration
(hours)
Average
Weekly
Hours in Q2
2024
Rochsoles Cc 38 46 197 16 43 20 50 14
Page 16 of 186

Page 17

Salsburgh Cc 38 55 120 63 144 84 164 42
Shawhead Cc 52 83 214 133 301 144 343 69
Shotts Cf 52 219 476 168 398 221 589 91
Springfield Cc 52 50 124 45 132 49 120 30
Tannochside Cc 52 101 271 108 298 111 301 68
The Link 52 145 403 339 995 289 793 228
The Muirfield
Centre
52
599 1880 645 2262 682 2274 518
The Village Cc 38 17 63 26 102 32 105 30
Viewpark Cf 52 465 1462 436 1274 599 1632 292
Westfield Cc 38 39 109 37 127 82 215 39
Totals  7729 23665 8291 26202 10018 30295 
Pivot CF – closed.
Link CF – recently returned from use as vaccination centre.
Page 17 of 186

Page 18

Page 18 of 186

Page 19

North Lanarkshire Council
Report
Communities Committee
Does this report require to be approved? ☐ Yes   ☒ No
Ref    LR/HL Date 28/10/24
National Physical Activity for Health Framework  
From Lyall Rennie, Chief Officer (Community Operations)  
Email Liddleh@northlan.gov.uk Telephone 07973 726496
Executive Summary
This report provides an update on the new Physical Activity for Health Framework, recently
approved by Cosla.  The framework replaces the Active Scotland Outcomes Framework that
was published in 2018 and provides a framework for action to improve levels of physical
activity at both national and local level which is firmly founded on evidence-based international
guidance from the world health organisation and other global partners as to the approach
which is needed to deliver sustainable change.
Set within a North Lanarkshire context, the report outlines our proposed next steps to fulfil the
ambitions set within the overall framework.
Recommendations
It is recommended that Committee:
(1) Acknowledges the ambitions set out within the Physical Activity for Health
Framework.
(2) Otherwise, acknowledges the contents of this report.
The Plan for North Lanarkshire
Priority Improve the health and wellbeing of our communities
Ambition statement (15) Encourage the health and wellbeing of people through a
range of social, cultural, and leisure activities
Programme of Work All Programmes of Work
Item 3
Page 19 of 186

Page 20

1. Background 
1.1 In 2003, Scotland was amongst the first nations in the world to publish a strategy which
recognised the consequences to public health of physical inactivity and identified
approaches which would help to address this challenge. ‘Let’s Make Scotland More
Active’ aimed to increase the proportion of physically active people in Scotland and
recommended approaches based on international evidence by which this might be
achieved. 
1.2 In the intervening twenty years, addressing physical inactivity has remained a policy
priority for the Scottish Government and local authorities. The Commonwealth Games
in Glasgow in 2014 gave new impetus to this agenda and the availability of new
international research and guidance provided a clearer framework for the development
of more nuanced approaches. This was encapsulated in the Active Scotland Outcomes
Framework (2015) which set out the shared vision and goals which shaped the
approach it and a wide range of partner organisations would take to supporting and
enabling people in Scotland to be more physically active. 
2. Report 
2.1 The core messages of Let’s Make Scotland More Active in 2003 are still relevant today
and the actions which have been taken forward in the last twenty years have had an
impact. The people of Scotland are more active now than they were in 2003. In the last
10 years, the percentage of adults meeting recommended levels of physical activity
has increased by 3% from 62% in 2012 to 65% in 2022. 
2.2 As reported to Communities Committee in August 2024, much has been achieved in
North Lanarkshire.  The Active & Creative Communities Strategic Framework 2020-24
has provided a clear focus on increasing participation and activity through a range of
social, cultural and leisure activities in response to the outcomes set for increased
activity.  The 2020-24 strategy was based within the context of the Active Scotland
Outcomes and sought to achieve an overall increase in physical activity.  The council’s
approach at that time sought to tackle both physical and mental health, with a
recognition that participation in a range of activities was the most effective method of
ensuring overall health and well-being. Over the period from 2020 to date, North
Lanarkshire has seen an increase of over 150% in participation among its community.   
2.3 However, much more work is needed. Insufficient physical activity is one of the 5 main
modifiable risk factors for the 5 main non-communicable diseases: cardiovascular
diseases, cancer, diabetes, chronic respiratory diseases, and poor mental health.  An
estimated 3,000 deaths in Scotland each year are attributable to physical inactivity.
More than 80% of deaths attributable to inactivity occur amongst those undertaking
very low levels of activity (under 30 minutes per week) 
2.4 What is Changing? 
2.4.1 Physical Activity for Health – Scotland’s National Framework has been developed over
the past 18 months with system partners including COSLA, Scottish Government,
sportscotland, Public Health Scotland, Community Leisure UK, Paths 4 All, Transport
Scotland and Nature Scot. The approach to improving levels of physical activity in
Scotland outlined in the framework document is underpinned by key overarching public
health principles, adapted from the World Health Organisation Global Action Plan for
Physical Activity.
Page 20 of 186

Page 21

• Human Rights Approach – the highest attainable standard of health is a
fundamental right of every human being.
• Equity Across the Life Course – it is recognised that disparities in physical
activity participation by protected characteristic must be addressed.  The needs
of all must be addressed to reduce inequality.
• Evidence-based Practice – all actions must be based on robust scientific
evidence from active evaluation and demonstration of impact. 
2.4.2 The overall vision for Scotland, as has been since 2003, is ‘More People, More Active,
More Often’; this remains the vision for Scotland’s new framework and is based on the
recognition that improving levels of activity is vital for the health and wellbeing of the
people of Scotland. Global evidence 1 indicates the actions which will lead to achieving
this vision. They encompass both national and local programmes and success will be
dependent on widespread acceptance of a common goal and an understanding of
where our collective priorities for action must be focussed. 
2.4.3 Within North Lanarkshire, Active & Creative Communities (ACC) are working with NHS
Lanarkshire to promote a local whole systems approach to public health which
recognises the need to bring a range of services and people together to support a
commitment to increasing activity and tackling the challenges outlined.  The actions
are wide ranging, ambitious, and long term – using the national framework to provide
an overall direction, supporting eight strategic outcomes: 
• Active systems
• Active places of learning
• Active travel
• Active places and spaces
• Active health and social care
• Active communications
• Sports and recreation
• Active workplaces 
2.4.4 Work with NHSL is at an early stage and will be shared with elected members as plans
are developed. 
2.5 Progress to Date 
2.5.1 While the priorities set out in paragraph 2.4.3 have just been launched, it is important
to recognise that the council has made critical progress in many key areas: 
• Active systems – we work closely with partners in sportscotland, Public Health
Scotland and NHS Lanarkshire to ensure a collective and strengthened
approach to physical activity.  The council has signed up to a four-year plan,
supported by sportscotland to deliver on the key priorities underpinning a more
active Scotland.
• Active places of learning – through our Active Schools team, we continue to
work with primary and secondary schools across North Lanarkshire to deliver
extra-curricular activities – at total of 1341 activities and 21,470 participants
during 2023/24.
• Active travel – members are aware of the council’s commitment to the Active
Travel Strategy, with ambitious projects underway across the North
Lanarkshire area.
Page 21 of 186

Page 22

• Active places and spaces – we continue to work together to maximise the
potential of public spaces, ensuring physical activity is a priority in all decisions. 
Ongoing discussions around the new Watersports Centre are an excellent
example of keeping health and wellbeing as a central tenet of development
discussions.
• Active health and social care – our partnership with NHS Lanarkshire continues
to develop with increasing recognition of the role that physical activity and
support from fitness specialists can play in supporting overall rehabilitation. 
Recent discussions around supporting heart health are ongoing.
• Active communication – still at an early stage, we are beginning to consider
how we target communication to key target groups, using the mechanisms
already in place.  A current example under development is targeting cervical
health messages to Active NL members.  We continue to work with Corporate
Communications to promote opportunities for physical activity and health
across North Lanarkshire.
• Sport and recreation – we continue to consider how best to use our sport
services to target key groups with a view to improving overall health.  In recent
years, our Active 60 and Active Teen programmes have seen hugely significant
results by the council’s ability to offer attractive programme offers.
• Active workplaces – for our own workplace, a discounted staff membership to
local gyms has seen a significant increase in activity, with ongoing staff offers
and programmes throughout the year, e.g. National Fitness Day on 17
September with free access to all services for staff. 
3. Measures of success 
3.1 Improved levels of physical activity at both national and local level which is firmly
founded on evidence-based international guidance. 
4.        Supporting documentation 
N/A 
Lyall Rennie
Chief Officer (Community Operations) 
Page 22 of 186

Page 23

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?
Page 23 of 186

Page 24

Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☐ 
Page 24 of 186

Page 25

North Lanarkshire Council
Report
Communities Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref    SP/MC Date 28/10/24 
Community Board Local Development Programme 
From  Stephen Penman, Chief Officer (Strategic Communication and Engagement) 
E-mail Penmanste@northlan.gov.uk 
Costellom@northlan.gov.uk  Telephone 07725 289559 
Executive Summary
This report provides an update on progress with the Community Board Local Development
Programme (LDP) projects previously approved by committee. 
In addition, the report seeks in principle approval for new potential projects as proposed by
local community groups. 
Recommendations
It is recommended that the Communities Committee:
(1) Recognises progress with the remaining 2022/23 programme and 2023/24 onwards
and approve projects which have potential for delivery in future financial years
depending on availability of budget and community support (Appendix 1);
(2) Recognises the capital budget allocated to the LDP for each Community Board area
in the new capital programme from 2024/25 onwards. (Appendix 2);
(3) Acknowledges the examples of completed project case studies (Appendix 3)
(4) Recognises the delivery of play area projects for 2023/24 (Appendix 4);
(5) Approves amendments to existing projects and further project proposals and project
criteria;
(6) Acknowledges current challenges faced in achieving delivery of the Local
Development Programme;  
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement (20) Improve the involvement of communities in the decisions,
and development of services and supports, that affect them
Programme of Work All Programmes of Work
Item 4
Page 25 of 186

Page 26

1. Background 
1.1 The Policy and Strategy committee agreed, in March 2019, that all projects from
2019/20 onwards, recommended by Community Matters partnerships (now replaced
by Community Boards) should be subject to agreement by the former Youth, Equalities
and Empowerment Committee before proceeding beyond the in-principle/ conceptual
stage. Further approvals will now be sought through the Communities Committee as
required.    
1.2 The current Capital Programme was reviewed and a new Capital Programme for
2024/25 to 2028/29 was agreed by the Council on 14th March 2024. The LDP has
secured funding for the new five-year plan totalling £10.369 million. The allocation of
funding includes a new capital allocation to support the Community Asset Transfer
(CAT) process. A total amount of £2.3 million from the LDP has been allocated to
support CAT over the 5-year budget period. This funding will be augmented by
£670,000 from the Shared Prosperity Fund to provide a £3 million fund to support CAT
over the next five years, as detailed in the report to the Policy and Strategy Committee
in June 2024. 
1.3 The indicative allocation of LDP funding by Community Board area is set out in the
table in Appendix 2 of this report. The level of funding shown for each Community Board
area excludes the CAT element of £2.3 million, which will be allocated via the process
set out in the Policy and Strategy Committee report of June 2024. 
1.4 Appendix 2 shows the allocation of LDP by Community Board area over the 5 years of
the capital plan. The allocation for each Board area is a calculation based on population
size and deprivation. The population percentages are drawn from the National Records
for Scotland 2020 mid-year estimates and the 2020 Scottish Index of Multiple
Deprivation (SIMD). 85% is allocated based on population, while 15% of the LDP
budget is allocated based on deprivation. The 15% figure is drawn from the proportion
of people who were “income deprived” in the 2020 SIMD. 
1.5 Appendix 3 of the report contains case study of a recently completed LDP projects, the
new junior play area at Kirkwood in the Coatbridge community board area, the
resurfacing of a path in Branchalwood Estate in Wishaw and the restoration of an
artwork at the Meadowhead underpass in Cumbernauld. The purpose of the case
studies is to provide elected members with greater insight into how LDP projects are
developed and delivered, from initial proposals through to the completion of the project.
All future LDP reports to Committee will include LDP project case studies. 
1.6 One of the key priorities for the LDP is the delivery of upgraded and new play facilities
across all 9 Community Board areas. Appendix 4 illustrates the progress made on the
2023/24 play area projects. Twenty two of the twenty-four play areas in the programme
have been completed by September 2024, with the two remaining projects due for
completion in October 20024. A programme for 2024/25 is under development and with
an initial start to the procurement process in October 2024. 
1.7 The amount allocated to each area reflects a reduction of up to 10% which will be
earmarked for delivery and other associated costs in relation to agreed projects, this
will include technical support, tendering processes, design and project management
and administration. 
Page 26 of 186

Page 27

2. Report 
Criteria for Local Development Programme 
2.1 To be eligible for inclusion in the Community Board Local Development Programme,
projects must meet the priorities of the Local Outcome Improvement Plan and
substantially subscribe to previously agreed criteria. 
The following are examples of some of the key criteria: 
• link to LOIP priorities
• be publicly visible and accessible;
• come from community groups or individual;
• improve community safety;
• benefit a large number of people;
• improve the appearance of an area.
• maximise the use of alternative sources of funding.
• be a capital projects on council owned land. 
All Local Development Programme proposal forms should indicate which, if any, of 
the Local Outcome Improvement Plan priorities the project supports. Where the 
project does not align with identified priorities, evidence must be provided to show 
how the project will support improved local outcomes.  
2.2 Project Progress 
• Information on current and potential future projects is contained within Appendix 1.
• Please note the figures in Appendix 1 are notional/indicative potential project costs
and that no budget has been allocated to specific projects. 
• The Community Board Local Development Programme highlights the council’s
commitment to community led neighbourhood regeneration.
• Prioritisation work has been undertaken taking account of the allocated budgets
and criteria to schedule project delivery of the current holding over the five-year
budget cycle. These priorities may change as projects develop and clearer costs
become available.
• Where feasibility checks have identified that the project is not viable, the
recommendation within Appendix 1 is to delete such projects from the list moving
forward. 
Page 27 of 186

Page 28

2.3  Projects seeking approval. 
Table 1 below, provides a summary of the LDP projects seeking Committee approval
in this cycle. In total, 13 projects across 6 of 9 the Community Board areas are seeking
Committee Approval. 
Table 1. Projects seeking approval from this cycle of Community Boards 
Community
Board Area
Project Name  Project
Description 
Project
Potential
Cost 
Additional
external or
partner
funding
available 
Additional
Notes 
Airdrie Milton Court
Social Place 
Seating Area  Seeking
Approval 
TBC  Project
proposal to be
completed with
Tenants &
Residents
Association.
Contact Project
Team to
progress
further. 
Airdrie  Ballochney
Road Plains
Path installation 
Surfacing  Seeking
Approval 
£20000  Community
engagement
complete. 
Surfacing: Path
installation. 
Site visit and
feasibility
checks to be
carried out 
Bellshill Belvidere
Crescent
Parking Bellshill
Additional
parking
spaces
Seeking
Approval
£15,000 Timescale FY
24-25. LDP
project proposal
submitted. 6
potential
spaces
Bellshill Clay Crescent
MUGA
The area
distinctly lacks
sufficient open
space public
sports
facilities. Using
existing red
ash paved
football pitch
which is a
health and
safety concern
for causing
injuries. 
Seeking
Approval
TBC + DC
(200K)
Proposal form
received. Site
visit completed.
Potentially to be
procured Jan
25
Cumbernauld Glencairn Road
Boulder removal
and extra
parking spaces
Environmental
& Parking
Seeking
Approval
Approx £5k 
Feasibility
checks
completed.
Boulders can
be removed
and placed in
Page 28 of 186

Page 29

Kildrum Primary
School.
To be
completed by
end of Sept 24
Motherwell Outdoor Gym,
Glenmore Rd-
Lomond Walk,
Newarthill
Development
of an outdoor
gym for
community
use
Seeking
Approval
£40,000 Proposal form
received from
Community
Action
Newarthill. 
Early stages,
validity checks
of project
required. 
Consultation to
be arranged.
Location to be
confirmed
Motherwell Coursington
Crescent
Parking
Additional
parking
Seeking
Approval
£15,000 Timescale FY
24-25
Proposal form
submitted. Site
visit and scope
checks
completed.
Potential for 10
spaces.
To be part of
procurement
post summer
24
Presence of
gas service
along the fence
but no issues
found
Motherwell Lighting on
pathway and
dog park,
welfare park,
Newarthill
Lighting
project
Seeking
Approval
TBC Proposal form
submitted.
Location
confirmed
Solar lighting to
be extended
and site visit to
be arranged.
Issues
identified re
different
surfacing
Motherwell Jerviston Play
Area
Replacement 
Play Area
replacement
Seeking
Approval
TBC Proposal form
submitted.
Consultation
underway.
Timescale FY
25-26
Northern
Corridor
Frankfield
Road,
Cardowan ash
area project
To provide a
new whin
dust gravel
surface on
the ash area
Seeking
Approval
£10,000 Proposal
received. Site
visit &
feasibility
Page 29 of 186

Page 30

next to
Cardowan
Multi-Use
Games Area
(MUGA)
facility, at
Frankfield
Road,
Cardowan. A
new surface
would
support
improved
delivery of
bike hub
activities by
Cardowan
Community
Hub.
checks
completed.
Wishaw Waverly Drive
Play Area
Replacement
and upgrade
of Waverley
Drive Play
Area 
Seeking
Approval
TBC (SG
Funding)
Further
consultation
and
engagement
with the local
community to
follow in
relation to
preferences
for play area
design. 
Wishaw Newmains
Community
Council MUGA
Clarification
on project
one survey
findings is
received
Seeking
Approval
£140,000 Awaiting
survey results.
Follow up
meeting with
Community
Council being
arranged.
Working with
local
organisations
to develop a
Community
Action Plan.
Future
engagement
planned for
the summer.
Wishaw Cambusnetha
n Memorial
Park Play Area
Replacement
and upgrade
of Play Area
Seeking
Approval
TBC (SG
funding)
Further
consultation
and
engagement
with the local
community to
follow in
relation to
Page 30 of 186

Page 31

preferences
for play area
design. 
LDP programme and financial position 
2.4  Graph 1 below sets out LDP project spend by community Board areas for financial year
2024/25, from 1 April 2024 to 10 September 2024. The data shown on the chart
illustrates the actual spend on the ledger at this date. 
2.5 The total expenditure to date is £962,610. This is the total spend for the LDP
programme, which includes Council capital funding for the programme, including carry
forward from financial year 2023/24, and, where relevant, Scottish Government Play
Area Renewal Funding and developer contributions. These funding sources are
dedicated to the funding of play areas and Multi Use Games Areas (MUGAs). 
2.6 Graph 1. LDP Programme Expenditure by Board Area 2024/25 
2.7 The graph illustrates project spend by Board area in the current financial year, as at
September 2024, based on payments made by the LDP project team. It should be
noted that there is a considerable variation in expenditure across the Community Board
area. This reflects, to a large extent, the type of project that has been completed in
each area since the start of the financial year. For example, both Bellshill and Northern
Corridor show a high level of spend. Both Community Board areas have had large
MUGA projects installed this year as well as other play facilities. 
2.8  Conversely, Kilsyth shows no expenditure, as of mid- September. Graph 1 does not
show that the Bogside play area project has recently been completed which has a
budget expenditure of £80,000. As more projects complete over the remainder of the
year, for example two play area projects will be completed in Airdrie in late September,
project expenditure by Board area will show far less variation than presently. 
2.9     Graph 2. below shows the breakdown of LDP projects by development stages for
financial year 2024/25. It shows the scale of the LDP programme, in terms of the
number of projects that have been approved (potential) and are in progress, a total of
82, and the number that are under development (38) and seeking approval (10). This
is a very large number of projects, fully detailed in Appendix 1, and indicates the high
level of demand for LDP projects from the Community Board areas of North
Lanarkshire.  Graph 2. also illustrates that 23 projects have been completed by mid-
Page 31 of 186

Page 32

September, with many more in the pipeline to be completed by the end of the financial
year. 
Graph 2. Number of LDP projects by development stage 2024-25 
2.10  Further detail at a Community Board level is provided in Graph 3. This illustrates the
number of projects at each development stage by Community Board area. Graph 3.
Shows more detailed information on the status of projects for each Community Board
area. As with the information included in each of the graphs, this will be updated for
each future Committee report. 
Graph 3. LDP projects by development stage by Community Board area 2024/25 
Page 32 of 186

Page 33

3. Measures of success 
3.1  Projects delivered within agreed timescales taking into account all relevant factors and
budgetary considerations. 
3.2 Local communities are involved from the earliest stage in the development of project
designs and delivery and are generally satisfied with the outcome. 
3.3 People in communities whose voices are seldom heard are engaged in putting
forward/influencing projects within their community. 
3.4 The governance role of the Community Boards is consolidated in terms of project
development, approvals, and monitoring processes.   
4. Supporting documentation 
4.1 Appendix 1    Community Board Local Development Programme 2023/24 onwards
4.2 Appendix 2    Budget Information
4.3  Appendix 3    Your community asked, we delivered: LDP project case study, Kirkwood
junior play area Coatbridge, Branchal wood estate path upgrade Wishaw and
underpass restoration Cumbernauld.
4.4 Appendix 4    Play Area Development List 2023/24   
Stephen Penman
Chief Officer (Strategic Communication and Engagement) 
Page 33 of 186

Page 34

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Each of the projects in the attached Appendices, if deemed appropriate for delivery
and where budget is available is supported through funding available via the
Community Board Local Development Programme capital allocation. Consideration
will also be given to maximising external and other partner contributions where
possible. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data? 
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
Page 34 of 186

Page 35

5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Several of the projects will have a positive effect on the local environment,
contributing to safer areas to play and addressing issues traffic congestion in
specific areas. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The LDP is discussed widely with community groups and local consultation will be
communicated as required. In conjunction with local communities, a
communications approach will ensure that projects are promoted positively. 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
There are no significant financial risks which have been identified at this stage in
the financial year, however this will continue to be closely monitored. Some
projects may not proceed as a result of e.g., community consultation or site
investigations and outstanding budgets will be re-allocated to other projects which
will be reported to a future Community Board. It should be acknowledged that there
are nationwide challenges in relation to supply of materials and there is also an
impact on material costs leading to potentially higher contract costs which could
impact on delivery of projects. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Page 35 of 186

Page 36

Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☒ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
Information is provided regarding upgraded and new play areas across North
Lanarkshire. 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☒ 
Page 36 of 186

Page 37

Appendix 1
Airdrie
Project Name  Project
Description 
Progress  Budget  Notes 
Calderbank Welcome
Road Sign 
Welcome Sign  Under
Development 
£3000  A site has been identified,
north of Brownsburn park-
proposal form had been
sent, awaiting return. 
Lost Villages  Heritage
Project 
Under
Development 
TBC  Feasibility checks to be
done. 
Chapelhall/ Bellside
Road Parking 
Surfacing  Under
Development 
£40000  Awaiting outcome of legal
issues (Approved Previously
by Board) 
No progress till further
Notice 
Petersburn Play Area,
Varnsdorf way 
Toddlers Play
Area 
Under
Development 
£50000  Feasibility Checks to be
done. 
Arrange site visit and check
land ownership 
Timescale FY 25-26 
Holehills Kickabout
Area 
New Play Area  Under
Development 
TBC  Seek Permission from
Education. 
Consultation Letter is out
on the site, no proposal
form yet. Possibility of
developing dual access.
Liased with Forward
Planning Team 
Potential to resurface the
MUGA with polymeric
surface 
Milton Court Social
Place 
Seating Area  Seeking
Approval 
TBC  Project proposal to be
completed with Tenants &
Residents Association. 
Page 37 of 186

