Page 1

16 June 2026 
Members of the 
Audit and Scrutiny Panel
Chief Executive’s Office
Rachel Blair
Chief Officer (Legal, Democratic and Strategy)
Civic Centre, Windmillhill Street,
Motherwell ML1 1AB
www.northlanarkshire.gov.uk 
Notice is given that a Meeting of the Audit and Scrutiny Panel is to be held in the
Committee Room 1, Civic Centre, Windmillhill Street, Motherwell, ML1 1AB on Thursday, 25
June 2026 at 10:00 AM which you are requested to attend. 
The agenda of business is attached. 
Rachel Blair
Chief Officer (Legal, Democratic and Strategy) 
Members : 
Clerk Name: Karen Swan
Clerk Telephone: 07919 730272
Clerk Email: committee@northlan.gov.uk 
S Watson, P Kelly, C Costello, M Hughes, J Hume, D Johnston, J Leckie, A McCrory, M
McCulloch, J McLaren, G Robinson.  
Page 1 of 20

Page 2

Page 2 of 20

Page 3

Agenda 
1 Declarations of Interest In Terms of the Ethical
Standards In Public Life Etc. (Scotland) Act 2000 
YEAR-END ITEMS 
2 Internal Audit Annual Report and Opinion 2025-26
Submit report by the Chief Officer (Audit and Risk)
setting out the Internal Audit Annual Report 2025/26
and associated opinion of the Chief Officer. 
5 - 20 
3 Strategic Governance Framework
Submit report by the Chief Officer (Legal, Democratic
and Strategy) (copy to follow) 
4 Annual Governance Statement
Submit report by the Chief Officer (Legal, Democratic
and Strategy) (copy to follow) 
5 Unaudited Annual Accounts - Year Ending 31
March 2026
Submit report by the Chief Officer (Finance and
Technology) (copy to follow) 
Page 3 of 20

Page 4

Page 4 of 20

Page 5

North Lanarkshire Council
Report
Audit and Scrutiny Panel 
Does this report require to be approved? ☐ Yes   ☒ No
Ref    FS/ASP/June2026 Date 25/06/26 
Internal Audit Annual Report 2025-26 
From  Francis Scott, Chief Officer (Audit and Risk)  
E-mail scottfr@northlan.gov.uk   
Executive Summary
The Global Internal Audit Standards (GIAS) and the Council’s Internal Audit Charter require
the Chief Officer (Audit and Risk) to provide the Audit and Scrutiny Panel with an annual
summary of the work undertaken by Internal Audit and to provide an independent opinion
on the Council’s corporate governance, risk management and internal control
arrangements.  This report fulfils that requirement for the year 2025-26. 
The annual opinion is unqualified and states that reasonable assurance can be placed
on the Council’s governance, risk management and internal control arrangements. 
This report has previously been submitted to the Chief Executive, Business Management
Team and Corporate Management Team. 
Recommendations
The Panel is invited to note the Internal Audit Annual Report 2025-26 and the associated
annual opinion of the Chief Officer (Audit and Risk).   
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement All ambition statements
Programme of Work All Programmes of Work
Item 2
Page 5 of 20

