NORTH AYRSHIRE COUNCIL 
24th May 2023                                                                                                                                                            
Planning Committee 
Locality  North Coast and Cumbraes
Reference 23/00131/PP
Application Registered 22nd February 2023
Decision Due 22nd April 2023
Ward North Coast 
Recommendation  Approved subject to Conditions 
__________________________________________________________________ 
Location  Former Coal Terminal Hunterston West Kilbride
Ayrshire  
Applicant  XLCC F.A.O. Mr Alan Mathers 
Proposal  Variation of condition 11 of planning permission
N/22/00133/PPPM relating to the construction of a
high voltage sub-sea cable manufacturing facility
___________________________________________________________________ 
1. Description 
This can be ascertained by reference to the attached plans and photographs. 
Planning permission is sought to vary Condition 11 of permission 22/00133/PPPM. That
permission granted planning permission in principle for the erection of a high voltage cable
manufacturing facility, including detailed planning permission for the construction of a 185m
high extrusion tower with associated factories, research and testing laboratories, offices
with associated stores, transport, access, parking and landscaping with on-site generation
and electrical infrastructure and cable delivery system. 
Condition 11 of the permission currently states, 
Prior to commencement of the development of the tower, details of a financial bond to be
secured with the land owner for the removal of the tower in the event of redundancy shall be
submitted to North Ayrshire Council, as Planning Authority, for written approval. Any such
bond shall be retained through the life of the development with confirmation to be provided
to North Ayrshire Council, as Planning Authority, on a yearly basis following completion of
the tower.

Page 2

The reason Condition 11 was imposed is as follows, 
To ensure steps are in place to remove the tower should the site become redundant, in the
interest of visual amenity, and in recognition of the landowner being ultimately responsible
for compliance with any conditions. 
This application seeks to change the wording to read, 
Prior to commencement of the works above ground level of development of the tower,
details of a financial bond to be secured with the landowner for the removal of the tower in
the event of redundancy shall be submitted to North Ayrshire Council, as Planning Authority,
for written approval. Any such bond shall be retained through the life of the development
with confirmation to be provided to North Ayrshire Council, as Planning Authority, on a
yearly basis following completion of the tower. 
The use of the site is restricted by condition to the construction, repair and decommissioning
of large marine related structures. This is further restricted to oil rigs, platforms and similar
structures that haver served the oil and gas and offshore renewable industries. It is not
proposed to change this restriction. 
The application also originally sought to vary Condition 12 to lengthen the time before a
redundant tower should be removed. This part of the application was withdrawn by the
applicant, following an indication that it would be unlikely to be recommended to the
Planning Committee for approval. 
An application to vary Conditions 11 and 12 (ref: 22/00759/PP) was withdrawn in February
2023 following advice that it was unlikely to be supported. That application sought to vary
the wording of Condition 11 to change reference from a financial bond to a binding
agreement as well as extend the time period in Condition 12. 
The site is some 51ha in area, including existing access roads and jetty. The site is a former
coal yard, which has been vacant since 2016. The development would make use of an
existing access and the existing jetty and port. The site is identified in the Local
Development Plan (LDP) as part of the Hunterston Strategic Development Area and
suitable for business and industrial development. The Southannan Sands Site of Special
Scientific Interest ("the SSSI") is some 85m to the west. The Hunterston House Tree
Preservation Order ("the TPO") runs along the eastern boundary of the site. 
The relevant policy of the Local Development Plan adopted November 2019 (LDP) is
considered to be Strategic Policy 2: Placemaking; and Policy 15: Landscape and Seascape. 
National Planning Policy 4 (NPF4) was adopted 13th February 2023. NPF4 identifies
Hunterston as a Strategic Asset. NPF4 is considered to be a material consideration for this
application. The relevant policy considered to be Policy 14. The Scottish Government's
Planning Circular 4/1998 sets out their policy on the use of planning conditions. 
Relevant Development Plan Policies 
Strategic Policy 2

