North Lanarkshire Council
Report
Audit and Scrutiny Panel 
Does this report require to be approved? ☐ Yes   ☒ No
Ref:  KH/LJ Date 16/02/23 
PO003.2: DigitalNL Quantifying and Reporting on Non-Financial
Benefits 
From  Katrina Hassell, Chief Officer (Business and Digital)  
E-mail HassellK@northlan.gov.uk Telephone    07903 096 121 
Executive Summary
The DigitalNL programme is subject to a series of audits with such aimed at providing levels
of assurance that the overall programme is progressing against predetermined targets, that
governance is robust and that benefits as outlined in the approved Full Business Case are
being realised. 
To date, the DigitalNL programme has been subject to four audits with each making a small
number of recommendations with regards suggested improvements.  On each occasion
management within Business and Digital have viewed the outcome of such reports and the
recommendations contained therein as valuable feedback for improving processes within
the overall programme. 
This report focusses on the recommendation made within the most recent internal audit
report for DigitalNL completed in November 2021 with regard to the identification,
calculation, monitoring and tracking of non-financial benefits.  This recommendation was
assessed with a residual risk rating of medium. 
The tools and techniques developed and utilised within the service for the DigitalNL
programme are highlighted as is the complexity of such in capturing and reporting on both
council-wide and service non-financial benefits in line with the already approved Year 4
Roadmap. 
The report highlights a number of next steps to be developed in order to finalise and fully
deploy the non-financial benefits element of the Benefits Tracker.
Recommendations
It is recommended that the Audit and Scrutiny Panel: 
(1) Recognise the development and implementation of a bespoke Benefits Tracker to
capture financial and non-financial benefits for the DigitalNL Programme
(2) Acknowledge the robust processes in place for capturing non-financial benefits
(3) Recognise the commitment to the continued development of non-financial benefits
through the deployment of the approved Year 4 Roadmap
(4) Support the next steps outlined in paragraph 2.23 of this report
Otherwise note the report.

Page 2

1. Background 
1.1 The DigitalNL Transformation Business Case (FBC) approved by Policy and Strategy
Committee in March 2019 highlighted that transformation had to go beyond council
walls and operations, with a whole place approach required to turn the Council’s Digital
Vision and The Plan for North Lanarkshire into reality.  Recognising the complexity of
change required to operational and customer facing infrastructure, IT services and
culture, this FBC proposed two complementary and interdependent programmes (a)
Digital Economy and Place and (b) Digital Council Transformation (DigitalNL), be
progressed to enable the Council to use technological advancement such as ultra-fast
broadband, artificial intelligence and next generation smart devices to redesign
services around the needs of communities and businesses.  Whilst non-financial
benefits were identified as the key drivers of these complementary programmes, our
Digital Business partner’s experience of similar transformations indicted the proposed
digital solution deployments could also be financially beneficial to the Council. 
1.2 The DigitalNL aspect of the Council’s Transformation Programme focussed on three
distinct areas: - 
• Digital Workplace (M365) to improve collaboration
• Cloud Storage Solution to create agility and efficiencies
• Digital Platform (Customer Relationship Management) transforming how the
council interacts with its citizens. 
1.3 However, as Members are aware aspirational programmes such as DigitalNL and
Smart NL slowed considerably during 2020-21 and 2021-22 as the Covid-19 pandemic
took hold. 
1.4 As part of the Council’s recovery planning, and the governance arrangements in place
for the DigitalNL Programme, during 2021-22 and 2022/23, a series of root and branch
reviews of the programme focussed on: 
• The planning of future years’ business change, service design and technology
build
• Alignment of associated capital and revenue expenditure
• Envisaged financial and non-financial benefits 
1.5 At its meeting of 1 December 2022 the Policy and Strategy Committee received a
report “PoW003.2 DigitalNL – Next Steps” from the Chief Executive which provided a
review of the programme deliverables achieved to date against those outlined in the
FBC approved by Members in March 2019.  It outlined what had gone well alongside
the challenges encountered in achieving financial and non-financial benefits to date. 
1.6 Since its inception the DigitalNL Programme, including that of the FBC, has been
subject to a series of internal audits with the aim of providing assurance on the
adequacy and effectiveness of the arrangements in managing the programme.
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (18) Ensure our digital transformation is responsive to all people's
needs and enable access to the services they need