Page 6

1. Background 
1.1 Internal Audit is an independent, objective assurance and advisory function designed
to add value and improve the Council’s operations.  It helps the Council accomplish its
objectives by bringing a systematic, disciplined approach to evaluating and improving
the effectiveness of the Council’s risk management, internal control and governance
processes. 
1.2 Internal Audit’s primary objectives are: 
• To examine and evaluate internal control systems and governance arrangements
within the Council.
• To provide assurance to elected members and senior officers on the adequacy and
robustness of these systems.
• To assist the Audit and Scrutiny Panel (the Panel), elected members and officers of
the Council in the effective discharge of their responsibilities. 
1.3 Internal Audit aims to provide a high quality and customer focused service which is
responsive and flexible, consistent with best professional practice, focuses on areas
that matter, uses resources efficiently and effectively, and is seen by stakeholders as
adding value and making a vibrant and relevant contribution to the Council. 
1.4 The purpose, mandate, authority and responsibilities of the Council’s Internal Audit
function are outlined in the Internal Audit Charter, the most recent version of which was
approved by the Panel in May 2026. 
1.5 Internal Audit reports its outputs regularly throughout the year to the Panel in accordance
with the Internal Audit Charter.  The Panel also approves Internal Audit’s annual audit
plan and monitors the performance of the function. 
1.6 Internal Audit activity is planned to enable the Chief Officer (Audit and Risk) to provide
an independent annual opinion on the adequacy and effectiveness of internal controls
within the authority, including the systems designed to achieve the corporate objectives
of the Council and those that manage the material risks faced by the authority. 
1.7 It should be noted that the presence of an effective Internal Audit function contributes
towards, but is not a substitute for, effective control.  It is primarily the responsibility of
management to establish internal controls so that the Council’s activities are conducted
in an efficient and well-ordered manner, to ensure that management policies and
directives are adhered to, and that assets and records are safeguarded. 
2. Report 
Internal Audit Team 
2.1 The Internal Audit team has an establishment of 8.5 full-time equivalent (FTE) members
of staff, comprising a Chief Officer, an Audit Manager, six Auditors and an Audit and
Risk Assistant.  All members of the team above assistant level hold, or are working
towards, a relevant professional qualification. 
2.2 The Chief Officer (Audit and Risk) reports directly to the Chief Executive and is a
member of the Council’s Corporate Management Team.  The role and status of the
Chief Officer and the Internal Audit function within the Council is consistent with the
requirements of the Global Internal Audit Standards (GIAS) and best practice. 
Page 6 of 20

Page 7

2.3 The team experienced some staffing changes during 2025-26, which had the overall
effect of operating with one vacant auditor post for much of the year.  This resulted in
some changes to the implementation of the audit plan. 
2.4 A performance management framework for Internal Audit is included within the Internal
Audit Strategy. Results of the key performance indicators are reported on an annual
basis, and Appendix 3 sets out these results for 2025-26.  These indicators may be
subject to review during 2026-27, with any revised framework being presented to the
Panel.  Customer satisfaction surveys are issued to service management at the
conclusion of each audit, with the results being reported to each meeting of the Panel. 
During 2025-26, the team continued to receive positive feedback from Services for the
work undertaken. 
2.5  The team continues to foster effective working relationships with colleagues from other
organisations.  The Chief Officer (Audit and Risk) is a member of the CIPFA Internal
Audit Special Interest Group and the Scottish Local Authorities Chief Internal Auditors’
Group (SLACIAG).  Additionally, members of the team attend and contribute to
SLACIAG’s sub-groups covering computer audit, data analytics and counter fraud. 
These are valuable forums through which best practice and intelligence is shared, and
relevant training provided.   
2.6 Joint working is also undertaken with the appointed Chief Internal Auditor for NHS
Lanarkshire, for the provision of a joint internal audit service to North Lanarkshire
Integrated Joint Board.  Internal Audit staff also continue to liaise closely with Audit
Scotland, the Council’s appointed external auditors, to facilitate their work and to avoid
any potential duplication of effort. 
Global Internal Audit Standards 
2.7 Since their introduction in 2013, the Public Sector Internal Audit Standards (PSIAS)
were mandatory for Internal Audit functions.  The PSIAS required the Chief Officer
(Audit and Risk) to develop and maintain a Quality Assurance and Improvement
Programme (QAIP) which included periodic internal assessments, and an independent
External Quality Assessment (EQA) to be undertaken at least every five years. 
2.8 The most recent independent EQA was undertaken by Stirling Council in 2024 and
confirmed that Internal Audit fully conformed with the PSIAS.  This was reported to the
Panel in May 2024.  Both the self-assessment and EQA highlighted some areas for
improvement and consideration, and these are highlighted in the QAIP action plan at
Appendix 4. 
2.9 From April 2025, the PSIAS was replaced by the Global Internal Audit Standards
(GIAS), which required a revision to the current internal audit methodology and working
practices. A gap analysis exercise was undertaken to determine actions to ensure
compliance with the new standards, and we are working towards this in preparation for
the next EQA in 2028-29.  As part of the QAIP, the GIAS also require ongoing internal
review and periodic self-assessment.   
Internal Audit Activity During 2025-26 
2.10 The Internal Audit plan for 2025-26 was approved by the Panel in May 2025.  During
the year, 21 audit assignments were undertaken from the plan (compared with 17
planned assignments during 2024-25). This resulted in the following assurance
opinions. 
Page 7 of 20