Page 3

Our Placemaking policy will ensure we are meeting LOIP priorities to make North Ayrshire
safer and healthier by ensuring that all development contributes to making quality places.
The policy also safeguards, and where possible enhances environmental quality through
the avoidance of unacceptable adverse environmental or amenity impacts. We expect that
all applications for planning permission meet the six qualities of successful places,
contained in this policy. This is in addition to establishing the principle of development in
accordance with Strategic Policy 1: Spatial Strategy. These detailed criteria are generally
not repeated in the detailed policies section of the LDP. They will apply, as appropriate, to all
developments. 
Six qualities of a successful place 
Distinctive
The proposal draws upon the positive characteristics of the surrounding area including
landscapes, topography, ecology, skylines, spaces and scales, street and building forms,
and materials to create places with a sense of identity. 
Welcoming
The proposal considers the future users of the site and helps people to find their way
around, for example, by accentuating existing landmarks to create or improve views
(including sea views), locating a distinctive work of art in a notable place or making the most
of gateway features to and from the development. It should also ensure that appropriate
signage and lighting is used to improve safety and illuminate attractive buildings.
Safe and Pleasant
The proposal creates attractive places by providing a sense of security, including by
encouraging activity, considering crime rates, providing a clear distinction between private
and public space, creating active frontages and considering the benefits of natural
surveillance for streets, paths and open spaces.
The proposal creates a pleasant, positive sense of place by promoting visual quality,
encouraging social and economic interaction and activity, and by considering the place
before vehicle movement.
The proposal respects the amenity of existing and future users in terms of noise, privacy,
sunlight/daylight, smells, vibrations, glare, traffic generation, and parking. The proposal
sufficiently investigates and responds to any issues of ground instability. 
Adaptable
The proposal considers future users of the site and ensures that the design is adaptable to
their needs. This includes consideration of future changes of use that may involve a mix of
densities, tenures, and typologies to ensure that future diverse but compatible uses can be
integrated including the provision of versatile multi-functional greenspace. 
Resource Efficient
The proposal maximises the efficient use of resources. This can be achieved by re-using or
sharing existing resources and by minimising their future depletion. This includes
consideration of technological and natural means such as flood drainage systems, heat
networks, solar gain, renewable energy and waste recycling as well as use of green and
blue networks. 
Easy to Move Around and Beyond
The proposal considers the connectedness of the site for people before the movement of
motor vehicles, by prioritising sustainable and active travel choices, such as walking, cycling

Page 4

and public transport and ensuring layouts reflect likely desire lines, through routes and
future expansions. 
Detailed Policy 15-Landscape & Seascape 
Landscape and Seascape 
We will support development that protects and/or enhances our landscape/seascape
character, avoiding unacceptable adverse impacts on our designated and non-designated
landscape areas and features. In particular, we will consider the following: 
a) National Scenic Areas
Development that affects the North Arran National Scenic Area including the need to
protect existing sport and recreation interests, will only be supported where:
i) the objectives of the designation and the overall integrity of the area will not be
compromised; or
ii) any significant adverse effects on the qualities for which the area has been
designated are clearly outweighed by social, environmental or economic benefits of
national importance. 
b) Special Landscape Areas
We will only support development which affects Special Landscape Areas where it
would not have an unacceptable impact on their special character, qualities and
setting. 
c) Wild Land
We will only support development within Wild Land areas where any significant
effects on the qualities of these areas can be substantially overcome by siting, design
or other mitigation. 
d) Local Landscape Features
Where appropriate, development should take into consideration its individual and
cumulative impacts on landscape features, including:
i) patterns of woodlands, fields, hedgerows and trees;
ii) lochs, ponds, watercourses, wetlands, the coast and wider seascape;
iii) settlement setting, including approaches to settlements;
iv) the setting of green network corridors, such as important transport routes and the
cycle and footpath network;
v) historic, natural and recreational features of interest, skylines and hill features,
including important views to, from and within them. 
For all development with the potential to have an impact on either Landscape Character or
Landscape features (including their setting), appropriate mitigation measures should be
considered as part of any planning application. Where there is potential for development to
result in significant adverse landscape/visual impact, a landscape and visual impact
assessment (LVIA) will be required. The Ayrshire Landscape Character Assessment (SNH,
1998) and North Ayrshire Settlement Development Strategy (Entec, 2008) provide further
information on designations such as Local Landscape Character Areas and the Potential
Limit of Development Expansion areas as shown on the map on page 81 and on our online
proposals map. These landscape assessment documents, and any new or updated

