North Lanarkshire Council
Report
Audit and Scrutiny Panel
Does this report require to be approved? ☐ Yes   ☒ No
Ref:  KA/ASP/2023/Feb  Date 16/02/23
Risk Management update
From  Ken Adamson, Chief Officer - Audit & Risk
E-mail adamsonk@northlan.gov.uk Telephone 07939 280602 
Executive Summary
The Council continues to operate within a complex and challenging environment reflected in
corporate and service risks registers.  This report provides the Panel with a brief update on
key risk management developments since the most recent update report to the Panel in
November 2022.
As well as providing an update on the Council’s corporate risk register and highlighting a
selection of the more significant issues which are of current focus from a risk perspective, the
report also provides an update on recent changes in internal governance arrangements and
the expected impacts on how risk issues are managed and monitored by senior management. 
The report also confirms that the planned review of the Council’s Risk Management Strategy
is now complete and a report setting out proposed changes will be submitted for approval to
the Policy and Strategy meeting due to be held on 16 March 2023.
Strategically significant risks of current focus remain largely unchanged from the last update
and include responding to the ongoing challenges presented by current inflationary pressures
and future levels of funding for local government.  The Council is also fully engaged with
ongoing attempts to assess and respond effectively to the likely significant impacts of the
National Care Service draft legislation and associated guidance on service users, staff and the
Council more generally.  How the Council is responding to this latter issue is the subject of a
separate report to the Panel.
Significant operational risks of current focus include work to ensure the resilience of the
Council’s home care service in light of ongoing pressures and increased challenges over the
winter period and ongoing work relating to staffing issues, including responding to industrial
action and to recruitment and retention challenges.  Finally, risk issues continue to be
addressed in relation to a number of significant projects and programmes of work. 
Recommendations
The Panel is asked to consider the contents of the report and to:
(1) note the current residual scores for those risks agreed for inclusion in the corporate risk
register for 2022-23 at Appendix 1;
(2) note the references to other topical risk issues highlighted in Section 2; and
(3) note the work ongoing to further strengthen and embed risk management arrangements. 
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement All ambition statements

Page 2

1. Background
1.1 The Council’s Risk Management Strategy requires that the corporate risk register is
refreshed on an annual basis; led by the Corporate Risk Team, working with the Risk
Management Corporate Working Group (RMCWG) on behalf of, and in consultation with,
the Corporate Management Team (CMT).  In addition, each Service is required to
maintain its own risk register in respect of the operational service risks within their areas
of responsibility.  CMT previously approved the 2022-23 corporate risk register as
outlined in the table at Appendix 1.
1.2 It is widely recognised that the environment within which the Council operates and
provides services is dynamic, and corporate and service risk registers must continually
evolve to keep pace with and accurately reflect, the ongoing challenges facing the
Council.
1.3 The current Risk Management Strategy sets out required frequencies for the ongoing
review by management of both Corporate and Service risks. 
2. Report
2.1 The corporate risk register approved for 2022-23 is at Appendix 1.  Risks contained
within the register have been subject to ongoing monitoring and review throughout the
year, with regular risk reporting to CMT and the Panel both on the overall register, and
with detail on individual risks being reported by relevant Risk Leads.
2.2 The definition of a corporate risk is ‘those risks which can impact the Council in
achieving its priorities and stated objectives and/or are more strategic in nature and
require corporate oversight.  For example, such risks may have the potential to impact
many Services, and/or can impact significantly on the Council in terms of financial costs
and reputational damage.  The Corporate Risk Register will reflect an amalgamated
position of Service-level risks and may also include significant Service-level risks which
have been escalated for attention at a strategic level.’ 
Update on the 2022-23 corporate risk register
2.3 Since the last update to the Panel, there have been no substantive changes to the risks
contained within the corporate risk register or the scores of those risks since the report
to the Panel in November 2022.  Additional issues currently being considered for
possible future inclusion in the corporate risk register include Black Start/Power
Resilience, Home Support service delivery and Home to School Transport.
2.4 Currently all bar three risks are classified as ‘live’ with completed risk documentation;
the two risks classified as ‘draft’ where relevant documentation is currently being
finalised are ‘Target Operating Model’ and ‘Improving Educational Outcomes’.  Both
risks are due to be finalised and to be able to be reported as live before the end of the
financial year.  The remaining risk, ‘Impact of National Care Service proposals’ is
documented but remains unscored and actively under review in light of ongoing
uncertainty and developments as the relevant legislative process proceeds.
2.5 Members will note at Appendix 1, that the overall corporate risk profile has changed
with a notable increase in the number of risks which now sit within the ‘High’ category
for residual risk rating.  This is to be expected because of the complex and challenging
environment in which the Council is operating, and the changing risk profile itself should
be a key consideration in the planning and decision-making activities of the Council.
2.6 Generally corporate risks are being reviewed within reasonable timescales, however
there can be occasions where they fall overdue and Risk Leads have been reminded
of the need to contact the Corporate Risk Team promptly when e-mail reminders are
received to advise that a risk is due its review.  The Corporate Risk team will then assist
in the facilitation and co-ordination of those reviews, and timely consideration will allow
risk review frequencies to be maintained aligned to risk rating, and avoid risks
becoming out of date, ensuring risks are current and reflective of the most current
position.