Page 38

Ballochney Road Plains
Path installation 
Surfacing  Seeking
Approval 
£20000  Community engagement
complete. 
Surfacing: Path installation. 
Site visit and feasibility
checks to be carried out 
Caldercruix Play Area  Play Area
Upgrade 
Potential/ In
progress 
£100000  Site visit completed. 
Design specification
underway. 
To be delivered in FY 2024-
25  
Arrange further school &
community consultation. 
Consultation in progress,
letters sent 
Petersburn Main Play
Area 
Renew existent
play area and
concentrate all
play provisions
in one play area 
Potential/ In
progress 
£100000  To be delivered in FY 24-25. 
Consultation in progress,
letters sent 
BMX Pump Track,  Funding to
support
regenerating of
the facilities or
build a new
pump track.
Pump Track -
Play 
Potential/ In
progress 
LDP: £10000 
External
Funding:
£140,000 
Proposed site identified
following site meeting.
Project Team to progress.
To be progressed in
2024/25 
Holehills Development,
Play Area Kenilburn
Ave, 
Play Area  Potential/ In
progress 
£10000 +  
Housing
Developers
off-site
contribution 
Feasibility of utilising area
at Kenilburn Ave done 
Due to be delivered 24/25 
Site visit complete, location
identified 
Consultation in progress,
letters have been sent out 
Brownsburn Park,  Upgrade to
Paths 
Potential/ In
progress 
£45,000   Completed mid-September
24 
Page 38 of 186

Page 39

Whinhall Allotments  The installation
of new path,
raised beds and
associated
ground works 
Potential/ In
progress 
£15000  Projects Team confirming
contract delivery and start
date  
Craigneuk Play Area,
Calderigg place, 
Play Area  Potential/ In
progress 
£100,000  Contractor appointed. 
Project completed;
inspection underway 
Community Safety
CCTV 
CCTV
installations 
Potential/ In
progress 
£25000  £15,000 for Petersburn
New Play Area - Completed 
Chapelhall (Est: £15k), due
to be installed 
CCTV for Petersburn re fly
tipping Installed end of Aug
24 
Caldercruix Heritage
Project 
Heritage
Project 
Potential/ In
progress 
£42,945  Site open- May 2024. 
Project Team to arrange for
outstanding works due to
be completed. 
Glen Road, Petersburn  Parking  Potential/ In
progress 
£15000  Progressing in FY 24-25 
West end/ Centernary
Park 
New
Interpretation
boards 
Potential/ In
progress 
£15000  Progressing in FY 24-25 
Community Partnership
Initiatives 
  
Potential/ In
progress 
£10000    
Hill Street Parking,
Caldercruix 
Creation of
Additional
Parking Bays 
Completed  £16600.65  Completed Feb 24 
Jarvie Avenue, Plains  Parking  Completed  £20655.5  Completed April 2024 
Plains Community
Features, Outdoor Gym 
Outdoor Gym  Completed  £24200 + 
£13000
grants from
Consortium &
Lottery 
Works completed summer
2024
Page 39 of 186

Page 40

Gartleahill Play Area  Play Area  Completed  £99,909  Wheeled sports - year
2024-2025  
Contractor appointed. 
Project completed;
inspection
underway September 2024
Rawyards Roundabout  Environmental
improvement 
Completed  £10000  Veg clearance works
complete. Supplementary
Planting and general
maintenance work ongoing. 
Victor Street/ Stemac
Lane Plains 
Parking  Completed  £6196.51  Completed Feb 2024 
Four Isles Community
Centre, Fencing Project 
Install fencing to
create outdoor
area behind the
community
centre 
Removed  £10,000  Group who proposed
project have disbanded
therefore project no longer
required. Propose to
remove from the list. 
Crowwood Road,
Calderbank 
Parking  Removed  £15000  Progressing in FY 2024-25. 
Community engagement
underway. 
Location & scope to be
confirmed 
Removed due to presence
of trees and on a corner 
Calderbank Dog
Walking Area 
Install fencing to
create a dog
walking area
adjacent to the
synthetic grass
pitch 
Removed  £15000  20 June 24: A decision was
made by management that
it will not be progressing 
Page 40 of 186

Page 41

Bellshill
Project Name  Project Details Progress Budget Notes
Juniper Place Parking
Viewpark
Additional
parking spaces
Under
Development
£15,000 LDP project
proposal
submitted. Needs
approval from
Roads re Footpath.
Location
confirmed. No
services present
Timescale FY 25-26
Easter Wood
Crescent Parking
Viewpark
Additional
parking spaces
Under
Development
£15,000 LDP project
proposal
submitted.
Location to be
checked in with
Roads Team. Lock
up site to be used
first. Approx 15
spaces
Alder Bank Parking
Viewpark
Additional
parking spaces
Under
Development
£15,000 Timescale FY 25-26
LDP project
proposal
submitted. Site visit
completed;
services check
completed
McCracken Drive
Parking Viewpark
Additional
parking spaces
Under
Development
£15,000 Timescale FY 24-25.
LDP project
proposal
submitted. Site visit
to be arranged.
Possibility of 8
bays. Presence of
lighting service. To
be procured Oct 24
Page 41 of 186

Page 42

Windsor Road
Parking
Additional
parking spaces
Under
Development
£30,000 LDP project
proposal
submitted. Site visit
to be arranged.
Possible roadworks
to create access.
Site visit
completed. Project
out of LDP Scope
Belvidere Crescent
Parking Bellshill
Additional
parking spaces
Seeking
Approval
£15,000 Timescale FY 24-25.
LDP project
proposal
submitted. 6
potential spaces
Clay Crescent MUGA The area
distinctly lacks
sufficient open
space public
sports facilities.
Using existing
red ash paved
football pitch
which is a health
and safety
concern for
causing injuries. 
Seeking
Approval
TBC + DC
(200K)
Proposal form
received. Site visit
completed.
Potentially to be
procured Jan 25
Laburnum Rd
footbridge and
environment 
To repair side
panels of an
existing
footbridge.
Addressing litter
and fly tipping
issues 
In progress/
Potential
£10,000 Timescale FY2024-
25 To be
completed by
Structures Team of
council. Scope to
be determined by
the Structures
Team
Sycamore Ave,
Viewpark
Community Garden 
To create
community
garden or dog
walking area
In progress/
Potential
£25,000 Timescale FY 2025-
26. 
Subject to
Community Asset
Transfer (CAT)
inquiry. 
Design and
development
paused for
outcome of CAT. 
Page 42 of 186

Page 43

Main Street,
Holytown
Community Garden 
Community
Garden
In progress/
Potential
£25,000 Ideas from
residents for design
and development
received. 
Timescale FY 2024-
25. 
Holytown Main
Street fencing 
hoarding/fencing In progress/
Potential
£15,000 LDP proposal
submitted and
approved at CB
June 2024.
Discussion to be
arranged with
Graphics
Redwood Crescent,
Viewpark
Community Garden 
Project to create
a community
greenspace. 
In progress/
Potential
£30,000 Feasibility checks
required in terms
of scope,
engagement, and
design. 
Timescale FY 2024-
25. Paused for
further
investigation re
CAT. Proposer to
be changed
Page 43 of 186

Page 44

Viewpark Gardens
Office Cabin 
The proposed
project involves
the installation
of a portable
cabin on site,
which can help
to create a
multi-purpose
space which can
benefit the
community
within Viewpark.
In progress/
Potentia
£20,000 Timescale FY 2024-
25 for delivery in
conjunction with
local group subject
to legal agreement.
LDP Proposal
submitted. Subject
to CAT
Community Safety –
CCTV 
Additional CCTV
in locality in
conjunction with
community
safety partners 
In progress/
Potential
£25,000 FY 2024-25. None
so far
Community
Partnership
initiatives 
In progress/
Potential
£10,000  Year 3 delivery. 
Funding to support
partnership
initiatives.
Page 44 of 186

Page 45

Lilac Crescent
Parking 
Car Parking In progress/
Potential
£17500 Approved at CB
March 2024. 
Design
development and
consultation
underway.
Consultation
completed May 24.
Unclear responses
received from
residents. Possible
removal
Bellshill Gateway-
community Garden 
Bellshill
Gateway-
community
Garden 
In progress/
Potential
£25,000 LDP contribution
(Internal transfer to
greenspace) to
existing Gateway
project for the
community garden
construction. 
Site visit planned.
Liberty Road,
Parking Bellshill 
Additional
parking spaces
In progress/
Potential
£30,000 LDP proposal
submitted and
approved at CB
June 2024.
Potential for 8
spaces only as
services present
near location.
Design
development in
progress
Douglas Street,
Viewpark 
Car parking In progress/
Potential
£18000  Further
information is
required for
identifying location
and scope of work. 
To progress in FY
2024-25.
Needs approval
from Roads team.
To be part of
procurement post
summer 2024
Page 45 of 186

Page 46

Telford Street
Parking Bellshill
Additional
parking spaces
Removed £15,000 LDP project
proposal
submitted.
Location to be
confirmed.
Project not moving
forward
Crowflat View,
Viewpark
Car parking
project
Completed £10,209.80 Works completed.
Napier Square (north
side), Bellshill - car
park project
Car Parking Completed £15,804.40 Works completed.
Baird’s Ave,
Viewpark 
Play facilities
improvement
Project
Upgrading play
equipment in an
existing play
area    
Completed £99,578  Contractor
appointed. 
Work commenced
mid-May 2024. 
Works completed
July 24, site open,
inspection
completed.
Footpath works
ongoing
Clydesdale
Rd/Mossend Primary
School – car parking  
Car Parking Removed £35,000 Further
consultation
required with
Education and
Roads to determine
final proposal. 
Removing after
feasibility checks
Gemini Grove,
Holytown Wall
entrance project
Project to cut
through an
opening through
a low-level brick
wall for
residents’ access
to a public car
park. 
🎯
Completed
£2500 Contractor
appointed. 
Completed March
2024.
Page 46 of 186

Page 47

Orbiston bing
project
Vegetation
clearance to
footpaths and
existing
pedestrian
routes. 
🎯
Completed
£10,000 Arrangements
underway to
proceed. 
Veg clearance
completed March
2024; however
additional works
identified. Usage of
the site to be
assessed based on
Hub building
getting build in
future years.
Rosevale Crescent
MUGA  
Potential MUGA
facility 
Completed £30,000 +
£100000
External
Funding
Contractor
appointed and on
site. 
To be completed
by end of mid-June
2024 
Completed July 24
and open to use.
Footpath works
ongoing
Hamilton Place Play
Area (Quarry Street
Play Area)
New play area
development
Removed £130,000 Timescale FY 25-26.
LDP Project
Proposal
submitted.
Site visit
completed.
Removed due to
site near houses 
Coatbridge
Project Name  Project Details Progress Budget Notes
Greenend Play Area Full refurb. Add
to wheeled
sports provision,
extra play
equipment
Under
Development
TBC Request from T&R Org. 
Feasibility checks
completed.
Consultation underway.
To be part of
procurement October
24
Page 47 of 186

Page 48

Whifflet Park Environmental
Improvement
Under
Development
£0 Fountain area clear up
(Streetscene) & support
to T&RA to replace
benches around the
fountain. 
No LDP Proposal
needed
Bargeddie Play Area Play Area
upgrade
Under
Development
£20,000 Feasibility ongoing.
Proposal in progress.
Planning community
consultation June 2024.
1 unit/equipment needs
to be replaced
Cumberland place
and sharp avenue
Parking, 
Parking Potential/ In
progress
TBC Creating parking spaces,
congested area.
Potential issues
identified with this
project. Need to check
with roads
Community
Partnership
Initiatives 
Potential/ In
progress
£10000  
Mitchell Street,
Kirkwood Parking 
Parking approx.
6 bays
Potential/ In
progress
Funding
proposal
submitted for
£10k. £20K
required to
complete
project.
Funding proposal
submitted for 10k. £20K
required to complete
project.
Approved and Project
going to Convener’s
meeting. 
Feasibility checks
conducted.
Going to procurement
post summer 2024
Community Safety –
CCTV 
Additional CCTV in
locality in
conjunction with
Community Safety
Partners 
Potential/ In
progress
£25000 As required
Page 48 of 186

Page 49

Carnbroe Welcome
Signage & Heritage
panels 
Signage on
Roundabouts re
welcome & safe
driving &
heritage panels
to safely screen
mine cap in
community
garden
Potential/ In
progress
£10,000 Project requested by
CCAR – proposal
submitted; initial
feasibility completed.
Design process
completed with CCAR.
Only one signage to be
placed.
Requesting permission
from landowner
Kelso Quadrant
Community space, 
Create a useable
community
space on
currently
unused waste
ground to rear
of properties
Potential/ In
progress
£10000 Design workshop
completed, site drawing
in progress, initial clear
& cut back completed.
Potential for Street
Scene to provide
benches
Shining Stars
Outdoor Learning
Space Project 
Use space at
rear of building
to create secure
learning and
performance
space for ASN
theatre school
Potential/ In
progress
£10000 Initial feasibility
completed; project
proposal form
submitted. 
Design of outdoor
education space in
process with project
members and
supported by street
scene team.
Greenwood Crescent
Community Garden 
Community
Garden
Potential/ In
progress
£5000 + £5000
matched
resource from
Housing
Proposal submitted,
agreed matched
resources with Housing.
Internal transfer to
housing.
Project requested by
tenants.
Community
consultation completed
Page 49 of 186

Page 50

Langloan Community
Space 
reclaiming
community
spaces in
Langloan. Goal
Posts, roll bars
& seating area.
Potential/ In
progress
£5,000 Goalposts & Roll bars on
grass area leading to
‘the bumps’ to help
reclaim the space for
children & community,
also includes potential
support to community
garden space.
Goalposts received.
Awaiting delivery of Roll
Bars. Benches to be
arranged
Kirkwood Local
Improvements Dog
Walking Area
Dog Walking
Area
Removed £15000 Survey reports
complete. 
Scheduling in progress. 
On hold, Received
negative responses in
consultation, hence
removal of project.
Shawhead
Recreation Space 
Play Area Removed New Supply Project to progress
under New Supply as
part of Dunnotar
Avenue project – like
for like replacement of
recreation space.
Bargeddie restrict
access to quad bikes
Environmental
improvements
Removed £0 Block access to quad
bikes request from
residents.
Proposal received
Last Tram Project LDP Funding Completed £10,000 +
£5,000 Active &
Creative
Communities 
£1100 through 
Community
Benefits 
Funding proposal
submitted for 10k. £20K
required to complete
project. 
Approved and Project
going to Convener’s
meeting. 
Oak Place, Greenend
Parking Bays
Creation of
additional
parking bays to
alleviate
congestion
Completed £10,733.55  17 April 2024:
Works completed
Page 50 of 186

Page 51

Kirkwood Local
Improvements-
Junior Play area
Junior Play Area
Development
Completed £60000 Design Brief complete.
Final design
consultation completed.
Contractor appointed. 
Work commenced.
Completed June 2024
Margaret Street Park Remove fencing
& upgrade
lighting
Removed £0 Fencing completed. 
Upgrade from single to
dual light in progress
Feasibility of
changing/adding light to
be confirmed by GD
Project removed as light
levels already exceeds
maximum for the area
Summerlee Street
pathway
Parking &
Environmental
Completed £16,874.95  Extension of footpath
along grass verge.
Scheduling in progress 
Contractor appointed.
Completed March 2024
Dunure Place
Coatbridge
Creation of
parking bays to
alleviate
congestion
Completed £12,951.85  Works completed April
24
Dunure Street
Coatbridge Dog
Walking
Dog Walking
Area
Completed £15000 Contractor appointed. 
Completed May 24 
Cumbernauld
Project Name
& ID
Project Details Progress Budget Notes
Lime Crescent,
Abronhill
Parking Under
Development
TBC Application received.
Potential location to be
identified. Feasibility checks
to be conducted
Gap Site
Hoardings
Design of the
hoardings to include
historical information
and images of the
Village
Under
Development
TBC Proposal form received
Page 51 of 186

Page 52

Glencairn
Road Boulder
removal and
extra parking
spaces
Environmental &
Parking
Seeking
Approval
Approx £5k 
Feasibility checks completed.
Boulders can be removed
and placed in Kildrum
Primary School.
To be completed by end of
Sept 24
Afton Road,
Parking 
Parking In
progress/Pote
ntial
£15000 Request for additional
parking- feasibility checks
completed.
Community council
identified project as priority
one, out of applications
submitted.
Potential for 2 additional
parking bays. To be tendered
late summer 2024 subject to
further investigation
(Presence of trees)
To be tendered post summer
24.
Birch Parking In
progress/Pote
ntial
£45000 Three proposals submitted. 
Potential for 10 parking
bays. 
Consultation to be
conducted. To be included
within infrastructure
frameworks
Handrails,
Kildrum (3
Areas) 
Pathway Handrails
for 3 areas
In
progress/Pote
ntial
£10000 Proposal submitted by CC
and supported by local
community. 
Locations confirmed.  
Page 52 of 186

Page 53

Community
Notice boards,
Kildrum (3) 
Community Notice
Boards
In
progress/Pote
ntial
£7500 Proposal submitted by CC
and supported by local
community. Locations
confirmed                                      
Watch us
grow, 
Environmental
Improvements
In
progress/Pote
ntial
£10000 Natures Scotland License
received, funding to be
released by mid-September
24
Netherwood
Road, 
Parking In
progress/Pote
ntial
£15906.90 Contract awarded. 
Outstanding technical issues
to be resolved re trees. Trees
to be relocated and
replanted. Parking to be
completed by Oct 24.
Replanting to be completed
by Feb 25
Cumbernauld
Peace Garden
Memory Walk 
Memory Walk In
progress/Pote
ntial
£10000 Detail design required. To be
tendered in 2024-25. 
Site visit completed
Potentially combining 2
projects (Memory Walk &
Dementia Garden)
Eastfield Play
Area 
Playpark In
progress/Pote
ntial
£100000 Balloch site identified,
proposal submitted by local
community. 
To be progressed in 2024-25. 
School Children Consultation
completed June 2024. 
Design spec to be produced. 
Online Consultation
completed July 2024;
positive responses received
Melrose Road,
Greenfaulds 
Parking
Improvements
In
progress/Pote
ntial
£10833.75 Contract awarded. 
Outstanding technical issues
to be resolved. To be
completed by end of Oct 24
Page 53 of 186

Page 54

Community
Partnership
Initiatives
Funding to support
community
partnership
initiatives
In
progress/Pote
ntial
£10,000  
CCTV  CCTV In
progress/Pote
ntial
£25000 FY 2024-25:
Burns Road CCTV installation
- Removed
Installed & Operational
Clouden/Ellisland
Rowan Road
Carbrain Gully
Cumbernauld
Heritage
Project,
Abronhill 
Heritage Project In
progress/Pote
ntial
£4,900 Restoring of underpass
painting/mural. Advice
sought from Active and
creative communities.
Getting the artist on the NLC
system is in progress
Oak Road
Football Pitch,
Abronhill
Parking
improvements
Completed £30506.30 Completed Feb 2024
Millcroft road,
South Carbrain
Play Area Upgrade Completed £80,000
(Scottish
Government
money)
Works completed May 2024. 
Braehead
Road, Kildrum
Play Area Upgrade Completed £50,000
(Scottish
government
money)
Contract awarded. Works
completed end of March
2024, however additional
drainage issues identified
and to be resolved by June
2024.
Completed July 24
Ben Venue
Eastfield
Parking
Parking Removed £8941.50 Contract awarded, however
feasibility issues identified.
Following further
investigation, project
identified not viable due to
presence of other services
(Gas etc.)
Mossywood
Court,
Westfield
Parking
Parking Removed £12,000 Potential for 4 spaces. Not
viable because of trees 
Page 54 of 186

Page 55

Ellisland Road,
Kildrum
Parking
Parking Removed £15000 
Possible removal as Potential
location not identified.
Project could be for Roads
Team
Additional parking not
feasible
Darroch Way,
Seafar
Parking Removed £15000 Feasibility checks required.
Removal due to presence of
water pipe underground -
Inchwood
Road,
Westfield 
Parking Removed £10,412.24 Contract awarded. 
Works to be completed by
June 2024. 
On hold till confirmation
from Roads Team. 
Project removed due to
presence of trees and
services 
Kilsyth
Project Name  Project Details Progress Budget Notes
Kilsyth Old Peoples
Welfare Committee
– centre renovations
Contribution
towards
improvements
works at Old
Library
(Burngreen)
Under
Development
TBC Organisation seeking
third party funding
support for essential
building and facility
improvements.
Proposal will require
to be updated
CCTV   In
progress/Potential
£10000 Barlandfauld CCTV
completed: £14k
Argyll Place Parking,  Additional
parking spaces
required
In
progress/Potential
£15000 To be progressed in
2024-25. To be part of
Newlay's Programme
of Work. To be
completed by end of
Oct 24
Banton Parking,  Parking bays In
progress/Potential
£12552.50 Issues with street
lighting & location,
hence timescale
changed to FY 25-26
Page 55 of 186

Page 56

Rennie Road Play
Park, 
Replace Play
Area
In
progress/Potential
Est £80000 Community Group
(Tenants and
Residents) now
established.
Project scope to be
determined.
Site visit completed &
location confirmed.
CPO met with
community group;
Proposal received.
Utilising Natural Play
Community
Partnership
Initiatives
Funding to support
partnership
initiatives  
In
progress/Potential
£1500  
Bogside Park Play Park
Upgrade
Completed £15000+
£50000
Scottish
Government
Tender awarded Jan
2024. Works
commenced, to be
completed by end of
Aug 24
Project complete end
of Aug 24
Croy Community
Hub, community
garden
Outdoor
Community
Space (Garden)
Removed £15000 Timescale FY2024-
25. Costings to be
determined and
community
engagement required. 
Following Community
Consultation, project
no longer
progressing. 
Page 56 of 186

Page 57

Motherwell
Project Name &  Project Details Status Budget Notes
Rail bridge Project,
Craigneuk
Working with
the community
to develop a
rail bridge art
project, which
will include the
potential for
improvement
works on
Glencairn Road
Under
Development
TBC Early stages, scoping of
project required. No
proposal form received to
date. 
Further community
guidance required from
Glencassels community
development project. 
Land ownership checks in
progress
Outdoor Gym,
Glenmore Rd-
Lomond Walk,
Newarthill
Development
of an outdoor
gym for
community use
Seeking
Approval
£40,000 Proposal form received
from Community Action
Newarthill. 
Early stages, validity checks
of project required. 
Consultation to be
arranged.
Location to be confirmed
Coursington
Crescent Parking
Additional
parking
Seeking
Approval
£15,000 Timescale FY 24-25
Proposal form submitted.
Site visit and scope checks
completed. Potential for 10
spaces.
To be part of procurement
post summer 24
Presence of gas service
along the fence but no
issues found
Lighting on pathway
and dog park,
welfare park,
Newarthill
Lighting project Seeking
Approval
TBC Proposal form submitted.
Location confirmed
Solar lighting to be
extended and site visit to
be arranged. Issues
identified re different
surfacing
Page 57 of 186