Page 8

Substantial
Assurance
Reasonable
Assurance
Limited
Assurance No Assurance Other/TBC *
3 13 2 0 3
*  The remaining 3 audit reports have not yet been finalised, but the completed fieldwork
indicates that they will provide Reasonable Assurance 
2.11 One unplanned assurance audit was undertaken during the year on the Clyde Valley
Waste Contract, which provided Substantial Assurance.  In addition, investigative work
was undertaken relating to potentially fraudulent business grant claims – this is
discussed in more detail at paragraph 2.23.  Appendix 2 provides details of the planned
and unplanned work undertaken during 2025-26. 
2.12 The GIAS require the audit plan to be subject to ongoing review to ensure it remains
relevant and fit for purpose.  During the year, some amendments were made to the
plan to enable the function to respond flexibly to changing circumstances, and to take
account of the effect of auditor vacancies within the team. These changes were
approved by the Panel in March 2026, and included: 
Audit Reason for Change
Project Management Partially deferred to 2026-27 due to resources
Debt Management Partially deferred to 2026-27 due to resources
Traffic Commissioner
Report
Audit no longer required as the Driver and Vehicle Standards
Agency provided assurance that outstanding actions complete
Compliance with Grant
Conditions
Removed due to resources and other unplanned work on
business grants
Digital NL Process
Redesign
Removed due to resources and ongoing Council review of the
Programme of Work
NL Community Planning
Partnership
Removed due to resources and other planned audit work on the
Leadership and Operating Model which included community
hubs 
2.13 Considering these changes to the audit plan and the additional unplanned work
undertaken during the year, it is my view that sufficient coverage has been obtained to
inform the annual opinion. 
2.14 Internal Audit continues to support Service management to ensure recommendations
made within audit reports are implemented as agreed, and an update on all outstanding
audit recommendations is presented to each meeting of the Panel.  The Internal Audit
Annual Reports for 2023-24 and 2024-25 noted a marked improvement in the actions
and engagement of management in implementing audit recommendations, and this has
continued throughout 2025-26. 
2.15 Internal Audit also has responsibility for investigating alleged frauds and irregularities
brought to our attention in accordance with the Council’s Corporate Fraud Policy. 
Where detailed work is carried out, the findings are reported to the Chief Executive and
the relevant Chief Officer, with details of the work presented to the Panel, in line with
the Internal Audit Charter. 
Page 8 of 20

