North Lanarkshire Council
Report
Adult Care and Social Work Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref  DF/MF/KW Date 16/05/23 
Community Alarm Analogue to Digital Transition and Service
Review Update 
From  Diane Fraser, Chief Officer (Adult Social Work Services) 
E-mail fraserd@northlan.gov.uk Telephone 01698 332001 
Executive Summary 
This report informs Committee of the current position in relation to the Community Alarm
Service, particularly describing the drivers for undertaking a review of the service and
anticipated outcomes; and the Service’s transition from an Analogue to Digital
infrastructure. 
Recommendations 
It is recommended that the Adult Care and Social Work Committee: 
(1) Acknowledge the contents of this Community Alarm Service Report.
(2) Acknowledge the work being undertaken to ensure a seamless transition from
analogue to digital and the work to date. 
(3) Acknowledge the progress to date and work ongoing regarding the Community
Alarm Service review including the review of co-dependent services, particularly
Home Support Out of Hours provision, Social Work Emergency Services and
Registered Social Landlords.
(4) Acknowledge the position with current and future charging for the service.
(5) Acknowledge that recommendations will come back to the committee for
endorsement from the review.    
The Plan for North Lanarkshire
Priority  Improve the health and wellbeing of our communities
Ambition statement
(13) Improve preventative approaches including self-management
and giving people information and choice over supports and
services

Page 2

1. Background 
1.1 The Community Alarm Service supports people in North Lanarkshire live safely in their
own home by providing a range of responses depending on the individual
circumstances of calls made through the button and box in each person’s home. The
responses include: 
• Providing reassurance 
• Contacting a friend or family member to visit 
• Arranging a home support worker to attend 
• Contacting GP or Emergency Services 
1.2 The service operates 24 hours per day, 7 days a week, 365 days per year.   When the
individual activates the alarm, a signal is sent via the telephone line to the alarm
receiving centre in North Lanarkshire which is staffed 24 hours a day, 365 days a year.
A Response Advisor (call handler) speaks directly to the person to find out what kind
of assistance is required. 
1.3 The service provides 7,500 people in North Lanarkshire with the confidence that they
can call for help at any time of the day or night, every day of the year and is an essential
service when people experience particular difficulties such as a fall or sudden illness. 
1.4  The majority of people live in their own home however the service also provides cover
to all tenants living within NLC Sheltered Housing Complexes during out of hours and
variously to registered social landlords. 
1.5 The Community Alarm Service currently provides a telecare service to around 6,500
service users using dispersed analogue community alarms and to around 1,000 users
within sheltered accommodation. 
1.6 The service receives on average 1,000 alarm activations per day.  Approximately 20%
of these daily activations result in a Home Support Worker responding to support the
person in their own home, to support with either personal care or in the event of a fall. 
Most alarm calls are for reassurance, essential to maintaining people in their own
homes. 
1.7 In addition to the basic button and box which people generally associate with
Community Alarms, there are over 1,000 pieces of assistive technology programmed
through to the alarm receiving centre. This ranges from door contacts to hard wired
smoke detectors for individuals with cognitive impairment. 
1.8 In 2020, as part of the centralisation of Care at Home, the service was relocated to the
Dalziel Building to sit alongside the centralised Home Support Service, strengthening
links and connections. Because of the responsive nature of the support offered through
Community Alarms, as well as providing core service it also provides resource to
support the Home Support Service, particularly out of hours, as well as significant
support to the Social Work Emergency Service. The reach and stretch of the service
requires a review of the operating model. 
1.9 By 2025 all analogue telephone services in the UK will be switched off and replaced by
digital systems using internet protocol (IP) technology. Telecommunication suppliers
are well on the way to making this switch to IP networks. Scotland’s telecare service
providers including health and social care partnerships, housing associations and many
other organisations who use analogue connectivity to deliver their services, need to
upgrade.