Page 5

landscape assessments, will be key considerations in determining whether development
proposals would be acceptable within the landscape. 
2. Consultations and Representations 
The application was subject to statutory neighbour notification procedures. There have
been seven objections received, including objections from Fairlie Community Council which
can be summarised as follows; 
1. The wording of Condition 11 should not change as it would risk the local area being
blighted by the tower which will dominate the landscape. The bond is required to ensure the
tower does not become an eyesore should it become redundant. The wording should
remain the same to ensure the tower is not a permanent blot on the landscape. Works below
ground level will still be visible.  
Response: The proposed wording is considered fully below. However, it is noted that the
proposed working would prevent any works above ground level, unless and until details of a
bond are provided. This means the changes to Condition 11 would not put the area at risk of
a redundant tower. It is not considered that works below ground level would be readily
visible outwith the site and this is considered further below. 
2. A bond must be required. Who would be liable to comply with the condition without a
bond? 
Response: Agreed. A bond would still be required by the terms of the varied condition.
Ultimately the landowner would be responsible for complying with any breaches of planning
control on their land. 
3. Condition 12 should remain the same as the time scales are appropriate to protect the
area in the event of the tower becoming redundant. 
Response: Agreed. Concerns regarding changes to Condition 12 were communicated to
the applicant and that part of the application has now been withdrawn. 
4. Any development of the site will have an impact on wildlife and residents. 
Response: Permission has already been granted for the development and such factors
were considered in the granting of that permission. This application relates specifically to a
condition and must be assessed in that context only.  
5. The applicant should not be allowed to continue to make piecemeal applications. If it were
considered in full it would be refused. 
Response: The original application was for permission in principle for the factory and full
permission for the tower. The other application is to provide details required by that
permission. The Planning Acts allow the submission of such applications and to vary
conditions.  
6. Fairlie Community Council do not consider the landowner to have the appetite for any risk
to them. Why were the community not consulted prior to the submission of the application.

Page 6

Response: Opinions on the character or intentions of the landowner are not relevant
material considerations. Under planning legislation, the landowner would be ultimately
responsible for any breaches of planning control on their land. This application seeks to vary
a condition and no prior consultation with the public is required. 
3. Analysis 
Planning permission in principle for the use of the land as a cable factory and detailed
permission for the construction of the tower has been granted. The principle of the
development is therefore established. The application considers only whether or not the
revised Condition 11 would accord with the LDP, NPF4, Scottish Government advice and
any other material considerations. 
Strategic Policy 2 of the LDP sets out the six qualities of a successful place. The relevant
quality is 'distinctive' which requires development to consider the local landscape. Policy 14
of NPF4 is essentially a reiteration of Strategic Policy 2. 
Policy 15 of the LDP states that support will be given the development that avoids
unacceptable adverse impacts on our landscape areas.
The revised wording of Condition 11 would allow works to commence at ground level and
below. This would essentially allow the foundations and basement level of the tower to be
commenced. 
The reason Condition 11 was imposed was to ensure steps are in place to remove the tower
should the site become redundant, in the interest of visual amenity, and in recognition of the
landowner being ultimately responsible for compliance with any conditions. 
The tower would be some 1450sqm in area. It would be sited some 440m north of the
southern boundary of the site and 75m west of the eastern boundary of the site. It would be
25m wide, west to east, and 58m in length, north to south. It would be approx. 1km south of
the settlement of Fairlie, as identified by the LDP. The site of the tower is within an existing
industrial yard. The site of the tower is surrounded to the south, east and north by trees
including the Hunterston House Tree Preservation Order (TPO). It would be approx. 2.8km
from Cumbrae to the west. Permission in principle has been granted for the factory buildings
which would surround the towers. Those buildings are expected to be approx. 25-30m in
height. 
Given all of the above, it is considered allowing the works up to ground level to commence
without a bond would have no impact on visual amenity or the wider landscape. As such the
amendment to the condition would accord with Strategic Policy 2 and Policy 15 of the LDP
and Policy 14 of NPF4. 
Planning Circular 4/1998 states that planning conditions should only be imposed where they
are necessary, relevant to planning, relevant to the development to be permitted,
enforceable, precise, and reasonable in all other respects. It is considered that the amended
condition would remain relevant to planning, relevant to the development, enforceable and
precise. The condition would remain necessary in respect of the tower i.e. the removal of the
tower in the case of redundancy, being a structure visible in public realm. The condition

