North Lanarkshire Council
Report
Audit and Scrutiny Panel 
☐approval ☒noting Ref KA/LM/ASP/Sep 2022 Date 08/09/22 
Internal Audit: Follow up of actions previously agreed by
management in response to audit recommendations 
From Ken Adamson, Head of Audit and Risk
Email adamsonk@northlan.gov.uk Telephone 07939 280602 
Executive Summary
The purpose of this report is to update the Panel on the results of Internal Audit’s follow-up
work reviewing the extent to which management have implemented actions previously
committed to in response to previous Internal and External Audit recommendations.
Information is contained in respect of the last two years External Audit outputs and those
actions agreed in response to ‘High’ and ‘Medium’ Internal Audit recommendations which
were due to be completed in the period up to the end of June 2022.
The Panel should note that where actions are not yet ‘complete’ this does not mean that no
relevant activity has been undertaken by management and that often the actions
taken/progress made to date will have reduced the risk exposure in respect of the
weaknesses previously identified even if the action is not yet complete.
It should note that, as reported to the Audit and Scrutiny Panel in December 2021, there has
been a change to our reporting on follow-up and those recommendations which were
previously reported to the Panel as partially implemented will now be monitored against
revised target implementation dates agreed with management.
9 of the 14 actions agreed in respect of External Audit outputs have been completed, one
has been partially implemented and four are no longer relevant. 
10 of the 27 actions agreed in response to relevant Internal Audit recommendations due in
the period have been fully completed, 15 have been assessed as partially implemented and
two as no longer relevant.
Recommendations
The Panel is invited to:
(1) note the contents of this report; and
(2) approve the recommendations made by Internal Audit at Appendix 1 and to consider
whether there are any issues arising from this report on which they wish to receive
further information from relevant management.  
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement  All ambition statements

Page 2

1. Background
1.1 All Internal and External Audit reports contain management responses to audit
recommendations which generally include a commitment to specific actions by a stated
date.  This report presents an overview of progress by management in addressing all
External Audit recommendations made in the last two years and all ‘High’ and ‘Medium’
Internal Audit recommendations which were previously reported as outstanding or
where the proposed actions were due to be completed by the end of June 2022.
1.2 The format of this report is designed to allow the Panel to focus on those issues where
non-implementation of agreed actions presents the most significant ongoing risk to the
Council and to enable the Panel to hold relevant senior management to account.
1.3 As reported to the Audit and Scrutiny Panel in December 2021, Internal Audit recently
reviewed our arrangements for following-up audit recommendations.  As a result, we
amended our processes to include, in certain circumstances, agreeing a revised
implementation date and monitoring and reporting against these revised dates where
we are provided with a strong rationale for the non-implementation of the audit
recommendation by the original agreed date.  This avoids repeatedly reporting and
focusing on actions which are ‘late’ where there are sound reasons for non-
implementation by the originally agreed date. 
1.4 This change means that this report presents the assessment of the potential risks
arising from those planned actions agreed in response to Internal Audit
recommendations due in the period (April to June 2022) which are not yet fully
completed.
1.5 The updates from management on progress to date have been verified on a sample
basis by Internal Audit as part of the preparation of this report.  However, it should be
noted that this review has focused on whether planned actions have been completed
and has not included detailed substantive testing of whether the implemented actions
have been effective in addressing previously identified weaknesses. 
2. Report 
Actions previously agreed by management – Internal Audit recommendations
2.1 Table 1 overleaf shows whether management have implemented those actions
previously agreed to in response to ‘High’ and ‘Medium’ Internal Audit
recommendations which were due to be completed by the end of June 2022.  Overall,
10 of the agreed actions have been completed, 15 are partially implemented and two
are no longer relevant.
Table 1
Head of Service Area Complete Partially
implemented
No longer
relevant Total
Adult Social Work Services 2 1 0 3
Asset and Procurement 2 1 0 3
Audit and Risk 0 0 1 1
Business and Digital 0 8 0 8
Education (North/South) 1 2 0 3
Education and Families 0 1 0 1
Financial Solutions 2 1 1 4
People & Organisational Development 1 1 0 2
Performance, Planning and Quality
Assurance 2 0 0 2
TOTAL 10 15 2 27

