Planning Committee
22 March 2023 
At a Meeting of the Planning Committee of North Ayrshire Council at 2.00 p.m.
involving a combination of participation by remote electronic means and physical
attendance within the Council Chambers, Irvine. 
Present (Physical Participation)
Robert Foster, Stewart Ferguson, Cameron Inglis and Davina McTiernan. 
Present (Remote Participation)
Timothy Billings, Scott Davidson, Amanda Kerr, Jim Montgomerie, Ian Murdoch and
Chloé Robertson. 
In Attendance
Y. Baulk, Head of Service (Housing & Public Protection) and J. Miller, Chief
Planning Officer (Place); and R. Lynch, Senior Manager (Legal Services), J.
Niven, Solicitor (Legal Services) and C. Stewart and S. Wilson, Committee
Services Officers (Democratic Services) (Chief Executive’s Service). 
Chair
Councillor Foster in the Chair. 
1. Declarations of Interest 
In respect of Agenda Item 3 (23/00070/PP: Site to Former Coal Terminal,
Hunterston, West Kilbride), Councillor Murdoch made a transparency statement
advising that he was as a member of Hunterston Park Liaison Committee.  Having
applied the objective test, he assessed that it was not an interest in terms of the
Councillors’ Code of Conduct which would prevent him from taking part in the
decision. Accordingly, Councillor Murdoch did not require to leave the meeting for
this item of business. 
2. Minutes 
The Minutes of the Meeting held on 22 February 2023 were confirmed and signed in
accordance with Paragraph 7 (1) of Schedule 7 of the Local Government (Scotland)
Act 1973. 
3. 23/00070/PP: Site to Former Coal Terminal, Hunterston, West Kilbride 
XLCC have applied for a Variation of conditions 9 and 18 of planning permission
N/22/00133/PPPM relating to the construction of a high voltage sub-sea cable
manufacturing facility at the site to Former Coal Terminal, Hunterston, West Kilbride. 
The Chief Planning Officer advised that following preparation of the report,
comments had been received from Fairlie Community Council and from a firm of
Solicitors instructed by the Community Council.  The Chief Planning Officer informed
the Committee of the nature of comments received and the officer response.

Page 2

Members asked questions and were provided with information in relation to: 
• the risk of flooding with particular reference to finished floor levels;
• the rationale for the application coming forward at this time and whether there
was an overall timeline for the full application; and
• the nature of a previous decision by the Planning Committee, in respect of a
complete ‘as one’ application coming to the Committee for determination. 
Councillor Inglis, seconded by Councillor Ferguson, moved that the application be
granted, subject to conditions. There being no amendment, the motion was declared
carried. 
The Committee agreed to grant the application, subject to the following conditions: 
1. That the permission was for a high voltage cable manufacturing facility with
associated factories, research and testing laboratories, offices with associated
stores, transport, access, parking and landscaping with on-site generation and
electrical infrastructure and cable delivery system only and planning
permission would be required for any other use within Class 5 of the Town
and Country Planning (General Permitted Development) (Scotland) Order, as
amended. 
2. That the approval of North Ayrshire Council, as Planning Authority, with
regard to the siting, design and external appearance of all building and
external plant or machinery, including landscaping, means of access, internal
roads, external lighting, sustainable travel plan and low and zero carbon
technology, shall be obtained before the development permitted in principle is
commenced. 
3. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by an assessment of on-site heat recovery and re-use, or a heat
network infrastructure plan, or demonstrable evidence that such schemes
have been explored but are not feasible for technical or economic reasons. 
4. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by a Construction Management Plan and Code of Practice,
including details for monitoring and action against non-compliance. For the
avoidance of doubt this shall include an assessment of use of the rail and port
connections as a first principle and the prohibition of the use of the A78
through Fairlie, the B780/B781, the C26 and all local non-classified roads by
construction vehicles and details of management of impact on the core path
and cycle rout network. 
5. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by details of an appointed Ecological Clerk of Works (ECoW).
The details shall include contact details, the scope and responsibilities of the
ECoW as well as confirmation of their power to halt or otherwise stop works
which are not in accordance with the mitigation measures identified in the EIA
or others, as may be approved.