Page 58

Jerviston Play Area
Replacement 
Play Area
replacement
Seeking
Approval
TBC Proposal form submitted.
Consultation underway.
Timescale FY 25-26
Community
Partnership
Initiatives
Funding to
support
community
partnership
initiatives
Potential/ In
progress
£10,000  
Community Safety
CCTV
Additional
CCTV in locality
in conjunction
with
Community
Safety Partners
Potential/ In
progress
£25000 Potential CCTV for issues in
Muirhouse:  Antisocial
Behaviour 5K
Duchess Park,
Hamilton Road 
New Notice
boards/signage
Potential/ In
progress
TBC Approved to order Notice
boards and signage.
Fife Drive,
Forgewood play park
improvement and
expansion 
Replace
missing
equipment and
consider
adding some
more play
equipment to
improve the
park
Potential/ In
progress
£80,000 Further discussion with the
local organisation and
community in progress. 
Application received.
Consultation underway.
Newarthill Path
lighting 
Path-lighting,
woodland
walking area
Potential/ In
progress
£7K to 10K Proposal submitted. 
Need to establish full scope
of work.
Newarthill Tree
Lighting Project 
Community
Council want to
light up 5 trees
next to the
welcome to
Newarthill
entrance
feature
Potential/ In
progress
£15,000 Work commenced.
Estimated delivery
Financial Year 24-25.
Page 58 of 186

Page 59

George St Park,
constructing walking
path 
LDP form
received from
the group
regarding
constructing a
walking Path
round the park,
with bench,
Trim trail and a
bog garden etc
Potential/ In
progress
Indicative
£80K to
£100K: SG
Early stages, validity checks
of project required. 
Local group to do local
consultation in Spring 24.
Site visit to be arranged
Lyons Quadrant,
Craigneuk
Additional
parking bays to
alleviate
congestion
Removed   Need to establish full scope
of work. 
To proceed next financial
year. 
Consultation completed
end of May 24 -> Negative
responses received; project
removed
Wittagreen Crescent
Play Park
Replace play
park
Removed £0 Proposal form submitted. 
Project removed after
feasibility checks
Newarthill Glenburn
Ave. Parking
Parking Removed £8,498.50 Additional fibre cabling
installed on site, no longer
feasible to proceed with
the project.
Kinloch Drive Parking Completed £3,300 Completed March 2024. 
Robert Burns
Avenue, Newarthill
Parking bays Completed £8,067 Contractor appointed. 
Completed April 2024.
Roman Road,
Motherwell Central
Play Area
Play Area Completed £140,000 Works completed June 24 
Page 59 of 186

Page 60

Northern Corridor
Project Name  Project Details Progress Budget Notes
Frankfield Road,
Cardowan ash
area project
To provide a new
whin dust gravel
surface on the ash
area next to
Cardowan Multi-
Use Games Area
(MUGA) facility, at
Frankfield Road,
Cardowan. A new
surface would
support improved
delivery of bike
hub activities by
Cardowan
Community Hub.
Seeking Approval £10,000 Proposal received. Site visit
& feasibility checks
completed.
Moodiesburn
Outdoor Gym
Establish an
outdoor gym
Potential/ In
progress
£20,000 Proposal form signed by
Moodiesburn Community
Action.
Location updated: Pivot
Community Centre,
Glenmanor Drive.
Feasibility and service
checks complete; and
agreed with community
Lochside Play
Area, Gartcosh 
Refurbish Play
Area
Potential/ In
progress
£10,000 +
£80,000 (SG
Funding)
£5000
(Developer's
contribution)
Work schedule to be
reassessed then start date
confirmed.
Auchinloch
Community
Council Outdoor
gym 
Establish outdoor
gym facility in
Auchinloch 
Potential/ In
progress
£20,000 Timescale financial Year
2024-25
Approved at Community
Board 21 Feb. 2024
Project identified through
Auchinloch Community
Action Plan.
Feasibility checks on
potential sites completed.
To be procured after
September 2024.
Page 60 of 186

Page 61

Moodiesburn
Play Area 
Create play area
at top end of
Moodiesburn 
Potential/ In
progress
£75K Timescale Financial Year
2024-25. 
Identified by Moodiesburn
Community Action Group
consultation. 
Consultation with schools
and community completed
April 2024. 
Proposed site on ground at
St. Michael’s PS,
Blackwoods Crescent
approved for use. 
To be procured after
September 2024.
Site visit completed by
Project Team
Cardowan
Community
Meadow
Outdoor Gym 
Establish outdoor
gym facility in
Cardowan
Potential/ In
progress
£20,000 Timescale Financial Year
2024-25. 
Endorsed at Community
Board 21/02/2024. 
Project identified through
Cardowan Community
Action Plan. 
Feasibility checks on
potential sites completed. 
To be procured after
September 2024.
Moodiesburn
Christmas Tree
Project 
Erect permanent
Christmas Tree in
Moodiesburn
Potential/ In
progress
£3,000 Timescale Financial Year
2025-26.
CPT and Streetscene to
conduct further feasibility
checks on potential sites
(Pivot CC).
CCTV
Community
Safety 
Additional CCTV in
the locality in
conjunction with
community safety
partners 
Potential/ In
progress
£15,000  
Community
Partnership
Initiatives
Funding to
support
community
partnership
initiatives
Potential/ In
progress
£3,000  
Page 61 of 186

Page 62

Dunalistair Drive
Play Area,
Millerston 
Replace Play Area Completed £60,000 +
£60,000
Scottish
Government
Funding
Completed April 2024
Kelvin Drive,
Moodiesburn
Wheeled sports
facility  
Wheeled sports
area
Completed £20,000 +
£133,000
(Developer's
contribution)
Works completed, May
2024
Northern
Corridor
Community
Volunteers:
Locality Heritage
Project
Further develop
local heritage
project
Completed £5000
External
Grant
Timescale Financial Year
2024-25.
Approved at Community
Board 21 Feb. '24. 
Stage 2 implementation of
the project.
Completed July '24
Blades Court,
Gartcosh
Parking
Car Parking bays Completed £7430.70 Completed March 2024
Lochside,
Gartcosh
Parking
Car Parking bays Completed £13,853.75 Completed March 2024
Frankfield Road,
Cardowan
MUGA
Cardowan MUGA
(Multi Use Games
Area) project 
Completed £107,291.52 Works completed July 2024 
Shotts
Project Name &
ID
Project Details Progress Budget Notes
Alexander
Peden PS
Harthill
Community
access to play and
greenspace
opportunities
Under
Development
TBC Initial discussions with
education services re
access to playpark
Summerhill
Place, Parking
Allanton
Parking project at
Allanton
Under
Development
£20000 Future years delivery
dependent on budget
and feasibility. Proposal
form received.
Water services found
after site visit, possible
removal
Page 62 of 186

Page 63

Salsburgh
Community
Council -
commemorative
Commemorative
Railway Hutch
and Wagon on
Rails and Pathway
Lighting
Under
Development
£15000 Timescale FY 24-25.
Delivery dependent on
budget and feasibility.
Pathway lighting to be
included as well.
Site visit completed.
Proposer resigned as
Chair
Salsburgh
Community
Council - Solar
Lighting
Solar lighting at
outdoor
community space
to aide
community safety 
Under
Development
£5000 Future years delivery
dependent on budget
and feasibility.
Possible merging with
commemorative project
Stane Gardens,
Additional
benches
Request for
additional
benches at Stane
Gardens
Under
Development
£3000 Future years delivery
dependent on budget
and feasibility. Service
cannot fund, looking for
LDP contribution
Nevis Place
Parking
Installation of
parking bays and
lining of parking
area in existent
area
Under
Development
£1000 Initial engagement taken
place. Proposal form
submitted. Lining of bays
to be included in current
contracts.
To be completed by end
of Oct 24
Erskine Way
Shotts Parking
Improvements
To increase the
number of spaces
available for local
household
vehicles. 
Under
Development
TBC Proposal form
submitted. Feasibility
checks need to be
conducted.
Belmont Drive
Parking
Installation of
parking bays
Under
Development  
Engagement undertaken.
Proposal form with
projects team for
feasibility checks. 
Not supporting due to
parking close by funded
recently by LDP
Hirst Gardens
Parking
Installation of
parking bays
Under
Development
TBC Proposal form received.
Awaiting feasibility
checks
Page 63 of 186

Page 64

Convenanter
Road Harthill
Parking and
accessibility
improvements
Installation of
parking bays
Under
Development
TBC Proposal form received.
Feasibility checks
completed; possible
removal due to presence
of water services, out of
LDP scope
Stane Corner
Parking 
Manse Road car
park lining and
directional
signage project to
be undertaken
along with a
community
awareness
campaign to
promote car park
usage
Potential/ In
progress
£10000 Contractor appointed for
delivery.
Project with Graphics
Team.
Sign graphics ready and
awaiting order for
contractor to build. Signs
to be relocated
Shotts Leisure
Centre Outdoor
Gym LD
Outdoor Gym Potential/ In
progress
£30000 Timescale FY2025-26. 
Delivery dependent on
budget and feasibility.
Community
Safety CCTV  
Additional CCTV
in the locality in
conjunction with
community safety
partners 
Potential/ In
progress
£25,000 Programme of camera
upgrades and new
installations undertaken
including support
towards a deployable
CCTV trailer. 
None so far
Hartwood Play
Area upgrade 
Funding to
support local
organisation with
play area
refurbishment
Potential/ In
progress
£15,000
LDP for
year 3
+ £70,000
EKF
external
funding
sourced by
organisatio
n 
Handover delayed till
new drainage installed
due to flooding risks.
Inspection completed.
Drainage work on site
completed in September
24.
Salsburgh
Feature
Lighting 
Project to install
lighting on
entrance features
and war
memorial   
Potential/ In
progress
£10000 Background planning
being finalised before
installation. 
Work in progress
(Columns installed).
Lighting arrived, more
ordered
Page 64 of 186

Page 65

Laggan
Path Parking 
Parking Project Potential/ In
progress
£10000 Currently assigned to
2024/25 delivery. Site
visit & Feasibility checks
completed. 
Not feasible at current
site, but possible
alternate location could
be suggested. 
Community
Partnership
Initiatives
Funding to
support
community
partnership
initiatives 
Potential/ In
progress
£2000 Approved at Community
Empowerment
Committee 
Salsburgh
Community
Council Wider
improvement
programme for
King George V
Park 
Wider
improvement
programme for
King George V
Park 
Removed TBC Future years delivery
dependent on budget
and feasibility. Proposal
form received. Service
cannot fund so unlikely
to move forward.
Project removed
Muldron
Terrace, Parking
Development of
parking bays to
reduce
congestion  
Completed £10302.87 Main build completed
but lining and top
dressing to be finalised. 
Completed May 24
Torbothie Rd  
Shotts Parking 
Creation Of Off-
Street Parking on
Torbothie Road
(176-180) to
alleviate local
issues. 
Completed £12900 Contractor appointed for
delivery. Expected to
complete by July 2024.
Delayed but projects
team assurance of
completion in short term
Completed June 24
Lochaber Road
Parking
Parking project Completed £28314.25 Main build installed.
Lining and top dressing
still to be completed.
Meeting held with street
scene to agree a solution
and location of a new
gate access. 
Completed May 2024 
Page 65 of 186

Page 66

Wishaw
Project Name  Project Details Status Budget Notes
Cleland Parking Lack of parking
at Crossgates
Ave, Crosshill Dr
& Fraser St
Under
Development
TBC Project idea raised by
local community – Site
visit completed. Further
checks required.
Proposal submitted.
Wishawhill/St
Matthews
Socialtrack
Project 
Environmental
& Woodland
improvements
around
Wishawhill
Woods
including
further
development of
pump
track/cycling
facilities 
Under
Development
Third Party
Contribution
TBC +
Potential of
up to
£100,000
funding from
Sports
Scotland
Facilities
Fund 
Idea being developed in
partnership with Social
Track and Green Action
Trust. Proposal to be
submitted in due
course. 
Overtown solar
lighting on
pathway
Built in Solar
Lighting on
pathway
Under
Development
Third Party
Contribution
TBC +
Potential of
up to
£100,000
funding from
Sports
Scotland
Facilities
Fund 
LDP Proposal currently
being worked with local
organisation. 
Arrange site visit and
check feasibility as well
as durability
Cleland Christmas
Trees
NLC funding of
50% costs
towards
community
Christmas trees
in Cleland in
partnership
with cleland
community
council
Under
Development
£1000 Proposal form signed.
NLC funding of 50%
costs towards
community Christmas
trees in Cleland in
partnership with
Cleland community
council
Page 66 of 186

Page 67

Newmains
Community
Council MUGA
Clarification on
project one
survey findings
is received
Seeking
Approval
£140,000 Awaiting survey results.
Follow up meeting with
Community Council
being arranged.
Working with local
organisations to
develop a Community
Action Plan. Future
engagement planned
for the summer.
Waverly Drive
Play Area
Replacement
and upgrade of
Waverley Drive
Play Area 
Seeking
Approval
TBC (SG
Funding)
Further consultation
and engagement with
the local community to
follow in relation to
preferences for play
area design. 
Cambusnethan
Memorial Park
Play Area
Replacement
and upgrade of
Play Area
Seeking
Approval
TBC (SG
funding)
Further consultation
and engagement with
the local community to
follow in relation to
preferences for play
area design. 
Cleland Sydney
Devine Memorial 
Memorial
Plaque for
Sydney Devine
in his town of
birth. 
Potential/ In
progress
£4k to £5k Proposal being
developed along with
local representatives. 
Positive response
received in community
board. Awaiting plaque
design details from
community group
Page 67 of 186

Page 68

Branchalwood
Estate, Coltness 
Environmental
improvements
Completed £5000 Nature Walk Upgrades.
Idea being developed by
local neighbourhood
group. Proposal form
submitted with location
plan. 
Pathway Improvement
works to be started end
of Aug 24. completed
mid Sept 24.
Signage to be ordered
Coltness
Welcome Sign 
Welcome Sign Potential/ In
progress
£20,000 Joint site visits
complete. Consultation
in progress. Project
team conducting
feasibility checks to
progress.
King George V
Play Area,
Wishaw 
Replace Play
Area
Potential/ In
progress
£50,000 +
£100,000
external
funding
Consultation and Design
Specification
completed. Contractor
appointed. 
Work commenced in
September 2024.
Cleland MUGA  Creation of new
MUGA
Potential/ In
progress
£70,000 Possible removal as no
community group
present or match
funding available
Cleland Public
Park 
Refurb and
extend play
area
Potential/ In
progress
£55,000 Contract awarded. 
Works completed;
Inspection completed
Aug 24
Signage to be installed.
Lyman Drive Play
Area 
Replace Play
area - upgrade
park
Potential/ In
progress
£40,000 Consultation and Design
specification completed. 
Contractor appointed. 
Works commenced Aug
24
Page 68 of 186

Page 69

Newmains
Community
Council Village
Welcome Sign 
Creation of
welcome sign
Potential/ In
progress
£20000 Timescale FY2024-25 
Consultation with
Newmains CC re
developed design
specification underway. 
Received positive
response re design from
CC
Works commenced. To
be completed by end of
Sept 24
CCTV Additional CCTV
in locality in
conjunction
with community
safety partners 
Potential/ In
progress
£25,000  
Community
Partnership
Initiatives
Funding to
support
community
partnership
initiatives 
Potential/ In
progress
£10,000  
Newmains Play
Area at
Community Hub
Improved play
area facilities in
conjunction
with local
community 
Completed £175,000 Works completed
Overtown
Brighter
Neighbourhood
Group - Outdoor
Gym
Outdoor Gym Completed £45,000 Works completed and
site handed over May
24
Park Quadrant
Parking
Junction
improvements
Completed £10,264.85 Works completed May
24
Install new swing
bay Parkside Play
Area, Cleland
Additional
works
Completed £5K external
funding
1 Nov 23: works
completed
Greenfield Drive
(Cambusnethan
Parking)
Parking Completed £9907.88 Completed 1 Mar 24
Page 69 of 186

Page 70

Cambusnethan
Dog Walking Area
Dog Walking
Area at
Cambusnethan
memorial park
Removed 0 LDP Project Proposal
received from
Cambusnethan CC in
support of the
community for a formal
dog walking area at the
Memorial Park.
LDP not supporting
anymore Dog Walking
areas but open to
development of other
local development 
Page 70 of 186

Page 71

Appendix 2
LDP 5-year allocation by Community Board
Year Airdrie Bellshill Coatbridge Cumbernauld Kilsyth Motherwell Northern
Corridor
Shotts  Wishaw
2024/25 £180,318 £134,642 £151,700 £158,383 £38,080 £174,494 £85,190 £49,722 £115,471
2025/26 £240,537 £177,823 £206,856 £212,200 £50,519 £232,809 £105,025 £65,964 £154,512
2026/27 £269,137 £199,039 £226,740 £237,506 £56,546 £260,494 £127,953 £73,833 £172,947
2027/28 £236,643 £174,944 £199,297 £208,740 £49,700 £229,046 £103,305 £64,266 £152,011
2028/29 £266,973 £197,366 £224,840 £235,494 £56,069 £258,402 £116,545 £73,211 £171,494 
Page 71 of 186

Page 72

Appendix 3
Your community asked, we delivered
LDP project case study: Kirkwood junior play area
The focus of this case study is the new, junior play area, designed for younger children, in Renfrew
Street in the Kirkwood area of Coatbridge. The case study sets out the background and process for
the development and the delivery of the project, which was completed in June 2024.
Background
Initial consultation work was carried out by the Kirkwood Tenants and Residents Association in 2022,
asking local residents “what does the area need”.   Following this initial piece of work the Kirkwood
Tenants and Residents Association approached the Community Partnership team for further support
and guidance. 
The local Community Partnership Officer (CPO), working with the Tenants and Residents Association
conducted a further, broader consultation exercise in late 2022. This consultation was to gauge local
support for the project and to help identify any further priorities for the local area which could be
supported through LDP. A total of 221 responses to the survey were submitted by local residents
which clearly identified the junior play area as a priority.
A location for the project was identified at Renfrew Street in Kirkshaws, the location shown in the
picture below. 
Picture 1: Site for Kirkshaws Junior Play area, Renfrew Street, Coatbridge 
Page 72 of 186

Page 73

Project Development
A project proposal was developed for the junior play area, and this was approved in February 2023,
with an indicative budget of £60,000. Work was undertaken to draft up a design brief for the new play
area. This involved the CPO undertaking further community consultation, including the local primary
school. Once the brief had been drafted this was shared with the local community through the Tenants
and Residents Association to ensure residents were kept up to date with progress.
The brief for the junior play area was included in a larger procurement exercise for a total of 14 play
areas across North Lanarkshire which was undertaken in October and November 2023. The CPO
provided regular updates toe the Tenants and Residents association regarding progress of the project
throughout the procurement process. 
A contract for the junior play area was awarded in December 2023, with an initial meeting with the
successful contractor and the LDP project team in January 2024. The team and the contractor agreed
a timescale and delivery plan, with a start date of May 2024. This time allowed for the design build and
delivery of the play equipment for the play area, which took approximately three months. It also meant
that the installation of the play area would take place in the Spring and early summer when the
weather and ground conditions would be better.
The installation of the play area was completed in June 2024, and following sign off by independent
inspectors the play area was opened to the public. The CPO also ran a design competition with local
children, to “design a sign” for the new play area, with the winning design being turned into the play
area. Some images of the new Kirkwood junior play area are included below. 
Page 73 of 186

Page 74

Images Kirkwood Junior Play area 
Page 74 of 186

Page 75

Page 75 of 186

Page 76

Page 76 of 186

Page 77

Page 77 of 186

Page 78

Branchal wood Estate, Nature Walk pathway upgrades, Wishaw
This case study presents a project from the Wishaw community board area, to renew path surfacing in
the woodland area around Coltness and  North Branchal woods.   The pathway runs through a mature,
estate woodlands, which provides a home for wildlife and a host of trees and plants.   The area provides
walking and leisure opportunities for the local community in a beautiful woodland setting.  
Background
The Branchal wood Estate Community Group, contacted the Community Partnership Officer (CPO) for
the Wishaw area in early 2023, seeking support for a project to make environmental improvements to
the natural heritage nature walk from the entrance at Lyman Drive.   The projects aim was to encourage
more people from the community to walk in the park, to be closer to the natural environment and to
support their overall health and wellbeing.   Both are Local Outcome Improvement Plan (LOIP)
priorities for the Wishaw Community Board area.   
The Branchal wood Estate community group worked with the CPO to develop an LDP funding proposal,
which was submitted in June 2023.  Working with the CPO the Branchal wood Estate group consulted
with local residents to ensure that there was strong local support for the proposal.  Local support for
the project was secured and the proposal was subsequently endorsed by the Wishaw Community
Board and approved by the Council’s Communities committee later in 2023.      
Project Development
Once approved, the project was included as one of 24 LDP surfacing projects which went to
procurement in the autumn of 2023.   The successful contractor was appointed just before Christmas
with work planned in over a six-month period starting in February 2024.   The LDP team worked closely
with the surfacing contractor to programme in project work and to ensure that projects were
completed to the required standard during the period of the contract.   
The Branchal wood project started at the end of August 2024 and completed at the end of September
2024.   The photographs that follow show the project at the “before, during and after” stage of delivery
of the project.   The photographs illustrate the considerable improvement to the pathway in Branchal
wood that has been achievable through LDP funding. 
Page 78 of 186

Page 79

LDP Project – Branchal Wood Nature Walk Pathway relay / up-grade
1. Pre-project pathway 
Page 79 of 186

Page 80

2. Midway point of project delivery showing clearance works                 
Page 80 of 186

Page 81

3. Midway point of project delivery showing Clearance works & drainage.                 
Pathway Clearance                                             Drainage clearance & up-grade 
4. Project Completion 
Page 81 of 186

Page 82

Page 82 of 186

Page 83

5. Comparison pre-Start to Completion example at the mid-way section of the pathway,
showing the bench seating area, resting point                   
Page 83 of 186

Page 84

LDP project case study: Restoration of Brain Miller Artwork at Meadowhead Underpass
Cumbernauld.
This case study details the restoration of the Brian Miller artwork at the Meadowhead underpass in
Kildrum, Cumbernauld. The case study highlights the background, development process, and
successful delivery of the project, which was completed in October 2024.
Background
The Meadowhead Underpass had been painted by artist Brian Miller in the 1960s and had significantly
deteriorated over the years which was compounded by graffiti and mould that covered over some
aspects of the painting which prompted concerns from the local community. Residents, through their
local elected member, raised the issue with the Council.
During an initial consultation, residents expressed a clear desire for the underpass to be restored,
rather than simply painted over. Over time, the mural had become an eyesore, and locals reported
feeling unsafe when using the underpass particularly at night as it was dark.
A proposal for the restoration of the underpass, under the Local Development Plan (LDP), was
submitted by the local Councillor and Kildrum Community Council on behalf of the community. In 2022,
the Community Partnership Officer (CPO) worked in collaboration with Kildrum Community Council to
carry out a broader consultation to gauge support for the project. The feedback was overwhelmingly
in favour of restoration. 
1. Underpass before Restoration 
Page 84 of 186

Page 85

Project Development
A formal project proposal for the restoration of the underpass, designated as a Heritage Project was
developed. A local artist, who had previously collaborated with Kildrum Community Council on other
community art projects, was selected to lead the work and an indicative budget of £4,980 was agreed
upon for the project.
In August 2024, the contract for the restoration work was awarded, with the artist scheduled to begin
work in September 2024. A detailed timescale and delivery plan was agreed with the artist, ensuring
minimal local disruption. The short timeline was achievable as the project was not weather-dependent,
and the artist was able to work during off-peak hours.
Completion
The work was completed on 4th October 2024, with the underpass artwork fully restored. The restored
artwork has been positively received by the community, bringing the underpass back to life and
restoring a sense of safety and pride to the area.
2. Restoration Complete 
The success of this project demonstrates the importance of community engagement and collaboration
in preserving local heritage while addressing practical community concerns. 
Page 85 of 186