Page 9

2.16 In addition to undertaking audit reviews, the Internal Audit team are involved in several
other areas which serve to contribute to good governance across the council and
enhance the overall control environment. During 2025-26, this included: 
• Participation in corporate working groups, project boards and Programme of Work
thematic boards.
• Provision of advice and guidance on systems development and control issues to
services and Chief Officers.
• Preparation of reports and agendas, and participation at meetings, to enable the
Panel to fulfil its role. 
• Co-ordinating the work of the Council’s involvement with the National Fraud
Initiative.
• Consideration of reports by Audit Scotland and the Accounts Commission and
highlighting key issues. 
Audit Issues 2025-26 
2.17 The nature of audit assignments is such that most Internal Audit reports identify some
weaknesses or areas where scope for improvement exists, and during 2025-26, a
number of recommendations were made to address such areas identified from the audit
work undertaken.  However, as noted in paragraph 2.10, the majority of audits
undertaken during the year received opinions of either Reasonable or Substantial
Assurance, and there are no issues arising from these audits which require to be
highlighted in this report. 
2.18 The 2023-24 Annual Report discussed reports on the Housing and Corporate Property
Maintenance Contract and the whistleblowing allegations received by Audit Scotland,
and audit work during 2024-25 concluded that significant progress had been made in
implementing the recommendations in both reports, with some aspects being fully
implemented.  Substantive audit work on the operation of the new contract was included
in the Internal Audit Plan for 2025-26 and no significant issues have been identified. 
2.19 Two audits during 2025-26 provided Limited Assurance.  The first was in relation to
unannounced spot check visits at a sample of education establishments – while the
audit testing also considered physical security, health and safety, and information
security arrangements,  the limited assurance opinion was due to control weaknesses
in the management of school funds (specifically non-compliance with procedures, and
insufficient oversight of the processes by Head teachers and senior school
management).   
2.20 The control environment around school funds has been subject of repeated audit activity
over recent years and was mentioned specifically in the Internal Audit Annual Report
for 2024-25.  While work is ongoing to address the control weaknesses, the agreed
actions from previous audits have not yet been fully implemented, meaning the areas
of concern identified have not been addressed.  Further work in this area has been
included as part of the 2026-27 Internal Audit Plan. 
2.21 The second report with Limited Assurance relates to the arrangements for the use of
Self-Directed Support (SDS).  The audit found significant weaknesses in relation to the
application of procedures and retention of key documentation for each of the four care
delivery options available to service users, as well as in the consistency of monitoring
Direct Payment expenditure.  These weaknesses could lead to funds being misused,
assessed needs not being met and potential financial loss and reputational damage for
the Council (although there was no evidence of misuse of funds from the sample of
cases tested). 
Page 9 of 20

Page 10

2.22 Although the issues noted above can be significant to the control environment in the
individual system or areas audited, they are not material enough to have a significant
impact on my overall opinion on the adequacy of the Council’s control environment. 
2.23 One fraud investigation was undertaken during 2025-26. This followed concerns
identified by officers in relation to potentially fraudulent applications for business grants
by external parties.  The investigation report is currently being finalised and will be
presented at the next meeting of the Panel in August 2026 for discussion and
consideration. 
Corporate Risk Team 
2.24 The Corporate Risk Team has an establishment of 2.5 FTE members of staff, comprising
a Corporate Risk Manager, a Corporate Risk Officer and an Audit and Risk Assistant. 
The Corporate Risk Manager, Corporate Risk Officer and the Chief Officer are members
of the Association of Local Authority Risk Managers (ALARM).  Members of the
Corporate Risk Team also attend the SLACIAG risk management sub-group which,
alongside the ALARM membership, provides opportunities for learning and access to
sector information materials.   
2.25 The Corporate Risk Team is responsible for the co-ordination and continuous
development of risk management arrangements across the Council, and maintenance
of the Corporate Risk Register.  The team also provides support and guidance to all
services on the management of risk, including formal training opportunities and the
provision of risk workshops.  Progress on the work of the team is reported quarterly to
the Panel.
2.26 The Risk Management Corporate Working Group (RMCWG) supports Council services
and the Corporate Management Team to implement the Risk Management Strategy
and embed and promote good risk management practice. There were seven meetings
of the RMCWG during the reporting period – these were chaired by the Corporate Risk
Manager and were consistently well attended with high levels of engagement from
across services.  
2.27 During 2025-26, some of the key outcomes from the work of the Corporate Risk Team
included:
• A refresh of the Council’s Risk Management Strategy for the three-year period to
2029, incorporating high-level deliverables for the Corporate Risk Team.  The
strategy document was approved by Policy and Strategy Committee in March 2026.
• Collaborating with service risk champions to identify and capture improvement
actions using the Risk Management Monitoring Tool.  The exercise was undertaken
twice during 2025-26 and reviewed through the RMCWG.
• Development of resources to support services in identifying matters to be captured
in corporate and service risk registers through horizon scanning.  This also included
high-level comparison of external horizon scanning publications and survey results
with existing risk registers.
• Provision and facilitation of risk management training for officers and members. 
During 2025-26 this comprised improving the content of the mandatory e-learning
module, coordinating external accredited training courses for service risk champions
and facilitators, delivering CPD sessions for legal officers and provision of ad-hoc
training on the risk management system.
• Liaison with the application supplier to refine the risk management system to capture
additional details, adjust reporting formats and introduce new functionality.  Page 10 of 20