Page 3

6. Prior to development commencing the applicant shall implement the
measures detailed under Mitigation Measures Adopted as Part of the Project
in Chapter 9 Hydrogeology, Geology and Ground Conditions of the submitted
EIA report dated February 2022. All documentation be verified by a suitably
qualified Environmental Consultant and submitted to the satisfaction of North
Ayrshire Council, as Planning Authority. 
7. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by a Dust Management Plan. This shall include the measures
detailed under Mitigation Measures Adopted as Part of the Project in Chapter
13 Air Quality of the submitted EIA report dated February 2022. All
documentation be verified by a suitably qualified Environmental Consultant
and submitted to the satisfaction of North Ayrshire Council as Planning
Authority. 
8. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by an assessment of the details in terms of the rated noise
level, as defined in `BS4142:2014+A1:2019, from the operation of the facility.
The assessment must demonstrate that the noise from the operation of the
facility will not exceed the background noise level at the curtilage of any
existing or consented noise sensitive property at the time of application and
include details of a monitoring scheme for the first 12months of operation of
the facility. 
9. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by a scheme to treat surface water arising from the or otherwise
affecting the site, prepared in accordance with the principles and practices
contained in 'The SuDS Manual' (CIRIA report C7453, published November
2015) and the requirements of The Water Environment (Controlled Activities)
(Scotland) Regulations 2011, and certified by a suitably qualified person, shall
be submitted to North Ayrshire Council, as Planning Authority, for written
approval. Any scheme approved shall include details of proposed ground
levels, finished floor levels, and pre & post development overland flows that
shall demonstrate that people and property would not be put at flood risk
during the designed storm event (1 in 200 return period plus an allowance for
climate change and urban creep) when the capacity of the proposed
infrastructure is exceeded. 
10. That further application(s) for approval under the terms of Condition 1 shall be
accompanied by a habitat survey dated not more than 1 year prior to the date
of the submission of the application. 
11. Prior to commencement of the development of the tower, details of a financial
bond to be secured with the landowner for the removal of the tower in the
event of redundancy shall be submitted to North Ayrshire Council, as Planning
Authority, for written approval. Any such bond shall be retained through the
life of the development with confirmation to be provided to North Ayrshire
Council, as Planning Authority, on a yearly basis following completion of the
tower.

Page 4

12. Should the tower become redundant, it shall be removed within 6 months of
redundancy. For the avoidance of doubt, redundancy means the factory not
becoming operational within 3 years of construction of the tower or the factory
ceasing to operate for a period of more than 1 year after first becoming
operational. 
13. The prior to commencement of the development of the tower, details of the
external finish shall be submitted to North Ayrshire Council, as Planning
Authority, for written approval. The development will thereafter be
undertaken in accordance with any details as may be approved and the
tower maintained with those details unless otherwise agreed in writing with
the Planning Authority. 
14. The prior to the commencement of the development of the tower, a Dust
Management Plan for the control of dust from the construction of the tower
shall be submitted to North Ayrshire Council, as Planning Authority, for
written approval. Thereafter the development shall be undertaken in
accordance with any Plan as may be approved. 
15. That prior to the commencement of the development of the tower, a
Construction Management Plan and Code of Practice, including details for
monitoring and action against non-compliance shall be submitted to North
Ayrshire Council, as Planning Authority, for approval. Thereafter the
construction shall be carried out only as approved by the Plan and Code of
Practice. For the avoidance of doubt this shall include an assessment of use
of the rail and port connections as a first principle and the prohibition of the
use of the A78 through Fairlie, the B780/B781, the C26 and all local non-
classified roads by construction vehicles and details of management of
impact on the core path and cycle rout network. 
16. That prior to the commencement of the development of the tower, details of
an appointed Ecological Clerk of Works (ECoW) shall be submitted to North
Ayrshire Council, as Planning Authority, for approval. The details shall
include contact details, the scope and responsibilities of the ECoW as well
as confirmation of their power to halt or otherwise stop works which are not
in accordance with the mitigation measures identified in the EIA or others, as
may be approved. The development will thereafter be undertaken only with
the oversight of the appointed ECoW. 
17. The rated noise level, as defined in `BS4142:2014+A1:2019, from the
operation of the tower must not exceed the background noise level at the
curtilage of any existing or consented noise sensitive property at the time of
application. 
18. The prior to the commencement of the development of the tower, that a
scheme to treat surface water arising from the or otherwise affecting the site
of the tower, prepared in accordance with the principles and practices
contained in 'The SuDS Manual' (CIRIA report C7453, published November
2015) and the requirements of The Water Environment (Controlled Activities)
(Scotland) Regulations 2011, and certified by a suitably qualified person,
shall be submitted to North Ayrshire Council, as Planning Authority, for