Page 3

2.7 It had previously been proposed, with effect from this committee cycle, to supplement
the Corporate/Strategic risk register information included in this report with, for the first
time, a summary of key Service risks from service risk registers.  However, work to do
so has identified a lack of consensus on how service risks might be selected for
reporting and a degree of inconsistency in the quality and content of Service risk
registers.  Consequently, key Service risks are not included in this report and the Risk
Management Corporate Working Group continues to explore with Service Risk
Champions how best to identify which Service risks will be reported to both CMT and
the Panel in future risk management update reports.  As part of this process, Services
have also been asked to review and ensure that risk registers are comprehensive, of
appropriate quality and up to date (and that this is reported to, and confirmed by,
Service Management Teams as part of their formal role as outlined below).
Governance arrangements - oversight of risk registers
2.8 Regular consideration by senior management of Service risks and Service risk registers
is expected, but how such consideration is undertaken has previously not been
prescribed as it was considered appropriate to ensure that how risks are considered is
aligned to and integrated within each Service areas own distinct management
arrangements.  All Services have been encouraged however to regularly review risk
registers for completeness and to ensure that Service risks are reported regularly to
Service management teams.  
2.9 Recent changes to internal governance arrangements at senior management level
within the Council have, however, provided an opportunity to strengthen and further
embed risk management and specific responsibilities in respect of risk have been
included in relevant terms of reference.  The Corporate Management Team (CMT) will
retain responsibility for oversight of corporate risks and ensuring that these are being
managed in accordance with the approved Risk Management Strategy.  Service
Management Team (SMT) meetings are now formally expected to regularly review and
monitor service risk registers ensuring that registers are complete and up-to-date, and
that new and emerging risks are identified, assessed and managed effectively and that
service risk registers are used to support management discussions and inform
decision-making.
2.10 The corporate risk team will be developing formal measures to review and report on
compliance in this aspect of the Council’s risk arrangements during 2023-24.  The
Corporate Risk team will continue to work with Corporate Risk Leads and Service Risk
Champions to ensure that risks registers continue to capture and reflect the current key
challenges facing the organisation.
Strategic and operational risks of current focus
2.11 Strategically significant risks of current focus include responding to the ongoing
challenges presented by current inflationary pressures and increased uncertainty over
future levels of funding for local government in light of wider developments in UK and
Scottish public sector finances.  These issues have been the subject of recent reports
to the Policy and Strategy Committee.
2.12 The Council is also fully engaged with wider policy developments which have the
potential to impact significantly on the Council and its corporate ambitions.  This
includes ongoing attempts to understand, assess and respond effectively to the likely
significant impacts on service users, staff and the Council more generally of the
National Care Service draft legislation and associated guidance.  Responding to the
outcomes arising from the current consultation by the Scottish Government on the
future of education in Scotland is also likely to be of increasing focus.  National
developments in both areas will continue to be kept under review and actioned as
required, with updates provided to relevant Committees at key development points.