Page 3

1.10 North Lanarkshire Health and Social Care Partnership (NL H&SCP) and North
Lanarkshire Council (NLC) have invested significantly in early intervention and
supported self-management for over a decade, with support for change and investment
across all sectors which focus on wellbeing. The Community Alarm Service is a key
part of supporting self-management with technological advancements creating the
opportunity to move from being a crisis response service to being more proactive and
preventative. 
1.11 The above circumstances summaries the importance of the Community Alarms
Service, the changes to the digital infrastructure and need to review the operating
model for the service. A review of the Community Alarms Service will develop options
for the future service model that capitalise on new ways of working using digital
technology, to establish community alarm and telecare services that are person-
centred, and outcome focused, and support the achievement of the priorities and
ambitions of the North Lanarkshire Health and Social Care Strategic Commissioning
Plan 2023-26 
2. Report 
Community Alarm Service Review 
2.1 In line with the Digital Health and Care Strategy, a joint initiative between the Scottish
Government and COSLA published in October 2021, we aim to improve the health and
wellbeing in our communities. We must examine the current community alarm service
and identify areas for development or changes required to the service to facilitate a
more positive outcome for our citizens. Digital transformation must encompass the full
range of health, social care and wellbeing services commissioned and provided by
Health Boards, by Integration Authorities and by Local Authorities and their third and
independent sector partners. Importantly, it extends as well to informal care, self-care,
prevention, and public health. 
2.2 This community alarm review will ensure that we are providing a person-centred and
outcome focused approach to our community alarm and telecare service delivery that
puts the citizen at the centre to ensure that new ways of working and technology will
meet the long-term needs of the people of North Lanarkshire (Independent Review of
Adult Social Care Scotland). 
2.3 The review will consider the current service delivery model and involve communities,
service users, families, carers, staff, and other key stakeholders to have their say in
development options for the future service model that will deliver the best outcomes for
users. 
2.4  Focus groups will be a key aspect of this review to allow the views and wishes of our
communities and services who have input to our Community Alarm Service to have
their voices heard. These focus groups will ensure that we are building towards a
person centre service that will meet the ongoing and future needs of the people who
require to use the service and those who may require to use the service in the future.
In addition, surveys will be sent to key stakeholders including for example GP services
across North Lanarkshire for their feedback on the existing service and future needs.

Page 4

2.5  Focus Groups will include but will not be limited to: 
• Community Alarm Service 
• Home Support 
• Social Work Services (Social Work/Integrated Rehab Team/Integrated Day     
Service /Locality Support Service/Mental Health) 
• Health Care (Acute/District Nurses/GP’s/Falls Team/Pharmacy) 
• 3rd Sector (VANL/Getting Better Together Shotts) 
• Carers (Carers Together/MacMillan) 
• Housing Services including Registered Social Landlords 
2.6  A range of data sources across a variety of systems in use in North Lanarkshire will
provide essential information regarding the current community alarm usage and will
allow us to detail how and who we support in our communities. This data will also help
us determine how we currently use the resources within the Community Alarm Service.   
2.7 Using one of our third sector partners we will interview around one hundred individuals
living in North Lanarkshire who have had a Community Alarm Service recently,
currently use the service or a carer of a family member of someone using the service.  
2.8 We will analyse and interpret the range of feedback that has been gathered by the
service from the public, from families and wider stakeholders contacting the service.   
2.9  We also have Care Inspectorate Inspection Reports of the service and will use the
information provided to enhance our learning of the service overall. The review will
consider the recommendation to review the registration of the service. 
2.10 The move from an Analogue ARC to a Digital ARC will require additional ongoing
resources within the Community Alarm Service team to implement and manage the
new operational environment. There will be various Device Management Platforms
(DMP) that will need to be utilised to monitor, configure and setup new alarms onto the
new Digital ARC, and this additional requirement needs to be included in the resource
review of the service. 
2.11  The service has not been included in any of the recent service reviews of the linked
services it supports. It is therefore important that all areas of support the Community
Alarm Service provides are included to ensure that proper management and
governance structures are in place to support the transition to a new digital platform. 
Analogue to Digital   
2.12  Telephone lines in the UK are being upgraded to digital technology. The process of
migrating to digital telephone lines has already started. The rollout is scheduled to be
completed by 2025, when analogue telephone services in the UK will be switched off
and replaced by digital systems using internet protocol (IP) technology. 
2.13 Telecommunication suppliers are well on their journey to making this switch to ‘IP
networks’.  Any systems relying on analogue lines, such as telecare, will be affected by
this change. Individuals who have been provided with Analogue telecare equipment
from North Lanarkshire Council must have their equipment updated to Digital ready
devices to continue to receive a safe and reliable service. 
2.14 North Lanarkshire is being supported in this transition by the Digital Office for Scottish
Local Government. Across Scotland, most current solutions use analogue dial-up
protocols to carry status and alarm signalling between the alarms devices in users’
homes and the Alarm Receiving Centres (ARC) - North Lanarkshire’s ARC is based in