Page 5

written approval. Thereafter, the certified scheme shall be implemented prior
to the completion of the development of the tower and maintained thereafter
to the satisfaction of North Ayrshire Council, as Planning Authority. Any
scheme approved shall include details of proposed ground levels, finished
floor levels, and pre & post development overland flows that shall
demonstrate that people and property would not be put at flood risk during
the designed storm event (1 in 200 return period plus an allowance for
climate change and urban creep) when the capacity of the proposed
infrastructure is exceeded. 
19. Prior to the commencement of the tower, confirmation that the basement
proposals are sufficiently flood resilient/resistant, including an accompanying
certified flood management plan suitably addresses residual flood risk at the
site from all sources of flooding, certified by a suitable qualified person, shall
be submitted in writing for the written approval of North Ayrshire Council, as
Planning Authority. 
20. In the event that the works to commence the tower are not undertaken within
1 year of the date of this permission, an updated habitat survey dated not
more than 1 year prior to the date of commencement shall be submitted to
North Ayrshire Council, as Planning Authority, for written approval prior to
the commencement. 
21. Prior to the commencement of the development, details of omni-directional
red aviation warning lights to be fitted to the tower shall be submitted to
North Ayrshire Council, as Planning Authority, for approval in consultation
with Prestwick Airport, Air Traffic Control and the Ministry of Defence. The
lighting will thereafter be fitted and retained thereafter in accordance with
any details as may be approved. 
4. 23/00058/PP: Site to Oldhall ERF 16 – 20 Murdoch Place, Oldhall West
Industrial Estate, Irvine 
Submitted report by the Chief Planning Officer regarding Proposal to increase flue
height at energy recovery facility by an additional 10m as alternative to permitted
scheme under refs. 20/00819/PPM and 19/00539/PPM. 
Councillor Billings, seconded by Councillor McTiernan, moved that the application be
granted, subject to conditions. There being no amendment, the motion was declared
carried. 
The Committee agreed to grant the application, subject to the following condition: 
1. That the flue stack shall be fitted with an omni-directional red warning light
which requires to be commissioned immediately upon erection of the stack.
The warning light shall be operated continuously during hours of darkness
and permanently retained in working condition thereafter unless otherwise
agreed in writing with North Ayrshire Council as Planning Authority.