Page 3

2.2 Internal Audit has reviewed the management updates and agreed revised
implementation dates for all 15 recommendations listed as partially implemented at
Table 1 with relevant management.  These recommendations will now be monitored in
line with the agreed revised date and will be reported back to the Panel in accordance
with this revised timescale at which time consideration will be given as to whether
previously identified weaknesses have now been addressed. 
2.3 Detail in respect of each of these recommendations and the current residual risk
assessed by Internal Audit as a result of partial implementation is provided in Appendix
1.  In this appendix, we have also made suggestions as to how the Panel may wish to
consider these issues.  Definitions of the residual risk ratings are provided at Appendix
2. 
2.4 The two issues assessed as being no ‘longer relevant’ relate to Risk Management and
Debt Management. These are being followed up separately as part of detailed audit
work presently being undertaken in these areas and, where appropriate, updated
recommendations will be made in the current audit report.
Actions previously agreed by management – External Audit recommendations
2.5 Table 2 shows the status of actions agreed by management in response to External
Audit reports issued as part of the 2019/20 and 2020/21 audits.  Internal Audit has
concluded that nine of the 14 agreed actions have been completed, one has been
partially implemented and the remaining four actions are no longer relevant.
Table 2 Completed Partially
implemented
Not yet
due
No longer
relevant Total Report Title/Year
2019/20
Interim Audit Report 1 1 0 2 4
Annual Report 2 0 0 1 3
2020/21
Interim Audit Report 3 0 0 1 4
Annual Report 3 0 0 0 3
TOTAL 9 1 0 4 14
2.6 The four External Audit actions assessed as ‘no longer relevant’ relate to issues on
which External Audit have made a subsequent recommendation in subsequent audit
reports. 
3. Measures of success
3.1 Internal Audit report each cycle to the Audit and Scrutiny Panel on the progress made
by management in implementing actions previously committed to in response to
Internal and External Audit reports. 
4. Supporting documents
Appendix 1 Internal Audit recommendations - Management actions assessed as
‘not yet complete’ in this cycle
Appendix 2  Residual risk rating definition 
Ken Adamson, Head of Audit and Risk

Page 4

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public Sector
Equality Duty and/or Fairer Scotland Duty?
Yes ☐ No ☒
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☐ No ☒
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal data?  
Yes ☐ No ☒
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☐ No ☒
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☐ No ☒
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed?
Failure by Services to address previously identified issues and/or weaknesses will
impact on the effectiveness of the relevant control framework.  This, depending on the
nature of the issue, will be captured and should be reflected in the relevant Service
risk register or the Corporate risk register (as appropriate).

Page 5

Appendix 1 Internal Audit recommendations - Management actions assessed as ‘not yet complete’ in this cycle
Head of Service
Report Details Details from original recommendation Current position per
management update
Original and
revised timescales Internal Audit comment
Head of Asset and Procurement
Procurement 
(November 2021)
Risk: If performance measures are not correctly
calculated in line with the definition, management and
elected members may misinterpret the information
presented to them and may not raise appropriate
questions. 
Recommendation: Asset and Procurement Solutions
should review the processes in place to ensure that all
future performance measures contained within the
Annual Procurement Report are accurately and
consistently calculated in line with the corresponding
definition.
Category: Medium
Performance indicators have
been reviewed and amended. 
Work is ongoing with the Scottish
Government to ensure that
relevant content is incorporated
into the future Annual
Procurement Report.
The Annual Procurement Report
is currently being finalised prior to
it being reported to the Finance
and Resource Committee in
September 2022. 
Original timescale:
June 2022 
Revised timescale: 
September 2022
The Service has indicated that they consider
this recommendation to be largely complete
and have committed to finalising the Annual
Procurement Report for the next meeting of
the Finance and Resource Committee
scheduled for September 2022.
We consider the revised timescale to be
reasonable and have assessed the residual
risk for this recommendation as ‘Low’.
Accordingly, we would suggest that the Panel
may simply wish to consider agreeing to note
the progress made and the revised
completion date
Head of Business and Digital 
Corporate
Governance
Principles E, F &
G
(June 2021)
Risk: The operating model may result in Community
Boards failing to discharge their roles and responsibilities
adequately or effectively which may impact on the
achievement of the shared ambition.
Recommendation: The Chief Executive should ensure,
after allowing a sufficient period of time for the model and
individual Boards to become established, that a formal
review (or self-assessment) of the effectiveness of the
Community Boards should be undertaken.
Category: Medium
A number of actions have been
progressed aimed at assessing
ongoing effectiveness of
Community Boards.  A
performance framework for
delivery of Local Outcome
Improvement Plans has been
established and progress will be
reported to the Council’s People
and Communities Committee
and the Strategic Leadership
Board of North Lanarkshire
Partnership. The performance
framework and reporting
arrangements will be further
developed to ensure that the
Council and its partners have
confidence that the Community
Boards are operating effectively.
Original timescale:    
April 2022 
Revised timescale: 
March 2023 
We acknowledge that, to date, there has been
some progress made in measuring the
effectiveness of the Community Boards. 
While we appreciate that oversight and
governance of the Boards is largely a matter
for the Strategic Leadership Board of the
North Lanarkshire Partnership, we welcome
the further steps being taken to ensure that
the Council and its partners can have
confidence that these Boards are operating
effectively. 
Given that action is required to further
improve the control environment we assess
the residual risk as ‘Medium’ and consider it
important the agreed extension date of March
2023 is achieved.
We would suggest that the Panel may wish to
consider agreeing to note the progress made
and agree to monitor progress being made as
part of the next follow-up report.