Page 5

the Dalziel Building in Motherwell.  Digital IP telephone lines are not designed to support
these analogue protocols meaning that there is a risk that telecare alarm signalling will
not operate reliably. This may result in a higher number of failed calls and redials being
seen by the Community Alarm responders on the ARC system. 
2.15  Current telecare equipment is connected to an individual’s home phone telephone line.
The new digital solutions being installed connect to a home’s Broadband Router and
from there connect to the IP telephone network. These require mains power to operate,
but if there is a mains failure in the house the digital connection (and therefore the
Community Alarm) would not work.  Backup connection for community alarms is
provided via the mobile telephone network using a SIM card in the digital alarm. The
currently installed analogue alarms do not have a SIM and therefor have no resilience
in the event of a power outage. 
2.16  This transition to digital will require reviewing all the alarm devices that are in place
within homes in the community and sheltered house residencies and replace these
current analogue devices with digital ready alarm devices. There will also be a
requirement for digitally enabled peripherals such as falls detectors, door contacts etc,
to be thoroughly tested to ensure that they are compatible with any new digital alarm
receiving centre and alarm device.  The ability to connect existing interconnected
fire/smoke detectors via the digital alarm is currently not available.  Some
manufacturers are working on solutions and have indicated there may soon be an
ability to connect with some specific mainstream supplier products.   
2.17  We have already changed over 1900 analogue alarms, with a further 600 scheduled to
be exchanged by June 2023 to meet the planned change over dates advised by the
Telephony providers. 
2.18  There will be a requirement for the implementation of a digital ARC in North Lanarkshire
to replace our current Analogue ARC to safely allow for calls to be transmitted through
the digital network. The requirement of a new digital ARC to support this transition has
allowed North Lanarkshire to work with the Digital Office for Local Government to create
a tender for a national shared digital ARC. This will allow the Partnership to adopt a
new Digital Solution that will meet future requirements and can be customised to our
specific operational requirements.  This work has included 13 other local authorities to
ensure that a robust and secure solution can be found. The tender for this solution was
published in March 2023, with a planned award date of June 2023. 
2.19 North Lanarkshire currently runs PNC 8.1 an analogue ARC provided by Tunstall
Healthcare (UK) Ltd. The current contract runs until the 31st of March 2023 and is being
extended for 1 year. 
2.20  North Lanarkshire Council have committed to be part of a Nationally Procured Digital
Alarm Receiving Centre, led by the Digital Office. This procurement is now live, and the
anticipated award date is the end of June 2023. North Lanarkshire will be one of the
first adopters.   
2.21 Funding was secured from Technology Enabled Care (TEC) Scotland to the sum of
£15k to support us to carry out a telecare service review in anticipation of Analogue to
Digital transition.