Page 6

5. 23/00120/PP: Site to Oldhall ERF 16 – 20 Murdoch Place, Oldhall West
Industrial Estate, Irvine 
Submitted report by the Chief Planning Officer regarding Proposal for Variation of
Condition 1 of planning permissions 19/00539/PPM and 20/00819/PPM to facilitate
temporary 24 hour working on the slip forming of the approved concrete bunker. 
Members asked questions and were provided with information in relation to: 
• noise and addition of traffic movement at night, particularly in relation to trucks
and the frequency of truck movements;
• the routes that the trucks would use and whether they would go through any
residential areas on their way to and from the site; and
• the potential issue of light pollution at night and whether this could have an
adverse impact on the amenity of nearby residential properties (or commercial
property that provided overnight accommodation). 
The Chief Planning Officer advised Committee that only one condition was involved
in this application. Whilst the report mentioned a ‘Temporary Construction Hours of
Variation of Condition’ document, this was a typographical error and should have
read ‘Temporary working hours supporting statement’ (which was available online).
Accordingly, Recommended Condition 1 should therefore be amended to reflect this. 
Councillor Billings, seconded by Councillor Kerr, moved that the application be
granted, subject to conditions (as revised). There being no amendment, the motion
was declared carried. 
The Committee agreed to grant the application, subject to the following condition:- 
1. That condition 1 of planning permissions 19/00539/PPM and 20/00819/PPM
are hereby amended as follows: 
“That the development hereby approved shall be implemented in accordance with
the details and recommendations contained in the supporting accommodation
submitted with the planning application unless otherwise indicated below, and in
accordance with the details submitted in the ‘Planning Statement - Temporary
Construction Hours’ document dated 15/02/2023, all to the satisfaction of North
Ayrshire Council as Planning Authority.” 
For the avoidance of doubt, all other conditions attached to the above planning
permissions are unaffected by this decision and shall continue to have effect. 
6. 23/00097/CON: Site at Benthead Farm, Kilwinning 
Submitted report by the Chief Planning Officer regarding proposal for installation of a
solar farm with a generating capacity of up to 63MW and a battery storage system
with a capacity of up to 31.1MW and associated infrastructure.

Page 7

Members asked questions and were provided with information in relation to: 
• consideration of any risk assessment particularly in relation to fire risk, the
issue of battery storage and the size of storage area that would require to be
put in place for this;
• the issue of fencing, in terms of protecting the site from any external
interference/disturbance; and
• the intended height of the deer fencing in relation to site boundaries. 
Councillor Davidson, seconded by Councillor McTiernan, moved that the Committee
agree it had no objections to the application, subject to conditions. There being no
amendment, the motion was declared carried. 
The Committee indicated that it had no objections to the application, subject to the
following conditions: 
1. That the development shall be implemented in accordance with the submitted
plans, drawings and recommendations contained in the application (inclusive
of all associated supporting reports and documentation) unless otherwise
indicated below, all to the satisfaction of North Ayrshire Council as Planning
Authority. 
2. That prior to the commencement of the development, the applicant shall
submit a Construction Environmental Management Plan for the written
approval of North Ayrshire Council as Planning Authority, which shall address
site construction traffic routes and management, working hours, dust
suppression measures, noise control measures and surface water run-off
control measures. Thereafter, the development shall be implemented in
accordance with such details as may be approved to the satisfaction of North
Ayrshire Council as Planning Authority. 
3. That, for all roads/tracks accessing the site, visibility splays of 2.5 metres by
120 metres, in both directions, shall be provided and maintained at the
junction with the associated public road. No item with a height greater than
1.05 metre above adjacent carriageway level must be located within these
sightline triangles. 
4. That, prior to the commencement of the development, the applicant shall
submit for the written approval of North Ayrshire Council as Planning Authority
a scheme of landscaping and tree planting. The scheme shall include: 
- the restoration of existing hedgerows, including the planting of hedgerow
trees throughout the site;
- the restoration of existing woodland areas, including the removal of
diseased/dead trees and details of their replacement;
- details of tree protection measures; 
- details of wild flower planting; 
The landscaping and tree planting scheme shall include details of species,
planting densities, soil treatment and aftercare. Thereafter, the scheme as
may be approved shall be implemented prior the development becoming
operational and managed thereafter to the satisfaction of North Ayrshire
Council as Planning Authority.