Page 11

Internal Audit Opinion 2025-26 
2.28 The opinion is presented to members of the Audit and Scrutiny Panel, the Chief
Executive and the other members of the Council’s Corporate Management Team and
is intended to provide independent and objective assurance as to the adequacy and
effectiveness of governance, internal control and risk management arrangements within
the Council. 
Annual
Opinion
Reasonable
Assurance
There is generally an overall sound system of governance,
risk management and internal control in place.  While some
issues, non-compliance or scope for improvement were
identified, individually these do not significantly impair the
Council’s system of internal control. 
2.29 My formal Internal Audit Opinion on the soundness of the Council’s internal control
systems for 2025-26 is presented at Appendix 1.   
Acknowledgements 
2.30 I would like to take this opportunity to express my thanks to all staff in the Audit and Risk
team for their hard work and commitment throughout the past year.  I would also like to
thank all Council staff who have assisted Internal Audit during our work throughout
2025-26, and the Chief Officers and elected members for the consideration and due
regard given to our work. 
3. Measures of success 
3.1  Internal Audit reports annually on its performance to the Panel and is also subject to
review annually by the Council’s appointed external auditors.   
4. Supporting documentation 
Appendix 1 Internal Audit Opinion 2025-26
Appendix 2 Audit Work Undertaken 2025-26
Appendix 3 Internal Audit Performance  
Appendix 4  Quality Assurance Improvement Programme (QAIP) Action Plan 
Francis Scott
Chief Officer (Audit and Risk) 
Page 11 of 20

Page 12

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant financial impacts been discussed and agreed with
Finance? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts been discussed and agreed with Legal and
Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Page 12 of 20

Page 13

Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
Failure to operate an effective Internal Audit function, consistent with the Global
Internal Audit Standards (GIAS) could impair the Council’s compliance with its
Code of Corporate Governance.  Risks to the effective operation of the Internal
Audit service (including failure to comply with GIAS) and how these are mitigated
are documented in the Service’s risk register which is subject to regular review by
the Audit and Risk management team. 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services. 
5.11 Children’s rights and wellbeing impact 
Does the report contain any information regarding any council activity, service
delivery, policy, or plan that has an impact on children and young people up to the
age of 18, or on a specific group of these? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact and the provision that has
been made to ensure there has been appropriate consideration of the relevant
Articles from the United Nations Convention on the Rights of the Child (UNCRC). 
If Yes, has a Children’s Rights and Wellbeing Impact Assessment (CRWIA) been
carried out? 
Yes ☐ No ☐ 
Page 13 of 20