Page 6

Appendix 1 (continued) Internal Audit recommendations - Management actions assessed as ‘not yet complete’ 
Head of Service
Report Details Details from original recommendation Current position per management
update
Original and
revised timescales Internal Audit comment
Head of Business and Digital 
Digital NL
(November 2021)
Risk: Inadequate arrangements for identifying, agreeing and
realising expected outcomes (including expected financial savings)
within timescales may result in consequential impacts on the
management of the Council’s finances.  
Recommendation: Management should continue to review the
future deliverability of the revised Digital NL programme to ensure
timescales for delivery and expected outcomes are realistic and
achievable.  This should include consideration of:
• further developing/enhancing the RAG status for assessing
individual projects/workstreams.  In particular consideration
should be given to splitting the RAG status to provide separate
assessments of achievement of timescales and achievement of
projected benefits (including expected savings) to enable the
impact of the RAG status on savings to be more clearly
documented.  
• the use of optimism bias to make explicit risk-based
adjustments to the projected estimates of projects costs,
benefits (including expected savings), and duration; and  
• the identification and implementation of actions necessary to
address the continual movement of projected savings.  
Category: High
A full review of deliverability of the
DigitalNL programme, SmartNL and
infrastructure business has taken place. 
The outstanding year 3 development work
and the potential Year 4 Roadmap were
reviewed in line with shape and size,
resource availability, benefits realisation,
funding availability and risk.  A
prioritisation matrix has been developed
and an Assessment Board created to
ensure all activities are reviewed in line
with the newly developed Integrated
Programme Plan. 
The full end to end process was presented
to the SRO meeting on 26 May 2022 with
approval given at this meeting to further
develop the proposals.  In recognising the
Delivery Board is responsible for
governing the DigitalNL programme and
its associated outcomes, the final
proposals will be presented to the Delivery
Board in August 2022 for consideration
and approval as appropriate.
Original timescale:
June 2022 
Revised timescale: 
August 2022 
The Service has indicated that
they consider these actions to
be largely complete. However,
while we acknowledge that
there has been some progress
made in this area, we consider
there is still further action which
requires to be taken to fully
address the identified risks.
Given that action is required to
further improve the control
environment we assess the
residual risk as ‘Medium’ and
consider it important that the
agreed extension dates are
achieved.
We would suggest that the
Panel may wish to consider
agreeing to note the progress
made and the revised
completion date and to monitor
progress being made as part of
the next follow-up report.
Risk: Benefits and savings may not be being adequately tracked
and monitored resulting in the Council being unable to demonstrate
the achievement of the objectives of the programme.  
Recommendation: Management should ensure that:  
(1) the non-financial benefits tracker is finalised and approved with
non-financial benefits thereafter identified, calculated, tracked and
monitored for all workstreams; and  
(2) the review of the suite of documentation cited in the Benefits
Management Realisation approach is completed and the process
thereafter updated and circulated to all relevant parties. 
Category: Medium
The non-financial benefits tracker has
been finalised and the updated Benefits
Management Approach revised and
updated.  However, the non-financial
benefits tracker has not yet been
populated for all workstreams and work is
ongoing in this area.  
The agenda for SRO/Delivery Board has
recently been amended to focus on
Benefits Realisation as the first agenda
item. 
Original timescale: 
April 2022 
Revised timescale:
September 2022