Page 4

2.13 The National Care Service (Scotland) Bill proposals allows Scottish Ministers to transfer
social care responsibility from local authorities to a new national service.  Policy and
Strategy Committee were provided with a report in September 2022 which provided an
update on the then current position of the Bill.
2.14 In view of the significant and wide-ranging impact which the NCS proposals are likely
to have on the Council and the future delivery of support to individuals and families, the
Policy and Strategy Committee (in September 2022) approved the establishment of a
Member Officer Group to guide the council’s future engagement with the Bill process,
support planning and management of the potential impacts for the council, and ensure
the delivery of public services remain steadfast during what is expected to be a
significant period of change.
2.15 The Bill also has significant implications for the council in terms of the proposed transfer
on existing functions and staffing, the wider impact on service delivery and delivery of
The Plan for North Lanarkshire, and on the future functions of the council.  A separate
report from management outlines how the Council plans to ensure the ongoing
identification and effective management of associated risks and provide oversight in
relation to the operational impact on future council functions.
2.16 Operationally, the Council continues to manage a wide range of risks associated with
day-to-day service delivery and progressing projects and programmes of work. 
Significant operational risks of current focus currently include work underway to ensure
the resilience of the Council’s home care service in light of ongoing pressures and the
increased challenges facing the Service over the winter period and ongoing work
around responding in both the short and longer-term to current and future challenges
around the provision of school transport.  Staffing issues, including industrial action and
responding to recruitment and retention challenges, have also featured prominently in
recent months.  Finally, risk issues continue to be addressed in relation to a number of
significant projects and programmes of work including the Enterprise Contract, which
was the subject of a report to Policy and Strategy in December.
Review and updating of the Risk Management Strategy
2.17 The planned review of the existing Corporate Risk Management Strategy has now been
undertaken, with the proposed revised strategy being reported to the Policy and
Strategy Committee for approval in March 2023.  Full details of the planned changes
will be included in that report, but the Panel should note that the proposed changes to
the strategy are, overall, relatively minor and are designed to deliver incremental
improvements to what is assessed as an already sound strategic approach.
2.18 It is being proposed as part of the revised Corporate Risk Management Strategy that
there will be some focus on ‘fine-tuning' the risk scoring approach to ensure this
provides greater differentiation in ratings (and rationale for those ratings), that will
enable CMT and elected members to better distinguish areas that require more focus
particularly within the ‘High’ residual risk category.  More details on the impact of this
change (if approved) will be provided in the next update to the Panel. 
3. Measures of success
3.1 The corporate risk management team will continue to report quarterly to BMT and CMT
and the Audit and Scrutiny Panel providing an overview of key developments in risk
management and updating on progress in respect of planned improvements to the
Council’s risk management arrangements.

Page 5

3.2 The adequacy and effectiveness of the Council’s risk management arrangements will
be independently and regularly reviewed by Internal Audit, who will report directly on
the results of that work to the Audit and Scrutiny Panel.
3.3 Effective risk management arrangements assist the Council in achieving planned
outcomes and/or help the Council mitigate the impacts of adverse events. 
4. Supporting documentation 
Appendix 1: 2022-23 corporate risk register
Appendix 2:  Risk scoring matrix and descriptors 
Ken Adamson
Chief Officer - Audit and Risk

Page 6

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact because of the Public Sector
Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☐ No ☒
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal data?  
Yes ☐ No ☒
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If yes, please provide a summary of the key risks and potential impacts, highlighting
where the risk(s) are assessed and recorded (e.g. Corporate or Service or Project
Risk Registers), and how they are managed?
Effective risk management arrangements including the identification, assessment,
management and oversight of relevant risks will increase the likelihood of the Council
achieving its ambitions and plans by making it more likely that the Council will be able
to effectively mitigate potential threats to planned outcomes.  It also contributes to
effective management of risks relating to all service and operational areas.
5.10 Armed Forces Covenant Duty
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)?
Yes    ☐                No ☒