Page 14

APPENDIX 1 – Internal Audit Opinion 2025-26 
To the members of North Lanarkshire Council’s Audit and Scrutiny Panel, the Chief
Executive and Corporate Management Team 
As Chief Officer (Audit and Risk) of North Lanarkshire Council, I am pleased to present my
annual statement on the adequacy and effectiveness of the Council’s framework of
governance, risk management and internal control for the year ended 31 March 2026. 
Respective responsibilities of management and internal auditors in relation to
governance, risk management and internal control 
It is the responsibility of the Council’s senior management to establish appropriate and sound
systems of governance, risk management and internal control and to monitor the continuing
effectiveness of those systems.  It is the responsibility of the Chief Officer (Audit and Risk) to
provide an independent annual opinion on the adequacy and effectiveness of the Council’s
framework of governance, risk management and internal control. 
The Council’s framework of governance, risk management and internal controls 
The main objectives of the Council’s framework of governance, risk management and internal
controls are to ensure that resources are directed in accordance with agreed plans, policies
and priorities and to ensure that there is sound decision-making and clear accountability for
the use of those resources to achieve the desired outcomes for service users and communities. 
This includes ensuring that appropriate internal controls and risk management arrangements
are in place to effectively manage issues which might impact on the delivery of Council
services, the achievement of corporate and service objectives, ambitions and priorities and
public confidence in the Council.  The Council also requires effective internal controls and risk
management arrangements to safeguard its employees, to protect its assets, to maintain
effective stewardship of public funds, to ensure good corporate governance, to ensure
compliance with statutory requirements and to ensure it continues to deliver best value. 
The work of Internal Audit 
Internal Audit is an independent, objective and risk-based assurance function designed to add
value and to improve the Council’s operations.  It enhances the Council’s achievement of its
objectives, decision making and oversight by bringing a systematic approach to evaluate and
improve the effectiveness of the Council’s risk management, control and governance
processes and by providing an independent and objective opinion on the Council’s internal
control environment.  In doing so, Internal Audit contributes to the Council’s reputation and
credibility with its stakeholders and its ability to serve the public interest.   
Internal Audit operated throughout 2025-26 in accordance with the Global Internal Audit
Standards (GIAS).  As part of the Internal Audit Quality Assurance and Improvement
Programme, I have assessed the extent to which current internal audit activity, policies and
procedures conform to expected requirements.  The results show that Internal Audit continues
to substantively comply with the GIAS. 
Internal Audit undertakes an annual programme of work formally approved by the Audit and
Scrutiny Panel.  The audit plan is risk-based and is revised on an ongoing basis to reflect my
assessment of the evolving risks and operational changes within the Council. 
All Internal Audit reports identifying system weaknesses or non-compliance with expected
controls are brought to the attention of management and include appropriate recommendations
and agreed action plans.  It is management’s responsibility to ensure that proper consideration Page 14 of 20

Page 15

is given to Internal Audit reports, and that appropriate action is taken on audit
recommendations. 
Internal Audit is required to ensure that appropriate arrangements are made to determine
whether action has been taken on Internal Audit recommendations or, where appropriate, that
management has understood and assumed the risk of not acting.  Significant matters (including
non-compliance with audit recommendations) arising from internal audit work are reported
regularly to the Chief Executive, to the Corporate Management Team and to the Audit and
Scrutiny Panel. 
Basis of Opinion 
My evaluation of the control environment is informed by several sources: 
• The audit work undertaken by Internal Audit during the year to 31 March 2026.
• The assessment of risk completed during the preparation of the 2025-26 and 2026-27
Internal Audit plans.
• My wider knowledge of the Council’s corporate governance, risk management and
performance management arrangements.
• Assurances of the general control environment within individual Services in 2025-26
provided by Chief Officers.
• Reports issued by the Council’s external auditors during 2025-26, together with reports
from other external review and inspection bodies. 
Opinion 
It is my opinion that reasonable assurance can be placed upon the adequacy and effectiveness
of the Council’s framework of governance, risk management and internal control for the year
ended 31 March 2026. 
Francis Scott
Chief Officer (Audit and Risk)
North Lanarkshire Council 
May 2026
Page 15 of 20