Page 7

Appendix 1 (continued) Internal Audit recommendations - Management actions assessed as ‘not yet complete’ 
Head of Service
Report Details Details from original recommendation Current position per management
update
Original and
revised timescales Internal Audit comment
Head of Business and Digital 
Digital NL
(November 2021)
Risk: Without full, clear and timely information, key
stakeholders may not be able to effectively monitor
performance in respect of the DigitalNL programme and/or
progress against expected benefits and planned outcomes or
determine whether the programme is achieving its targets,
and/or identify and agree timely action to address areas of
underperformance and/or make informed decisions about the
future direction of the DigitalNL programme.  
Without clear recording of actions prescribed and identified
responsible officers for actions planned in response to
highlighted risks, key stakeholders would be unable to monitor
the risk to ascertain if it had been addressed/mitigated.
Recommendation: Management should ensure that:  
(1) reports on DigitalNL to the Delivery Board, CMT and
Committee are amended to provide a clear and
comprehensive assessment of progress/status of both the
programme as a whole and of individual workstreams.  This
should include an assessment of each project/workstreams
RAG status; 
(2) reports submitted to the Board make clear reference to all
those significant risks with the potential to impact on the
successful delivery of the programme including the relevant
mitigating controls; actions planned to further address the
relevant risk and identified officers tasked with doing so and
that key risks are tracked and monitored at each meeting of
the Board; and  
(3) discussions at the Board in relation to any high/significant
programme risks included on the Programme Highlight Report
submitted to the Board, including the corresponding
prescribed action(s) and identified officers, are clearly
documented in the Action Note or Action Summary of that
meeting.  
Category: Medium
The Programme Highlight report submitted to
the Delivery Board has been reviewed and
amended to clearly show the RAG status and
the financial and non-financial benefits
anticipated for each business change sprint.
The reports submitted to the Board make clear
reference to significant risks and a link to the
Risk Register has been added to the
Programme Highlight Report. 
The Action Summary, introduced in early 2022,
allows members of the Delivery Board to focus
on agreed actions.
Original timescale:
June 2022 
Revised timescale: 
September 2022 
The Service has indicated that
they consider this action to be
substantially complete. 
However, due to the limited
number of Delivery Board
meetings since the process
was amended, we have not yet
been able to determine
whether adequate detail is
provided and/or appropriate
discussions held with regards
to those risks assessed as
‘high’/red.
We consider the revised
timescale to be reasonable and
have assessed the residual risk
for this recommendation as
‘Low’.
Accordingly, we would suggest
that the Panel may wish to
consider agreeing to note the
progress made and the revised
completion date.