Page 6

Community Alarm Charging 
2.22 From 14 September 2020 a charge of £3.40 per week (49p per day) was introduced,
with the rate remaining the same since that time. Any calls made to the response
centre are also billed as normal telephone calls by the person’s telephone company. 
2.23 At the time of introducing the charge everyone with a Community Alarm was offered a
full financial assessment. Anyone receiving a service since or considering a service is
offered a financial assessment to check their income is fully maximised. In these
uncertain times and recognising the cost-of-living pressures, the importance of this offer
is recognised. Anyone whose circumstances change or who is concerned about the
affordability is also encouraged to discuss this with the service with further assistance
offered. 
2.23 The weekly charge of £3.40 was introduced at the North Lanarkshire Council budget
setting meeting on 24th February 2020 which was consistent with the average charge
in Scotland as per 2019/20 Audit Scotland Local Government Overview report. North
Lanarkshire was one of the last local authority areas in Scotland to introduce a charge.
The total projected annual value of the approved charge was £1.410m. 
2.24 It was recognised that the agreed charge would support the Council and the Integration
Joint Board to continue to deliver this service to a high standard through having the
appropriate staffing and financial resources to meet the needs of those who use the
service. 
2.25 It should also be noted that the transition from Analogue to Digital alarms will attract
further operating costs as each alarm will have as a minimum one roaming SIM card,
and perhaps two if there is no home broadband connection that can be used as a
primary connection to the ARC. Current costs for these roaming SIM cards are £4.00
per month per unit, the cost of which could increase annually in line with inflation. The
Digital Office have indicated that they will engage with Telecom suppliers to try and
negotiate a Social Tariff, however this has not progressed as yet. Based on a current
installed estate of 7,500 alarm units this will bring an operating cost of between
£360,000 and £450,000 per annum (based on £4.00 per month current charge or an
anticipated £5.00 per month) to support the new digital alarms. 
2.23    Due to the Covid-19 outbreak introduction of the charge for community alarm was
delayed until September 2020.  This delay ensured that the communication to
recipients and support with enquiries and financial assessment was effectively
resourced. 
2.24    It was agreed that a 4 weekly invoice would be issued to people receiving the community
alarm service. As the charge has progressed the service has supported people and
their families in setting up direct debit payments for the community alarm charge. As a
result of the system supporting billing, unfortunately when paying the charge via a direct
debit an invoice continues to be issued every 4 weeks as the system is unable to
identify and remove those service users from the billing system. 
2.25 The volume of invoices now being issued is excessive, with around 83,000 invoices
being issued over the course of the last financial year.  To improve the experience for
people in receipt of a community alarm, or for family members paying it on their behalf,
and to minimise the oncome lost through the administration of the billing process,
improvements to the billing system, alternatives, and a wider range of options for
payment are being explored.

Page 7

2.26 It is important that we move to as position of issuing less invoices and issuing them to
reflect the payments arrangements that suit people. Consideration is being given to
introducing the options of paying annually or quarterly for community alarms which may
be attractive to some recipients and would reduce the cost associated with issuing
invoices. 
2.26    Income generated within the current financial year 2022/23 at Period 12 is £822k, with
a forecasted outturn of £981k for the full year.  Income generation while substantial falls
short of the initial estimated income generation of £1.410m which was an over
estimation evident as a result of cleansing of the information supporting the
assumptions in the calculation. 
2.27 Non-payment of around £280k of charges has accrued. Given the age profile and
vulnerability of the people supported via the community alarm, the service would like to
be able to contact all service users more quickly to support with alternative payment
methods and to offer financial reassessment. 
2.28   The income generated from the charge for community alarms is important to the
continued development of the service and increased operating costs associated with
digital advancement. It is however important to note that the Council had not pursued
the recovery of debt and as noted in previous Committee Reports, given the
vulnerability of people using the service individual community alarms will not be cut off
due to non-payment. 
2.27    The review of the current service will include a review of the staffing resources needed
to support the charging process.   
3. Measures of success 
3.1  The review will consider the current service delivery model and involve communities,
service users, families, carers, staff, and other key stakeholders to have their say in
development options for the future service model that will deliver the best outcomes for
people. The review will also ensure that the service is digitally ready to continue to
provide a safe and reliable service.   
4. Supporting documentation   
None 
Diane Fraser
Chief Officer (Adult Social Work Services)

Page 8

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☒ No ☐  
If Yes, please provide a brief summary of the impact? 
An EQIA and Fairer Scotland Impact Assessment will be undertaken as part of the
review process.   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☒
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The future financial impact will be explored fully as part of the review process. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
HR Business partners have been fully engaged in the design and development of
the review process and will be key partners in undertaking analysis of the
information gathered. 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☒ No ☐  
Legal impacts will be fully explored as part of the review process. 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?

Page 9

Yes ☒ No ☐  
A data protection impact assessment will be undertaken as part of the review
process 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
The risk register will be updated in line with the findings and outcome of the review
of the service.
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.