Page 16

APPENDIX 2 – Audit Work Undertaken 2025-26
Audit  Status Recommendation Priority Assurance Opinion Reported to Audit &
Scrutiny Panel High Medium Low
Planned 
1. Risk Management  Complete 0 3 2 Reasonable March 2026
2. Roads Contract Complete 0 1 2 Reasonable  May 2026
3. Strategic Governance Arrangements Complete 0 1 0 Substantial August 2025
4. Information Governance  Complete 0 1 0 Reasonable November 2025
5. Financial Sustainability Complete 0 0 1 Substantial March 2026
6. Housing Repairs Contract Ongoing     Expected August 2026
7. External Legal Fees  Ongoing     Expected August 2026
8. Self-Directed Support Complete 1 3 1 Limited May 2026
9. Sundry Debtors Complete 0 0 3 Substantial March 2026
10. Contract Management Complete 0 4 0 Reasonable May 2026
11. Education Establishment Visits Complete 1 1 2 Limited May 2026
12. Community Asset Transfers Complete 0 3 1 Reasonable November 2025
13. Procurement – Compliance   Complete 0 1 1 Reasonable May 2026
14. Procurement – Non-Contract Spend Complete 0 3 1 Reasonable August 2025
15. Protecting Vulnerable Groups (PVG) Complete 1 2 1 Reasonable March 2026
16. Attendance Management  Complete 0 0 2 Reasonable November 2025
17. Payroll Leavers Process Complete 0 3 2 Reasonable November 2025
18. Fleet Services Complete 2 3 0 Reasonable November 2025
19. Homelessness Complete 0 3 1 Reasonable March 2026
20. Leadership and Operating Model Ongoing     Expected August 2026
21. Anti-Fraud Arrangements  Complete 0 2 0 Reasonable  March 2026 
Page 16 of 20

Page 17

Audit  Status Recommendation Priority Assurance Opinion Reported to Audit &
Scrutiny Panel High Medium Low
Unplanned Work
22. Clyde Valley Waste Contract Complete 0 0 1  Substantial May 2026
23. Business Grants Ongoing     Expected August 2026 
Assurance Opinion Definitions
Substantial Assurance A sound system of governance, risk management and control exists, with internal controls operating effectively and being
consistently applied to support the achievement of objectives in the area audited.
Reasonable Assurance There is a generally sound system of governance, risk management and control in place. Some issues, non-compliance or scope
for improvement were identified which may put at risk the achievement of objectives in the area audited.
Limited Assurance Significant gaps, weaknesses or non-compliance were identified. Improvement is required to the system of governance, risk
management and control to effectively manage risks to the achievement of objectives in the area audited.
No Assurance Immediate action is required to address fundamental gaps, weaknesses or non-compliance identified. The system of governance,
risk management and control is inadequate to effectively manage risks to the achievement of objectives in the area audited. 
Page 17 of 20

Page 18

APPENDIX 3 – Internal Audit Performance
Category Measure 2025-26 Performance 2024-25 Performance
1. Delivery of Annual
Plan  Percentage completion of agreed plan 80.6% 87.9%
2. Targeting
Percentage of key corporate risks and key financial
systems over which assurance provided (note 100%
coverage planned over a 3-year rolling period)
Corporate risks – 36% audited in
2025-26
Financial systems – 17% audited
in 2025-26
Corporate risks – 27% audited in
2024-25 
Financial systems – 42% audited
in 2024-25
3. Efficiency Cost of Internal Audit per £ million revenue budget To be confirmed To be confirmed
4. Efficiency % of productive hours delivered v Plan 85.9% 89.8%
5. Delivery /
recommendations
Percentage implementation of agreed actions by
implementation date (cumulative year to date) 79% 54%
6. Delivery / other Number of significant irregularity / fraud
investigations 1 1
7. Quality / standards Quality review outcomes – EQA or internal self-
evaluation
2024 EQA ‘Fully Conforming’ with
PSIAS
2024 EQA ‘Fully Conforming’ with
PSIAS
8. Delivery of Annual
Report Annual opinion /report prepared by 31 May annually Annual opinion/report signed
28/05/26
Annual opinion/report signed
27/05/25
9. Targeting Approval by CMT and A&SP of strategy and annual
plan by 31 May annually
Annual plan endorsed by CMT 
01/05/26
Annual Plan approved by A&SP
14/05/26
Annual plan endorsed by CMT 
28/04/25
Annual Plan approved by A&SP
08/05/25 
Page 18 of 20