Page 8

Appendix 1 (continued) Internal Audit recommendations - Management actions assessed as ‘not yet complete’ 
Head of Service
Report Details Details from original recommendation Current position per
management update
Original and
revised timescales Internal Audit comment
Head of Business and Digital 
Governance of
Capital Projects
(December 2019) 
Housing
Investment
Programme
(October 2020) 
Managing
Strategic Change 
(June 2021)
The three audit reports listed each raised issues regarding the Council’s
project management model.  In summary the risks and recommendations
arising comprised the following:
Risk: 
The Council’s project management arrangements may not reflect good
practice which may lead to projects being managed and documented on an
inconsistent basis.
Key stakeholders may not be adequately informed of progress in the Council’s
key corporate projects and may not be able to undertake effective oversight
and/or ensure that timely remedial action, necessary to ensure that projects
are delivered successfully, has been progressed by relevant management.
Recommendation: 
Management should:
• review and update, as appropriate, the project management model to
ensure that it is sufficiently prescriptive to enable officers to identify the
circumstances of when, and to what extent, it should be followed.
• review and amend the project management documentation to ensure that
it requires the title of the project to be recorded and includes version control
to clearly detail when it was prepared and last updated.
• review the ‘project management model review programme’ particularly in
relation to: expanding the sample of projects being reviewed to incorporate
some capital and non-capital projects that Services have not received
advance notification of; and reviewing and updating the checklist giving
due consideration to the suggested improvements made by Internal Audit.
• progress the previously identified action of establishing a reporting
mechanism which better facilitates regular and ongoing oversight by key
stakeholders of the progress of key projects against plan, including
management of key risks, progress against timelines, cost against budget,
achievement or otherwise of key milestones and expected outcomes or
benefits realisation.  We suggest that this could include introducing a
standard reporting template and adopting a traffic light system to report
progress against key criteria, project milestones and overall deliverability
against expected time, cost and any other intended outcomes.
Category: Medium
The planned review process
and subsequent refresh of the
council’s Project Management
Model took place from
February to June 2022.  A
Review Team comprising
representatives from all
Services, including audit and
risk, took part in the evaluation
and review process.  The
refreshed Project Management
Framework was circulated to
the Review Team for their final
input in June 2022.  
Insufficient feedback was
received from the majority of
service representatives on the
Review Team which led to a
delay in the finalisation of the
refreshed Project Management
Framework.  Further work is
being undertaken on a 1:1
basis to ensure Services are
fully engaged with, and
involved in, the final
development stages of the
refreshed Project Management
Framework.  Following this, the
Project Management
Framework will be finalised and
submitted to CMT for approval.
Original timescale:
June 2020 or
September 2021 
Revised timescale: 
April 2022 
Further revised
timescale:          
September 2022
The Service has indicated that
these actions are largely
complete and that the delay in
implementation is largely due
to insufficient feedback from
service representatives which
the Service are currently taking
steps to address.
Given the extensive delay in
implementation of these
recommendations, we assess
the residual risk as ‘High’ and
would suggest that the Panel
may wish to consider noting the
progress made to date and the
revised timescale but also to
request an update on this issue
from relevant senior
management at the next
meeting of the Panel if the
action is not fully implemented
at that time.

Page 9

Appendix 1 (continued) Internal Audit recommendations - Management actions assessed as ‘not yet complete’ 
Head of Service
Report Details Details from original recommendation Current position per management
update
Original and
revised timescales Internal Audit comment
Head of Education  (North/South)
Follow Up: Scottish
Attainment Challenge &
Pupil Equity Fund
(August 2021)
Risk: Without short, medium and long-term targets
against which performance can be monitored, there is
a risk that effective oversight of the SAC and PEF
programmes may be impaired. 
Without an effective performance management
framework, management would not be able to measure
whether the SAC and PEF programmes were being
delivered and/or may not be able to take appropriate
action to address areas of ‘under-performance’.  
Recommendation: Management should: 
(1) identify and set realistic short, medium and long-
term targets for the SAC and PEF programmes and
consider the current and future planned actions which
will be taken to deliver against the identified objectives
and measures of success 
(2) ensure that appropriate and realistic SMART
performance measures are used wherever possible in
the annual SAC Plan, subsequent progress reports to
committee and within the individual establishments’
SIPs and SIRS to ensure that progress of key all
actions and interventions can be appropriately tracked;
and 
(3) set out clearly defined baselines against which the
activities or interventions will be assessed for their
contribution to closing the poverty-related attainment
gap and ensure that the reports at both authority and
individual establishment level clearly set out to key
stakeholders the progress made against the identified
targets/milestones together with any significant
challenges in achieving these targets.
Category: Medium
Previous targets have been set by the Scottish
Government but from 2022, targets in relation to
progress in attainment are being set in
collaboration and discussion with local authorities
and both the SAC and PEF Team are engaging
in discussions to agree on aspirational yet
achievable targets and align the plans for the year
ahead.
Further development sessions for Headteachers
and senior managers have taken place to assist
with the development of clear rationales; help with
the identification of outcomes and measures and
provide both a local and national context to their
approach.  
Whilst improvements in planning at school level
have been noted the SAC and PEF Team
consider there is still work to be done in
encouraging greater detail in school improvement
plans.  The Improvement and Equity Lead
continues to support and challenge
establishments in both their SAC and PEF
submissions through scrutiny of plans and
encouraging all schools to ensure that, wherever
possible, data should form the basis of all
submissions of progress in the bi-annual
checkpoints.  
Original timescale:
December 2021 
Revised timescale:
June 2022 
Further revised
timescale:      
September 2022
Whilst we acknowledge that
there has been some action
taken to address the
recommendations made, we
consider that there is still
further action required to fully
mitigate the identified risks.
Given that action is required to
further improve the control
environment we assess the
residual risk as ‘Medium’ and
consider it important that the
agreed extension date of
September 2022 is achieved.
We would suggest that the
Panel may simply wish to
consider agreeing to note the
progress made and the revised
completion date and to monitor
progress being made as part of
the next follow-up report.