Page 3

1.7 The fourth such audit was reported to Audit and Scrutiny Panel on 9 December 2021
and recognised that the governance arrangements for the Programme appeared to
be adequate.  However, the audit also highlighted that given the programme’s
performance to date in delivering expected savings, the compression of the
programme as a result of Covid and other impacts and the challenges presented by
delivering many of the remaining individual projects/workstreams it was considered
that uncertainty remained over the ability of the programme to fully deliver future
expected savings”.
1.8 The report further recognised the work of Business and Digital in devising a Benefits
Tracker, with Internal Audit advising that they were pleased to note that re-baselined
financial benefits were being tracked. 
1.9 However, there was recognition that non-financial benefits required to be adequately
tracked and monitored to allow the Council to demonstrate the achievement of the
objectives of the programme. As a result, the report recommended that “the non-
financial benefits tracker is finalised and approved with non-financial benefits
thereafter identified, calculated, tracked and monitored for all workstreams.” 
1.10 Updates on progress with the development of the non-financial benefits element of
the Benefits Tracker were provided to the Audit and Scrutiny Panel in September and
November 2022 respectively. Having considered the current position and associated
Internal Audit commentary on 24 November 2022, the Panel requested senior
management provide a report for their next meeting which details plans to finalise the
non-financial benefits element of the Benefits Tracker. This report satisfies that
request, but also takes the opportunity to remind members of the progress and
approvals realised to date. 
2. Report 
2.1 It was highlighted in the FBC in March 2019 that non-financial benefits, including
process efficiency, upskilling of the workforce and development of data as a strategic
asset were the key drivers for the DigitalNL Programme.  However, during financial
year 2019-20, with the Council moving towards a challenging 3-year budget, the
emphasis on financial benefits became the prominent driver. 
2.2 Notwithstanding this, initial design concept work for the Council’s benefits
management arrangements, and specifically processes for identifying non-financial
benefits, continued with support from our Business Partner, PwC, moving into the
development phase during early 2020. 
2.3 The intended aim behind such a development was to integrate benefits management
as the way in which the council would know that the planned change(s) has
happened, is fully sustainable and that the benefits identified are being realised. By
proactively managing this approach, the Council would ensure that anticipated
improvements and returns from investment are realised. 
2.4 From the outset the design documents set out five key pillars to ensure the design
and delivery of the council’s future state with benefits at its core, would incorporate
the following:   
(i) Be as straightforward and as easy to understand as possible to ensure
adherence to processes.

Page 4

(ii) Allow tracking and assessment of all identified benefits as part of the future
state design. 
(iii) Form a key facet of programme planning to ensure that a focus on benefits
drives all activities and decision-making. 
(iv) Assign ownership of benefits to ensure there is always a responsible person
accountable for successful delivery. 
(v) Include robust reporting arrangements to ensure the relevant Boards and
Committees receive an update regularly. 
2.5 The programme consists of three strategic strands with benefits, once identified,
linked to one or more of these strands thus ensuring the Council delivers the change
and demonstrates the impact of improvement. 
(*including transactions, workforce, analytics, and insights) 
2.6 An update on the non-financial benefits for all three strands was presented within the
“PoW:003.2 DigitalNL - Year 4 Roadmap report submitted to Policy and Strategy
Committee on 29 September 2022.  Additional information on the Digital Economy
benefits was submitted to Policy and Strategy Committee on 1 December 2022 with a
further update on Digital Communities being presented to the Communities
Committee on 6 February 2023.   
2.7 Focusing now on the Digital Council, the finalised “Benefits Realisation Management
Approach” provides the framework by which financial and non-financial benefits for the
Digital Council are realised.  This was approved at the DigitalNL Delivery Board in May
2020 and thereafter updated and approved in February 2021 to incorporate the ‘Design
to Live’ stages of Business Change. 
2.8 Following approval at the DigitalNL Delivery Board the “Benefits Realisation
Management Approach” was issued to the Corporate and Operational Management
Teams to cascade throughout the organisation, thereby increasing council-wide
awareness of the process and templates used for capturing benefits arising from