Page 19

APPENDIX 4 – Quality Assurance Improvement Programme (QAIP) Action Plan
No. Source  Recommendation Management Response  Responsible Officer
and Target Date Status
1 Self-
assessment
Annual audit plan conforms with all aspects
detailed in PSIAS and expectation is that all
assignments will be completed in the year,
however individual audits are not formally
prioritised in the plan.  
N/A Chief Officer (Audit
and Risk) 
March 2025
Complete – working
version of Internal Audit
plan for 2025-26 has
prioritised audits.   
2 Self-
assessment
Include explicit reference to QAIP and
monitoring progress of agreed actions. 
N/A Chief Officer (Audit
and Risk) 
May 2024
Complete – Included in
Internal Audit Annual
report for 2023-24 and
2024-25 
3 Self-
assessment
and EQA
The PRD process should be re-introduced for
all members of the Internal Audit team, to
ensure that all Internal Audit staff are able to
discuss and subsequently access appropriate
training and development activities.
Revised and refreshed Corporate
PRD process launched in May
2023.  Now that the re-structure of
the Audit team is complete and
recruitment for new posts is
underway the PRD process,
incorporating a formal assessment
against the skills and competency
framework, will be taken forward.
Audit Manager 
August 2024
December 2025
April 2026
Complete – PRD
conversations reinstated
from April 2026 for all staff. 
Additionally, Chief Officer
undertakes 6-monthly 121
meetings with all staff. 
4 Self-
assessment
and EQA
Review current best practice in relation to
assurance mapping and how other public
bodies use this to inform the Internal Audit
planning process, to ensure effective co-
ordination of activities with other assurance
providers.
The Chief Officer (Audit and Risk)
will progress work on developing
an approach to assurance mapping
in a way that allows this to inform
the 2025/26 Internal Audit Plan. 
Chief Officer (Audit
and Risk)
Audit Manager 
December 2024
August 2025
Complete – work
undertaken as part of the
approved 2025/26 audit
plan.  Other providers of
assurance also key point
of discussion with Chief
Officers in preparation of
the 2025/26 audit plan 
Page 19 of 20

Page 20

No. Source  Recommendation Management Response  Responsible Officer
and Target Date Status
5 EQA As risk management and, in particular, counter
fraud arrangements continue to mature, the
Chief Officer (Audit and Risk), should seek
independent, external assurance on the
adequacy of these arrangements. In doing so,
however, a pragmatic and cost-effective
approach must be taken. One possibility may
be peer review by another Local Authority,
similar to this Internal Audit external quality
assessment process.
The Chief Officer (Audit and Risk)
will ensure that due consideration
is given to the need for
independent external assurance on
the adequacy of risk management
and counter fraud arrangements. 
This will be undertaken on an
annual basis as part of the annual
planning and reporting process.
Chief Officer (Audit
and Risk) 
April 2025
April 2026
Complete – audit work in
these areas in 2025-26
audit plan was undertaken
by the Audit Manager,
independently of the Chief
Officer.  The provision of
an independent external
review will be considered
for future years.
6 EQA The Chief Officer (Audit and Risk) and the Audit
Manager should consider the proportionality of
the current review process, particularly at the
working paper stage, to establish whether there
may be scope for further streamlining and
improving the audit process while maintaining
appropriate oversight in relation to quality
control.
The recently implemented change
to the Audit team structure will
naturally result in a change to the
current review process.  After
allowing for the new structure to
embed, the Audit Manager will
consider the proportionality of the
review process ensuring that any
amendments still facilitate the
ability to properly supervise all
engagement to ensure that
objectives are achieved, and
quality is assured.
Audit Manager 
March 2025
May 2026
Revised Date – review of
audit methodology
ongoing looking at all
aspects of process to
modernise work of the
audit team, identify
improvement areas and
scope for streamlining. 
7 Self-
assessment
Preparation of a gap analysis, comparing the
requirements of the PSIAS with the new Global
Internal Audit Standards (GIAS) and identifying
actions to ensure conformance.
N/A Audit Manager 
December 2025
August 2026
Revised Date – gap
analysis is complete, work
now progressing on
ensuring Internal Audit
conforms with GIAS, with
full self-assessment to be
carried out during 2026-
27. 