Page 10

Appendix 1 (continued) Internal Audit recommendations - Management actions assessed as ‘not yet complete’ 
Head of Service
Report Details Details from original recommendation Current position per
management update
Original and
revised timescales Internal Audit comment
Head of Education (North/South) 
Follow Up: Scottish
Attainment
Challenge & Pupil
Equity Fund
(August 2021)
Risk: Services may not be procured in accordance with the
Framework. 
Without formal documentation, schools may not be able to
evidence why a particular procurement method and/or
supplier was selected and/or be able to demonstrate best
value when procuring services
Recommendation: Management should:  
(1) remind/encourage all schools to use the Procurement
framework as far as possible and of the requirements of
the Framework (including the use of approved suppliers
wherever possible) and the importance of completing
the RFP documentation for each procurement exercise; 
(2)  periodically report to senior management on the use of,
and expenditure incurred via, the Framework against the
total spend allocation; and  
(3) ensure that they periodically review non-Framework
expenditure items to obtain sufficient assurance that
procurement activity funded via SAC/PEF is being
undertaken in accordance with corporate expectations
and can demonstrate best value.
Category: Medium
Headteachers are reminded
on an ongoing basis of the
requirements of the
Procurement Framework.
A review of Framework and
non-Framework expenditure
for session 2021-22 has been
undertaken with subsequent
findings to be reported to the
Programme Board and
Services Senior Leadership
Team in August 2022.
Original timescale:
December 2021 
Revised timescale:
June 2022 
Further revised
timescale: 
September 2022
Whilst we acknowledge that there has been
some action taken to address the
recommendations made, we consider that
there is still further action required to fully
mitigate the identified risks.
Given that action is required to further
improve the control environment we assess
the residual risk as ‘Medium’ and consider
it important that the agreed extension date
of September 2022 is achieved.
We would suggest that the Panel may wish
to consider agreeing to note the progress
made and the revised completion date and
to monitor progress being made as part of
the next follow-up report.
Head of Education and Families
Public Protection
(September 2021) Risk: If areas for improvement are not adequately identified,
quantified, addressed and regularly monitored and reviewed
the Council may fail to effectively deliver its public protection
responsibilities.
Recommendation: Management should ensure that
consideration is given to preparing and thereafter tracking
and monitoring an action plan for the NLCOPPG.
Category: Medium
The NLCOPPG have
delegated responsibility for
taking forward improvement
actions arising from the self-
evaluation to the Lead
Officers Public Protection
Group.  Action areas have
been agreed and the action
plan and progress report will
be presented to the
NLCOPPG at its next
meeting in October 2022. 
Original timescale:
November 2021 
Revised timescale: 
May 2022 
Further revised
timescale:
October 2022
The Service has indicated that the majority
of the recommendations have been
addressed.  The outstanding actions relate
to reports being presented to future
meetings of the NLCOPPG.
We consider the revised timescale to be
reasonable and have assessed the residual
risk for this recommendation as ‘Low’.
Accordingly, we would suggest that the
Panel may wish to consider agreeing to note
the progress made and the revised
completion date.