Page 7

Appendix 1: 2022-23 corporate risk register 
CORPORATE RISKS (Operational) Likelihood Impact Rating Evaluation
1. Information Governance – Data Migration 5 5 25 High
2. Information Governance & Information Security 5 4 20 High
3. ICT operational capability 4 4 16 High
4. Public Protection 4 4 16 High
5. Human Resources 4 4 16 High
6. Governance Leadership & Decision Making 4 4 16 High
7. Supply Chain Risk 4 4 16 High
8. Scottish Child Abuse Inquiry 4 4 16 High
9. Health and Safety 5 3 15 High
10. Business continuity planning 5 3 15 High
11. Terrorism 3 5 15 High
12. Procurement risk 3 4 12 Medium
13. Resilience planning 2 5 10 Medium
14. Serious organised crime, fraud and corruption  3 3 9 Medium
CORPORATE RISKS (Strategic) Likelihood Impact Rating Proximity
15. Tackling Poverty 5 4 20 High
16. Climate Change 4 4 16 High
17. Implementation of Economic Regeneration
Development Plan  3 5 15 High
18. Financial Sustainability 3 5 15 High
19. Enterprise Project 3 4 12 Medium
20. Managing strategic change  3 4 12 Medium
21. Digital and IT strategy 4 3  12 Medium
22. Engagement and consultation 3 3 9 Medium
23. Target Operating Model – (Ensuring resources
(workforce, digital and assets) and service delivery
are fully aligned to support the successful
implementation of the Council’s future operating
model. 
To be
confirmed
To be
confirmed
To be
confirmed
To be
confirmed
24. Impact of National Care Service To be
confirmed
To be
confirmed
To be
confirmed
To be
confirmed
25. Improving Educational Outcomes  To be
confirmed
To be
confirmed
To be
confirmed
To be
confirmed

Page 8

APPENDIX 2: LIKELIHOOD / IMPACT DESCRIPTORS AND RISK MATRIX
Likelihood Descriptors:
Score Probability of occurrence Description
5 Over 90% Almost certain to occur within 12 months
4 61-90% Likely to occur within 12 months
3 31-60% Possible that it may occur within 12 months
2 11 - 30% Unlikely to occur within 12 months 
1 10% or less Rare that it would occur within 12 months
Impact Descriptors:
Score
Description of impact
On Service
Objectives Financial On people On time to recover On reputation
5 Catastrophic
Unable to
function, inability
to fulfil
obligations
Severe financial
loss (over 25%
of budget)
Death
Serious – more than 2
years to recover to pre-
event position
Highly damaging,
severe loss of public
confidence
4 Major
Significant
impact on
service
objectives
Major financial
loss (between
10% and 25% of
budget)
Extensive injury,
major
permanent harm
Major – between 1 and
2 years to recover to
pre-event position
Major adverse publicity,
major loss of
confidence
3 Moderate
Moderate impact
on service
objectives
Significant
financial loss
(between 2.5%
and 10% of
budget)
Medical
treatment
required, semi-
permanent harm
up to one year
Considerable –
between 6 months to 1
year to recover to pre-
event position
Some adverse
publicity, legal
implications
2 Minor
Minor impact on
service
objectives
Moderate
financial loss
(between 1%
and 2.5% of
budget)
First aid
treatment, non-
permanent harm
up to 1 month
Some – 2 to 6 months
to recover to pre-event
position
Short-term public
embarrassment and no
damage to reputation
1 Insignificant
Minimal impact,
no service
disruption
Minimal loss (up
to 1% of budget)
No obvious
harm/injury
Minimal – up to 2
months to recover
No interest to the
media, internal only.
Risk Matrix:
Likelihood
5 - Almost certain 5 10 15 20 25
4 - Likely 4 8 12 16 20
3 - Possible 3 6 9 12 15
2 - Unlikely 2 4 6 8 10
1 - Rare 1 2 3 4 5 
1 - Insignificant 2 - Minor 3 - Moderate 4 - Major 5 - Catastrophic
Impact
Risk Rating
Insignificant
1-3
Low
4-6
Medium
8-12
High
15-25

Page 9