Page 86

TESTIMONIES COLLECTED BY Danielle Nixon, Artist
‘Whilst painting so many people stopped to say kind words, to tell me I was doing an amazing job.  I
noted a few words in my notes as I thought it could be quite nice to document that so many people
have enjoyed Brian Miller’s works for a long time.’ (Danielle Nixon)
• ‘I remember when this was first painted in the 60’s. Brian Miller made Cumbernauld so
colourful and it’s so nice to see it coming back again’ (Local Resident)
• ‘It’s so nice to see it getting painted.  It’s really brightened the place up.’ (Local Resident)
• ‘I hope that the council get more of these painted it makes them less scary and enjoyable to
walk through.’ (Local resident)
• ‘It’s great to see the council doing something about these underpasses, they can be so scary.’
(Local resident)
• ‘I’ve been looking coming through since being a wee boy and it’s really good that this is getting
restored.’ (Local resident) 
Page 86 of 186

Page 87

Appendix 4
Play Area Development Update 2023/24
Community
Board
Project Name Project
Description
Project
Potential
Cost
Additional
external or
partner funding
available
Additional Notes
Airdrie Gartleahill play
area
Replacement
and upgrade
of existing
play area
£20,000 £80,000 Installation
completed
September 2024
Airdrie Craigneuk play
area
New play area £90,000 £0 Installation
completed
September 2024 
Airdrie Holehill/
Kenniburn
Avenue
New play area £50,000 £0 Project delayed
until 2024/25. 
Airdrie Moffat View
Play Area
Replace
existing play
area
£50,000  Installation
completed
September 2023 
Airdrie Plains Outdoor
gym
New outdoor
gym facility
£35,000 £0 Installation
completed Spring
2024.      
Bellshill Baird’s Avenue
Park 
Improving play
facilities and
equipment at
an existing
play area  
£30,000 £70,000 Installation
completed July
2024
Bellshill Rosevale
Crescent/Calder
Park MUGA
project,
Mossend 
Multi-Use
Games Area
(MUGA)
facility 
£30,000 +
additional
external
funding 
£100,000
Developer
contribution 
Installation
completed June
2024      
Coatbridge Kirkwood Junior
Play area
New play area
for younger
children
£60,000 £0 Installation
completed June
2024      
Cumbernauld Millcroft Road Upgrade Play
Area 
£80,000 Scottish
Government Play
Park renewal
fund. 
installation
completed end of
March 2024
Cumbernauld Braehead Road Upgrade Play
Area 
£50,000 Scottish
Government Play
Park renewal
fund. 
installation
completed end of
March 2024      
Page 87 of 186

Page 88

Kilsyth Bogside Park Replacement
and upgrade
of existing
play area
£15,000 £65,000 Scottish
Government Play
Area Renewal
Fund
Installation
completed August
2024      
Motherwell The Loaning
Motherwell
Improvements
to play area
£50,000 £100,000 Scottish
Government Play
Park renewal
fund
Installation
completed
September 2023
Motherwell The Roman
Road
Improvement
and renewal
of a play area
£50,000 £90,000 Scottish
Government Play
Park renewal
fund
Installation
completed June
2024      
Northern
Corridor
Moodiesburn
Kelvin Drive
Wheeled sports
facility 
Wheeled
sports facility
£20,000 £52,000
Developers
Contribution
Installation
completed Autumn
2023
Northern
Corridor
Frankfield Road
MUGA
New Multi Use
Games Area
£130,000  Installation
completed May
2024.
North
Corridor
Dunalistair Drive
Play Area 
Replacement
play area
£120,000   Installed
completed
September 2023  
North
Corridor
Lochside Play
area Gartcosh
Replacement
play area
£0 £80,000 Due to start
October 2024      
Shotts Hartwood   Funding to
support local
play area
refurbishment 
£15,000   Installed December
2023. Opened in
June 2024
Shotts Hareshaw Additional
play
equipment
£5,000  Installation
completed
September 2023      
Wishaw Overtown  Outdoor Gym  £45,000    Installation
completed in May
2024
Wishaw Lyman Drive
play area
Replacement
play area
£0 £40,000 Scottish
Government Play
area renewal
funding
Installation due in
October 2024
Wishaw Newmains  Improved play
area 
£150,000   Installation
completed
September 2023
Wishaw Cleland Public
Park 
Refurb and
extend play
area 
£50,000.00    Installation
completed October
2023
Wishaw Parkside Install new
swing bay
£5,000  Installation
completed
September 2023 
Page 88 of 186

Page 89

North Lanarkshire Council
Report
Communities Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref    SP/MC Date 28/10/24 
Community Boards and Partnership Communications Strategy 
From  Stephen Penman, Chief Officer (Strategic Communication and Engagement)  
E-mail penmanste@northland.gov.uk 
costellom@northlan.gov.uk  Telephone 07725 289559 
Executive Summary
This report provides an update on key progress linked to supporting the development of
the Community Boards model including updates on the 17th cycle of Community Board
meetings which took place throughout August/September 2024. 
• Progress with the delivery of the nine Local Outcome Improvement Plans (LOIPs) and
the implementation of an associated Monitoring and Management Framework and
Partnership delivery approach 
• Progress with the Community Board Development Programme 
• Work to commence development of a Partnership Communications Strategy
• Continued development of a Partnership Communications Strategy 
As previously agreed by committee, reports on the work of the nine Community Boards are
provided to the committee relating to each committee cycle. Progress is also reported to
the North Lanarkshire Community Planning Partnership Strategic Leadership Board to
reflect the statutory nature of the Boards in Community Planning terms in providing local
governance for the Local Outcome Improvement Plans. This report covers cycle 17
Community Board meetings. 
The process and focus of reporting on the work of the Community Boards will continue to
be reviewed and elements included within the Local Outcome Improvement Plan
monitoring and management framework. 
Recommendations
It is recommended that the Communities Committee: 
(1)  Recognises work to continue to develop and improve the integrated approach to
supporting the local Community Board model.   
Item 5
Page 89 of 186

Page 90

1. Background 
1.1 Community Matters - A Framework for Working with Communities set out the
Community Planning Partnership’s commitment to engaging with communities
underpinned by a set of principles and approaches designed to deliver on key priorities
associated with working with communities which included the creation of Community
Boards. The framework was approved by the Policy & Strategy Committee at its
meeting on 19 March 2020. 
1.2 The Community Boards are integral to supporting community participation and
providing a single coordinated approach to governance for local communities, reflecting
statutory and regulatory requirements. The Boards continue to develop in a manner
consistent with influencing and delivering the Plan for North Lanarkshire outcomes at
local level. This is being driven through the Local Outcome Improvement Plans (LOIPs)
for each of the nine areas, ensuring a partnership focus on supporting service design,
delivery and community action reflecting both the ambitions within The Plan for North
Lanarkshire and the priorities and circumstances of individual areas. The LOIPs are
published on the North Lanarkshire Council website and were circulated to all
Community Boards.   
1.3 The monitoring and management framework for the delivery of the LOIPs is in place
and operational along with supporting partnership delivery approach through the
establishment of Local Partnership Teams. This is being used to inform reporting to
Committee, the North Lanarkshire Partnership (NLP) Strategic Leadership Board and
individual Community Boards.  A separate LOIP update is provided to the Communities
Committee and the NLP Strategic Leadership Board on a 6 monthly basis providing a
snapshot of highlights and future priorities for each of the board areas and a detailed
progress report is submitted to each of the 9 Community Boards annually. 
1.4 The seventeenth cycle of Board meetings has now taken place, and an example of an
agenda is included in Appendix 1. 
Table 1 – Cycle 17 Community Board Meetings 
The Plan for North Lanarkshire
Priority  Enhance participation, capacity, and empowerment across our
communities
Ambition statement (20) Improve the involvement of communities in the decisions, and
development of services and supports, that affect them
Programme of Work All Programmes of Work
Area Meeting Date & Time Location
Shotts 21/05/2024 at 6:30pm Shotts Community Centre
Northern Corridor 22/05/2024 at 7:00pm Chryston Parish Church
Coatbridge 23/05/2024 at 6:30pm Coatbridge Community Centre
Cumbernauld 28/05/2024 at 6:30pm Pollock Hall, Condorrat
Kilsyth & Villages 29/05/2024 at 6:30pm St. Patrick’s Primary School
Wishaw 30/05/2024 at 6:30pm Cleland Community Centre
Airdrie 05/06/2024 at 6:30pm Cairnlea Church, Airdrie
Bellshill 06/06/2024 at 6:30pm Tannochside Primary School
Page 90 of 186

Page 91

2. Report 
Community Boards – Cycle 17 
Representation at Community Board Meetings 
2.1 At the 17th cycle of Community Board meetings, attendance reflected a good mixture
of partners, elected members, community groups and local people at all Board
meetings.  Approximately 245 people attended this cycle of meetings which was an
increase on the previous cycle of meetings with 64 community organisations and 89
community representatives in attendance. In addition, 37 individual local people
attended meetings which was a slight increase from the previous cycle of Board
meetings. 
2.2 A broader range of community representation is generally in evidence at Community
Board meetings. 9 new organisations attended Community Boards in Cycle 17. 
2.3 The categories of participants in Cycle 17 Community Boards are as set out in Table 2
below: 
Table 2 - Participants (Cycle 17) 
Participants at Community Boards (Cycle 17)
Community Councils  Tenants and Residents Associations 
Historical/Cultural Groups  Community Forums 
MSYP/Youth Fora Police Scotland 
Scottish Fire & Rescue  NHS Lanarkshire 
Voluntary Action North Lanarkshire  NL Disability Access Panel
Elected Members  Council Officers
Faith Groups  Parent Councils 
Local people/residents  Voice of Experience Forum 
Community Organisations  African Collaborative 
Participation in meetings 
2.4 Work is continuing by all Community Planning Partners to encourage wider
representation at Community Board meetings.  Meeting information is circulated across
social media channels including NLC website and My Town pages four weeks in
advance of each meeting with additional promotion scheduled 1 week in advance and
on the day of the Board Meeting.   Posters are also circulated to approximately 1300
Community Board members and local groups and organisations for wider local
Motherwell 11/06/2023 at 6:30pm Dalziel St Andrew’s Parish Church
Page 91 of 186

Page 92

circulation; to Community Councils and Tenants and Residents Associations and wider
networks to raise awareness about Community Board meetings.  All Community
Planning Partners, Elected Members, and Board members have responsibility for
encouraging wider participation at Board meetings and for using information from wider
engagement activity through LOIP subgroups and community networks to represent
the views of the wider community as appropriate. 
2.5 There was an increase in participation at this cycle of Board meetings overall in
comparison to the previous cycle in February/March 2024.  There was a marked
increase in the number of Community Groups represented for example, in the number
of Parent Council’s, Tenants and Residents associations, Community Council’s
represented. 
Agenda items 
2.6 During Cycle 17, seven out of nine Community Boards had agenda items put forward
by community groups and organisations in advance of Board meetings.  Examples of
Agenda items put forward included: Pivot Centre, Community Forum Evidence Report
in the Northern Corridor, Flood Prevention and Town Action Plan in Kilsyth; School
transport follow up in Cumbernauld; Citizen’s Advice Bureau (CAB) presentation in
Airdrie, Parking issues in Wishaw; Vandalism and Recycling Centre Access in Shotts
and School Transport in Motherwell. 
2.7 In addition to the agenda items above, local community groups provided updates at
some Boards including Pet Pantry and Cornerstone House at Cumbernauld Board,
Moodiesburn Community Action Group in Northern Corridor Board, Kirkwood Tenants
and Residents at Coatbridge Board and Hartwood Community Development Group in
Shotts. 
2.8 Council officers were also asked to attend or provide updates to Board meetings in
response to agenda items and issues raised by community representatives. Council
and Community Planning Partnership Partners will continue to be invited to attend in
relation to specific agenda items raised. External organisations are also invited to
attend Board meetings in response to agenda items raised by communities as
required. For example, in this cycle, the Team Leader for Water Management was
asked to attend the Kilsyth Community Board and NLC Greenspace and Country Parks
Manager was asked to attend Northern Corridor Community Board. 
Opportunities to provide updates and share views 
2.9 As previously reported, all nine Community Boards endorsed Local Outcome
Improvement Plans (LOIPs) which have been published and can be accessed via this
link. Community Board agendas are now organised around LOIP priorities and updates
from communities and partner agencies are linked to priorities where possible to ensure
clear focus on progress towards achieving actions to address the key priorities that
were identified by local communities.  Local people can also raise ad hoc issues or
share local information through the Community Matters section of the agenda. 
2.10 Positive progress continues to be made with subgroups meeting to progress agreed
actions to address local priorities where this is the most appropriate mechanism.  Work
is ongoing and meetings are taking place and scheduled with local community groups
and organisations to further develop subgroups. 
2.11 Community Board Self Evaluation Workshops were carried out across 9 Community
Boards throughout August and September 2024.  Community Board Chairs were
Page 92 of 186

Page 93

invited to participate in a working group to discuss the findings of the Self Evaluation
that was previously carried out. The purpose of these workshops was to enable
Community Board members to discuss these findings and agree proposals for
improvements moving forward. 
Special Board Meetings 
2.12 No special Board Meetings were requested at this round of Community Boards. 
Community Board Local Development Programme (LDP) Projects 
2.13 As previously reported, community organisations requested a positional statement
regarding outstanding Local Development Programme projects.  The LDP report,
continues to be split by Community Board area, and detailing the status of projects,
was circulated in advance of Cycle 17 Board Meetings. The project proposal form
identified in previous reports to committee, continues to be utilised to record LDP
project ideas and suggestions put forward from local communities. LDP continues to
be a set item on the agenda at all Community Board meetings and is subject to a
separate report to this committee.   
Involving Communities 
2.14 Cycle 17 meetings saw continued involvement of seldom heard voices in Community
Board meetings. The Community Partnership team will continue as a priority to
proactively work with local community groups and people with lived experience to
support this objective. 
2.15 Work is ongoing with youth groups to encourage them to provide a presentation/ update
to Community Boards in Community Board areas.  At this cycle of meetings, two
MSYPs attended both Northern Corridor and Coatbridge Community Boards to provide
an update on their role and involvement in youth engagement activity. Further
information will be provided in due course. 
Our Lives – An exploration of the lived experiences of North Lanarkshire’s 
2.16 Black, Asian, and other Minority Ethnic People
Community Planning Partner organisations continue to progress the work associated
with the recommendations set out in the Our Lives Research with Lead Officers coming
together to develop an action plan. 
2.17 The findings of the work that was undertaken by the Community Partnership Team and 
the Council’s Equality Team to understand the make-up of the community 
representatives of the Community Boards and how representative they are of the local 
population was fed back to Community Boards at this cycle of Board meetings. 
Moving Forward 
2.18 Community Board Chairs
In cycle 17, 8 out of 9 Community Board meetings were chaired by Community
representatives with Motherwell Board being chaired by a local elected member. 
Page 93 of 186

Page 94

Community Board Development Programme 
2.19 Community Board Members have finally been removed from the NLC employee 
mandatory e-learning list and will no longer receive enrolment or reminder emails to 
complete the e-learning. We now have two hubs - one for Community Board Members 
only, where a specific setting has been added to the audience set up removing them 
from the mandatory e-learning. The second hub is an exact replica which is for NLC 
staff and Elected Members where the audience settings still assign members the 
mandatory e-learning. 
2.20 An activity report run on the 11 September 2024 identifies we have 129 members with 
login details. 70 have logged in and accessed different areas of the hub with the latest 
activity being the 10th September 2024. 
2.21 Following a meeting that took place on the 16th July 2024, the possibility of having a 
PageTiger interaction digital document relating to induction topics on the hub. The 
PageTiger document will have direct links to topics areas within the hub for ease of 
access. Although this was discussed, further meetings will need to take place to identify 
the exact content of the PageTiger document.
The Role of Chief Officers as Community Coordinators 
2.22 As previously reported, Community Coordinators are in place and attending their 
designated Community Board Meetings.  Community Coordinator updates continue to 
be a standing item on all Community Board agendas as well as participation in 
discussion relating to a range of local matters. Community Coordinators meet with key 
senior partners between Board cycles to discuss common matters, any leadership 
action required, and to collectively consider input to future meetings. 
Future Board Meetings 
2.23 The next cycle of Community Board meetings will be held in November/December 
2024. Following consultation with community group representatives and elected 
members who attend Community Boards, it was identified that most Boards preferred 
a mix of online and face-to-face meetings moving forward and during Cycle 17, all 
Board meetings took place face-to-face in Community Facilities. 
Cycle 18 meeting dates are set out in Table 3 below. 
Table 3 – Community Board Meeting Dates (Cycle 18) 
Community Board  Day Date
Shotts Tuesday 19/11/2024
Northern Corridor Wednesday 20/11/2024
Coatbridge Thursday 21/11/2024
Cumbernauld Tuesday 26/11/2024
Kilsyth & Villages Wednesday 27/11/2024
Wishaw Thursday 28/11/2024
Airdrie Wednesday 04/12/2024
Bellshill Thursday 05/12/2024
Motherwell Tuesday 10/12/2024 
Local Outcome Improvement Plans – Partnership Delivery, Monitoring, and
Management Framework 
Page 94 of 186

Page 95

2.24 As previously reported, the online LOIP monitoring, and evaluation framework is in 
place. This management tool is being used by community planning partners to ensure 
that progress towards addressing key priorities that were agreed with local 
communities is monitored, recorded, and reported.   
3. Measures of success 
3.1 Delivery of LOIP outcomes and increased levels of engagement with local communities
and partners, resulting in generally positive impacts on communities across a variety
of priorities and key issues identified through effective locality planning and the
implementation of the Community Boards, particularly in areas where further
consultation has been required.         
4. Supporting documentation 
4.1 Appendix 1 – Example of Cycle 17 Community Board Agenda. 
Stephen Penman
Chief Officer (Strategic Communication and Engagement) 
Page 95 of 186

Page 96

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public Sector
Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Page 96 of 186

Page 97

Where the impact identifies a requirement for significant technology change, has an
assessment been carried out (or is scheduled to be carried out) by the Enterprise
Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The report makes reference to communication activities in relation to community
engagement and promotion of the community boards.
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has been
made to ensure there has been appropriate consideration of the relevant Articles
from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☐ 
Page 97 of 186

Page 98

Appendix 1
Community Board Agenda (Cycle 17)     
AGENDA (example)  
1. Welcome and Introduction: 
• CPT to record the minutes of Board meetings. 
2. Apologies 
3. Minute of previous meeting and matters arising 
4. Local priorities Local Outcome Improvement Plan (LOIP) updates: 
• Local priorities for each Community Board Area
• Local partner updates from Police Scotland and Scottish Fire & Rescue
Service, NHSL, VANL related to LOIP priorities.   
5. Cervical Screening Presentation (NHS Lanarkshire) 
6. Community Matters 
7. Local engagement/investment   
• Local engagement/consultation 
• Funding opportunities 
8. Standing agenda items 
• Community Coordinator update 
• Local Development Programme (LDP) update 
9. AOCB 
10. Date and time of next meeting. 
Page 98 of 186

Page 99

North Lanarkshire Council Report
Communities Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref    SP/LP Date 28/10/24 
Access to Free Period Products (Period Dignity Initiative) –
Annual Update 
From  Stephen Penman, Chief Officer (Strategic Communication & Engagement) 
E-mail penmanste@northlan.gov.uk
pollockle@northlan.gov.uk Telephone 07947 997750 
Executive Summary
This report provides an update on the activity relating to the delivery and further
development of the Access to Free Period Product / Period Dignity initiative.
Members will be aware that since August 2018 all local authorities in Scotland were
provided with funding to introduce access to free period products in schools. 
From January 2019 the Scottish Government provided additional funding to all local
authorities to increase the number and range of places where period products are available
free of charge to those who need them, with a focus on publicly accessible buildings.
The purpose of the funding for schools remains to support equality, dignity and rights for
those who menstruate and to ensure that lack of access to products does not impact on an
individual’s ability to fully participate in education, at all levels. 
The main intent of the wider roll out for community provision remains tackling poverty but
also wider need and to address the overarching gender equality and dignity issues that
affect all of those who menstruate regardless of income. Currently, spending is split
between school and community provision. This approach has been designed to reflect the
needs of communities across the council area.
The Period Products (Free Provision) (Scotland) Act 2021 received Royal Assent on 12th
January 2021, became legislation on the 15th of August 2022 and fully into force in January
2023. 
This important work will continue to be informed by the findings from online consultation with
residents. 
Recommendations
It is recommended that the Community Committee –  
(1) Acknowledge the significant work carried out to date across key council services and
partner agencies 
(2) Endorse the planned developments for delivery of the project outlined in this report
dependent on funding availability. 
Item 6
Page 99 of 186

Page 100

1. Background 
1.1 From August 2018, all local authorities in Scotland were allocated funding to provide
access to free sanitary products in schools. The Scottish Government made a new
commitment in the 2018 funding year to expand this provision beyond schools. In
November 2018 COSLA Leaders agreed to this proposal and developed ‘Guiding
Principles’ in partnership with Scottish Government. Since then, North Lanarkshire
Council has been allocated a share of funding annually to further develop the initiative. 
1.2 The focus for this initiative is creating access to free period products, and by doing so
tackling the impact of poverty or low income, which can often mean people are unable to
afford the essential products needed while menstruating. 
By ensuring access to free products, many local people have some relief from the high
costs of purchasing period products and the potential stigma of not
being able to afford them. 
1.3 Annual funding from the Scottish Government has enabled the council to continue to
develop the network of public building access points, to work with local community
partners to target support across priority communities and to develop a campaign to raise
awareness of the offer available and encourage a more open dialogue around periods
and period products. 
1.4 The council has undertaken a community consultation to find out residents’ views on the
current offer, improvement ideas, and early experiences of the initiative. The findings from
the consultation, along with feedback from other stakeholders, will be used to lead the
‘Statement of Intent’, which the council is required to publish and submit to Scottish
Government to confirm the council’s commitment to supporting the new law and the
continued wider access to products 
2. Report 
2.1 The main objective for this initiative is to create access points where residents can access
a range of free period products and in doing so support people experiencing poverty.
Consistent with the Plan for North Lanarkshire, the North Lanarkshire model has been
developed with community planning partners to ensure wide reach and accessibility from
public buildings and facilities, as well as distribution by local anchor organisations. 
2.2 The approach reflects the principles of: 
• Protecting people’s dignity, avoiding anxiety, embarrassment and stigma.
• Making a range of products visible in places that people use.
• Reflecting community views and needs.
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement (20) Improve the involvement of communities in the decisions, and
development of services and supports, that affect them
Programme of Work All Programmes of Work
Page 100 of 186