Page 8

5. That, prior to the commencement of any peatland restoration, the applicant
shall submit for the written approval of North Ayrshire Council as Planning
Authority a detailed scheme of such works, including their timing and future
management arrangements. Thereafter, the scheme as may be approved
shall be implemented and managed during the lifespan of the solar farm to the
satisfaction of North Ayrshire Council as Planning Authority. 
6. That, unless otherwise agreed in writing by North Ayrshire Council as
Planning Authority, the rated noise level, as defined in BS
4142:2014+A1:2019, from the operation of fixed plant and machinery,
including the battery storage facilities, sub-station, transformers, etc. shall not
exceed the background noise level at the curtilage of any noise sensitive
property existing or consented at the time of the application. 
7. That the solar farm and battery storage facilities hereby permitted shall be
removed and the land restored for agriculture and/or nature conservation
purposes within 40 years of the date of the consent, all to the satisfaction of
North Ayrshire Council as Planning Authority, unless otherwise agreed
beforehand. 
7. Grouping of Trees in the grounds surrounding Moorpark House, Kilbirnie 
Submitted report by the Chief Planning Officer regarding the process and merits of
protecting a group of trees located on the grounds of Moorpark House, Kilbirnie via a
Tree Preservation Order (TPO). 
The report indicated that concerns had been raised by a member of the public in
connection with a lack of protection afforded to the trees, some of which were
currently subject to works, located within the grounds of Moorpark House. Council
Officers conducted a site visit and desk top analysis to assess the suitability of a
TPO and relevant legislation.  Accordingly, it was considered that the trees were an
important characteristic of the local area and were visible from various parts of
Kilbirnie and its fringes. The western part of the proposed TPO area was directly
adjacent to a Core Path, which led from the edge of the town centre to the more rural
northwest fringes of the settlement. The site was also allocated as Open Space
within the Local Development Plan, which green infrastructure such as trees played
a significant role in contributing to amenity and setting. A subsequent site visit
confirmed a mix of tree species including Scots Pine, Sycamore, Lime, Larch and
Horse Chestnut. The trees were found to have met the criteria for a TPO and the
report recommended that this be served in the interests of protection of public
amenity. 
Councillor Inglis, seconded by Councillor Robertson, moved to support the serving of
a TPO in line with the report recommendation. There being no amendment, the
motion was declared carried. 
The Committee agreed to the serving of a Tree Preservation Order (TPO) under
Section 160 of the Town and Country Planning (Scotland) Act 1997.

Page 9

8. Notice under Section 145 of the Town and Country Planning (Scotland)
Act 1997: 17 Auldlea Road, Beith 
Submitted report by the Chief Planning Officer seeking authority to serve a Notice
under Section 145 of the Town and Country Planning (Scotland) Act 1997 requiring
compliance with Condition 1 of planning permission (ref. 22/00536/PP). 
The report advised that on 5 June 2022, it was brought to the Council’s attention that
a conservatory extension had been erected to the rear of an end-terraced
dwellinghouse at 17 Auldlea Road, Beith. Public concerns had been raised regarding
the scale and height of the conservatory. The conservatory was measured on site
and was found to have exceeded the height limits set out in Class 1A of the HPDR.
Consequently, an application for planning permission was requested from the
householder at 17 Auldlea Road, Beith. 
A retrospective planning application was duly received in July 2022 and validated on
1 August 2022. Mitigation measures were discussed with the applicant’s agent and it
was agreed with the agent that the matter could be addressed by a condition. The
planning application was duly granted, subject to conditions, on 27 September 2022. 
Condition 1 of the permission stated that details of the obscure glazing required to be
submitted within four weeks of the date of the decision (27 September 2022).
However, the required details were not received within four weeks of the decision
notice, nor since. Likewise, obscure glazing required as part of the second part of the
condition had not been installed to the north elevation of the conservatory. 
The Committee also noted that over five months had elapsed since the date of the
decision. Accordingly, it was considered that the applicant has had sufficient time to
comply with, or to challenge, the condition. 
Accordingly, the Committee agreed to grant authority for the service of a Notice
under Section 145 of the Town and Country Planning (Scotland) Act 1997 requiring
compliance with Condition 1 of planning permission ref. 22/00536/PP at 17 Auldlea
Road, Beith. 
8. Chair’s Closing Remarks 
The Chair informed the Committee that this was the last meeting which Jim Miller,
Chief Planning Officer, would attend as he was retiring from Council service. 
On behalf of the Committee, Councillor Foster thanked Mr Miller for all his expert
guidance, dedication and commitment over many years, which had contributed to
making North Ayrshire Council the best performing Planning Authority in Scotland
and wished him a long and happy retirement. The Members present warmly
concurred. 