Page 11

Appendix 1 (continued) Internal Audit recommendations - Management actions assessed as ‘not yet complete’ 
Head of Service
Report Details Details from original recommendation Current position per
management update
Original and
revised timescales Internal Audit comment
Head of Education and Families
Tackling Poverty
(November 2021)
Risk: If the process to create a consolidated
action plan is not properly documented, the
LCPAR action plan may not be appropriately
aligned with the strategy action plan which may
result in key actions potentially being missed in
error.   
Feedback from external reviews may not be
incorporated into the LCPAR resulting in a
failure to address or progress relevant actions
or activities.
Recommendation: Management should
ensure that: 
(1) all relevant key actions from the strategy are,
where appropriate, incorporated within the
LCPAR action plan and/or that where actions
are removed/not included there is appropriate
documentary evidence maintained to support
the rationale for their removal; and 
(2) all outstanding recommendations and
actions arising from the NL Fairness
Commission and Scottish Government reviews
are, where appropriate, incorporated into the
LCPAR.
Category: Medium
Following the production of the Best
Start, Bright Futures Child Poverty
Delivery Plan 2022-2026, the LCPAR
will be incorporated within the
production of a new Tackling Poverty
Strategy 2023-2026 which will allow for
forward planning whilst meeting the
requirements of the Scottish
Government.  This document will include
all of the outstanding recommendations
and actions from the North Lanarkshire
Fairness Commission and Scottish
Government reviews.
The Local Child Poverty Action Report
will be prepared and submitted to the
Policy and Strategy Committee in
September 2022.
Original timescale:   
June 2022 
Revised timescale: 
September 2022 
The delay in implementing this action is
due to a number of factors, including the
Council elections, however a firm
commitment has been given by the
Service to submit the LCPAR to
Committee in September 2022.
We consider the revised timescale to be
reasonable and have assessed the
residual risk for this recommendation as
‘Low’.
Accordingly, we would suggest that the
Panel may wish to consider agreeing to
note the progress made and the revised
completion date.

Page 12

Appendix 1 (continued) Internal Audit recommendations - Management actions assessed as ‘not yet complete’ 
Head of Service
Report Details Details from original recommendation Current position per
management update
Original and revised
timescales Internal Audit comment
Head of Financial Solutions
Use of Corporate Credit
Cards and Purchase
Cards
(November 2021)
Risk: Without a clear statement of expected procedures and
oversight arrangements, there is an increased risk of
inadequate control over the administration of purchase cards
and expenditure incurred which may be inappropriate and/or
not appropriately monitored.
Recommendation: The Head of Financial Solutions should,
in conjunction with Facility Support Services, undertake a
formal review of the purchase card scheme, to ensure that
an appropriate and effective control environment is
established and thereafter implemented.  The review should
include, but not be limited to, considering the issues
identified in the finding.
Category: High
The review of the purchase
card scheme is currently
underway.  Delays in
implementation are due to staff
changes, shortages and a
prioritisation of financial year
end activities.
Original timescale: April
2022 
Revised timescale: 
September 2022
Although the review of the purchase card
scheme is not yet complete, we
acknowledge that the delay in
implementing this is due to a number of
factors, including changes in staff. A firm
commitment has been given by the
Service to complete the review by the
proposed revised timescale. 
Given that action is required to further
improve the control environment we
assess the residual risk as ‘Medium’ and
consider it important that the agreed
extension date of September 2022 is
achieved.
We consider it important, that the revised
timescale is achieved and would suggest
that the Panel may wish to consider
agreeing to monitor progress as part of
future follow-up reports.
Head of People and Organisational Development  
Corporate Governance
Principles A & B
(February 2022)
Risk: Without effective workforce planning there is a risk the
Council may not have in place (or identified the actions it
needs to progress to ensure it has in place) the staff and
skills it needs to enable it to deliver services and achieve
planned outcomes 
Recommendation: The Head of People and Organisational
Development should ensure that the service workforce plans
are completed and reported in accordance with the revised
timescales to inform future workforce planning activity.  
Category: Medium
Workforce Plans have been
completed for each service and
were presented to CMT April
2022.  A summary report will be
submitted to the Policy and
Strategy Committee in
September 2022.
Thereafter refreshed
streamlined plans and
associated action plans will be
submitted to CMT December
2022
Original timescale: June
2022 
Revised timescale:
December 2022
The Service has indicated that the
recommendation has largely been
addressed.  The outstanding actions
relate to refreshed streamlined plans and
associated action plans being presented
to CMT.
We consider the revised timescale to be
reasonable and have assessed the
residual risk for this recommendation as
‘Low’.
Accordingly, we would suggest that the
Panel may wish to consider agreeing to
note the progress made and the revised
completion date.

Page 13

Appendix 2  Residual Risk Rating definition
Internal Audit Assessment of Residual Risk from non-implementation 
High Non-implementation of actions has the potential to significantly undermine the
relevant control environment.
Medium Non-implementation of actions has the potential to impact upon the achievement
of the control environment.
Low Other issues which require management attention but which pose less significant
or less immediate impacts to the control environment.