Page 7

would also remain reasonable in that it would allow works which will not have an adverse
impact on visual amenity. 
Planning permission should therefore be granted for the variation of Condition 11 as set out
below. 
4. Full Recommendation 
Approved subject to Conditions 
Reasons for Decision 
Condition 
1. That the permission is for a high voltage cable manufacturing facility with associated
factories, research and testing laboratories, offices with associated stores, transport,
access, parking and landscaping with on-site generation and electrical infrastructure and
cable delivery system only and planning permission would be required for any other use
within Class 5 of the Town and Country Planning (General Permitted Development)
(Scotland) Order, as amended. 
Reason 
In recognition of the special justification for the tower and to retain control over the
site and re-assess the need for the tower in the event of a different operation. 
Condition 
2.  That the approval of North Ayrshire Council, as Planning Authority, with regard to the
siting, design and external appearance of all building and external plant or machinery,
including landscaping, means of access, internal roads, external lighting, sustainable travel
plan and low and zero carbon technology, shall be obtained before the development
permitted in principle is commenced. 
Reason 
In order that these matters can be considered in detail. 
Condition 
3. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by an assessment of on-site heat recovery and re-use, or a heat network
infrastructure plan, or demonstrable evidence that such schemes have been explored but
are not feasible for technical or economic reasons. 
Reason 
In order that the future proofing of the site for heat networks is properly considered as
required by Policy 31 of the LDP. 
Condition 
4. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by a Construction Management Plan and Code of Practice, including details
for monitoring and action against non-compliance. For the avoidance of doubt this shall
include an assessment of use of the rail and port connections as a first principle and the
prohibition of the use of the A78 through Fairlie, the B780/B781, the C26 and all local

Page 8

non-classified roads by construction vehicles and details of management of impact on the
core path and cycle rout network. 
Reason 
To ensure proper management of the construction process, including impact on the
road network. 
Condition 
5. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by details of an appointed Ecological Clerk of Works (ECoW). The details
shall include contact details, the scope and responsibilities of the ECoW as well as
confirmation of their power to halt or otherwise stop works which are not in accordance with
the mitigation measures identified in the EIA or others, as may be approved. 
Reason 
To ensure appropriate oversight of the construction of the development 
Condition 
6. Prior to development commencing the applicant shall implement the measures
detailed under Mitigation Measures Adopted as Part of the Project in Chapter 9
Hydrogeology, Geology and Ground Conditions of the submitted EIA report dated February
2022.  All documentation be verified by a suitably qualified Environmental Consultant and
submitted to the satisfaction of North Ayrshire Council, as Planning Authority. 
Reason 
To ensure proper consideration is given to ground conditions and ground water. 
Condition 
7. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by a Dust Management Plan. This shall include the measures detailed under
Mitigation Measures Adopted as Part of the Project in Chapter 13 Air Quality of the
submitted EIA report dated February 2022.  All documentation be verified by a suitably
qualified Environmental Consultant and submitted to the satisfaction of North Ayrshire
Council as Planning Authority. 
Reason 
To ensure proper management of dust throughout the construction period. 
Condition 
8. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by an assessment of the details in terms of the rated noise level, as defined in
`BS4142:2014+A1:2019, from the operation of the facility. The assessment must
demonstrate that the noise from the operation of the facility will not exceed the background
noise level at the curtilage of any existing or consented noise sensitive property at the time
of application and include details of a monitoring scheme for the first 12months of operation
of the facility. 
Reason 
To ensure proper consideration of potential noise from the development. 
Condition