Page 101

• An efficient and effective approach that demonstrates value for money.
• Individuals being able to get sufficient products to meet their needs.
• Gender equality ensuring anyone who menstruates can access products including
transgender men/nonbinary individuals and that language is gender inclusive.
• Awareness raising and education to both promote the ‘offer’ and attempt to change cultural
norms. 
North Lanarkshire Council Funding Allocation (2023-24) 
2.3 Table 1 
Financial Year  Amount of Funding 
2023-24 £336,000 
Key highlights from 2023/24 
2.4 The number of period products distributed from 1 April 2023 to 31 March 2024 numbers of
period products distributed via schools, public buildings or community anchor organisations is
as follows: 
• Single-use period products – (includes all single use sanitary products e.g., towels, tampons,
liners): North Lanarkshire Total – 876,919 this has is an increase from the previous year
(686,592). 
• Number of Period Products distributed through public buildings or community anchor
organisations – 731,008 this is an increase from the previous year (608,196). 
• Number of Period Products distributed through schools – 145,327 this is an increase from the
previous year (78,390). 
2.5 From January 2024 the Education Establishment element of the period dignity project was
transferred to the Community Partnership Team, This was to mainstream the project by having
one overall lead, to dictate time and resources to develop the approach to delivery of the
project with Educations Establishments and to build stronger links between the Education
Establishment and local community venues to provide a better overall offering to the local
community, young people and their families. 
2.6 The introduction of a new online order form was introduced to make ordering products easier
and more accessible for community and education establishments. This process was also
developed to provide the Community Partnership Team with a better mechanism for tracking
stock and reporting data on the project.   
Community Projects 
2.7 Throughout the reporting period the council continued to work in partnership with nine
community anchor organisations to ensure effective targeting of support to priority
communities within their area and to support individuals who are unable to attend local access
points due to personal circumstances including. This is an increase from eight organisations
in 2022-23. 
• Mobility and health.
• Being unable to afford the cost of public transport.
• Distance from home to the nearest access point for example living further than 20- minute
return journey, which will be more likely for those living in rural communities. 
Page 101 of 186

Page 102

2.8 The 9 organisations included 
1. Getting Better Together - Shotts
2. Newmains Community Trust - Wishaw
3. Glenboig Development Trust – Northen Corridor
4. Cornerstone House – Cumbernauld
5. Kirkshaws Neighbourhood Trust - Coatbridge
6. Diamonds in the Community - Airdrie
7. Jervistion Community Centre – African Collaboration Group - Motherwell
8. Lanarkshire Community Food and Health Partnership – North Lanarkshire Wide
9. VIP Arts & Sports Academy – Bellshill 
2.9 Additional information is contained within Appendix 1. 
2.10 Over and above delivering against the main objectives for the Period Dignity Initiative, all the
organisations involved are committed to taking a sustainable approach to the project delivery. 
2.11 Most of the projects have an environmental focus and are delivered by local volunteers using
bicycles and e-bikes to reduce the carbon footprint of the projects. Each organisation also acts
as a champion for the promotion of the use of sustainable environmentally friendly products. 
2.12 Each organisation has also been provided with a new information pop-up with QR codes that
link to the NLC interactive pick-up location app. 
Communication and awareness raising: 
2.13 Work continues to raise awareness raising with dedicated marketing materials in a bid to
promote and increase knowledge of the initiative to community residents and all Education
Establishments. 
2.14 Activities within the campaign include. 
• Posters and leaflets in all public buildings and facilities
• Promotions at local events
• Period products pick up location QR code, highlighting all accessible venues across North
Lanarkshire 
2.15 In October 23 a new marking campaign was launched to raise awareness of free period
products across North Lanarkshire. This involved the use of North Lanarkshire Councils online
and social media networks. 
2.16 A suite of five different adverts versions were created, each promoting a different type of period
product available for free, and one with all the products. The adverts demonstrated where to
collect products with the primary messaging clearly stating that they are free for anyone who
needs them. 
2.17 The adverts were promoted across North Lanarkshire via outdoor advertising for example 
• bus adverts
• static and digital billboards
• posters and flyers
Page 102 of 186

Page 103

• plasma screens in leisure centres, cultural venues, schools, community centres and GP
surgeries
• provision of bespoke pull up banners for the 9 community anchor organisations, online
through an animated advert using Snapchat, Instagram, Facebook, Google and YouTube.
• News articles also appeared in local press and an article in the council’s tenant’s
newsletter to reach 36k North Lanarkshire tenants. 
2.18 A QR code was used on all offline materials, linking through to the map to “find free period
products near you”. 
2.19 Since the campaign launched, the website has been viewed 48k times and the pick-up point
map has been viewed 63k times. The online advert/animation has been viewed 87k times. 
2.20 When polled, 62% of respondents said they knew where to collect free period products from
(primary aim) 90% of people said that they felt that seeing the adverts made talking about
period products easier and more acceptable (secondary aim). 
2.21 Appendix 2 provides examples of some of the campaign materials. This marketing and
advertising has resulted in a greater awareness of free period products to the residents of
North Lanarkshire. 
NLC Interactive Map 
2.22 The NLC interactive map continues to be updated on a weekly basis making sure it is fully to
date to allow residents access the latest comprehensive list of local access points. North
Lanarkshire now has over 100 access points ensuring wide reach and accessibility to the
people of North Lanarkshire. This map was viewed over 63,000 times during this period. 
Partnership Working 
2.23 Partnership working continues to be an important factor throughout this initiative. Liaising with
community facilities, library service, Active and Creative Communities, Voluntary Action North
Lanarkshire, NHS Lanarkshire, and local community delivery partners have ensured that a
coordinated approach to development, delivery and logistical processes have been
established. 
2.24 Greater links have also been established with Early Years nurseries and family learning
centres to promote awareness of the offer. 
2.25 We continue to have partnership meetings and professional dialogue has taken place to assist
in helping to monitor and review activity and identifying and considering options to improve
Page 103 of 186

Page 104

and develop the service whilst providing updates on any of the project delivery that individual
agencies may be leading on. 
Statement of Exercise of Functions 
2.26 As part of The Period Products (Free Provision) (Scotland) Act 2021 local authorities are
required to produce and communicate a Statement on the Exercise of Functions to summarise
the arrangements in place to meet the legal duties, which includes carrying out one or more
public consultations. 
2.27 The information gained from the public consultation work carried out in March to July 2022 has
been used to create the North Lanarkshire Council Statement of Exercise of Functions. The
statement is contained within Appendix 3 and sets out North Lanarkshire Council’s commitment
to free product provision including provision in education establishments and the wider
community. 
Education Establishments Consultation 
2.28 In February 2024 consultation surveys were issued to all education establishments and school
parent councils. The survey was designed to capture the views of the schools with a particular
focus on how the project is delivered within each establishment. This is so that enhancements
can be made to make products more accessible for pupils within schools without facing stigma.
Results of each survey can be found in Appendix 4. 
2.29 The school consultation covered the following broad themes: 
• Where pupils can pick up products?
• What type of products do you have available?
• How do you promote access and pupils know where to pick up free period products?
• Do pupils find it easy without stigma to pick up products within the school without stigma? 
2.30 The parent council consultation covered the following broad themes: 
• Are you aware if your school currently has stock of free period products and promotes
awareness of where to pick up free products?
• Does the parent council help to promote free period products and where to pick up within
school or your community?
• Do pupils find it easy to pick up products within the school without stigma? 
2.31 The survey was completed by 84 headteachers and 49 parent councils. 
Delivery Priorities for the 2024/25 Period 
2.32 Using intelligence from previous consultation work as well as other feedback from schools,
partners and stakeholders, several key developments are currently underway. These actions
will assist with a further targeted expansion and the implementation of improvements aimed
to improve the processes, services delivery and the overall experience of the residents of
North Lanarkshire. 
1. Recruitment for a project officer (due to take up post early October 2024) with a focus on
promoting and providing access for young people within education establishments and
within the wider community. The focus for this role will be looking at different options for
increasing uptake within this demographic and piloting various projects to remove barriers
Page 104 of 186

Page 105

for different  groups to see what works best with an emphasis on school/pupil involvement
to design the approach. 
2. Continuation of gap analysis and mapping on a year-to-year basis to identify new access
sites within each locality. The principal of the 20-minute neighbourhood is being used for
this, this is with the aim to have access points for residents within a short walk or cycle
lasting no longer than 20 minutes for the journey. 
3. Review of existing access points to reduce clustering of sites. To reduce unnecessary
duplication or grouping of access points in the location of nearby public buildings. The better
used site, with longer opening hours will be preferred. However, where there is a
demonstrated need for multiple sites within an area, this can be retained. 
4. An evaluation of the current anchor organisation provision partnership to review if the model
is working in the locations identified and if improvements or a shift in focus is required. 
5. Look to develop a peer- led youth project to deliver period dignity workshops and information
sessions within schools and local youth groups. 
6. Improve data collection and analysis tools to better inform future developments and
improvements. This will help identify the current locations being used and what areas need
more targeted development work and support. 
7. Undertake a further community consultation online questionnaire. This is to capture the
views of the public with a particular focus on views from those currently using sanitary
products, those who will use sanitary products in the future and those who may collect
sanitary products on behalf of others. 
8. Consider options to improve the accessibility of products for residents over the weekend,
public holidays, and extended school holiday period when schools and public buildings may
be closed. 
9. Continue to review the set-up of access points to ensure products can be easily accessed
preferably by self-selection or other formats that are viewed as less embarrassing for
residents. 
10. Continue to develop a community resilience/contingency plan to deal with any event of
future civil incident of national emergency. 
Further information 
2.33 Additional information, including the information pages on the NLC website, the NLC
interactive mapping tool and the My Period App can be accessed using the links below: 
• North Lanarkshire interactive map 
• North Lanarkshire Council website – Free Period Products Scottish Government ‘Pick up
my period’ app enables someone to put in a town, city or post code and find out where to
accessproducts. 
• https://apps.apple.com/gb/app/pickupmyperiod/id1500403938https://play.google.com/sto
re/apps/details?id=com.myperiodapp 
3. Measures of success 
3.1    Number of products distributed.
3.2    Number of individuals accessing free products
Page 105 of 186

Page 106

3.3 Number of community organisations partnerships
3.4 Number of distribution points across North Lanarkshire       
4. Supporting documentation 
4.1 Appendix 1 - Details of community anchor organisations supporting the initiative
4.2 Appendix 2 - Example campaign materials
4.3 Appendix 3 - Statement of Exercise of Function
4.4 Appendix 4 - Details of School and Parent Council Survey’s 
Stephen Penman 
Chief Officer (Strategic Communication & Development) 
Page 106 of 186

Page 107

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
An integrated equality impact / Fairer Scotland assessment has been completed
during the initial planning of the delivery approach. This will be further informed by
our ongoing monitoring, reviews and public consultations and community
engagement activity. 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The period dignity / access to free period products is expected to cost the council
circa £336,000 to operate. This is for both existing operations and new
developments. However, funding for the initiative has to date been provided
through an additional grant from the Scottish Government. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
Page 107 of 186

Page 108

5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Wider use of environmentally friendly products and delivery products is
encouraged. This includes looking at testing approaches to increasing access to
environmentally friendly products and piloting low carbon delivery mechanisms with
local voluntary organisations. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
A communication campaign is outlined in this report 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
Page 108 of 186

Page 109

5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☐ 
Page 109 of 186

Page 110

Details of Community Anchor Organisations Supporting the Initiative                                                    Appendix 1 
Community Projects Location Description
Glenboig Development Trust
Period Dignity Project
Glenboig The programme aims to promote access to period products, promote
environmentally friendly period products and ensure dignity to
menstruating persons living in Glenboig and surrounding areas whilst
respectful of our carbon footprint and the local environment.
Improving on last year they added another electric vehicle to their fleet an
E-Moped which allows for distribution to a further reach within the
community compared to E-Cycles. Worked in tandem with partner
agencies and use of social media to spread awareness of the Period
Dignity Campaign. Training of 3 volunteers to support the campaign with
continued focus on dignity putting in place various methods to procure
products from discreet on site pick up to delivery through request from
various sources such as email, text and social media.
Kirkshaws Neighbourhood Trust
NLC Period Dignity Project
(Coatbridge)
Coatbridge Products provided by North Lanarkshire Council will be distributed freely
and delivered to local women, girls, groups and organisations by
Kirkshaws Neighbourhood Centre on Electric Bike (to reduce carbon and
supporting North Lanarkshire Council to achieve #Act2021). We will
encourage women and girls to consider the more sustainable
environmental products such as Hey Girls environmentally friendly
products by providing information and opportunities for them to try these
products, which for many would be unaffordable.
Having purchased E-Bikes this has seen the project be environmentally
friendly, along with the training of more volunteers there has been more
awareness spread for the campaign and helping to reduce stigma around
period health as a talking point. Continual strengthening of links with other
organisations is helping in delivery of information and sanitary products.
Page 110 of 186

Page 111

Newmains Community Trust 
Flo & Go Dignity in Menstruation Project
Newmains Newmains Community Trust will undertake a Period Product Delivery
Scheme within Newmains and Surrounding Areas. The scheme will
involve a team of trained volunteers taking orders and delivering re-usable
and environmentally friendly Period Products to those who need it in the
community. It is the aim of this project to ensure that access to Period
Products does not become another source of deprivation to those living in
Newmains and that anyone who needs them, can access them in person
or through the delivery scheme.
Improving on last year the volunteers have been successful in delivering
sanitary products to the community with hopes on expanding the reach
across Newmains further. There is a focus on delivering more reusable
products as they are in demand in the area, this will have a positive impact
on the environment, coupled with the use of E-Bikes. Further promotion of
the campaign has also been achieved through various events and working
in tandem with partner agencies.
Getting Better Together - Healthy Living
Centre
The Cycle
Shotts Develop a delivery service by training staff and volunteers to use Electric
Bikes to transport orders of Hey Girls environmentally friendly and lifestyle
products to people in rural communities. This links in with the council
commitment to ACT2021- Action on Climate Together 2021.
Following the successful implementation of E-Bikes as well as an E-Van a
delivery system has been established in the area. This helps get sanitary
products out to households within the remote regions near Shotts as well
as those who have trouble accessing drop off points. Increased work to
promote the period dignity project as well as how to access the delivery
service, along with an increase in attendance of events to further
collaborative work and promotion. Aims to increase the reach and scale of
those delivered to within the community in the future upon what is already
established maintaining healthy growth.
Cornerstone House Centre
Period Products Project
Cumbernauld Promotion of the ‘pickup point’ using Cornerstone House Centre’s
marketing materials and social platforms, website and in-house
information points. Cornerstone House Centre will raise awareness of the
‘app’ ‘Pickup My Period’ which allows users to identify locations across
Scotland where Free Period Products will be available. Developed by Hey
Girls and funded by the Scottish Government through their education arm
Page 111 of 186

Page 112

‘My Period’. Hey Girls products are all sustainably sourced, reusable and
plastic free. Inform local partners and key organisations of the service
being provided at Cornerstone House Centre within the Health &
Wellbeing focus already in place. 
Ensure ‘anyone who needs them’ has access to different types of Period
Products ‘reasonably easily’ and with ‘reasonably dignity’. Provide
environmentally suitable products provided by an authorised provider.
Support other areas, identified if relevant by users of the service as
financial or other issues may need support/help.
Lanarkshire Community Food and Health
Partnership
NLC Period Dignity Project
Coatbridge
(Bargeddie)
Proposal to help provide all participants in our food classes - for
themselves and their suitable family members – with free sanitary
products. We also aim to supply all eligible community members who
receive food parcels with the necessary sanitary products of their need.
LCFHP also provide various foodbanks or community groups with a
supply of sanitary products as and when they require.
Jerviston Community Centre – African
Collaborative Group
Period Dignity Project
Motherwell The African Collaborative group helped to operate a food bank in the
Motherwell region, now looking to expand providing free sanitary products
across the region as well. With aims of procuring E-Bikes and establishing
a delivery service for those who can’t attend the access point due to
disability and other issues faced. Including a delivery service and acting as
a pick up point there will be a focus on building further relationships within
the community to break down stigma around period discussion and
continued work to promote the service/project.
Diamonds in the Community
Period Dignity Project
Airdrie Diamonds in the Community proposed to become an anchor organisation
helping to support the period dignity campaign within the Airdrie region.
Aims of the organisation are to promote and support NLC’s delivery of the
period dignity campaign, promotion of the pick up My Period App,
promotion of the campaign. Collaborative efforts within the community to
raise awareness and combat stigma around periods and period health
promoting healthy discussion and inclusion. Collection of data and feeding
back key elements to NLC.
Page 112 of 186

Page 113

VIP Arts & Sports Academy Bellshill The project will support the council to continue to supply free sanitary
products by advising all participants within the VIP programs and our
wider community of our commitment and dedication to helping with this
free program, leaflets will be distributed and a designated area and
worker within the Centre will be provided, so that people do not feel
uncomfortable when accessing products.
We will also let partners from our network know we are the Centre for
this area, promoting on all our advertising and community window and
social media forums.
Page 113 of 186

Page 114

Appendix 2
Example Campaign Materials 
• Billboard Adverts/Rear Bus Adverts/Railway Station Adverts/Plasma Screen Adverts/Pull up Banners/Posters/Flyers 
Page 114 of 186

Page 115

Page 115 of 186

Page 116

Digital Billboard – Plasma Screen Adverts – Bus Shelter Adverts   
Page 116 of 186

Page 117

Events 2023-24 
The Community Partnership Team
attend various events across Noth
Lanarkshire to spread the awareness
surrounding the Period Dignity
Campaign. As seen in the images
provided there was a pop-up banner
display created that established the
goal of making members of the public
aware of free period products in their
area. It served as a good platform to
have discussions with members of the
community, spread awareness, discuss
the products we have to offer both
single and reusable including my first
period kit’s and the pad for dad’s kit’s.
We were also able to have a positive
impact in diverting people to make use
of the NLC Directory Map showcasing
all our pickup points across the NLC
Vicinity. Not only that but we have had
positive engagement with community
members since this took place with
many querying for more information.
Showing a great uptake in community
interest.
Page 117 of 186

Page 118

QR Code 
Going forward we are looking to make the following
QR code uniform across all our promotional material
as it directly leads to the North Lanarkshire Council’s
website in particular the NLC Directory Map. This is
where members of the public can access a map that
lists all the period pick up points across the NLC
Region. It is easily accessible for all those who have a
smartphone as it can quickly be scanned through
their camera and have them on the website in a
matter of seconds providing valuable information to
those who need it.
Page 118 of 186

Page 119

Appendix 3
North Lanarkshire Council
Period Products (Free Provision) Scotland Act 2021
Statement on Exercise of Functions 
1.     Introduction
The Period Products (Free Provision) (Scotland) Act 2021 was passed by the Scottish
Parliament on 24th November 2020 and gained royal assent on 12th January 2021. The Act
requires local authorities as a responsible body to provide period products free of charge to
anyone who needs them, by making products reasonably easy to obtain.
Additionally, as a responsible body – this should be done mindful of respecting
dignity and by offering a reasonable choice of types of period products.
Local Authorities are required to produce a Statement on Exercise of Functions to summarise
the arrangements that will be put in place to meet the duty, which includes carrying out one
or more public consultations.
This statement has been produced in accordance with our statutory duties and outlines
North Lanarkshire Council’s commitment to free product provision and details current and
future provision within education establishments and the wider community.
5. Our commitment
North Lanarkshire Council is committed to providing free period products for those who need
them. Our approach involves children and young people having access to products within
their school setting and for residents and visitors through a network of local access points
within public buildings and community facilities within North Lanarkshire.
Individuals unable to attend a local access point can contact the council so that alternative
arrangements can made, which may include postal deliver or deliver by our local community
partner organisations. Funding has been made available by the Scottish government to
enable this.
In providing this free service, it is our aim to ensure that:
• A range of period products, including single use items and re-usable environmentally
friendly products are available to those who need them via all secondary schools and a
network of local access points.
• Our local access network is kept under review and developed further where appropriate. It
is our commitment to do this in conjunction with community planning partners and third
sector organisations, mindful of geographically gaps in provision and also of the 20-
minute neighbourhood model.
• Barriers to access are minimised and removed and that people can access
products with dignity and without stigma.
• Consideration is given to additional support for those who may require it.
• Product demand is regularly monitored so that public buildings and community
facilities do not run out of stock.
• Residents and visitors are aware of our free provision. This will involve a range of
advertising and promotional campaigns. Information will also be available on the council
website; through social media platforms and through other communications such as
posters and informational flyers.
• Regular feedback is sought from service users so that improvements can be identified.
Page 119 of 186

Page 120

• Public consultations and community engagement is carried out to inform our provision 
6. Public Consultation
The North Lanarkshire public consultation took the form of an online
questionnaire. This was launched in March 2022 and ran until the end of July
2022.
The survey was designed to capture the views of the general public with a
particular focus on views from those currently using sanitary products; those
who will use sanitary products in the future and those who may collect sanitary
products on behalf of others.
The consultation covered the following broad themes:
a. General awareness of the availability of free period products and advertising
campaigns
b. Types of products currently used and views on accessing environmentally friendly
products
c. Locations of access points used and suggestions for new sites
d. Availability of products and views on service received at access points 
The survey was completed by 288 people and the findings from the consultation will
be used to inform the provision within North Lanarkshire.
Full details of the findings are contained within the 2022 update report which can be
accessed on our website.
7. Community Based Provision
North Lanarkshire Council has developed a large network of community access points.
The access points are in all 9 towns and many local communities within public buildings,
and community facilities. To date we have over 100 local access points throughout North
Lanarkshire which we will continue to monitor, review, grow and update accordingly. The
access points have been established in public buildings and community facilities.
North Lanarkshire Council have also partnered with eight local community anchor
organisations who will provide local services within a cluster of priority communities.
This also includes a fast free local delivery service for those who cannot attend our centres
and access to environmentally friendly period products.
Local food banks and organisations providing emergency food aid are also part of
our network and on request can provide products to vulnerable individuals and
families.
Additionally, residents can contact the council directly by email to request
products. In doing so the quickest method of delivery will be selected.
Products available within our community access points include single use pads (with
and without wings, regular, super and long) and tampons (regular and super) the various
Page 120 of 186

Page 121

sizes/ absorbencies provided allow us to accommodate individual needs and
preferences. The type of products available will be regularly reviewed to meet the needs
and wants of the community. Environmentally friendly products are available on request.
Products are available for collection by anyone who needs them, or by anyone collecting
on behalf of another person. Products will normally be available within toilet facilities of a
building, unless otherwise stated. Those who wish to access products can do so without
having to ask a member of staff and in a way that respects their dignity. A person may
access as many products as required.
Information on stocked venues can be accessed via the PickUpMyPeriod App and North
Lanarkshire Council Directory website. This allows users to enter a postcode or location
to see where free period products are available in their area.
8. Provision within Education 
North Lanarkshire Council provide free products in all secondary school establishments and
on request will be made available to primary schools.
Products will be available in a way which respects the dignity of the pupil and can be
accessed without having to ask a teacher.
Products will be available during term time in at least one part of the school, normally the
toilet facilities or from the school reception. Some schools may have products available in
multiple locations.
North Lanarkshire Council will provide ongoing support to its education establishments to
ensure every pupil who requires products is able to obtain them easily.
9. Communication
Information on our free period product initiative is available on the North Lanarkshire
Council website. Details are provided on how, where and when people can obtain free
products via our own easy to use app and the official Period Products Locator app.
Enquiries can also be submitted at any time and will be dealt with by our Community
Partnership Team.
It is our intention to regularly promote and raise awareness of the free access to period
products. This will involve advertising and marketing campaigns using digital and
traditional methods. Information posters are also posted on notice and information
boards in all our public buildings and community facilities.
10. Future Provision and Improvements
North Lanarkshire Council recognises the importance of securing period dignity for all and
will commit to using intelligence from our consultation work as well as other feedback from
partners and stakeholders, to continue to develop our approach to providing free period
products within North Lanarkshire.
From our recent consultation and engagement work a number of key developments are
currently underway. Completion of which will assist with a further targeted expansion and the
Page 121 of 186