Page 5

redesign activities.  The Business Change Team issue this documentation as part of
the service design to live process and carry out workshops with senior service-based
staff to communicate transformation processes including those required to identify,
calculate, track, and monitor financial and non-financial benefits.   
2.9 Following approval and cascade of the benefits realisation approaches the scope and
design of the tool required to monitor financial and non-financial benefits commenced
with phase one of the Benefits Tracker – identifying and monitoring financial benefits
(a budget tracker) - being approved at the DigitalNL Delivery Board in February 2021.   
2.10 As has been reported previously to the former Transformation and Digitisation
Committee, following implementation of the Budget Tracker, and with the focus on the
financial position as detailed in 2.1 above, resources were targeted towards the re-
basing of the financial benefits defined in the FBC.   
2.11 Phase Two, the design of the non-financial tracker, took place during 2021/22,
capturing input and feedback from the Business Change Team and ensuring the
strategic links to The Plan for North Lanarkshire and associated Programme of Work
continue.  The outline scope of the non-financial element of the Benefits Tracker was
approved at the DigitalNL Delivery Board in February 2022.  This summarises the
benefits/achievements categorised into one of the three digital strands outlined in 2.5
above. 
2.12 Non-financial benefits for the Digital Council comprising council and service-wide
benefits are documented in BR08 Benefit Summary (Appendix One).   A condensed
version of this benefits summary was included in the aforementioned report to Policy
and Strategy Committee in September 2022. 
Non-financial Benefits – Digital Council 
2.13 Within the benefits approach a “Benefit” is defined as “The measurable improvement
resulting from an outcome perceived as an advantage by one or more stakeholders,
which contributes towards one or more organisational objectives” 
This ensures that all benefits:   
• are measurable 
• show the improvement resulting from the change 
• create links between tangible outputs and strategic goals 
• ensure alignment of effort, resources, and investment towards achieving
organisational objectives 
2.14 In order to ensure alignment with The Plan for North Lanarkshire there are five areas
of impact to categorise benefits. These are shown in Table 1 overleaf.

Page 6

Primary Area  Explanation  Impact  Ambition  Statement 
Financial  Saving money or
reducing expenditure 
21  Continue to identify and
access opportunities to
leverage additional resources
to support our ambitions 
Process  Improving efficiency
and promoting channel
shift 
24  Review and design services
around people, communities,
and shared resources 
Customer  Enhancing user
experience and
satisfaction 
19  Improve engagement with
communities and develop their
capacity to help themselves 
Employee  Investing in employees
by providing training,
tools, and support 
25  Build a workforce for the
future capable of delivering on
our priorities and shared
ambition 
Environmental  Reducing the councils
carbon footprint by
producing fewer
emissions etc. 
22  Facilitate a North Lanarkshire
wide approach to asset
rationalisation, including with
communities and partners 
Table 1 – Benefit Categories 
The Six Stage Process 
2.15 In order to identify such benefits, a clear six-stage process is in place: 
Define Success  develops a clear understanding of why the change
programme is required 
Identify and quantify considers the approach to identifying benefits
(including discovery workshops, benefits mapping
and ‘customer insight’) as well as forecasting the
scale of the improvement anticipated and
identification of links to The Plan for North
Lanarkshire 
Value and appraise models financial benefits in monetary terms; and
assesses value, volume, or transactional measure
for non-financial benefits 
Plan considers the approach to validating and
prioritising benefits, selecting benefits measures,
engagement with stakeholders, identifying roles
and responsibilities, and pulling all document
outputs together 
Realise covers tracking, reporting, corrective action,
effective approaches to stakeholder management
and achieving change 
Review considers the importance of review as a basis for
learning and continuous improvement before,
during and after change 
2.16 To be successful in the realisation of benefits, the identification of a defined set of
objectives, benefits, and impact is an essential start.   
Step 1 – identify the original objectives from the FBC – this is the first reference point

Page 7

Step 2 – identify and quantify the benefits captured from engagement activity
(Opportunity Workshops, Playback Sessions and 1:1’s with Service Management
Teams) 
Step 3 – quantify the impact if the change programme is implemented, ensuring any
benefit identified have a direct link to The Plan for North Lanarkshire 
Step 4 – use the above information to complete the relevant supporting documents
including the Benefit Profile and Map. 
Identification of Non-Financial Benefits 
2.17 At the outset of the DigitalNL programme early indicators of non-financial benefits were
captured via a benefits log and used as a reference to design benefit maps for each of
the service areas within the FBC.  At that time Transformation Opportunities were
translated into maps with each indicating the following: 
• Theme
• Opportunity
• Requirement (relating to process, technology, and people)
• New way of working
• Benefit linked to one or more of the primary areas of impact: -   
Process – reduction in front office costs   
Customer – improved customer satisfaction   
Employee – improved staff satisfaction   
Environmental – improving the councils carbon footprint 
2.18 Transformation opportunities were linked to associated themes and digital enablers. 
Digital Themes 
Digital Enablers 
2.19 Appendix Two provides an overview of the Waste Management Self-Service theme and
outlines the journey for online capabilities where customers can access online services
24/7 to pay for a service, book a service or report an issue.  The final benefits map for
Waste Services and that for Built Environment will be completed in January 2023.
Thereafter maps will be designed for each service area in line with the approved Year
4 Roadmap.