Page 9

9. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by a scheme to treat surface water arising from the or otherwise affecting the
site, prepared in accordance with the principles and practices contained in 'The SuDS
Manual' (CIRIA report C7453, published November 2015) and the requirements of The
Water Environment (Controlled Activities) (Scotland) Regulations 2011, and certified by a
suitably qualified person, shall be submitted to North Ayrshire Council, as Planning
Authority, for written approval. 
Any scheme approved shall include details of proposed ground levels, finished floor levels,
and pre & post development overland flows that shall demonstrate that people and property
would not be put at flood risk during the designed storm event (1 in 200 return period plus an
allowance for climate change and urban creep) when the capacity of the proposed
infrastructure is exceeded. In accordance with the recommendations of the submitted FRA,
finished floor levels shall be set a minimum of 6m AOD, threshold levels shall be raised a
minimum of 150mm above external ground levels and all key external infrastructure shall be
elevated by at least 150mm or protected by bunds 
Reason 
To ensure proper consideration of surface water drainage. 
Condition
10. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by a habitat survey dated not more than 1 year prior to the date of the
submission of the application. 
Reason 
To ensure habitat and protected species considerations are of an appropriate date. 
Condition
11. Prior to commencement of the works above ground level of development of the
tower, details of a financial bond to be secured with the landowner for the removal of the
tower in the event of redundancy shall be submitted to North Ayrshire Council, as Planning
Authority, for written approval. Any such bond shall be retained through the life of the
development with confirmation to be provided to North Ayrshire Council, as Planning
Authority, on a yearly basis following completion of the tower. 
Reason 
To ensure steps are in place to remove the tower should the site become redundant,
in the interest of visual amenity, and in recognition of the landowner being ultimately
responsible for compliance with any conditions. 
Condition
12. Should the tower become redundant, it shall be removed within 6 months of
redundancy. For the avoidance of doubt, redundancy means the factory not becoming
operational within 3 years of construction of the tower or the factory ceasing to operate for a
period of more than 1 year after first becoming operational. 
Reason 
To ensure the timely removal of the tower should the site become redundant, in the
interest of visual amenity.

Page 10

Condition
13. The prior to commencement of the development of the tower, details of the external
finish shall be submitted to North Ayrshire Council, as Planning Authority, for written
approval. The development will thereafter be undertaken in accordance with any details as
may be approved and the tower maintained with those details unless otherwise agreed in
writing with the Planning Authority. 
Reason 
To ensure an appropriate external finish for the tower in the interest of visual amenity. 
Condition
14. The prior to the commencement of the development of the tower, a Dust
Management Plan for the control of dust from the construction of the tower shall be
submitted to North Ayrshire Council, as Planning Authority, for written approval. Thereafter
the development shall be undertaken in accordance with any Plan as may be approved. 
Reason 
To ensure proper management of dust throughout the construction period. 
Condition
15. That prior to the commencement of the development of the tower, a Construction
Management Plan and Code of Practice, including details for monitoring and action against
non-compliance shall be submitted to North Ayrshire Council, as Planning Authority, for
approval. Thereafter the construction shall be carried out only as approved by the Plan and
Code of Practice. For the avoidance of doubt this shall include an assessment of use of the
rail and port connections as a first principle and the prohibition of the use of the A78 through
Fairlie, the B780/B781, the C26 and all local non-classified roads by construction vehicles
and details of management of impact on the core path and cycle rout network. 
Reason 
To ensure proper management of the construction process, including impact on the
road network 
Condition
16. That prior to the commencement of the development of the tower, details of an
appointed Ecological Clerk of Works (ECoW) shall be submitted to North Ayrshire Council,
as Planning Authority, for approval. The details shall include contact details, the scope and
responsibilities of the ECoW as well as confirmation of their power to halt or otherwise stop
works which are not in accordance with the mitigation measures identified in the EIA or
others, as may be approved. The development will thereafter be undertaken only with the
oversight of the appointed ECoW. 
Reason 
To ensure proper oversight of the construction of the tower. 
Condition
17. The rated noise level, as defined in `BS4142:2014+A1:2019, from the operation of
the tower must not exceed the background noise level at the curtilage of any existing or
consented noise sensitive property at the time of application. 
Reason