Page 122

implementation of improvements aimed to improve processes, service deliver and the overall
offer for residents and visitors. Further details are provided within the 2022 update report
which can be accessed on our website.
11. Further information
Additional information can be found on the NLC website free period products
(northlanarkshire.gov.uk)
The NLC interactive mapping tool can be accessed using the following link:
Directory records | North Lanarkshire Council
Scottish Government ‘Pick up my period’ app enables individuals to put in a town,
city or post code and find out where to access products.
PickupMyPeriod on the App Store (apple.com)
PickupMyPeriod - Apps on Google Play
Index - MyPeriod (myperiodlive.azurewebsites.net
Page 122 of 186

Page 123

Appendix 4 
*Please Note some questions were omitted due to personal information e.g.
names and email addresses. 
Page 123 of 186

Page 124

Page 124 of 186

Page 125

Page 125 of 186

Page 126

Page 126 of 186

Page 127

Page 127 of 186

Page 128

Page 128 of 186

Page 129

Page 129 of 186

Page 130

Page 130 of 186

Page 131

Page 131 of 186

Page 132

Page 132 of 186

Page 133

Page 133 of 186

Page 134

Page 134 of 186

Page 135

North Lanarkshire Council
Report
Communities Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref    SP/LP Date 28/10/24 
Community Ownership and Management of Assets: Overtown
Sports Pitch and Pavillion 
From:  Stephen Penman, (Chief Officer of Strategic Communication and Engagement)
E-mail penmanste@northlan.gov.uk
pollockle@northlan.gov.uk  Telephone 07947 997750
07814 916564 
1. Background 
1.1 The Community Empowerment (Scotland) Act 2015 encourages community-based
groups to take control of assets to be utilised for positive outcomes as driven and
directed at a local level. Qualifying groups can apply to a relevant authority, which
includes local authorities, to either lease or purchase an asset. 
Executive Summary 
The purpose of this report is to provide the Communities Committee with the details of a
Community Asset Transfer (CAT) request relating to Overtown Sports Pitch and Pavilion (as
outlined in Appendix 1 of this report) made by Fir Park Corner Football Club and to provide
information on the outcome of the assessment process together with a recommendation for
approval of the request. 
Recommendations
It is recommended that the Communities Committee:
(1) Considers the detailed assessment of the application against approved criteria,
included at Appendix 2, of this report. 
(2) Approves the recommendation by the Community Ownership and Management of
Assets Leadership Group for approval in principle of the request made by Fir Park
Corner Football Club to take full ownership of the Overtown Sports Pitch and
Pavillion. 
The Plan for North Lanarkshire
Priority  Enhance participation, capacity, and empowerment across our
communities
Ambition statement (20) Improve the involvement of communities in the decisions,
and development of services and supports, that affect them
Programme of Work Resilient People
Item 7
Page 135 of 186

Page 136

1.2 Upon a formal application being made, the relevant authority is bound to carry out an
assessment of the request, establish that the applicant is a qualifying body and assess
both the sustainability and likely benefit of the asset transfer. Benefits can include social
wellbeing, economic benefit and provision of services and activities that would not
otherwise be provided. 
1.3 In general terms a where a group meets qualifying and eligibility criteria they can apply
for any asset held by a relevant authority. The asset does not have to be surplus to the
council’s operational requirements. Exclusions apply in a few circumstances including 
• NLP mortgaged properties
• Common Good Assets 
• Where the council has entered into a legal agreement for sale or demolition of
an asset 
1.4 If it is determined that the asset is not surplus the council needs to assess the
operational benefit of retaining the asset against the benefits brought by the transfer.
An application can be rejected on grounds such as; the business model is not
sustainable, the group cannot evidence community support or community benefit, or
the group cannot demonstrate that they have the capacity to manage the asset. 
1.5 The Policy and Strategy Committee approved a new Community Ownership and
Management of Assets Policy and associated resources aiming to improve the
council’s approach to building capacity and opportunity with organisations looking to
take on ownership, lease or management of a council owned asset. The aim is to shift
the focus to achieving positive outcomes and using available resources and tools to
over time increase the pace and volume of successful outcomes while protecting the
council and risk levels. The policy and approach can be accessed here and further
information and tools are available on the council’s website. 
2. Report 
2.1 Fir Park Corner is a Scottish Charitable Incorporated Organisation (SCIO) (charity
number SC051821). The organisation is a Community Football Club who currently have
an amateur team, an over 35’s team and four children’s teams. 
2.2 Fir Park Corner submitted a formal request to purchase Overtown Sports Pitch and
Pavilion (as outlined in Appendix 1 of this report) inclusive of the pitch, pavilion and
associated carpark, at a discounted rate of £17,500 to reflect social value / community
benefit and planned improvement work. This pitch is one that the council agreed at the
last Communities Committee meeting to remove as a bookable site based on low usage
and that the council has no operational requirement for. 
2.3 The organisation proposes to use the site as a base for their football teams to train,
play matches and host local events for the wider community through collaboration with
other local organisations. Acquiring the site would enable them to expand their offer by
adding further teams and therefore opportunities for more local people across age
ranges to participate in sport. This would also reduce the need for and cost of booking
pitches and facilities to run the club and matches and enable them to divert these
resources into the maintenance and upkeep of the site. 
Page 136 of 186

Page 137

2.4 The group commissioned a valuation of the site. The valuer utilised a per acre base
rate to arrive at a value of £35,000. This value is within the anticipated range for this
type of asset.  The offered price is 50 per cent of the valuation (£17,500) and reflects
characteristics of the site, its current use and the community benefit outlined in the
submitted application. It is normal practice for the Estates Service to seek some form
of legal ‘security’ over the site when a discount is applied. The form of security is
dependent on various factors for example funding structure of the group or
constitutional organisation matters. Such an agreement will be sought in this case but
only where it is practical to do so.   
2.5 Should the recommendation to approve this request be endorsed by committee, the
Estates Service will look to agree Heads of Terms with the applicant. This will form the
detailed terms for the title transfer, subject to approval of the Chief Officer of Assets
and Procurement under delegated authority. 
2.6 The scoring and assessment process overall provided assurance that community
ownership of the Overtown sports pitch and pavilion by Fir Park corner Football Club
has the potential to make a lasting impact on the health and wellbeing of the club’s
members and to provide a valuable asset to the wider community. 
2.7 The application scored strongly with 7 of the 8 assessment criteria scoring as strong or
very strong and 1 scoring as moderate. An overview of assessment can is at figure 1.
The details of the assessment are attached at appendix 2. 
Figure 1. 
Summary Grading Very
Strong
Strong Moderate Weak Very Weak
1.Details of the asset  x   
2.Organisation information  x   
3.Type of Request   x  
4.Link to the NL Plan  x   
5.Community Proposal  x   
6.Support x    
7.Financial Information  x   
8.Risk/Social Impact  x   
2.8 The organisation scored particularly strongly under community support where they
demonstrated that they had developed a robust community engagement plan and
consulted extensively with local stakeholders (community council, businesses, football
teams operating in the wider areas, elected members, local politicians, local church and
community groups) They also held a community information session and developed a
questionnaire / survey for the wider community. Over 350 local residents completed the
survey with the majority of respondents fully supportive of their plans. 
2.9 It should be noted that the moderate assessment score was for ‘type of request’ and
reflects that the amount offered is below what the council would expect to be market
value. This is an expected score for an organising submitting an application to take on
ownership of an asset at less than market value due to the assessment criteria applied,
and assurance has come from the information related to community benefit. During
assessment, the panel felt that some more detailed information could be
provided within the finance section for example relating to cash flow and
Page 137 of 186

Page 138

projected running costs. On request, the club has since submitted further information
and clarification which the scoring panel and Leadership Group are satisfied with. One
of the matters highlighted was that some of the costings presented did not match the
councils’ expected costs based on internal projections, but the panel remains confident
that the organisation has taken reasonable steps to adequately identify future
operational costs based on their own operating model. 
2.10 The club proposes that they will ensure that the asset will serve as vital resource for
encouraging physical activity across many age groups. This will be achieved through
the operations of amateur Saturday and Sunday adult football teams, as well as youth
academy teams. Future plans outlined include the development of women’s football
team and additional academy teams. 
2.11 Additionally, the club have detailed a four-stage plan for improving the sports pitch and
pavilion which when implemented aims to bring back to full use this underused and
dated community facility. The improvement work will also enhance the local area and
lead to increased community involvement with the club and the community activities it
plans to deliver. The club also intends to deliver a range of community events and
activities throughout the year. 
2.12 The club has submitted, alongside their application, a request to access the Community
Asset Fund for improvements to the asset to the value of £100k. They have provided
information on the types of improvements and quotes that they have obtained for the
works including plumbing, joinery, groundworks and roof works for the pavilion as well
as works to upgrade the pitch, signage, perimeter security and car park area. 
2.13 Community support for the proposal has been established through various community
engagement activities and the club plan to build on the relationships that they have
started to develop. 
2.14 Overall, the scoring panel and leadership group felt satisfied and assured that the
community ownership of this facility can create sustainability for this asset and will
provide greater community benefit than is currently being achieved. 
2.15 In line with the council’s Community Ownership and Management Policy and
associated scoring process the findings of the Officer Assessment Panel were reported
to the Community Ownership Leadership Group for consideration (comprising; Chief
Officers for Strategic Communication and Engagement; Asset and Procurement;
Community Operations; Legal and Democratic, and; Financial Solutions). The
recommendation is that the Communities Committee approves the application in
principle subject to final negotiation of terms through the council’s property and legal
processes. 
3. Measures of success 
3.1 Support provided to community groups and organisations as a result of initial CAT or
PR enquiries; and 
3.2 Positive outcomes or referrals because of initial CAT or PR enquiries. 
3.3 Increased completions for transfer of assets to community organisations 
Page 138 of 186

Page 139

4. Supporting documentation 
4.1  Community Ownership and Management of Assets Policy and approach here
4.2  Further information and tools are available on the councils website. 
4.3  Appendix 1      Map of Asset 
4.4  Appendix 2    Assessment of Fir Park Corner request to purchase Overtown Sports
Pitch and Pavilion
4.5  Equality Impact Assessment will be published here   
Stephen Penman 
Chief Officer (Strategic Communication and Engagement)   
Page 139 of 186

Page 140

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?, 
The recommendation involves the transfer of an asset to community ownership for
community use and recognises the associated community benefit that is expected
from the proposal. This should benefit the community positively but an EQIA has
been undertaken to consider any impact on equalities groups and will be available
here 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The proposed purchase price is below what the council would consider as the
marketable value of the asset. However assessment of the application as well as
the condition, location and current use of the concluded that community benefit of
the proposal outweighs the true value of the asset to the council. Financial
Solutions are involved in the assessment process and the Leadership Group
responsible for making recommendation to committee. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☒ No ☐ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The council approach to community Ownership and Management of Assets reflects
and supports the requirements of the Community Empowerment (Scotland) Act
Page 140 of 186

Page 141

2015. Representatives from Legal and Democratic Services are involved in the
Corporate Community Ownership and Management of Assets Working Group and
the Leadership Group as required. 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☒ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☒
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
There is inherent risk in transferring an asset for community ownership. However
the club has demonstrated strong community support, cognisance of the research,
business case and diligence checks completed as part of the application process.
The demonstrated knowledge, and experience of the management committee has
provided assurance of the organisations capacity to take ownership of the asset
and to implement their plans to bring the sports pitch and pavilion in full use. The
risk has been determined as low but the organisation will be encouraged to
consider strengthening their contingency planning and to review their plans for
dealing with potential drainage issues on the pitch.
Page 141 of 186

Page 142

5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☒ 
Page 142 of 186

Page 143

Appendix 1 
Asset location map 
Page 143 of 186

Page 144

Appendix 2 
Assessment framework used to inform the recommendation on a Community
Asset Transfer Request
Name of Organisation/Applicant Fir Park Corner Football Club
Details of the Asset  Overtown Sport Pitch and Pavilion
Community Area/Ward  Overtown 
(Wishaw Community Board) 
Wishaw - Ward 21
Date submitted 12 June 2024
Date of Decision 2 September 2024 
Recommendation Approve/Reject/ Defer
(delete as appropriate)
Approve
Summary comments The scoring panel are of the view that
community ownership of the Overtown sports
pitch and pavilion by Fir Park corner Football
Club has the potential to make a lasting impact
on the health and wellbeing of the club’s
member. Evidence from across Scotland and
from the description provided by the club
indicates many benefits from having accessible
local sports facilities on health outcomes. The
club will serve a vital resource for encouraging
physical activity across many age groups. This
will be achieved through the operations of
amateur Saturday and Sunday adult football
teams, as well as youth academy teams. Future
plans include the development of women’s
football team and additional academy teams. 
The club have indicated a four-stage plan for
improving the sports pitch and pavilion which
when implemented will go some way to bring
back to full use an underused and dated
community facility. The improvement work will
also enhance the local environs and will
hopefully lead to increased community
involvement with the club and the community
activities it plans to deliver.  Although football
training and matches will be the mainstay at
the facility the club intend to deliver a range of
community events and activities throughout
the year. 
The transfer of this asset to the community
football club will also support efforts to address
Page 144 of 186

Page 145

local inequalities. By offering members
affordable access to physical activity. 
Additionally, the facility will create volunteering
opportunities and pathways for young people
interested in sports and leisure careers. This
should contribute to the local economy through
skills development of the volunteers 
Community support for the proposal has been
established through various community
engagement activities and the club plan to
build on the relationships that they have
started to develop. 
Overall, we are confident that the community
ownership of this facility will foster long-terms
sustainability for this asset.
Final Decision 
Summary Grading Very
Strong
Strong Moderate Weak Very Weak
1.Details of the asset  x   
2.Organisation information  x   
3.Type of Request   x  
4.Link to the NL Plan  x   
5.Community Proposal  x   
6.Support x    
7.Financial Information   x  
8.Risk/Social Impact  x   
1 Details of the Asset – Includes asset status and proposed use
This section asks the council to ensure they are in a position to transfer the asset 
฀  Very Strong:  The proposal has a cost saving, does not impact on council direct delivery or     
service and there are no restrictions on the asset transfer 
฀   Strong: The proposal is cost neutral to the council, it does not impact on council direct      
delivery of services and there are no restrictions on the asset transfer. 
The asset is currently managed and operated by Active and Creative Communities Team.
However, over the last few years has been significantly underused, with occasional ad-hoc
bookings. The holding service has reviewed the asset as part of the sports pitch strategy and
have identified that the site is no longer needed for operations. 
The transfer of ownership to Fir Park Corner Football Club presents an opportunity to safeguard
the pitch and pavilion for long-term community use and remove the cost burden for the council.
With the applicant proposing a full transfer of ownership and a commitment to secure funding to
improve the facility, provides a positive solution for the site, which otherwise would be
earmarked for closure.
Page 145 of 186

Page 146

The applicant if successful, is proposing to use the pitch and pavilion for training and football
matches for all of the teams which they operate. The site has the potential of enabling the club
to further develop additional teams and services. 
฀   Moderate: the proposals presents difficulties on the council in terms of one or two of the 
following – direct cost, council direct delivery of services and or restrictions on the assets     
transfer. 
฀   Weak: the proposals presents difficulties to the council in terms of cost, council direct 
deliver of services and restrictions on the asset transfer. 
฀   Very Weak: unlikely to proceed because of ownership restrictions on the asset this would      
prevent a transfer of responsibility or ownership to another organisation. 
2 Organisational Information – Includes governance and capacity to deliver 
ÿ   Very Strong: Applicant has clearly evidenced that they are a robust and viable organisation 
with effective governance arrangements in place. 
฀   Strong: Applicant has provided adequate evidence that they are a robust and viable      
organisation with satisfactory governance arrangements. 
The organisation has outlined the strengths and experiences of their management committee.
Currently seven North Lanarkshire residents are involved in the management and day-today
operations of the club. The management committee come from various professional
backgrounds and most have significant experience in terms of community football operations.
They have demonstrated a strong personnel base, which should be a positive in terms of
implementing their plans and further developing and improving the club. 
The club meet regularly throughout the year and all meetings and decisions made are noted. The
club are set up as Scottish Charity in the form of a Scottish Charitable Incorporated organisation.
The trustee of the charity (management committee) is elected from within the membership.
Initial checks made, have identified that the club have relevant policy, procedures and safeguards
in place. 
฀   Moderate: Applicant has evidenced some signs of being robust and viable and partial      
information provided on governance arrangements. 
฀   Weak: Applicant has shown no evidence of being robust and viable and no/little information     
being provided on governance arrangements. 
฀   Very Weak: Applicant has provided no evidence of being robust or viable. Governance      
arrangement does not meet the criteria for asset transfer. 
Page 146 of 186

Page 147

3 Type of request, payment and conditions
This section confirms the type of request and seeks and whether or not the price reflects a
fair price for the asset taking into consideration community benefit 
฀   Very Strong: Applicant has proposed acceptable terms, with prices reflecting Market/Fair 
Value. (score would reflect acceptable terms; for example – the right timescale for being      
able to complete the sale or lease and funds are already in place) 
฀  Strong: Applicant has proposed terms, with prices reflecting Market/Fair Value. 
฀  Moderate: Applicant has proposed terms, with prices well below Market/Fair Value. 
The club are proposing a full purchase of the title inclusive of the pitch, pavilion and associated
carpark, at a discounted rate to reflect social value / community benefit and planned
improvement work. An offer of £17,500 has been made by the club, and whilst this is under our
internal estimate of value, the scoring panel on advice from Estates agree that the offer is within
an acceptable range reflecting the site is landlocked and an agreement to allow a discount for
the social value described by the club. 
However, consideration of imposing a standard security may be needed. Additionally, a check on
the site by Estates and Operational Property has identified encroachment issues, which means
the title cannot be transferred with full vacant possession to the club. These matters will need to
be considered as part of the negotiation for the heads of terms. 
฀  Weak: Applicant has failed to propose terms or prices. 
฀  Very Weak: Applicant unsure of securing funding to afford costs. 
4 Link to Strategy– How the project links into the vision and ambitions set out in the Plan
for North Lanarkshire (TPFNL) 
฀   Very Strong: Applicant has clearly evidenced that their project links in to the key themes of      
TPFNL 
฀   Strong: Satisfactory evidence that the applicant understands the importance of linking to the      
outcomes of the TPFNL 
The club have demonstrated satisfactory understanding of their contributions to the Plan for
North Lanarkshire and the proposed activities should positively contribute to priorities agreed for
the Wishaw Local Outcome Improvement Plan (LOIP). 
The scoring panel view that the plans developed by the club will align closely with our ambition
for improving the health and wellbeing of our communities and enhancing participation, capacity
and empowerment across our communities. 
฀   Moderate: Limited evidence that the applicant understands the need to ensure the projects      
reflect one of more of the strands of the  TPFNL.
Page 147 of 186

Page 148

฀   Weak:  Little or no evidence that the applicant has made a clear connection to the TPFNL 
฀   Very Weak: Applicant has no understanding of the TPFNL 
5 Community Proposal – Includes project aims, community engagement and community
benefit/need 
฀   Very Strong: Full consideration has been given to the aims, objectives and vision with clear      
thought to the future direction of the proposal. The proposal provides, for example, a      
social/economic/environmental impact. Comprehensive evidence of need/demand provided       
including consultations, research and surveys. 
฀    Strong: Adequate description of aims, objectives and vision for the proposal. A good       
understanding of the community benefits including adequate evidence. Need/demand 
evidence include some consultation and research. 
The organisation has presented a strong case for need behind this asset transfer request and
have outlined a plan which will help address the availability issues of local pitches for football
clubs, this include allowing other clubs to access the facility when it is not in use. 
The club have also identified a need and gap in terms of local football options within easy reach
of Overtown. Their plan brings football back to the heart of the local community and the transfer
of the facility will enable them to develop new additional academy teams for children and young
people to access. 
The club have clearly articulated the social benefits for their plans and if their application is
successful, they envisage offering a route into healthy, low-cost physical activity with positive
contributions to the securing improving the general health and mental health of residents. 
The club have also outlined the contributions to the community wealth building agenda, and
anticipate that supporters will bring additional footfall to local businesses on match days. 
฀    Moderate: Limited description of the aims, objectives and vision for the proposal. Some       
understanding of the community benefit but not underpinned by substantive evidence. Some       
evidence of need/demand provided including limited consultations, research and surveys. 
฀    Weak: Inadequate or no description of aims, objectives and vision for the proposal. Limited      
reference to community benefit and associated opportunities. No evidence of need/demand       
provided. 
฀    Very Weak: No description of aims, objectives and vision for the proposal. No reference to       
community benefit. No evidence of need or demand provided. 
Page 148 of 186

Page 149

6 Support – Includes stakeholder engagement and partnership working
This section looks Including evidence community and stakeholders have been engaged 
฀    Very Strong: Applicant has clearly demonstrated links with relevant stakeholders and groups      
as well as strong local partnership and community engagement. Evidence of joint responsibility      
for delivery of other projects/service. 
The organisation created a robust community engagement plan and consulted with many local
stakeholders (community council, businesses, football teams operating in the wider areas, elected
members, local politicians, local church and community groups) They also held a community
information session and developed a questionnaire / survey for the wider community. Over 350
local residents completed the survey with the majority of respondents fully supportive of their
plans. 
No formal representations were received during the formal 4 week consultation period. 
฀    Strong: applicant has evidenced some partnership working arrangements. Relevant links with       
groups also evidenced along with strong community engagement activity. 
฀    Moderate: Applicant has demonstrated limited links with groups and community engagement       
activity. Some evidence of partnership working provided. 
฀    Weak: No/poor evidence of community involvement. No/poor evidence of partnership 
Working.
฀   Very Weak: No evidence of community involvement. No evidence of partnership working. 
7 Financial Information – Includes fundraising, financial planning and management
We will seek clarification of funding being in place or any potential delay in funding being
in place in time for the final transfer deadline. 
฀    Very Strong: Clear Evidence that sufficient financial resources are/will be in place by the time       
of transfer and good resource planning for short/ medium/long term sustainability       
demonstrated. Detailed, realistic and achievable income and expenditure, cash flow       
forecast provided along with a comprehensive contingency plan. 
฀    Strong: Evidence indicates that sufficient financial resources are/will be in place by the time of       
transfer and some resource planning has been demonstrated. Satisfactory income and       
expenditure and cash flow forecast. Some consideration has been given to contingency 
planning. 
The organisation has provided a three-year forecast of income and expenditure. The improvement
work for the facility has been designed to be completed in four stages and the club are confident
of being able to complete this work whilst operating the site. They intend to apply to funders and
to fundraise also. Initial conversations have taken place with National Lottery and Sports Scotland. 
The scoring panel requested that the club provide some more detailed information related to this
section for example around budget, cash flow, running costings etc and the club has since
provided additional clarification. Some of the concern was linked to the costings provided by the
club not matching the councils costings for similar. However on receipt of further information and
Page 149 of 186