Page 8

2.20 With non-financial benefits having been reviewed for those Council and Service sprints
already complete, the updated BR08 Benefit Summary was considered at the Business
and Digital Delivery Board on 15 December 2022, with Board Members confirming such
sufficiently assures them that non-financial benefits are being tracked, monitored and
recorded in accordance with benefit maps. 
Non-Financial Benefits – Achievements to date 
2.21 With improved tools for communication and collaboration rolled-out across the
organisation through the M365 project, the first non-financial benefits were identified
through increased productivity, efficiency, and environmental sustainability. The
enablement of an agile, flexible, and modern workforce by the delivery of modern
technology has led to easier collaboration both internally and with external partners.  A
smoother hand-off between staff on business-critical documents are now evident along
with the ability to implement hybrid and home working without disruption to the working
day.  Further details are provided in BR08 - Digital Council Summary (Appendix Three)
which provides a detailed overview of the non-financial benefits currently being tracked. 
Category Activity Impact
Process Improvement –
leading to an efficiency saving
by reducing manual transaction-
based activities and adopting an
automated on-line solution
Customer Services Hub 
Business Intelligence Hub 
Robotic Process Automation
(RPA) 
M365 
File Management
Digital Self Service:  Transactions
designed in a way that they
require minimum effort from
customers and staff 
Real-time dashboards and
analytics allowing the Council to
make informed operational
decisions 
Automation of simple / rules-
based queries and tasks
removing time consuming low
value activities 
The ability for staff and partners
to collaborate. 
Staff are highly mobile and not
tied to council offices 
Information stored in line with
Corporate File Plan and retention
and disposal of information
managed with an electronic
records management tool
Improved Customer
Experience – by enabling the
service user to self-serve online
and receive automated
notifications enhancing the user
experience and digital skills
Customer Portal (Dynamics)
Website (Drupal) 
Internet of Things (IoT) –
Damp Monitors 
A digital customer interface that
enables customers to self-
manage, self-assess, and provide
a single point of access to
services 
Installation of damp monitor
sensors to automate reporting,
response and fixing of problems

Page 9

Category Activity Impact
Employee Development – by
providing training, tools, and
support, enhancing digital skills
and the workforce
M365 Rollout 
Customer Services Hub 
Digital Platform and Azure
Development Training 
ITIL Qualification 
On-line training suite developed
for M365 
Additional customer care training
for customer services staff 
Knowledge transfer and upskilling
of in-house developers and ICT
staff 
Introduction of ITIL training for ICT
and Business Change teams 
Environmental Sustainability
– a reduction in the Council’s
carbon footprint
Virtual Housing Repairs
Inspections 
Customer Portal 
Reduced travelling and increased
productivity 
A digital customer interface to –
reduce printing and postage costs 
Next Steps 
2.22 Full implementation of the Benefits Tracker remains a key objective and will be
supported through: 
• Maximising the use of the Digital Platform to achieve non-financial benefits
• Identifying, calculating, and tracking the impacts of non-financial benefits arising
from redesign activity detailed within the approved Year 4 Roadmap
• Focussing on recommendations from Internal Audit to satisfy any further
recommendations for improvement so identified. 
3. Measures of success 
3.1  Success will be evidenced through the realisation of non-financial benefits through the
approach outlined in the Benefits Realisation Management Approach 
3.2 Specific measures of success will be identified in the benefits log and maps associated
with the Year 4 Sprint Roadmap.   
4. Supporting documentation 
Appendix One – Combined Benefits Summary
Appendix Two –  Benefits Map – Waste Services
Appendix Three -  Non-financial Benefits – Digital Council 
Katrina Hassell
Chief Officer (Business and Digital)

Page 10

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☒ No ☐

Page 11

If Yes, please provide a brief summary of the impact? 
Business and Digital is responsible for the design, deployment and maintenance of
all ICT and digital assets required by the Council. It has approved revenue and
capital funding available to maintain supportable applications and transition Council
services towards increased self-service and community-focussed delivery.
Significant changes are envisaged regarding connectivity, IoT, software and
hardware, but all will be considered by the Council’s Enterprise Architecture
Governance Group (EAGG) as part of the overarching deployment process. 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
Business and Digital have a defined risk management strategy in place to capture,
assess and mitigate risks and issues.  The annual review was reported to the
Delivery Board on 12 December 2022 and provided clear integration between
corporate, service and programme risks. 
Within the risk register R81 – Failure to realise identified benefits within the
programme may lead to the programme not being able to deliver expected
capabilities and outcomes. 
DNL Programme Risk  Likelihood
   Impact  Rating Evaluation Last Review
Date  
Next Review
Date  
Failure to realise identified
benefits within the
programme may lead to the
programme not being able to
deliver on expected
capabilities and outcomes.
4 4      
16  
High   19/12/2022  16/01/2023
(reviewed
monthly) 
5.10 Armed Forces Covenant Duty

Page 12

Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 13

Appendix One
Combined Benefits Summary

Page 14

Appendix Two

Page 15

Appendix Three