Page 11

To ensure the operation of the tower does not cause undue noise disturbance or
sterilise the wider area for further development. 
Condition
18. The prior to the commencement of the development of the tower, that a scheme to
treat surface water arising from the or otherwise affecting the site of the tower, prepared in
accordance with the principles and practices contained in 'The SuDS Manual' (CIRIA report
C7453, published November 2015) and the requirements of The Water Environment
(Controlled Activities) (Scotland) Regulations 2011, and certified by a suitably qualified
person, shall be submitted to North Ayrshire Council, as Planning Authority, for written
approval. Thereafter, the certified scheme shall be implemented prior to the completion of
the development of the tower and maintained thereafter to the satisfaction of North Ayrshire
Council, as Planning Authority. 
Any scheme approved shall include details of proposed ground levels, finished floor levels,
and pre & post development overland flows that shall demonstrate that people and property
would not be piut at flood risk during the designed storm event (1 in 200 return period plus
an allowance for climate change and urban creep) when the capacity of the proposed
infrastructure is exceeded. In accordance with the recommendations of the submitted FRA,
finished floor levels shall be set a minimum of 6m AOD, threshold levels shall be raised a
minimum of 150mm above external ground levels and all key external infrastructure shall be
elevated by at least 150mm or protected by bunds 
Reason 
To ensure the proper treatment of surface water. 
Condition
19. Prior to the commencement of the tower, confirmation that the basement proposals
are sufficiently flood resilient/resistant, including an accompanying certified flood
management plan suitably addresses residual flood risk at the site form all sources of
flooding, certified by a suitable qualified person, shall be submitted in writing for the written
approval of North Ayrshire Council, as Planning Authority. 
Reason 
To ensure the risk of flooding to basement level proposal is suitable addressed. 
Condition
20. In the event that the works to commence the tower are not undertaken within 1 year
of the date of this permission, an updated habitat survey dated not more than 1 year prior to
the date of commencement shall be submitted to North Ayrshire Council, as Planning
Authority, for written approval prior to the commencement. 
Reason 
To ensure habitat and protected species considerations are of an appropriate date. 
Condition
21. Prior to the commencement of the development, details of omni-directional red
aviation warning lights to be fitted to the tower shall be submitted to North Ayrshire Council,
as Planning Authority, for approval in consultation with Prestwick Airport, Air Traffic Control
and the Ministry of Defence. The lighting will thereafter be fitted and retained thereafter in
accordance with any details as may be approved.

Page 12

Reason 
To meet the requirements of the relevant Air Authorities. 
Yvonne Baulk 
Head of Service           
For further information please contact Mr Iain Davies  on 01294 324320.

Page 13

Appendix 1 – Location Plan           
DO NOT SCALE Reproduced from the Ordnance Survey mapping with the permission of the Controller of Her Majesty’s Stationery
Office © Crown Copyright.  Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings.
North Ayrshire Council Licence Number 100023393.