Page 150

discussion with the club the panel is confident that the organisation has taken reasonable steps to
adequately to identify future operational costs for their own operating model. 
฀    Moderate: Applicant has demonstrated there are some financial resources in place but all       
finances may not be available within the timeframe. There is limited evidence of resource       
planning. Basic income and  expenditure and cash flow forecast induced with limited       
consideration given to contingency planning. 
฀    Weak: Insufficient financial resources currently in place and unlikely to be ready within the       
Time frame. No evidence to demonstrate resource planning. No income and expenditure and       
cash flow forecast provided and no contingency plan outlined. 
฀    Very Weak: No evidence of financial resources in place. No evidence of resources or financial 
forecast to predict cash flow. 
8 Risk/Social Impact – Includes potential impact and barriers/challenges and 
understanding of managing the asset. 
฀   Very Strong: Full evidence that applicant has in place the necessary capabilities to manage the      
asset. Considerable awareness of the potential impact of the transfer on others, and      
barriers/challenges clearly identified. Comprehensive information provide on the anticipated      
social benefit/impact of the transfer and how this will be measured. 
฀   Strong: Satisfactory evidence that applicant has the necessary capabilities to manage the asset.     
Sufficient awareness of the potential impact of the transfer on others with consideration given     
to potential barriers/challenges. Adequate information provided on the anticipated social     
benefit/transfer. 
With the club demonstrating strong community support for the community asset transfer and
taking cognisance of the research, business case and diligence checks completed by the club as
part of the application process; and combined with the knowledge, understanding and experience
of the management committee in terms operating a community football club, it has been deemed
that the organisation has demonstrated that they will have the capacity to take ownership of the
asset and to implement their plans to bring the sports pitch and pavilion in full use. 
The organisation has outlined the social benefits which they expect to see from their ownership
and management of the asset. Risk has been determined as low but the organisation will be
encouraged to consider strengthening their contingency planning and to review their plans for
dealing with potential drainage issues on the pitch. 
฀   Moderate: Limited evidence to demonstrate capabilities to manage the asset. Some awareness     
of the potential impact of transfer on others and consideration given to potential     
barriers/challenges. Minimal information provided on the anticipated social benefit/impact of     
the transfer. 
฀   Weak: Inadequate or no evidence of capabilities in place to manage the asset. Little or no 
awareness of the potential impact of the transfer on others or possible barriers/challenges     
identified. No social benefit/impact monitoring outlined. 
Page 150 of 186

Page 151

฀   Very Weak: applicant has provided no evidence of capabilities to manage the asset. No     
awareness of the potential impact of the transfer on others. No social benefit or impact    
monitoring in place. 
Page 151 of 186

Page 152

Page 152 of 186

Page 153

North Lanarkshire Council
Report
Communities Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref KH/GR/RB Date 28/10/24 
Digital North Lanarkshire PoW Update: Immersive Experience Project 
From  Katrina Hassell, Chief Officer (Business and Digital)  
E-mail HassellK@northlan.gov.uk Telephone 07903 096 121 
Executive Summary
At its most recent meeting held on 19th August, members acknowledged that activities contained
within the Digital North Lanarkshire Programme of Work (PoW) which are linked to the Council’s
ambition statement 18 below would be reported to future meetings of the Communities Committee. 
Members will be familiar with the Council’s approved Digital & IT Strategy (the Strategy) 2024-
2027, which illustrates how embedded digital thinking and practice support the Council to embrace
available technologies to find new ways to interact with its communities – at pace and scale - to
ultimately turn the Council’s overall ambition of inclusive growth and prosperity for all in The Plan
for North Lanarkshire into a reality.
The Digital North Lanarkshire PoW theme contains twelve key deliverables, categorised as: (a)
Digital Culture, Leadership and Knowledge; (b) Improved Customer Experience; (c) Digital First
Operations and (d) Performance Optimisation. When taken together, these deliverables enable
the Council to deliver on its Digital Communities, Digital Economy and Digital Council aspirations.
This report is focused on the following key activity within the ‘Digital First Operations’ theme:
The report highlights the steps taken from initial scoping and option appraisal to procurement and
installation of immersive rooms across the council estate, using key performance for the
Motherwell Library immersive room (launched in January 2024) to illustrate progress against this
key PoW deliverable. The report also outlines the operational and governance structures that have
been put in place to manage the development post build. 
Recommendations
It is recommended that the Communities Committee: 
(1)  Acknowledge the content of the report, and progress to date in delivering community access
to immersive pods across the Council area. 
Develop and deliver community access to the immersive pods (sensory spaces which can
be utilised to house the latest sensory technology to provide support, in such areas as
mental health and employability) across North Lanarkshire. 
Item 8
Page 153 of 186

Page 154

1. Background 
1.1 Reports presented to committee in recent years illustrate that the Council and the
communities we support need to function in a modern digital world, which is fast moving,
forever changing, and increasingly reliant upon technology for work, learning, business, and
connecting with others. 
1.2 As technology continues to play an ever-increasing role in the way in which service users,
residents, and businesses live, learn, work, invest, and visit within North Lanarkshire both
now and in the future, it is vital that the council - as a critical provider of public care, supports,
and services – embraces developing technology to improve user access and experience. 
1.3 The Council’s approved Digital & IT Strategy 2024 to 2027 (‘the Strategy’) provides direction
on what ‘being digital’ means for the council and the services it delivers. By delivering
against its strategy, the Council aims to deliver on its Digital Communities, Digital Economy
and Digital Council aspirations. 
1.4 The Digital North Lanarkshire theme of the Programme of Work for 2023 to 2028 sets out a
roadmap to deliver on the Council’s digital aspirations, a key aim of which is to promote
innovative, connected, and secure service delivery for our communities. 
1.5 Initially approved by the former Transformation and Digitisation Committee in November
2020, the Council has been developing Immersive Experience pods to transform community
access to and experience of digital services. Following contract award approval at Finance
and Resources Committee in September 2023, the Council is expanding the number of
immersive rooms available within its area. 
1.6 Funding for this project was secured via the ERDP programme and Business and Digital’s
capital programme. The project focusses on developing three immersive rooms in sites
across the authority, as well as an upgrade of the initial immersive room within the Muirfield
Centre, Cumbernauld. 
1.7 The aim of the development is to offer interactive learning environments that use digital
projection to create an interactive 360- or 270-degree experience on three and four walls.
Rooms are designed to be accessible to all community groups, schools, partners, local
businesses and in some cases individuals who work, study, live, visit or invest in North
Lanarkshire. 
1.8 A working group was created made up of representatives from key partners from across the
council, including Education & Families, Active & Creative Communities, Community
Learning & Development and Business & Digital Services, to conduct an option appraisal
on sites for the three new rooms and to manage the tender for a supplier. BT were
successful in securing the tender to design and build the rooms (working with their partners
at Immersive Interactive) and upgrade the room in the Muirfield Centre. The option appraisal
process identified the following sites for the new immersive rooms: 
(a) Summerlee Museum of Industrial Life, 
(b) Motherwell Library and 
The Plan for North Lanarkshire
Priority  Enhance participation, capacity, and empowerment across our
communities
Ambition statement (18) Ensure our digital transformation is responsive to all people's
needs and enable access to the services they need
Programme of Work Digital North Lanarkshire
Page 154 of 186

Page 155

(c) Airdrie Library. 
1.9 This report provides details of progress made to date in achieving the targeted aims and
describes the status of the operational and governance structures which are required to
manage the development and operation of the facilities post-build phase. 
2. Project Development Update 
Build Update 
2.1 To date two of the three new immersive rooms (in Motherwell Library and Summerlee
Museum of Industrial Life) have been built and are operational. The immersive room in the
Muirfield centre has also been upgraded and is operational. The room being created at the
Airdrie Library site is due for completion by the middle of November 2024. 
2.2 The upgrade to the immersive room in Muirfield (a free standing 360-degree immersive
space) included a full upgrade to the projection unit, a refurbishment of the walls and floor,
and installation of aroma technology. 
2.3 The room built in Motherwell library (a free standing 360-degree immersive space) has been
developed as part of a wider digital hub development within the building. It is situated on the
first floor alongside flexible learning spaces and the Letitia McKell Makerspace. 
2.4 The immersive room in Summerlee Museum of Industrial Life is a 270-degree designed
multifunctional space with projectors fitted to the ceiling and the option to use the space for
other events and activities when the immersive experience isn’t being used. 
2.5 The immersive room in Airdrie Library will also be a 270-degree multifunctional space which
has been specifically designed to be sympathetic to this historic library and the community
needs that the library fulfils. 
2.6 Each of the rooms are within existing operational buildings with their own history,
uniqueness, established use and relationship to the surrounding premise and community
operations.  It was therefore critical that the designs were cognisant to these factors with
each therefore designed to incorporate that need for flexibility and access. 
2.7 The build of these unique multipurpose environments has been a learning curve for all
involved, requiring understanding of the technical requirements of the technology and the
physical environment they operate in. This has delayed the overall delivery timescale but
has resulted in better designed multi-purpose spaces. 
Immersive Room Operating Model 
2.8 A draft immersive room operating model has been developed, which will address the
following operating issues: 
2.8.1  Opening Times and Booking Periods - Opening times for each immersive room will vary and
are dependent on the opening times of the buildings within which they are located, and the
availability of staff to support access. 
2.8.2  Access Controls - Access to the immersive rooms will be controlled via an agreed booking
process 
2.8.3  Charging - Where possible access to each immersive room, for general use by schools,
council partners, charities and local groups will be free. A charging mechanism will apply to
Page 155 of 186

Page 156

business and other interested parties who wish to access the room. A breakdown of the
draft charging model can be seen in appendix 1 
2.8.4 Content Creation - Where possible the service will look to develop bespoke learning
resources, based around local need. Colleagues within Active & Creative Communities and
Education and Families will work together, where appropriate to develop bespoke learning
resources. 
2.8.5 Training and Sharing - A training and sharing Teams channel has been set up in order for
relevant NLC staff to sharing information and ideas. Onsite training and information sharing
sessions, beyond initial induction, will also be delivered. 
Immersive room development governance structure 
2.9  A two tier governance and operational management structure has been developed as part
of the immersive rooms project. 
2.9.1 Governance group - An Immersive Room Governance Group has been created to retain an
overview of the general performance and use of all immersive room services, create and
maintain a service-wide action plan -, which incorporates the vision and direction of travel
for the Immersive room services - and monitor contract performance. 
2.9.2 Operational group - An operating group, made up of representatives from the services
managing the immersive room, has been formed with a remit of sharing good practice,
sharing content, trouble shooting and developing and managing the immersive room
operating plan. 
Impact of the immersive room project to date 
2.10  The access of and use of the completed spaces, to date has been significant. The space in
Motherwell library, for example, has held 80 engagement sessions since its opening in
January 2024, for 34 different partner organisations, with 1046 visitors. See appendix 2 for
further details. 
2.11 There are plans to continue to expand the outreach of the offer by working with a range of
groups such as Hope for Autism, Partners in Play, The Gaelic Medium Unit and Saint Mary’s
Guild church group.  
3. Measures of success
3.1 General performance will be measured by the number of bookings taken within a specified
period and the number of users of each interactive room within a specified period. 
3.2 Specific outcomes will be developed for each immersive room that will focus on a range of
areas such as digital skills development, health and wellbeing improvement, social skills
development, attainment of knowledge, employability and pathways to future learning
opportunities. 
4. Supporting documents 
4.1 Appendix 1 Draft Charging Model 
4.2 Appendix 2 Immersive Room Usage – Motherwell Library Digital Hub 
Page 156 of 186

Page 157

Katrina Hassell
Chief Officer (Business and Digital)  
Page 157 of 186

Page 158

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public Sector
Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
An Equality / Fairer Scotland Duty Impact Assessment was undertaken when
developing the Digital and IT Strategy 2024 to 2027. This assessment highlighted key
impacts may exist for older people, low-income groups, those with a disability, and
people who are homeless, asylum seekers or whose first language is something other
than English.  
Deploying fibre-enable immersive experience rooms across the Council area doesn’t
materially change the impacts which were previously identified for the Digital & IT
Strategy. These will therefore remain as an area of focus and consideration as we look
to maximise the capabilities available through these technologies. 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments 
Yes ☒ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
Funding for this project was secured from a combination of Business and Digital’s
capital Budget, and grant funding available to Active and Creative Communities. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact?
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact?
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-mailed
Page 158 of 186

Page 159

to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
The Digital North Lanarkshire priority in the Programme of Work to 2028 envisages
significant changes to applications, software, hardware, and connectivity, with all duly
considered from a Digital First and Enterprise Architecture perspective through the key
governance groups of the Enterprise Architecture Governance Group (EAGG) and Data
Governance Board (DGB). 
The solution utilises the Council’s network, with network redesign required to ensure
successful deployment. Equipment deployed to individual sites will be maintained by the
supplier. Support for ongoing use is expected to come predominantly from local users
and solution champions.   
Where the impact identifies a requirement for significant technology change, has an
assessment been carried out (or is scheduled to be carried out) by the Enterprise
Architecture Governance Group (EAGG)? 
Yes ☒ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
Communication with all stakeholders will remain a key priority in implementing the
Digital and IT Strategy 2024 to 2027 and deploying the roadmap and delivery plan in
pursuit of a Digital North Lanarkshire. 
There is also opportunity to promote these immersive experience rooms to communities
through the Council’s Driving Digital Locally sub-group. 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service or
Project Risk Registers), and how they are managed?
The governance structure described above will ensure that appropriate controls exist to
minimise any further impacts on the existing corporate risks of:
➢ Information Security and Information Governance (current score of 20),
➢ ICT Operational Capability (current score of 20),
➢ Digital and IT Strategy (current score of 12), and
➢ Digital Adoption (current score of 20). 
Page 159 of 186

Page 160

5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-Service
personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to ensure
there has been appropriate consideration of the particular needs of the Armed Forces
community to make sure that they do not face disadvantage compared to other citizens
in the provision of public services.
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service delivery,
policy, or plan that has an impact on children and young people up to the age of 18, or
on a specific group of these? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact and the provision that has been
made to ensure there has been appropriate consideration of the relevant Articles from
the United Nations Convention on the Rights of the Child (UNCRC).
Implementation of the Digital and IT Strategy 2024 to 2027, and therefore its key
deliverables around the use of immersive experience rooms, is considered to have an
indirect impact on children. In particular, article 2 (non-discrimination) and article 23
(children with a disability).  It is recognised that the rights of the child, and the needs of
certain groups, require to be considered throughout the journey to a Digital North
Lanarkshire. The technologies described within this report aim to make services more
accessible, with opportunity to improve people’s lives though digital technology,
solutions, and skills. 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been carried
out? 
Yes ☒ No ☐
Page 160 of 186

Page 161

Appendix 1 
Draft Charging Model 
If access to the room to use existing
modules is required
Monday to Friday £22 per hour
Saturdays £32 per hour
Sundays £50 per hour
If access is required in order to utilise
learning resources supplied by the
customer
Monday to Friday £22 per hour
Saturdays £32 per hour
Sundays £50 per hour
An additional £20 per hour up to a
maximum of 3 hours to cover staffing costs
to upload the module(s) to the system.
If the customer requires any amendments
to existing learning resources
£20 per hour for the amendments a
maximum of 7 hours to cover staffing costs
and the following per hour for access to the
room: 
Monday to Friday £22 per hour
Saturdays £32 per hour
Sundays £50 per hour (Summerlee only) 
Page 161 of 186

Page 162

Appendix 2
Immersive Room Usage – Motherwell Library Digital Hub 
The official opening date for Motherwell Library / Digital Hub was Thursday 25th January 2024. On that occasion a number of pupils from Ladywell
PS had the opportunity to explore the Immersive Room and be photographed in it as part of the publicity. Thereafter visitors, including elected
members, were able to experience the Immersive Room as part of the official tours.
Thereafter a number of technical issues were dealt with, the skin attached to the front of the unit, and additional training for staff continued. Staff
from other departments visited to explore IR and begin discussions around usage. Content development continues.
Date Group No of
Adults
No of
Children
Notes
15/2/2024 School visit 3 26 Glencairn Primary School
16/02/2024 CLD Adult learning Men’s group 5  
16/02/2024 Macmillan volunteer coordinator 1  Introduction to IR following initial
discussions about volunteers visiting
29/02/2024 School visit 6 52 Joint event with NLC Heritage Centre
– pupils visited the Millie Frood art
exhibition and workshop, other class in
hub using Immersive Room and also
creating AI inspired art in Flexible
space
5/03/2024 School visit: World Book Day events 10 90 Cathedral PS
06/03/2024 School visits: World Book Day events 11 75 Cathedral PS
06/03/2024 NLC Performing Arts team 1  Initial visit to explore concept
07/03/2024 School visits: World Book Day events 10 83 Cathedral PS
08/03/2024 School visits: World Book Day events 6 50 Cathedral PS
08/03/2024 Visit Clare Adamson MSP and staff 2  Marion Fellows MP should also have
attended but was unwell
12/03/2024 Code Club Motherwell visit to IR 5 8 
Page 162 of 186

Page 163

Date Group No of
Adults
No of
Children
Notes
14/03/2024 School visit  2 12 St Brendan’s
14/03/2024 Hope for Autism 2  Initial visit by senior staff in group to
explore possible usage
18/03/2024 Macmillan volunteer leads 5  Opportunity for Macmillan volunteers
to learn more about IR so that they
can refer individuals in for use
18/03/2024 Motherwell Town Hall project  6  Architects, contractors and NLC staff
involved in project. Discussion around
using this space later in the project to
be able to show visual walkthrough of
proposals
19/03/2024 Motherwell Heritage Centre staff  3  Introductory visit to build knowledge
base and begin content creation
conversation
21/03/2024 Routes to Work 13  Course tutor used the room to provide
a mock up scenario for delegates
attending mock interviews.
26/03/2024 Code club (Wishaw) 4 6 Youngsters and parents visited
02/04/2024 Content generation meeting 11  Number of possible partners (NLC and
3rd sector)
03/04/2024 Let’s Go Easter activities (2 sessions) 8 18 Opportunity for public access as an
easter holiday activity
03/04/2024 St Mary’s Church Guild 1 1 Pre-planning visit with committee
member
04/04/2024 North Lanarkshire Carers 2  Initial visit to discuss possible use
04/04/2024 NLC SumIt Up team members 2  Initial visit to discuss possible uses
with groups
Page 163 of 186

Page 164

Date Group No of
Adults
No of
Children
Notes
05/04/2024 Macmillan volunteer leads 6  Opportunity for Macmillan volunteers
to learn more about IR so that they
can refer individuals in for use
09/04/2024 Let’s Go Easter activities 9 10 Opportunity for public access as an
easter holiday activity
10/04/2024 NLC Care team 3  Learning disability adult supported by
two carers from NLC (not prebooked)
11/04/2024 Let’s Go Easter activities 6 10 Opportunity for public access as an
easter holiday activity
12/04/2024 NLC Motherwell Locality Adult care 3  Learning disability adult supported by
two carers
30/04/2024 School visit 5 45 Combined visit with NLC Heritage
Centre. (non NLC school)
01/05/2024 CLD Adult Learning: Motherwell Men’s Group 8  Seasons for Growth project – IR being
used as part of scene setting and
reflection exercises.
02/05/2024 NL Carers Group  1  Ailsa Tweedie
02/05/2024 Mobile Play in Action (out of school care) 3 12 Airdrie based OOS care 
03/05/2024 NLC Motherwell Locality staff planning visit 2  Planning ahead of visit with learning
disability adults and carers
06/0502024 Hope for Autism training team 2 2 (teens) Initial visit to view room and discuss
use within the group and training
delivery
07/05/2024 Catherine Johnstone  1 1 (teen) Ex Cllr / Head Teacher (Gaelic unit) –
exploring possible use with
community. Individual is involved with
the procurement and installation of
similar pod in Islay.
Page 164 of 186

Page 165

Date Group No of
Adults
No of
Children
Notes
09/05/2024 CLD Adult Learning: Motherwell Men’s Group 8  Seasons for Growth project – IR being
used as part of scene setting and
reflection exercises.
08/05/2024 Motherwell Locality Learning Disability Week events 27  Adults with learning difficulties and
carers 
09/05/2024 St Mary’s Church Guild 2  Committee members exploring IR
before looking to arrange to bring 20+
to event in November
09/05/2024 Wishaw Locality SW staff 2  Staff development / training session in
advance of exploration of use by
clients.
15/05/2024 CLD Adult Learning: Motherwell Men’s Group 8  Seasons for Growth project – IR being
used as part of scene setting and
reflection exercises.
15/05/2024 Content creation meeting 3  NLC Corporate Comms & Gaelic staff
– exploration of use in Community
Gaelic funded project. To be
developed further in Autumn
16/05/2024 New College Lanarkshire: Art students & staff 26  Initial visit for students to see and
experience space ahead of Art Show
at end of month
20/05/2024 Motherwell Locality support & clients 3  
21/05/2024 School visit 2 26 Glencairn PS
22/05/2024 CLD Adult Learning: Motherwell Men’s Group 8  Seasons for Growth project – IR being
used as part of scene setting and
reflection exercises
23/05/2024 Heads of Public Library services visit 0  
Page 165 of 186

Page 166

Date Group No of
Adults
No of
Children
Notes
29/05/2024 CLD Adult Learning: Motherwell Men’s Group 8  Seasons for Growth project – IR being
used as part of scene setting and
reflection exercises
05/06/2024 New College Lanarkshire NOW exhibition – staff preview
/ final testing
1  
06/06/2024 New College Lanarkshire NOW exhibition – private
launch for students and their invited guests
34  Students from 6 course (NQ and HNC
level) had their final pieces of art
digitised and transformed into an
immersive gallery (created by libraries
Digital Hub staff). Students work was
exhibited in large format on walls of
interlinked galleries and also included
some short video pieces. 
08/06/2024 New College Lanarkshire NOW exhibition – open to
public
7  As above – students from the course
were on hand to curate the gallery
space
10/06/2024 New College Lanarkshire NOW exhibition – open to
public
19  As above
17/06/2024 NLC Supported Employment 3  Staff training / development around
possible uses of content
17/06/2024 Townhead Primary School Wellbeing Hub 2 1 pupil with complex needs, parent and
staff member
18/06/2024 NLC Performing Arts team  3  exploration of possible community
projects
19/06/2024 CLD Adult Learning: Motherwell Men’s Group 8  Seasons for Growth project – IR being
used as part of scene setting and
reflection exercises
20/06/2024 School visit 2 24 Glencairn PS P5 Ancient Egypt
20/06/2024 Driving Digital Locally group visit 8  
Page 166 of 186

Page 167

Date Group No of
Adults
No of
Children
Notes
25/06/2024 Wishaw locality staff visit 9  NLC Carers teams’ awareness visit
26/06/2024 CLD Adult Learning: Motherwell Men’s Group 8  Seasons for Growth project – IR being
used as part of scene setting and
reflection exercises
27/06/2024 Airdrie Astronomical Society initial visit 2  Demonstration / exploration of content
01/07/2024 Mobile Play in Action 2 7 Out of hours care summer activity
01/07/2024 NLC Planning & Regeneration team 5  Exploration of how room could be
used during consultation and
development meetings
03/07/2024 CLD Adult Learning: Motherwell Men’s Group 8  Seasons for Growth project – IR being
used as part of scene setting and
reflection exercises
08/07/2024 NLC Gaelic  1  Content development session
08/07/2024 Partners in Play 3  Use of room with non-verbal young
adult and carers
08/07/2024 Partners in Play 2  Staff development - demonstration of
space to inform identification of
possible client use
26/07/2024 Safety Zone (Bargeddie) / Hope for Autism 4 15 
06/08/2024 Mobile Play in Action  2 12 Out of hours care summer activity
13/08/2024 NLC Creative Arts 1  Demonstration / exploration of content
21/08/2024 Supported Employment (Motherwell) 6  Job interview preparation scenarios
with established supported
employment group
29/08/2024 NHS Greater Glasgow & Clyde 7  Visit at request of BT / Immersive to
allow partners to explore possible
uses of room to help inform their
consultation exercises
Page 167 of 186

Page 168

Date Group No of
Adults
No of
Children
Notes
03/09/2024 Catherine Johnstone plus 2 colleagues (1 remote) 3  Ex Cllr / Head Teacher (Gaelic unit) –
exploring possible use with
community. Individual is involved with
the procurement and installation of
similar pod in Islay.
06/09/2024 NHS Lothian 3  Visit at request of BT / Immersive to
allow partners to explore possible
uses of room to help inform their
consultation exercises
12/09/2024 Partners in Play 3  Young adult with severe learning
difficulties and carers
17/09/2024 CLD Women’s Group (Wishaw) Mindfulness project 2  Exploration of content with CLD staff
for possible upcoming group
18/09/2024 School visit 3 25 Glencairn PS P3s France
18/09/2024 East Dumbartonshire Libraries staff visit 5  
23/09/2024 Partners in Play 4  2 adults 1x Downs Syndrome, 1
physical disability and carers 
Page 168 of 186

Page 169

TOTALS:
❖ Events / engagements – 80  (of which school visits – 11)
❖ Total visitors : 1046 ( of which school visits – 568)
❖ Adults – 435  (of which school visits – 60)
❖ Children – 611 (of which school visits – 508)
Pending projects :
CLD :
• Request to run another Seasons for Growth project with a Wishaw group 
• Women’s group – Mindfulness group being established in October / November who will use room and space outside
• Newly established Motherwell Women’s Group exploring ideas for use.
NLC :
• Gaelic team looking to develop translation of content for community use and events
• Care teams – looking to establish a timetable of regular sessions that they can use with clients
• Regeneration teams looking at ways in which to develop content for public consultations / meetings with colleagues to show visual plans
for buildings and spaces
Schools :
Glencairn Primary: awaiting information regarding topics in order to timetable a series of visits for classes throughout year.
Expression of interest from HT at Muir Street
Partners in Play  (Welcome to Partners in Play - Partners in Play)
Charity who offer support and information to families of children and young people with disabilities have identified a number of their young
adult clients who would benefit from use of the room with their families and/or carers. Some of these clients are non-verbal.
Currently trying to timetable a schedule of visits 
Page 169 of 186

Page 170

Hope for Autism
Looking to explore possible development with their Scotrail link person involved too
BT / Immersive
Have requested another site visit for their clients to see working space and explore content as part of their development process.
Church group 
• St Mary’s Guild are scheduled to visit on November 11th 
NOTES :
Activities over summer in particular were limited by staff vacancies and the delivery of other Robotics summer activities.
Training – new DA receiving training on room and content development
Agreed to explore with Librarian and Supervisors ways in which library assistants can receive training on controlling content in room. This
would allow them to be involved in sessions and thus increase capacity in available appointment times. This is the only way we can see to be
able to look to accommodate requests from NLC Care teams, Partners in Play etc for regular usage by those with additional learning needs. 
Page 170 of 186

Page 171

North Lanarkshire Council
Report
Communities Committee
Does this report require to be approved? ☒ Yes   ☐ No
Ref   AA/LJ Date 28/10/24
Democracy Matters 2    
From  Archie Aitken, Chief Officer (Legal and Democratic)  
E-mail AitkenA@northlan.gov.uk Telephone 07939 280102 
Executive Summary 
In 2017, the Scottish Government and COSLA launched the Local Governance Review to
ensure Scotland’s diverse communities and different places have greater control and influence
over decisions that affect them most. 
To aid the review process, during 2018 Scottish Government launched the Democracy Matters
engagement process.  A second phase launched in August 2023 with the intention that it would
last for a period of six months.  The outcome report was published in late September 2024. 
This report provides an overview of the outcomes of the Democracy Matters 2 engagement
which sought to gain a deeper understanding and facilitate conversations around future
governance arrangements for the public sector and decision-making bodies.   
A summary of the emerging themes from the one hundred and sixty-six responses is contained
herein as well as a number of next steps.  Overall, the key message was that whilst there is
support for greater community-decision making in Scotland, it is highlighted that multiple
considerations need to be addressed to ensure a new layer of decision-making could work
effectively. 
Further developments from Democracy Matters 2 will be incorporated within the Programme
of Work to 2028 with future reports to the Communities Committee encompassing such areas
from the One Service Programme Board which are linked to the Council’s Ambition 19: Improve
engagement with communities and develop their capacity to help themselves. 
Recommendations
It is recommended that the Communities Committee: 
(1) Acknowledge the contents of this report; 
(2) Acknowledge the themes emerging from the Democracy Matters 2 consultation
(3) Endorse the next steps outlined herein, including the submission of this report to the
Strategic Leadership Board and Community Boards thereafter. 
Item 9
Page 171 of 186

Page 172

1. Background 
1.1. In 2018, Scottish Government advised of the intent to consult with communities, as part
of their ongoing Local Governance Review.  The aim of this wider Review was to look
across all of Scotland’s public services to consider how power, responsibility and
resources should be shared across national and local government and with different
communities. 
1.2. That initial conversation, Democracy Matters, encouraged over 4,000 individual
responses with feedback being gathered on a number of broad questions relating to
communities: 
• Would they like to be involved in making decisions about their community?
• If they would like their community to have more control over some decisions and what
these might cover?
• The different types and sizes of communities that would make the most sense when taking
decisions about their future?
• What needs to change for communities to have more power? 
1.3. Approximately forty public sector partners also submitted feedback to various aspects of
the consultation. 
1.4. The second phase deliberation on the future of community decision-making, Democracy
Matters 2, was launched by the Minister for Community Wealth and Public Finance, the
Minister for Local Government, Empowerment and Planning and the COSLA Presidential
Team in August 2023 and ran for a period of six months through multiple engagement
channels. 
1.5. Financial support, circa £300, was made available for community organisations to help
support venue hire, catering, creche facilities and transport with the aim of helping
communities of all backgrounds to join the conversation. 
1.6. Democracy Matters engagement is recognised as an important part of the Local
Governance Review with the aim of helping to deliver community, fiscal and functional
empowerment for Scotland’s different places and diverse communities of interest and
place 
2. Report 
2.1 Democracy Matters 2 sought to generate deeper learning by engaging with communities
using a specific set of questions (Appendix 1) to consider what different government
arrangements could be like in different places.   
2.2 The questions looked across all public services and the roles that communities might
play in their design and delivery to improve local people’s lives.  Engagement was open
to everyone across Scotland and communities were encouraged to discuss and respond 
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement (19) Improve engagement with communities and develop their
capacity to help themselves
Programme of
Work One Service
Page 172 of 186

Page 173

to the questions with their families, friends and neighbours to understand different
perspectives. 
2.3 In total Democracy Matters 2 received 166 unique responses with the vast majority, 159,
submitted directly to the consultation hub or Scottish Government.  Of these: 
• 83 responses arose from conversations within communities 
• 46 organisations submitted their views
• 30 were sent by individuals who responded directly to the consultation 
2.4 The final 7 responses were from facilitated conversations. 
2.5 A response on behalf of the North Lanarkshire Partnership was prepared and submitted
by the due date, this was signed off by the Strategic Leadership Board at their meeting
in February 2024 Appendix Two.  However, further analysis of the information contained
within the Democracy Matters 2 report suggests that there was no further representation
from North Lanarkshire in either the community conversations nor facilitated events. 
Analysis and Key Findings 
2.6 Analysis to understand the full range of views expressed was carried out by a 3rd party
organisation, The Lines Between.  This was to ensure that a robust, independent
analysis of the responses to the public consultation was provided. 
2.7 The report itself Democracy Matters 2 Analysis Responses provides a thematic analysis
and these have been identified as follows: 
2.7.1 Powers
There was a clear desire amongst participants to have a greater say in community
decision-making and to have resources which can be directed independently without
ringfencing. 
A range of services for the involvement of communities included – transport and
environmental services including running transport services, repairing roads and
maintaining green spaces.  Levels of desire for community involvement varied. 
2.7.2 Representation 
Strong support among participants for community decision-making to be representative
of the whole community and that there should be a concerted effort to include people
with protected characteristics.  Involving young people was also a frequent suggestion. 
2.7.3 Participation 
Seeing the impact of community governance leading to positive change was a key
message and a way of encouraging participation in community decision-making.  Further
suggestions focussed on support for attendees through cash payments, paid childcare,
vouchers or paid time off to volunteer. 
2.7.4 Boundaries 
There was little consensus about boundaries for any new decision-making
arrangements.  There was, however, recognition that the definition of “local” can vary
considerably. 
2.7.5 Accountability and Standards 
Many respondents suggested that community decision-making bodies could be held
accountable by ensuring that communications are clear and that future community action
Page 173 of 186

Page 174

plans feature SMART (Specific, Measurable, Relevant and Timebound) objectives. 
Support for frameworks covering clarity of purpose, accountability as well as regulatory
and legal issues to ensure trust were suggested. 
Developing a community charter was supported which would be agreed by the public,
community decision-making bodies and other community groups.   
2.7.6 Funding Community decision-making 
Whilst there is support for community decision-making bodies to have direct funding from
national and local government some participants expressed scepticism as to whether or
not this was a realistic ask. A funding model was suggested to allow communities to take
a long-term view and plan effectively, however, others advocated that funding should
remain with local authorities to prevent disagreement within communities on how the
money is spent. 
2.7.7 Support to develop skills and knowledge 
A need for support and training to enable community decision-making bodies to make
important decisions, take on more responsibilities and deliver effective services was
highlighted. 
Participants also suggested that such bodies should be able to employ staff to take on
responsibilities such as administration, financial management and HR and legal
functions.  This was in addition to such roles as youth work.  It was felt essential that as
communities take on more responsibility roles carried out by paid staff should not be
transferred to volunteers. 
There was a call for more community development professionals to act as critical bridges
between institutions and communities. 
2.7.8 Implications for public bodies 
There was recognition that the role of public bodies would change and perhaps allow
them to take a more strategic approach to their future responsibilities.  It was noted that
there needed to be a clearly thought-out role for Community Councils in any future
governance arrangements. 
Key Findings 
2.8 In summary, the main findings from the discussions and consultations responses were: 
• Arrangements for community decision-making should be flexible and responsive to
the needs of the community and place.
• Decision-making bodies should be a platform to influence decisions and shape
services in a structured and meaningful way, and be representative of their
community, including groups with protected characteristics.
• Ensuring accountability and trust was seen as critical.
• Clear participative mechanisms should be in place to make decisions with various
approaches used to maximise accessibility and encourage participation.
• A decision-making body should have a sustainable budget that can be directed
independently.
• Community capacity building and skills development will be important to enabling
communities to deliver more. 
Page 174 of 186

Page 175

Next Steps 
2.9 A number of next steps will be developed including: 
• Oversight of the direction of travel and the emerging approach from Scottish
Government will be maintained through the Programme of Work to 2028 One
Service Programme Board.
• Any course of action deemed appropriate by Scottish Government will be developed
in line with Community Wealth Building requirements and is the subject of a separate
report to the Enterprise and Fair Work Committee.
• This report, if approved, will be submitted to the Strategic Leadership Board on 6
December and thereafter to Community Boards. 
3. Measures of success 
3.1  Success with be measured through the implementation of the direction of travel outlined
in due course by Scottish Government as part of the Local Governance Review.       
4. Supporting documentation
4.1 Appendix 1   Democracy Matters 2 – Consultation Questions
4.2   Appendix 2 Democracy Matters 2 – Consultation Response – North Lanarkshire  
Partnership 
Archie Aitken   
Chief Officer (Legal and Democratic) 
Page 175 of 186

Page 176

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the
Public Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-
community/equalities/equality-and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☒
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with
People Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters,
statutory considerations (including employment law considerations), or new
legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with
Legal and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of
personal data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to
the data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out
and e-mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
Page 176 of 186

Page 177

5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology,
digital transformation, service redesign / business change processes, data
management, or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒     
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on
any environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential
impacts, highlighting where the risk(s) are assessed and recorded (e.g.
Corporate or Service or Project Risk Registers), and how they are
managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant
Duty (i.e. does it relate to healthcare, housing, or education services for in-
Service or ex-Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been
made to ensure there has been appropriate consideration of the particular
needs of the Armed Forces community to make sure that they do not face
disadvantage compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity,
service delivery, policy, or plan that has an impact on children and young
people up to the age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that
has been made to ensure there has been appropriate consideration of the
Page 177 of 186

Page 178

relevant Articles from the United Nations Convention on the Rights of the
Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA)
been carried out? 
Yes ☐ No ☐ 
Page 178 of 186

Page 179

Democracy Matters 2 – Consultation Questions           Appendix 1 
The following 16 open questions were included in the Democracy Matters Phase 2
consultation paper. 
Q1.  How could your community use these types of powers to achieve its
ambitions, now and into the future? 
Q2.  What other powers should be added, and are there some which should be
retained by existing decision-makers? 
Q3.  When thinking about who might be part of new decision-making bodies, what
are the best ways to ensure they truly reflect their communities and enhance
equality? 
Q4.  Thinking about your own community, what groups would you like to see
represented through other selection methods, and what should these methods
be? 
Q5.  What would the role of local elected representatives be, and what would
incentivise other people to take on/be part of decision-making? 
Q6.  What do you think are the best ways to ensure new decision-making bodies
are accountable to their community? 
Q7.  Are community events a good way to involve local people in scrutinising
progress and setting future direction? 
Q8.  What other mechanisms would help achieve high levels of community
participation in local decision-making processes? 
Q9.  What else should this process include to provide new community decision-
making bodies with a strong locally agreed mandate? 
Q10.  Are there ways to ensure new bodies are still wanted – for example by making
them time-bound and subject to renewal ballots? 
Q11. How do you think community decision-making bodies should be resourced? 
Q.12.  Are these the right set of standards to provide reassurance that new 
community decision-making bodies will be effective and treat everyone with
dignity and respect? 
Q13.  How could a charter be designed to best ensure a positive relationship 
between community decision-makers and their partners in national and local
government and the wider public sector? 
Q14.  What types of support might communities need to build capacity, and how 
could this change the role of councils and public sector organisations? 
Page 179 of 186

Page 180

Q15.  Are there specific additional powers and resources which would help public
sector organisations to work effectively in partnership with new community
decision- making bodies? 
Q16.  Thank you for considering these questions. When sending us your views,
please also tell us about anything else you think is important for us to know at
this stage. 
Questions used in facilitated conversations 
The seven facilitated conversations and several of the community conversations held
by participants used a shorter version of the questionnaire. This focused on six wider
themes encompassing the consultation questions. 
Q1:  What powers do communities need to take democratic action? 
Q2:  How would people be selected, and how can people best reflect their 
communities? 
Q3: How can we make sure any new structures are accountable to the community? 
Q4: How can the wider community participate in decision-making? 
Q5: What resources and standards are required for democratic involvement? 
Q6: How can we share and grow skills and knowledge for local democracy? 
Page 180 of 186

Page 181

Appendix 2 
Our Ref:  SD/LJ/JL 
Your Ref:  
Contact:  Linda Johnston 
Tel:  07939 280883  
E-mail:  johnstonl@northlan.gov.uk  
Date:  26 February 2024 
Community Empowerment, Reform and Governance Division 
Scottish Government 
Area 3F North  
Victoria Quay 
Edinburgh 
EH6 6QQ 
Dear Sir/Madam 
Local Governance Review – Democracy Matters 2 Consultation 
I refer to the ‘Democracy Matters 2’ consultation currently underway by the Scottish
Government and CoSLA. 
North Lanarkshire Community Planning Partnership’s Strategic Leadership Board has kept
abreast of the progress of Democracy Matters 2 and encouraged community and voluntary
organisations and local people to participate. While the consultation materials and
‘community conversations’ are rightly targeted at local communities, we would like to provide
some feedback, observations and suggestions for further engagement. 
Place Based 
North Lanarkshire Partnership has previously identified community empowerment and the
development of Community Hubs as strategic priorities. Through North Lanarkshire Council’s
Community Hubs, partner agencies, including the community and voluntary sector, are
working jointly with local communities and individual families in designing and developing
services and whole system approaches that address what matters most to local people at
each stage in their lives. We have developed a Memorandum of Understanding amongst
partners to facilitate and support their access to the partnership zones, bookable spaces and
amenities available in the Community Hubs and this helps to foster a culture and
commitment to collaboration. Local Outcome Improvement Plans for each of our 9
communities of place provide a partnership focus for place-based action with communities
around jointly agreed priorities. The supporting partnership delivery mechanisms provide a
structure for co design and delivery of the council and partnership ambitions.    
Participatory Democracy 
Page 181 of 186

Page 182

Community Boards are our key delivery vehicle for community empowerment and
participatory democracy. The network of nine Community Boards encourages local
involvement in identifying and agreeing local priorities and service design with decision
making through the Local Development Programme and Participatory Budgeting, plus
consultation and engagement events. At a strategic level, Community Boards are
responsible for ensuring that the shared ambitions in The Plan for North Lanarkshire are
implemented locally, while at a community level, each Board has developed its own Local
Outcome Improvement Plan (LOIP) that sets out the locally determined priorities and actions.
Local Partnership Teams, whose membership comprises officers with a geographical or
thematic responsibility, support the Community Boards and drive and embed delivery of the
LOIPs across the Community Planning Partnership and ensure effective monitoring and
management of progress. 
Community Solutions provides a further example of place-based decision making.
Established in 2013, Community Solutions is a partnership between: University Health and
Social Care North Lanarkshire; Voluntary Action North Lanarkshire; and the community and
voluntary sector. Six Locality Consortia, with membership from community and voluntary
sector organisations and representatives from the council and NHS are responsible for the
co-production of an “Improving Lives Locality Development Plan”, informed by residents’ and
service users’ views and priorities. Delivery of this plan is supported by: 
• collective management of an “Improving Lives Local Activity Fund”, providing
small grants to community and voluntary sector organisations to support delivery of
the agreed plan; and, 
• collaboration on community and voluntary sector capacity building to
strengthen their ability to support local people.    
The Locality Fund is supplemented by further thematic funds awarded to community and
voluntary organisations to provide support on issues such as mental health and wellbeing;
carers’ support; and provision of community support following discharge from hospital.
University Health and Social Care North Lanarkshire provides recurrent, annual funding for
the programme at around £1.2 million, supplemented by additional fixed-term funding from
Health and Social Care and other sources.    
Representation 
The Community Boards have formal Terms of Reference and membership includes
organisations that are representative of the local community. It is important that the
membership clause within the Terms of Reference for any community decision-making body
makes provision for a wide range of representation and reflects the demographic profile,
diversity and needs of the local community. As such representation should include
communities of interest as well as geographically based organisations and representation by
groups that support and promote equalities and inclusion – for example: disabled people;
people living with long term conditions and challenges relating to their health; people from
the LGBTQIA+ community; people from Black and Minority Ethnic communities; and other
people who may be traditionally under-represented within the local area. Potential barriers to
engagement, such as transport to attend in-person meetings; carers’ needs and
responsibilities; language and accessibility needs; and digital skills, connectivity and access
to devices should be identified and addressed, with support provided as required to ensure
maximum participation.    
Through North Lanarkshire Council’s Equalities Board work is underway to examine barriers
to participation for equalities groups and to establish a baseline of information to identify
improvement actions aimed at increasing participation.  Thereafter awareness raising and
development work will be delivered through Community Boards to identify and agree
Page 182 of 186

Page 183

improvement actions. A North Lanarkshire Partnership Lead Officers’ Group, established in
response to research jointly undertaken by the council with Heriot Watt University and the
University of West of Scotland, is examining the lived experiences of people from Black and
Minority Ethnic communities to address barriers and unmet needs as well as supporting the
actions above to increase participation.    
Accountability and Transparency 
Accountability and transparency are key to the success of any community decision-making
model. As such, the Terms of Reference must clearly articulate the objectives of the
community decision-making body and provide clarity and a universally shared understanding
of the powers that rest with the decision-making body. The expectations and responsibilities
placed on representatives should be widely understood to avoid misunderstanding and
minimise the potential risk of conflict and dissatisfaction or disillusionment in the process. 
Training    
It is essential that local representatives serving on community decision-making bodies are
confident in their roles and equipped with the knowledge and skills to undertake their
responsibilities, including reporting and being accountable to the communities or
organisations that they represent. Similarly, local representatives should have the skills and
capacity to enable them to consider and take decisions that will benefit their area and
improve outcomes. 
North Lanarkshire has developed an online training and development portal aimed at
Community Board and Local Partnership Team members. Informed by training needs’
analysis, with content developed by North Lanarkshire Council’s People Resources and
Libraries Teams, the portal hosts a wide range of modules including: Participatory Budgeting;
Community Planning Structures and partners; being an effective chairperson; Your role on
the Community Board; Community Asset Transfer and Participation Requests. 
Culture Change 
Training, empowering staff and creating a culture amongst and within individual partner
organisations that values and actively supports community empowerment and decision
making is also critical. NHS Lanarkshire has established a Lived Experience Advisory Panel
to strengthen community informed research and participation in its health inequalities
programme. Engagement between health practitioners, policy advisers and the Lived
Experience Advisory Panel aims to develop models of working that encourage successful
interfacing between community assets and better integrated health and social care systems. 
North Lanarkshire Partnership is in the process of finalising the Implementation Plan to
support delivery of our ‘CommUnity Agreement’. Developed over the past two years, through
an Appreciative Inquiry approach that involved 500+ participants including the community
and voluntary sector, elected members and partnership staff, the CommUnity Agreement
sets out shared values and approaches to empowering and investing in local communities to
support improved wellbeing, equality and sustainability. It is designed to enhance trust and
joint working between local communities, voluntary organisations and partners with a
combined focus on improving the wellbeing of North Lanarkshire’s communities and people.
Partners have already adopted the CommUnity Agreement and the implementation stages
require individual agencies to cascade the principles and approaches within their own
organisations to ensure collective ownership, awareness and delivery. 
Page 183 of 186

Page 184

Communications 
All communications between statutory bodies, partners and the community decision-making
body must be straightforward, accessible and inclusive. This should also be in place for
communications between the community decision-making body and the communities it
represents. Communications should be published digitally and/or in formats that best meet
the needs of targeted audiences. Honest conversations on resources, priorities and any
matters where there is limited scope, or very specific parameters on how services are
developed and delivered, are also essential. 
Evaluation and Review 
Structured and transparent review arrangements, with the purpose of the review, process
and reporting arrangements shared and agreed locally, can help to instil trust and ensure
that the participatory democracy arrangements are effective and achieving their intended
benefits in terms of increased engagement, participation and local decision making.
Evaluation and review of effectiveness should examine representation, wider engagement,
decision-making, outcomes and the types and levels of support provided.    
Strategic Direction and Subsidiarity 
Achieving the effective balance between strategic direction, that is determined corporately or
at an authority wide level, and local community planning can be extremely powerful. At an
authority wide level, public sector bodies set the strategic priorities to address inequality,
poverty or disadvantage and ensure fairness and equity across the wider population. They
can use their scale and influence to excellent effect to promote prosperity and inclusive
growth for all. Local elected members, as the only locally democratically elected body in each
authority area, are key to ensuring the principles of subsidiarity and local self-determination
and are able to balance representing the views and needs of their constituents with
developing wider strategic priorities and resources to benefit the local authority area and the
people and communities served. 
Conclusion 
Other community planning partnerships will have similar place-based decision-making
arrangements to those described above. There is an opportunity to learn from these in terms
of representation, encouraging people to participate and communicating the work of the
community decision-making body. To this end, targeted engagement with community
planning partnerships on existing community decision-making and participative processes
that enable local people to be involved in the design, delivery, review and implementation of
services should be considered. 
I trust this information is useful and if you have any questions or would like to explore further
any of the examples or points made by North Lanarkshire Community Planning Partnership
please contact North Lanarkshire Council’s Business Strategy Manager at the address
above. 
Yours faithfully 
Page 184 of 186

Page 185

Stephen Dolan 
Chair on behalf of North Lanarkshire Partnership Strategic Leadership Board 
Page 185 of 186

Page 186

Page 186 of 186